HomeMy WebLinkAbout20220207Decision Memo.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON
COMMISSIONER CHATBURN
COMMISSIONER HAMMOND
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: DAYN HARDIE
DEPUTY ATTORNEY GENERAL
DATE: FEBRUARY 4, 2022
SUBJECT: IN THE MATTER OF ROCKY MOUNTAIN POWER’S APPLICATION
FOR AUTHORITY TO REVERT THE BLUE SKY BLOCK VALUE TO 100
KILOWATT HOURS FROM 200 KILOWATT HOURS; CASE NO. PAC-E-
22-02.
On January 24, 2022, PacifiCorp dba Rocky Mountain Power (“Company”) applied
for authority to revert the standard Blue Sky block size to 100 kilowatt hours (“kWh”) from 200
kWh.1 The Company requested its Application be processed by Modified Procedure with an
effective date of April 1, 2022.
STAFF RECOMMENDATION
Staff recommends the Commission issue a Notice of Application and Notice of
Modified Procedure establishing a public comment deadline of March 9, 2022 and a Company
reply deadline of March 16, 2022.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Modified
Procedure setting a March 9, 2022, public comment deadline and a March 16, 2022, reply
deadline?
Dayn Hardie
Deputy Attorney General
I:\Legal\ELECTRIC\PAC-E-22-02 Revert Block Value\memos\PACE2202_dec_dh.docx
1 Blue Sky blocks are available to customers under Schedule Nos. 70 and 73. The program is voluntary and self-
funded.