Loading...
HomeMy WebLinkAbout202204042021 IRP Update.pdfROCKY MOUNTAIN POWER ij 1407 W North Temple, Suite 330 Salt Lake City, Utah 84114 , . .: ;,i'il "'i, Pii 3: 2T April4,2022 YIA ELECTRONIC FILING Jan Noriyuki Commission Secretary Idaho Public Utilities Commission I l33l W Chinden Blvd Building 8 Suite 20lA Boise,Idaho, 83714 RE: CASE NO. PAC-E-21-19 - PACIFICORP'S APPLICATION FOR ACKNOWLEDGEMENT OF TIJE 2O2I INTEGRATED RESOURCE PLAN Dear Ms. Noriyuki: Please find enclosed PacifiCorp's2021Integrated Resource Plan Update ("2021 IRP Update"). Copies of the 2021 IRP Update are also available electronically on PacifiCorp's website, at www.pacificorp.com/irp. Confidential and non-confidential workpapers for the 2021 IRP Update will be made available in BOX, and a separate email will be sent with the password to access this data. PacifiCorp's2021IRP Update provides a number of updates including a description of resource planning, procurement activities, an updated load and resource balance, an updated resource portfolio reflecting updates to load forecast and other model inputs, and a status update on action plan items from the 2021 IRP. All formal correspondence and data requests regarding this filing should be addressed as follows: By E-mail (prefened):datarequest@pacifi corp.com irp@pacificorp.com ted.weston@pacifi corp.com emi l),.wesener@Paci fi corP.com By regular mail:Data Request Response Center PacifiCorp 825 NE Multnomah, Suite 2000 Portland, OR 97232 Informal inquiries may be directed to Ted Weston, Idaho Regulatory Affairs Manager, at (801) 220-2963. April4,2022 Page2 Senior Vice Presidenq Regulation Enclosures cc:Jim Yost,Idaho Govemor's Office Benjarnin Otto, Idatro Conservation League Mark Stokes, Idaho Power Company Teni Carloclq Idaho Public Utilities Commission staff Riley Newton, Idaho Fublic Utilities Commission staff TJBudge, Monsanto Nancy Kelly, Western Resource Advocates Rose Monahan, Sierra Club Ana Boyd, Sierra Club Meant for bleeds only! Always bleed this trigon at .125” 2021 Integrated Resource Plan Update MARCH 31, 2022 This 2021 Integrated Resource Plan Update is based upon the best available information at the time of preparation. The IRP action plan will be implemented as described herein, but is subject to change as new information becomes available or as circumstances change. It is PacifiCorp’s intention to revisit and refresh the IRP action plan no less frequently than annually. Any refreshed IRP action plan will be submitted to the State Commissions for their information. For more information, contact: PacifiCorp Resource Planning 825 N.E. Multnomah, Suite 600 Portland, Oregon 97232 (503) 813-5245 irp@pacificorp.com www.pacificorp.com Cover Photos (Top to Bottom): Pavant III Solar Plant Marengo Wind Project Transmission Line - Wyoming Panguitch Solar & Battery Storage PACIFICORP – 2021 IRP TABLE OF CONTENTS i TABLE OF CONTENTS TABLE OF CONTENTS ................................................................................................ i INDEX OF TABLES .................................................................................................... iv INDEX OF FIGURES ...................................................................................................vi CHAPTER 1 – EXECUTIVE SUMMARY…………………………………………………………..……………….1 PACIFICORP’S VISION ..................................................................................................................................................... 1 The time is now .................................................................................................................................................... 1 Delivering on our promise .................................................................................................................................... 1 PUTTING OUR CUSTOMERS AT THE CENTER OF EVERYTHING WE DO .......................................................................................... 2 Our customer-centered vision embodies four core themes: ................................................................................ 2 2021 IRP UPDATE ROADMAP ......................................................................................................................................... 2 PACIFICORP’S INTEGRATED RESOURCE PLAN APPROACH ...................................................................................... 3 2021 IRP UPDATE PREFERRED PORTFOLIO HIGHLIGHTS ......................................................................................... 4 NEW SOLAR RESOURCES ................................................................................................................................................. 8 NEW WIND RESOURCES .................................................................................................................................................. 8 NEW STORAGE RESOURCES.............................................................................................................................................. 9 OTHER NON-EMITTING RESOURCES .................................................................................................................................. 9 DEMAND-SIDE MANAGEMENT ......................................................................................................................................... 9 WHOLESALE POWER MARKET PRICES AND PURCHASES ....................................................................................................... 11 COAL AND GAS RETIREMENTS/GAS CONVERSIONS ............................................................................................................. 12 CARBON DIOXIDE EMISSIONS ......................................................................................................................................... 13 RENEWABLE PORTFOLIO STANDARDS ............................................................................................................................... 14 CHAPTER 2 – INTRODUCTION ………………………………………………………………………………….17 CHAPTER 3 – THE PLANNING ENVIRONMENT ……………………………………………………………….19 FEDERAL POLICY UPDATE ..................................................................................................................................... 19 FEDERAL CLIMATE CHANGE LEGISLATION .......................................................................................................................... 19 NEW SOURCE PERFORMANCE STANDARDS FOR CARBON EMISSIONS – CLEAN AIR ACT § 111(B) ................................................ 19 CARBON EMISSION GUIDELINES FOR EXISTING SOURCES – CLEAN AIR ACT § 111(D) ................................................................ 19 CREDIT FOR CARBON OXIDE SEQUESTRATION – INTERNAL REVENUE SERVICE (IRS) § 45Q ........................................................ 19 CLEAN AIR ACT CRITERIA POLLUTANTS – NATIONAL AMBIENT AIR QUALITY STANDARDS ........................................................... 20 REGIONAL HAZE .......................................................................................................................................................... 22 Utah Regional Haze ............................................................................................................................................ 22 Wyoming Regional Haze .................................................................................................................................... 24 Arizona Regional Haze ....................................................................................................................................... 26 Colorado Regional Haze ..................................................................................................................................... 26 MERCURY AND HAZARDOUS AIR POLLUTANTS ................................................................................................................... 26 COAL COMBUSTION RESIDUALS ...................................................................................................................................... 27 WATER QUALITY STANDARDS ......................................................................................................................................... 28 Cooling Water Intake Structures ........................................................................................................................ 28 Effluent Limit Guidelines .................................................................................................................................... 29 2015 TAX EXTENDER LEGISLATION ................................................................................................................................. 30 PACIFICORP – 2021 IRP TABLE OF CONTENTS ii STATE POLICY UPDATE ......................................................................................................................................... 31 CALIFORNIA ................................................................................................................................................................ 31 OREGON .................................................................................................................................................................... 32 WASHINGTON ............................................................................................................................................................. 33 UTAH ........................................................................................................................................................................ 33 WYOMING ................................................................................................................................................................. 34 GREENHOUSE GAS EMISSION PERFORMANCE STANDARDS ................................................................................................... 35 ENERGY GATEWAY TRANSMISSION PROGRAM PLANNING .................................................................................. 35 ENERGY GATEWAY TRANSMISSION PROJECT UPDATES ........................................................................................................ 36 Wallula to McNary (Segment A) ........................................................................................................................ 36 Gateway West (Segments D and E) .................................................................................................................... 37 Gateway West (Segment E)................................................................................................................................ 37 Gateway South (Segment F) ............................................................................................................................... 37 Boardman to Hemingway (Segment H) ............................................................................................................. 38 In-Service Dates .................................................................................................................................................. 38 REGIONAL MARKETS ............................................................................................................................................ 39 CHAPTER 4 – LOAD-AND-RESOURCE BALANCE …………………………………………………………….41 INTRODUCTION ................................................................................................................................................... 41 SYSTEM COINCIDENT PEAK LOAD FORECAST ....................................................................................................... 41 WIND AND SOLAR QUALIFYING FACILITY RESOURCE UPDATES ............................................................................ 42 UPDATED CAPACITY LOAD-AND-RESOURCE BALANCE ......................................................................................... 42 LOAD-AND-RESOURCE BALANCE COMPONENTS ................................................................................................................. 42 Existing Resources .............................................................................................................................................. 43 Obligation ........................................................................................................................................................... 44 System Position .................................................................................................................................................. 45 CAPACITY BALANCE DETERMINATION AND RESULTS ............................................................................................................ 45 Methodology ...................................................................................................................................................... 45 Capacity Balance Results .................................................................................................................................... 46 ENERGY BALANCE DETERMINATION ................................................................................................................................. 52 Methodology ...................................................................................................................................................... 52 ENERGY BALANCE RESULTS ............................................................................................................................................ 53 CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE ….……………………………………………….55 GENERAL ASSUMPTIONS ..................................................................................................................................... 55 INFLATION RATES ......................................................................................................................................................... 55 DISCOUNT FACTOR ....................................................................................................................................................... 55 FRONT OFFICE TRANSACTIONS (FOTS) ............................................................................................................................ 55 STOCHASTIC PARAMETERS ............................................................................................................................................. 56 FLEXIBLE RESERVE STUDY .............................................................................................................................................. 56 NATURAL GAS AND POWER MARKET PRICE UPDATES ......................................................................................... 56 CARBON DIOXIDE EMISSION POLICY .................................................................................................................... 57 SUPPLY-SIDE RESOURCES ..................................................................................................................................... 58 MODELING ENHANCEMENTS AND RESOURCE UPDATES ...................................................................................... 63 PACIFICORP – 2021 IRP TABLE OF CONTENTS iii DEMAND SIDE MANAGEMENT ........................................................................................................................................ 63 2020 ALL-SOURCE REQUEST FOR PROPOSALS RESOURCES (2020AS RFP) ............................................................................. 63 OTHER CONTRACTS ...................................................................................................................................................... 63 CHAPTER 6 – PORTFOLIO DEVELOPMENT ……………….….……………………………………………….65 INTRODUCTION ................................................................................................................................................... 65 2021 IRP UPDATE PREFERRED PORTFOLIO ........................................................................................................... 65 KEY UPDATES .............................................................................................................................................................. 65 PORTFOLIO OUTCOMES................................................................................................................................................. 65 Present Value Revenue Requirement (PVRR) ..................................................................................................... 66 Load Increase ..................................................................................................................................................... 67 Transmission Acceleration ................................................................................................................................. 67 New Solar Resources .......................................................................................................................................... 69 New Wind Resources .......................................................................................................................................... 70 New Storage Resources ...................................................................................................................................... 70 Other Non-Emitting Resources ........................................................................................................................... 71 Demand-Side Management ............................................................................................................................... 71 Market Activity ................................................................................................................................................... 72 Coal and Gas Retirements/Gas Conversions ...................................................................................................... 72 CARBON DIOXIDE EMISSIONS .............................................................................................................................. 81 RENEWABLE PORTFOLIO STANDARDS ................................................................................................................. 82 WASHINGTON CLEAN ENERGY TRANSFORMATION ACT ...................................................................................... 85 OREGON CLEAN ENERGY PLAN ............................................................................................................................ 87 PROJECTED ENERGY MIX ..................................................................................................................................... 87 ADDITIONAL STUDIES .......................................................................................................................................... 88 Boardman-to-Hemingway Variant (No B2H) ..................................................................................................... 89 Energy Gateway South and Sub-Segment D.1 Variant (No GWS) ...................................................................... 91 2020AS RFP Variant (No RFP) ............................................................................................................................. 93 REGIONAL HAZE HUNTER-HUNTINGTON SENSITIVITY .......................................................................................................... 95 CHAPTER 7 – ACTION PLAN UPDATE …………………….….……………………………………………….97 APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS ………………..………………..………………109 PACIFICORP – 2021 IRP TABLE OF CONTENTS iv INDEX OF TABLES CHAPTER 1 – EXECUTIVE SUMMARY TABLE 1.1 – TRANSMISSION UPGRADE CHANGES IN THE 2021 IRP UPDATE PREFERRED PORTFOLIO COMPARED TO THE 2021 IRP PREFERRED PORTFOLIO ..................................................................................................................................... 6 TABLE 1.2 – TRANSMISSION PROJECTS INCLUDED IN THE 2021 IRP UPDATE PREFERRED PORTFOLIO ........................................ 7 CHAPTER 2 – INTRODUCTION CHAPTER 3 – THE PLANNING ENVIRONMENT TABLE 3.1 – TAX EXTENDER LEGISLATION AND PHASEOUT OF PTC AND ITC ....................................................................... 31 TABLE 3.2 - ENERGY GATEWAY SEGMENT IN-SERVICE DATES .......................................................................................... 39 CHAPTER 4 – LOAD-AND-RESOURCE BALANCE TABLE 4.1 – NEW POWER PURCHASE AGREEMENTS ...................................................................................................... 42 TABLE 4.2 – SUMMER PEAK - SYSTEM CAPACITY LOAD AND RESOURCE BALANCE WITHOUT RESOURCE ADDITIONS, 2021 IRP UPDATE (2022-2031) (MEGAWATTS) ............................................................................................................. 47 TABLE 4.3 – WINTER PEAK – SYSTEM CAPACITY LOAD AND RESOURCE BALANCE WITHOUT RESOURCE ADDITIONS, 2021 IRP UPDATE (2022-2031) (MEGAWATTS) ............................................................................................................ 49 CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE TABLE 5.1 - MAXIMUM AVAILABLE FRONT OFFICE TRANSACTION QUANTITY BY MARKET HUB .............................................. 56 TABLE 5.2 - 2021 IRP UPDATE SUPPLY SIDE RESOURCES ............................................................................................... 61 TABLE 5.3 – 2021 IRP UPDATE SUPPLY SIDE RESOURCES .............................................................................................. 61 TABLE 5.4 – 2021 IRP UPDATE SUPPLY SIDE RESOURCES .............................................................................................. 62 CHAPTER 6 – PORTFOLIO DEVELOPMENT TABLE 6.1 – COST AND RISK PORTFOLIO SUMMARY ...................................................................................................... 66 TABLE 6.2 – TRANSMISSION UPGRADE CHANGES IN THE 2021 IRP UPDATE PREFERRED PORTFOLIO COMPARED TO THE 2021 IRP PREFERRED PORTFOLIO ................................................................................................................................... 68 TABLE 6.3 – TRANSMISSION PROJECTS INCLUDED IN THE 2021 IRP UPDATE PREFERRED PORTFOLIO ...................................... 69 TABLE 6.4 – COMPARISON OF 2021 IRP UPDATE WITH 2021 IRP PREFERRED PORTFOLIO (MEGAWATTS) ............................. 75 TABLE 6.5 – 2021 IRP UPDATE SUMMER CAPACITY LOAD AND RESOURCE BALANCE (MEGAWATTS) ..................................... 77 TABLE 6.6 – 2021 IRP UPDATE WINTER CAPACITY LOAD AND RESOURCE BALANCE (MEGAWATTS) ...................................... 79 TABLE 6.7 – PVRR(D) OF THE 2021 IRP UPDATE PORTFOLIO RELATIVE TO THE BASE PORTFOLIO UNDER VARYING PRICE-POLICY SCENARIOS ................................................................................................................................................... 86 TABLE 6.8 – BASE CASE VARIANT PORTFOLIOS ............................................................................................................. 89 TABLE 6.9 – COST AND RISK SUMMARY OF VARIANT PORTFOLIOS .................................................................................... 89 TABLE 6.10 – PVRR(D) OF THE NO B2H PORTFOLIO RELATIVE TO THE BASE PORTFOLIO UNDER VARYING PRICE-POLICY SCENARIOS ................................................................................................................................................... 91 TABLE 6.11 – PVRR(D) OF THE NO GWS PORTFOLIO RELATIVE TO THE BASE PORTFOLIO UNDER VARYING PRICE-POLICY SCENARIOS ................................................................................................................................................... 93 TABLE 6.12 – PVRR(D) OF THE NO RFP PORTFOLIO RELATIVE TO THE BASE PORTFOLIO UNDER VARYING PRICE-POLICY SCENARIOS ................................................................................................................................................... 95 TABLE 6.13 – COST AND RISK SUMMARY OF REGIONAL HAZE HUNTER-HUNTINGTON SENSITIVITY ......................................... 95 CHAPTER 7 – ACTION PLAN UPDATE TABLE 7.1 – 2021 IRP ACTION PLAN STATUS UPDATE................................................................................................... 97 PACIFICORP – 2021 IRP TABLE OF CONTENTS v APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS TABLE A.1 – FORECASTED ANNUAL LOAD GROWTH, 2022 THROUGH 2031 (MEGAWATT-HOURS), AT ................................ 109 TABLE A.2 - FORECASTED ANNUAL COINCIDENT PEAK LOAD (MEGAWATTS) AT GENERATION, PRE- ...................................... 110 TABLE A.3 – ANNUAL LOAD GROWTH CHANGE: 2021 IRP UPDATE FORECAST LESS 2021 IRP FORECAST (MEGAWATT-HOURS) AT GENERATION, PRE-DSM ............................................................................................................................... 110 TABLE A.4 – ANNUAL COINCIDENT PEAK GROWTH CHANGE: 2021 IRP UPDATE FORECAST LESS 2017 IRP FORECAST (MEGAWATTS) AT GENERATION, PRE-DSM ..................................................................................................... 111 TABLE A.5 – SYSTEM ANNUAL RETAIL SALES FORECAST 2022 THROUGH 2031 (MEGAWATT-HOURS), POST-DSM ................ 111 TABLE A.6– FORECASTED RETAIL SALES GROWTH IN OREGON, POST-DSM ..................................................................... 112 TABLE A.7 – FORECASTED RETAIL SALES GROWTH IN WASHINGTON, POST-DSM ............................................................. 112 TABLE A.8 – FORECASTED RETAIL SALES GROWTH IN CALIFORNIA, POST-DSM ................................................................. 113 TABLE A.9 – FORECASTED RETAIL SALES GROWTH IN UTAH, POST-DSM ......................................................................... 113 TABLE A.10 – FORECASTED RETAIL SALES GROWTH IN IDAHO, POST-DSM ...................................................................... 114 TABLE A.11 – FORECASTED RETAIL SALES GROWTH IN WYOMING, POST-DSM ................................................................ 114 PACIFICORP – 2021 IRP TABLE OF CONTENTS vi INDEX OF Figures CHAPTER 1 – EXECUTIVE SUMMARY FIGURE 1.1 – KEY ELEMENTS OF PACIFICORP’S 2021 IRP APPROACH ................................................................................ 4 FIGURE 1.2 – 2021 IRP UPDATE PREFERRED PORTFOLIO (ALL RESOURCES) ........................................................................ 5 FIGURE 1.3 – 2021 IRP UPDATE PREFERRED PORTFOLIO NEW SOLAR CAPACITY .................................................................. 8 FIGURE 1.4 – 2021 IRP UPDATE PREFERRED PORTFOLIO NEW WIND CAPACITY .................................................................. 8 FIGURE 1.5 – 2021 IRP UPDATE PREFERRED PORTFOLIO NEW STORAGE CAPACITY .............................................................. 9 FIGURE 1.6 – 2021 IRP UPDATE OTHER NON-EMITTING RESOURCES CAPACITY .................................................................. 9 FIGURE 1.7 – FORECASTED ANNUAL LOAD (GWH) (BEFORE INCREMENTAL ENERGY EFFICIENCY SAVINGS) .............................. 10 FIGURE 1.8 -- FORECASTED ANNUAL COINCIDENT PEAK LOAD (MW) ............................................................................... 10 FIGURE 1.9 – 2021 IRP UPDATE PREFERRED PORTFOLIO ENERGY EFFICIENCY (CLASS 2 DSM) AND DIRECT LOAD CONTROL CAPACITY (CLASS 1 DSM) .............................................................................................................................. 11 FIGURE 1.10 – COMPARISON OF POWER PRICES AND NATURAL GAS PRICES IN RECENT IRPS ................................................ 11 FIGURE 1.11 – 2021 IRP UPDATE MARKET ACTIVITY COMPARISON TO 2021 IRP STUDIES ................................................. 12 FIGURE 1.12 – 2021 IRP UPDATE PREFERRED PORTFOLIO CO2 EMISSIONS AND PACIFICORP CO2 EQUIVALENT EMISSIONS TRAJECTORY ................................................................................................................................................. 14 FIGURE 1.13 – ANNUAL STATE RPS COMPLIANCE FORECAST .......................................................................................... 15 CHAPTER 2 – INTRODUCTION CHAPTER 3 – THE PLANNING ENVIRONMENT FIGURE 3.1 – ENERGY GATEWAY MAP ........................................................................................................................ 36 CHAPTER 4 – LOAD-AND-RESOURCE BALANCE FIGURE 4.1 - FORECASTED ANNUAL LOAD (GWH) ........................................................................................................ 41 FIGURE 4.2 – FORECASTED ANNUAL COINCIDENT PEAK LOAD (MW) ............................................................................... 42 FIGURE 4.3 – SUMMER SYSTEM CAPACITY POSITION TREND ........................................................................................... 51 FIGURE 4.4 – WINTER SYSTEM CAPACITY POSITION TREND ............................................................................................ 52 FIGURE 4.5 – SYSTEM AVERAGE MONTHLY ENERGY POSITIONS ....................................................................................... 53 CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE FIGURE 5.1 – NOMINAL WHOLESALE ELECTRICITY AND NATURAL GAS PRICE SCENARIOS ...................................................... 57 FIGURE 5.2 – MEDIUM, HIGH AND SOCIAL COST OF GREENHOUSE GAS CO2 PRICES ........................................................... 58 CHAPTER 6 – PORTFOLIO DEVELOPMENT FIGURE 6.1 – CUMULATIVE INCREASE/(DECREASE) IN 2021 IRP UPDATE AND ................................................................... 66 FIGURE 6.2 – ANNUAL PRESENT VALUE REVENUE REQUIREMENT COMPARISON ................................................................. 67 FIGURE 6.3 – LOAD FORECAST COMPARISON ............................................................................................................... 67 FIGURE 6.4 – 2021 IRP UPDATE PREFERRED PORTFOLIO NEW SOLAR CAPACITY ................................................................ 70 FIGURE 6.5 – 2021 IRP UPDATE PREFERRED PORTFOLIO NEW WIND CAPACITY ................................................................ 70 FIGURE 6.6 – 2021 IRP UPDATE PREFERRED PORTFOLIO NEW STORAGE CAPACITY ............................................................ 71 FIGURE 6.7 – 2021 IRP UPDATE OTHER NON-EMITTING RESOURCES CAPACITY ................................................................ 71 FIGURE 6.8 – 2021 IRP UPDATE PREFERRED PORTFOLIO ENERGY EFFICIENCY (CLASS 2 DSM) AND DIRECT LOAD CONTROL CAPACITY (CLASS 1 DSM) .............................................................................................................................. 72 FIGURE 6.9 – 2021 IRP UPDATE MARKET ACTIVITY COMPARISON TO 2021 IRP STUDIES ................................................... 72 FIGURE 6.10 – 2021 IRP UPDATE PREFERRED PORTFOLIO COAL RETIREMENTS/GAS CONVERSIONS ...................................... 73 FIGURE 6.11 – 2021 IRP PREFERRED PORTFOLIO CO2 EMISSIONS AND PACIFICORP CO2 EQUIVALENT EMISSIONS TRAJECTORY . 81 PACIFICORP – 2021 IRP TABLE OF CONTENTS vii FIGURE 6.12 – 2021 IRP UPDATE MONTHLY CO2 ....................................................................................................... 82 FIGURE 6.13 – ANNUAL STATE RPS COMPLIANCE FORECAST .......................................................................................... 84 FIGURE 6.14 - 2021 IRP UPDATE INTERIM TARGETS .................................................................................................... 87 FIGURE 6.15 – PROJECTED ENERGY MIX WITH 2021 IRP UPDATE PREFERRED PORTFOLIO RESOURCES .................................. 88 FIGURE 6.16 – INCREASE/(DECREASE) IN PROXY RESOURCES WHEN THE B2H TRANSMISSION LINE IS ELIMINATED FROM THE BASE PORTFOLIO ................................................................................................................................................... 90 FIGURE 6.17 - INCREASE/(DECREASE) IN SYSTEM COSTS WHEN THE B2H TRANSMISSION LINE IS ELIMINATED FROM THE BASE PORTFOLIO ................................................................................................................................................... 90 FIGURE 6.18 – INCREASE/(DECREASE) IN PROXY RESOURCES WHEN THE GWS AND D.1 TRANSMISSION LINES ARE ELIMINATED FROM THE BASE PORTFOLIO ............................................................................................................................. 92 FIGURE 6.19 – INCREASE/(DECREASE) IN SYSTEM COSTS WHEN THE GWS AND D.1 TRANSMISSION LINES ARE ELIMINATED FROM THE BASE PORTFOLIO ..................................................................................................................................... 92 FIGURE 6.20 – INCREASE/(DECREASE) IN PROXY RESOURCES WHEN 2020AS RFP RESOURCES ARE ELIMINATED FROM THE BASE PORTFOLIO ................................................................................................................................................... 94 FIGURE 6.21 – INCREASE/(DECREASE) IN SYSTEM COSTS WHEN RFP PROJECTS AND GWS AND D.1 TRANSMISSION LINES ARE ELIMINATED FROM THE BASE PORTFOLIO ........................................................................................................... 94 CHAPTER 7 – ACTION PLAN UPDATE APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS PACIFICORP – 2021 IRP TABLE OF CONTENTS viii [This page is intentionally left blank] PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 1 CHAPTER 1 – EXECUTIVE SUMMARY PacifiCorp submitted its 2021 Integrated Resource Plan (IRP) to state regulatory commissions on September 1, 2021. That plan provides a framework for future actions that PacifiCorp will take to provide reliable and reasonably priced service for its customers through the least-cost, least-risk resource portfolio. The 2021 IRP Update reflects resource planning and procurement activities that have occurred since the 2021 IRP and presents an updated load-and-resource balance and an updated resource portfolio consistent with changes in the planning environment. The 2021 IRP Update also provides a status update for the action plan filed with the 2021 IRP. In presenting the updated load-and-resource balance and updated resource portfolio, PacifiCorp highlights changes in the 2021 IRP Update preferred portfolio relative to the 2021 IRP preferred portfolio which covers the 2021 to 2040 planning horizon. Consistent with the 2021 IRP, the 2021 IRP Update preferred portfolio demonstrates reliable service will be maintained with investment in transmission infrastructure, the conversion of two coal units to natural gas peaking units, growth in demand response programs, the addition of advanced nuclear resources, the addition of energy storage resources, and over the long term, the addition of non-emitting peaking resources. PacifiCorp’s Vision The time is now At PacifiCorp, we share a vision with our customers and communities in which clean energy from across the West powers jobs and innovation. This bold vision has guided our work for years. Most recently, it took shape in our 2017, 2019 and 2021 IRPs, in which we outlined an ambitious path to substantially increase our renewable energy capacity, evolving our existing portfolio and connecting supply with demand through an expanded, modernized transmission system. Delivering on our promise The power of the West lies in its diversity: windswept plains and high deserts, the sun-soaked Great Basin, and rivers fed by rain and mountain snow. Taken together, these reserves of wind, solar and hydro power can help meet the growing and changing needs of homes and businesses throughout the West, cleanly, reliably and affordably. Yet, capturing this power alone is not enough. To unlock the full promise of these abundant resources, we must add transmission and storage capacity, unlock customer demand response resources with a modernized grid, and replace retiring thermal resources with non-emitting resources like advanced nuclear, to connect the West to its energy future—built on a resilient, hardened, adaptable grid that safely delivers power when and where it’s needed. PacifiCorp’s 2021 IRP Update remains a roadmap for action and reinforces the significant progress toward the goals laid out in the 2017, 2019 and 2021 IRPs. The 2021 IRP Update also confirms the benefits of critical investments in expanded and modernized transmission, renewable energy, storage, demand response and advanced nuclear resources. PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 2 Our integrated system connects and brings new opportunities to the West, building on a foundation of infrastructure designed to handle extreme weather and enhance the energy resilience of communities from the Pacific Coast to the Rocky Mountains, all while continuing to deliver energy solutions for our customers at prices that are below national and regional averages. As our 2021 IRP Update shows, this expanded, modernized transmission system will connect supply with demand from east to west and from north to south, serving as the backbone of the West for the hundreds of energy providers that serve our region alongside PacifiCorp. Putting our customers at the center of everything we do At PacifiCorp, we’re committed to meeting the demands of our customers and communities throughout the West to deliver safe, affordable, clean energy and a resilient, modern grid. Together with the communities we serve and our regional partners, it is time to act, with targeted, strategic investments that will position us to continue delivering affordable, reliable power. Our customer-centered vision embodies four core themes: Reliable Power: We strive to deliver energy safely during all hours, and plan extensively to ensure that we have sufficient supply and ability to deliver to the communities we serve. We understand that electricity is an essential service, and work around the clock to ensure that we are dependable, and communities can rely on us. Resilient Infrastructure: We live in times of rapid change, with more extreme weather and challenging conditions. We are working to minimize disruptions, implement strategies to recover quickly when they occur, and deploy upgrades that will strengthen our critical infrastructure. Affordable Prices: PacifiCorp is proud to be one of the lowest-cost electricity providers in the nation and the region. As we plan for our next generation of resources, we are prioritizing resources that add value and keep customer prices low. Clean Energy: Through strategic, customer-focused investments in diverse resources, PacifiCorp remains committed to reducing carbon emissions, system-wide, by 74 percent from 2005 levels by 2030. Although a higher load forecast has driven an increase in emissions based on this IRP Update, primarily in the last 10 years of the 20-year study period, the 2021 IRP Update resource plan includes continued significant new renewable additions among other diverse, advanced technologies to keep us on that path and achieve even deeper decarbonization beyond 2030. The higher load forecast can be viewed as a less extreme version of the S01 High Load sensitivity from the 2021 IRP, driving a similar trajectory. However, PacifiCorp fully anticipates that additional transmission and resource options explored in the 2023 IRP will counter the immediate appearance on an uptick in emissions outcomes. 2021 IRP Update Roadmap The 2021 IRP Update continues to fulfill on PacifiCorp’s bold vision for the West between now and 2040 and stays on course to achieve a clean, resilient and affordable energy future that PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 3 leverages the abundant, diverse, clean energy resources that the West can offer through a modernized and expanded grid. • Continue our growth into a grid powered by clean energy: o 4,685 MW from energy efficiency programs o 5,297 MW of new solar resources (most paired with storage) o 4,160 MW of new wind resources o 5,546 MW of storage resources, including battery storage co-located with solar, standalone battery storage and pumped hydro storage resources o 978 MW of direct load control programs o 500 MW of advanced nuclear (the Natrium TM reactor demonstration project) in 2028, with an additional 1,000 MW of advanced nuclear over the long-term o 1,237 MW of non-emitting peaker resources • Connect and optimize these diverse, clean resources across the West with a strengthened and modernized transmission network that ensures resilient service, reduces costs and creates maximum opportunities for our communities to thrive (incremental to projects already online): o 416 miles of new transmission from the new Aeolus substation near Medicine Bow, Wyoming, to the Clover substation near Mona, Utah (Energy Gateway South) o 59 miles of new transmission from the Shirley Basin substation in southeastern Wyoming to the Windstar substation near Glenrock, Wyoming (Energy Gateway West Sub-Segment D.1) o 290 miles of new transmission from the Boardman substation in north central Oregon to the Hemingway substation in south central Idaho PacifiCorp’s Integrated Resource Plan Approach PacifiCorp has been making progress in its efforts to bring the best of the West to its customers. In September 2021, the 2021 IRP set forth a clear path to provide reliable and reasonably priced service to its customers. The analysis supporting this plan helps PacifiCorp, its customers, and its regulators understand the effect of both near-term and long-term resource decisions on customer bills, the reliability of electric service PacifiCorp customers receive, and changes to emissions from the generation sources used to serve customers. In the 2021 IRP Update, PacifiCorp presents a preferred portfolio that continues to build on its vision to deliver energy affordably, reliably and responsibly through near-term investments in transmission infrastructure that will facilitate continued growth in new renewable resource capacity while maintaining substantial investment in energy efficiency and demand response programs. All of this can be achieved by maintaining reliable service with incremental investments in transmission infrastructure and other non-emitting flexible resources capable of shaping and responding to changes in energy from an increasing supply of wind and solar resources. The primary objective of an IRP is to identify the best mix of resources to serve customers in the future. The best mix of resources is identified through analysis that measures cost and risk. The least-cost, least-risk resource portfolio—defined as the “preferred portfolio”—is the portfolio that can be delivered through specific action items at a reasonable cost and with manageable risks, PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 4 while considering customer demand for clean energy and ensuring compliance with state and federal regulatory obligations. The 2021 IRP Update serves as a checkpoint to the recent IRP roadmap to ensure that changes in the planning environment are considered in between the full IRP planning process that is completed every two years, thus providing guidance as to constantly evolving trends and events which may ultimately impact our customers. As depicted in Figure 1.1, PacifiCorp’s 2021 IRP and this 2021 IRP Update were developed by working through five fundamental planning steps that began with development of key inputs and assumptions to inform the modeling and portfolio evaluation process. The optimization of the updated preferred portfolio allows for a new endogenous selection of retirements, transmission and resources to meet projected gaps in the updated load and resource balance, characterized by the type, timing, and location of new resources in PacifiCorp’s system. Options for the 2021 IRP Update considered a wide range of potential coal retirement dates, options to convert to gas or to retrofit for carbon capture utilization and sequestration for certain coal units, and other planning uncertainties. PacifiCorp then developed key variants of the updated preferred portfolio, focusing on three variant studies from the 2021 IRP which address large transmission projects and significant volumes of associated resources. In the resource portfolio analysis step, PacifiCorp conducted targeted reliability analysis to ensure portfolios had sufficient flexible capacity resources to meet reliability requirements. PacifiCorp then analyzed these different resource portfolios to measure the comparative cost, risk, reliability, and emission levels. This resource portfolio analysis ultimately informed selection of the least-cost and least-risk portfolio and the 2021 IRP Update preferred portfolio. Figure 1.1 – Key Elements of PacifiCorp’s 2021 IRP Approach 2021 IRP Update Preferred Portfolio Highlights Figure 1.2 shows that PacifiCorp’s 2021 Update preferred portfolio continues to include substantial new renewables, facilitated by incremental transmission investments, demand-side management (DSM) resources, significant storage resources, and continues to show support for advanced nuclear and non-emitting peaker resources. By the end of 2024, the 2021 IRP Update preferred portfolio includes the 2020 All-Source Request for Proposals (RFP) final shortlist resources. These projects include 1,792 MW of wind, 1,150 MW of solar additions, and 639 MW of battery storage capacity—439 MW paired with solar and PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 5 a 200 MW standalone battery.1 During this time, the Update preferred portfolio also includes the acquisition and repowering of Rock River I (49 MW) and Foote Creek II-IV (43 MW) wind projects located in Wyoming. Through the end of 2026, the 2021 IRP Update preferred portfolio includes an additional 597 MW of wind and an additional 600 MW solar co-located with storage. The 2021 IRP Update preferred portfolio includes the 500 MW advanced nuclear NatriumTM demonstration project, which will come online by summer 2028. Through 2040, the 2021 IRP Update preferred portfolio includes 1,000 MW of additional advanced nuclear resources and 1,237 MW of non-emitting peaking resources. Over the 20-year planning horizon, the 2021 IRP Update preferred portfolio includes 4,160 MW2 of new wind and 5,297 MW of new solar co-located with storage. Figure 1.2 – 2021 IRP Update Preferred Portfolio (All Resources) To facilitate the delivery of new renewable energy resources to PacifiCorp customers across the West, the updated preferred portfolio includes necessary transmission investments. Specifically, the portfolio includes the Energy Gateway South transmission line - a new 416-mile high-voltage 500-kilovolt transmission line and associated infrastructure running from the new Aeolus substation near Medicine Bow, Wyoming, to the Clover substation near Mona, Utah. The 2021 Update preferred portfolio also includes the Energy Gateway West Subsegment D.1 project - a new 59-mile, high-voltage (230-kilovolt) transmission line from the Shirley Basin substation in southeastern Wyoming to the Windstar substation near Glenrock, Wyoming. Both transmission lines will come online by the end of 2024. 1 The reported capacity for RFP solar resources reflects their expected maximum output after degradation in their first full year of operation. 2 This figure includes 160 MW of hybrid wind located in Yakima Washington as part of CETA compliance -10000 -5000 0 5000 10000 15000 20000 In s t a l l e d M W Coal Gas Contracts QF Hydro Nuclear Hydro Storage Battery Solar Solar+Storage Wind Wind+Storage Geothermal Energy Efficiency Demand Response Non-Emitting Peaker Converted Gas PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 6 The 2021 IRP Update preferred portfolio also includes a 290-mile high-voltage 500-kilovolt transmission line known as Boardman-to-Hemingway, which connects those respective substations in Oregon and Idaho, which will come online in 2026. Further, the portfolio includes near-term and long-term transmission upgrades across the system that will facilitate continued and long-term growth in new resources needed to serve our customers. A higher load forecast drives new and accelerated transmission in the updated preferred portfolio. Table 1.1 reports changes in transmission selections relative to the 2021 IRP. Four transmission paths are accelerated and two new paths are selected, adding 300 MW of interconnection capability to the system. One transmission upgrade, Portland North coast to Willamette Valley, is delayed in the back 10 years of the model horizon. Finally, one transmission path, Portland North Coast to Southern Oregon, is removed, partly offset by the accelerations, particularly of the Central Oregon to Willamette Valley transmission line, as well as the additional transmission options. Table 1.1 – Transmission Upgrade Changes in the 2021 IRP Update Preferred Portfolio Compared to the 2021 IRP Preferred Portfolio1 1 – Negative values in the “Change” column indicates the number of years of acceleration compared to the 2021 IRP Preferred Portfolio. Table 1.2 summarizes the incremental transmission projects in the 2021 IRP Update preferred portfolio. Upgrade Export Capacity 2021 Update Year 2021 IRP Year Change CON Central OR > TxCON 2027 100 2030 2037 -7 CON Yakima > TxCON 2027a 180 2029 2030 -1 CON Yakima > TxCON 2027b 100 2029 -New INC Central OR > Willamette Valley 2037 1500 2037 2040 -3 INC Portland North Coast > Southern Oregon 2037 1500 -2040 Removed INC Portland North Coast > Willamette Valley 2032 450 2038 2032 6 INC Utah South > Utah North 2032 800 2032 2033 -1 INC Walla Walla - WA > Yakima 2030 200 2030 -New PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 7 Table 1.2 – Transmission Projects Included in the 2021 IRP Update Preferred Portfolio1,2,* 1 - TTC = total transfer capability. The scope and cost of transmission upgrades are planning estimates. Actual scope and costs will vary depending upon the interconnection queue, the transmission service queue, the specific location of any given generating resource and the type of equipment proposed for any given generating resource. 2 - Energy Gateway South is modeled in the 2021 IRP Update as a contingent option with bids in the 2020 All-Source Request for Proposals. Other transmission options prior to 2026 are not modeled as transmission requirements and costs are accounted for in the 2020 All-Source Request for Proposals transmission cluster study for all other resource bids. * - Reclaimed transmission is committed with resources with a commercial operation date later than the date of retirement. PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 8 New Solar Resources As reported in Figure 1.3, the 2021 IRP Update preferred portfolio includes 1,709 MW of new solar by the end of 2024 and 2,309 MW by the end of 2026, with additions of 5,297 MW through 2040. Accounting for a 153 MW reduction in resources associated with the 2020 AS RFP, the 2021 IRP Update includes 833 MW more new solar capacity by the end of 2031 compared to the 2021 IRP preferred portfolio. After 2031, driven by more efficient higher cost transmission and energy efficiency gains, solar additions are ultimately reduced 730 MW by 2040. Figure 1.3 – 2021 IRP Update Preferred Portfolio New Solar Capacity* * 2021 IRP Update solar capacity shown in the figure includes solar resources coming via the 2020 All-Source Request for Proposals by the end of 2024. Resources are shown in the first full year of operation (the year after the year-online dates). The reported capacity for the 2020 All-Source Request for Proposals solar resources reflects their expected maximum output after degradation in their first full year of operation. New Wind Resources As shown in Figure 1.4, by the end of 2024, PacifiCorp’s 2021 IRP Update preferred portfolio includes 1,815 MW of new wind generation resulting from the 2020 All-Source RFP and the acquisition and repowering of Rock River I (49 MW) and Foote Creek II-IV (43 MW). Through the end of 2026, the 2021 IRP Update preferred portfolio includes an additional 2,363 MW of new wind and more than 4,000 MW of new wind by 2040. Relative to the 2021 IRP, 2021 IRP Update wind additions are mostly reduced or flat through 2037, and ultimately increase by 348 MW of new wind by the end of 2040. Figure 1.4 – 2021 IRP Update Preferred Portfolio New Wind Capacity* *Note: Wind additions shown are incremental to Energy Vision 2020 and other projects that have come online over the past few years. Resources are shown in the first full year of operation (the year after year-end online dates). 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP 0 1,000 2,000 3,000 4,000 5,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 9 New Storage Resources New storage resources in the 2021 IRP Update preferred portfolio are summarized in Figure 1.5. The updated portfolio includes nearly 639 MW of battery storage by the end of 2024 – 200 MW of which is a standalone battery and the remaining portion paired with solar resources resulting from the 2020 All-Source RFP. Through 2040, the 2021 IRP includes 4,146 MW of storage co- located with solar resources, 900 MW of standalone battery, and 500 MW of pumped hydro. Figure 1.5 – 2021 IRP Update Preferred Portfolio New Storage Capacity* *Note: Resources are shown in the first full year of operation (the year after the year-end online dates). Other Non-Emitting Resources The 2021 IRP was the first to include new advanced nuclear and non-emitting peaking resources as part of its least-cost, least-risk preferred portfolio. The 2021 IRP Update continues to select these resources. As shown in Figure 1.6, the 500 MW advanced nuclear NatriumTM demonstration project is projected to come online by summer 2028. Through 2040, the 2021 IRP Update preferred portfolio includes 1,500 MW of advanced nuclear resources and 1,237 MW of non-emitting peaking resources. Figure 1.6 – 2021 IRP Update Other Non-Emitting Resources Capacity* *Note: Resources are shown in the first full year of operation (the year after the year-end online dates). Demand-Side Management PacifiCorp evaluates new DSM opportunities, which includes both energy efficiency and direct load control programs, as a resource that competes with traditional new generation and wholesale power market purchases when developing the IRP Update preferred portfolio. Figure 1.7 shows that PacifiCorp’s load forecast before incremental energy efficiency savings has increased relative 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP 0 500 1,000 1,500 2,000 2,500 3,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 10 to projected loads used in the 2021 IRP. On average, forecasted system load is up 1.9 percent and forecasted coincident system peak is up 2.1 percent when compared to the 2021 IRP. Over the planning horizon, the average annual growth rate, before accounting for incremental energy efficiency improvements, is 1.28 percent for load and 0.85 percent for peak. Changes to PacifiCorp’s load forecast are driven by higher projected demand from data centers driving up the commercial forecast. Figure 1.7 – Forecasted Annual Load (GWh) (Before Incremental Energy Efficiency Savings) Figure 1.8 -- Forecasted Annual Coincident Peak Load (MW) PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 11 DSM resources continue to play a key role in PacifiCorp’s resource mix. The chart to the left in Figure 1.9 compares total energy efficiency capacity savings in the 2021 IRP Update preferred portfolio relative to the 2021 IRP preferred portfolio and includes 4,685 MW by the end of the planning period. This increase is attributed to the reductions in demand response, combined with the alignment of energy efficiency to load, both described in Chapter 5 – Modeling Updates. For the 2021 IRP Update, selections of demand response have been scaled back to realistic targets, which is responsible for decreases shown on the right-hand side of Figure 1.9. Demand response selections in the 2021 IRP Update total nearly 1,000 MW over the 20-year horizon. By the end of 2040 and relative to the 2021 IRP preferred portfolio, energy efficiency selection increases by nearly 400 MW, whereas demand response selections are reduced by more than 1,400 MW. Figure 1.9 – 2021 IRP Update Preferred Portfolio Energy Efficiency (Class 2 DSM) and Direct Load Control Capacity (Class 1 DSM) Wholesale Power Market Prices and Purchases Figure 1.10 summarizes the three wholesale electricity price forecasts and three natural gas price forecasts used in the Base and scenario cases for the 2021 IRP Update. As shown, low and medium power and gas prices are higher in the near term. All three power price scenarios trend higher beginning in 2024, but generally escalate at different increasing rates. Additional detail regarding power and gas prices is provided in Chapter 5 – Modeling and Assumptions Update. Figure 1.10 – Comparison of Power Prices and Natural Gas Prices in Recent IRPs 0 1,000 2,000 3,000 4,000 5,000 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Cu m u l a t i v e M W Energy Efficiency (Class 2 DSM) 2021 IRP Update 2021 IRP 0 500 1,000 1,500 2,000 2,500 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Cu m u l a t i v e M W Direct Load Control (Class 1 DSM) 2021 IRP Update 2021 IRP $0 $1 $2 $3 $4 $5 $6 $7 $8 $9 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 $/ M M B t u Natural Gas Prices Henry Hub Medium Low High $0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 $/ M W h Wholesale Electricity Prices Average of Palo Verde and Mid-C (Flat) Mgas_MCO2 Hgas_HCO2 Lgas_0CO2 PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 12 Figure 1.11 compares market purchases and sales among the 2021 IRP preferred portfolio, the 2021 IRP S01 High Load sensitivity and the 2021 IRP Update. While the 2021 IRP Update averages approximately 500 GWh additional sales annually compared to the 2021 IRP preferred portfolio or the 2021 IRP High Load scenario, offsetting purchases are higher in some years, particularly 2032 to 2037. On average, 2021 IRP Update purchase increase by an average of 200 MW annually on a purely volumetric basis. Given near-term concerns over resource adequacy, generally lower market purchases in 2021 IRP Update portfolio in the first 5 years are viewed favorably. Figure 1.11 – 2021 IRP Update Market Activity Comparison to 2021 IRP Studies Coal and Gas Retirements/Gas Conversions Coal resources have been an important resource in PacifiCorp’s resource portfolio for many years. PacifiCorp’s coal resources will continue to play a pivotal role in following fluctuations in renewable energy as the remaining coal units approach retirement dates. The 2021 IRP Update yields the same retirement timing as seen in the 2021 IRP. Driven in part by ongoing cost pressures on existing coal-fired facilities and cost-effective new resource alternatives, of the 22 coal units currently serving PacifiCorp customers, the preferred portfolio includes retirement of 14 of the units by 2030 and 19 of the 22 units by the end of the planning period in 2040. Coal unit retirements scheduled under the preferred portfolio include: • 2023 = Jim Bridger Units 1-2, converted to natural gas peakers • 2025 = Naughton Units 1-2 • 2025 = Craig Unit 1 • 2025 = Colstrip Units 3-4 • 2027 = Dave Johnston Units 1-4 • 2027 = Hayden Unit 2 • 2028 = Craig Unit 2 • 2028 = Hayden Unit 1 • 2036 = Huntington Units 1-2 • 2037 = Jim Bridger Units 3-4 • 2039 = Wyodak 2,000 3,000 4,000 5,000 6,000 7,000 8,000 En e r g y ( G W h ) Market Purchases Purch-21 IRP CETA Purch-21 IRP High Load Purch-21 IRP Update CETA (10,000) (9,000) (8,000) (7,000) (6,000) (5,000) (4,000) En e r g y ( G W h ) Market Sales Sales-21 IRP CETA Sales-21 IRP High Load Sales-21 IRP Update CETA PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 13 In addition to the coal unit retirements outlined above, the preferred portfolio reflects 1,554 MW natural gas retirements through 2040. This includes Naughton Unit 3 at the end of 2029, Gadsby at the end of 2032, Hermiston at the end of 2036, and Jim Bridger Units 1 and 2 at the end of 2037. Carbon Dioxide Emissions While the 2021 IRP Update preferred portfolio reflects PacifiCorp’s on-going efforts to provide cost-effective clean-energy solutions for our customers, increased load has driven thermal dispatch and therefore emissions higher based on currently modeled resource options and assumptions. Portfolio emissions and costs due to the higher load forecast present a less extreme version of the S01 High Load sensitivity from the 2021 IRP. PacifiCorp’s emissions have been declining and are expected to continue to decline related to several factors including PacifiCorp’s participation in the energy imbalance market, which reduces customer costs and maximizes use of clean energy; PacifiCorp’s on-going transition to clean- energy resources including new renewable resources, new advanced nuclear resources, new non- emitting resources, storage, transmission, and Regional Haze compliance that capitalizes on flexibility. Input updates and additional transmission and resource options in the 2023 IRP are expected to allow economic emissions reductions not available to the 2021 IRP Update and in the absence of a full IRP cycle. The chart on the left in Figure 1.12 compares projected annual CO2 emissions between the 2021 IRP update and 2021 IRP preferred portfolios. In this graph, emissions are not assigned to market purchases or sales. The chart on the right in Figure 1.12 includes historical data, assigns emissions at a rate of 0.4708 tons CO2 equivalent per MWh to market purchases (with no credit to market sales), includes emissions associated with specified purchases, and extrapolates projections out through 2050. This graph demonstrates that relative to a 2005 baseline, 2021 IRP Update preferred portfolio system CO2 equivalent emissions are down 49 percent in 2025, 69 percent in 2030, 78 percent in 2035, 88 percent in 2040, 94 percent in 2045, and 100 percent in 2050. PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 14 Figure 1.12 – 2021 IRP Update Preferred Portfolio CO2 Emissions and PacifiCorp CO2 Equivalent Emissions Trajectory* *Note: PacifiCorp CO2 equivalent emissions trajectory reflects actual emissions through 2020 from owned facilities, specified sources and unspecified sources. From 2022 through the end of the twenty-year planning period in 2040, emissions reflect those from the 2021 IRP Update preferred portfolio with emissions from specified sources reported in CO2 equivalent. Beyond 2040, emissions reflect the rolling average emissions of each resource from the 2021 IRP update preferred portfolio through the life of the resource. The emissions trajectory does not incorporate clean energy targets set forth in Oregon House Bill 2021 or any other state-specific emissions trajectories. PacifiCorp expects these targets, and an Oregon-specific emissions trajectory, to be incorporated following the 2023 integrated resource plan when PacifiCorp is required under the bill to file a Clean Energy Plan. Renewable Portfolio Standards Figure 1.13 shows PacifiCorp’s renewable portfolio standard (RPS) compliance forecast for California, Oregon, and Washington after accounting for new renewable resources in the preferred portfolio. While these resources are included in the preferred portfolio as cost-effective system resources and are not included to specifically meet RPS targets, they nonetheless contribute to meeting RPS targets in PacifiCorp’s western states. Oregon RPS compliance is achieved through 2040 with the addition of new renewable resources and transmission in the 2021 IRP Update preferred portfolio. Consistent with the 2021 IRP, in the 2021 IRP Update, Washington RPS compliance is achieved with the benefit of increased system renewable resources beginning 2022 as well as additional resources procured that meet the state’s Clean Energy Transformation Act. Under PacifiCorp’s 2020 Protocol, and the Washington Interjurisdictional Allocation Methodology, Washington’s RPS position is improved by receiving a system share of renewable resources across the PacifiCorp’s system. The California RPS compliance position will be met with owned and contracted renewable resources, as well as REC purchases throughout the study period. The ramping RPS requirement results in an increased need for unbundled REC purchases to meet the annual and compliance period targets in 2021-2040. New renewable resources and transmission in the 2021 IRP update preferred portfolio mitigate that shortfall, but the company has made a 120,000 REC purchase towards compliance period 4, years 2021-2024, and will continue to evaluate the need for unbundled RECs and issue RFPs to meet its state RPS compliance requirements as needed. While not shown in Figure 1.13, PacifiCorp meets the Utah 2025 state target to supply 20 percent of adjusted retail sales with eligible renewable resources with existing owned and contracted resources and new renewable resources and transmission in the 2021 IRP Update preferred portfolio. 0 10 20 30 40 50 60 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Mi l l i o n T o n s CO2 Emissions 2021 IRP Update 2021 IRP 0 0.2 0.4 0.6 0.8 1 0 10 20 30 40 50 60 20 1 1 20 1 3 20 1 5 20 1 7 20 1 9 20 2 1 20 2 3 20 2 5 20 2 7 20 2 9 20 3 1 20 3 3 20 3 5 20 3 7 20 3 9 20 4 1 20 4 3 20 4 5 20 4 7 20 4 9 % o f 2 0 0 5 B a s e Mi l l i o n T o n s ( C O 2e) PacifiCorp CO2 Equivalent Emissions Trajectory PacifiCorp Emissions (Million ST CO2e)PacifiCorp 2005 Base (Million ST CO2e) % Reduction from 2005 Base PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 15 Figure 1.13 – Annual State RPS Compliance Forecast 0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 RE C s ( T h o u s a n d s ) Oregon RPS Unbundled Surrendered Bundled Surrendered Unbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement 0 100 200 300 400 500 600 700 RE C s ( T h o u s a n d s ) California RPS Unbundled Surrendered Bundled Surrendered Shortfall Requirement 0 2,000 4,000 6,000 8,000 10,000 12,000 RE C s ( T h o u s a n d s ) Washington RPS Unbundled Surrendered Bundled Surrendered Unbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY 16 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 2 – INTRODUCTION 17 CHAPTER 2 – INTRODUCTION This 2021 IRP Update describes resource planning activities following the filing of the 2021 IRP on September 1, 2021 and presents an updated load-and-resource balance, an updated preferred portfolio consistent with changes in the planning environment and provides a status update on the action plan filed with the 2021 IRP. In presenting the updated load and resource balance assessment and updated preferred portfolio, PacifiCorp describes changes relative to the 2021 IRP. PacifiCorp’s 2021 IRP Update preferred portfolio reflects updates to load, existing resources, signed contracts and modeling improvements. The 2021 IRP Update also includes an update to certain variant analysis conducted in the 2021 IRP related to portfolio analysis of major transmission projects and related resources including Energy Gateway South and D.1, Boardman- to-Hemingway and the 2020 All Source Request for Proposals final shortlist projects. Chapter 1 of the 2021 IRP Update provides an executive summary focused on the updated preferred portfolio. Chapter 3 describes the current planning environment, load updates, resource updates, state and federal policy updates, transmission upgrades and recent changes in the Western Resource Adequacy Program. Chapter 4 provides updated load-and-resource balance information. Chapter 5 describes changes to key inputs and assumptions relative to those used for the 2021 IRP. Chapter 6 presents the updated preferred portfolio, variant studies, a regional haze study and additional bookend price-policy studies for information. A status update on the 2021 IRP Action Plan is provided in Chapter 7. The Appendix provides additional load forecast details. PACIFICORP – 2021 IRP UPDATE CHAPTER 2 – INTRODUCTION 18 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 19 CHAPTER 3 – THE PLANNING ENVIRONMENT Federal Policy Update Federal Climate Change Legislation To date, no federal legislative climate change proposal has been passed by the U.S. Congress. Federal climate change legislation is not anticipated in the near term but remains possible in the mid- to long-term. New Source Performance Standards for Carbon Emissions – Clean Air Act § 111(b) New Source Performance Standards (NSPS) are established under the Clean Air Act for certain industrial sources of emissions determined to endanger public health and welfare. On October 23, 2015, the U.S. Environmental Protection Agency (EPA) finalized a rule limiting carbon emissions from coal-fueled and natural-gas-fueled power plants. New natural-gas-fueled power plants can emit no more than 1,000 pounds of carbon dioxide (CO2) per megawatt-hour (MWh). New coal- fueled power plants can emit no more than 1,400 pounds of CO2/MWh. The final rule largely exempts simple cycle combustion turbines from meeting the standards. On December 6, 2018, the EPA proposed to revise the NSPS for greenhouse gas emissions from new, modified, and reconstructed fossil fuel-fired power plants. EPA’s proposal would replace EPA’s 2015 determination that carbon capture and storage technology was the best system of emissions reduction for new coal units. The comment period for the proposed revisions closed in March 2019. In January 2021, the EPA issued the final rule. However, in April 2021, at the request of the EPA as directed by the Biden Administration, the D.C. Circuit vacated and remanded the January 2021 final rule. Carbon Emission Guidelines for Existing Sources – Clean Air Act § 111(d) On August 3, 2015, EPA issued a final rule, referred to as the Clean Power Plan (CPP), regulating CO2 emissions from existing power plants. On February 9, 2016, the U.S. Supreme Court issued a stay of the CPP suspending implementation of the rule pending the outcome of the merits of litigation before the D.C. Circuit Court of Appeals. On October 10, 2017, EPA proposed to repeal the CPP and on August 21, 2018, proposed the Affordable Clean Energy (ACE) rule to replace the CPP. The ACE rule sets forth a list of “candidate technologies” that states can use to reduce greenhouse gas emissions at coal-fueled power plants. The ACE rule was finalized June 19, 2019, replacing the CPP. On January 19, 2021, the D.C. Circuit vacated the ACE rule and directed the EPA to proceed with new rulemaking for the control of carbon emissions from electric utility coal-fired boilers. Credit for Carbon Oxide Sequestration – Internal Revenue Service (IRS) § 45Q In 2008, the Internal Revenue Service issued a tax credit for carbon oxide sequestration under section 45Q to incentivize carbon capture and sequestration (CCS) investments. The tax credit is computed PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 20 per metric ton (tonne) of qualified carbon oxide captured and sequestered.1 Carbon oxide can either be permanently disposed of in secure geological storage or the carbon oxide can be utilized – typically as a tertiary injectant in enhanced oil recovery (EOR). The Bipartisan Budget Act of 2018 reformed 45Q for carbon capture equipment that is placed in service on or after February 9, 2018, increasing the credit amount from $10/tonne to $35/tonne for utilization and from $20/tonne to $50/tonne for storage.2 This Act also removed the limit on the amount of tax credits that could be awarded for CCS, and, instead, requires a minimum amount of carbon oxide to be captured annually and is available for 12 years from the date the carbon capture equipment is originally placed into service.3 Clean Air Act Criteria Pollutants – National Ambient Air Quality Standards The Clean Air Act requires EPA to set National Ambient Air Quality Standards (NAAQS) for six criteria pollutants that have the potential of harming human health or the environment. The NAAQS are rigorously vetted by the scientific community, industry, public interest groups, and the general public, and establish the maximum allowable concentration allowed for each “criteria” pollutant in outdoor air. The six pollutants are carbon monoxide, lead, ground-level ozone, nitrogen dioxide (NOX), particulate matter (PM), and sulfur dioxide (SO2). The standards are set at a level that protects public health with an adequate margin of safety. All states are required to develop a state implementation plan (SIP) to implement the NAAQS, and that plan must be approved by EPA. The plan must provide for implementation, maintenance, and enforcement of the NAAQS for each pollutant, with more specific requirements and limits imposed on states that fail to achieve the NAAQS for a particular pollutant. SIPs must also contain adequate provisions to prevent emissions that significantly contribute to nonattainment of the NAAQS in any other state. In October 2015, EPA issued a final rule modifying the standards for ground-level ozone from 75 parts per billion (ppb) to 70 ppb. On November 16, 2017, the EPA designated all counties where PacifiCorp’s coal facilities are located (Lincoln, Sweetwater, Converse and Campbell Counties in Wyoming; and Emery County in Utah) as attainment/unclassifiable. On June 4, 2018, the EPA designated two areas in Utah as Marginal Nonattainment: Salt Lake County and three neighboring counties (Northern Wasatch Front) where the PacifiCorp Gadsby facility is located, and part of Utah County (Southern Wasatch Front) where the PacifiCorp Lake Side facility is located. A marginal designation is the least stringent classification for an ozone nonattainment area and does not require a formal nonattainment SIP. Utah submitted its strategy for meeting the standard to EPA in May of 2021. The Wasatch Front was required to attain the ozone standard by August 3, 2021. Recent monitoring data indicates that the Southern Wasatch Front nonattainment area has attained the standard, and Utah has initiated the process for redesignation to attainment for this area. However, recent monitoring data indicates that the Northern Wasatch Front nonattainment area will not attain the ozone standard by that date and will be bumped up to moderate classification in 2022. 1 Before February 9, 2018, the tax credit was strictly for CO2. 2 The tax credit reaches $35/tonne and $50/tonne in 2026. 3 For an electric generating facility, a minimum of 500,000 tonnes of qualified carbon oxide must be captured per year to receive the 45Q tax credit. Construction of the qualified facility must begin before January 1, 2026. PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 21 On March 11, 2022, the Environmental Protection Agency released a pre-publication version of its "Ozone Transport Rule" (also called Good Neighbor Rule or Cross-State Air Pollution Rule), which contains proposed revisions intended to address ozone transport between states. The rule is focused on reductions of nitrogen oxides, precursors to ozone formation, and covers 26 states. Four states, including Wyoming and Utah, are included in the cross-state program for the first time. Under the proposed rule, beginning in 2023, trading allowances and emissions budgets would be set to achieve reductions from current emissions through immediately available measures. Starting in May of 2026, emissions budgets would be set for coal-fired units at levels achievable by the installation of selective catalytic reduction (SCR) controls. Daily emission “backstop” limits for units with SCR will become effective in 2027. PacifiCorp is evaluating the pre-publication version of the proposed rule and its potentially significant impacts on coal-fired power plants in both Utah and Wyoming as first-time participants in the trading program. PacifiCorp anticipates submitting comments as part of the public comment process. The public comment process will commence when the proposed rule is published in the Federal Register and run for 60-days. Further review of the lengthy and complex OTR is needed to determine how it will impact specific Utah and Wyoming facilities. However, on initial review, it appears that emissions levels for coal-fired units without SCR could be significantly impacted starting in 2026, while existing natural gas units will not experience significant reduction requirements from 2021 levels. The rule has yet to be formally proposed and could change before its expected finalization in late 2022 or early 2023. In April 2017, the EPA Administrator signed a final action to reclassify the Salt Lake City and Provo PM2.5 nonattainment area from moderate to serious. PacifiCorp’s Lake Side and Gadsby facilities were identified as major sources subject to Utah’s serious nonattainment area SIP for PM2.5 and PM2.5 precursors. On April 27, 2017, PacifiCorp submitted a best-available control measure technology analysis for Lake Side and Gadsby to the Utah Division of Air Quality for review. PacifiCorp proposed ammonia limits for the Gadsby and Lake Side facilities. On January 2, 2019, the Utah Air Quality Board adopted source specific emission limits and operating practices in the SIP which incorporated the current emission and operating limits for the Lake Side and Gadsby facilities. On November 6, 2020, EPA proposed approval to redesignate the Salt Lake City and Provo nonattainment areas for PM2.5 as attainment. The rulemaking was delayed by corrections issued in May of 2021 and has not yet been finalized. On January 9, 2018, EPA published the results for the air quality designations for the 2010 SO2 primary NAAQS-Round three in the Federal Register. The Utah county of Emery, where PacifiCorp’s Hunter and Huntington Generation Stations are located, was classified as attainment/unclassifiable. The Wyoming counties of Campbell and Lincoln, where PacifiCorp’s Wyodak and Naughton generation stations are located, were classified as attainment/unclassifiable. The eastern portion of Sweetwater County, where PacifiCorp’s Jim Bridger generation station is located, was classified as attainment/unclassifiable. PacifiCorp’s Jim Bridger facility has conducted on-site ambient SO2 monitoring to demonstrate compliance and is currently working with the state and federal agencies to terminate the monitoring site. On March 26, 2021, the EPA issued the last of its final designations for the 2010 primary SO2 standard. Included in this round was designation of Converse County, Wyoming as an attainment/unclassifiable area. PacifiCorp's Dave Johnston generating facility is located in Converse County. PacifiCorp facilities located in areas classified as attainment/unclassifiable will PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 22 be required to demonstrate ongoing compliance by performing modeling every three years using actual facility emission data. Regional Haze EPA’s regional haze rule, finalized in 1999, requires states to develop and implement plans to improve visibility in certain national park and wilderness areas. On June 15, 2005, EPA issued final amendments to its regional haze rule to require emission controls known as the Best Available Retrofit Technology (BART) for industrial facilities meeting certain regulatory criteria with emissions that have the potential to affect visibility. The regulated pollutants include PM, NOX, SO2, certain volatile organic compounds, and ammonia. The 2005 amendments included final guidelines, known as BART guidelines, for states to use in determining which facilities must install controls and the type of controls the facilities must use. States were given until December 2007 to develop their implementation plans, in which states were responsible for identifying the facilities that would have to reduce emissions under BART guidelines, as well as establishing BART emissions limits for those facilities. States are also required to periodically update or revise their implementation plans to reflect current visibility data and an effective long-term strategy for achieving reasonable progress toward visibility goals. In January 2017, EPA issued a final rule updating requirements for the first periodic update to the SIP. EPA required states to submit their second periodic SIP update by July 31, 2021, unless granted an extension. The regional haze rule is intended to achieve natural visibility conditions by 2064 in specific National Parks and Wilderness Areas, many of which are in the western United States where PacifiCorp owns and operates several coal-fired generating units (Utah, Wyoming, Colorado and Montana as well as Arizona, where a PacifiCorp-owned coal unit ceased operating in 2020). On August 20, 2019, EPA issued a final guidance document on the technical aspects of developing regional haze SIPs for the second implementation period of the Regional Haze Program. EPA issued additional guidance through a memorandum on July 8, 2021, that emphasizes the 4-factor reasonable progress analysis for the second planning period and the reduced weight of visibility as a factor in the second planning period. Utah Regional Haze In May 2011, the state of Utah issued a regional haze SIP requiring the installation of SO2, NOX and PM controls on Hunter Units 1 and 2 and Huntington Units 1 and 2. In December 2012, the EPA approved the SO2 portion of the Utah regional haze SIP and disapproved the NOX and PM portions. EPA’s approval of the SO2 SIP was appealed by environmental advocacy groups to the Tenth Circuit Court of Appeals (“Tenth Circuit” or “Court"). In addition, PacifiCorp and the state of Utah appealed EPA’s disapproval of the NOX and PM SIP. PacifiCorp and the state’s appeals were dismissed, and EPA’s approval of the SO2 SIP was upheld by the Tenth Circuit. In June 2015, the state of Utah submitted a revised SIP to EPA for approval with an alternative BART NOX analysis incorporating a requirement for PacifiCorp to retire Carbon Units 1 and 2, crediting NOX controls previously installed on Hunter Unit 3, and concluding that no incremental controls (beyond those included in the May 2011 SIP and already installed) were required at the Hunter and Huntington units. On June 1, 2016, EPA issued a final rule to partially approve and partially disapprove Utah’s regional haze BART NOx SIP and propose a federal implementation plan (FIP). The FIP required the installation of selective catalytic reduction (SCR) controls by August 4, 2021, at four of PacifiCorp’s units in Utah: Hunter Units 1 and 2 and Huntington Units 1 and 2. On PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 23 September 2, 2016, the state of Utah and PacifiCorp filed petitions for administrative and judicial review of EPA’s final rule, followed by a motion to stay the effective date of the final rule. On June 30, 2017, Utah and PacifiCorp provided new information to EPA, again requesting reconsideration. EPA responded on July 14, 2017, indicating its intent to reconsider its FIP. EPA also filed a motion with the Tenth Circuit to stay EPA’s FIP and hold the litigation in abeyance pending the rule’s reconsideration. On September 11, 2017, the Tenth Circuit granted the petition for stay and the request for abatement. The compliance deadline of the FIP and the litigation were stayed pending EPA’s reconsideration, and EPA was required to file periodic status reports with the Court. Utah and PacifiCorp worked with EPA to develop a revised Utah Regional Haze SIP, based on the new Comprehensive Air Quality Model with Extensions (CAMx) modeling. The Utah Air Quality Board approved the revised SIP on June 24, 2019, and the SIP Revision was submitted to EPA for review on July 3, 2019. On December 3, 2019, Utah submitted a supplement to EPA with a minor SIP revision relating to PM 2.5. On January 10, 2020, the EPA published its proposed approval of the Utah SIP Revision and withdrawal of the FIP requirements for the installation of SCR on Hunter Units 1 and 2 and Huntington Units 1 and 2. After receiving public comments and holding a public hearing in the Price area on February 12, 2020, EPA issued final approval of the Utah SIP Revision and FIP withdrawal on November 27, 2020. The final rule credits existing NOX emission controls at the Hunter and Huntington plants as well as NOX and PM emission reductions provided by the closure of the Carbon plant in 2015. Based on the newly approved plan, EPA also withdrew the 2016 FIP requirements to install selective catalytic reduction (SCR) control technology on Hunter Units 1 and 2 and Huntington Units 1 and 2. On January 11, 2021, the Tenth Circuit granted Utah, PacifiCorp, and EPA’s motion to dismiss the Utah regional haze petitions. Environmental advocacy groups filed a petition for review, objecting to the revised Utah regional haze SIP on January 19, 2021, in the Tenth Circuit. At EPA’s request, the Tenth Circuit abated the petition on February 4, 2021, while EPA considered the petition under the new Biden administration’s guidelines. The state of Utah, PacifiCorp and co-owners of the Hunter plant filed motions to intervene. EPA notified the court that it would defend the revised Utah regional haze SIP, and the court granted intervention to Utah and PacifiCorp in December of 2021. The parties scheduled briefing, and HEAL Utah submitted its opening brief on February 8, 2022, challenging the legitimacy of the states’ modeling as well as crediting emissions from the Carbon plant retirement and requesting reinstatement of the FIP and the SCR requirement at Hunter Units 1 and 2 and Huntington Units 1 and 2. EPA’s response brief is due April 5, 2022, with briefs from Utah and PacifiCorp to follow on May 3, 2022. The Western Regional Air Partnership (WRAP) developed modeling for the state’s use for the implementation of the second planning period. Utah used a ‘Q/d’ screening level of 10 to determine which sources to evaluate for reasonable progress controls under the rule. On April 21, 2020, PacifiCorp submitted a Regional Haze Reasonable Progress Analysis for the second planning period to the Utah Department of Environmental Quality (Utah DEQ) for PacifiCorp’s Huntington and Hunter plants. The analysis was requested by the State as part of its second planning period SIP (2PP SIP) development process. PacifiCorp’s analysis included a proposal to implement reasonable progress emission limits for NOx and SO2 on the Hunter and Huntington units to meet PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 24 second planning period requirements. On October 20, 2020, PacifiCorp submitted a follow-up letter in response to questions from the Utah DEQ about proposed emission reductions and costs for control technology. The state is on track to submit a final implementation plan to the state air quality board in March or April 2022 and plans to submit the final state-approved implementation plan to the Environmental Protection Agency late summer/early fall of 2022. Wyoming Regional Haze On January 30, 2014, EPA issued a final rule partially approving and partially disapproving the Wyoming SIP. The final rule required installation of the following NOX and PM controls at PacifiCorp facilities for regional haze first planning period: • Naughton Units 1 and 2: low-NOX burners (LNB)/over-fired air (OFA) as BART • Naughton Unit 3 by December 31, 2014: SCR equipment and a baghouse, BART • Jim Bridger Units 1 – 4: LNB/separated over-fired air (SOFA), BART • Jim Bridger Unit 3 by December 31, 2015: SCR equipment, long-term strategy (LTS) • Jim Bridger Unit 4 by December 31, 2016: SCR equipment, LTS • Jim Bridger Unit 2 by December 31, 2021: SCR equipment, LTS • Jim Bridger Unit 1 by December 31, 2022: SCR equipment, LTS • Dave Johnston Unit 3: SCR within five years or a commitment to shut down in 2027, BART • Dave Johnston Unit 4: LNB/OFA, BART • Wyodak: SCR equipment within five years, BART Wyodak – PacifiCorp and the state of Wyoming petitioned EPA’s final action on Wyodak, which required SCR. PacifiCorp and the state of Wyoming successfully requested a stay of EPA’s final rule relating to the Wyoming SIP, pending resolution of the petition. PacifiCorp subsequently submitted a request for reconsideration to EPA and is currently engaged in a settlement process with EPA and Wyoming. The EPA, state of Wyoming and PacifiCorp signed a Settlement Agreement for Wyodak on December 16, 2020, removing the requirement to install SCR in lieu of monthly and annual NOX emission limits. EPA published the Settlement Agreement in the Federal Register requesting public comment on January 4, 2021. PacifiCorp submitted formal comments to the EPA on March 5, 2021, in support of the Wyodak Settlement Agreement. The public comment period was extended through July 6, 2021. EPA did not proceed with final approval of the Settlement Agreement and is currently engaged with Wyoming and PacifiCorp regarding alternative paths for resolution. Naughton – In its 2014 rule, EPA approved Wyoming’s determination that BART for Units 1 and 2 was LNB/OFA. EPA also indicated support for the conversion of Naughton Unit 3 to natural gas in lieu of retrofitting the unit with SCR and stated that it would expedite consideration of the gas conversion once the state of Wyoming submitted the requisite SIP amendment. Wyoming submitted its regional haze SIP amendment regarding Naughton Unit 3 to EPA on November 28, 2017. On March 7, 2017, Wyoming issued PacifiCorp a permit for Naughton Unit 3’s conversion to natural gas, extending the requirement to cease coal firing to no later than January 30, 2019. PacifiCorp ceased coal operation on Naughton Unit 3 on January 30, 2019. EPA’s final rule approval of Wyoming’s SIP revision for Naughton Unit 3 gas conversion was published in the Federal Register on March 21, 2019, with an effective date of April 22, 2019. Naughton Unit 3 PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 25 currently operates on natural gas. Environmental groups petitioned EPA’s approval of LNB/OFA as BART for Units 1 and 2 in the Tenth Circuit. The petition was stayed by the Court and remains stayed. The environmental groups have participated in on-going mediation with Wyoming, PacifiCorp and EPA to settle the Naughton claims. Jim Bridger – PacifiCorp installed SCR on Jim Bridger Units 3 and 4 by 2015 and 2016, the dates required by Wyoming state law as well as the 2014 SIP. On February 5, 2019, PacifiCorp submitted to Wyoming an application and proposed SIP revision instituting plant-wide variable average monthly-block pound per hour NOX and SO2 emission limits, in addition to an annual combined NOX and SO2 limit, on all four Jim Bridger units in lieu of the requirement to install SCR on Units 1 and 2. The proposed SIP revision demonstrates that the proposed limits are more cost effective while leading to better modeled visibility than the SCR installation on Units 1 and 2 required in the federally approved SIP. Wyoming’s proposed approval of the SIP revision was published for public comment July 20, 2019, through August 23, 2019. On May 5, 2020, the Wyoming Department of Environmental Quality issued permit P0025809 with PacifiCorp’s proposed monthly and annual NOX and SO2 emission limits. Under the permit, the new emissions limits become effective January 1, 2022. Wyoming submitted a corresponding regional haze SIP revision to EPA on May 14, 2020. After initially signaling that the SIP revision had been approved by EPA Region 8 in November of 2020, EPA did not finalize the approval by publication in the Federal Register after an administration change. EPA failed to act upon the SIP revision by November 14, 2021, as required by law. EPA, PacifiCorp and Wyoming worked to find a solution for the unresolved SIP revision and the pending January 1, 2022, SCR requirement. Using authority granted by the Clean Air Act, the Governor of Wyoming issued a temporary emergency order on December 27, 2021, suspending the current state implementation plan requirement for Jim Bridger Unit 2 to install SCR by December 31, 2021. The suspension was issued for the full four months allowed by the act due to EPA’s failure to act on the SIP revision submitted by Wyoming in 2020, by November 14, 2021. EPA published a proposed disapproval of Wyoming’s SIP revision on January 18, 2022, commencing a 30-day public comment period. Discussions between EPA, Wyoming, and PacifiCorp regarding the SIP revision and regional haze compliance at Jim Bridger are ongoing. The Wyoming district court approved a consent decree between PacifiCorp and Wyoming on February 14, 2022, to resolve regional haze compliance issues for the Jim Bridger plant. The consent decree enables PacifiCorp to continue operation of Jim Bridger units 1 and 2 until they are converted to natural gas in 2024. The consent decree commits Wyoming to processing a state implementation plan revision with post-conversion emission limits in a timely manner. WRAP performed modeling for the state to use for the implementation of the second planning period. On March 31, 2020, PacifiCorp submitted a four-factor reasonable progress analysis to Wyoming which analyzed PacifiCorp’s Naughton, Jim Bridger, Dave Johnston, and Wyodak plants. The four-factor analysis was used by the state in its development of the SIP for the regional haze second planning period (2PP SIP). The state of Wyoming issued its proposed 2PP SIP for public comment on February 18, 2022, and held a public hearing on March 23, 2022 to receive comments on their proposed plan. PacifiCorp participated in the hearing and provided verbal and written comments. It is estimated that the state will submit a final state-approved implementation plan to the U.S. Environmental Protection Agency in April 2022. In February of 2022 PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 26 environmental groups submitted a 60-day notice of intent to sue EPA to take action against states that have missed the deadline to submit their second planning period SIPs. Arizona Regional Haze The state of Arizona issued a regional haze SIP requiring, among other things, the installation of SO2, NOX and PM controls on Cholla Unit 4, which is owned by PacifiCorp and operated by Arizona Public Service. EPA approved, in part, and disapproved, in part, the Arizona SIP and issued a FIP requiring the installation of SCR equipment on Cholla Unit 4. PacifiCorp filed an appeal regarding the FIP as it relates to Cholla Unit 4, and the Arizona Department of Environmental Quality and other affected Arizona utilities filed separate appeals of the FIP as related to their interests. For the Cholla FIP requirements, the Ninth Circuit Court of Appeals stayed the appeals while parties attempted to agree on an alternative compliance approach. In July 2016, the EPA issued a proposed rule to approve an alternative Arizona SIP, which included the option to convert Cholla 4 to a natural gas-fired unit or retire the unit by in 2025. EPA approved the revised SIP on March 27, 2017. The final action allowed Cholla Unit 4 to utilize coal until April 30, 2025, with an option to convert to gas by July 31, 2025. Cholla Unit 4 was retired in December 2020. Colorado Regional Haze The Colorado regional haze SIP required SCR controls at Craig Unit 2 and Hayden Units 1 and 2, which were installed by the required dates, and the installation of selective non-catalytic reduction (SNCR) technology at Craig Unit 1. Environmental groups appealed EPA’s action, and PacifiCorp intervened in support of EPA. In July 2014, parties to the litigation, other than PacifiCorp, entered into a settlement agreement that required installation of SCR equipment at Craig Unit 1 in 2021. This was incorporated into a regional haze SIP revision that was approved by EPA in 2015. EPA approved a modified SIP on July 5, 2018, that requires Craig Unit 1 to retire by December 31, 2025, or, to convert the unit to natural gas by August 31, 2023. Colorado’s regional haze SIP for the second planning period were adopted in phases in 2020 and 2021 by the Colorado Air Quality Control Commission. The SIP includes retirements of Craig Units 1 and 2 by 2025 and 2028, respectively, and Hayden Units 1 and 2 by 2028 and 2027, respectively. Mercury and Hazardous Air Pollutants The Mercury and Air Toxics Standards (MATS) became effective April 16, 2012. The MATS rule requires that new and existing coal-fueled facilities achieve emission standards for mercury, acid gases and other non-mercury hazardous air pollutants. Existing sources were required to comply with the new standards by April 16, 2015. However, individual sources may have been granted up to one additional year, at the discretion of the Title V permitting authority, to complete installation of controls or for transmission system reliability reasons. By April 2015, PacifiCorp had taken the required actions to comply with MATS across its generation facilities. On April 25, 2016, the EPA published a Supplemental Finding that determined that it is appropriate and necessary to regulate under the MATS rule which addressed the Supreme Court decision. On February 7, 2019, the EPA published a reconsideration of the Supplemental Finding in which it proposed to find that it is not appropriate and necessary to regulate hazardous air pollutants, reversing PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 27 the Agency’s prior determination. In May 2020, the EPA published its decision to repeal the appropriate and necessary findings in the MATS rule regarding regulation of electric utility steam generating units, and to retain the rule’s current emission standards. The rule took effect in July 2020. Several petitions for review were filed in the D.C. Circuit by parties challenging and supporting the EPA's decision to rescind the appropriate and necessary finding. On February 9, 2022, the EPA proposed to revoke the May 2020, decision that is not appropriate and necessary to regulate under Section 112 and reaffirm the April 2016 finding. Coal Combustion Residuals In May 2010, the EPA released a proposed rule to regulate the management and disposal of coal combustion byproducts under the Resource Conservation and Recovery Act (RCRA). The final rule became effective October 19, 2015. The final rule regulates coal combustion byproducts as non- hazardous waste under RCRA Subtitle D and establishes minimum nationwide standards for the disposal of coal combustion residuals (CCR). Under the final rule, surface impoundments and landfills utilized for coal combustion byproducts may need to be closed unless they can meet the more stringent regulatory requirements. The final rule requires regulated entities to post annual groundwater monitoring and corrective action reports. The first of these reports was posted to PacifiCorp’s coal combustion rule compliance data and information websites in March 2018. Based on the results in those reports, additional action was required under the rule. At the time the rule became effective in October 2015, nine surface impoundments and four landfills were in operation and subject to the final rule. Since that time, three surface impoundments have been closed under the CCR rules and two are in the process of closure. Multiple parties filed challenges over various aspects of the final rule in 2015, resulting in settlement of some of the issues and subsequent regulatory action by the EPA, including subjecting inactive surface impoundments to regulation. In response to legal challenges and court actions, EPA, in March 2018, issued a proposal to address provisions of the final CCR rule that were remanded back to the agency. The proposal included provisions that establish alternative performance standards for owners and operators of CCR units located in states that have approved permit programs or are otherwise subject to oversight through a permit program administered by the EPA. The first phase of the CCR rule amendments was made effective in August 2018 (the "Phase 1, Part 1 rule"). In addition to adopting alternative performance standards and revising groundwater performance standards for certain constituents, the EPA extended the deadline by which facilities must initiate closure of unlined ash ponds exceeding a groundwater protection standard and impoundments that do not meet the rule's aquifer location restrictions to October 2020. Following the March 2019 submittal of competing motions from environmental groups, EPA finalized its Holistic Approach to Closure: Part A rule ("Part A rule") in September 2020. The rule reclassified compacted-soil lined surface impoundments from "lined" to "unlined," established a deadline of April 11, 2021, by which all unlined surface impoundments must initiate closure, and revised the alternative closure provisions to grant facilities additional time to initiate closure in order to manage CCR and non-CCR waste streams either due to a lack of alternative capacity or due to a commitment to close the coal-fueled operating unit and complete closure of unlined impoundments by a date certain. The Part A rule also revised certain requirements regarding annual groundwater monitoring and corrective action reports and publicly accessible CCR internet sites. A provision in Part A allows demonstrations to be submitted to the EPA allowing for operation of unlined CCR ponds beyond the April 11, 2021, deadline for initiation of closure. The demonstrations were allowed to be submitted for: (1) a site- specific extension to develop alternate disposal capacity and initiate closure by October 15, 2023; and (2) a site-specific extension for facilities that agree to shut down the coal-fueled unit and PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 28 complete ash pond closure activities by October 17, 2028. PacifiCorp has submitted alternative closure demonstrations for the Naughton South Ash Pond and the Jim Bridger FGD Pond 2, submitted in November 2020. Approval of these demonstrations was anticipated in first quarter 2021 prior to the April 11, 2021, cease receipt of waste date, but has not been granted as of February 2022. On January 11, 2022, PacifiCorp received notice from the EPA that the Jim Bridger and Naughton demonstrations have been determined to be complete and the April 11, 2021, cease receipt of waste deadline is tolled until the EPA issues a final decision. On October 16, 2020, the EPA released the pre-publication version of the final Holistic Approach to Closure: Part B rule ("Part B rule"). The Part B rule finalizes a two-step process, as set forth in the March 2020 proposal, allowing facilities to request approval to continue operating an existing unlined CCR surface impoundment with an alternate liner system. The other provisions that were contained in the Part B proposal, including (1) options to use CCR during closure of a CCR unit, (2) an additional closure-by-removal option and (3) new requirements for annual closure progress reports, were not finalized with the Part B rule. These options will be addressed by the EPA in a subsequent rulemaking action. In addition to the Part A and Part B rules, the EPA has proposed the Phase II rule, the federal CCR permit program rule, and the advanced notice of proposed rulemaking for legacy impoundments. Until the proposals are finalized and fully litigated, PacifiCorp cannot determine whether additional action may be required. Separately, on August 10, 2017, the EPA issued proposed permitting guidance on how states' CCR permit programs should comply with the requirements of the final rule as authorized under the December 2016 Water Infrastructure Improvements for the Nation Act. To date, none of the states in which PacifiCorp operates has submitted an application to the EPA for approval of state permitting authority. The state of Utah adopted the federal final rule in September 2016, which required PacifiCorp to submit permit applications for two of its landfills by March 2017. It is anticipated that the state of Utah will submit an application to EPA for approval of CCR permit program prior to the end of 2022. In 2019, the state of Wyoming proposed to adopt state rules which incorporate the final federal rule by reference. Wyoming finalized its rule in late 2020 and is waiting on legislative approval, likely in 2022, before submitting an application to the EPA to implement a state permit program. Water Quality Standards Cooling Water Intake Structures The federal Water Pollution Control Act (“Clean Water Act”) establishes the framework for maintaining and improving water quality in the U.S. through a program that regulates, among other things, discharges to and withdrawals from waterways. The Clean Water Act requires that cooling- water-intake structures reflect the “best technology available for minimizing adverse environmental impact” to aquatic organisms. In May 2014, EPA issued a final rule, effective October 2014, under § 316(b) of the Clean Water Act to regulate cooling-water intakes at existing facilities. The final rule established requirements for electric-generating facilities that withdraw more than two million gallons per day, based on total design intake capacity, of water from waters of the U.S. and use at least 25 percent of the withdrawn water exclusively for cooling purposes. PacifiCorp’s Dave Johnston generating facility withdraws more than two million gallons per day of water from waters of the U.S. for once-through cooling applications. Jim Bridger, Naughton, Gadsby, Hunter, and Huntington generating facilities currently use closed-cycle cooling towers but withdraw more than two million gallons of water per day. The rule includes impingement (i.e., when fish and other aquatic organisms are trapped against screens when water is drawn into a facility’s cooling system) mortality standards and entrainment (i.e., when organisms are drawn PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 29 into the facility) standards. The standards will be set on a case-by-case basis to be determined through site-specific studies and will be incorporated into each facility’s discharge permit. Rule-required permit application requirements (PARs) have been submitted to the appropriate permitting authorities for the Jim Bridger, Naughton, Gadsby, Hunter and Huntington plants. As the five facilities utilize closed-cycle recirculating cooling water systems (cooling towers) exclusively for equipment cooling, it is expected that state agencies will require no further action from PacifiCorp to comply with the rule-required standards. Because Dave Johnston utilizes once-through cooling with withdrawal rates greater than 125 million gallons per day, the facility has been required to conduct more rigorous permit application requirements. The Dave Johnston permit application requirements were submitted to the Wyoming Water Quality Division on May 31, 2019. The application proposed that no modifications to the intake structure were required; however, upon review of the submittal and subsequent issuance of a draft permit for public notice, the Water Quality Division has indicated that PacifiCorp may be required to select and implement an approved 316(b) impingement mortality compliance option by December 31, 2023. As the final Dave Johnston Wyoming Pollutant Discharge Elimination System permit has yet to be issued which is expected to include 316(b) impingement mortality (IM) compliance requirements, it is anticipated that the December 31, 2023, IM technology implementation date will be adjusted to compensate for the actual permit issuance date. As of March 2022, the Wyoming and Utah regulatory agencies have yet to make 316(b) compliance determinations for the site-specific permit application requirements which were provided to the agencies for each PacifiCorp rule-affected facility. Effluent Limit Guidelines In November 2015, the EPA published final effluent limitation guidelines and standards for the steam electric power generating sector which, among other things, regulate the discharge of bottom ash transport water, fly ash transport water, combustion residual leachate and non-chemical metal cleaning wastes. These guidelines, which had not been revised since 1982, were revised in response to the EPA's concerns that the addition of controls for air emissions has changed the effluent discharged from coal- and natural gas-fueled generating facilities. Under the originally promulgated guidelines, permitting authorities were required to include the new limits in each impacted facility's National Pollutant Discharge Elimination System permit upon renewal with the new limits to be met as soon as possible, beginning November 1, 2018, and fully implemented by December 31, 2023. On April 5, 2017, a request for reconsideration and administrative stay of the guidelines was filed with the EPA. EPA granted the request for reconsideration and extended certain compliance dates for flue gas desulfurization wastewater and bottom ash transport water limits until November 1, 2020. On November 22, 2019, EPA proposed updates to the 2015 rule, specifically addressing flue gas desulfurization wastewater and bottom ash transport water. Those proposals were formalized in rule when the EPA administrator signed the Reconsideration Rule, and it was published in the Federal Register on October 13, 2020. The rule eases selenium limits on flue gas desulfurization wastewater, eases the zero-discharge requirements on bottom ash transport water associated with blowdown of ash handling systems, allows a two-year time extension to meet flue gas desulfurization wastewater requirements, and includes additional subcategories to both wastewater categories. Most of the issues raised by this rule are already being addressed at PacifiCorp facilities through compliance with the coal combustion residuals rule and are not expected to impose significant PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 30 additional requirements on the facilities. The Dave Johnston plant anticipates achieving compliance with the rule by issuing a notice of planned participation for subcategorization, or by installation and operation of a bottom ash recycle system that would enable long-term compliance with the Reconsideration Rule. Tax Extender Legislation On Dec. 27, 2020, President Trump signed into law the Taxpayer Certainty and Disaster Relief Act of 2020. Among other things, the bill extended and expanded certain alternative energy tax credits. Notable as relating to the 2021 IRP, the renewable electricity production tax credit (PTC) was extended by one year for certain qualifying facilities; for wind facilities that begin construction during 2021, the credit continues to be equal to 60% of the full value of the PTC. The energy tax credit (ITC) was extended by two years for certain qualifying facilities; the bill extends the 26% ITC for solar energy property that begins construction during 2021 and 2022, before being phased down further. The energy tax credit was expanded to cover offshore wind facilities; generally, any offshore wind project that on which construction after December 31, 2017, and before January 1, 2026, will qualify for a 30% ITC. And, finally, the credit for carbon dioxide sequestration was extended to cover facilities that begin construction by the end of 2025. Additional schedules detailing the phase-out of the wind PTC and solar ITC are provided as follows: PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 31 Table 3.1 – Tax Extender Legislation and Phaseout of PTC and ITC These schedules remain then same as referenced in the 2021 IRP. State Policy Update California Under the authority of the Global Warming Solutions Act, the California Air Resources Board (CARB) adopted a greenhouse gas cap-and-trade program in October 2011, with an effective date of January 1, 2012; compliance obligations were imposed on regulated entities beginning in 2013. The first auction of greenhouse gas allowances was held in California in November 2012, and the second auction in February 2013. PacifiCorp is required to sell, through the auction process, its directly allocated allowances and purchase the required amount of allowances necessary to meet its compliance obligations. In May 2014, CARB approved the first update to the Assembly Bill (AB) 32 Climate Change scoping plan, which defined California’s climate change priorities for the next five years and set the groundwork for post-2020 climate goals. In April 2015, Governor Brown issued an executive PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 32 order to establish a mid-term reduction target for California of 40 percent below 1990 levels by 2030. CARB was subsequently directed to update the AB 32 scoping plan to reflect the new interim 2030 target and previously established 2050 target. In July 2017, California Governor Jerry Brown signed AB 398, extending the state’s California Cap and Trade program from January 1, 2021, through December 31, 2030. In 2022, CARB is expected to issue a revised scoping plan establishing emissions reduction targets post-2030. The 2022 scoping plan may also reduce target prior to 2030. In 2002, California established a renewable portfolio standard (RPS) requiring investor-owned utilities to increase procurement from eligible renewable energy resources. California’s RPS requirements have been accelerated and expanded a number of times since its inception. Most recently, in September 2018, Governor Jerry Brown signed into law the 100 Percent Clean Energy Act of 2018, Senate Bill (SB) 100, which requires utilities to procure 60 percent of their electricity from renewables by 2030 and enabled all the state’s agencies to work toward a longer-term planning target for 100 percent of California’s electricity to come from renewable and zero-carbon resources by December 31, 2045. Oregon In 2007, Oregon enacted SB 838 establishing an RPS requirement in Oregon. Under SB 838, utilities are required to deliver 25 percent of their electricity from renewable resources by 2025. On March 8, 2016, Governor Kate Brown signed SB 1547-B, the Clean Electricity and Coal Transition Plan, into law. SB 1547-B extends and expands the Oregon RPS requirement to 50 percent of electricity from renewable resources by 2040 and requires that coal-fueled resources are eliminated from Oregon’s allocation of electricity by January 1, 2030. The increase in the RPS requirements under SB 1547-B is staged—27 percent by 2025, 35 percent by 2030, 45 percent by 2035, and 50 percent by 2040. The bill changes the renewable energy certificate (REC) life to five years, while allowing RECs generated from the effective date of the bill passage until the end of 2022 from new long-term renewable projects to have unlimited life. The bill also includes provisions to create a community-solar program in Oregon and encourage greater reliance on electricity for transportation. On March 10, 2020, Oregon Governor Kate Brown issued Executive Order 20-04 (EO 20-04), which directs state agencies to take actions to reduce and regulate greenhouse gas emissions. EO 20-04 establishes emissions reduction goals for Oregon and directs certain state agencies to take specific actions to reduce emissions and mitigate the impacts of climate change. EO 20-04 also provides overarching direction to state agencies to exercise their statutory authority to help achieve Oregon's climate goals. In 2021, Oregon passed House Bill (HB) 2021, which directs utilities to reduce emissions levels below 2010-2012 baseline levels by 80% by 2030, 90% by 2035, and 100% by 2040. Utilities will also convene a Community Benefits and Impacts Advisory Group. PacifiCorp’s 2023 IRP will include modeling as appropriate to support HB 2021. HB 2021 also increases state goals for small- scale renewable energy projects, to ten percent of aggregate electrical capacity by 2030. HB 2021 is complementary to – but does not modify – Oregon’s longstanding RPS requirements. PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 33 Washington In November 2006, Washington voters approved Initiative 937 (I-937), the Washington Energy Independence Act, which imposes targets for energy conservation and the use of eligible renewable resources on electric utilities. Under I-937, utilities must supply 15 percent of their energy from renewable resources by 2020. Utilities must also set and meet energy conservation targets starting in 2010. In 2008, the Washington Legislature approved the Climate Change Framework E2SHB 2815, which establishes the following state greenhouse gas emissions reduction limits: (1) reduce emissions to 1990 levels by 2020; (2) reduce emissions to 25 percent below 1990 levels by 2035; and (3) by 2050, reduce emissions to 50 percent below 1990 levels or 70 percent below Washington’s forecasted emissions in 2050. In July 2015, Governor Inslee released an executive order that directed the Washington Department of Ecology to develop new rules to reduce carbon emissions in the state. In December 2017, Washington’s Superior Court concluded that the Department of Ecology did not have the authority to impose the Clean Air Rule without legislative approval. As a result, the Department of Ecology has suspended the rule’s compliance requirements. In 2019, the Washington Legislature approved the Clean Energy Transformation Act (CETA) which requires utilities to eliminate coal-fired resources from Washington rates by December 31, 2025, be carbon neutral by January 1, 2030, and establishes a target of 100 percent of its electricity from renewable and non-emitting resources by 2045. Finally, in 2021, Washington passed the Climate Commitment Act, which establishes a cap-and- trade program to be implemented by no later than January 1, 2023, through the regulatory rulemaking process. The Climate Commitment Act does not modify any of PacifiCorp’s obligations under CETA, and utility allowances within the cap-and-trade program are aligned with the CETA renewable energy requirements. The legislation allows – but does not require – linkage with cap-and-trade programs in jurisdictions outside of Washington state. Utilities are provided allowances at no cost to “mitigate the cost burden” of the program on customers, Utah In March 2008, Utah enacted the Energy Resource and Carbon Emission Reduction Initiative, which includes provisions to require utilities to pursue renewable energy to the extent that it is cost effective. It sets out a goal for utilities to use eligible renewable resources to account for 20 percent of their 2025 adjusted retail electric sales. On March 10, 2016, the Utah legislature passed SB 115–The Sustainable Transportation and Energy Plan (STEP). The bill supports plans for electric vehicle infrastructure and clean coal research in Utah and authorizes the development of a renewable energy tariff for new Utah customer loads. The legislation establishes a five-year pilot program to provide mandated funding for electric vehicle infrastructure and clean coal research, and discretionary funding for solar development, utility-scale battery storage, and other innovative technology and air quality initiatives. The legislation also allows PacifiCorp to recover its variable power supply costs through an energy balancing account and establishes a regulatory accounting mechanism to manage risks and provide planning flexibility associated with environmental compliance or other PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 34 economic impairments that may affect PacifiCorp’s coal-fueled resources in the future. The deferrals of variable power supply costs went into effect in June 2016, and implementation and approval of the other programs was completed by January 1, 2017. On March 11, 2020, the Utah Legislature passed HB 396, Electric Vehicle Charging Infrastructure Amendments, that enables PacifiCorp to create an Electrical Vehicle Infrastructure Program, with a maximum funding from customers of $50 million for all costs and expenses. The legislation allows PacifiCorp to own and operate electric vehicle charging stations and to provide investments in make-ready infrastructure to interested customers. Wyoming On March 8, 2019, Wyoming Senate File 0159 (SF 159) was passed into law. SF 159 limits the recovery costs for the retirement of coal fired electric generation facilities, provides a process for the sale of an otherwise retiring coal fired electric generation facility, exempts a person purchasing an otherwise retiring coal fired electric generation facility from regulation as a public utility; requires purchase of electricity generated from purchased retiring coal fired electric generation facility (as specified in final bill); and provides an effective date. Cost recovery associated with electric generation built to replace a retiring coal fired generation facility shall not be allowed by the Wyoming Public Service Commission unless the Commission has determined that the public utility made a good faith effort to sell the facility to another person prior to its retirement and that the public utility did not refuse a reasonable offer to purchase the facility or the Commission determines that, if a reasonable offer was received, the sale was not completed for a reason beyond the reasonable control of the public utility. Under SF 159 electric public utilities, other than cooperative electric utilities, shall be obligated to purchase electricity generated from a coal fired electric generation facility purchased under agreement approved by the Commission, provided the otherwise retiring coal fired electric generation facility offers to sell some or all of the electricity from the facility to an electric public utility, the electricity is sold at a price that is no greater than the purchasing electric utility’s avoided cost, the electricity is sold under a power purchase agreement, and the Commission approves a 100 percent cost recovery in rates for the cost of the power purchase agreement and the agreement is 100 percent allocated to the public utility’s Wyoming customers unless otherwise agreed to by the public utility. In March 2020, the Wyoming legislature passed House Bill 200 (HB 200), Reliable and Dispatchable Low-Carbon Energy Standards. HB 200 requires the Wyoming Public Service Commission to put in place a standard for each public utility specifying a percentage of electricity to be generated from coal-fired generation utilizing carbon capture technology by 2030. The requirement would only apply to generation allocated to Wyoming customers. HB 200 will require each public utility to demonstrate in its IRP the steps taken to achieve the electricity generation standard established by the Commission and will allow rate recovery of costs incurred by a public utility that utilizes coal-fired generation with carbon capture technology installed. The Commission finalized administrative rules to implement HB 200, which became effective January 7, 2022. The administrative rules require public utilities to file an initial application to establish intermediate standards for compliance by March 31, 2022, and an application to PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 35 establish the final plan for compliance by March 31, 2023. PacifiCorp filed the initial application with the Commission on March 31, 2022, as required. During the 2022 legislative session, the Wyoming Legislature passed HB 131, nuclear power plant and storage amendments, that will help facilitate development of the Natrium nuclear demonstration project. The bill modifies existing laws to clarify the authority of the United States Nuclear Regulatory Commission. The bill also requires the operator of the facility, at least 30 days prior to construction, to submit a report identifying the number of jobs expected to be created by the project, the amount of local and state taxes estimated to be generated by the project, and the anticipated benefits and impacts that will accrue to the state and local community from the project. With respect to SF 159, the bill provides that the requirements of that law shall not apply to a public utility that replaces a coal-fired generation facility with an advanced nuclear reactor. Finally, the bill exempts tax payments, but provides that, beginning July 1, 2035, the exemption only applies if not less than 80 percent of the uranium is sourced in the United States. Greenhouse Gas Emission Performance Standards California, Oregon and Washington have greenhouse gas emission performance standards applicable to all electricity generated in the state or delivered from outside the state that is no higher than the greenhouse gas emission levels of a state-of-the-art combined cycle natural gas generation facility. The standards for Oregon and California are currently set at 1,100 lb. CO2/MWh, which is defined as a metric measure used to compare the emissions from various greenhouse gases based on their global warming potential. In September 2018, the Washington Department of Commerce issued a new rule lowering the emissions performance standard to 925 lb. CO2/MWh. Energy Gateway Transmission Program Planning As discussed in 2021 IRP, the Energy Gateway transmission project continues to play an important role in PacifiCorp’s commitment to provide safe, reliable, reasonably priced electricity to meet the needs of our customers. Energy Gateway’s design and extensive footprint provides needed system reliability improvements and supports the development of a diverse range of cost-effective resources required for meeting customers’ energy needs. The IRP has incorporated Energy Gateway as part of a solution for delivering the least cost resource portfolio for multiple IRP planning cycles. PacifiCorp continues to develop methods, in parallel with current industry best practices and regional transmission planning requirements, to better quantify all the benefits of transmission that are essential to serve customers. For example, Energy Gateway is designed to relieve operating limitations, increase capacity, and improve operations and reliability in the existing electric transmission grid. Figure 3.1 shows a high-level geography of the Energy Gateway transmission project. PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 36 Figure 3.1 – Energy Gateway Map This map is for general reference only and reflects current plans. It may not reflect the final routes, construction sequence or exact line configuration. Energy Gateway Transmission Project Updates Wallula to McNary (Segment A) This project was placed in service in January 2019. PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 37 Gateway West (Segments D and E) Under the National Environmental Policy Act (NEPA), the U.S. Bureau of Land Management (BLM) has completed the environmental impact statement (EIS) for the Gateway West project. The BLM released its final EIS on April 26, 2013, followed by the record of decision (ROD) on November 14, 2013, providing a right-of-way grant for all of Segment D and for all but two segments of Segment E, followed with a record of decision on these two segments of the line on April 19, 2018: • Gateway West (Segment D1): A single-circuit 230-kV line that will run approximately 59 miles between the existing Windstar substation in eastern Wyoming and the Aeolus substation near Medicine Bow, Wyoming, which includes a loop-in to the existing Shirley Basin 230-kV substation. The Aeolus – Shirley Basin 230-kV line section was energized in November 2020. This project was included in the 2021 IRP for acknowledgement with an in-service date of 2024. • Gateway West (Segment D2): This single-circuit 500-kV segment was placed in service November 2020. • Gateway West (Segment D3): A single-circuit 500-kV line running approximately 200 miles between the new Anticline substation which was placed in-service in November 2020 with the energization of Gateway West Segment D.2 and the Populus substation in southeast Idaho. Gateway West (Segment E) The Populus-to-Hemingway transmission project consists of two single-circuit 500-kV lines that run approximately 500 miles between the Populus substation in eastern Idaho to the Hemingway substation in western Idaho. Gateway South (Segment F) The 2021 PacifiCorp IRP preferred portfolio includes the Aeolus-to-Mona (Clover substation) transmission segment (Energy Gateway South or Segment F). To facilitate the delivery of new renewable energy resources to PacifiCorp customers across the West, the preferred portfolio includes significant transmission investment. Specifically, the 2021 IRP preferred portfolio includes the Energy Gateway South transmission line - a new 416-mile, high-voltage 500-kilovolt transmission line and associated infrastructure running from the new Aeolus substation near Medicine Bow, Wyoming, to the Clover substation near Mona, Utah. The 2021 preferred portfolio also includes the Energy Gateway West Subsegment D.1 project - a new 59 mile high-voltage 230-kilovolt transmission line from the Shirley Basin substation in southeastern Wyoming to the Windstar substation near Glenrock, Wyoming. Both transmission lines come online by the end of 2024. Timing of construction is driven by the phase-out schedule of federal production tax credits (PTCs), particularly the 2024 in-service requirements for 60 percent PTC eligibility, and potential risk associated with the termination of the BLM permit for non-use. In addition to supporting renewable resource additions in PacifiCorp’s generation portfolio, qualifying them for PTCs, the new transmission segment will increase transfer capability out of eastern Wyoming. PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 38 Boardman to Hemingway (Segment H) The Boardman to Hemingway project was included in the 2021 IRP request for acknowledgement and represents a significant improvement in the connection between PacifiCorp’s east and west control areas and will help deliver more diverse resources to serve its customers in Oregon, Washington, and California. Idaho Power leads the permitting efforts on this project and PacifiCorp continues to support the permitting efforts under the conditions of the Boardman to Hemingway Transmission Project Joint Permit Funding Agreement. The Bureau of Land Management’s Record of Decision was issued in November of 2017, followed by the U.S. Forest Service ROD issued on November 9, 2018. The Oregon Energy Facilities Siting Council’s final order on the Site Certificate is currently under process. In January 2020, the three parties signatory to the permitting agreement entered a non-binding term sheet that addresses the terms required to move the project to the next step of construction. In-Service Dates Table 3.2 summarizes the in-service dates for segments of the Energy Gateway transmission project. PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 39 Table 3.2 - Energy Gateway Segment In-Service Dates Segment & Name Description Approximate Mileage Status and Scheduled In-Service (A) Wallula-McNary 230 kV, single circuit 30 mi • Status: completed • Placed in-service: January 2019 (B) Populus-Terminal 345 kV, double circuit 135 mi • Status: completed • Placed in-service: November 2010 (C) Mona-Oquirrh 500 kV single circuit 345 kV double circuit 100 mi • Status: completed • Placed in-service: May 2013 Oquirrh-Terminal 345 kV double circuit 14 mi • Status: rights-of-way acquisition underway • Scheduled in-service: 2026 (D1) Windstar-Aeolus New 230 kV single circuit Re-built 230 kV single circuit 59 mi • Status: permitting underway • Scheduled in-service: 2024 (D2) Aeolus- Bridger/Anticline 500 kV single circuit 140 mi • Status: completed • Placed in-service: November 2020 (D3) Bridger/Anticline- Populus 500 kV single circuit 200 mi • Status: permitting underway • Scheduled in-service: 2027 earliest (E) Populus-Hemingway 500 kV single circuit 500 mi • Status: permitting underway • Scheduled in service: 2030 earliest (F) Aeolus-Mona 500 kV single circuit 416 mi • Status: permitting underway • Scheduled in-service: 2024 (G) Sigurd-Red Butte 345 kV single circuit 170 mi • Status: completed • Placed in-service: May 2015 (H) Boardman- Hemingway 500 kV single circuit 290 mi • Status: pursuing joint-development and/or firm capacity opportunities with project sponsors • Scheduled in-service: 2026 Regional Markets Increased renewable generation has contributed to the need for balancing sub-hourly demand and supply across a broader and more diverse market. For balancing purposes, PacifiCorp combined its resources with those of the CAISO through the creation of the EIM. The EIM became operational November 1, 2014, and as of March 2022 has 17 utilities participating. Tucson Electric Power and Bonneville Power Administration plan to join in 2022, while Avangrid, El Paso Electric and WAPA Desert Southwest plan to join in 2023.4 The multi-service area footprint brings greater resource and geographical diversity allowing for increased reliability and cost savings in balancing generation with demand using 15-minute interchange scheduling and five-minute dispatch. CAISO’s role is limited to the sub-hourly scheduling and dispatching of participating EIM generators. CAISO does not have any other grid operator responsibilities for PacifiCorp’s service areas. As part of other EIM participant entities, PacifiCorp is also participating in the CAISO stakeholder process to establish an Expanded Day-Ahead Market (EDAM). 4 https://www.westerneim.com/Pages/About/default.aspx PACIFICORP – 2021 IRP UPDATE CHAPTER 3 – THE PLANNING ENVIRONMENT 40 In December 2021, it was announced that the Western Resource Adequacy Program (WRAP), administered by the Western Power Pool (WPP), formerly known as the Northwest Power Pool, had entered the first stage of implementation. The WRAP consists of 26 participants, including PacifiCorp, who are working on the remaining program design questions and outstanding issues. Additionally, the WPP has partnered with the Southwest Power Pool (SPP) to provide program operation services, including facilitating the collection of participants data to perform modeling for the upcoming seasons.5 This program includes two components, a forward showing (FS) planning mechanism and an operational program (Ops Program) to help participants that are experiencing extreme events meet customer demand. The program is intended to be a starting point and does not solve every issue facing the region, but is an incremental step toward increased regional coordination, which could better position the region to continue to tackle these big issues. The WRAP will create a capacity RA program with a demonstration of deliverability. The region may also benefit from other forms of coordination, and while the structure and process associated with the program may serve as foundational building blocks to additional regional coordination, the WPP and the WRAP participants are only working to implement the capacity RA program at this time. The WRAP does not replace or supplant the resource planning processes used by states or provinces or the regulatory requirements of the Federal Energy Regulatory Commission (FERC), North America Electric Reliability Corporation (NERC) or Western Electricity Coordinating Council (WECC). The program is designed to be supplemental and complementary to those processes and requirements. Full implementation is expected to occur in 2024. 5 https://www.westernpowerpool.org/news/wrap-announces-full-participation-of-phase-3a PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 41 CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE Introduction This chapter presents an update to PacifiCorp’s load-and-resource balance. Updates to PacifiCorp’s long-term load forecasts (both energy and coincident peak load) for each state and the system as a whole are summarized in the Appendix. Updates to PacifiCorp’s load forecast, resources, and capacity position are presented and summarized in this chapter. System Coincident Peak Load Forecast The 2021 IRP Update relies on PacifiCorp’s May 2021 load forecast. Figure 4.1 compares PacifiCorp’s most recent load forecast to the forecast used for the 2021 IRP. Figure 4.2 compares PacifiCorp’s most recent coincident system peak load forecast to the forecast used for the 2021 IRP. Considering that PacifiCorp analyzes incremental energy efficiency and direct-load control programs as demand-side resource options in its IRP, both figures exclude incremental energy efficiency savings and direct-load control capacity included in the updated resource portfolio. The compounded average annual growth rate (CAGR) for system load is 1.46 percent over the period 2022 through 2031. The CAGR for system coincident peak is 1.04 percent over the period 2022 through 2031. Figure 4.1 - Forecasted Annual Load (GWh) PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 42 Figure 4.2 – Forecasted Annual Coincident Peak Load (MW) Wind and Solar Qualifying Facility Resource Updates Table 4.1 summarizes updates to the capacity from solar and geothermal power-purchase agreements (PPAs) with qualifying facilities (QFs) that have occurred since the September 1, 2021 IRP filing. Table 4.1 – New Power Purchase Agreements Updated Capacity Load-and-Resource Balance Load-and-Resource Balance Components Capacity and energy balances make use of the same load-and-resource components in their calculations. The main component categories consist of the following: resources, obligation, reserves, system position, and available front-office transactions (FOTs). The resource categories include resources by type—thermal, hydroelectric, renewable, QFs, purchases, and sales. Categories in the obligation section include load, private generation, existing demand response (includes interruptible contracts), and new energy efficiency from the updated Power Purchase Agreements Resource Type PPA or QF State Capacity (MW) COD Year Amor IX, LLC Soda Lake Geothermal QF Utah 20 2021 Castle Solar (Intermountain Health Care)Solar PPA Utah 20 2021 Solarize Rogue Solar QF Oregon 0.1296 2021 Wallowa County (Community Solar Project)Solar QF Oregon 0.36 2021 Sunnyside Solar Solar QF Washington 4.99 2023 PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 43 resource portfolio. Both resources and obligations can be represented as either a positive or negative value, which is consistent with how these elements are represented in portfolio modeling. A description of each of the resource categories is provided below. Existing Resources Capacity contribution is a measure of the ability for a resource to reliably meet demand. There are many possible ways to attribute capacity to specific resources and the portfolio modeling in the 2021 IRP Update doesn’t rely on a specific capacity contribution for each resource during portfolio development, in part because the reliability benefits of the next resource of a given type may not be the same as the reliability benefits from resources of that type already included in a portfolio. For the purpose of calculating capacity contribution, resources which are dispatchable for a limited duration (measured in hours) are distinguished from resources which are dispatchable for long durations (i.e., thermal) or whose output must be used as it is delivered, such as wind, solar and other non-dispatchable generators. Thermal This category includes all thermal plants that are wholly owned or partially owned by PacifiCorp. The capacity balance counts these plants at their expected availability (after derating for forced outages and maintenance), as discussed below. The energy balance also counts them at expected availability but includes all hours in the year. This includes the existing fleet of coal-fueled units, and seven natural-gas-fueled plants. Presently, these thermal resources account for roughly two thirds of the firm capacity available in the PacifiCorp system. Resources without duration limits For the purpose of reporting the capacity contribution resources without duration limits, including thermal, wind, solar, and other small generators, PacifiCorp first calculated the availability of each resource type during the top five percent of net load hours in each season (calculated as PacifiCorp’s load less the wind and solar generation in its portfolio).1 For the purpose of reporting load in the load and resource balance, the single highest load hour is used, and a planning reserve margin of 13% is added. Resources whose is output higher in the top five percent load hours than in the top give percent net load hours are allocated additional capacity value for their role in meeting peak requirements. It should be noted that while allocation of capacity among resources as described in this section is helpful for presenting a load and resource balance, the allocation to specific resources has no bearing on the reliability or economics of the preferred portfolio, which reflects the coordinated dispatch of all available resources in every hour of the year. The economics of resource additions are more closely aligned with marginal or “last-in” capacity contribution estimates, which are generally lower for resources whose output is positively correlated with other resources already present in the portfolio. For estimates of marginal capacity contribution values, please refer to PacifiCorp’s 2021 IRP, specifically Volume II, Appendix K (Capacity Contribution). 1 The Western Resource Adequacy Program (WRAP) has proposed a capacity contribution methodology that is based in part on the top five percent of net load hours. The WRAP proposal includes an effective load carrying capability (ELCC) analysis for a number of resource types. ELCC is very computationally intensive. For details, please refer to: https://www.westernpowerpool.org/private-media/documents/2021-12-21_RAPC_Minutes.pdf PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 44 Resources with duration limits Certain resource types have duration limits, such that while they could be called upon in any given hour, they cannot be called upon continuously for more than specified duration. Such resources include energy storage, such as batteries or pumped hydro, as well as demand response programs and contracts, which generally have limits on consecutive hours, hours per day, and/or hours per year. As a result, while these resources are available in every hour, they are limited in how often they can be called upon for energy. However, reliable system operation also requires resources that can be deployed at short notice to address unexpected events that occur relatively infrequently, such as a generator outage, increase in load, or decrease in wind and solar output. These operating reserve requirements are part of the load and resource balance, and because they do not require frequent energy dispatch, duration-limited resources are assumed to be able to provide operating reserves continuously. Once operating reserve needs are fulfilled in a given hour, energy limited resources would need to deploy energy to make additional contributions to serving load. This incremental energy is assumed to be deployed in the hours with the highest shortfalls, but is capped for each day at the lesser of the total duration of energy-limited resources (in MWh) and available excess generation capacity in hours where resources exceed the capacity requirement. This represents the need to charge batteries, for example, which represent the vast majority of the energy-limited resources through the study horizon. After summing the operating reserve and energy contributions of duration-limited resources, their capacity contribution as a class is calculated based on the net output in the top five percent net load hours, as described above. This total contribution is then allocated back to individual resources based on their duration capability, with shorter duration resources receiving a lower contribution. Sales Contracts for the sale of firm capacity and energy are treated the same as all other resources, except that they have a negative capacity value. The energy balance counts them by expected model dispatch. Obligation The obligation is the total electricity demand that PacifiCorp must serve, consisting of forecasted retail load, private generation, new energy efficiency from the preferred portfolio, existing demand response (including interruptible contracts). The following are descriptions of each of these components: Load and Private Generation The largest component of the obligation is retail load. In the 2021 IRP Update, the hourly retail load at a location is first reduced by hourly private generation at the same location. The system coincident peak is determined by summing the net loads for all locations (topology bubbles with loads) and then finding the highest hourly system load by year and season. Loads reported by east and west BAAs thus reflect loads at the time of PacifiCorp’s coincident system summer and winter peaks. The energy balance counts the average load on a monthly basis. For simplicity, load net of private generation is referred to as load in the following sections. Energy Efficiency (Class 2 DSM) An adjustment is made to load to remove the projected embedded energy efficiency as a reduction to load. Due to timing issues with the vintage of the load forecast, there was a level of 2020 energy efficiency that was not incorporated in the forecast for the 2021 IRP. The 2020 energy efficiency forecast of 73 MW was accounted for by adding an existing energy efficiency resource in the load- and-resource balance; this adjustment was not required for the 2021 IRP Update because the 2020 PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 45 projected embedded energy efficiency is included in the load forecast. The energy efficiency line includes the selected energy efficiency from the 2021 IRP Update preferred portfolio. Demand Response (Class 1 DSM) Existing demand response program capacity is categorized as a reduction to peak load. Also included in the demand response category are existing interruptible contracts. PacifiCorp has had interruptible contracts for approximately 177 MW of load interruption capability for many years. These contracts are a key aspect of the retail service provided to the associated customers, and absent these contracts their demand would likely be different from that included in the load forecast. To maintain an alignment with the load forecast, these contracts are assumed to continue indefinitely under their current structure. Planning Reserve Margin Planning reserve margin (PRM) represents an incremental capacity requirement, applied as an increase to the obligation to ensure that there will be sufficient capacity available on the system to manage uncertain events (i.e., weather, outages) and known requirements (i.e., operating reserves). System Position The system position is the resource surplus or deficit after subtracting obligation plus required reserves from total resources. While similar, the position calculation is slightly different for the capacity and energy views of the load and resource balance. Thus, the position calculation for each of the views will be presented in their respective sections. Capacity Balance Determination and Results Methodology The capacity balance is developed by first determining the system coincident peak load for each of the first ten years of the planning horizon. Then the annual firm-capacity availability of the existing resources is determined for each of these annual system summer and winter peak periods, as applicable, and summed as follows: Existing Resources = Coal + Gas + Hydro + Renewables + Contracts – Firm Sales The peak load, private generation, existing demand response, and new energy efficiency from the preferred portfolio are netted together for each of the annual system summer and winter peaks, as applicable, to compute the annual peak obligation: Obligation = Load – Private Generation – Demand Response – New Energy Efficiency The amount of reserves to be added to the obligation is then calculated. This is accomplished by the net system obligation calculated above multiplied by the 13 percent PRM adopted for the 2021 IRP Update. The formula for this calculation is: Planning Reserves = Obligation x PRM Finally, the annual system position is derived by adding the computed reserves to the obligation, and then subtracting this amount from existing resources, as shown in the following formula: System Position = (Existing Resources) – (Obligation + Planning Reserves) PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 46 Capacity Balance Results Table 4.2 and Table 4.3 show the annual capacity balances and component line items for the summer peak and winter peak, respectively, using a target PRM of 13 percent to calculate the planning reserve amount. Balances for PacifiCorp’s system as well as the east and west control areas are shown. While east and west control area balances are broken out separately, the PacifiCorp system is planned for and dispatched on a system basis. PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 47 Table 4.2 – Summer Peak - System Capacity Load and Resource Balance without Resource Additions, 2021 IRP Update (2022-2031) (Megawatts)2 2 The DSM line includes selected Class 2 DSM from the 2021 IRP Update resource portfolio. East 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Coal 3,536 3,474 3,505 3,513 3,076 3,067 2,343 2,245 2,199 2,198 Gas 1,942 1,964 1,922 1,947 1,968 1,933 1,950 1,942 1,753 1,748 Hydroelectric 108 108 88 88 88 88 88 87 87 87 Solar 377 521 197 424 341 320 352 316 291 161 Wind 337 405 262 452 445 424 422 491 490 395 Geothermal 49 50 51 50 50 52 51 50 51 50 Contracts 185 182 122 35 31 30 31 24 22 17 Sales and Ancillary Services (267)(267)(243)(243)(239)(236)(235)(234)(233)(233) East Existing Resources 6,268 6,438 5,905 6,265 5,760 5,678 5,003 4,922 4,660 4,423 Load 7,274 7,421 7,543 7,685 7,654 7,732 7,843 7,944 8,052 8,162 Private Generation (57)(66)(69)(71)(75)(81)(90)(103)(120)(144) Existing - Demand Response (594)(585)(594)(593)(520)(496)(460)(255)(220)(196) New Energy Efficiency (134)(210)(242)(379)(500)(810)(801)(1,051)(1,026)(1,252) East Total obligation 6,489 6,561 6,638 6,642 6,559 6,345 6,493 6,535 6,686 6,570 Planning Reserve Margin (13%)844 853 863 863 853 825 844 850 869 854 East Obligation + Reserves 7,332 7,413 7,501 7,505 7,412 7,170 7,337 7,385 7,555 7,424 East Position (1,065)(976)(1,596)(1,240)(1,653)(1,492)(2,334)(2,463)(2,895)(3,001) Available Front Office Transactions 0 0 0 0 0 0 0 0 0 0 West Coal 1,500 1,495 1,487 1,488 1,354 1,352 1,348 1,370 1,356 1,356 Gas 663 673 660 664 663 664 664 664 675 665 Hydroelectric 955 796 790 799 795 798 798 794 792 797 Solar 7 27 10 20 16 15 16 14 13 6 Wind 89 83 50 87 82 89 77 84 91 85 Geothermal 0 0 0 0 0 0 0 0 0 0 Contracts 171 168 131 146 132 97 102 72 63 47 Sales and Ancillary Services (209)(207)(182)(182)(179)(177)(177)(168)(168)(169) West Existing Resources 3,177 3,034 2,945 3,022 2,863 2,838 2,828 2,831 2,822 2,787 Load 3,372 3,402 3,434 3,471 3,501 3,534 3,569 3,604 3,640 3,679 Private Generation (28)(40)(45)(49)(54)(60)(67)(75)(85)(106) Existing - Demand Response 0 0 0 0 0 0 0 0 0 0 New Energy Efficiency (73)(120)(147)(192)(242)(157)(354)(264)(442)(321) West Total obligation 3,271 3,242 3,243 3,229 3,205 3,318 3,148 3,264 3,113 3,251 Planning Reserve Margin (13%)425 421 422 420 417 431 409 424 405 423 West Obligation + Reserves 3,696 3,664 3,664 3,649 3,622 3,749 3,557 3,688 3,518 3,674 West Position (520)(629)(719)(627)(758)(911)(729)(857)(695)(887) Available Front Office Transactions 500 500 500 500 500 500 500 500 500 500 System Total Resources 9,445 9,472 8,850 9,287 8,623 8,516 7,831 7,753 7,482 7,210 Obligation 9,760 9,803 9,880 9,871 9,764 9,663 9,641 9,799 9,799 9,821 Planning Reserves (13%)1,269 1,274 1,284 1,283 1,269 1,256 1,253 1,274 1,274 1,277 Obligation + Reserves 11,029 11,077 11,165 11,155 11,034 10,919 10,894 11,073 11,073 11,098 System Position (1,584)(1,605)(2,315)(1,867)(2,411)(2,403)(3,063)(3,320)(3,591)(3,888) Available Front Office Transactions 500 500 500 500 500 500 500 500 500 500 Uncommitted FOTs to meet remaining Need 1,584 1,605 2,315 1,867 500 500 500 500 500 500 Net Surplus/(Deficit)0 0 0 0 (1,911)(1,903)(2,563)(2,820)(3,091)(3,388) PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 48 Table 4.2 (cont.) – Summer Peak - System Capacity Load and Resource Balance without Resource Additions, 2021IRP Update (2032-2040) (Megawatts)3 3 The DSM line includes selected Class 2 DSM from the 2021 IRP Update resource portfolio. East 2032 2033 2034 2035 2036 2037 2038 2039 2040 Coal 2,212 2,219 2,207 2,219 2,218 1,359 1,362 1,357 1,100 Gas 1,743 1,412 1,401 1,397 1,398 1,403 1,403 1,399 1,410 Hydroelectric 86 87 87 86 87 86 86 87 87 Solar 30 136 124 132 125 137 144 142 83 Wind 252 355 359 353 333 475 502 480 457 Geothermal 51 50 51 51 52 50 20 20 20 Contracts 10 15 14 12 9 8 0 0 0 Sales and Ancillary Services (226)(230)(229)(228)(228)(233)(233)(234)(227) East Existing Resources 4,159 4,043 4,013 4,022 3,993 3,287 3,285 3,251 2,931 Load 8,266 8,370 8,473 8,444 8,585 8,679 8,793 8,655 8,759 Private Generation (173)(203)(236)(150)(173)(196)(221)(116)(128) Existing - Demand Response (176)(163)(161)(161)(160)(148)(144)(148)(142) New Energy Efficiency (1,489)(1,442)(1,522)(1,590)(1,607)(1,702)(1,753)(1,702)(1,844) East Total obligation 6,428 6,563 6,555 6,543 6,644 6,633 6,674 6,689 6,644 Planning Reserve Margin (13%)836 853 852 851 864 862 868 870 864 East Obligation + Reserves 7,264 7,416 7,407 7,394 7,508 7,495 7,542 7,559 7,508 East Position (3,105)(3,372)(3,394)(3,372)(3,515)(4,208)(4,257)(4,308)(4,577) Available Front Office Transactions 0 0 0 0 0 0 0 0 0 West Coal 1,356 1,358 1,355 1,354 1,353 1,351 0 0 0 Gas 667 665 665 663 677 449 448 446 446 Hydroelectric 793 794 796 792 793 795 795 798 798 Solar 1 5 4 5 5 9 10 10 7 Wind 56 88 77 73 83 97 114 117 84 Geothermal 0 0 0 0 0 0 0 0 0 Contracts 24 35 31 30 32 23 19 10 10 Sales and Ancillary Services (162)(169)(167)(160)(155)(161)(157)(156)(144) West Existing Resources 2,735 2,776 2,760 2,757 2,787 2,563 1,229 1,224 1,200 Load 3,711 3,747 3,785 3,775 3,809 3,854 3,892 3,861 3,896 Private Generation (147)(193)(247)(217)(254)(296)(341)(190)(221) Existing - Demand Response 0 0 0 0 0 0 0 0 0 New Energy Efficiency (432)(382)(412)(450)(561)(327)(344)(455)(685) West Total obligation 3,133 3,172 3,126 3,108 2,994 3,231 3,207 3,216 2,990 Planning Reserve Margin (13%)407 412 406 404 389 420 417 418 389 East Obligation + Reserves (24)30 (5)(46)(172)93 73 (37)(296) East Position 2,760 2,746 2,766 2,803 2,959 2,470 1,156 1,262 1,496 Available Front Office Transactions 500 500 500 500 500 500 500 500 500 System Total Resources 6,894 6,819 6,773 6,779 6,780 5,850 4,514 4,475 4,131 Obligation 9,561 9,735 9,681 9,651 9,638 9,863 9,882 9,905 9,634 Planning Reserves (13%)1,243 1,265 1,259 1,255 1,253 1,282 1,285 1,288 1,252 Obligation + Reserves 10,804 11,000 10,940 10,906 10,891 11,146 11,166 11,192 10,886 System Position (3,910)(4,181)(4,166)(4,127)(4,111)(5,295)(6,652)(6,717)(6,755) Available Front Office Transactions 500 500 500 500 500 500 500 500 500 Uncommitted FOTs to meet remaining Need 500 500 500 500 500 500 500 500 500 Net Surplus/(Deficit)(3,410)(3,681)(3,666)(3,627)(3,611)(4,795)(6,152)(6,217)(6,255) PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 49 Table 4.3 – Winter Peak – System Capacity Load and Resource Balance without Resource Additions, 2021 IRP Update (2022-2031) (Megawatts) 4 4 The DSM line includes selected Class 2 DSM from the 2021 IRP Update resource portfolio. East 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Coal 3,443 3,491 3,470 3,477 2,931 2,941 2,249 2,224 2,148 2,090 Gas 1,938 2,045 2,043 1,995 1,913 1,969 2,042 2,012 1,817 1,700 Hydroelectric 80 80 70 70 68 67 70 69 69 67 Solar 48 72 40 22 14 16 16 24 39 11 Wind 268 383 250 278 280 263 256 355 418 306 Geothermal 52 52 52 51 51 46 52 52 52 50 Contracts 164 137 66 16 15 15 15 9 9 8 Sales and Ancillary Services (212)(215)(189)(192)(190)(189)(191)(193)(194)(194) East Existing Resources 5,781 6,045 5,801 5,716 5,081 5,127 4,509 4,552 4,360 4,038 Load 5,691 5,868 5,936 6,050 5,977 6,033 6,138 6,220 6,297 6,374 Private Generation (1)(2)(2)(3)(4)(5)(6)(7)(8)(9) Existing - Demand Response (322)(309)(335)(408)(330)(324)(336)(229)(204)(180) New Energy Efficiency (108)(148)(198)(221)(275)(725)(400)(842)(880)(520) East Total obligation 5,260 5,410 5,401 5,418 5,368 4,980 5,396 5,142 5,205 5,665 Planning Reserve Margin (13%)684 703 702 704 698 647 701 668 677 736 East Obligation + Reserves 5,944 6,114 6,103 6,122 6,066 5,627 6,097 5,810 5,882 6,401 East Position (163)(69)(302)(406)(984)(500)(1,588)(1,258)(1,522)(2,363) Available Front Office Transactions 300 300 300 300 300 300 300 300 300 300 West Coal 1,488 1,488 1,319 1,468 1,321 1,314 1,338 1,335 1,360 1,313 Gas 718 718 711 713 697 693 717 715 630 695 Hydroelectric 1,038 858 865 861 847 843 869 866 869 843 Solar 0 1 1 1 0 0 0 1 1 0 Wind 39 52 33 50 39 33 34 44 52 50 Geothermal 0 0 0 0 0 0 0 0 0 0 Contracts 78 73 70 68 58 31 33 21 17 15 Sales and Ancillary Services (192)(174)(149)(146)(145)(142)(142)(147)(147)(146) West Existing Resources 3,168 3,016 2,850 3,014 2,818 2,772 2,849 2,834 2,782 2,771 Load 3,330 3,373 3,408 3,446 3,487 3,534 3,580 3,628 3,673 3,710 Private Generation (0)(1)(1)(1)(1)(2)(2)(3)(3)(4) Existing - Demand Response 0 0 0 0 0 0 0 0 0 0 New Energy Efficiency (76)(110)(165)(160)(191)150 (271)172 114 (339) West Total obligation 3,253 3,262 3,243 3,285 3,295 3,682 3,308 3,798 3,784 3,368 Planning Reserve Margin (13%)423 424 422 427 428 479 430 494 492 438 West Obligation + Reserves 3,676 3,686 3,664 3,712 3,723 4,161 3,738 4,291 4,276 3,806 West Position (508)(670)(815)(698)(905)(1,389)(889)(1,458)(1,494)(1,035) Available Front Office Transactions 700 700 700 700 700 700 700 700 700 700 System Total Resources 8,950 9,061 8,651 8,730 7,899 7,900 7,358 7,386 7,142 6,809 Obligation 8,513 8,672 8,644 8,703 8,663 8,662 8,703 8,939 8,989 9,033 Planning Reserves (13%)1,107 1,127 1,124 1,131 1,126 1,126 1,131 1,162 1,169 1,174 Obligation + Reserves 9,620 9,800 9,767 9,834 9,789 9,788 9,835 10,101 10,157 10,207 System Position (670)(739)(1,117)(1,104)(1,890)(1,889)(2,477)(2,716)(3,016)(3,398) Available Front Office Transactions 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 Uncommitted FOTs to meet remaining Need 670 739 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 Net Surplus/(Deficit)0 0 (117)(104)(890)(889)(1,477)(1,716)(2,016)(2,398) PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 50 Table 4.3 (cont.) – Winter Peak – System Capacity Load and Resource Balance without Resource Additions, 2021IRP Update (2032-2040) (Megawatts)5 5 The DSM line includes selected Class 2 DSM from the 2021 IRP Update resource portfolio. East 2032 2033 2034 2035 2036 2037 2038 2039 2040 Coal 2,051 2,203 2,178 2,212 2,188 1,353 1,332 1,338 1,178 Gas 1,736 1,444 1,473 1,485 1,353 1,482 1,479 1,487 1,466 Hydroelectric 66 69 69 69 69 70 69 69 69 Solar 7 6 9 23 33 31 37 36 24 Wind 220 271 274 389 454 578 701 744 561 Geothermal 49 52 49 52 52 52 20 20 20 Contracts 7 7 7 6 6 3 0 0 7 Sales and Ancillary Services (194)(196)(198)(203)(205)(202)(203)(205)(208) East Existing Resources 3,942 3,857 3,861 4,034 3,949 3,367 3,436 3,490 3,116 Load 6,459 6,542 6,645 6,724 6,801 6,890 6,992 7,083 7,190 Private Generation (10)(12)(13)(14)(16)(18)(19)(21)(23) Existing - Demand Response (166)(155)(155)(155)(162)(141)(137)(139)(135) New Energy Efficiency (905)(920)(1,185)(1,051)(1,057)(343)(1,143)(443)(1,458) East Total obligation 5,378 5,456 5,291 5,504 5,566 6,389 5,691 6,481 5,575 Planning Reserve Margin (13%)699 709 688 715 724 831 740 842 725 East Obligation + Reserves 6,077 6,165 5,979 6,219 6,289 7,219 6,431 7,323 6,299 East Position (2,135)(2,308)(2,118)(2,185)(2,340)(3,852)(2,996)(3,833)(3,183) Available Front Office Transactions 300 300 300 300 300 300 300 300 300 West Coal 1,285 1,323 1,361 1,362 1,360 1,360 0 0 27 Gas 680 710 718 718 683 490 489 490 495 Hydroelectric 828 865 874 875 874 877 878 880 879 Solar 0 0 0 0 0 1 1 1 0 Wind 31 41 46 52 60 79 83 82 68 Geothermal 0 0 0 0 0 0 0 0 0 Contracts 14 13 13 14 13 13 12 11 14 Sales and Ancillary Services (144)(141)(144)(145)(146)(143)(142)(142)(148) West Existing Resources 2,695 2,812 2,867 2,877 2,846 2,675 1,322 1,321 1,336 Load 3,756 3,805 3,854 3,902 3,946 3,994 4,048 4,102 4,156 Private Generation (4)(5)(6)(7)(8)(9)(11)(12)(13) Existing - Demand Response 0 0 0 0 0 0 0 0 0 New Energy Efficiency (80)(134)73 89 40 (934)(237)(1,013)(3) West Total obligation 3,672 3,666 3,921 3,985 3,978 3,051 3,801 3,076 4,139 Planning Reserve Margin (13%)477 477 510 518 517 397 494 400 538 East Obligation + Reserves 398 343 582 607 558 (537)257 (613)535 East Position 2,298 2,470 2,285 2,270 2,289 3,212 1,065 1,935 801 Available Front Office Transactions 700 700 700 700 700 700 700 700 700 System Total Resources 6,637 6,669 6,728 6,911 6,796 6,042 4,757 4,811 4,452 Obligation 9,050 9,121 9,212 9,488 9,544 9,440 9,492 9,557 9,714 Planning Reserves (13%)1,176 1,186 1,198 1,233 1,241 1,227 1,234 1,242 1,263 Obligation + Reserves 10,226 10,307 10,409 10,722 10,784 10,667 10,726 10,799 10,976 System Position (3,589)(3,638)(3,681)(3,810)(3,989)(4,625)(5,968)(5,988)(6,524) Available Front Office Transactions 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 Uncommitted FOTs to meet remaining Need 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 Net Surplus/(Deficit)(2,589)(2,638)(2,681)(2,810)(2,989)(3,625)(4,968)(4,988)(5,524) PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 51 Figure 4.3 and Figure 4.4 are graphic representations of the above tables for the 2021 IRP Update annual capacity position for the summer system, winter system respectively. Also shown in the system capacity position graphs are the capacity contribution from uncommitted FOTs, which as discussed above, are provided for informational purposes. Figure 4.3 – Summer System Capacity Position Trend 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Me g a w a t t s West Existing Resources East Existing Resources Uncommitted FOTs to meet remaining Need Obligation + Reserves Obligation East Existing Resources West Existing Resources 13% Reserves PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 52 Figure 4.4 – Winter System Capacity Position Trend Energy Balance Determination Methodology The energy balance shows the monthly surplus or (deficit) of energy. Please refer to the section on load and resource balance components for details on how energy for each component is counted. Existing Resources = Thermal + Hydro + Renewable + Firm Purchases + QF – Sales The average obligation is computed using the following formula: Obligation = Load + Firm Sales The energy position by month is then computed as follows: Energy Position = Existing Resources – Obligation – Operating Reserve Requirements Operating Reserve Requirements include spinning and non-spinning reserves, but not regulation reserves, which are expected to be close to energy neutral over time. As duration-limited resources such as batteries become a larger portion of the Company’s portfolio, less of the potential output of thermal resources is likely to be needed to meet Operating Reserve requirements. In addition, 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Me g a w a t t s West Existing Resources East Existing Resources Uncommitted FOTs to meet remaining Need Obligation + Reserves Obligation East Existing Resources West Existing Resources 13% Reserves PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 53 energy storage resources represent a net load, due to their roundtrip efficiency. For the 2021 IRP Update, storage resources are not included in the energy balance. Energy Balance Results The capacity position shows how existing resources and loads, accounting for coal unit retirements and incremental energy efficiency savings from the preferred portfolio, balance during the coincident peak summer and winter. Outside of these peak periods, PacifiCorp economically dispatches its resources to meet changing load conditions taking into consideration prevailing market conditions. In those periods when variable costs of the system resources are less than the prevailing market price for power, PacifiCorp can dispatch resources that in aggregate exceed then-current load obligations facilitating off system sales that reduce customer costs. Conversely, at times when system resource costs fall below prevailing market prices, system balancing market purchases can be used to meet then-current system load obligations to reduce customer costs. The economic dispatch of system resources is critical to how PacifiCorp manages net power costs. Figure 4.5 provides a snapshot of how existing system resources could be used to meet forecasted load across on-peak and off-peak periods given the assumptions about resource availability and wholesale power and natural gas prices. At times, resources are economically dispatched above load levels facilitating net system balancing sales. At other times, economic conditions result in net system balancing purchases, which occur more often during on-peak periods. Figure 4.5 also shows how much energy is available from existing resources at any given point in time. Those periods where all available resource energy falls below forecasted loads are highlighted in red and indicate short energy positions without the addition of incremental resources to the portfolio. Figure 4.5 – System Average Monthly Energy Positions 0 2,000 4,000 6,000 8,000 10,000 12,000 Ja n - 2 1 Ap r - 2 1 Ju l - 2 1 Oc t - 2 1 Ja n - 2 2 Ap r - 2 2 Ju l - 2 2 Oc t - 2 2 Ja n - 2 3 Ap r - 2 3 Ju l - 2 3 Oc t - 2 3 Ja n - 2 4 Ap r - 2 4 Ju l - 2 4 Oc t - 2 4 Ja n - 2 5 Ap r - 2 5 Ju l - 2 5 Oc t - 2 5 Ja n - 2 6 Ap r - 2 6 Ju l - 2 6 Oc t - 2 6 Ja n - 2 7 Ap r - 2 7 Ju l - 2 7 Oc t - 2 7 Ja n - 2 8 Ap r - 2 8 Ju l - 2 8 Oc t - 2 8 Ja n - 2 9 Ap r - 2 9 Ju l - 2 9 Oc t - 2 9 Ja n - 3 0 Ap r - 3 0 Ju l - 3 0 Oc t - 3 0 Av e r a g e E n e r g y A v a i l a b l e ( M W ) Monthly Energy Balance Energy at or Below Load Net Balancing Purchase Net Balancing Sale Energy Shortfall Energy Available Obligation PACIFICORP – 2021 IRP UPDATE CHAPTER 4 – LOAD-AND-RESOURCE BALANCE UPDATE 54 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 55 CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE General Assumptions Consistent with the 2021 IRP, the study period for the 2021 IRP Update is 2021-2040, with a focus on the 2022-2027 planning horizon. PacifiCorp has updated certain general assumptions in the 2021 IRP Update from the 2021 IRP as discussed below. Inflation Rates The 2021 IRP Update model simulations and cost data reflect PacifiCorp’s corporate inflation rate schedule unless otherwise noted. A single annual escalation rate value of 2.155 percent is assumed, consistent with the 2021 IRP. The annual escalation rate reflects the average of annual inflation rate projections for the period 2021 through 2040, using PacifiCorp’s September 2020 inflation curve. PacifiCorp’s inflation curve is a straight average of forecasts for Gross Domestic Product inflator and Consumer Price Index. Discount Factor The discount rate used in present-value calculations is based on PacifiCorp’s after-tax weighted average cost of capital (WACC). The value used for the 2021 IRP Update is 6.88 percent, consistent with the 2021 IRP. The use of the after-tax WACC complies with the Public Utility Commission of Oregon’s IRP guideline 1a, which requires that the after-tax WACC be used to discount all future resource costs.1 Present-value revenue requirement values reported in the 2021 IRP Update are reported in 2021 dollars. Front Office Transactions (FOTs) FOT modeling assumptions in the 2021 IRP Update are consistent with the FOT modeling assumptions from the 2021 IRP. Table 5.1 reports the available FOT modeling assumptions for reference; identifying the market hub, product type, annual capacity limit, and availability associated with the product. PacifiCorp develops its FOT planning limits based upon its active participation in wholesale power markets, its view of physical delivery constraints, market liquidity and depth, and with consideration of regional resource supply. 1 Public Utility Commission of Oregon, Order No. 07-002, Docket No. UM 1056, January 8, 2007. PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 56 Table 5.1 - Maximum Available Front Office Transaction Quantity by Market Hub Market Hub/Proxy FOT Product Type Available over Study Period Megawatt Limit and Availability (MW) Summer (July) Winter (December) Mid-Columbia (Mid-C) 350 350 Flat Annual or Heavy Load Hour Heavy Load Hour 150 0 California Oregon Border (COB) Flat Annual or Heavy Load Hour 0 250 Nevada Oregon Border (NOB) 0 100 Heavy Load Hour Mona 0 300 Heavy Load Hour Stochastic Parameters Stochastic parameters assumed in the 2021 IRP Update are consistent with those applied in the 2021 IRP. PacifiCorp provided a detailed description of its stochastic parameters and their development in Volume II, Appendix H of the 2021 IRP. Flexible Reserve Study PacifiCorp applied its Flexible Reserve Study methodology from the 2021 IRP in its 2021 IRP Update. PacifiCorp provided a detailed description of its Flexible Reserve Study in Volume II, Appendix F of the 2021 IRP. Natural Gas and Power Market Price Updates Portfolio modeling for the 2021 IRP Update was prepared using three market price forecasts that have not changed from the 2021 IRP, in part due to the short period of time that has transpired since the September 1, 2021, filing. PacifiCorp is also transitioning to a new third-party vendor for its price curves and a full set of updated prices are not yet available. Figure 5.1 summarizes the three wholesale electricity price forecasts and three natural gas price forecasts used in the base and scenario cases for the 2021 IRP Update. As shown, low and medium power and gas prices are higher in the near term. All three power price scenarios trend higher beginning in 2024, but generally escalate at different increasing rates. PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 57 Figure 5.1 – Nominal Wholesale Electricity and Natural Gas Price Scenarios PacifiCorp’s March 31, 2021, official forward price curve (OFPC) is used to represent medium natural gas price assumptions with no CO2 prices for the “MN” price-policy scenario. OFPCs are produced for both natural gas and power prices by point of delivery. For both gas and electricity, starting with the prompt month, the front 36 months of the OFPC reflects market forwards at the close of a given trading day.2 As such, these 36 months are market forwards as of March 2021. The blending period (months 37 through 48) is calculated by averaging the month-on-month market forward from the prior year with the month-on-month fundamentals-based price from the subsequent year. The fundamentals portion of the natural gas and electricity OFPCs reflect expert third-party price forecasts. PacifiCorp updates its natural gas price forecasts each quarter for the OFPC and, as a corollary, the electricity OFPC is also updated. Supply and demand for electricity and natural gas are related, and changes in some assumptions that directly impact one can result in prices changes that indirectly impact the other. Other assumptions may impact both markets directly. For example, greenhouse gas prices can impact demand for natural gas for electricity generation, but they can also impact demand for natural gas for other purposes. The combined impact of the change in demand will in turn change natural gas prices, which can in turn further impact demand in the electric sector. By using a single vendor for both electric and gas price forecasting, more of the interaction between these markets as a result of other assumptions can be captured in the price forecast. PacifiCorp previously prepared the fundamentals portion of the electricity forecast in house and could not capture these interactions, which are increasing in importance with the rising penetration of renewable resources and evolving policies that impact CO2-emitting generation resources. To improve its forecasts within this changing landscape, PacifiCorp is transitioning to third-party forecasts of both gas and electricity prices. PacifiCorp executed a two-year contract in February 2022 that will provide quarterly OFPC updates for both gas and electricity, starting with the March 2022 OFPC, as well as the price-policy sensitivities used in IRP modeling going forward. 2 The March 2021 OFPC prompt month is May 2021; April 2021 would be traded as “balance of month” when the OFPC is released. $0 $1 $2 $3 $4 $5 $6 $7 $8 $9 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 $/ M M B t u Natural Gas Prices Henry Hub Medium Low High $0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 $/ M W h Wholesale Electricity Prices Average of Palo Verde and Mid-C (Flat) Mgas_MCO2 Hgas_HCO2 Lgas_0CO2 PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 58 Carbon Dioxide Emission Policy Consistent with the 2021 IRP, PacifiCorp used three different CO2 price scenarios in the 2021 IRP Update—zero, medium, high. The medium and high scenario are derived from expert third-party multi-client “off-the-shelf” subscription services. Both scenarios apply a CO2 price as a tax beginning 2025. A fourth CO2 price scenario, social cost of greenhouse gas (SC-GHG), was used in the 2021 IRP but has not been incorporated into the 2021 IRP Update. This is primarily because the 2021 IRP Update is not an update to CETA or the CEIP, and updates such as the CETA Progress Report are addressed through other specified requirements. For informational purposes, the SC-GHG price curve is nonetheless discussed here for comparison to the medium and high price curves. In PacifiCorp’s 2021 IRP and future IRPs, the SC-GHG price curve will be incorporated in compliance with RCW 19.280.030. The social cost of greenhouse gases is applied such that the price for the SC-GHG is reflected in market prices and dispatch costs for the purposes of developing each portfolio (i.e., incorporated into capacity expansion optimization modeling). Aligned with Washington staff suggested treatment, system operations in a full IRP also include the SC-GHG once the portfolios are determined, presenting the risk that this operational assumption will not be aligned with actual market forces (i.e., market transactions at the Mid- Columbia market do not reflect the social cost of greenhouse gases and PacifiCorp does not directly incur emission costs at the price assumed for the social cost of greenhouse gases). For the purposes of the 2021 IRP Update, the zero and high CO2 price assumptions serve as bookends for future market environment analysis. As described further in Chapter 6, CETA-driven resource assumptions that consider the SC-GHG CO2 price are incorporated into the 2021 IRP Update preferred portfolio so that updated CETA interim targets could be evaluated. PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 59 Figure 5.2 – Medium, High and Social Cost of Greenhouse Gas CO2 Prices Supply-Side Resources Proxy resource costs and operating characteristics are generally unchanged from assumptions used in the 2021 IRP. The supply-side table in the 2021 IRP showed proxy costs for combined solar and storage resources based on storage capacity equal to 50% of solar nameplate, with four-hour duration. As part of the Reliability Assessment in the 2021 IRP, the storage capacity was set at 100% of solar nameplate, with four-hour duration. As part of the development of the 2021 IRP preferred portfolio, costs and operating characteristics for a hybrid wind-solar-storage resource were developed. Since these resource configurations were not included in the supply-side table for the 2021 IRP, they have been provided in the tables below. All costs remain in real levelized 2020 dollars. Cost (de)escalation curves are applied in the portfolio modeling process to the solar, wind, and/or storage components of a resource. The cost (de)escalation curves are unchanged from the 2021 IRP. $0$10$20$30$40$50$60$70$80$90$100$110$120$130$140$150$160 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Medium High Societal Cost PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 60 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 61 Table 5.2 - 2021 IRP Update Supply Side Resources Information Presented is Illustrative Table 5.3 – 2021 IRP Update Supply Side Resources Information Presented is Illustrative Elevation (AFSL) Net Capacity (MW) Commercial Operation Year Design Life (yrs) Base Capital ($/KW) Demolition Cost ($/kW) Var O&M ($/MWh) Fixed O&M ($/KW-yr) Average Full Load Heat Rate (HHV Btu/KWh)/ Efficiency EFOR (%)POR (%) Water Consumed (Gal/MWh) SO2 (lbs/MMBtu) NOx (lbs/MMBtu) Hg (lbs/TBTu) CO2 (lbs/MMBtu) Idah Falls, ID, 200 MW, Solar, CF: 26.1% + BESS: 100% pwr, 4 hours 4,700 200 2023 25 $ 3,020 $ 475 $ - $ 41.80 85%(a)(a)n/a n/a n/a n/a n/a Lakeview, OR, 200 MW, Solar, CF: 27.6% + BESS: 100% pwr, 4 hours 4,800 200 2023 25 $ 2,977 $ 475 $ - $ 41.80 85%(a)(a)n/a n/a n/a n/a n/a Milford, UT, 200 MW, Solar, CF: 30.2% + BESS: 100% pwr, 4 hours 5,000 200 2023 25 $ 2,907 $ 475 $ - $ 43.30 85%(a)(a)n/a n/a n/a n/a n/a Rock Springs, WY, 100 MW, Solar, CF: 27.9% + BESS: 100% pwr, 4 hours 6,400 100 2023 25 $ 3,201 $ 475 $ - $ 45.20 85%(a)(a)n/a n/a n/a n/a n/a Rock Springs, WY, 200 MW, Solar, CF: 27.9% + BESS: 100% pwr, 4 hours 6,400 200 2023 25 $ 2,960 $ 475 $ - $ 43.30 85%(a)(a)n/a n/a n/a n/a n/a Yakima, WA, 100 MW, Solar, CF: 24.2% + BESS: 100% pwr, 4 hours 1,000 100 2023 25 $ 3,323 $ 475 $ - $ 45.20 85%(a)(a)n/a n/a n/a n/a n/a Yakima, WA, 200 MW, Solar, CF: 24.2% + BESS: 100% pwr, 4 hours 1,000 200 2023 25 $ 3,077 $ 475 $ - $ 43.30 85%(a)(a)n/a n/a n/a n/a n/a Idah Falls, ID, 200 MW, Solar & Wind, CF: 26.1% + BESS: 100% pwr, 4 hours + 200 MW Wind 4,700 200 2023 25 $ 3,395 $ 488 $ - $ 82.95 85%(a)(a)n/a n/a n/a n/a n/a Lakeview, OR, 200 MW, Solar & Wind,CF: 27.6% + BESS: 100% pwr, 4 hours + 200 MW Wind 4,800 200 2023 25 $ 3,424 $ 488 $ - $ 82.95 85%(a)(a)n/a n/a n/a n/a n/a Milford, UT, 200 MW, Solar & Wind,CF: 30.2% + BESS: 100% pwr, 4 hours + 200 MW Wind 5,000 200 2023 25 $ 3,364 $ 488 $ - $ 81.45 85%(a)(a)n/a n/a n/a n/a n/a Rock Springs, WY, 200 MW, Solar & Wind,CF: 27.9% + BESS: 100% pwr, 4 hours + 200 MW Wind 6,400 200 2023 25 $ 3,364 $ 488 $ - $ 81.45 85%(a)(a)n/a n/a n/a n/a n/a Yakima, WA, 200 MW, Solar & Wind, CF: 24.2% + BESS: 100% pwr, 4 hours + 200 MW Wind 1,000 200 2023 25 $ 3,424 $ 488 $ - $ 81.45 85%(a)(a)n/a n/a n/a n/a n/a Resource Characteristics Costs Operating Characteristics EnvironmentalSupply Side Resource Options Mid-Calendar Year 2020 Dollars ($) Resource Description Supply Side Resource Options Mid-Calendar Year 2020 Dollars ($) Resource Description Total Capital Cost Demolition Cost Payment Factor Annual Payment ($/kW-Yr) O&M Capitalized Premium O&M Capitalized Gas Transportation Total Idah Falls, ID, 200 MW, Solar, CF: 26.1% + BESS: 100% pwr, 4 hours Yes 4,700 $3,020 $475 6.839%$239.06 $41.80 1.379%$0.58 $0.00 $42.38 $281.44 Lakeview, OR, 200 MW, Solar, CF: 27.6% + BESS: 100% pwr, 4 hours Yes 4,800 $2,977 $475 6.839%$236.10 $41.80 1.379%$0.58 $0.00 $42.38 $278.48 Milford, UT, 200 MW, Solar, CF: 30.2% + BESS: 100% pwr, 4 hours Yes 5,000 $2,907 $475 6.839%$231.30 $43.30 1.379%$0.60 $0.00 $43.90 $275.20 Rock Springs, WY, 200 MW, Solar, CF: 27.9% + BESS: 100% pwr, 4 hours Yes 6,400 $2,960 $475 6.839%$234.95 $43.30 1.379%$0.60 $0.00 $43.90 $278.85 Yakima, WA, 200 MW, Solar, CF: 24.2% + BESS: 100% pwr, 4 hours Yes 1,000 $3,077 $475 6.839%$242.90 $43.30 1.379%$0.60 $0.00 $43.90 $286.79 Idah Falls, ID, 200 MW, Solar, CF: 26.1% + BESS: 100% pwr, 4 hours Yes 4,700 $3,020 $475 6.839%$239.06 $41.80 1.379%$0.58 $0.00 $42.38 $281.44 Lakeview, OR, 200 MW, Solar, CF: 27.6% + BESS: 100% pwr, 4 hours Yes 4,800 $2,977 $475 6.839%$236.10 $41.80 1.379%$0.58 $0.00 $42.38 $278.48 Milford, UT, 200 MW, Solar, CF: 30.2% + BESS: 100% pwr, 4 hours Yes 5,000 $2,907 $475 6.839%$231.30 $43.30 1.379%$0.60 $0.00 $43.90 $275.20 Rock Springs, WY, 200 MW, Solar, CF: 27.9% + BESS: 100% pwr, 4 hours Yes 6,400 $2,960 $475 6.839%$234.95 $43.30 1.379%$0.60 $0.00 $43.90 $278.85 Yakima, WA, 200 MW, Solar, CF: 24.2% + BESS: 100% pwr, 4 hours Yes 1,000 $3,077 $475 6.839%$242.90 $43.30 1.379%$0.60 $0.00 $43.90 $286.79 Idah Falls, ID, 200 MW, Solar & Wind, CF: 26.1% + BESS: 100% pwr, 4 hours + 200 MW Wind No 4,700 $3,395 $488 6.839%$265.55 $82.95 1.379%$1.14 $0.00 $84.09 $349.64 Lakeview, OR, 200 MW, Solar & Wind,CF: 27.6% + BESS: 100% pwr, 4 hours + 200 MW Wind No 4,800 $3,424 $488 6.839%$267.48 $82.95 1.379%$1.14 $0.00 $84.09 $351.58 Milford, UT, 200 MW, Solar & Wind,CF: 30.2% + BESS: 100% pwr, 4 hours + 200 MW Wind No 5,000 $3,364 $488 6.839%$263.42 $81.45 1.379%$1.12 $0.00 $82.57 $345.99 Rock Springs, WY, 200 MW, Solar & Wind,CF: 27.9% + BESS: 100% pwr, 4 hours + 200 MW Wind No 6,400 $3,364 $488 6.839%$263.38 $81.45 1.379%$1.12 $0.00 $82.57 $345.95 Yakima, WA, 200 MW, Solar & Wind, CF: 24.2% + BESS: 100% pwr, 4 hours + 200 MW Wind No 1,000 $3,424 $488 6.839%$267.51 $81.45 1.379%$1.12 $0.00 $82.57 $350.08 Modeled IRP Elevation (AFSL) Fixed Cost Fixed O&M $/kW-Yr Total Fixed ($/kW-Yr) Capital Cost $/kW PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 62 Table 5.4 – 2021 IRP Update Supply Side Resources Information Presented is Illustrative Credits Capacity Factor Total Fixed ($/MWh) Storage Efficiency $/MMBtu $/MWh O&M Capitalized Premium O&M Capitalized Integration Cost Total Resource Cost PTC Tax Credits / ITC (Solar Only) / 45Q Tax Credits (CCUS Only) Idah Falls, ID, 200 MW, Solar, CF: 26.1% + BESS: 100% pwr, 4 hours 4,700 26%$123.09 85%-$ -$ -$ 0.00%-$ 0.70$ $123.80 (23.18)$ $100.62 Lakeview, OR, 200 MW, Solar, CF: 27.6% + BESS: 100% pwr, 4 hours 4,800 28%$115.18 85%-$ -$ -$ 0.00%-$ 0.70$ $115.88 (21.61)$ $94.28 Milford, UT, 200 MW, Solar, CF: 30.2% + BESS: 100% pwr, 4 hours 5,000 30%$104.02 85%-$ -$ -$ 0.00%-$ 0.70$ $104.73 (19.28)$ $85.45 Rock Springs, WY, 200 MW, Solar, CF: 27.9% + BESS: 100% pwr, 4 hours 6,400 28%$114.09 85%-$ -$ -$ 0.00%-$ 0.70$ $114.80 (21.25)$ $93.54 Yakima, WA, 200 MW, Solar, CF: 24.2% + BESS: 100% pwr, 4 hours 1,000 24%$135.29 85%-$ -$ -$ 0.00%-$ 0.70$ $135.99 (25.46)$ $110.52 Idah Falls, ID, 200 MW, Solar, CF: 26.1% + BESS: 100% pwr, 4 hours 4,700 26%$123.09 85%-$ -$ -$ 0.00%-$ 0.70$ $123.80 (1.10)$ $122.70 Lakeview, OR, 200 MW, Solar, CF: 27.6% + BESS: 100% pwr, 4 hours 4,800 28%$115.18 85%-$ -$ -$ 0.00%-$ 0.70$ $115.88 (1.03)$ $114.86 Milford, UT, 200 MW, Solar, CF: 30.2% + BESS: 100% pwr, 4 hours 5,000 30%$104.02 85%-$ -$ -$ 0.00%-$ 0.70$ $104.73 (0.91)$ $103.81 Rock Springs, WY, 200 MW, Solar, CF: 27.9% + BESS: 100% pwr, 4 hours 6,400 28%$114.09 85%-$ -$ -$ 0.00%-$ 0.70$ $114.80 (1.01)$ $113.79 Yakima, WA, 200 MW, Solar, CF: 24.2% + BESS: 100% pwr, 4 hours 1,000 24%$135.29 85%-$ -$ -$ 0.00%-$ 0.70$ $135.99 (1.21)$ $134.78 Idah Falls, ID, 200 MW, Solar & Wind, CF: 26.1% + BESS: 100% pwr, 4 hours + 200 MW Wind 4,700 26%$152.92 85%-$ -$ -$ 0.00%-$ 0.70$ $153.63 -$ $153.63 Lakeview, OR, 200 MW, Solar & Wind,CF: 27.6% + BESS: 100% pwr, 4 hours + 200 MW Wind 4,800 28%$145.41 85%-$ -$ -$ 0.00%-$ 0.70$ $146.12 -$ $146.12 Milford, UT, 200 MW, Solar & Wind,CF: 30.2% + BESS: 100% pwr, 4 hours + 200 MW Wind 5,000 30%$130.78 85%-$ -$ -$ 0.00%-$ 0.70$ $131.49 -$ $131.49 Rock Springs, WY, 200 MW, Solar & Wind,CF: 27.9% + BESS: 100% pwr, 4 hours + 200 MW 6,400 28%$141.55 85%-$ -$ -$ 0.00%-$ 0.70$ $142.25 -$ $142.25 Yakima, WA, 200 MW, Solar & Wind, CF: 24.2% + BESS: 100% pwr, 4 hours + 200 MW Wind 1,000 24%$165.14 85%-$ -$ -$ 0.00%-$ 0.70$ $165.84 -$ $165.84 Supply Side Resource Options Mid-Calendar Year 2020 Dollars ($) Resource Description Elevation (AFSL) Convert to $/MWh Total Resource Cost - with PTC / ITC / 45Q Credits Variable Costs ($/MWh) Levelized Fuel PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 63 Modeling Enhancements and Resource Updates Demand Side Management PacifiCorp evaluates new DSM opportunities, which includes both energy efficiency and demand response programs, as a resource that competes with traditional new generation and wholesale power market purchases when developing the IRP Update preferred portfolio. Upon additional review of demand response availability, demand response targets have been scaled back to obtainable levels, decreasing potential selections in this update. Also in the 2021 IRP Update, energy efficiency shapes are now aligned to load, better representing the relative effectiveness of bundles to meet system need. 2020 All-source Request for Proposals Resources (2020AS RFP) Since September 1, 2021, two 2020AS RFP resources withdrew from further contract negotiations and have been removed from assumed development. These solar resources were planned to contribute 153 MW of nameplate capacity and 58 MW of storage capacity in the 2024-2025 timeframe. At this time no replacement has been identified for these solar projects. Other Contracts Five contracts have been signed since September 2021, comprising 45 MW of nameplate solar and geothermal capacity, partially offsetting losses due to changes in the 2020AS RFP. As an original purchaser of the output of the Priest Rapids and Wanapum hydro projects, PacifiCorp has an annual option to purchase approximately 100 MW of the output from these plants at market-based rates. For this IRP Update, it has been assumed that PacifiCorp elects to purchase this hydro output in each year of the study horizon. PACIFICORP – 2021 IRP UPDATE CHAPTER 5 – MODELING AND ASSUMPTIONS UPDATE 64 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 65 CHAPTER 6 – PORTFOLIO DEVELOPMENT Introduction PacifiCorp used Plexos’ three optimization models to develop an updated preferred portfolio based on inputs and assumptions that have changed since the 2021 Integrated Resource Plan (IRP) was filed September 1, 2021. This updated resource portfolio is consistent with PacifiCorp’s most recent load-and-resource balance as described in Chapter 4. This chapter presents the 2021 IRP Update preferred portfolio and a comparison of changes relative to the 2021 IRP preferred portfolio. This chapter also includes three key variants studied in the 2021 IRP regarding significant transmission projects and related resources, and one regional haze sensitivity evaluating compliance strategy for Hunter and Huntington coal. 2021 IRP Update Preferred Portfolio Key Updates As discussed in Chapter 5 – Modeling and Assumptions Updates, key updates driving preferred portfolio outcomes include higher load (approaching the 2021 IRP high-load sensitivity), DSM alignment with achievable objectives and improved alignment to load, and resource changes due to 2020AS RFP activity and newly signed contracts. Also of note is the March 11, 2022 release of the Environmental Protection Agency’s pre-publication version of its "Ozone Transport Rule" (also called Good Neighbor Rule or Cross-State Air Pollution Rule). The rule, discussed in Chapter 3 – Planning Environment, could not be modeled in the 2021 IRP Update at this early juncture, but is expected to be considered in the 2023 IRP development cycle. Portfolio Outcomes The 2021 IRP Update focuses on updates following PacifiCorp’s filed 2021 IRP. These include updates to load forecast, changes in existing resources and PacifiCorp’s contracts with other entities. Figure 6.1 summarizes the annual nameplate capacity in the 2021 IRP Update relative to the 2021 IRP preferred portfolio for the 20-year period 2021 through 2040. Consistent with the change in PacifiCorp’s load-and-resource balance, the increase in loads accelerates transmission projects and related resources into earlier timeframes and re-balances the resource mix as a result. PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 66 Figure 6.1 – Cumulative Increase/(Decrease) in 2021 IRP Update and 2021 IRP Preferred Portfolio As in the 2021 IRP, the 2021 IRP Update preferred portfolio does not include any new natural gas proxy resources through the 20-year planning horizon. Table 6.5 (summer) and (winter) summarize the 2021 IRP Update load and resource balance, inclusive of incremental resources, for 2021-2040. Present Value Revenue Requirement (PVRR) In Table 6.1, the 2021 IRP Update reports a PVRR differential (PVRR(d)) increase in system cost of $946m compared to the 2021 IRP preferred portfolio. Increased load is the primary driver for differences between the two studies, and therefore the High Load sensitivity (S01) analyzed in the 2021 IRP is also compared for reference. The 2021 IRP Update portfolio’s increase in cost falls intuitively between the cost of the 2021 IRP preferred portfolio and the High Load sensitivity. The increased load trends notably higher but does not exceed the high load forecast, as seen in Figure 6.3, below. Emissions and energy not served are also marginally higher, but the 2021 IRP Update portfolio avoids the extremes anticipated in the S01 High Load sensitivity. Table 6.1 – Cost and Risk Portfolio Summary Figure 6.2 reports the relative annual PVRR of three portfolios, indicating the magnitude of the load change in the 2021 IRP Update compared to the 2021 IRP and also to the S01 High Load sensitivity. The results show that the annual PVRR of the updated portfolio is higher than in the -3000 -2500 -2000 -1500 -1000 -500 0 500 1000 1500 2000 In s t a l l e d M W Coal Gas Contracts QF Hydro Nuclear Hydro Storage Battery Solar Solar+Storage Wind Wind+Storage Geothermal Energy Efficiency Demand Response Non-Emitting Peaker Converted Gas 21 IRP Update Preferred Portfolio Update (MM-CETA)26,866 27,289 122 419 $2,587 3.9 0.005647% 21 IRP Preferred Portfolio (P02-MM-CETA)26,740 27,167 -420 $2,594 3.9 0.005647% 21 IRP High Load (S01)27,606 28,436 1,269 409 $2,446 8.9 0.012619% 2021 to 2040 Vintage Study Name ST PVRR ($million) ST PVRR plus 5% of 95th Stochastic ($million) Risk Adjusted PVRR(d) Compared to 2021 Preferred Portfolio ($million) CO2 emissions (Mtons) CO2 emissions cost ($million) Avg Annual Energy Not Served plus Reserve Deficiency (GWh) Energy Not Served as a Percentage of Load (%) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 67 2021 IRP, generally lower than in the High Load sensitivity, but rises above the High Load sensitivity in some years (2029-2032). The trend comports with expected changes in PVRR under higher load conditions and intuitively tracks with the load trajectory over the course of the 20-year study period. Figure 6.2 – Annual Present Value Revenue Requirement Comparison Load Increase The 2021 IRP Update load forecast is significantly higher than the forecast at the time of the 2021 IRP, and is discussed in more detail in Chapter 4 – Load and Resource Balance. Figure 6.3 shows the load comparison among the 2021 IRP, 2021 IRP Update and the S01 High Load sensitivity from the 2021 IRP in support of the PVRR comparison discussed above. Figure 6.3 – Load Forecast Comparison 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 5,000 5,500 6,000 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 21 IRP CETA 21 IRP High Load 21 IRP Update CETA 55,000 60,000 65,000 70,000 75,000 80,000 85,000 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Forecasted Annual System Load (GWh) 2021 IRP Update 2021 IRP 2021 IRP High 8,000 9,000 10,000 11,000 12,000 13,000 14,000 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Forecasted Annual System Coincident Peak (MW) 2021 IRP Update 2021 IRP 2021 IRP High PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 68 Transmission Acceleration Load increase drives new and accelerated transmission in the updated preferred portfolio. While more expensive, accelerated transmission is necessary to meet the higher load. By the end of the study period, accumulated efficiencies including load-aligned DSM and improved resource locations allows the model to avoid a major transmission upgrade in year 2040, and to avoid approximately 400 MW of accompanying additional resources, net of the demand response decrease discussed in Chapter 5 – Modeling Updates. Table 6.2 reports changes in transmission selections relative the 2021 IRP. Four transmission paths are accelerated by a total of 12 years in combination and two new paths are selected, adding 30 MW of interconnection capability to the system. One transmission upgrade, Portland North coast to Willamette Valley, is delayed in the back 10 years of the model horizon. Finally, one transmission path, Portland North Coast to Southern Oregon, is removed, partly offset by the accelerations, particularly of the Central Oregon to Willamette Valley transmission line, as well as the additional transmission selected. Table 6.2 – Transmission Upgrade Changes in the 2021 IRP Update Preferred Portfolio Compared to the 2021 IRP Preferred Portfolio1 1 – Negative values in the “Change” column indicates the number of years of acceleration compared to the 2021 IRP Preferred Portfolio. Table 6.3 reports all of the transmission projects selected for the 2021 IRP Update. Upgrade Export Capacity 2021 Update Year 2020 IRP Year Change CON Central OR > TxCON 2027 100 2030 2037 -7 CON Yakima > TxCON 2027a 180 2029 2030 -1 CON Yakima > TxCON 2027b 100 2029 -New INC Central OR > Willamette Valley 2037 1500 2037 2040 -3 INC Portland North Coast > Southern Oregon 2037 1500 -2040 Removed INC Portland North Coast > Willamette Valley 2032 450 2038 2032 6 INC Utah South > Utah North 2032 800 2032 2033 -1 INC Walla Walla - WA > Yakima 2030 200 2030 -New PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 69 Table 6.3 – Transmission Projects Included in the 2021 IRP Update Preferred Portfolio1, 2 1 - TTC = total transfer capability. The scope and cost of transmission upgrades are planning estimates. Actual scope and costs will vary depending upon the interconnection queue, the transmission service queue, the specific location of any given generating resource and the type of equipment proposed for any given generating resource. 2 - Energy Gateway South is modeled in the 2021 IRP as a contingent option with bids in the 2020 All Source RFP. Other transmission options prior to 2026 are not modeled as transmission requirements and costs are accounted for in the 2020 All Source RFP cluster study for all other resource bids. * Reclaimed transmission is committed with resources with COD later than the date of retirement. New Solar Resources The 2021 IRP Update preferred portfolio includes 1,709 MW of new solar by the end of 2024 and 2,309 MW by the end of 2026, with additions of 5,297 MW through 2040. Accounting for a 153 MW reduction in resources associated with the 2020 AS RFP, the 2021 IRP Update includes 833 MW more new solar capacity by the end of 2031 compared to the 2021 IRP preferred portfolio. After 2031, driven by more efficient higher cost transmission and energy efficiency gains, solar additions are ultimately reduced 730 MW by 2040. Year Resource(s)From To Description 2025 1,641 MW RFP Wind (2025)Aeolus WY Clover Enables 1,930 MW of interconnection with 1700 MW of TTC: Energy Gateway South 2026 415 MW Wind (2026) 200 MW Standalone Battery (2026) Enables 615 MW of interconnection: Albany OR area reinforcement 130 MW Wind (2026) 450 MW Wind (2032) 2026 600 MW Solar+Storage (2026)Borah-Populous Hemingway Enables 600 MW of interconnection with 600 MW of TTC: B2H Boardman-Hemingway 2028 83 MW Solar+Storage (2028) 377 MW Solar+Storage (2030) Enables 460 MW of interconnection: Medford area reinforcement 2029 160 MW Solar+Wind+Storage (2030) 120 MW Solar+Storage (2030) Enables 280 MW of interconnection: Yakima local area reinforcement 2030 100 MW Wind (2030)Walla Walla Yakima Enables 100 MW of interconnection 2030 100 MW Solar+Storage (2030)Enables 100 MW of interconnection 2031 626 MW Solar+Storage (2031) 412 MW Non-Emitting Peaker (2033) Enables 1040 MW of interconnection: Northern UT 345 kV reinforcement 2032 1100 MW Solar+Storage (2032)Southern UT Northern UT Enables 1500 MW of interconnection with 800 MW TTC: Spanish Fork - Mercer 345 kV; New Emery – Clover 345 kV Southwest Wyoming Transmission Area Willamette Valley Central OR Transmission Area 2028*500 MW Adv Nuclear (2028)Reclaimed transmission upon retirement of Naughton 1 & 2 2029*500 MW Battery (2029) 330 MW Wind (2028 & 2029) Eastern Wyoming Reclaimed transmission upon retirement of Dave Johnston PlantTransmission Area 2038 412 MW Non-Emitting Peaker (2038) 1000 MW Adv Nuclear (2038) Bridger WY Within Willamette Valley OR Transmission Area Willamette Valley 2026 Portland North Coast Enables 450 MW of interconnection with 450 MW TTC; Portland Coast area reinforcement and Willamette Valley Yakima WA Transmission Area Northern UT Transmission Area 2037 155 MW Wind (2037) 500 MW Pumped Storage (2040) Within Southern OR Transmission Area Central OR Enables 980 MW of interconnection with 1500 MW of TTC Reclaimed transmission upon retirement of Jim Bridger Plant Transmission Area 2037 702 MW Solar+Storage (2037) 206 MW Non-Emitting Peaker (2037) Southern Utah Reclaimed transmission upon retirement of Huntington 1 & 2Transmission Area 2040 268 MW Wind (2040) Eastern Wyoming Reclaimed transmission upon retirement of Wyodak Transmission Area PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 70 Figure 6.4 – 2021 IRP Update Preferred Portfolio New Solar Capacity* * 2021 IRP Update solar capacity shown in the figure includes solar resources coming via the 2020 All-Source Request for Proposals by the end of 2024. Resources are shown in the first full year of operation (the year after the year-online dates). The reported capacity for the 2020 All-Source Request for Proposals solar resources reflects their expected maximum output after degradation in their first full year of operation. New Wind Resources As shown in Figure 6.5, by the end of 2024, PacifiCorp’s 2021 IRP Update preferred portfolio includes 1,815 MW of new wind generation resulting from the 2020 All-Source RFP and the acquisition and repowering of Rock River I (49 MW) and Foote Creek II-IV (43 MW). Through the end of 2026, the 2021 IRP Update preferred portfolio includes an additional 2,363 MW of new wind and more than 4,000 MW of new wind by 2040. Relative to the 2021 IRP, 2021 IRP Update wind additions are mostly reduced or flat through 2037, and ultimately increase by 348 MW of new wind by the end of 2040. Figure 6.5 – 2021 IRP Update Preferred Portfolio New Wind Capacity* *Note: Wind additions shown are incremental to Energy Vision 2020 and other projects that have come online over the past few years. Resources are shown in the first full year of operation (the year after year-end online dates). New Storage Resources New storage resources in the 2021 IRP Update preferred portfolio are summarized in Figure 6.6. The updated portfolio includes nearly 639 MW of battery storage by the end of 2024 – 200 MW of which is a standalone battery and the remaining portion paired with solar resources resulting from the 2020 All-Source RFP. Through 2040, the 2021 IRP includes 4,146 MW of storage co- located with solar resources, 900 MW of standalone battery, and 500 MW of pumped hydro. 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP 0 1,000 2,000 3,000 4,000 5,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 71 Figure 6.6 – 2021 IRP Update Preferred Portfolio New Storage Capacity* *Note: Resources are shown in the first full year of operation (the year after the year-end online dates). Other Non-Emitting Resources The 2021 IRP was the first to include new advanced nuclear and non-emitting peaking resources as part of its least-cost, least-risk preferred portfolio. The 2021 IRP Update continues to select these resources. As shown in Figure 6.7, the 500 MW advanced nuclear NatriumTM demonstration project is projected to come online by summer 2028. Through 2040, the 2021 IRP Update preferred portfolio includes 1,500 MW of advanced nuclear resources and 1,237 MW of non-emitting peaking resources to support meeting requirements. Compared to the 2021 IRP, non-emitting peaker additions increase by 11 MW due to capacity sizing differences of the selected locations. Figure 6.7 – 2021 IRP Update Other Non-Emitting Resources Capacity *Note: Resources are shown in the first full year of operation (the year after the year-end online dates). Demand-Side Management DSM resources continue to play a key role in PacifiCorp’s resource mix. The chart to the left in Figure 6.8 compares total energy efficiency capacity savings in the 2021 IRP Update preferred portfolio relative to the 2021 IRP preferred portfolio and includes 4,685 MW by the end of the planning period. This increase is attributed to the reductions in demand response, combined with the alignment of energy efficiency to load, both described in Chapter 5 – Modeling Updates. For the 2021 IRP Update, selections of demand response have been scaled back to realistic targets, which is responsible for decreases shown on the right-hand side of Figure 6.8. Demand response selections in the 2021 IRP Update total nearly 1,000 MW over the 20-year horizon. By the end of 2040 and relative to the 2021 IRP preferred portfolio, energy efficiency selection increases by nearly 400 MW, whereas demand response selections are reduced by more than 1,400 MW. 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP 0 500 1,000 1,500 2,000 2,500 3,000 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 72 Figure 6.8 – 2021 IRP Update Preferred Portfolio Energy Efficiency (Class 2 DSM) and Direct Load Control Capacity (Class 1 DSM) Market Activity Figure 6.9 compares market purchases and sales among the 2021 IRP preferred portfolio, the 2021 IRP S01 High Load sensitivity and the 2021 IRP Update. While the 2021 IRP Update averages approximately 500 GWh of additional sales annually compared to both the 2021 IRP preferred portfolio and the 2021 IRP High Load scenario, offsetting purchases are higher in some years, particularly 2032 to 2037. On average, 2021 IRP Update purchases increase by an average of 200 MW annually on a purely volumetric basis. Given near-term concerns over resource adequacy, generally lower market purchases in 2021 IRP Update portfolio in the first 5 years are viewed favorably. Figure 6.9 – 2021 IRP Update Market Activity Comparison to 2021 IRP Studies Coal and Gas Retirements/Gas Conversions The 2021 IRP Update did not trigger any changes to the retirement or conversion assumptions selected in the 2021 IRP. Driven in part by ongoing cost pressures on existing coal-fired facilities and dropping costs for new resource alternatives, of the 22 coal units currently serving PacifiCorp customers, the updated preferred portfolio continues to include retirement of 14 of the units by 2030 and 19 of the units by the end of the planning period in 2040. As shown in , coal unit retirements/gas peaker conversions in the 2021 IRP Update preferred portfolio will reduce coal- fueled generation capacity by 1,300 MW by the end of 2025, over 2,200 MW by 2030, and over 4,000 MW by 2040. 0 1,000 2,000 3,000 4,000 5,000 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Cu m u l a t i v e M W Energy Efficiency (Class 2 DSM) 2021 IRP Update 2021 IRP 0 500 1,000 1,500 2,000 2,500 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Cu m u l a t i v e M W Direct Load Control (Class 1 DSM) 2021 IRP Update 2021 IRP 2,000 3,000 4,000 5,000 6,000 7,000 8,000 En e r g y ( G W h ) Market Purchases Purch-21 IRP CETA Purch-21 IRP High Load Purch-21 IRP Update CETA (10,000) (9,000) (8,000) (7,000) (6,000) (5,000) (4,000) En e r g y ( G W h ) Market Sales Sales-21 IRP CETA Sales-21 IRP High Load Sales-21 IRP Update CETA PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 73 Figure 6.10 – 2021 IRP Update Preferred Portfolio Coal Retirements/Gas Conversions* * Note: Coal retirements are assumed to occur by the end of the year before the year shown in the graph. The graph shows the year in which the capacity will not be available for meeting summer peak load. All figures represent PacifiCorp’s ownership share of jointly owned facilities. (4,500) (4,000) (3,500) (3,000) (2,500) (2,000) (1,500) (1,000) (500) 0 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Cu m u l a t i v e M W 2021 IRP Update 2021 IRP* PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 74 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 75 Table 6.4 – Comparison of 2021 IRP Update with 2021 IRP Preferred Portfolio (Megawatts) 2021 IRP Update Capacity (MW)10- year Total Resource 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2021-2040 Expansion Options Gas - CCCT - - - - - - - - - - - - - - - - - - - - - Gas- Peaking - - - - - - - - - - - - - - - - - - - - - NonEmitting Peaking - - - - - - - - - - 412 - - - - - 412 412 - - 1,237 DSM - Energy Efficiency 146 124 131 132 199 237 270 304 323 347 348 339 322 296 262 230 201 176 155 143 4,685 DSM - Demand Response - 117 148 74 61 35 37 62 58 58 54 28 24 22 47 24 72 20 17 20 978 Renewable - Wind 49 - - 194 1,641 547 - 255 202 308 - - - - - - 156 450 - 268 4,069 Renewable - Wind+Storage - - - - - - - - 160 - - - - - - - - - - - 160 Renewable - Utility Solar - - - - - - - - - - - - - - - - - - - - - Renewable - Utility Solar + Storage - - - 345 805 600 - 83 160 477 626 1,100 - - - - 702 - - - 4,898 Renewable - Geothermal - - - - - - - - - - - - - - - - - - - - - Renewable - Battery (Wind+Storage)- - - - - - - - - - - - - - - - - - - - - Renewable - Battery (Solar+Storage)- - - 88 352 600 - 42 160 477 626 1,100 - - - - 702 - - - 4,146 Battery - Stand Alone - - - 200 - 200 - - 500 - - - - - - - - - - - 900 Storage - CAES - - - - - - - - - - - - - - - - - - - - - Storage - Pumped Hydro - - - - - - - - - - - - - - - - - - - 500 500 Nuclear - - - - - - - 345 - - - - - - - - - 690 - - 1,035 Nuclear + Storage - - - - - - - 155 - - - - - - - - - 310 - - 465 Front Office Transactions - Summer *125 59 108 132 171 113 129 141 188 172 163 164 251 253 301 251 255 309 348 351 199 Front Office Transactions - Winter *164 60 121 143 133 1 1 1 1 - - - - 89 103 138 366 607 670 714 166 Existing Unit Changes Thermal Plant End-of-life Retirements - - - - - (230) - (788) (123) - - - - - - - (909) (699) - (268) (3,018) Coal Early Retirement - - - - - (357) - - - - - - - - - - - - - - (357) Coal Plant Gas Conversion - - - 713 - - - - - - - - - - - - - (713) - - - Coal Plant ceases running as Coal - - - (713) - - - - - - - - - - - - - - - - Coal Plant ceases running as Coal(713) Gas Plant End-of-life Retirements - - - - - - - - - (247) - - (356) - - - (237) - - - (840) Total 484 360 509 1,306 3,361 1,746 437 600 1,630 1,592 2,228 2,730 240 661 713 644 1,720 1,561 1,191 1,728 * FOT in resource total are 20-year averages 2021 IRP Update less 2021 IRP Preferred Portfolio Capacity (MW)10- year Total Resource 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2021-2040 Expansion Options Gas - CCCT - - - - - - - - - - - - - - - - - - - - - Gas- Peaking - - - - - - - - - - - - - - - - - - - - - NonEmitting Peaking - - - - - - - - - - 412 - (402) - - - 412 (206) - (206) 11 DSM - Energy Efficiency (11) (14) (13) (33) 14 26 32 41 44 43 47 46 50 47 41 36 12 6 (5) (13) 395 DSM - Demand Response - (7) (94) (110) (18) (29) (32) (18) (19) (19) (29) (22) (189) (48) (113) (101) (111) (139) (90) (281) (1,471) Renewable - Wind - - (151) 151 - (198) - 255 202 (182) - (450) - - - - 156 450 - 208 441 Renewable - Wind+Storage - - - - - - - - 160 (160) - - - - - - - - - - - Renewable - Utility Solar - - - (95) - - - - - - - - - - - - - - - - (95) Renewable - Utility Solar + Storage - - - (407) 349 - - - 160 (81) (194) 1,100 (1,100) - - - (307) - - (156) (635) Renewable - Geothermal - - - - - - - - - - - - - - - - - - - - - Renewable - Battery (Wind+Storage)- - - - - - - - - - - - - - - - - - - - - Renewable - Battery (Solar+Storage)- - - (152) 94 - - - 160 (81) (194) 1,100 (1,100) - - - (307) - - (156) (635) Battery - Stand Alone - - - - - 200 - - (49) (1) - - - - - - (650) - - - (500) Storage - CAES - - - - - - - - - - - - - - - - - - - - - Storage - Pumped Hydro - - - - - - - - - - - - - - - - - - - - - Nuclear - - - - - - - - - - - - - - - - - - - - - Nuclear + Storage - - - - - - - - - - - - - - - - - - - - - Front Office Transactions - Summer *(90) (180) (119) (71) (138) (94) (117) (114) (145) (193) (210) (209) (122) (247) (72) (192) (179) (191) (152) (149) (149) Front Office Transactions - Winter *(6) (113) (78) (38) (56) (22) (40) (29) (29) (30) (22) (86) (165) (114) (102) (165) (64) 82 118 38 (46) Existing Unit Changes Thermal Plant End-of-life Retirements - - - - - - - - - - - - - - - - - - - - - Coal Early Retirement - - - - - - - - - - - - - - - - - - - - - Coal Plant Gas Conversion - - - - - - - - - - - - - - - - - - - - - Coal Plant ceases running as Coal - - - - - - - - - - - - - - - - - - - - - Gas Plant End-of-life Retirements - - - - - - - - - - - - - - - - - - - - - Total (107) (314) (456) (754) 244 (116) (158) 135 483 (703) (190) 1,479 (3,028) (361) (246) (423) (1,037) 1 (129) (714) * FOT in resource total are 20-year averages PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 76 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 77 Table 6.5 – 2021 IRP Update Summer Capacity Load and Resource Balance (Megawatts) East 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Coal 3,536 3,474 3,505 3,513 3,076 3,067 2,343 2,245 2,199 2,198 Gas 1,942 1,964 1,922 1,947 1,968 1,933 1,950 1,942 1,753 1,748 Hydroelectric 108 108 88 88 88 88 88 87 87 87 Solar 377 521 197 424 341 320 352 316 291 161 Wind 337 405 262 452 445 424 422 491 490 395 Geothermal 49 50 51 50 50 52 51 50 51 50 Contracts 185 182 122 35 31 30 31 24 22 17 Sales and Ancillary Services (267)(267)(243)(243)(239)(236)(235)(234)(233)(233) East Existing Resources 6,268 6,438 5,905 6,265 5,760 5,678 5,003 4,922 4,660 4,423 Front Office Transactions 300 300 300 124 0 0 0 0 0 0 NonEmitting Peaker 0 0 0 0 0 0 0 0 0 367 Wind 0 0 14 300 293 291 352 397 449 392 Solar 0 0 30 169 143 133 165 148 129 117 Storage 1 1 284 583 553 535 669 923 817 1,125 Nuclear 0 0 0 0 0 0 324 322 334 318 East Planned Resources 301 301 628 1,177 990 959 1,510 1,790 1,729 2,319 East Total Resources 6,569 6,739 6,533 7,442 6,749 6,637 6,513 6,712 6,388 6,742 Load 7,274 7,421 7,543 7,685 7,654 7,732 7,843 7,944 8,052 8,162 Private Generation (57)(66)(69)(71)(75)(81)(90)(103)(120)(144) Existing - Demand Response (594)(585)(594)(593)(520)(496)(460)(255)(220)(196) New Demand Response (74)(146)(169)(192)(182)(187)(202)(158)(141)(130) New Energy Efficiency (134)(210)(242)(379)(500)(810)(801)(1,051)(1,026)(1,252) East Total obligation 6,415 6,414 6,468 6,450 6,377 6,158 6,291 6,378 6,545 6,440 East Reserve Margin 2%5%1%15%6%8%4%5%-2%5% West Coal 1,500 1,495 1,487 1,488 1,354 1,352 1,348 1,370 1,356 1,356 Gas 663 673 660 664 663 664 664 664 675 665 Hydroelectric 955 796 790 799 795 798 798 794 792 797 Solar 7 27 10 20 16 15 16 14 13 6 Wind 89 83 50 87 82 89 77 84 91 85 Geothermal 0 0 0 0 0 0 0 0 0 0 Contracts 171 168 131 146 132 97 102 72 63 47 Sales and Ancillary Services (209)(207)(182)(182)(179)(177)(177)(168)(168)(169) West Existing Resources 3,177 3,034 2,945 3,022 2,863 2,838 2,828 2,831 2,822 2,787 Front Office Transactions 1,245 1,128 1,445 290 0 0 0 0 0 0 NonEmitting Peaker 0 0 0 0 0 0 0 0 0 0 Wind 0 0 0 0 141 153 162 223 273 239 Solar 0 0 0 59 157 154 190 196 274 151 Storage 0 0 0 53 844 844 886 868 1,092 971 Nuclear 0 0 0 0 0 0 0 0 0 0 West Planned Resources 1,245 1,128 1,445 402 1,142 1,151 1,238 1,286 1,640 1,361 West Total Resources 4,421 4,162 4,390 3,424 4,006 3,989 4,066 4,118 4,462 4,148 Load 3,372 3,402 3,434 3,471 3,501 3,534 3,569 3,604 3,640 3,679 Private Generation (28)(40)(45)(49)(54)(60)(67)(75)(85)(106) Existing - Demand Response 0 0 0 0 0 0 0 0 0 0 New Demand Response (42)(107)(149)(174)(164)(170)(174)(119)(110)(103) New Energy Efficiency (73)(120)(147)(192)(242)(157)(354)(264)(442)(321) West Total obligation 3,229 3,136 3,094 3,055 3,041 3,147 2,975 3,145 3,003 3,148 West Reserve Margin 37%33%42%12%32%27%37%31%49%32% System Total Resources 10,990 10,900 10,924 10,866 10,755 10,626 10,578 10,830 10,850 10,890 Obligation 9,644 9,550 9,562 9,505 9,418 9,305 9,265 9,523 9,548 9,588 Capacity Reserve Margin (13%)1,254 1,242 1,243 1,236 1,224 1,210 1,204 1,238 1,241 1,246 Obligation + Reserves 10,898 10,792 10,805 10,741 10,643 10,515 10,470 10,761 10,789 10,834 System Position 92 109 119 125 113 111 109 69 61 56 Reserve Margin 14%14%14%14%14%14%14%14%14%14% PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 78 Table 6.5 (Cont.) – 2021 IRP Update Summer Capacity Load and Resource Balance (Megawatts) East 2032 2033 2034 2035 2036 2037 2038 2039 2040 Thermal 2,212 2,219 2,207 2,219 2,218 1,359 1,362 1,357 1,100 Hydroelectric 1,743 1,412 1,401 1,397 1,398 1,403 1,403 1,399 1,410 Hydroelectric 86 87 87 86 87 86 86 87 87 Solar 30 136 124 132 125 137 144 142 83 Wind 252 355 359 353 333 475 502 480 457 Geothermal 51 50 51 51 52 50 20 20 20 Contracts 10 15 14 12 9 8 0 0 0 Sales and Ancillary Services (226)(230)(229)(228)(228)(233)(233)(234)(227) East Existing Resources 4,159 4,043 4,013 4,022 3,993 3,287 3,285 3,251 2,931 Front Office Transactions 0 0 0 0 0 0 0 0 0 NonEmitting Peaker 398 380 386 385 398 581 580 585 576 Wind 253 394 413 400 372 490 483 526 568 Solar 40 200 187 191 172 474 520 525 324 Storage 1,642 1,521 1,497 1,497 1,496 1,720 1,675 1,626 1,558 Nuclear 322 314 326 322 335 319 932 925 939 East Planned Resources 2,655 2,809 2,809 2,795 2,773 3,584 4,190 4,187 3,965 East Total Resources 6,813 6,853 6,822 6,817 6,766 6,871 7,475 7,438 6,896 Load 8,266 8,370 8,473 8,444 8,585 8,679 8,793 8,655 8,759 Private Generation (173)(203)(236)(150)(173)(196)(221)(116)(128) Existing - Demand Response (176)(163)(161)(161)(160)(148)(144)(148)(142) New Demand Response (119)(113)(113)(120)(122)(123)(121)(126)(122) New Energy Efficiency (1,489)(1,442)(1,522)(1,590)(1,607)(1,702)(1,753)(1,702)(1,844) East Total obligation 6,309 6,450 6,442 6,423 6,522 6,510 6,553 6,563 6,522 East Reserve Margin 8%6%6%6%4%6%14%13%6% West Coal 1,356 1,358 1,355 1,354 1,353 1,351 0 0 0 Gas 667 665 665 663 677 449 448 446 446 Hydroelectric 793 794 796 792 793 795 795 798 798 Solar 1 5 4 5 5 9 10 10 7 Wind 56 88 77 73 83 97 114 117 84 Geothermal 0 0 0 0 0 0 0 0 0 Contracts 24 35 31 30 32 23 19 10 10 Sales and Ancillary Services (162)(169)(167)(160)(155)(161)(157)(156)(144) West Existing Resources 2,735 2,776 2,760 2,757 2,787 2,563 1,229 1,224 1,200 Front Office Transactions 0 0 0 0 0 0 0 0 0 NonEmitting Peaker 0 0 0 0 0 196 566 575 586 Wind 157 246 256 220 220 343 522 543 470 Solar 35 137 126 127 130 249 272 278 183 Storage 873 809 796 796 796 735 915 940 1,364 Nuclear 0 0 0 0 0 0 0 0 0 West Planned Resources 1,065 1,192 1,177 1,143 1,145 1,522 2,276 2,337 2,603 West Total Resources 3,801 3,968 3,938 3,900 3,932 4,086 3,505 3,561 3,803 Load 3,711 3,747 3,785 3,775 3,809 3,854 3,892 3,861 3,896 Private Generation (147)(193)(247)(217)(254)(296)(341)(190)(221) Existing - Demand Response 0 0 0 0 0 0 0 0 0 New Demand Response (94)(88)(88)(90)(91)(85)(84)(87)(84) New Energy Efficiency (432)(382)(412)(450)(561)(327)(344)(455)(685) West Total obligation 3,040 3,084 3,038 3,018 2,902 3,145 3,124 3,129 2,906 West Reserve Margin 25%29%30%29%35%30%12%14%31% System Total Resources 10,614 10,820 10,760 10,716 10,699 10,957 10,980 10,999 10,698 Obligation 9,348 9,534 9,481 9,441 9,425 9,655 9,677 9,692 9,428 Capacity Reserve Margin (13%)1,215 1,239 1,232 1,227 1,225 1,255 1,258 1,260 1,226 Obligation + Reserves 10,563 10,773 10,713 10,668 10,650 10,911 10,935 10,952 10,653 System Position 51 47 47 48 49 46 45 47 45 Reserve Margin 14%13%13%14%14%13%13%13%13% PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 79 Table 6.6 – 2021 IRP Update Winter Capacity Load and Resource Balance (Megawatts) East 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Coal 3,443 3,491 3,470 3,477 2,931 2,941 2,249 2,224 2,148 2,090 Gas 1,938 2,045 2,043 1,995 1,913 1,969 2,042 2,012 1,817 1,700 Hydroelectric 80 80 70 70 68 67 70 69 69 67 Solar 48 72 40 22 14 16 16 24 39 11 Wind 268 383 250 278 280 263 256 355 418 306 Geothermal 52 52 52 51 51 46 52 52 52 50 Contracts 164 137 66 16 15 15 15 9 9 8 Sales and Ancillary Services (212)(215)(189)(192)(190)(189)(191)(193)(194)(194) East Existing Resources 5,781 6,045 5,801 5,716 5,081 5,127 4,509 4,552 4,360 4,038 Front Office Transactions 181 167 187 0 0 0 0 0 0 0 NonEmitting Peaker 0 0 0 0 0 0 0 0 11 375 Wind 0 0 20 293 255 247 309 424 539 460 Solar 0 0 7 14 10 11 8 14 24 13 Storage 1 1 250 491 456 453 614 847 758 1,037 Nuclear 0 0 0 0 0 3 308 309 308 297 East Planned Resources 182 168 464 797 722 715 1,240 1,594 1,640 2,182 East Total Resources 5,963 6,213 6,265 6,514 5,803 5,842 5,749 6,146 6,000 6,220 Load 5,691 5,868 5,936 6,050 5,977 6,033 6,138 6,220 6,297 6,374 Private Generation (1)(2)(2)(3)(4)(5)(6)(7)(8)(9) Existing - Demand Response (322)(309)(335)(408)(330)(324)(336)(229)(204)(180) New Demand Response (73)(138)(150)(166)(163)(167)(182)(142)(131)(120) New Energy Efficiency (108)(148)(198)(221)(275)(725)(400)(842)(880)(520) East Total obligation 5,186 5,273 5,251 5,252 5,205 4,813 5,213 5,000 5,074 5,545 East Reserve Margin 15%18%19%24%11%21%10%23%18%12% West Coal 1,488 1,488 1,319 1,468 1,321 1,314 1,338 1,335 1,360 1,313 Gas 718 718 711 713 697 693 717 715 630 695 Hydroelectric 1,038 858 865 861 847 843 869 866 869 843 Solar 0 1 1 1 0 0 0 1 1 0 Wind 39 52 33 50 39 33 34 44 52 50 Geothermal 0 0 0 0 0 0 0 0 0 0 Contracts 78 73 70 68 58 31 33 21 17 15 Sales and Ancillary Services (192)(174)(149)(146)(145)(142)(142)(147)(147)(146) West Existing Resources 3,168 3,016 2,850 3,014 2,818 2,772 2,849 2,834 2,782 2,771 Front Office Transactions 422 390 437 0 0 0 0 0 0 0 NonEmitting Peaker 0 0 0 0 0 0 0 0 0 0 Wind 0 0 0 2 67 63 60 109 135 123 Solar 0 0 0 3 7 7 8 11 21 8 Storage 0 0 0 53 844 844 886 782 1,013 894 Nuclear 0 0 0 0 0 0 0 0 0 0 West Planned Resources 422 390 437 58 918 915 954 902 1,169 1,025 West Total Resources 3,590 3,407 3,287 3,072 3,737 3,687 3,803 3,736 3,951 3,796 Load 3,330 3,373 3,408 3,446 3,487 3,534 3,580 3,628 3,673 3,710 Private Generation (0)(1)(1)(1)(1)(2)(2)(3)(3)(4) Existing - Demand Response 0 0 0 0 0 0 0 0 0 0 New Demand Response (35)(82)(108)(136)(129)(134)(144)(107)(102)(95) New Energy Efficiency (76)(110)(165)(160)(191)150 (271)172 114 (339) West Total obligation 3,218 3,179 3,135 3,148 3,166 3,548 3,164 3,690 3,682 3,273 West Reserve Margin 12%7%5%-2%18%4%20%1%7%16% System Total Resources 9,553 9,620 9,553 9,585 9,540 9,529 9,552 9,882 9,951 10,016 Obligation 8,405 8,452 8,385 8,401 8,371 8,361 8,377 8,690 8,756 8,818 Capacity Reserve Margin (13%)1,093 1,099 1,090 1,092 1,088 1,087 1,089 1,130 1,138 1,146 Obligation + Reserves 9,497 9,551 9,475 9,493 9,459 9,448 9,466 9,820 9,894 9,965 System Position 56 69 77 92 81 81 86 62 57 51 Reserve Margin 14%14%14%14%14%14%14%14%14%14% PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 80 Table 6.6 (Cont.) - 2021 IRP Update Winter Capacity Load and Resource Balance (Megawatts) East 2032 2033 2034 2035 2036 2037 2038 2039 2040 Coal 2,051 2,203 2,178 2,212 2,188 1,353 1,332 1,338 1,178 Gas 1,736 1,444 1,473 1,485 1,353 1,482 1,479 1,487 1,466 Hydroelectric 66 69 69 69 69 70 69 69 69 Solar 7 6 9 23 33 31 37 36 24 Wind 220 271 274 389 454 578 701 744 561 Geothermal 49 52 49 52 52 52 20 20 20 Contracts 7 7 7 6 6 3 0 0 7 Sales and Ancillary Services (194)(196)(198)(203)(205)(202)(203)(205)(208) East Existing Resources 3,942 3,857 3,861 4,034 3,949 3,367 3,436 3,490 3,116 Front Office Transactions 0 0 0 0 0 0 0 0 126 NonEmitting Peaker 360 382 387 385 386 577 579 581 569 Wind 300 424 460 535 581 676 790 852 792 Solar 11 13 16 39 59 100 112 114 84 Storage 1,549 1,449 1,445 1,447 1,509 1,634 1,596 1,523 1,478 Nuclear 278 312 314 310 305 342 945 955 906 East Planned Resources 2,498 2,581 2,622 2,715 2,841 3,328 4,022 4,024 3,955 East Total Resources 6,440 6,437 6,483 6,749 6,790 6,695 7,457 7,514 7,071 Load 6,459 6,542 6,645 6,724 6,801 6,890 6,992 7,083 7,190 Private Generation (10)(12)(13)(14)(16)(18)(19)(21)(23) Existing - Demand Response (166)(155)(155)(155)(162)(141)(137)(139)(135) New Demand Response (113)(107)(109)(116)(123)(117)(115)(118)(116) New Energy Efficiency (905)(920)(1,185)(1,051)(1,057)(343)(1,143)(443)(1,458) East Total obligation 5,265 5,348 5,183 5,387 5,443 6,272 5,576 6,363 5,459 East Reserve Margin 22%20%25%25%25%7%34%18%30% West Coal 1,285 1,323 1,361 1,362 1,360 1,360 0 0 27 Gas 680 710 718 718 683 490 489 490 495 Hydroelectric 828 865 874 875 874 877 878 880 879 Solar 0 0 0 0 0 1 1 1 0 Wind 31 41 46 52 60 79 83 82 68 Geothermal 0 0 0 0 0 0 0 0 0 Contracts 14 13 13 14 13 13 12 11 14 Sales and Ancillary Services (144)(141)(144)(145)(146)(143)(142)(142)(148) West Existing Resources 2,695 2,812 2,867 2,877 2,846 2,675 1,322 1,321 1,336 Front Office Transactions 0 0 0 0 0 0 0 0 293 NonEmitting Peaker 0 0 0 0 7 212 577 579 540 Wind 84 111 112 131 127 189 290 294 242 Solar 4 5 5 13 18 24 30 37 22 Storage 823 770 768 769 803 698 872 881 1,294 Nuclear 0 0 0 0 0 0 0 0 0 West Planned Resources 911 886 886 913 954 1,123 1,769 1,791 2,392 West Total Resources 3,606 3,699 3,753 3,790 3,801 3,798 3,091 3,112 3,727 Load 3,756 3,805 3,854 3,902 3,946 3,994 4,048 4,102 4,156 Private Generation (4)(5)(6)(7)(8)(9)(11)(12)(13) Existing - Demand Response 0 0 0 0 0 0 0 0 0 New Demand Response (88)(84)(85)(87)(92)(81)(80)(81)(80) New Energy Efficiency (80)(134)73 89 40 (934)(237)(1,013)(3) West Total obligation 3,584 3,582 3,836 3,898 3,886 2,970 3,721 2,995 4,059 West Reserve Margin 1%3%-2%-3%-2%28%-17%4%-8% System Total Resources 10,047 10,136 10,236 10,539 10,591 10,493 10,548 10,625 10,798 Obligation 8,848 8,930 9,018 9,285 9,329 9,243 9,297 9,358 9,518 Capacity Reserve Margin (13%)1,150 1,161 1,172 1,207 1,213 1,202 1,209 1,217 1,237 Obligation + Reserves 9,999 10,091 10,191 10,492 10,542 10,444 10,505 10,574 10,755 System Position 48 45 45 47 49 49 43 51 43 Reserve Margin 14%14%14%14%14%14%13%14%13% PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 81 Carbon Dioxide Emissions While the 2021 IRP Update preferred portfolio reflects PacifiCorp’s on-going efforts to provide cost-effective clean-energy solutions for our customers, increased load has driven thermal dispatch and therefore emissions higher based on currently modeled resource options and assumptions. Portfolio emissions and costs due to the higher load forecast present a less extreme version of the S01 High Load sensitivity from the 2021 IRP. PacifiCorp’s emissions have been declining and are expected to continue to decline related to several factors including PacifiCorp’s participation in the EIM, which reduces customer costs and maximizes use of clean energy; PacifiCorp’s on-going transition to clean-energy resources including new renewable resources, new advanced nuclear resources, new non-emitting resources, storage, and associated transmission; and Regional Haze compliance. Input updates and additional transmission and resource options in the 2023 IRP are expected to allow economic emissions reductions not available to the 2021 IRP Update and in the absence of a full IRP cycle. The chart on the left in Figure 6.11 compares projected annual CO2 emissions between the 2021 IRP update and 2021 IRP preferred portfolios. In this graph, emissions are not assigned to market purchases or sales. The chart on the right in Figure 6.11 includes historical data, assigns emissions at a rate of 0.4708 tons CO2 equivalent per MWh to market purchases (with no credit to market sales), includes emissions associated with specified purchases, and extrapolates projections out through 2050. This graph demonstrates that relative to a 2005 baseline, 2021 IRP Update preferred portfolio system CO2 equivalent emissions are down 49 percent in 2025, 69 percent in 2030, 78 percent in 2035, 88 percent in 2040, 94 percent in 2045, and 100 percent in 2050. Figure 6.11 – 2021 IRP Preferred Portfolio CO2 Emissions and PacifiCorp CO2 Equivalent Emissions Trajectory* *Note: PacifiCorp CO2 equivalent emissions trajectory reflects actual emissions through 2020 from owned facilities, specified sources and unspecified sources. From 2021 through the end of the twenty-year planning period in 2040, emissions reflect those from the 2021 IRP Update preferred portfolio with emissions from specified sources reported in CO2 equivalent. Market purchases are assigned a default emission factor (0.4708 short tons CO2e/MWh) – emissions from sales are not removed. Beyond 2040, emissions reflect the rolling average emissions of each resource from the 2021 IRP update preferred portfolio through the life of the resource. The emissions trajectory does not incorporate clean energy targets set forth in Oregon House Bill 2021 or any other state-specific emissions trajectories. PacifiCorp expects these targets, and an Oregon-specific emissions trajectory, to be incorporated following the 2023 integrated resource plan when PacifiCorp is required under the bill to file a Clean Energy Plan. 0 10 20 30 40 50 60 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Mi l l i o n T o n s CO2 Emissions 2021 IRP Update 2021 IRP 0 0.2 0.4 0.6 0.8 1 0 10 20 30 40 50 60 20 1 1 20 1 3 20 1 5 20 1 7 20 1 9 20 2 1 20 2 3 20 2 5 20 2 7 20 2 9 20 3 1 20 3 3 20 3 5 20 3 7 20 3 9 20 4 1 20 4 3 20 4 5 20 4 7 20 4 9 % o f 2 0 0 5 B a s e Mi l l i o n T o n s ( C O 2e) PacifiCorp CO2 Equivalent Emissions Trajectory PacifiCorp Emissions (Million ST CO2e)PacifiCorp 2005 Base (Million ST CO2e) % Reduction from 2005 Base PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 82 Monthly CO2 emissions are available for the preferred portfolio as shown in Figure 6.12 below. Figure 6.12 – 2021 IRP Update Monthly CO2 Renewable Portfolio Standards Figure 6.13 shows PacifiCorp’s renewable portfolio standard (RPS) compliance forecast for California, Oregon, and Washington after accounting for new renewable resources in the preferred portfolio. While these resources are included in the preferred portfolio as cost-effective system resources and are not included to specifically meet RPS targets, they nonetheless contribute to meeting RPS targets in PacifiCorp’s western states. Oregon RPS compliance is achieved through 2040 with the addition of new renewable resources and transmission in the 2021 IRP Update preferred portfolio. Consistent with the 2021 IRP, in the 2021 IRP Update, Washington RPS compliance is achieved with the benefit of increased system renewable resources as well as additional resources procured that meet the state’s Clean Energy Transformation Act. Under PacifiCorp’s 2020 Protocol, and the Washington Interjurisdictional Allocation Methodology, Washington’s RPS position is improved by receiving a system share of renewable resources across the PacifiCorp’s system. The California RPS compliance position will be met with owned and contracted renewable resources, as well as REC purchases throughout the study period. The ramping RPS requirement results in an increased need for unbundled REC purchases to meet the annual and compliance period targets in 2021-2040. New renewable resources and transmission in the 2021 IRP update preferred portfolio mitigate that shortfall, but the company has made a 120,000 REC purchase PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 83 towards compliance period 4, years 2021-2024, and will continue to evaluate the need for unbundled RECs and issue RFPs to meet its state RPS compliance requirements as needed. While not shown in Figure 6.13, PacifiCorp meets the Utah 2025 state target to supply 20 percent of adjusted retail sales with eligible renewable resources with existing owned and contracted resources and new renewable resources and transmission in the 2021 IRP Update preferred portfolio. PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 84 Figure 6.13 – Annual State RPS Compliance Forecast 0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 RE C s ( T h o u s a n d s ) Oregon RPS Unbundled Surrendered Bundled Surrendered Unbundled Bank Surrendered Bundled Bank Surrendered Year-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement 0 100 200 300 400 500 600 700 RE C s ( T h o u s a n d s ) California RPS Unbundled Surrendered Bundled Surrendered Shortfall Requirement 0 2,000 4,000 6,000 8,000 10,000 12,000 RE C s ( T h o u s a n d s ) Washington RPS Unbundled Surrendered Bundled Surrendered Unbundled Bank Surrendered Bundled Bank Surrendered Year-end Unbundled Bank Balance Year-end Bundled Bank Balance Shortfall Requirement PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 85 Washington Clean Energy Transformation Act Washington’s Clean Energy Transformation Act (CETA) legislation establishes specific targets for utilities serving customers in Washington including: • By 2025, utilities remove coal-fueled generation from Washington’s allocation of electricity;1 • By 2030, Washington retail sales are carbon-neutral; • By 2045, Washington’s retail sales are 100 percent renewable and non-carbon-emitting. In the 2021 IRP, resources required to achieve compliance and meet targets in 2030 and 2045 were identified. These resource additions are not re-evaluated in the 2021 IRP Update, which is not a Clean Energy Implementation Plan Update (CEIP) and is not a Washington requirement. Instead, the same CETA resource considerations made in the 2021 IRP are included in the 2021 IRP Update, with adjustments made only to the extent necessary to align with changes in the updated portfolio. The two changes layered into the 2021 IRP Update portfolio are 1) the inclusion of incremental demand-side management resources specific to Washington identified from the P02- SCGHG portfolio in the 2021 IRP, and 2) in 2029, the creation of a hybrid Washington-situs assigned 160 MW Yakima resource that includes wind collocated with the solar and storage resource. This Washington-situs assigned resource maximizes usage of transmission interconnection availability at this location, and as a result is added in 2029 rather than 2030, to align with the one-year acceleration of Yakima transmission included as part of the least-cost least- risk selection of transmission upgrades. As previously noted, in the 2021 IRP Update preferred portfolio, increased system load drives the acceleration of 300 MW of new transmission interconnection into the front 10 years, as well as increased energy efficiency and other portfolio shifts when compared to the 2021 IRP preferred portfolio. The added renewables and system dispatch in the ST model, partly offset by the loss of two 2020AS RFP resources, contributes to reducing the cost of the previously identified CETA portfolio additions relative to the updated base portfolio. Although higher load increases PVRR across all cases, relative to the base case, CETA portfolio costs are reduced from $164 million to $122 million on a risk adjusted PVRR(d) basis. Bearing in mind that PVRR(d) is not the measure of CETA incremental costs, the CETA portfolio in the 2021 RP Update is $42 million less costly than in the 2021 IRP on a risk-adjusted PVRR(d) basis. Table 6.7 summarizes the PVRR(d) of the 2021 IRP Update preferred portfolio, including CETA resource, relative to the Base portfolio under a range of different price-policy scenarios. 1 RCW 19.405.030(1)(a) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 86 Table 6.7 – PVRR(d) of the 2021 IRP Update Portfolio Relative to the Base Portfolio Under Varying Price-Policy Scenarios While a full assessment of incremental costs as calculated in the Washington Clean Energy Implementation Plan is not contemplated here, this comparison is informative as PacifiCorp’s CETA Progress Report is developed to be filed January 1, 2023, ahead of the March 31, 2023, filing of the 2023 IRP. Figure 6.14 reports updated CETA interim targets assuming the same compliance resources assumed in both the 2021 IRP and the CEIP, prior to alternative compliance via unbundled REC purchases. In the 2021 IRP Update, PacifiCorp achieves 100 percent compliance with the 2030 and 2045 CETA standard with lower reliance on alternative compliance through the purchase of unbundled RECs. While CO2 emissions are higher by roughly 3 percent over the planning period, Washington has no coal generation in its energy portfolio from 2025 forward, and therefore the projection to meeting CETA requirements is largely unaffected.   ST PVRR ($million) ST PVRR plus 5% of 95th Stochastic ($million) Energy Not Served as a Percentage of Load (%) CO2 emissions (Mtons) Base MM $26,740 $27,167 0.0056%420 Base LN $23,367 $23,732 0.0059%460 Base HH $29,946 $30,311 0.0056%386 2021 IRP Update CETA MM $26,866 $27,289 0.0056%419 2021 IRP Update CETA LN $23,533 $23,899 0.0059%460 2021 IRP Update CETA HH $30,045 $30,410 0.0056%385 Change from P02-MM-MM $126 $122 0.0000%(1) Change from P02-MM-LN $167 $167 0.0000%(0) Change from P02-MM-HH $99 $99 0.0000%(1) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 87 Figure 6.14 - 2021 IRP Update Interim Targets Oregon Clean Energy Plan The 2021 IRP Update preferred portfolio of resources, similar to the 2021 IRP preferred portfolio, anticipates the high-level environmental objectives of Oregon’s Clean Energy Plan (CEP), which was passed by the Oregon legislature in 2021 in House Bill 2021, through the procurement of renewable and non-emitting resources. CEP provisions are not modeled in the 2021 IRP Update; however, PacifiCorp is actively engaged with the Public Utility Commission of Oregon’s rulemaking efforts in this regard and is in the process of developing its public engagement and planning. The CEP will be further considered and discussed in the 2023 IRP development cycle. Additional information regarding the CEP is included in Chapter 3 – Planning Environment. Projected Energy Mix Figure 6.15 how PacifiCorp’s system energy mix is projected to change over time. In developing these figures, purchased power is reported in identifiable resource categories where possible. Energy mix figures are based upon preferred portfolio outcomes in the long-term (LT) model. Renewable capacity and generation reflect categorization by technology type and not disposition of renewable energy attributes for regulatory compliance requirements.2 On an energy basis, coal 2The projected PacifiCorp 2021 IRP preferred portfolio “energy mix” is based on energy production and not resource capability, capacity or delivered energy. All or some of the renewable energy attributes associated with wind, biomass, geothermal and qualifying hydro facilities in PacifiCorp’s energy mix may be: (a) used in future PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 88 generation drops to 25 percent by 2028, falls to 10 percent by 2032, and declines to only 2 percent by the end of the planning period. Reduced energy from coal is offset primarily by increased energy from renewable and storage resources, nuclear resources, DSM resources, and to a smaller extent later in the plan, non-emitting peaker resources. Figure 6.15 – Projected Energy Mix with 2021 IRP Update Preferred Portfolio Resources Additional Studies In addition to the 2021 IRP Update preferred portfolio, PacifiCorp developed key variants of the updated preferred portfolio, focusing on three variant studies from the 2021 IRP which address large transmission projects and significant volumes of associated resources. The economics of these studies further supports their value in the 2021 IRP Update preferred portfolio as the least- cost, least-risk portfolio. In addition, PacifiCorp examined one regional haze sensitivity. The variant portfolios are summarized in the Table 6.8. Each variant portfolio is aligned with a P02-MM variant portfolio from the 2021 IRP, updated here to assess the impacts of assumption updates since the filing of the 2021 IRP. years to comply with renewable portfolio standards or other regulatory requirements; (b) sold to third parties in the form of renewable energy credits or other environmental commodities; or (c) excluded from energy purchased. PacifiCorp’s 2021 IRP preferred portfolio energy mix includes owned resources and purchases from third parties. 50%46%43%43% 31%27%26%21%18%17%14%10%10%8%8%8%8%3%3%2% 13%15%18%14% 15%13%14% 14%13%13%13%13%12%13%13%13%12% 11%11%10% 5%7%5%5% 5% 4%4% 4%4%4%4%4%4%4%4%3%3% 3%3%3% 4.0%3.9%3.8%3.6%3.4%3.4%3.3%3.3%3.3%3.2%8.2%8.2%7.6% 1.1% 1.9%1.8%1.6%3.1%2.9%3.2%4.0%4.1%4.6%4.8%4.8%5.0%4.9%4.9%5.7% 24%24%25%28% 40%45%44%45%46%48%50%54%54%53%53%52%53%53%53%52% 2%3%4%4%5%6%6%7%7%7%8%8%9%9%9%10%10%10% 1.9%1.9%1.8%1.8%1.5%1.3%1.4%1.4%1.5%1.4%1.5%1.4%1.4%1.4%1.4%1.4%1.3%1.3%1.3%1.3% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Coal Gas Existing Purchases Hydroelectric Nuclear Storage Renewable Energy Efficiency Demand Response Non-Emitting Peaker Front Office Transactions PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 89 Table 6.8 – Base Case Variant Portfolios1, 2 1 – The Base case in the 2021 IRP Update is equivalent the P02-MM case from the 2021 IRP in that it is the least-cost least-risk portfolio for the entire system prior to small additions made for Washington CETA compliance. 2- In the 2021 IRP, the No B2H case equivalent was referred to as P02b – No B2H; the No GWS case equivalent was referred to as P02c – No GWS; the No RFP case equivalent was referred to as P02c – No RFP Table 6.9 provides a cost and risk summary of the variant portfolios compared to the Base case, which is the least-cost least-risk portfolio before the addition of CETA-compliant Washington demand response and the Yakima 160 MW hybrid renewable resource. Table 6.9 – Cost and Risk Summary of Variant Portfolios Boardman-to-Hemingway Variant (No B2H) The B2H transmission line provides more flexibility and increased load-serving capability on the 500-kV transmission system into the central Oregon load pocket. In the case where the Boardman to Hemingway (B2H) transmission line and associated renewable resources is excluded from consideration, the portfolio responds by replacing 200 MW of wind in the Willamette Valley area with 200 MW of standalone storage in 2026. The 2026 removal of wind in favor of storage is accompanied by a 41 aMW increase in front office transactions. In 2030, 207 MW of Solar plus Storage is removed relative to the Base portfolio, offset by an additional 87 aMW increase in front office transactions. Figure 6.16 shows the cumulative (at left) and incremental (at right) portfolio changes when the B2H transmission line is eliminated from the Base portfolio. A positive value indicates an increase Case Description No B2H Excludes Boardman-to-Hemingway transmission segment No GWS Excludes the Energy Gateway South transmission segment No RFP Excludes 2020 All-Source Request for Proposals Final Shortlist and the Energy Gateway South transmission segment 21 IRP Update Base 26,740 27,167 -420 $2,594 3.9 0.005647% 21 IRP Update No B2H 27,154 27,607 439 423 $2,625 3.9 0.005648% 21 IRP Update No GWS 27,010 27,562 395 451 $3,000 4.3 0.006117% 21 IRP Update No RFP 28,415 29,084 1,916 499 $3,404 35.6 0.051194% 2021 to 2040 Vintage Study Name ST PVRR ($million) ST PVRR plus 5% of 95th Stochastic ($million) Risk Adjusted PVRR(d) ($million) CO2 emissions (Mtons) CO2 emissions cost ($million) Avg Annual Energy Not Served plus Reserve Deficiency (GWh) Energy Not Served as a Percentage of Load (%) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 90 in resources and a negative value indicates a decrease in resources when the transmission line is eliminated. Figure 6.16 – Increase/(Decrease) in Proxy Resources when the B2H Transmission Line is Eliminated from the Base portfolio Through 2040, the risk-adjusted PVRR(d) of the portfolio without the B2H transmission line is $439 million higher cost than the Base portfolio. This substantial outcome is comparable to the $453 million higher cost PVRR(d) seen in the 2021 IRP. Relative to the Base case, the No B2H case is also slightly less reliable as measured by the energy not served as a percentage of load and reports 2.7 million tons of higher CO2 emissions. This analysis assumes that 725 MW of incremental 4-hour battery resources and other transmission upgrades would also be needed in southern Oregon if the B2H transmission line is not built. Transmission cost savings reflect the fact that these investments would be avoided if B2H is built. Figure 6.17 - Increase/(Decrease) in System Costs when the B2H Transmission Line is Eliminated from the Base Portfolio Table 6.10 summarizes the PVRR(d) of the No B2H portfolio relative to the Base portfolio under a range of different price-policy scenarios. Eliminating the B2H transmission line increases the ST PVRR and the risk-adjusted PVRR for all price-policy scenarios, Removal of B2H also results in higher emissions. Note, that both portfolios, as measured by ENS results, are very reliable among all price-policy scenarios. While the cost increase from B2H in the LN price-policy scenario is low relative to other price-policy scenarios, it is more likely than not that there will be some form of policy that will impute a cost on greenhouse gas emissions. It is also unlikely that gas prices will -500 0 500 In s t a l l e d M W Cumulative Changes Coal Gas ContractsQFHydroNuclearHydro Storage Battery Solar Solar+Storage Wind Wind+StorageGeothermalEnergy Efficiency Demand ResponseNon-Emitting Peaker Converted Gas -500 0 500 Ca p a c i t y B u i l t M W Incremental Portfolio Changes Coal Gas Contracts QF Hydro Nuclear Hydro Storage Battery Solar Solar+Storage Wind Wind+Storage Geothermal Energy Efficiency Demand Response Non-Emitting Peaker Converted Gas ($100) $0 $100 $200 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 $ m i l l i o n s Annual Change in Cost by Line Item Coal & Gas Fixed Coal & Gas Variable Proxy Resource Costs Emissions Net Market Transactions Transmission $414 $0 $50 $100 $150 $200 $250 $300 $350 $400 $450 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Net Difference In Total System Cost Net Cost/(Benefit)Cumulative PVRR(d) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 91 remain low for decades to come. In aggregate, these results support the inclusion of the B2H transmission line in the 2021 IRP Update preferred portfolio. Table 6.10 – PVRR(d) of the No B2H Portfolio Relative to the Base Portfolio Under Varying Price-Policy Scenarios Energy Gateway South and Sub-Segment D.1 Variant (No GWS) The No GWS portfolio is a variant of the Base portfolio that eliminates the Energy Gateway South and D.1 transmission lines. Because wind bids selected to the 2020AS RFP final shortlist that are located in eastern Wyoming cannot interconnect without these two transmission lines,3 these resources are also eliminated from the No GWS portfolio. When GWS and D.1 transmission upgrades are excluded from consideration in the modeling, resource shifts are more significant than in the Boardman to Hemingway exclusion, as Energy Gateway South supports 1,641 MW of renewable resources which are no longer eligible to come online in 2025. An additional 289 MW of Wyoming East wind relying on GWS interconnection will no longer be built in years 2029 and 2030. To meet reliability, the model replaces 100 MW of Willamette Valley wind with 100 MW of standalone battery in 2026. Additionally, 500 MW of wind and standalone battery is removed from the Dave Johnson brownfield site to allow for the inclusion of a 500 MW advanced nuclear project in 2030. Figure 6.18 shows the cumulative (at left) and incremental (at right) portfolio changes when the GWS and D.1 transmission line are eliminated from the Base portfolio. A positive value indicates an increase in resources and a negative value indicates a decrease in resources when the transmission lines are eliminated. 3 Examination of this variant focuses on the estimated impacts to resource procurement, market purchases, and system costs, but ignores the elimination of GWS and D.1 transmission lines would interfere with PacifiCorp transmission’s ability to provide nearly 2,500 MW of requests for transmission and interconnection service governed by multiple FERC-jurisdictional executed contracts.  PVRR ($m) ST PVRR + 5% of 95th Stochastic ($m) ENS Average % of Load CO2 Emissions 2021-2040 (Million Tons) Base MM $26,740 $27,167 0.0056%420 Base LN $23,367 $23,732 0.0059%460 Base HH $29,946 $30,311 0.0056%386 No B2H MM $27,154 $27,607 0.0056%423 No B2H LN $23,514 $23,797 0.0059%462 No B2H HH $30,394 $31,007 0.0056%392 Change from Base MM $414 $439 0.0000%3 Change from Base LN $148 $65 0.0000%2 Change from Base HH $448 $696 0.0000%6 PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 92 Figure 6.18 – Increase/(Decrease) in Proxy Resources when the GWS and D.1 Transmission Lines are Eliminated from the Base portfolio The removal of GWS and associated RFP wind resources results in a cost increase to the system of $395 million on a risk-adjusted PVRR(d) basis. This is $135 million more in relative costs than measured in the 2021 IRP variant P02c. The relative increase in the value of GWS compared to the 2021 IRP is primarily driven by higher load, increasing the value of the renewables enabled by GWS transmission. Cost increases without GWS stem from higher thermal generation and emission costs, and market purchases, which are more expensive than transmission plus low cost renewables. Market purchases increase by 134 aMW. Without GWS and D.1, emissions from PacifiCorp’s fossil-fueled resources increase by 7 percent, and energy not served increase by more than 8 percent. These factors further substantiate the benefits of GWS and D.1, which lower portfolio emissions and provide system reliability. Figure 6.19 – Increase/(Decrease) in System Costs when the GWS and D.1 Transmission Lines are Eliminated from the Base Portfolio Table 6.11 summarizes the PVRR(d) of the No GWS portfolio relative to the Base portfolio under a range of different price-policy scenarios. System costs increase when GWS and D.1 are removed from the portfolio in MM, and HH price-policy scenarios. Conversely, costs decrease in the LN price-policy scenario. Without GWS and D.1, emissions from PacifiCorp’s fossil-fueled resources increase considerably—ranging from 6.9% in the MM price-policy scenario to 9.7% in the HH price-policy scenario. As discussed earlier, it is more likely than not that there will be some form of policy action taken to impute a cost or penalty on greenhouse gas emissions. It is also unlikely gas prices will be suppressed for many decades to come, as assumed in the LN price-policy -4000 -2000 0 2000 In s t a l l e d M W Cumulative Changes Coal Gas Contracts QF Hydro Nuclear Hydro Storage Battery SolarSolar+Storage Wind Wind+StorageGeothermalEnergy Efficiency Demand ResponseNon-Emitting Peaker Converted Gas -2000 0 2000 Ca p a c i t y B u i l t M W Incremental Portfolio Changes Coal Gas ContractsQFHydroNuclearHydro Storage Battery SolarSolar+Storage Wind Wind+StorageGeothermalEnergy Efficiency Demand ResponseNon-Emitting Peaker Converted Gas ($400) ($300) ($200) ($100) $0 $100 $200 $300 $400 $500 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 $ m i l l i o n s Annual Change in Cost by Line Item Coal & Gas Fixed Coal & Gas Variable Proxy Resource Costs Emissions Net Market Transactions Transmission $271 ($50) $0 $50 $100 $150 $200 $250 $300 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Net Difference In Total System Cost Net Cost/(Benefit)Cumulative PVRR(d) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 93 scenario. Further, cost-and-risk results indicate that there is a tremendous opportunity cost of not building these transmission lines should policies develop that impose costs on greenhouse gas emissions. This is seen with the disproportionate increase in costs under MM and HH price-policy scenarios relative to the size of cost reductions in the unlikely LN price-policy scenario. Considering the removal of GWS and D.1 increases system costs in the MM and HH price-policy scenarios, increases emissions and associated costs and risks, and significantly increases market- reliance risk, this analysis supports including GWS, D.1, and the associated 2020AS RFP wind resources in the 2021 IRP Update preferred portfolio. Table 6.11 – PVRR(d) of the No GWS Portfolio Relative to the Base Portfolio Under Varying Price-Policy Scenarios 2020AS RFP Variant (No RFP) The No RFP portfolio is a variant of the Base portfolio that eliminates all 2020AS RFP resources, including the GWS and D.1 transmission lines. Compared to either the No B2H or No GWS variants, resource changes are more drastic with the removal of all RFP-related transmission and resources, where more than 3,400 MW of RFP renewable resources are excluded. As a result, 100 MW of Willamette Valley wind is replaced by 100 MW of standalone battery in 2026. At Dave Johnson, 500 MW of advanced Nuclear in 2030 replaces 100 MW of wind and 400 MW of standalone battery. In Utah, 207 MW of Solar plus Storage is replaced with 207 MW of non- emitting peaker. Figure 6.20 shows the cumulative (at left) and incremental (at right) portfolio changes when the 2020AS RFP resources are eliminated from the Base portfolio. A positive value indicates an increase in resources and a negative value indicates a decrease in resources when the 2020AS RFP resources and the GWS and D.1 transmission lines are eliminated.   ST PVRR ($million) ST PVRR plus 5% of 95th Stochastic ($million) Energy Not Served as a Percentage of Load (%) CO2 emissions (Mtons) Base MM $26,740 $27,167 0.0056%420 Base LN $23,367 $23,732 0.0059%460 Base HH $29,946 $30,311 0.0056%386 No GWS MM $27,010 $27,562 0.0061%451 No GWS LN $22,814 $23,162 0.0063%498 No GWS HH $30,945 $31,687 0.0060%427 Change from Base MM $271 $395 0.0005%31 Change from Base LN ($553)($570)0.0003%38 Change from Base HH $999 $1,375 0.0004%41 PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 94 Figure 6.20 – Increase/(Decrease) in Proxy Resources when 2020AS RFP Resources are Eliminated from the Base portfolio The removal of all RFP renewables increases costs to the system by $1.9 billion on a risk-adjusted PVRR(d) basis. This is $651 million more in relative costs than measured in the 2021 IRP variant P02d. The relative increase in the value of the RFP resources including GWS and D.1 is primarily driven by higher load, which increases the value of the additional renewables. This cost increase is primarily comprised of higher thermal generation and emission costs and heavy market reliance. Market purchases increase by 282 aMW. Without RFP bids and the GWS and D.1 projects, emissions from PacifiCorp’s fossil-fueled resources increase by nearly 19 percent, and energy not served increases by more than eight-fold. Figure 6.21 – Increase/(Decrease) in System Costs when RFP Projects and GWS and D.1 Transmission Lines are Eliminated from the Base Portfolio Table 6.12 summarizes the PVRR(d) of the No RFP portfolio relative to the Base portfolio under a range of different price-policy scenarios. System costs increase significantly when 2020AS RFP resources are removed from the portfolio in all three price-policy scenarios. Without the RFP resources, emissions from PacifiCorp’s fossil-fueled resources increase considerably—ranging from 15.8% in the MM price-policy scenario to 17.4% in the HH price-policy scenario. As discussed earlier, it is more likely than not that there will be policy actions taken to impute a cost or penalty on greenhouse gas emissions. It is also unlikely that gas prices will be suppressed for many decades to come, as assumed in the LN price-policy scenario. Further, cost-and-risk results indicate that there is a tremendous opportunity cost of not pursuing the RFP resources along with the associated investments in the GWS and D.1 transmission lines should policies develop that -5000 0 5000 In s t a l l e d M W Cumulative Changes Coal Gas Contracts QF Hydro NuclearHydro Storage Battery Solar Solar+Storage Wind Wind+Storage Geothermal Energy Efficiency Demand ResponseNon-Emitting Peaker Converted Gas -4000 -2000 0 2000 Ca p a c i t y B u i l t M W Incremental Portfolio Changes Coal Gas Contracts QF Hydro Nuclear Hydro Storage Battery SolarSolar+Storage Wind Wind+Storage Geothermal Energy Efficiency Demand Response Non-Emitting Peaker Converted Gas ($600)($500)($400)($300)($200)($100)$0$100$200$300$400$500$600$700$800$900$1,000 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 $ m i l l i o n s Annual Change in Cost by Line Item Coal & Gas Fixed Coal & Gas Variable Proxy Resource Costs Emissions Net Market Transactions Transmission $1,676 ($200) $0 $200 $400 $600 $800 $1,000 $1,200 $1,400 $1,600 $1,800 20 2 1 20 2 2 20 2 3 20 2 4 20 2 5 20 2 6 20 2 7 20 2 8 20 2 9 20 3 0 20 3 1 20 3 2 20 3 3 20 3 4 20 3 5 20 3 6 20 3 7 20 3 8 20 3 9 20 4 0 Net Difference In Total System Cost Net Cost/(Benefit)Cumulative PVRR(d) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 95 impose costs on greenhouse gas emissions. This is seen with the disproportionate increase in costs under MM and HH price-policy scenarios relative to the size of cost increase in the unlikely LN price-policy scenario. Further, each of cases that remove 2020AS RFP resources show a more notable decline in reliability, as measured by the ENS metric. Considering the removal of 2020AS RFP bids and the associated investment in the GWS and D.1 transmission lines increases system costs among all price-policy scenarios, significantly increases emissions and associated costs, and significantly increases market-reliance risk, this analysis supports including 2020AS RFP resources in the 2021 IRP Update preferred portfolio. Table 6.12 – PVRR(d) of the No RFP Portfolio Relative to the Base Portfolio Under Varying Price-Policy Scenarios Regional Haze Hunter-Huntington Sensitivity Table 6.13 reports the cost and risk outcome of the regional haze sensitivity. Additional discussion of Regional Haze under the EPA’s rule finalized in 1999 is presented in Chapter 3 – The Planning Environment. The study is designed to look at reducing nitrogen oxide starting in 2022 under the State of Utah’s proposed state implementation plan for the second planning period for the Hunter and Huntington coal plants. Decreasing nitrogen oxide emission limits are implemented using a “reasonable progress emission limits” (RPEL) approach that will require changes to how these coal plants operate but avoids installation of costly emission control equipment. Table 6.13 – Cost and Risk Summary of Regional Haze Hunter-Huntington Sensitivity   ST PVRR ($million) ST PVRR plus 5% of 95th Stochastic ($million) Energy Not Served as a Percentage of Load (%) CO2 emissions (Mtons) Base MM $26,740 $27,167 0.0056%420 Base LN $23,367 $23,732 0.0059%460 Base HH $29,946 $30,311 0.0056%386 No RFP MM $28,415 $29,084 0.0512%499 No RFP LN $23,530 $23,958 0.0589%535 No RFP HH $33,056 $33,946 0.0542%467 Change from Base MM $1,676 $1,916 0.0455%79 Change from Base LN $164 $226 0.0529%75 Change from Base HH $3,110 $3,634 0.0486%81 21 IRP Update Base 26,740 27,167 -420 $2,594 3.9 0.005647% 21 IRP Update Regional Haze Hunter-Huntington 26,756 27,184 16 418 $2,597 3.9 0.005663% 2021 to 2040 Vintage Study Name ST PVRR ($million) ST PVRR plus 5% of 95th Stochastic ($million) Risk Adjusted PVRR(d) ($million) CO2 emissions (Mtons) CO2 emissions cost ($million) Avg Annual Energy Not Served plus Reserve Deficiency (GWh) Energy Not Served as a Percentage of Load (%) PACIFICORP – 2021 IRP UPDATE CHAPTER 6 – PORTFOLIO DEVELOPMENT 96 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 97 CHAPTER 7 – ACTION PLAN STATUS UPDATE This chapter provides an update to the action items listed in the Action Plan of PacifiCorp’s 2021 IRP. The status for all action items is provided in Table 7.1 below. Table 7.1 – 2021 IRP Action Plan Status Update Action Item 1. Existing Resource Actions Status 1a Colstrip Units 3 and 4: • PacifiCorp will continue to work closely with co- owners to seek the most cost-effective path forward toward the 2021 IRP preferred portfolio target exit date of December 31, 2025. • The Company continues to work with co-owners to develop the most cost-effective path toward an exit from the project. 1b Craig Unit 1: • PacifiCorp will continue to work closely with co- owners to seek the most cost-effective path forward toward the 2021 IRP preferred portfolio target exit date of December 31, 2025. • The Company continues to work with co-owners to develop the most cost-effective path toward an exit from the project. 1b Naughton Units 1 and 2: • PacifiCorp will initiate the process of retiring Naughton Units 1-2 by the end of December 2025, including completion of all required regulatory notices and filings. • By the end of Q2 2023, PacifiCorp will confirm transmission system reliability assessment and year- end 2025 retirement economics in 2023 IRP filing. • By the end of Q4 2023, PacifiCorp will initiate the process with the Wyoming Public Service Commission for approval of a reverse request for • PacifiCorp is on track to complete required regulatory notices and filings to process the retirements of Naughton units 1 and 2. • PacifiCorp’s Integrate Resource Planning group has initiated gathering updated assumptions and stakeholder feedback for the 2023 IRP. • PacifiCorp is on track to initiate the approval process of a reverse request for proposals for a potential sale of Naughton Units 1 and 2. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 98 (1b) proposals for a potential sale of Naughton Units 1 and 2. • By the end of Q4 2023, PacifiCorp will administer termination, amendment, or close-out of existing permits, contracts, and other agreements. • PacifiCorp is on track to close-out existing environmental permits and coal agreements for Naughton Units 1 and 2. 1c Jim Bridger Units 1 and 2 Gas Conversion: • PacifiCorp will initiate the process of ending coal- fueled operations and seeking permitting for a natural-gas conversion by 2024, including completion of all required regulatory notices and filings. • By the end of Q2 2022, PacifiCorp will finalize an employee transition plan. • By the end of Q2 2022, PacifiCorp will develop a community action plan in coordination with community leaders. • By the end of Q4 2023, PacifiCorp will administer termination, amendment, or close-out of existing permits, contracts, and other agreements. • By the end of Q4, 2023, PacifiCorp will remove units 1 and 2 from Washington’s allocation of electricity. • PacifiCorp plans to submit a permit application to the Wyoming Department of Environmental Quality in Q2 2022 for the conversion of JB Units 1 &2 to natural gas by 2024 and is on track to complete required regulatory notices and filings. • An Impacted Employee Transition Plan was created and finalized in 2020 and will be updated as needed. • In 2020, PacifiCorp assigned a Certified Economic Developer (CEcD) to work with impacted communities, state and federal agencies and state associations to identify economic diversification funding and resources. In May 2021, the Company provided an update to the WPSC and will provide another in April 2022. • PacifiCorp is on track to remove units 1 and 2 from Washington’s allocation of electricity. 1d Carbon Capture, Utilization, and Sequestration/Wyoming House Bill 200 Compliance: • PacifiCorp issued a carbon capture, utilization, and sequestration (CCUS) request for expression of interest (REOI) on June 29, 2021. PacifiCorp will complete the 2021 CCUS REOI process and utilize any new relevant information. Additional model sensitivities will be run accordingly. • PacifiCorp issued a carbon capture, utilization, and sequestration (CCUS) request for expression of interest (REOI) on June 29, 2021. PacifiCorp completed the 2021 CCUS REOI process and a third party evaluated the responses. • PacifiCorp will issue two CCUS Requests for Proposals (RFP) in 2022. • A completed CCUS Front End Engineering & Design Study (FEED Study) based on a new CCUS technology was submitted to PacifiCorp in July 2021 PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 99 (1d) • PacifiCorp will issue a CCUS Request for Proposals (RFP) in 2022. The 2021 CCUS REOI responses will inform the scope of the CCUS RFP. • A completed CCUS Front End Engineering & Design Study (FEED Study) based on a new CCUS technology was submitted to PacifiCorp in July 2021 for Dave Johnston Unit 2. Third-party review of the FEED Study will be completed by Q1 2022, and model sensitivities will subsequently be run as needed, with FEED Study assumptions and inputs as appropriate. • Subject to finalization of rules by the Wyoming Public Service Commission (WPSC) to implement House Bill 200 (HB 200), the Wyoming Low Carbon Energy Standard (anticipated by Q4 2021), by March 31, 2022, PacifiCorp will file with the WPSC an initial CCUS application to establish intermediate CCUS standards and requirements. • Subject to finalization of rules by the WPSC to implement HB 200, the Wyoming Low Carbon Energy Standard (anticipated by Q4 2021), PacifiCorp will submit for WPSC approval a final plan with its proposed energy portfolio standard for dispatchable and reliable low-carbon electricity, its plan for achieving the standard, and a target date of no later than July 1, 2030. for Dave Johnston Unit 2. Third-party review of the FEED Study was completed in February 2022. Model sensitivities will be run in the 2023 IRP with the FEED Study assumptions and inputs as appropriate. • PacifiCorp filed with the Wyoming Public Service Commission (WPSC), an initial application to establish intermediate CCUS standards and requirements on March 31, 2022, as required under Wyoming House Bill 200. • PacifiCorp will submit a final plan with its proposed energy portfolio standard for dispatchable and reliable low-carbon electricity by March 31, 2023. The final plan will be submitted for WPSC approval and will detail the Company’s plan for achieving the standard, by July 1, 2030. 1e Regional Haze Compliance: • Following the resolution of first planning period regional haze compliance disputes, and the submission of second planning period regional haze state implementation plans, PacifiCorp will evaluate and model any emission control retrofits, emission • PacifiCorp is working with parties to resolve regional haze first planning period disputes, and has engaged with states and commented on proposed second planning period implementation plans. No second planning periods requirements have been finalized to date. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 100 (1e) limitations, or utilization reductions that are required for coal units. • PacifiCorp will continue to engage with the Environmental Protection Agency, state agencies, and stakeholders to achieve second planning period regional haze compliance outcomes that improve Class I visibility, provide environmental benefits, and are cost effective. • PacifiCorp is on track in engaging with the Environmental Protection Agency, state agencies, and stakeholders relating to second planning period regional haze compliance. Action Item 2. New Resource Actions Status 2a Customer Preference Request for Proposals: • Consistent with Utah Community Renewable Energy Act, PacifiCorp continues to work with eligible communities to develop program to achieve goal of being net 100 percent renewable by 2030; PacifiCorp anticipates filing an application for approval of the program with the Utah Public Service Commission in 2022, which may necessitate issuance of a request for proposals to procure resources within the action plan window. • The Company and the eligible communities are meeting monthly to discuss program design. Subject to finalization of the program details, PacifiCorp anticipates filing an application for approval of the program with the Utah Public Service Commission in 2022. 2b • Acquisition and Repowering of Foote Creek II-IV and Rock River I: • In Q3 2021, PacifiCorp will pursue necessary regulatory approvals to authorize the acquisition and repowering of Foote Creek II-IV in order to issue repowering contracts in Q1 2022 in support of a late 2023 in-service date. • In Q1 2022, PacifiCorp will pursue necessary regulatory approvals to authorize the acquisition and repowering of Rock River I following the expiration of • PacifiCorp is pursuing necessary regulatory approvals to authorize the acquisition and repowering of Foote Creek II-IV in order to commence construction in late Q2 2022 in support of a late 2023 in-service date. PacifiCorp filed a certificate of public convenience and necessity (CPCN) application with the WPSC for Foote Creek II-IV in October 2021. A decision from the WPSC is expected sometime in Q2 2022. • In Q1 2022, PacifiCorp initiated necessary regulatory approvals to authorize the acquisition and repowering PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 101 (2b) the existing power purchase agreement in order to issue repowering contracts in Q3 2022 to support a late 2024 in-service date. of Rock River I in order to issue repowering contracts in Q3 2022 to support a late 2024 in-service date. PacifiCorp filed a CPCN application with the WPSC for Rock River I in March 2022 and requested a decision in Q3 2022. 2c NatriumTM Demonstration Project: • PacifiCorp will continue to monitor key TerraPower milestones for development and will make regulatory filings, as applicable. • By the end of 2022, PacifiCorp will finalize commercial agreements for the NatriumTM project. • Q1 2022, PacifiCorp will develop a community action plan in coordination with community leaders. • By 2025, PacifiCorp will begin training operators. • PacifiCorp will continue to monitor key TerraPower milestones for development and will make regulatory filings, as applicable, including, but not limited to, a request for the Oregon Public Utility Commission to explicitly acknowledge an alternative acquisition method consistent with OAR 860-089-0100(3)(c), and a request for a waiver of a solicitation for a significant energy resource decision consistent with Utah statute 54-17-501. • The Company continues to monitor TerraPower’s development of the NatriumTM project. The Company and TerraPower are discussing potential commercial agreement structures. The agreement is expected to contain numerous conditions precedent, including the Company obtaining required regulatory approvals and/or waivers, project offramps and performance related metrics which must be met for the PacifiCorp to move forward with acquisition of the NatriumTM project to provide protections to customers. • PacifiCorp will supplement TerraPower in stakeholder outreach and coordination with community leaders in PacifiCorp’s service territory. • PacifiCorp is evaluating training schedules, positions, and requirements for the NatriumTM project. • See response to 2c bullet 1. No regulatory filings are required at this time. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 102 2d 2022 All-Source Request for Proposals: • PacifiCorp will issue an all-source Request for Proposals (RFP) to procure resources that can achieve commercial operations by the end of December 2026. • In September 2021, PacifiCorp will notify the Public Utility Commission of Oregon, the Public Service Commission of Utah, and the Washington Utilities and Transportation Commission, of PacifiCorp’s need for an independent evaluator. • In October 2021, PacifiCorp will file a draft all-source RFP with applicable state utility commissions. • In January 2022, PacifiCorp expects to receive approval of the all-source RFP from applicable state utility commissions and issue the RFP to the market. • In Q2 2022, PacifiCorp will identify an initial shortlist in advance of annual Cluster Request Window. • In Q1 2023, PacifiCorp will identify a final shortlist from the all-source RFP, and file for approval of the final shortlist in Oregon, file, certificate of public convenience and necessity (CPCN) applications, as applicable. • By Q2 2023 PacifiCorp will execute definitive agreements with winning bids from the all-source RFP. • By Q4 2025-2026, winning bids from the all-source RFP are expected to achieve commercial operation. Resources must have commercial operation date of December 31, 2026, or earlier. • PacifiCorp will issue an all-source Request for Proposals (RFP) to procure resources that can achieve commercial operations by the end of December 2027. • In Q4 2021, PacifiCorp notified the Public Utility Commission of Oregon, the Public Service Commission of Utah, and the Washington Utilities and Transportation Commission, of PacifiCorp’s need for an independent evaluator. • In December 2021 and January 2022, PacifiCorp filed a draft all-source RFP with applicable state utility commissions. • In March 2022, PacifiCorp received approval from the Washington Utilities and Transportation Commission and in April, PacifiCorp expects to receive approval of the all-source RFP from the Public Utility Commission of Oregon, the Public Service Commission of Utah and issue the RFP to the market. • In Q2 2023, PacifiCorp will identify a final shortlist from the all-source RFP, and in Q3 2023 file for approval of the final shortlist in Oregon, file, certificate of public convenience and necessity (CPCN) applications, as applicable. • By Q1 2024 PacifiCorp will execute definitive agreements with winning bids from the all-source RFP. • By Q4 2027, winning bids from the all-source RFP are expected to achieve commercial operation. Resources must have commercial operation date of December 31, 2027, or earlier. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 103 2e 2020 All-Source Request for Proposals: • PacifiCorp filed for approval of the final shortlist in Oregon in June 2021. • In September 2021, PacifiCorp will file CPCN applications in Wyoming, as applicable, for final shortlist. • In Q4 2021, PacifiCorp will make a filing in Utah for significant energy resources on final shortlist. • In September 2021, PacifiCorp filed CPCN applications for the Gateway South Transmission project in Wyoming, as applicable, in support of the 2020AS RFP final shortlist. • In January 2022, Rocky Mountain Power (RMP) filed an Application for Waiver to the Utah Public Service Commission (PUC) to waive the requirement that RMP obtain certain significant energy resource decisions representing five bids in the 2020AS RFP. On February 2022, the waiver, subject to certain conditions, was granted by the Utah PUC (see Docket No. 22-035-03 for further details). Action Item 3. Transmission Action Items Status 3a Energy Gateway South Segment F (Aeolus-Clover 500 kV transmission line): • By Q2 2022, obtain Utah and Wyoming Certificates of Public Convenance and Necessity. • By the end of Q1 2022, Bureau of Land Management notice to proceed to construct Energy Gateway South. • In Q3 2024, construction of Energy Gateway South is expected to be completed and placed in service. • Regulatory approval processes for certificates of public convenience and necessity in Utah and Wyoming are on track. In Utah an unopposed stipulation for the CPCN was filed February 22, 2022 and a commission order is pending. In Wyoming, hearings were completed March 2, 2022 and briefs due April 1, 2022; a decision is expected in early Q2 2022. Wyoming approval will be conditioned on obtaining all right-of-way, which is on track to be completed by the end of Q2 2022. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 104 3b Energy Gateway West, Segment D.1 (Windstar-Shirley Basin 230 kV transmission line): • By Q2 2022, obtain conditional Wyoming Certificate of Public Convenance and Necessity • By Q3 2022 complete ROW easement acquisition and option full Wyoming CPCN • In Q3 2024, construction of Energy Gateway West segment D.1 to be completed and placed in service. • The Wyoming approval process for the certificate of public convenience and necessity is on track; hearings were completed March 2, 2022 and briefs due April 1, 2022, with a decision expected in early Q2 2022. Approval will be conditioned on obtaining all right-of-way, which is on track to be completed by Q3 2022. 3c Boardman-to-Hemingway (500 kV transmission line): • Continue to support the project under the conditions of the Boardman-to-Hemingway Transmission Project (B2H) Joint Permit Funding Agreement. • Continue to participate in the development and negotiations of the construction agreement. • Continue to participate in “pre-construction” activities in support of the 2026 in-service date. • Continue negotiations for plan of service post B2H for parties to the permitting agreement. • PacifiCorp has continued to participate in the support, negotiations, planning and permitting of the Boardman-to-Hemingway 500 kV transmission line, which remains targeted for a 2026 in-service date. 3d Initiate Local Reinforcement Projects as identified with the addition of new resources per the preferred portfolio, and follow-on requests for proposal successful bids • Reinforcements have been identified. A final assessment of upgrades is pending signed agreements. 3e Continue permitting support for Gateway West segments D.3 and E. • PacifiCorp continues permitting efforts on both segments D.3 and E, maintaining the record of decision on each segment. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 105 Action Item 4. Demand-Side Management (DSM) Actions Status 4a Energy Efficiency Targets: • PacifiCorp will acquire cost-effective Class 2 DSM (energy efficiency) resources targeting annual system energy and capacity selections from the preferred portfolio as summarized below. PacifiCorp’s state- specific processes for planning for DSM acquisitions is provided in Appendix D in Volume II of the 2021 IRP. • PacifiCorp will pursue cost-effective energy efficiency resources as summarized in the table below: • PacifiCorp will pursue cost-effective Class 1 (demand response) resources targeting annual system capacity1 selections from the preferred portfolio2 as summarized in the table below: 1 Capacity impacts for demand response include both summer and winter impacts within a year. 2A portion of cost-effective demand response resources identified in the 2021 preferred portfolio are expected to be • PacifiCorp achieved the Action Plan target of 510 GWh in 2021 and the Company is on track to achieve its 2022 Class 2 DSM target. • PacifiCorp is actively working to pursue demand response resources in multiple states. The Company is currently expanding its existing programs and contracting for new demand response resources identified in the 2021 demand response RFP. In the event additional demand response resource need is identified, PacifiCorp may issue a voluntary targeted RFP outlining the specific remaining incremental resource needs, including type, location and timing. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 106 (4a) acquired through a previously issued demand response RFP soliciting resources identified in the 2019 IRP. PacifiCorp will pursue all cost-effective demand response resources identified as incremental to resources subsequently procured under the previously issued RFP in compliance with state level procurement requirements. Action Item 5. Market Purchases Status 5a Market Purchases: • Acquire short-term firm market purchases for on- peak delivery from 2021-2023 consistent with the Risk Management Policy and Energy Supply Management Front Office Procedures and Practices. These short-term firm market purchases will be acquired through multiple means: Balance of month and day-ahead brokered transactions in which the broker provides a competitive price. • Balance of month, day-ahead, and hour-ahead transactions executed through an exchange, such as the Intercontinental Exchange, in which the exchange provides a competitive price. • Prompt-month, balance-of-month, day-ahead, and hour-ahead non-brokered bi-lateral transactions. • Since the publication of the 2021 IRP action plan, PacifiCorp has continued to engage in financially beneficial transactions to support customers’ interests. Such transactions include seeking competitive pricing to acquire short-term firm purchases, execute balance of month, day-ahead and hour-ahead transactions through exchanges, and engage in prompt-month, balance-of-month, day-ahead and hour-ahead non- brokered bi-lateral transactions. PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 107 Action Item 6. Renewable Energy Credit (REC) Actions Status 6a Renewable Portfolio Standards (RPS): • PacifiCorp will pursue unbundled REC RFPs and purchases to meet its state RPS compliance requirements. • As needed, issue RFPs seeking then current-year or forward-year vintage unbundled RECs that will qualify in meeting California RPS targets through 2024. • Since October 1, 2021, PacifiCorp has purchased unbundled RECs to meet its California RPS targets through 2024. PacifiCorp will continue to evaluate the need for unbundled RECs and issue RFPs to meet its state RPS compliance requirements as needed. 6b Renewable Energy Credit Sales: • Maximize the sale of RECs that are not required to meet state RPS compliance obligations. • On October 27, 2021, PacifiCorp issued a reverse RFPs to sell RECs and completed several bilateral transactions. PacifiCorp will continue to issue reverse RFPs to maximize the sale of RECs that are not required to meet state RPS compliance obligations PACIFICORP – 2021 IRP UPDATE CHAPTER 7 – ACTION PLAN STATUS UPDATE 108 [This page is intentionally left blank] PACIFICORP – 2021 IRP UPDATE APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS 109 APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS The load forecast presented in Chapter 4 represents the data used for capacity expansion modeling and excludes load reductions from incremental energy efficiency resources (Class 2 DSM). The load forecast used in the 2021 IRP Update was produced in May 2021. The average annual energy growth rate for the 10-year period (2022 through 2031) is 1.46 percent. Relative to the load forecast prepared for the 2021 IRP, PacifiCorp’s 2031 forecasted energy requirement decreased in all jurisdictions other than Oregon and Utah, while PacifiCorp system energy requirement increased approximately 2.3 percent. Table A.1 and Table A.2 illustrate the annual load and coincident peak load forecast when not reducing load projections to account for new energy efficiency measures (Class 2 DSM).1 Table A.1 – Forecasted Annual Load Growth, 2022 through 2031 (Megawatt-hours), at Generation, pre-DSM 1 Class 2 DSM load reductions are included as resources in the System Optimizer model. Year Total OR WA CA UT WY ID 2022 61,564,330 15,225,790 4,605,340 870,230 27,635,390 9,281,340 3,946,240 2023 63,153,010 15,542,160 4,643,520 871,480 28,603,020 9,538,990 3,953,840 2024 64,661,770 16,080,310 4,681,580 874,560 29,438,980 9,627,450 3,958,890 2025 65,743,100 16,349,100 4,691,870 873,570 29,989,480 9,867,530 3,971,550 2026 65,308,270 16,677,410 4,720,470 876,030 29,123,740 9,920,230 3,990,390 2027 66,210,480 17,013,040 4,755,770 879,110 29,600,710 9,953,650 4,008,200 2028 67,345,980 17,408,920 4,810,220 884,040 30,182,810 10,027,440 4,032,550 2029 68,250,270 17,742,390 4,843,960 884,190 30,679,530 10,052,470 4,047,730 2030 69,298,260 18,122,940 4,890,370 886,080 31,248,620 10,091,160 4,059,090 2031 70,122,890 18,357,130 4,938,900 887,880 31,741,320 10,128,710 4,068,950 2022-31 1.46%2.10%0.78%0.22%1.55%0.98%0.34% Compound Annual Growth Rate PACIFICORP – 2021 IRP UPDATE APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS 110 Table A.2 - Forecasted Annual Coincident Peak Load (Megawatts) at Generation, pre- DSM Table A.3 and Table A.4 show the forecast changes relative to the 2021 IRP load forecast for loads and coincident system peak, respectively. Table A.3 – Annual Load Growth Change: 2021 IRP Update Forecast less 2021 IRP Forecast (Megawatt-hours) at Generation, pre-DSM Year Total OR WA CA UT WY ID 2022 10,561 2,429 775 140 5,201 1,231 786 2023 10,717 2,442 779 142 5,320 1,250 785 2024 10,864 2,468 782 140 5,423 1,265 786 2025 11,035 2,494 787 141 5,524 1,293 796 2026 11,027 2,516 790 141 5,481 1,298 801 2027 11,126 2,538 795 142 5,545 1,302 805 2028 11,255 2,560 799 143 5,636 1,309 808 2029 11,370 2,582 805 142 5,717 1,312 812 2030 11,487 2,603 810 142 5,800 1,317 815 2031 11,590 2,613 818 142 5,875 1,321 821 2022-31 1.04%0.81%0.60%0.10%1.36%0.79%0.49% Compound Annual Growth Rate Year Total OR WA CA UT WY ID 2022 (196,580) (180,480) 14,320 (9,030) 191,300 (186,600) (26,090) 2023 (89,980) (216,520) (12,510) (11,020) 392,640 (217,480) (25,090) 2024 210,460 (25,810) (29,060) (13,610) 646,800 (335,810) (32,050) 2025 580,840 109,590 (38,370) (15,320) 648,450 (89,470) (34,040) 2026 781,240 258,590 (40,420) (15,100) 770,820 (159,280) (33,370) 2027 1,032,080 403,790 (40,420) (13,300) 899,780 (186,400) (31,370) 2028 1,262,560 552,280 (40,180) (12,240) 989,950 (200,380) (26,870) 2029 1,481,610 705,290 (35,940) (11,180) 1,069,680 (225,750) (20,490) 2030 1,575,050 854,900 (32,730) (12,530) 1,092,870 (302,510) (24,950) 2031 1,594,240 877,130 (19,280) (11,680) 1,107,530 (336,960) (22,500) PACIFICORP – 2021 IRP UPDATE APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS 111 Table A.4 – Annual Coincident Peak Growth Change: 2021 IRP Update Forecast less 2017 IRP Forecast (Megawatts) at Generation, pre-DSM This section provides total system and state-level forecasted retail sales summaries measured at the customer meter by customer class including load reduction projections from new energy efficiency measures from the 2021 IRP Update preferred portfolio. The average annual retail sales growth rate for the 10-year period (2022 through 2031) is 0.58 percent. Table A.5 – System Annual Retail Sales Forecast 2022 through 2031 (Megawatt-hours), post-DSM Year Total OR WA CA UT WY ID 2022 26 (13) (4) (0) 42 (17) 18 2023 26 (20) (10) (0) 65 (29) 20 2024 56 (13) (14) (1) 97 (35) 21 2025 93 (6) (17) (1) 105 (9) 21 2026 160 3 (20) (1) 173 (16) 22 2027 186 11 (22) (1) 194 (19) 23 2028 212 20 (24) (0) 211 (20) 25 2029 237 30 (26) (0) 227 (23) 28 2030 248 41 (27) (0) 237 (31) 29 2031 252 42 (28) (0) 244 (35) 29 Year Residential Commercial Industrial Irrigation Lighting Total 2022 16,883,025 19,430,835 18,304,202 1,483,507 107,925 56,209,495 2023 16,880,836 20,126,970 18,576,997 1,482,501 102,792 57,170,096 2024 17,023,491 20,766,719 18,657,118 1,482,555 99,255 58,029,138 2025 17,101,849 21,036,255 18,773,837 1,482,228 96,195 58,490,363 2026 17,296,271 21,299,464 17,330,721 1,481,509 94,166 57,502,131 2027 17,526,492 21,499,322 17,278,284 1,479,999 92,587 57,876,684 2028 17,861,288 21,747,665 17,257,346 1,478,048 91,497 58,435,844 2029 18,081,010 21,871,791 17,160,525 1,475,700 89,955 58,678,981 2030 18,305,130 22,031,321 17,120,319 1,473,386 88,706 59,018,862 2031 18,546,830 22,014,167 17,088,099 1,470,631 87,515 59,207,242 2022-31 1.05%1.40%-0.76%-0.10%-2.30%0.58% System Retail Sales – Megawatt-hours (MWh) Compound Annual Growth Rate PACIFICORP – 2021 IRP UPDATE APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS 112 Table A.6– Forecasted Retail Sales Growth in Oregon, post-DSM Table A.7 – Forecasted Retail Sales Growth in Washington, post-DSM Year Residential Commercial Industrial Irrigation Lighting Total 2022 5,787,079 5,887,735 1,480,507 333,775 36,859 13,525,955 2023 5,762,694 6,066,118 1,437,047 333,504 35,996 13,635,359 2024 5,785,881 6,372,669 1,408,680 333,517 35,350 13,936,096 2025 5,796,057 6,501,134 1,401,833 333,409 34,630 14,067,063 2026 5,838,292 6,640,891 1,397,397 333,326 34,138 14,244,045 2027 5,887,806 6,778,086 1,393,803 333,013 33,759 14,426,467 2028 5,972,311 6,925,882 1,392,590 332,569 33,571 14,656,922 2029 6,036,711 7,051,309 1,389,902 332,002 33,263 14,843,186 2030 6,121,032 7,189,924 1,388,345 331,520 33,109 15,063,930 2031 6,203,383 7,201,637 1,389,462 331,062 32,998 15,158,541 2022-31 0.77%2.26%-0.70%-0.09%-1.22%1.27% Oregon Retail Sales – Megawatt-hours (MWh) Compound Annual Growth Rate Year Residential Commercial Industrial Irrigation Lighting Total 2022 1,529,078 1,563,728 854,633 160,251 3,514 4,111,204 2023 1,510,337 1,581,369 842,930 159,721 3,283 4,097,639 2024 1,504,658 1,586,702 831,049 159,603 3,220 4,085,232 2025 1,491,410 1,582,136 817,469 159,602 3,188 4,053,805 2026 1,484,929 1,577,641 809,322 159,577 3,181 4,034,651 2027 1,480,508 1,571,996 803,278 159,531 3,179 4,018,493 2028 1,483,834 1,569,934 799,933 159,466 3,189 4,016,356 2029 1,479,846 1,560,954 793,073 159,322 3,179 3,996,373 2030 1,479,029 1,559,549 789,220 159,096 3,179 3,990,074 2031 1,480,155 1,559,370 787,489 158,885 3,179 3,989,077 2022-31 -0.36%-0.03%-0.91%-0.10%-1.11%-0.33% Washington Retail Sales – Megawatt-hours (MWh) Compound Annual Growth Rate PACIFICORP – 2021 IRP UPDATE APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS 113 Table A.8 – Forecasted Retail Sales Growth in California, post-DSM Table A.9 – Forecasted Retail Sales Growth in Utah, post-DSM Year Residential Commercial Industrial Irrigation Lighting Total 2022 382,297 235,420 53,687 91,103 1,421 763,928 2023 381,755 235,971 52,872 90,973 1,323 762,893 2024 383,221 236,685 51,010 90,920 1,246 763,081 2025 382,098 235,693 49,105 90,846 1,178 758,920 2026 382,238 235,144 47,575 90,647 1,128 756,731 2027 382,478 234,065 46,454 90,367 1,091 754,454 2028 384,043 233,155 45,038 90,051 1,066 753,353 2029 383,329 230,679 43,237 89,700 1,043 747,988 2030 383,712 228,952 41,414 89,361 1,029 744,469 2031 384,512 227,073 39,790 88,986 1,018 741,380 2022-31 0.06%-0.40%-3.27%-0.26%-3.63%-0.33% California Retail Sales – Megawatt-hours (MWh) Compound Annual Growth Rate Year Residential Commercial Industrial Irrigation Lighting Total 2022 7,486,721 9,885,130 7,826,692 232,649 51,617 25,482,810 2023 7,563,353 10,386,939 7,921,202 232,571 47,781 26,151,846 2024 7,698,651 10,706,741 8,005,055 232,586 45,136 26,688,169 2025 7,807,461 10,869,905 7,962,311 232,495 43,154 26,915,326 2026 7,977,241 11,013,101 6,544,182 232,429 41,986 25,808,940 2027 8,170,602 11,104,346 6,536,315 232,339 41,275 26,084,877 2028 8,414,703 11,226,321 6,529,252 232,207 40,969 26,443,452 2029 8,584,013 11,261,726 6,485,280 231,928 40,603 26,603,549 2030 8,749,010 11,302,572 6,480,594 231,603 40,457 26,804,237 2031 8,933,960 11,288,665 6,468,866 231,292 40,373 26,963,156 2022-31 1.98%1.49%-2.09%-0.06%-2.69%0.63% Utah Retail Sales – Megawatt-hours (MWh) Compound Annual Growth Rate PACIFICORP – 2021 IRP UPDATE APPENDIX A – ADDITIONAL LOAD FORECAST DETAILS 114 Table A.10 – Forecasted Retail Sales Growth in Idaho, post-DSM Table A.11 – Forecasted Retail Sales Growth in Wyoming, post-DSM Year Residential Commercial Industrial Irrigation Lighting Total 2022 731,411 536,502 1,740,182 638,729 2,607 3,649,432 2023 720,703 536,531 1,746,769 638,753 2,574 3,645,330 2024 723,863 540,050 1,732,842 638,946 2,547 3,638,247 2025 720,853 540,125 1,732,104 638,909 2,504 3,634,496 2026 723,428 539,778 1,730,168 638,580 2,469 3,634,423 2027 726,455 537,494 1,726,496 637,829 2,434 3,630,709 2028 733,689 536,026 1,722,956 636,869 2,407 3,631,947 2029 736,108 531,204 1,717,517 635,903 2,367 3,623,099 2030 731,214 528,740 1,713,034 634,996 2,335 3,610,320 2031 724,653 527,341 1,709,501 633,630 2,304 3,597,428 2022-31 -0.10%-0.19%-0.20%-0.09%-1.36%-0.16% Idaho Retail Sales – Megawatt-hours (MWh) Compound Annual Growth Rate Year Residential Commercial Industrial Irrigation Lighting Total 2022 966,439 1,322,319 6,348,502 26,999 11,907 8,676,165 2023 941,994 1,320,042 6,576,179 26,979 11,836 8,877,030 2024 927,218 1,323,873 6,628,483 26,983 11,757 8,918,313 2025 903,969 1,307,262 6,811,014 26,967 11,542 9,060,753 2026 890,143 1,292,909 6,802,077 26,950 11,263 9,023,341 2027 878,643 1,273,335 6,771,939 26,920 10,848 8,961,685 2028 872,709 1,256,347 6,767,577 26,885 10,295 8,933,814 2029 861,004 1,235,919 6,731,517 26,845 9,501 8,864,786 2030 841,131 1,221,583 6,707,712 26,809 8,598 8,805,833 2031 820,168 1,210,082 6,692,991 26,776 7,643 8,757,660 2022-31 -1.81%-0.98%0.59%-0.09%-4.81%0.10% Wyoming Retail Sales – Megawatt-hours (MWh) Compound Annual Growth Rate