1407 W. North Temple, Suite 330
Salt Lake City, UT 84116
August 21, 2023 VIA ELECTRONIC FILING
Jan Noriyuki Commission Secretary Idaho Public Utilities Commission
11331 W Chinden Blvd.
Building 8 Suite 201A Boise, ID 83714
Re: CASE NO. PAC-E-23-18 IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR A DEFERRED ACCOUNTING ORDER RELATED TO INSURANCE COSTS
Dear Ms. Noriyuki: Please find Rocky Mountain Power’s electronic filing of this Application in the above referenced matter.
Informal inquiries may be directed to Mark Alder, Idaho Regulatory Affairs Manager at (801) 220-2313.
Sincerely, Joelle Steward
Senior Vice President, Regulation and Customer & Community Solutions Enclosures CC: Terri Carlock
RECEIVED
2023 August 21, PM 4:02
IDAHO PUBLIC
UTILITIES COMMISSION
Page 1
Joseph Dallas (ISB#10330)
825 NE Multnomah St., Suite 2000
Portland, OR 97232
Telephone: (360) 560-1937
Email: joseph.dallas@pacificorp.com
Attorney for Rocky Mountain Power
BEFORE THE IDAHO PUBLIC SERVICE COMMISSION
IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR A DEFERRED ACCOUNTING ORDER RELATED TO INSURANCE COSTS
)
)
) ) ) )
CASE NO. PAC-E-23-18 APPLICATION FOR ACCOUNTING ORDER
_____________________________________________________________________________
Pursuant to I.C. § 61-524 and IDAPA 31.01.01.052, Rocky Mountain Power, a division of
PacifiCorp, (“Rocky Mountain Power” or the “Company”), applies to the Idaho Public Utilities
Commission (“Commission”) for an accounting order authorizing the Company to record a
regulatory asset associated with the costs associated with increased insurance premiums
(“Deferred Amount”). Wildfire liability risk is impacting the commercial insurance markets with
an increase in the premiums for available insurance coverage.
In support of this Application, Rocky Mountain Power states as follows:
1. Rocky Mountain Power is a public utility in the state of Idaho and is subject to the
jurisdiction of the Commission with regard to its rates and service. Rocky Mountain Power also
provides retail electric service in the states of Utah and Wyoming.
2. Communications regarding this Application should be addressed to:
By e-mail (preferred): datarequest@pacificorp.com mark.alder@pacificorp.com
Page 2
joseph.dallas@pacificorp.com carla.scarsella@pacificorp.com
By mail: Data Request Response Center Rocky Mountain Power 825 NE Multnomah St., Suite 2000 Portland, OR 97232
Mark Alder Rocky Mountain Power 1407 W. North Temple, Suite 330 Salt Lake City, UT 84116 Telephone: (801) 220-2313
3. Wildfires across the western United States have resulted in significantly increasing
wildfire costs and inability to acquire insurance at rates that have been consistent with past
premiums. Liability insurance, including wildfire liability insurance, is a prudent business expense
that protects the Company and customers against financial losses from third-party claims.
4. PacifiCorp’s currently approved rates include premiums for commercial insurance
covering third-party liability for claims in excess of $10 million (the Company self-insurances for
small claims under $10 million), and a self-insurance reserve for property damage in each state.
However, because the wildfire risk for utilities in the western United States has radically changed
in the past few years, the premiums for available commercial insurance coverage have significantly
increased. As was noted in the Insurance Journal, insurers have taken note of the fact that,
“[l]iability on the scale imposed by the Oregon jury presents an existential threat to an industry
that faces increasing wildfire risk from more extreme weather fueled by climate change.”1
5. As discussed above, PacifiCorp requests authorization to defer the incremental
costs associated with Company’s insurance coverage. Based on the best available information
known in its last rate case, PacifiCorp’s rates were approved to reflect a reasonable level of self-
1 Joel Rosenblatt, Utility Investors Wary of Exposures After Buffet’s PacifiCorp Held Liable for Wildfires,
INSURANCE JOURNAL (July 19, 2023), https://www.insurancejournal.com/news/national/2023/07/19/731224.htm.
Page 3
insurance and commercial insurance related to third-party claims, which is a normal part of
providing electric service to customers. The costs identified in this application would account for
the incremental cost of acquiring coverage for the policy periods commencing August 15, 2023 or
later. As such, all costs are related to claims against PacifiCorp resulting from providing service
to its customers.
6. The combined amount of these insurance premiums, and continued ability to
maintain coverage may represent a material impact to the financial stability of the Company that
resulted from unique and unforeseen circumstances outside the Company’s reasonable control.
Additionally, this deferral covers insurance costs for the third-party claims on PacifiCorp for
events that may occur under both Federal and State emergency declarations. The potential
magnitude of the insurance costs exceeds normal costs anticipated by PacifiCorp and included in
its retail rates and could also far exceed the reasonable business risk associated with these claims.
7. If this application is approved, the Company will record deferred amounts by
debiting Federal Energy Regulatory Commission (“FERC”) Account 182.3-Other Regulatory
Assets and crediting FERC Account 925-Injuries and damages. If this application is denied, the
costs will remain in FERC Account 925.
8. PacifiCorp estimates that the commercial insurance costs are approximately $125
million (total company) for the policy period beginning August 15, 2023 or later. Current rates
reflect $32.7 million (total company), which would result in a deferral for Idaho’s allocated share
of approximately $92.3 million (total company) for the difference between the new costs and the
amount in rates.
9. The Company acknowledges that the Commission’s approval of deferred
accounting treatment for these increased insurance costs will not, in itself, constitute approval of
Page 4
ultimate recovery of those costs. Recovery of the costs would be subject to a prudence review and
a final decision on rate recovery in a future regulatory filing.
10. Rocky Mountain Power believes that a hearing is not necessary to consider the
issues presented herein and respectfully requests that this Application be processed under Modified
Procedure, i.e., by written submissions rather than by hearing, in accordance with RP 201 et seq.
WHEREFORE, Rocky Mountain Power respectfully requests an accounting order
authorizing it to record a regulatory asset to FERC Account 182.3 (Other Regulatory Assets).
Recovery of the deferred insurance costs will only be authorized through a subsequent regulatory
filing.
DATED: August 21, 2023 Respectfully submitted,
______________________
Joseph Dallas (ISB#10330) 825 NE Multnomah St., Suite 2000
Portland, OR 97232 Telephone: (360) 560-1937 Email: joseph.dallas@pacificorp.com
Attorney for Rocky Mountain Power