HomeMy WebLinkAbout20200428Final_Order_No_34647.pdfORDER NO. 34647 1
Office of the Secretary
Service Date
April 28, 2020
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF AVISTA
CORPORATION’S APPLICATION FOR A
DETERMINATION OF 2016-2017 ELECTRIC
ENERGY EFFICIENCY EXPENSES AS
PRUDENTLY INCURRED
IN THE MATTER OF AVISTA
CORPORATION’S APPLICATION FOR A
DETERMINATION OF 2014-2017 NATURAL
GAS ENERGY EFFICIENCY EXPENSES AS
PRUDENTLY INCURRED
)
)
)
)
)
)
)
)
)
)
)
CASE NO. AVU-E-18-12
AVU-G-18-08
ORDER NO. 34647
On February 11, 2020, Avista Corporation (“Avista” or “Company”) signed a
Stipulation and Settlement (“Settlement”) with Commission Staff regarding the Company’s
electric and natural gas energy efficiency prudency cases. See Case Nos. AVU-E-18-12 and AVU-
G-18-08. On February 18, 2020, the Company filed the Settlement for Commission consideration,
under Procedural Rule 274. See IDAPA 31.01.01.274. The Commission issued a Notice of Motion
to Approve Settlement Agreement on March 9, 2020, setting a March 26, 2020 comment deadline
and an April 2, 2020 reply comment deadline. The Commission received two public comments on
the Settlement.
Having reviewed the record, the Commission approves the Settlement.
BACKGROUND
On November 16, 2018, Avista filed two applications with the Commission. The first
application, Case No. AVU-G-18-08, requested the Commission determine whether the Company
prudently incurred $2,899,525 in natural gas energy efficiency expenses from January 1, 2014
through December 31, 2017. The second application, Case No. AVU-E-18-12, requested the
Commission determine whether the Company prudently incurred $22,719,204 in electric energy
efficiency expenses in 2016 and 2017.
The Commission issued notices of Application and set intervention deadlines for both
cases in December 2018. See Order Nos. 34210 and 34222. During the ensuing months, Staff
worked closely with the Company to understand its data and processes. Staff submitted 33
production requests in Case No. AVU-G-18-08 and 40 production requests in Case No. AVU-E-
18-12. Onsite audits were conducted in February 2019 and July 2019.
ORDER NO. 34647 2
On September 17, 2019, the Commission issued notices of Modified Procedure, setting
a November 18, 2019 comment deadline and a December 2, 2019 reply comment deadline in both
cases. See Order Nos. 34446 and 34444.
On October 29, 2019, Staff notified the Commission that, per Commission Rule 272
(IDAPA 31.01.01.272), it would begin settlement negotiations with Avista in both cases. At the
request of Staff, the Commission pushed back the comment deadlines for the cases to December
9, 2019 for comments and December 23, 2019 for reply comments. See Order Nos. 34487 and
34489.
On December 9, 2019, Staff filed comments for both cases. Staff stated it had settled
with the Company in principle and that it believed the Settlement would be ready to file soon. Staff
recommended that once the Settlement was filed with the Commission, the Commission should
set new comment deadlines in both cases to allow the public to provide feedback on the Settlement.
On February 18, 2020, Avista filed the Settlement—signed by Staff and the
Company—for Commission consideration.
THE SETTLEMENT
Action items
In the Settlement, Avista acknowledged it “did not completely accomplish the objective
of supporting the overall prudence of Avista’s energy efficiency expenditures.” Settlement at 6.
Many of the action items in the Settlement arose from a November 9, 2019 settlement negotiation
meeting, in which Staff presented 11 comments and recommendations regarding Avista’s Energy
Efficiency Program. Acknowledging these concerns, the Company agreed to eight action items:
1. Review the previously submitted “2018 Annual Conservation Report” and
determine the changes that should be made to assure that it conforms with the
terms of this agreement no later than the first quarter of Calendar Year (“CY”)
2020.
2. Review the contract and the statement of work with the current third-party
Evaluation, Measurement and Verification (EM&V) vendor to ensure that
future work conforms with the terms of this Stipulation. The EM&V vendor
will partner with Avista Supply Chain Contract Management to develop a
vendor performance management plan and to add clarity and process around
roles, relationships, and internal controls by the second quarter of CY 2020.
Avista will provide this plan to Staff by August 1, 2020.
ORDER NO. 34647 3
3. Hold one or more business process improvement (BPI) workshops, to be
facilitated by Avista’s internal BPI experts, focused on Avista’s internal
processes and staffing roles for compiling and verifying annual EM&V and
information contained in Avista’s annual conservation reports by the second
quarter of CY 2020. The recommendations of this workshop and a plan for
realizing them, will be provided to Staff by August 1, 2020.
4. Direct Avista Internal Audit to perform an audit of the energy efficiency
processes for adequacy of controls and adherence to industry best practices. The
Company will provide audit findings, recommendations, and a plan for
realizing them to Staff by August 1, 2020.
5. Evaluate the format and process for the annual report. Avista will consider
preparing the report internally (or contracting out to a writing resource) and
leaving the EM&V with the current third-party vendor, doing so by the second
quarter of CY 2020. The Company will provide the results of its evaluation and
its decisions about a third-party vendor by August 1, 2020.
6. Review team roles and responsibilities. Avista will hire or develop staff
expertise and reassign roles and responsibilities to ensure performance that
meets expectations.
7. Engage with Commission Staff when selecting a third-party EM&V vendor.
Avista will work with Staff to identify a schedule for evaluations that more
closely matches the prudence filing dates so that results can be evaluated,
discussed, and programmatic changes can be implemented within a reasonable
timeframe.
8. Address the issues and implement the recommendations identified in
Attachment A: Issues and Staff Recommendations Regarding Avista’s demand-
side management (“DSM”) Programs, November 2019. Avista will submit a
report to Staff on the status of each of these items by July 31, 2020.
Settlement at 4-5.
Additionally, Avista described the steps it is already taking to address Staff’s concerns.
Where previously the annual report has been developed by a third-party evaluator, Avista will now
develop the annual report in-house. The Company is also updating the annual report’s format to
organize its subject matter by program. Avista’s internal BPI team will be evaluating the annual
report development process to determine how it can be improved. The Company will also create a
new technical resource manual and will work with Commission Staff on its content. The Company
told its third-party evaluator that its deliverables must include work papers to support the
evaluation and samplings. Experienced Avista employees will review the annual report and
ORDER NO. 34647 4
participate in the BPI. Finally, Avista recently hired an analyst with considerable energy efficiency
experience who will support the Company’s analytics group by providing more detailed reporting
and program-design knowledge.
Avista agreed to “take a more proactive approach to manage expectations and the
quality of the work performed by its third-party EM&V evaluators.” Settlement at 6.
Tariff rider adjustments
As part of the Settlement, the Company and Staff agreed to several adjustments to the
energy efficiency tariff rider accounts. Notably, the parties agreed the third-party evaluator’s
energy efficiency reports were not used and useful because they contained many significant errors
and insufficient documentation. Also, the recommendations from the reports were not properly
implemented. The parties agreed to remove the cost of the third-party evaluations from the energy
efficiency tariff rider accounts—$87,762 from the natural gas account and $287,172 from the
electric account. The Settlement stipulates that these adjustments will be funded by Avista and are
not recoverable from customers.
Adjustments totaling $41,625 were also made to correct a number of errors, including
costs that should have been assigned to Washington operations or to a different fuel. The
Settlement stipulates that Avista will restore these amounts to their respective tariff rider balances.
Besides these issues, the Company and Staff agreed Avista’s remaining energy efficiency
expenditures should be allowed as prudent.
The Company and Staff agreed that if the Commission finds Avista did not implement
all of the action items in the Settlement in a satisfactory manner, Avista must fund an additional
$84,000 to the electric and natural gas tariff riders.1 The $84,000 would not be recoverable from
customers.
Other general provisions
The Company and Staff agreed the Settlement is in the public interest and that its terms
are fair, just, and reasonable. The Settlement states that if the Commission “rejects any part or all
of [the Settlement] or imposes any additional material conditions on approval of [the Settlement],”
each party reserves the right to withdraw from the Settlement. Settlement at 9.
1 90% of the penalty would be applied to the electric tariff rider, and 10% to the natural gas tariff rider.
ORDER NO. 34647 5
PUBLIC COMMENTS
The Commission received two public comments on the Settlement. While neither
comment expressly opposed the Settlement, both had concerns about the practices and
management of Avista’s Energy Efficiency Program. Specifically, the commenters recommended
Avista’s internal EM&V evaluation team be completely independent from the Energy Efficiency
Program. One comment also suggested the Company incorporate into its August 1, 2020 report a
plan on how it will work toward achieving a fully independent and transparent EM&V process.
One comment also questioned how Avista calculates the cost effectiveness of its DSM
programs. The commenter noted Avista uses gross savings to calculate cost effectiveness. The
commenter asserted this practice violates nationally recognized and accepted DSM evaluations
standards, which require the cost effectiveness of DSM programs be calculated based on net
savings.
COMMISSION FINDINGS AND DECISION
The Company is an electrical corporation under Idaho Code § 61-119, a gas
corporation under Idaho Code § 61-116, and a public utility subject to the Commission’s
jurisdiction under Idaho Code § 61-129. Having reviewed the record, we accept the Settlement as
just, fair, reasonable, and in the public interest. We find that Avista’s 2016-2017 electric energy
efficiency expenditures and 2014-2017 natural gas energy efficiency expenditures were prudently
incurred in the amount authorized by the Settlement.
The Settlement represents a procedural roadmap for improving the reporting and
management of Avista’s Energy Efficiency Program. Case Nos. AVU-E-18-12 and AVU-G-18-
08 began in November 2018, which indicates the time, effort, and resources that Commission Staff
dedicated to identifying and remedying issues with Avista’s Energy Efficiency Program and
ensuring that costs included in the Application were prudently incurred. Both parties now
acknowledge the Application’s deficiencies and the inadequate processes that led to the
deficiencies.
Staff identified expenses that were not used and useful and worked with the Company
to address the problems prospectively. The action items agreed to by the parties are not a mere
checklist but indicate the Company’s willingness, as encouraged and directed by Staff, to improve
the Company’s entire Energy Efficiency Program. We understand these action items to be tools
ORDER NO. 34647 6
with which the management of and reporting for Avista’s Energy Efficiency Program can be
calibrated over time.
In sum, we anticipate the Settlement will substantially improve the Company’s Energy
Efficiency Program. The Settlement reflects Staff’s hard work and engagement and the Company’s
willingness to improve its internal operations to achieve better results, which will benefit all
customers.
O R D E R
IT IS HEREBY ORDERED that the Settlement is approved.
IT IS FURTHER ORDERED that Avista prudently incurred $22,421,337 in electric
energy efficiency expenses in 2016-2017.
IT IS FURTHER ORDERED that Avista prudently incurred $2,780,833 in natural gas
energy efficiency expenses in 2014-2017.
THIS IS A FINAL ORDER. Any person interested in this Order may petition for
reconsideration within twenty-one (21) days of the service date of this Order about any matter
decided in this Order. Within seven (7) days after any person has petitioned for reconsideration,
any other person may cross-petition for reconsideration. See Idaho Code § 61-626.
///
ORDER NO. 34647 7
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 28th
day of April 2020.
PAUL KJELLANDER, PRESIDENT
KRISTINE RAPER, COMMISSIONER
ERIC ANDERSON, COMMISSIONER
ATTEST:
Diane M. Hanian
Commission Secretary
I:\Legal\ELECTRIC\AVU-E-18-12_AVU-G-18-08\ORDERS\AVUG1808_AVUE1812_final_mh_ej.docx