Loading...
HomeMy WebLinkAbout20020722_211.pdfDECISION MEMORANDUM TO:COMMISSIONER KJELLANDER CO MMISSI 0 NER SMITH CO MMISSI 0 NER HANSEN JEAN JEWELL RON LAW LOUANN WESTERFIELD TONY A CLARK DON HOWELL DAVE SCHUNKE RICK STERLING RANDY LOBB LYNN ANDERSON GENE FADNESS WORKING FILE FROM:SCOTT WOODBURY DATE:MARCH 1, 2002 RE:CASE NO. IPC-01-38 (Idaho Power) AMENDMENT TO TARIFF SCHEDULE 72 INTERCONNECTION TO NON-UTILITY GENERATION On November 9, 2001 , Idaho Power Company (Idaho Power; Company) filed an Application with the Idaho Public Utilities Commission (Commission) requesting approval of proposed amendments to the Company s tariff Schedule 72-Interconnections to Non-Utility Generation. BACKGROUND On April 12, 1991 , the Commission issued Order No. 23631 approving the current tariff Schedule 72. Since approval of Schedule 72 in 1991 , Idaho Power states that it has continued to review its generation interconnection practices and has determined that it would be beneficial to modify Schedule 72 to bring the Schedule into conformance with current standards of best utility practices for non-utility generation interconnection. The purpose of these proposed changes, the Company states, is to provide a template for non-utility generation interconnection that provides a safe, economic and reliable interconnection while at the same time ensuring that DECISION MEMORANDUM Idaho Power s other customers do not subsidize the costs associated with non-utility generation interconnections. Description of Changes Idaho Power s experience gained by interconnecting non-utility generation projects of varying sizes from the extremely small (300 watts) to the moderately large (10 MW) has led Idaho Power to propose that Schedule 72 be amended to accommodate a range of interconnection requirements with increasing levels of sophistication depending on the size the generating facility. As a result, the Company is proposing a simple interconnection process for net metering projects, and a more streamlined and simple interconnection process for projects 100 kWs and smaller. Projects greater than 100 kWs and less than 1 MW and projects 1 MW and greater will be required to comply with more complex interconnection standards. Reference Application Attachment 1. The proposed Schedule 72 interconnection policy requires customer generators to pay for any necessary equipment, modifications and upgrades to insure safety and reliability. The policy requires submission of designs, plans and specifications; proof that all required permits, licenses, inspections and approvals have been obtained; proof that adequate protective and disconnection equipment has been installed; and spells out other provisions regarding ownership, operation, maintenance, and inspection of necessary equipment. On November 23 2001 , the Commission issued Notices of Application and Modified Procedure in Case No. IPC-01-38. The deadline for filing written comments was December 21 , 2001. Comments were filed by the Renewable Northwest Project, Idaho Rivers United, the Northwest Energy Coalition, Northwest Seed, Climate Solutions and American Wind Energy Association--collectively the "Renewable Energy Advocates , the Idaho Rural Council Commission Staff and a few ofthe Company s customers. Idaho Power filed reply comments on January 25 2002. The comments can be summarized as follows: Idaho Rural Council (IRC) It is IRe's contention that the interconnection requirements proposed by Idaho Power are too cumbersome and expensive. Interconnection equipment, it states, has met the tests and standards of reliability and safety. While it makes sense to have those installations inspected in the beginning, it is, IRC contends, totally unnecessary to impose the economic burden of annual DECISION MEMORANDUM inspections. New certification, it suggests, should only be required if the system is changed or repaired. Commission Staff One of the primary obj ectives of an interconnection policy for non-utility generation Staff states, is to insure that a safe, reliable electrical system is maintained. Idaho Power objective in revising the existing interconnection policy is to simplify the interconnection requirements for very small generation facilities and for net metering installations. Staff believes that for the most part, the proposed revisions to the interconnection policy accomplish that objective. One area, however, in which Staff does have some concerns is the net metering system requirement for annual certifications from an independent qualified party licensed in the State of Idaho, certifying that the generation facility and equipment are in compliance with all current applicable electrical and safety codes and are able to safely and reliably continue to operate. Staff certainly agrees in principle that periodic inspections and certifications are important, especially for larger generation facilities. However, Staff believes that annual inspections and certifications may be excessive for net metering systems smaller than 25 kW. Staff contends that such frequent inspections for such small systems could potentially encourage even less rigorous compliance with electrical and safety codes. The cost of an annual certification for very small systems would be a significant expense compared to the value of the energy produced by the system over the course of a year. Inspections could become less thorough if they become too routine. As an alternative, Staff recommends that certification for net metering systems be required of customer generators only once every three years, and whenever any material modifications or additions are made to equipment. However, Staff also recommends that Idaho Power be permitted to perform inspections of disconnection and protective equipment at whatever intervals it chooses using its own personnel or by hiring qualified persons at its own expense. Because Idaho Power must protect the integrity of its own system and insure its safety, Staff believes the Company must not relegate complete responsibility for interconnection safety to customer generators and the inspectors they choose to hire. Schedule 72, as drafted, already includes a provision requiring customers to submit designs, plans specifications and DECISION MEMORANDUM performance data for their generation facility. It also already contains a provision for Idaho Power to retain the right to inspect customer s equipment at its discretion. Renewable Energy Advocates (REA) Renewable Energy Advocates perceIve the Company s suggested changes to Schedule 72 as imposing unnecessary and expensive bureaucratic burdens for the interconnection of net-metered generation systems. REA opposes the Company s proposal of an open-ended requirement that the customer-generator "pay all costs of interconnecting a generation facility to the Company s system." Unbounded risks of interconnection expenses it contends would likely be a strong deterrent to installation of net-metered generation systems. As a practical matter, it states, actual utility experience with net metering facilities across the county has demonstrated that in the vast majority of cases, the customer s equipment provides the necessary safety and power quality protection and the distribution system can accommodate the facilities without any modification. Under these circumstances, it contends that the proposed language is over broad and does nothing more than create uncertainty for the customer regarding the total cost of a net metering facility. The Renewable Energy Advocates suggest that the Commission incorporate a three- tier review process, which would create a presumption that net-metered systems will be interconnected to the grid at no cost to the customer, unless the utility makes an affirmative finding that equipment modifications are necessary to assure a safe and reliable interconnection. Reference California Three Tiered Review Process for Distributed Generation Facilities. See Footnote 2, REA Comments, p. 10. In addition, the Renewable Energy Advocates contend that the Commission should eliminate Idaho Power s suggested requirement for up-front and annual certifications by an independent qualified party licensed in the state of Idaho" that a net-metered system will operate safely and reliably. Such duplicative requirements, they contend, would do little to ensure grid safety and integrity, particularly considering (1) that practically every net metering system would require approval by a local or state electrical inspector; and (2) that the vast majority of interconnection systems already comply with extremely rigorous, uniform technical standards. Also, it is suggested that Idaho Power s proposed requirement for duplicative certifications by an independent party would impose an economic barrier to net metering, particularly for small-scale systems. DECISION MEMORANDUM If Idaho Power makes an affirmative determination that additional safety and reliability equipment for net metering systems is necessary, the Renewable Energy Advocates agree that is reasonable to impose such costs on the customer generators. However, they contend that Idaho Power should be responsible for installation of additional meters to measure power both consumed and generated by the customer, consistent with the utility s traditional metering responsibilities. The Renewable Energy Advocates suggest that the Commission draw from Oregon s statutory language as follows: An electric utility that offers residential and commercial electric service: (a) Shall allow net metering facilities to be interconnected using a standard meter that is capable of registering the flow electricity in two directions. (b) May at its own expense install one or more additional meters to monitor the flow of electricity in each direction. Such allocation of responsibility for meter installation, the Renewable Energy Advocates contend, would resolve metering and billing concerns, particularly for irrigation and large customers. In claiming that "installation of additional metering to register the delivery of energy to Idaho Power s systems negates the concept of net metering," Idaho Power, they contend, implies that the use of one meter is the essence of net metering. Reference Company Response to First Production Request of Commission Staff. At its core, the Renewable Energy Advocates contend that the number of meters involved is a minor issue relative to the primary issues of customer choice and the ability to pay the "net" of generation against consumption. They recommend that the Commission provide an option for the installation of additional meters if necessary to resolve technical or billing considerations for irrigation and large customers. Idaho Power Reply Comments System safety and reliability requires periodic inspection of interconnection facilities. Idaho Power believes that it would be correct to assume that all of the commentors recognIze the need for periodic inspections of interconnection facilities for larger projects. Interconnections of larger generation facilities, the Company contends, certainly pose the greatest risk to Company personnel, as well as to customer equipment and overall system DECISION MEMORANDUM reliability. inspections. The Company agrees that small net-metered projects may not need annual Net metering projects, even very small ones, the Company contends, present a real dichotomy to an electric utility. On the one hand, most very small net-metered projects will utilize inverter technology and other interconnection equipment that has become very standardized and reliable. When this standardized equipment is properly installed and maintained, Idaho Power agrees that it will provide a high degree of system protection. On the other hand, small net-metered projects are also more likely to be of the do-it-yourself variety. Inspection by the local building authority provides little security because both the inspector and owner-operator will have very little understanding of how the interconnection equipment operates in conjunction with Idaho Power s system and will certainly not provide any assistance in ensuring that the owner-operator will be able to properly maintain the equipment in the future. In addition, future remodeling projects and other home repair situations can result in the interconnection safety equipment being relocated or otherwise altered from the original configuration that was inspected and approved by Idaho Power. As a result, Idaho Power feels strongly that some interval of periodic inspection is necessary even for the smallest net-metered projects. Idaho Power would accept the three-year interval as proposed by Staff if clarifying language can be added to the tariff that specifies that certification of Schedule 84 net metering systems will be required once every three years and/or whenever material modifications or additions are made to the generating equipment and/or interconnection facilities. The clarifying language would also provide that sellers are required to notify Idaho Power of any material modifications or additions prior to making such modifications or additions, and if at any time that Idaho Power determines that such material modifications have been made without notice Idaho Power will have the ability to disconnect the facility until such time as certification of the modified facility is submitted to and accepted by Idaho Power. Idaho Power believes this modification strikes a reasonable balance between the Company s need for safety and the customer s desire to minimize interconnection costs. Customers Choosing to Develop Net Metered Projects should pay the costs of interconnections. Idaho Power believes that in all likelihood very small net-metered projects utilizing standardized disconnection equipment will not require the expenditure of extraordinary interconnection costs on the part of Idaho Power. The Renewable Resource Advocates urge the DECISION MEMORANDUM Commission to adopt language that is equivalent to a presumption that small net metered projects will not have to pay interconnection costs unless the utility specifically identifies required cost items and notifies the customer of the required additional costs. This proposed presumption, the Company contends, makes sense only when the net metering option is limited to small projects, i., projects 25 kW or less. Projects larger than 25 kW are much more likely, the Company contends, to require additional interconnection expenditures. That being said, Idaho Power still believes that it is important for the tariff to explicitly state that all interconnection costs will be borne by the customer-generator. In the case of small net-metered projects, in most instances, the customer may satisfy that requirement by providing an inverter and other interconnection equipment meeting nationally recognized standards, which have been reviewed and approved by Idaho Power in advance. However language in a tariff, the Company contends, should not create ambiguity. There should be no misunderstanding that if an interconnection requires more than the customer-furnished standard equipment, it will be the customer-generator responsibility to bear those additional interconnection expenses. Idaho Power contends that there are no great differences between what it has filed and the comments of Commission Staff and the Renewable Energy Advocates, so long as the size of net metered projects remains small. If the size of net-metered projects is expanded beyond 25 kW, the Company feels strongly that annual inspections are imperative to ensure the safety of its employees and the reliability of the system. Commission Decision Idaho Power proposes changes to its Schedule 72 tariff to establish streamlined procedures for interconnecting non-utility generation to the Company s system without compromising safety and reliability. The commenting parties suggest changes in the Company requirements for 1) annual inspection and certification of interconnection facilities and 2) the Company proposed tariff language that the customer-generator "pay all costs of interconnecting a generation facility to the Company s system. For small net metering projects (25 kW) utilizing an invertor and other interconnection equipment meeting naturally recognized demands, the Company agrees that a three year inspection period (with clarifying language regarding modification or additions) is DECISION MEMORANDUM acceptable.For larger projects (greater than 25 kW) the Company maintains that annual inspection and certification is required. Regarding interconnection cost responsibility, the Company cautions that the net- metering tariff should be unambiguous in stating that all interconnection costs will be borne by the customer-generator. The Renewable Energy Advocates fear that an "open ended requirement" will have a chilling effect on construction of small net metering projects and urge a presumption of interconnection at no cost, with a three tiered review process. Scott Woodbury vld/MIPCEO138 sw2 DECISION MEMORANDUM