HomeMy WebLinkAbout20240206Decision Memo.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON
COMMISSIONER HAMMOND
COMMISSIONER LODGE
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: CHRIS BURDIN
DEPUTY ATTORNEY GENERAL
DATE: FEBRUARY 6, 2024
SUBJECT: IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN
POWER FOR APPROVAL OF A CAPACITY DEFICIENCY PERIOD TO
BE USED FOR AVOIDED COST CALCULATIONS; CASE NO. PAC-E-24-
01.
On January 19, 2024, Rocky Mountain Power, a division of PacifiCorp (“Company”), filed
an application (“Application”) with the Idaho Public Utilities Commission (“Commission”) for
approval of the capacity deficiency period determination to be used for both Surrogate Avoided
Resource-Based Contracts and Integrated Resource Plan-Based Contracts.
STAFF RECOMMENDATION
Commission Staff recommends the Commission issue a Notice of Application and Notice
of Modified Procedure establishing an April 29, 2024, initial comment deadline, and a May 13,
2024, reply comment deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Modified
Procedure establishing an April 29, 2024, initial comment deadline, and a May 13, 2024, reply
comment deadline?
__________________________
Chris Burdin
Deputy Attorney General
I:\Legal\ELECTRIC\PAC-E-24-01_CapDef\memos\PACE2401_dec1_cb.docx