PUBLIC INVOLVEMENT
Part of the Integrated Resource Plan is to involve the public in the least cost
planning process. To accomplish this, the Company held two public Technical
Advisory Committee (TAC) Meetings to review different phases of the plan during
2002. The first meeting was a joint session with the Avista Corp. electric TAC
members and the natural gas TAC members covering Washington , Idaho, and
Oregon. The second meeting was held with just the natural gas TAC members
and covered Washington , Idaho, and Oregon.
In addition to state commission staff, the meetings included representatives from
other state government agencies several industrial customers, county
government, and pipeline companies. A list of active and inactive participants
can be made available by request.
Comments regarding the draft filing of this plan have been included in this filing.
Comments were received from several members of the T AC, including
comments from the Washington, Idaho, and Oregon State Commission staffs.
Table 1 lists the Technical Advisory Committee meetings that were held.
3 of 4
TABLE
TECHNICAL ADVISORY COMMITTEE MEETINGS
Date Location
September 24, 2002 Spokane, Washington
Topics of Discussion:
(Joint meeting with Avista Utilities electric IRP TAC)
Purpose of IRP
Background of Least Cost Planning
Gas and Electric Forecast Methodology
Washingtonlldaho/Oregon Load Forecast
Gas Outlook and Price Forecast
Gas and Electric DSM Plans
December 4, 2002 Spokane, Washington
Topics of Discussion:
Explanation of Distribution Planning
Demonstration of Distribution Model
Demonstration of GIS
Explanation of Resource Planning
Demonstration of SENDOUT~ Planning Model
4 of 4
~'V'ST lie
Corp.
APPENDIX '
ACTION
PLAN
1 of 8
~~~'V'ST
Corp.
TABLE OF CONTENTS
ACTION PLAN ..................................................................... G-
2000 Action Plan Review............................................. G-
Sales Forecasting .............................................. G-
Modeling/Daily Forecasting ................................ G-
Supply/Capacity................................................. G-
Demand Side Management................................ G-
Distribution Planning .......................................... G-
Public Involvement ............................................. G-
2003 Action Plan .............................. ...................... ..... G-
Sales Forecasting .............................................. G-
Modeling/Daily Forecasting ................................ G-
Supply/Capacity................................................. G-
Demand Side Management................................ G-
Distribution Planning .......................................... G-
Public Involvement ............................................. G-
2 of 8
ACTION PLAN
VISTA CORP. 2000 ACTION PLAN REVIEW
Since the 2000 IRP was published , several major changes have occurred within
the Avista Corporation. One change being the appointment of Gary Ely as the
CEO of Avista Corporation. Along with this was the appointment of Scott Morris
as President of Avista Utilities. Mr. Ely and Mr. Morris have many years of varied
experience within Avista Corporation. The other major change for the
Corporation was the emphasis to "get back to the basics . That "basics" being
an electric and gas utility in the Pacific Northwest.
I. SALES FORECASTING
Avista Utilities will re-estimate temperature sensitive customer usage
models utilizing alternative measures of degree days. Avista Utilities will
also track the price elasticity customer use responses over the action plan
period to validate or modify the lag structure.
Avista Utilities has re-estimated temperature sensitive
customer usage models utilizing alternative measures of
degree days. Now included in the equation are "high quality
degree days accounting for Winter response differences.
Avista Utilities has tracked the price elasticity customer use
responses over the action plan period and modified the lag
structure. The results of this tracking analysis have reduced
the price responsiveness of customers. The support for this
analytical result is that price responsiveness is being
measured after conservation responses. During 2001
conservation messages to customers were at unprecedented
levels, as was program participation. This appears to account
for the lowered response rates to prices during 2001 and 2002.
II. MODELING/DAIL Y FORECASTING
Avista Utilities will continue to use the SENDOUT~ Gas Planning Model to
evaluate capacity requirements storage requirements supply
requirements , monthly guidance for Gas control, etc.
SENDOUT~ remains the focal point for all planning studies
done by Avista Utilities.
3 of 8
Avista Utilities will evaluate , purchase, and install a daily forecasting
system.
Nostradamus~ forecasting software was purchased from New
Energy Associates for daily load forecasting. This software
has enhanced our accuracy in daily/weekly load forecasting.
III. SUPPLY/CAPACITY
Avista Utilities will continue to monitor Avista Energy as part of the "bench
marking" agreement.
As part of the "bench marking" agreement, Avista Utilities has
continued to monitor Avista Energy, along with supplying
quarterly reports to the state commissions. Within this
process , a Strategic Oversight Committee (SOG) was
established. At the time of this printing, Idaho and Oregon
have extended the "bench marking" through March 2005 as
filed by the Company. Washington has not settled on the
continuation of the "bench mark" which went to hearing in late
November, the company asking to continue beyond January
2004.
IV. DEMAND SIDE MANAGEMENT
Avista Utilities will provide continuing support to the evaluation of natural
gas efficiency measures by:
maintaining a dialogue with stakeholders regarding the role of gas
efficiency programs within the Avista Utilities resource portfolio.
reporting on gas efficiency efforts in a manner that facilitates a
meaningful opportunity for stakeholders to contribute to the process.
leveraging the efforts being made within our electric service territory to
achieve natural gas savings when encountered.
lending support for changes in energy codes that are cost-effective in
a strong majority of circumstances.
continuing to monitor and evaluate the impact of developing
technologies and their impact upon natural gas usage.
The Company has worked with the External Energy Efficiency
board to maintain an ongoing awareness of cost-effective gas-
efficiency opportunities. The result of this process was the
determination that increased gas avoided cost and growing
technical potential created an opportunity for cost-effective
4 of 8
programs. Consequently the Company reestablished a gas
demand-side management tariff rider for our Washington and
Idaho jurisdictions in early 2001. The gas-efficiency programs
have been integrated into the Company s DSM programs and
have, through 2002 substantially exceeded the goals
established within the tariffs.
V. DISTRIBUTION PLANNING
Avista Utilities will continue to use the Stoner Workstation in activities of
distribution planning and continue to integrate the GIS system into the
planning functions.
The Stoner Workstation continues to be an integral part of the
distribution planning effort at Avista Utilities. Avista Utilities is
currently refining planning procedures to apply accurate and
standard load study practices to all of the Companies
distribution systems.
VI. PUBLIC INVOLVEMENT
Avista Utilities will continue to participate in the energy planning efforts of
other organizations in the Northwest.
Avista has been an active participate in the planning efforts of
other utilities in the Northwest. Avista was an active
participant in UM1056, the bill in Oregon looking at the IRP
rules, this bill has currently been suspended. Avista continues
to be involved with studies being conducted in the northwest
looking at demand and capacity in the northwest.
5 of 8
VISTA CORP. 2003 ACTION PLAN
The natural gas industry is in a very fluid state due to changes in pipeline
regulations , national energy policy changes and implementation , changes
customer preferences for natural gas end uses, changes in regional and national
economies, increasing environmental awareness for uses of natural gas and
increasing competition both in terms of choices customers have in meeting their
energy needs and in resources available to the Company to meet its customer
needs . This statement has been at the beginning of every Natural Gas IRP
Action Plan items. This statement still holds true today, as it did three years ago.
Things have changed , the FERC has proposed constant changes in the shortand long term pipeline regulation , the involvement of marketers into the
commodity arena , huge fluctuations in commodity costs...
The objective of Avista s 2003 Action Plan is to continue to further integrate the
objectives of Integrated Resource Planning and Least Cost Planning into the
Company s daily operations.
The 2003 action plan is focused on six key areas:
. Sales Forecasting
. Modeling/Forecasting
. Supply/Capacity
Demand Side Management
. Distribution Planning
. Public Involvement
I. SALES FORECASTING
Avista Utilities will continue to track the price elasticity customer use
responses over the action plan period to validate or modify the lag
structure.
II. MODELING/DAILY FORECASTING
Avista Utilities will continue to use the SENDOUT~ Gas Planning Modeland the Nostradamus~ Forecasting Model to evaluate capacity
requirements storage requirements, supply requirements, monthly
guidance for Gas Supply, etc.
6 of 8
III. SUPPLY/CAPACITY
Avista Utilities will continue to monitor Avista Energy as part of the "bench
marking" agreement. Avista Utilities will continue to supply the State
Commission staffs with quarterly reports as stipulated in the "bench
marking" agreement. Avista Utilities will also continue to analyze the need
for additional interstate pipeline capacity and to evaluate the renewal of
transportation contracts as they expire.
IV.DEMAND SIDE MANAGEMENT
Within the Company s Washington and Idaho service territory we will work
toward achieving available cost-effective gas-efficiency opportunities while
simultaneously bringing the tariff rider balance back to zero in a timely
manner. Towards these ends we have identified the following action
items for these two jurisdictions:
Continue to target low-cost / no-cost and lost opportunity measures
in the commercial/industrial segments.
Evaluate the rotation of programs contained within the residential
portfolio to create a sense of urgency on the part of customers and
dealer infrastructure.
Leverage regional and local electric-efficiency programs to realize
gas-efficiency opportunities.
Within the Oregon jurisdiction the Company has identified the following
action items:
Evaluate the impact of the space and water heating gas-efficiency
programs, to include an evaluation of the market transformation
effects.
. We will continuously reevaluate our approach to meeting our
mandated residential weatherization commercial audit and
commercial incentive program responsibilities. We will work with
external stakeholder groups to meet common objectives and
optimize implementation.
DISTRIBUTION PLANNING
Avista Utilities will continue to use the Stoner Workstation in activities of
distribution planning and continue to integrate the GIS system into the
planning functions.
7 of 8
VI. PUBLIC INVOLVEMENT
Avista Utilities will continue to participate in the energy planning efforts of
other organizations in the Northwest as well as any national studies that
may occur. This includes , but is not limited to studies being performed
under the guidance of the American Gas Association, the Northwest Gas
Association , the FERC
Avista Utilities will also look to other utilities in the northwest to find better
ways to get active, meaningful participation in the Technical Advisory
Committee (TAC).