Loading...
HomeMy WebLinkAbout20210525Exhibit 6.pdf Exhibit 6 November 25, 2019 Letter from Kristopher Bremer P.O. Box 2757 Portland, OR 97208-2757 825 NE Multnomah St., Suite 550 Portland, Oregon 97232 November 25, 2019 Q1182: Fall River Rural Electric Cooperative, Inc. – Chester Hydro / Notice of Delay of System Impact Study Report Provision Dear Mr. Peterson: Due to a significant number of Interconnection Requests proposing to interconnect in the same geographical area of PacifiCorp’s electrical system as the Interconnection Request submitted by Fall River Rural Electric Cooperative, Inc. (“Interconnection Customer”), PacifiCorp will be unable to provide the Interconnection Customer’s System Impact Study (“Study”) within the timelines outlined in PacifiCorp’s Small Generation Interconnection Procedures. If you have any questions, please contact me at (503) 813-6496. Sincerely, Kristopher Bremer Director, Generation Interconnection PacifiCorp Exhibit 6 Page 1