HomeMy WebLinkAbout20210901IRP Vol I.pdfMeant for bleeds only! Always bleed this trigon at .125”
2021 Integrated Resource Plan
VOLUME I | SEPTEMBER 1, 2021
This 2021 Integrated Resource Plan Report is based upon the best available information at the
time of preparation. The IRP action plan will be implemented as described herein, but is subject
to change as new information becomes available or as circumstances change. It is PacifiCorp’s
intention to revisit and refresh the IRP action plan no less frequently than annually. Any
refreshed IRP action plan will be submitted to the State Commissions for their information.
For more information, contact:
PacifiCorp Resource Planning
825 N.E. Multnomah, Suite 600
Portland, Oregon 97232
(503) 813-5245
irp@pacificorp.com
www.pacificorp.com
Cover Photos (Top to Bottom):
Pavant III Solar Plant
Marengo Wind Project
Transmission Line - Wyoming
Panguitch Solar & Battery Storage
Chapter 1 – Executive Summary
PACIFICORP’S VISION .......................................................................................................................1
THE TIME IS NOW ............................................................................................................................1
DELIVERING ON OUR PROMISE ........................................................................................................1
PUTTING OUR CUSTOMERS AT THE CENTER OF EVERYTHING WE DO ..................................................2
OUR CUSTOMER-CENTERED VISION EMBODIES FOUR CORE THEMES: ................................................2
2021 IRP ROADMAP .........................................................................................................................2
MEETING OUR GOALS. ACCELERATING OUR PROGRESS. ...................................................................3
EVOLVING OUR PORTFOLIO ..............................................................................................................4
CO-CREATING ENERGY SOLUTIONS WITH CUSTOMERS AND COMMUNITIES .........................................4
CLEAN TRANSPORTATION INFRASTRUCTURE ....................................................................................5
SOLAR + STORAGE IN OUR COMMUNITIES ........................................................................................5
ADVANCED NUCLEAR DEMONSTRATION PROJECT .............................................................................5
DELIVERING RESILIENCE AND RELIABILITY THROUGH A CONNECTED WEST .......................................5
EXPANDED CONSERVATION MEASURES ............................................................................................6
PUTTING OUR SHARED VISION TO WORK FOR OUR CUSTOMERS .........................................................6
PacifiCorp’s Integrated Resource Plan Approach ...........................................................................7
Preferred Portfolio Highlights ..........................................................................................................8
NEW SOLAR RESOURCES ................................................................................................................10
NEW WIND RESOURCES ..................................................................................................................11
NEW STORAGE RESOURCES ............................................................................................................11
OTHER NON-EMITTING RESOURCES ...............................................................................................12
DEMAND-SIDE MANAGEMENT ........................................................................................................12
WHOLESALE POWER MARKET PRICES AND PURCHASES .................................................................13
COAL AND GAS RETIREMENTS/GAS CONVERSIONS ........................................................................14
CARBON DIOXIDE EMISSIONS .........................................................................................................16
RENEWABLE PORTFOLIO STANDARDS ............................................................................................17
2021 IRP Advancements and Supplemental Studies .....................................................................19
IRP ADVANCEMENTS ......................................................................................................................19
SUPPLEMENTAL STUDIES ................................................................................................................20
Action Plan.....................................................................................................................................23
Chapter 2 – Introduction
Chapter 3 – Planning Environment
Introduction ....................................................................................................................................38
Wholesale Electricity Markets .......................................................................................................38
NATURAL GAS UNCERTAINTY ....................................................................................................... 41
PACIFICORP’S MULTI-STATE PROCESS .......................................................................................... 46
LIST OF IMPLEMENTED ISSUES ..................................................................................................... 48
LIST OF RESOLVED ISSUES ........................................................................................................... 48
UPDATE ON 2020 PROTOCOL AND STATUS OF FRAMEWORK ISSUES .............................................. 49
ANALYSIS OF “OUTSTANDING MATERIAL DISAGREEMENTS” ......................................................... 50
The Future of Federal Environmental Regulation and Legislation ...............................................50
Federal Policy Update ....................................................................................................................51
NEW SOURCE PERFORMANCE STANDARDS FOR CARBON EMISSIONS – CLEAN AIR ACT § 111(B) . 51
CARBON EMISSION GUIDELINES FOR EXISTING SOURCES – CLEAN AIR ACT § 111(D) .................. 51
CREDIT FOR CARBON OXIDE SEQUESTRATION – INTERNAL REVENUE SERVICE (IRS) § 45Q ........ 52
CLEAN AIR ACT CRITERIA POLLUTANTS – NATIONAL AMBIENT AIR QUALITY STANDARDS ......... 52
REGIONAL HAZE ............................................................................................................................ 53
UTAH REGIONAL HAZE ................................................................................................................ 53
WYOMING REGIONAL HAZE ......................................................................................................... 55
ARIZONA REGIONAL HAZE ........................................................................................................... 56
COLORADO REGIONAL HAZE ....................................................................................................... 56
MERCURY AND HAZARDOUS AIR POLLUTANTS ............................................................................. 57
COAL COMBUSTION RESIDUALS .................................................................................................... 57
WATER QUALITY STANDARDS ....................................................................................................... 59
COOLING WATER INTAKE STRUCTURES ........................................................................................ 59
EFFLUENT LIMIT GUIDELINES ..................................................................................................... 59
RENEWABLE GENERATION REGULATORY FRAMEWORK ................................................................ 60
TAX EXTENDER LEGISLATION ....................................................................................................... 61
State Policy Update ........................................................................................................................62
CALIFORNIA ................................................................................................................................... 62
OREGON ......................................................................................................................................... 63
WASHINGTON ................................................................................................................................ 64
UTAH ............................................................................................................................................. 64
WYOMING ...................................................................................................................................... 65
GREENHOUSE GAS EMISSION PERFORMANCE STANDARDS ............................................................ 66
Renewable Portfolio Standards ......................................................................................................66
CALIFORNIA ................................................................................................................................... 67
OREGON ......................................................................................................................................... 69
UTAH ............................................................................................................................................. 70
Chapter 4 - Transmission
Introduction ....................................................................................................................................83
Regulatory Requirements...............................................................................................................84
OPEN ACCESS TRANSMISSION TARIFF ........................................................................................... 84
RELIABILITY STANDARDS .............................................................................................................. 85
GENERATION INTERCONNECTION QUEUE REFORM ........................................................................ 85
Aeolus to Bridger/Anticline ...........................................................................................................86
Aeolus-to-Mona (Gateway South) .................................................................................................86
Gateway West – Continued Permitting..........................................................................................87
WINDSTAR TO POPULUS (SEGMENT D) .......................................................................................... 87
POPULUS TO HEMINGWAY (SEGMENT E) ....................................................................................... 87
PLAN TO CONTINUE PERMITTING – GATEWAY WEST .................................................................... 88
Request for Acknowledgement for Boardman-to-Hemingway .....................................................88
FACTORS SUPPORTING ACKNOWLEDGEMENT ................................................................................ 89
NEXT STEPS ................................................................................................................................... 91
Energy Gateway Transmission Expansion Plan ............................................................................91
INTRODUCTION .............................................................................................................................. 91
BACKGROUND ................................................................................................................................ 91
PLANNING INITIATIVES .................................................................................................................. 91
ENERGY GATEWAY CONFIGURATION ............................................................................................ 93
ENERGY GATEWAY’S CONTINUED EVOLUTION ............................................................................. 94
Efforts to Maximize Existing System Capability ..........................................................................98
TRANSMISSION SYSTEM IMPROVEMENTS PLACED IN-SERVICE SINCE THE 2019 IRP 99
PACIFICORP EAST (PACE) CONTROL AREA .................................................................................. 99
PACIFICORP WEST (PACW) CONTROL AREA .............................................................................. 100
PLANNED TRANSMISSION SYSTEM IMPROVEMENTS ..................................................................... 100
PACIFICORP EAST (PACE) CONTROL AREA .............................................................................. 100
PACIFICORP WEST (PACW) CONTROL AREA ............................................................................. 102
Chapter 5 – Reliability and Resiliency
Introduction ..................................................................................................................................105
Supply-Based Reliability .............................................................................................................105
REGIONAL RESOURCE ADEQUACY ............................................................................................... 105
WECC WESTERN ASSESSMENT OF RESOURCE ADEQUACY REPORT ........................................... 106
NERC LONG-TERM RESOURCE ADEQUACY (LTRA) .................................................................. 110
RESOURCES .............................................................................................................................. 110
WECC SUBREGIONS ................................................................................................................. 110
CHAPTER 6 – LOAD AND RESOURCE BALANCE
Introduction ..................................................................................................................................135
System Coincident Peak Load Forecast .......................................................................................136
Existing Resources .......................................................................................................................136
THERMAL PLANTS ....................................................................................................................... 136
RENEWABLE RESOURCES ............................................................................................................. 138
WIND ........................................................................................................................................ 138
SOLAR....................................................................................................................................... 140
GEOTHERMAL ........................................................................................................................... 142
BIOMASS/BIOGAS ...................................................................................................................... 142
RENEWABLES NET METERING .................................................................................................... 142
HYDROELECTRIC GENERATION .................................................................................................... 143
DEMAND-SIDE MANAGEMENT ..................................................................................................... 145
PRIVATE GENERATION ................................................................................................................. 147
POWER-PURCHASE AGREEMENTS ................................................................................................ 148
Load and Resource Balance .........................................................................................................149
CAPACITY AND ENERGY BALANCE OVERVIEW ............................................................................ 149
LOAD AND RESOURCE BALANCE COMPONENTS ........................................................................... 149
EXISTING RESOURCES ............................................................................................................... 150
OBLIGATION ............................................................................................................................. 151
POSITION .................................................................................................................................. 152
CAPACITY BALANCE DETERMINATION ........................................................................................ 152
METHODOLOGY ........................................................................................................................ 152
CAPACITY BALANCE RESULTS .................................................................................................... 153
ENERGY BALANCE DETERMINATION ........................................................................................... 161
METHODOLOGY ........................................................................................................................ 161
ENERGY BALANCE RESULTS ........................................................................................................ 162
CHAPTER 7 – RESOURCE OPTIONS
Introduction ..................................................................................................................................163
Supply-Side Resources ................................................................................................................163
DERIVATION OF RESOURCE ATTRIBUTES ..................................................................................... 164
HANDLING OF TECHNOLOGY IMPROVEMENT TRENDS AND COST UNCERTAINTIES ...................... 165
RESOURCE OPTIONS AND ATTRIBUTES ........................................................................................ 167
RESOURCE OPTION DESCRIPTIONS ............................................................................................... 187
RESOURCE TYPES ........................................................................................................................ 190
CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
Introduction ..................................................................................................................................215
Modeling and Evaluation Steps ...................................................................................................217
Resource Portfolio Development .................................................................................................219
LONG-TERM (LT) CAPACITY EXPANSION MODEL ....................................................................... 219
TRANSMISSION SYSTEM .............................................................................................................. 220
TRANSMISSION COSTS ................................................................................................................ 220
RESOURCE ADEQUACY .............................................................................................................. 221
GRANULARITY AND RELIABILITY ADJUSTMENTS .......................................................................... 221
NEW RESOURCE OPTIONS ......................................................................................................... 221
CAPITAL COSTS ......................................................................................................................... 223
GENERAL ASSUMPTIONS ............................................................................................................ 223
Cost and Risk Analysis ................................................................................................................226
SHORT-TERM (ST) SCHEDULE MODEL ........................................................................................ 226
RELIABILITY ASSESSMENT AND SYSTEM COST ............................................................................. 227
MEDIUM-TERM (MT) SCHEDULE MODEL .................................................................................... 228
COST AND RISK ANALYSIS .......................................................................................................... 228
STOCHASTIC MODEL PARAMETER ESTIMATION .......................................................................... 229
STOCHASTIC PORTFOLIO PERFORMANCE MEASURES .................................................................. 238
FORWARD PRICE CURVE SCENARIOS ......................................................................................... 239
OTHER PLEXOS MODELING METHODS AND ASSUMPTIONS .......................................................... 240
OTHER COST AND RISK CONSIDERATIONS ................................................................................... 240
FUEL SOURCE DIVERSITY .......................................................................................................... 240
CUSTOMER RATE IMPACTS ........................................................................................................ 241
MARKET RELIANCE ................................................................................................................... 241
Portfolio Selection .......................................................................................................................241
Final Evaluation and Preferred Portfolio Selection .....................................................................241
Case Definitions ...........................................................................................................................242
INITIAL PORTFOLIOS .................................................................................................................... 242
P02 (OPTIMIZED COAL RETIREMENTS) ........................................................................................ 243
P03 (COAL RETIRED BY 2030) .................................................................................................... 244
BUSINESS AS USUAL CASES ........................................................................................................ 244
BAU1 (END-OF-LIFE COAL RETIREMENTS) ................................................................................. 244
BAU2 (2019 IRP COAL RETIREMENTS) ...................................................................................... 245
PREFERRED PORTFOLIO SELECTION CASES .................................................................................. 245
P02A-JB1-2 GC ....................................................................................................................... 245
P02B-NO B2H .......................................................................................................................... 246
P02C-NO GWS ......................................................................................................................... 246
P02D-NO RFP ......................................................................................................................... 246
P02E-NO NUC ......................................................................................................................... 246
P02F-NO NAU25 ..................................................................................................................... 246
P02G-CCUS ............................................................................................................................ 246
P02H-JB3-4 RET ..................................................................................................................... 246
CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
Introduction ..................................................................................................................................252
Initial Portfolio Development ......................................................................................................252
INITIAL PORTFOLIO DEVELOPMENT ............................................................................................. 253
INITIAL PORTFOLIOS THERMAL RETIREMENTS ............................................................................ 253
INITIAL PORTFOLIOS NEW RENEWABLES AND NON-EMITTING RESOURCES .................................. 254
INITIAL PORTFOLIOS NEW STORAGE RESOURCES ....................................................................... 255
INITIAL PORTFOLIOS DEMAND-SIDE MANAGEMENT (DSM) RESOURCES ..................................... 256
CO2 EMISSIONS ........................................................................................................................ 258
P02 Variant Portfolios..................................................................................................................260
P02 VARIANT PORTFOLIOS PORTFOLIO SUMMARY ...................................................................... 261
COAL AND GAS RETIREMENTS .................................................................................................... 261
NEW RENEWABLE AND NON-EMITTING RESOURCES ................................................................... 262
NEW STORAGE RESOURCES ....................................................................................................... 263
P02 VARIANT PORTFOLIOS DEMAND-SIDE MANAGEMENT RESOURCES ....................................... 264
CO2 EMISSIONS ........................................................................................................................ 265
P02 VARIANTS PORTFOLIO DISCUSSION ...................................................................................... 267
PORTFOLIO DEVELOPMENT CONCLUSIONS .................................................................................. 287
Preferred Portfolio Selection........................................................................................................287
FINAL PREFERRED PORTFOLIO SELECTION ................................................................................ 287
CUSTOMER RATE PRESSURE 289
The 2021 IRP Preferred Portfolio ................................................................................................290
NEW SOLAR RESOURCES ............................................................................................................. 292
NEW WIND RESOURCES ............................................................................................................... 293
NEW STORAGE RESOURCES ......................................................................................................... 293
OTHER NON-EMITTING RESOURCES ............................................................................................ 294
DEMAND-SIDE MANAGEMENT ..................................................................................................... 294
WHOLESALE POWER MARKET PRICES AND PURCHASES .............................................................. 295
COAL AND GAS RETIREMENTS/GAS CONVERSIONS ..................................................................... 296
CARBON DIOXIDE EMISSIONS ...................................................................................................... 297
RENEWABLE PORTFOLIO STANDARDS ......................................................................................... 299
CAPACITY AND ENERGY .............................................................................................................. 302
DETAILED PREFERRED PORTFOLIO .............................................................................................. 303
Washington Clean Energy Transformation Act Required Scenarios ..........................................311
ALTERNATIVE LOWEST REASONABLE COST ................................................................................ 311
CLIMATE CHANGE ....................................................................................................................... 312
MAXIMUM CUSTOMER BENEFIT .................................................................................................. 313
Additional Sensitivity Analysis ...................................................................................................314
CHAPTER 10 – ACTION PLAN
Introduction ................................................................................................................................. 317
The 2021 IRP Action Plan .......................................................................................................... 319
Progress on Previous Action Plan Items ..................................................................................... 325
Acquisition Path Analysis ........................................................................................................... 337
RESOURCE AND COMPLIANCE STRATEGIES .................................................................................. 337
ACQUISITION PATH DECISION MECHANISM ................................................................................. 337
Procurement Delays .................................................................................................................... 341
IRP Action Plan Linkage to Business Planning .......................................................................... 342
Resource Procurement Strategy .................................................................................................. 342
RENEWABLE RESOURCES, STORAGE RESOURCES, AND DISPATCHABLE RESOURCES ................... 343
RENEWABLE ENERGY CREDITS .................................................................................................... 343
DEMAND-SIDE MANAGEMENT ..................................................................................................... 343
Assessment of Owning Assets versus Purchasing Power ........................................................... 343
Managing Carbon Risk for Existing Plants ................................................................................ 344
Purpose of Hedging..................................................................................................................... 344
Treatment of Customer and Investor Risks ................................................................................ 346
STOCHASTIC RISK ASSESSMENT .................................................................................................. 346
CAPITAL COST RISKS ................................................................................................................... 346
SCENARIO RISK ASSESSMENT ...................................................................................................... 346
APPENDIX A – LOAD FORECAST DETAILS
Introduction ..................................................................................................................................... 1
SUMMARY LOAD FORECAST ............................................................................................................ 1
Load Forecast Assumptions ............................................................................................................ 4
REGIONAL ECONOMY BY JURISDICTION ........................................................................................... 4
UTAH ............................................................................................................................................... 5
OREGON ........................................................................................................................................... 6
WYOMING ........................................................................................................................................ 6
WASHINGTON .................................................................................................................................. 7
IDAHO .............................................................................................................................................. 7
CALIFORNIA ..................................................................................................................................... 8
Weather ........................................................................................................................................... 8
STATISTICALLY ADJUSTED END-USE (“SAE”) .............................................................................. 10
INDIVIDUAL CUSTOMER FORECAST ............................................................................................... 10
ACTUAL LOAD DATA ..................................................................................................................... 10
APPENDIX B – REGULATORY COMPLIANCE
Table B.1 – Integrated Resource Planning Standards and Guidelines Summary by State ............27
Table B.2 – Handling of 2021 IRP Acknowledgment and Other IRP Requirements ....................35
Table B.3 – Oregon Public Utility Commission IRP Standard and Guidelines ............................49
Table B.4 – Utah Public Service Commission IRP Standard and Guidelines ...............................62
Table B.5 – Washington Utilities and Transportation Commission IRP Standard and Guidelines to
Implement CETA Rules (RCW 19.280.030 and WAC 480-100-620 through WAC 480-100-630)
per Commission General Order R-601. .........................................................................................69
Table B.6 – Wyoming Public Service Commission Guideline......................................................80
APPENDIX C – PUBLIC INPUT
Participant List .............................................................................................................................. 83
COMMISSIONS ................................................................................................................................ 83
STAKEHOLDERS AND INDUSTRY EXPERTS ..................................................................................... 84
Public-Input Meetings ................................................................................................................... 85
GENERAL MEETINGS ...................................................................................................................... 85
STATE-SPECIFIC INPUT MEETINGS ................................................................................................. 88
Stakeholder Comments ................................................................................................................. 88
CARBON PRICE ........................................................................................................................... 89
COAL ANALYSIS ........................................................................................................................... 89
CONSERVATION POTENTIAL ASSESSMENT (CPA)/ENERGY EFFICIENCY/DEMAND RESPONSE .......... 90
CONSULTANT REPORTS ............................................................................................................... 93
CUSTOMER PREFERENCE ............................................................................................................ 93
DISTRIBUTED ENERGY RESOURCES .............................................................................................. 93
ENERGY EFFICIENCY ................................................................................................................... 93
ENERGY STORAGE ....................................................................................................................... 94
ENVIRONMENTAL POLICY ............................................................................................................ 95
IRP PUBLIC-INPUT MEETING PROCESS/GENERAL COMMENTS ..................................................... 95
LEGISLATION .............................................................................................................................. 95
LOAD FORECASTING .................................................................................................................... 95
MARKET RELIANCE ASSESSMENT ................................................................................................. 96
MODELING ASSUMPTIONS ........................................................................................................... 96
NATRIUM DEMONSTRATION PROJECT .......................................................................................... 97
NATURAL GAS ............................................................................................................................. 97
OPERATING LIMITS ..................................................................................................................... 97
PLEXOS ...................................................................................................................................... 97
PRIVATE GENERATION STUDY ...................................................................................................... 98
PROCUREMENT ........................................................................................................................... 98
RELIABILITY ASSESSMENT ............................................................................................................ 99
RENEWABLE ENERGY RESOURCES ................................................................................................ 99
RESOURCE ADEQUACY ................................................................................................................ 99
SENSITIVITY STUDIES ................................................................................................................... 99
STATE ENERGY POLICY .............................................................................................................. 101
APPENDIX D – DSM RESOURCES
Introduction ................................................................................................................................. 105
Conservation Potential Assessment (CPA) for 2021-2040 ......................................................... 105
Current DSM Program Offerings by State.................................................................................. 106
State-Specific DSM Planning Processes ..................................................................................... 108
Preferred Portfolio DSM Resource Selections ........................................................................... 109
APPENDIX E – SMART GRID
Introduction ................................................................................................................................. 111
TRANSMISSION NETWORK AND OPERATION ENHANCEMENTS ..................................................... 111
DYNAMIC LINE RATING ............................................................................................................. 111
DIGITAL FAULT RECORDERS / PHASOR MEASUREMENT UNIT DEPLOYMENT ................................ 112
DISTRIBUTION AUTOMATION AND RELIABILITY .......................................................................... 113
DISTRIBUTION AUTOMATION ..................................................................................................... 113
WILDFIRE MITIGATION .............................................................................................................. 113
IN RESPONSE TO CONCERNS OF WILDFIRE DANGER TO CUSTOMERS, PACIFICORP BEGAN DEVELOPING
COMMUNICATION SYSTEMS AND PRACTICES TO IMPROVE SYSTEM RELIABILITY IN AT RISK AREAS.
SELECTED SUBSTATIONS IN SISKIYOU COUNTY, CALIFORNIA AND WASATCH COUNTY, UTAH ARE
PRELIMINARY SITES THAT WILL HAVE REMOTE COMMUNICATION INSTALLED TO ALLOW DISPATCH
OPERATORS TO MODIFY RE-CLOSER SETTINGS. ............................................................................ 113
DISTRIBUTION SUBSTATION METERING ...................................................................................... 113
DISTRIBUTED ENERGY RESOURCES ............................................................................................. 114
ENERGY STORAGE SYSTEMS ....................................................................................................... 114
DEMAND RESPONSE .................................................................................................................. 114
DISPATCHABLE CUSTOMER RESOURCES..................................................................................... 114
ADVANCED METERING INFRASTRUCTURE ................................................................................... 115
OUTAGE MANAGEMENT IMPROVEMENTS .................................................................................... 116
Future Smart Grid ....................................................................................................................... 116
APPENDIX F – FLEXIBLE RESERVE STUDY
Introduction ................................................................................................................................. 117
OVERVIEW ................................................................................................................................... 118
Flexible Resource Requirements ................................................................................................ 119
CONTINGENCY RESERVE .............................................................................................................. 119
REGULATION RESERVE ................................................................................................................ 120
FREQUENCY RESPONSE RESERVE ................................................................................................ 121
BLACK START REQUIREMENTS .................................................................................................... 122
ANCILLARY SERVICES OPERATIONAL DISTINCTIONS ................................................................... 122
APPENDIX G – PLANT WATER CONSUMPTION STUDY………………153
APPENDIX H – STOCHASTIC PARAMETERS
Introduction ................................................................................................................................. 159
Overview ..................................................................................................................................... 159
Volatility ..................................................................................................................................... 160
Mean Reversion .......................................................................................................................... 160
Estimating Short-term Process Parameters ................................................................................. 162
Stochastic Process Description ................................................................................................... 162
DATA DEVELOPMENT .................................................................................................................. 163
PARAMETER ESTIMATION – AUTOREGRESSIVE MODEL ............................................................... 166
ELECTRICITY PRICE PROCESS ...................................................................................................... 168
REGIONAL LOAD PROCESS ........................................................................................................... 169
HYDRO GENERATION PROCESS .................................................................................................... 172
SHORT-TERM CORRELATION ESTIMATION ................................................................................... 173
APPENDIX I – CAPACITY EXPANSION RESULTS…………………...…177
APPENDIX J – STOCHASTIC SIMULATION RESULTS…………...……..211
APPENDIX K – CAPACITY CONTRIBUTION……….…………...……..217
APPENDIX L – PRIVATE GENERATION……….………….…....……..225
APPENDIX M – RENEWABLE RESOURCES ASSESSMENT...…………..225
APPENDIX N – ENERGY STORAGE POTENTIAL EVALUATION
Introduction ................................................................................................................................. 229
Part 1: Grid Services ................................................................................................................... 229
ENERGY VALUE ........................................................................................................................... 230
BACKGROUND ........................................................................................................................... 230
MODELING ............................................................................................................................... 231
OPERATING RESERVE VALUE ...................................................................................................... 233
BACKGROUND ........................................................................................................................... 233
MODELING ............................................................................................................................... 234
TRANSMISSION AND DISTRIBUTION CAPACITY ............................................................................ 234
GENERATION CAPACITY .............................................................................................................. 236
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
1
CHAPTER 1 – EXECUTIVE SUMMARY
PacifiCorp’s 2021 Integrated Resource Plan (IRP) was developed through comprehensive analysis
and an extensive public-input process spanning over a year and a half resulting in the selection of
a least-cost, least-risk preferred portfolio. With accelerated coal retirements, no new fossil-fueled
resources, continued growth in energy efficiency programs, and incremental renewable resources,
the 2021 IRP preferred portfolio results in a greater reduction in greenhouse gas emissions relative
to the 2019 IRP. Reliable service will be maintained with investment in transmission infrastructure,
the conversion of two coal units to natural gas peaking units, growth in demand response programs,
the addition of advanced nuclear resources, the addition of energy storage resources, and over the
long term, the addition of non-emitting peaking resources.
PacifiCorp’s Vision
The time is now
At PacifiCorp, we share a vision with our customers and communities in which clean energy from
across the West powers jobs and innovation. This bold vision has guided our work for years. Most
recently, it took shape in our 2017 and 2019 IRPs, in which we outlined an ambitious path to
substantially increase our renewable energy capacity, evolving our existing portfolio and
connecting supply with demand through an expanded, modernized transmission system.
Now is the time for further action.
Delivering on our promise
The power of the West lies in its diversity: windswept plains and high deserts, the sun-soaked
Great Basin, and rivers fed by rain and mountain snow. Taken together, these reserves of wind,
solar and hydro power can help meet the growing and changing needs of homes and businesses
throughout the West, cleanly, reliably and affordably.
Yet, capturing this power alone is not enough. To unlock the full promise of these abundant
resources, we must add transmission and storage capacity, unlock customer demand response
resources with a modernized grid, and replace retiring thermal resources with non-emitting
resources like advanced nuclear, to connect the West to its energy future—built on a resilient,
hardened, adaptable grid that safely delivers power when and where it’s needed.
PacifiCorp’s 2021 IRP is a roadmap for action. It sets forth a path to build upon our significant
progress toward the goals laid out in the 2017 and 2019 IRPs and identifies critical investments in
expanded and modernized transmission, renewable energy, storage, demand response and
advanced nuclear resources.
Our integrated system connects and brings new opportunities to the West, building on a foundation
of infrastructure designed to handle extreme weather and enhance the energy resilience of
communities from the Pacific Coast to the Rocky Mountains, all while continuing to deliver energy
solutions for our customers at prices that are below national and regional averages.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
2
As our 2021 IRP shows, this expanded, modernized transmission will connect supply with demand
from east to west and from north to south, serving as the backbone of the West for the hundreds
of energy providers that serve our region alongside PacifiCorp.
Putting our customers at the center of everything we do
At PacifiCorp, we’re committed to meeting the demands of our customers and communities
throughout the West to deliver safe, affordable, clean energy and a resilient, modern grid.
Together with the communities we serve and our regional partners, it is time to act, with targeted,
strategic investments that will position us to continue delivering affordable, reliable power.
Our customer-centered vision embodies four core themes:
Reliable Power: We strive to deliver energy safely during all hours, and plan extensively to ensure
that we have sufficient supply and ability to deliver to the communities we serve. We understand
that electricity is an essential service, and work around the clock to ensure that we are dependable,
and communities can rely on us.
Resilient Infrastructure: This is a time of rapid change, with more extreme weather and
challenging conditions. We are working to minimize disruptions, implement strategies to recover
quickly when they occur, and deploy upgrades that will strengthen our critical infrastructure.
Affordable Prices: PacifiCorp is proud to be one of the lowest-cost electricity providers in the
nation and the region. As we plan for our next generation of resources, we are prioritizing resources
that add value and keep customer prices low.
Clean Energy: Through strategic, customer-focused investments in a diversity of resources,
PacifiCorp is on a path to reduce carbon emissions, system-wide, by 74 percent from 2005 levels
by 2030. Our resource plan includes continued significant new renewable additions among other
diverse, advanced technologies to keep us on that path and achieve even deeper decarbonization
beyond 2030.
2021 IRP Roadmap
The 2021 IRP outlines PacifiCorp’s bold vision for the West between now and 2040 and sets us
on the path to achieve a clean, resilient and affordable energy future that leverages the abundant,
diverse, clean energy resources that the West can offer through a modernized and expanded grid.
• Continue our growth into a grid powered by clean energy (incremental to projects
already online and projects with executed agreements that will come online through
2023):
o 4,290 MW from energy efficiency programs
o 5,628 MW of new solar resources (most paired with storage)
o 3,628 MW of new wind resources
o 6,181 MW of storage resources, including battery storage co-located with solar,
standalone battery storage and pumped hydro storage resources
o 2,448 MW of direct load control programs
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
3
o 500 MW of advanced nuclear (the Natrium TM reactor demonstration project) in
2028, with an additional 1,000 MW of advanced nuclear over the long-term
• Connect and optimize these diverse, clean resources across the West with a
strengthened and modernized transmission network that ensures resilient service,
reduces costs and creates maximum opportunities for our communities to thrive
(incremental to projects already online):
o 416 miles of new transmission from the new Aeolus substation near Medicine
Bow, Wyoming, to the Clover substation near Mona, Utah (Energy Gateway
South)
o 59 miles of new transmission from the Shirley Basin substation in southeastern
Wyoming to the Windstar substation near Glenrock, Wyoming (Energy Gateway
West Sub-Segment D.1)
o 290 miles of new transmission from the Boardman substation in north central
Oregon to the Hemingway substation in south central Idaho
Meeting our goals. Accelerating our progress.
Our 2021 IRP positions PacifiCorp to rapidly expand its supply of clean energy while increasing
our storage capacity and delivering cost savings to our customers.1
Figure 1.1 – IRP preferred portfolio metrics and trajectory
1Resources acquired through customer partnerships, used for renewable portfolio standard compliance, or for third-
party sales of renewable attributes are included in the total capacity figures quoted.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
4
Evolving Our Portfolio
Working in close partnership with our communities, we are making significant progress in our
evolution to an increasingly low-carbon portfolio. Over the past two years, our progress toward
those goals has included:
• A completed coal-to-gas peaker conversion of Naughton Unit 3 in Kemmerer, Wyoming
• Retirement of the Cholla Unit 4 coal-fired generator in Joseph City, Arizona
Our resource strategy in the 2021 IRP continues that progress, and within the next four years will:
• Begin the process of retiring or divesting Colstrip Units 3 and 4 in Colstrip, Montana
• Begin the process of a coal-to-gas peaker conversion of Jim Bridger Units 1 and 2 in
Rock Springs, Wyoming
• Begin the process of retirement or sale of Naughton Units 1 and 2
Throughout, we are collaborating closely with affected communities and with state leadership to
support a successful transition for our employees and their communities.
Co-creating energy solutions with customers and communities
The communities PacifiCorp serves are why we exist, so we’re working in close collaboration with
them to build the opportunities and infrastructure that enables communities to thrive.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
5
Clean transportation infrastructure
There are good things ahead for electric transportation in the
West. In addition to the more than 2,100 new electric vehicle
charging ports that we have already helped install, we’re
expanding workplace charging, supporting regional solutions
to electrify interstates for cleaner freight transportation, and
making electric vehicle ownership more accessible for rural
and underserved communities.
Solar + Storage in our communities
PacifiCorp is partnering with the communities throughout its service area to leverage grid-scale
battery storage and solar projects to help meet community energy needs. In Panguitch Utah, a one-
megawatt peak capacity, five megawatt-hour energy storage system anticipates and responds to
peak electricity consumption and levels demand on the local grid. This enables PacifiCorp to
employ batteries as an alternative to traditional grid poles-and-wires infrastructure. The 650-
kilowatt solar photovoltaic component of this project was funded through a grant from the
company’s Blue Sky renewable energy program.
Similarly, through a partnership with the Oregon Institute of Technology in Klamath Falls,
Oregon, PacifiCorp is installing a two-megawatt peak capacity, six megawatt-hour energy storage
system that will partner with the existing geothermal and solar resources on the campus to provide
increased local grid stability. PacifiCorp will also facilitate the interconnection of 64 megawatts
of small community based solar systems over the next four years through the Oregon Community
Solar Program. These projects are designed to provide an opportunity for residential and low-
income customers to share in the benefits of local solar energy production.
Advanced nuclear demonstration project
A developer of an advanced nuclear reactor, TerraPower, has received support from the
Department of Energy to construct a demonstration plant for its Natrium™ technology.
TerraPower is investigating the opportunity to site Natrium at a retiring coal plant in Wyoming.
The project promises many benefits to PacifiCorp including a 24/7 reliable source of clean energy
with embedded storage, safety, cost and reduced spent fuel advantages while providing an
employment transition opportunity for our existing coal employees and an economic boost to the
community where they reside. Using safety features that take advantage of natural forces and do
not require human intervention, this reactor will be able to shut down safely and independently,
greatly reducing the risks associated with earlier nuclear reactors. TerraPower has not yet
identified the specific site for this facility. For modeling purposes in the 2021 IRP, the NatriumTM
demonstration project is placed at the Naughton facility. However, a modeling assumption does
not equate to the selection of a site. Should TerraPower’s site selection ultimately identify a
different location than what was modeled in the 2021 IRP, updated analysis of portfolio
implications will be made in a future IRP or IRP update.
Delivering resilience and reliability through a connected West
The diversity of the West’s landscape—including its abundant clean energy resources—are the key to
our strategy for delivering least-cost, least-risk, resilient power to our customers. We have already
collaborated with utilities from across the region to form the Western Energy Imbalance Market (EIM),
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
6
which allows utilities to trade surplus power in near-real time.
The EIM leverages diverse clean energy resources from across
the West to dramatically lower greenhouse gas emissions,
while increasing the grid’s resilience and lowering costs for our
customers.
In our 2019 IRP, we expanded our plans stemming from the
2017 IRP to significantly increase our transmission capacity to
integrate new renewable resources more effectively into the
grid and to deliver the full benefit of the EIM to our customers.
We are on target with all benchmarks established by that IRP.
• Completed reinforcements of high-voltage transmission in the Utah Valley, northern Utah,
southern Utah, and Yakima, Washington. These projects will allow the company to respond
to interconnection requests and accommodate the renewable resources identified in the 2019
IRP.
• Continuing the regulatory process to construct Energy Gateway South and Energy Gateway
West Sub-Segment D.1, which will connect eastern Wyoming to central Utah, enhance
system reliability and provide access to more generation resources.
Expanded conservation measures
We’re championing technical innovations that use fast-acting residential demand response
resources to support the bulk power system. Our approach moves beyond peak-load management
to create a grid-scale solution that turns demand response resources into frequency-responsive
operating reserves. With over 100,000 customers participating in our program, more than 200 MW
of operating reserve are available every day and can be dispatched in a matter of seconds. This
reduces our need to buy reserve power on the market, and it’s only used in emergencies,
minimizing inconvenience to customers.
Our partnership with The Wasatch Group enabled us to develop and manage a first-of-its-kind
battery demand response solution at an all-electric apartment building. That success has shaped a
new battery demand response option for any Utah customer with on-site solar generation. The
network of renewable energy stored in customer-owned batteries will enable greater use of
renewable power, improves overall grid resiliency, and helps keep prices down.
In the coming years, our ongoing conservation and cost-effective demand-response initiatives will
target to deliver:
• 603 MW of energy efficiency between 2021-2024
• 549 MW of demand response2 between 2021-2024
Putting our shared vision to work for our customers
Our 2021 IRP is grounded in our commitment to deliver reliable, affordable power to all our
customers through a dynamic, connected grid. It is the roadmap for a future of clean energy and
strengthened infrastructure to support the delivery of this essential service. It’s shaped by our
customers and communities, and new technologies and programs, like demand response. And it’s
2 Capacity impacts for demand response include both summer and winter impacts within a year.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
7
bolstered by innovations in power generation and storage that will help decarbonize our portfolio
while lowering costs and increasing reliability.
This is the vision, with clear, measurable steps that will connect the region to its massive energy
generating potential and leverage our transmission infrastructure across our six-state area to
enhance reliability and resilience throughout the West.
By investing in resilience, through expanded and modernized transmission, a hardened grid, and a
diverse, increasingly clean portfolio, we are delivering on our commitment to ensuring safe,
reliable, affordable power for our customers, now and for generations to come.
PacifiCorp’s Integrated Resource Plan Approach
PacifiCorp has been making progress in its efforts to bring the best of the West to its customers,
and PacifiCorp’s 2021 IRP presents the company’s plans to continue to make significant
advancements in this vision. The 2021 IRP sets forth a clear path to provide reliable and reasonably
priced service to its customers. The analysis supporting this plan helps PacifiCorp, its customers,
and its regulators understand the effect of both near-term and long-term resource decisions on
customer bills, the reliability of electric service PacifiCorp customers receive, and changes to
emissions from the generation sources used to serve customers. In the 2021 IRP, PacifiCorp
presents a preferred portfolio that builds on its vision to deliver energy affordably, reliably and
responsibly through near-term investments in transmission infrastructure that will facilitate
continued growth in new renewable resource capacity while maintaining substantial investment in
energy efficiency and demand response programs. All of this can be achieved by maintaining
reliable service with incremental investments in transmission infrastructure and other non-emitting
flexible resources capable of shaping and responding to changes in energy from an increasing
supply of wind and solar resources.
The primary objective of the IRP is to identify the best mix of resources to serve customers in the
future. The best mix of resources is identified through analysis that measures cost and risk. The
least-cost, least-risk resource portfolio—defined as the “preferred portfolio”—is the portfolio that
can be delivered through specific action items at a reasonable cost and with manageable risks,
while considering customer demand for clean energy and ensuring compliance with state and
federal regulatory obligations.
The full planning process is completed every two years, with a review and update completed in
the off years. Consequently, these plans, particularly the longer-range elements, can and do change
over time. PacifiCorp’s 2021 IRP was developed through an open and extensive public process,
with input from an active and diverse group of stakeholders, including customer advocacy groups,
community members, regulatory staff, and other interested parties. The public-input process began
with the first public-input meeting in January 2020. Over the subsequent year and a half,
PacifiCorp met with stakeholders and hosted eighteen public-input meetings. Throughout this
effort, PacifiCorp received valuable input from stakeholders and presented findings from a broad
range of studies and technical analyses that shaped and informed the 2021 IRP.
As depicted in Figure 1.2, PacifiCorp’s 2021 IRP was developed by working through five
fundamental planning steps that began with development of key inputs and assumptions to inform
the modeling and portfolio-development process. The portfolio-development process is where
PacifiCorp produced a range of different resource portfolios that meet projected gaps in the load
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
8
and resource balance, each uniquely characterized by the type, timing, and location of new
resources in PacifiCorp’s system. The resource portfolios produced for the 2021 IRP were created
considering a wide range of potential coal retirement dates, options to convert to gas or to retrofit
for carbon capture utilization and sequestration for certain coal units, and other planning
uncertainties.
PacifiCorp then developed variants of the top performing resource portfolio to further analyze
impacts of specific resource actions within the top performing portfolio. In the resource portfolio
analysis step, PacifiCorp conducted targeted reliability analysis to ensure portfolios had sufficient
flexible capacity resources to meet reliability requirements. PacifiCorp then analyzed these
different resource portfolios to measure the comparative cost, risk, reliability, and emission levels.
This resource portfolio analysis ultimately informed selection of the least-cost and least-risk
portfolio, the 2021 IRP preferred portfolio and development of the associated near-term resource
action plan. Throughout this process, PacifiCorp considered a wide range of factors to develop key
planning assumptions and to identify key planning uncertainties, with input from its stakeholder
group. Supplemental studies were also done to produce specific modeling assumptions.
Figure 1.2 – Key Elements of PacifiCorp’s 2021 IRP Approach
Preferred Portfolio Highlights
PacifiCorp’s selection of the 2021 IRP preferred portfolio is supported by comprehensive data
analysis and an extensive public-input process, described in the chapters that follow. Figure 1.3
shows that PacifiCorp’s 2021 preferred portfolio continues to include substantial new renewables,
facilitated by incremental transmission investments, demand-side management (DSM) resources,
significant storage resources, and for the first time, advanced nuclear.
By the end of 2024, the 2021 IRP preferred portfolio includes the 2020 All-Source Request for
Proposals (RFP) final shortlist resources. These projects include 1,792 MW of wind, 1,302 MW
of solar additions, and 697 MW of battery storage capacity—497 MW paired with solar and a 200
MW standalone battery. During this time, the preferred portfolio also includes the acquisition and
repowering of Rock River I (49 MW) and Foote Creek II-IV (43 MW) wind projects located in
Wyoming. Through the end of 2026, the 2021 IRP preferred portfolio includes an additional 745
MW of wind and an additional 600 MW solar co-located with storage. The 2021 IRP preferred
portfolio includes the 500 MW advanced nuclear NatriumTM demonstration project, which will
come online by summer 2028. Through 2040, the 2021 IRP preferred portfolio includes 1,000 MW
of additional advanced nuclear resources and 1,226 MW of non-emitting peaking resources.
Over the 20-year planning horizon, the 2021 IRP preferred portfolio includes 3,628 MW of new
wind and 5,628 MW of new solar co-located with storage.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
9
Figure 1.3 – 2021 IRP Preferred Portfolio (All Resources)
To facilitate the delivery of new renewable energy resources to PacifiCorp customers across the
West, the preferred portfolio includes additional transmission investment. Specifically, the 2021
IRP preferred portfolio includes the Energy Gateway South transmission line - a new 416-mile
high-voltage 500-kilovolt transmission line and associated infrastructure running from the new
Aeolus substation near Medicine Bow, Wyoming, to the Clover substation near Mona, Utah. The
2021 preferred portfolio also includes the Energy Gateway West Subsegment D.1 project - a new
59-mile, high-voltage (230-kilovolt) transmission line from the Shirley Basin substation in
southeastern Wyoming to the Windstar substation near Glenrock, Wyoming. Both transmission
lines will come online by the end of 2024.
The 2021 IRP preferred portfolio also includes a 290-mile high-voltage 500-kilovolt transmission
line known as Boardman-to-Hemingway, which connects those respective substations in Oregon
and Idaho, which will come online in 2026. Further, the 2021 IRP preferred portfolio further
includes near-term and long-term transmission upgrades across the system that will facilitate
continued and long-term growth in new resources needed to serve our customers. Table 1.1
summarizes the incremental transmission projects in the 2021 IRP preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
10
Table 1.1 – Transmission Projects Included in the 2021 IRP Preferred Portfolio1,2,*
1 - TTC = total transfer capability. The scope and cost of transmission upgrades are planning estimates. Actual scope
and costs will vary depending upon the interconnection queue, the transmission service queue, the specific location of
any given generating resource and the type of equipment proposed for any given generating resource.
2 - Energy Gateway South is modeled in the 2021 IRP as a contingent option with bids in the 2020 All-Source Request
for Proposals. Other transmission options prior to 2026 are not modeled as transmission requirements and costs are
accounted for in the 2020 All-Source Request for Proposals transmission cluster study for all other resource bids.
* - Reclaimed transmission is committed with resources with a commercial operation date later than the date of
retirement.
New Solar Resources
The 2021 IRP preferred portfolio includes 1,302 MW of new solar by the end of 2024 and 1,902
MW by the end of 2026. Through 2040, more than 5,600 MW of new solar is online as shown in
Figure 1.4.
Year Resource(s)From To Description
2025 1,641 MW RFP Wind (2025)Aeolus WY Clover Enables 1,930 MW of interconnection with 1700
MW of TTC: Energy Gateway South
2026 615 MW Wind (2026)Enables 615 MW of interconnection: Albany OR area
reinforcement
130 MW Wind (2026)
450 MW Wind (2032)
650 MW Battery (2037)
2026 600 MW Solar+Storage (2026)Borah-Populous Hemingway Enables 600 MW of interconnection with 600 MW
of TTC: B2H Boardman-Hemingway
2028 41 MW Solar+Storage (2028)
377 MW Solar+Storage (2030)
Enables 460 MW of interconnection: Medford area
reinforcement
2030 160 MW Solar+Wind+Storage (2030)
20 MW Solar+Storage (2030)
Enables 180 MW of interconnection: Yakima local
area reinforcement
2031 820 MW Solar+Storage (2031)
206 MW Non-Emitting Peaker (2033)
Enables 1040 MW of interconnection: Northern UT
345 kV reinforcement
2033 400 MW Non-Emitting Peaker (2033)
1100 MW Solar+Storage (2033)Southern UT Northern UT
Enables 1500 MW of interconnection with 800 MW
TTC: Spanish Fork - Mercer 345 kV; New Emery –
Clover 345 kV
Reclaimed transmission upon retirement of Dave
Johnston Plant
2028*500 MW Adv Nuclear (2028)Southwest Wyoming
Transmission Area
Reclaimed transmission upon retirement of Naughton
1 & 2
Transmission Area
Bridger WY
2029*549 MW Battery (2029)Eastern Wyoming
Transmission Area
2026
Within Willamette Valley OR Transmission Area
2040 Central OR Willamette Valley
Within Southern OR Transmission Area
156 MW Solar+Storage (2040)
500 MW Pumped Storage (2040)
Enables 2080 MW of interconnection with 1950
MW TTC; Portland Coast area reinforcement,
Willamette Valley and Southerm Oregon
Yakima WA Transmission Area
Northern UT Transmission Area
Portland North Coast
Willamette Valley
Southern Oregon
Enables 980 MW of interconnection with 1500 MW
of TTC
Reclaimed transmission upon retirement of Wyodak Transmission Area
2037 909 MW Solar+Storage (2037)Reclaimed transmission upon retirement of
Huntington 1 & 2
2038 412 MW Non-Emitting Peaker (2038)
1000 MW Adv Nuclear (2038)Transmission Area
2040 206 MW Non-Emitting Peaker (2040)
60 MW Wind (2040)
Eastern Wyoming
Reclaimed transmission upon retirement of Jim
Bridger Plant
Southern Utah
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
11
Figure 1.4 – 2021 IRP Preferred Portfolio New Solar Capacity*
*Note: 2021 IRP solar capacity shown in the figure includes solar resources coming via the 2020 All-Source Request
for Proposals by the end of 2024. Resources are shown in the first full year of operation (the year after the year-online
dates).
New Wind Resources
As shown in Figure 1.5, by the end of 2024, PacifiCorp’s 2021 IRP preferred portfolio includes
1,792 MW of new wind generation resulting from the 2020 AS RFP and the acquisition and
repowering of Rock River I (49 MW) and Foote Creek II-IV (43 MW). Through the end of 2026,
the 2021 IRP preferred portfolio includes an additional 745 MW of new wind and more than 3,700
MW of new wind by 2040.
Figure 1.5 – 2021 IRP Preferred Portfolio New Wind Capacity*
*Note: Wind additions shown are incremental to Energy Vision 2020 and other projects that have come online over
the past few years. Resources are shown in the first full year of operation (the year after year-end online dates).
New Storage Resources
New storage resources in the 2021 IRP preferred portfolio are summarized in Figure 1.6. The 2021
IRP preferred portfolio includes nearly 700 MW of battery storage by the end of 2024 – 200 MW
of which is a standalone battery and the remaining portion paired with solar resources resulting
from the 2020 All-Source RFP. Through 2040, the 2021 IRP includes 4,781 MW of storage co-
located with solar resources,1,400 MW of standalone battery, and 500 MW of pumped hydro.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
12
Figure 1.6 – 2021 IRP Preferred Portfolio New Storage Capacity*
*Note: Resources are shown in the first full year of operation (the year after the year-end online dates).
Other Non-Emitting Resources
This is the first PacifiCorp IRP that includes new advanced nuclear and non-emitting peaking
resources as part of its least-cost, least-risk preferred portfolio. As shown in Figure 1.7, the 500
MW advanced nuclear NatriumTM demonstration project will come online by summer 2028.
Through 2040, the 2021 IRP preferred portfolio includes 1,000 MW of additional advanced
nuclear resources and 1,226 MW of non-emitting peaking resources.
Figure 1.7 – 2021 IRP Other Non-Emitting Resources Capacity*
*Note: Resources are shown in the first full year of operation (the year after the year-end online dates).
Demand-Side Management
PacifiCorp evaluates new DSM opportunities, which includes both energy efficiency and direct
load control programs, as a resource that competes with traditional new generation and wholesale
power market purchases when developing resource portfolios for the IRP. Consequently, the load
forecast used as an input to the IRP does not reflect any incremental investment in new energy
efficiency programs; rather, the load forecast is reduced by the selected additions of energy
efficiency resources in the IRP. Figure 1.8 shows that PacifiCorp’s load forecast before
incremental energy efficiency savings has increased relative to projected loads used in the 2019
IRP. On average, forecasted system load is up 2.2 percent and forecasted coincident system peak
is up 1.1 percent when compared to the 2019 IRP. Over the planning horizon, the average annual
growth rate, before accounting for incremental energy efficiency improvements, is 1.21 percent
for load and 0.73 percent for peak. Changes to PacifiCorp’s load forecast are driven by higher
projected demand from data centers driving up the commercial forecast and an increased
residential forecast.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
13
Figure 1.8 – Load Forecast Comparison between Recent IRPs (Before Incremental Energy
Efficiency Savings)
DSM resources continue to play a key role in PacifiCorp’s resource mix. The chart to the left in
Figure 1.9 compares total energy efficiency capacity savings in the 2021 IRP preferred portfolio
relative to the 2019 IRP preferred portfolio and includes 4,290 MW by the end of the planning
period.
In addition to continued investment in energy efficiency programs, the preferred portfolio shows
an increasing role for incremental direct load control programs. The chart to the right in Figure 1.9
compares cumulative capacity of direct load control program capacity in the 2021 IRP preferred
portfolio relative to the 2019 IRP preferred portfolio and does not include capacity from existing
programs. In the 2021 IRP, direct load control resources previously identified in the 2019 IRP and
solicited via a demand response RFP, were modeled in addition to resources from the CPA
assessing the upper limit of demand response opportunities and value within the IRP. This allowed
for the evaluation of real-time resources as a substitute for front office transactions. The 2021 IRP
has a cumulative capacity of direct load control programs reaching 2,448 MW by 2040 – an over
400% increase over the planning horizon from the 2019 IRP.
Figure 1.9 – 2021 IRP Preferred Portfolio Energy Efficiency (Class 2 DSM) and Direct Load
Control Capacity (Class 1 DSM)
Wholesale Power Market Prices and Purchases
Figure 1.10 shows that the 2021 IRP’s base case forecast for natural gas prices has decreased along
with a decrease in wholesale power prices for most years relative to those in the 2019 IRP. These
forecasts are based on prices observed in the forward market and on projections from third-party
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
14
experts. The lower power prices observed in the 2021 IRP are primarily driven by the assumption
of lower natural gas prices than what was assumed in the 2019 IRP. Wholesale power prices are
higher in 2027 to 2031 because of higher inflation impacting new resource costs. Moreover, the
2021 IRP assumed lower natural gas prices than the 2019 IRP as Henry Hub in particular, is
softened by limited pipeline expansion lowering liquefied natural gas exports. While not shown in
the figure below, the 2021 IRP also evaluated low and high price scenarios when evaluating the
cost and risk of different resource portfolios.
Figure 1.10 – Comparison of Power Prices and Natural Gas Prices in Recent IRPs
Figure 1.11 shows an overall decline in reliance on wholesale power market firm purchases in the
2021 IRP preferred portfolio relative to the wholesale power market purchases included in the
2019 IRP preferred portfolio. In particular, reliance on wholesale power market purchases during
summer peak periods averages 366 MW per year over the 2020-2027 timeframe—down 60 percent
from wholesale power market purchases identified in the 2019 IRP preferred portfolio. This
reduction in wholesale power market purchases coincides with the period over which there are
resource adequacy concerns in the region. While wholesale power market purchases increase
beyond 2027, PacifiCorp is actively participating in regional efforts to develop day-ahead markets
and a resource adequacy program that will help unlock regional diversity and facilitate market
transactions over the long term.
Figure 1.11 – 2021 IRP Preferred Portfolio Market Purchases
Coal and Gas Retirements/Gas Conversions
Coal resources have been an important resource in PacifiCorp’s resource portfolio for many years.
However, there have been material changes in how PacifiCorp has been operating these assets (i.e.,
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
15
by lowering operating minimums and optimizing dispatch through the EIM) that has enabled the
company to reduce fuel consumption and associated costs and emissions, and instead buy
increasingly low-cost, zero-emissions renewable energy from market participants across the West,
which is accessed by our expansive transmission grid. PacifiCorp’s coal resources will continue
to play a pivotal role in following fluctuations in renewable energy as the remaining coal units
approach retirement dates. Driven in part by ongoing cost pressures on existing coal-fired facilities
and dropping costs for new resource alternatives, of the 22 coal units currently serving PacifiCorp
customers, the preferred portfolio includes retirement of 14 of the units by 2030 and 19 of the units
by the end of the planning period in 2040. As shown in Figure 1.12, coal unit retirements/gas
peaker conversions in the 2021 IRP preferred portfolio will reduce coal-fueled generation capacity
by 1,300 MW by the end of 2025, over 2,200 MW by 2030, and over 4,000 MW by 2040.
Coal unit retirements scheduled under the preferred portfolio include:
• 2023 = Jim Bridger Units 1-2, converted to natural gas peakers in 2024 (same retirement
year for Jim Bridger 1 in 2019 IRP and instead of 2028 for Jim Bridger 2 in the 2019 IRP).
• 2025 = Naughton Units 1-2 (same as 2019 IRP)
• 2025 = Craig Unit 1 (same as 2019 IRP)
• 2025 = Colstrip Units 3-4 (instead of 2027 in the 2019 IRP)
• 2027 = Dave Johnston Units 1-4 (same as 2019 IRP)
• 2027 = Hayden Unit 2 (instead of 2030 in the 2019 IRP)
• 2028 = Craig Unit 2 (instead of 2026 in the 2019 IRP)
• 2028 = Hayden Unit 1 (instead of 2030 in the 2019 IRP)
• 2036 = Huntington Units 1-2 (same as 2019 IRP)
• 2037 = Jim Bridger Units 3-4 (same as 2019 IRP)
• 2039 = Wyodak (same as 2019 IRP but outside of 2019 IRP planning horizon)
Figure 1.12 – 2021 IRP Preferred Portfolio Coal Retirements/Gas Conversions*
* Note: Coal retirements are assumed to occur by the end of the year before the year shown in the graph. The graph
shows the year in which the capacity will not be available for meeting summer peak load. All figures represent
PacifiCorp’s ownership share of jointly owned facilities.
In addition to the coal unit retirements outlined above, the preferred portfolio reflects 1,554 MW
natural gas retirements through 2040. This includes Naughton Unit 3 at the end of 2029, Gadsby
at the end of 2032, Hermiston at the end of 2036, and Jim Bridger Units 1 and 2 at the end of 2037.
Carbon Dioxide Emissions
The 2021 IRP preferred portfolio reflects PacifiCorp’s on-going efforts to provide cost-effective
clean-energy solutions for our customers and accordingly reflects a continued trajectory of
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
16
declining carbon dioxide (CO2) emissions. PacifiCorp’s emissions have been declining and
continue to decline related to several factors including PacifiCorp’s participation in the EIM,
which reduces customer costs and maximizes use of clean energy; PacifiCorp’s on-going transition
to clean-energy resources including new renewable resources, new advanced nuclear resources,
new non-emitting resources, storage, transmission, and Regional Haze compliance that capitalizes
on flexibility.
The chart on the left in Figure 1.13 compares projected annual CO2 emissions between the 2021
IRP and 2019 IRP preferred portfolios. In this graph, emissions are not assigned to market
purchases or sales, and in 2026, annual CO2 emissions are down 26 percent relative to the 2019
IRP preferred portfolio. By 2030, average annual CO2 emissions are down 34 percent relative to
the 2019 IRP preferred portfolio, and down 52 percent in 2035. By the end of the planning horizon,
system CO2 emissions are projected to fall from 39.1 million tons in 2021 to 4.8 million tons in
2040—a reduction of 88 percent.
The chart on the right in Figure 1.13 includes historical data, assigns emissions at a rate of 0.4708
tons CO2 equivalent per MWh to market purchases (with no credit to market sales), includes
emissions associated with specified purchases, and extrapolates projections out through 2050. This
graph demonstrates that relative to a 2005 baseline, system CO2 equivalent emissions are down 53
percent in 2025, 74 percent in 2030, 83 percent in 2035, 92 percent in 2040, 94 percent in 2045,
and 98 percent in 2050.
Figure 1.13 – 2021 IRP Preferred Portfolio CO2 Emissions and PacifiCorp CO2 Equivalent
Emissions Trajectory*
*Note: PacifiCorp CO2 equivalent emissions trajectory reflects actual emissions through 2020 from owned facilities,
specified sources and unspecified sources. From 2021 through the end of the twenty-year planning period in 2040,
emissions reflect those from the 2021 IRP preferred portfolio with emissions from specified sources reported in CO2
equivalent. Market purchases are assigned a default emission factor (0.4708 short tons CO2e/MWh) – emissions from
sales are not removed. Beyond 2040, emissions reflect the rolling average emissions of each resource from the 2021
IRP preferred portfolio through the life of the resource. The emissions trajectory does not incorporate clean energy
targets set forth in Oregon House Bill 2021 or any other state-specific emissions trajectories. PacifiCorp expects these
targets, and an Oregon-specific emissions trajectory, to be incorporated following the 2023 integrated resource plan
when PacifiCorp is required under the bill to file a Clean Energy Plan.
Renewable Portfolio Standards
Figure 1.14 shows PacifiCorp’s renewable portfolio standard (RPS) compliance forecast for
California, Oregon, and Washington after accounting for new renewable resources in the preferred
portfolio. While these resources are included in the preferred portfolio as cost-effective system
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
17
resources and are not included to specifically meet RPS targets, they nonetheless contribute to
meeting RPS targets in PacifiCorp’s western states.
Oregon RPS compliance is achieved through 2040 with the addition of new renewable resources
and transmission in the 2021 IRP preferred portfolio. Washington RPS compliance is achieved
with the benefit of increased system renewable resources beginning 2021 as well as additional
resources procured that meet the state’s Clean Energy Transformation Act. Under PacifiCorp’s
2020 Protocol, and the Washington Interjurisdictional Allocation Methodology, Washington’s
RPS position is improved by receiving a system share of renewable resources across the
PacifiCorp’s system.
The California RPS compliance position will be met with owned and contracted renewable
resources, as well as REC purchases throughout the 2021 IRP study period. The ramping RPS
requirement results in an increased need for unbundled REC purchases to meet the annual and
compliance period targets in 2021-2040. New renewable resources and transmission in the 2021
IRP preferred portfolio mitigate that shortfall, but the company may need to purchase
approximately 200,000 RECs in compliance periods 4 and 5, 2021-2024 and 2025-2028,
respectively. Beyond 2028, the company may need to purchase 200,000-300,000 RECs per year
to meet the ramping RPS.
While not shown in Figure 1.14, PacifiCorp meets the Utah 2025 state target to supply 20 percent
of adjusted retail sales with eligible renewable resources with existing owned and contracted
resources and new renewable resources and transmission in the 2021 IRP preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
18
Figure 1.14 – Annual State RPS Compliance Forecast
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
RE
C
s
(
T
h
o
u
s
a
n
d
s
)
Oregon RPS
Unbundled Surrendered Bundled SurrenderedUnbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement
0
200
400
600
800
RE
C
s
(
T
h
o
u
s
a
n
d
s
)
California RPS
Unbundled Surrendered Bundled SurrenderedUnbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement
0
500
1,000
1,500
2,000
RE
C
s
(
T
h
o
u
s
a
n
d
s
)
Washington RPS
Unbundled Surrendered Bundled SurrenderedUnbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
19
2021 IRP Advancements and Supplemental Studies
IRP Advancements
During each IRP planning cycle, PacifiCorp identifies and implements advancements to
continuously improve the IRP for its customers, other stakeholders, and regulatory commissions.
Some of the key advancements implemented in the 2021 IRP include:
• Implementation of Advanced Modeling System
As part of its 2021 IRP, PacifiCorp implemented a new and more advanced third-party
software to conduct its long-term capacity expansion modeling, hourly dispatch simulations of
resource portfolios and stochastic modeling. PacifiCorp implemented the Plexos modeling
system by Energy Exemplar. The three platforms of the Plexos tool (referred to as Long-term
(LT), Medium-term (MT) and Short-term (ST)) work on an integrated basis to inform the
optimal combination of resources by type, timing, size, and location over PacifiCorp’s 20-year
planning horizon. The Plexos tool also allows for improved endogenous modeling of resource
options simultaneously, greatly reducing the volume of individual portfolios needed to
evaluate impacts of varying resource decisions. See Volume I, Chapter 8 (Modeling and
Portfolio Evaluation Approach) for more information.
• Endogenous Modeling of Resources
As part of it 2021 IRP, the Plexos model was able to endogenously consider coal retirement
timing options along with other specified options such as gas conversion or carbon capture
utilization and sequestration retrofit for a coal unit. In addition, the Plexos model had the ability
to endogenously view costs and transmission capability associated with certain transmission
upgrades that allowed for selection of specific transmission investments that coincide with new
resource additions. Endogenous transmission modeling capabilities include the consideration
of 1) new incremental transmission options tied to resource selections, 2) existing transmission
rights tied to the use of post-retirement brownfield sites, and 3) incorporation of costs
associated with these transmission options, and 4) transmission options that interact with
multiple or complex elements of the IRP transmission topology. Endogenous modeling of
standalone and co-located battery resources was also improved with the Plexos model over the
2019 IRP. In the 2019 IRP, optimization of dispatch, charging and reserves for batteries was
modeled using an external tool, and the results brought back into the primary model. In the
2021 IRP, Plexos allows for the endogenous treatment of the entirety of battery optimization.
See Volume I, Chapter 8 (Modeling and Portfolio Evaluation Approach) for more information.
• Targeted Portfolio Reliability Analysis
In the 2021 IRP, PacifiCorp further advanced its approach for assessing the reliability of
resource portfolios and the ability of each unique resource portfolio to meet reliability
requirements. This IRP incorporates operating reserves in the LT model for capacity expansion
and optimizes available resources to meet requirements in all periods, not just the system peak.
With significant levels of economic renewable resource being selected in every resource
portfolio, PacifiCorp found that subsequent modeling of these resource portfolios using the
Short-Term (ST) hourly dispatch model, which considers more granularity and an explicit
accounting of operating reserve requirements, consistently identified capacity shortfalls
needed to maintain reliable operation of the system. PacifiCorp ran 20-year ST studies to
evaluate shortfalls on a portfolio-specific basis across each year of the 20-year planning
horizon. From the results of these hourly deterministic ST runs PacifiCorp developed a process
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
20
to remedy the incremental need for reliability resources through cost-effective resource
additions to a portfolio to ensure there is sufficient flexible capacity to meet reliability
requirements. See Volume I, Chapter 8 (Modeling and Portfolio Evaluation Approach) for
more information.
• Improvements in Modeling Assumptions
In the 2021 IRP, PacifiCorp improved several modeling assumptions including weather-
adjusted energy efficiency, wind and solar to better align with the load forecast, re-bundling
energy efficiency supply-side resource options on a net cost of capacity basis, optimizing
battery dispatch that adheres to charging constraints within the Plexos model, and multipath
endogenous transmission modeling options. See Volume I, Chapter 8 (Modeling and Portfolio
Evaluation Approach) for more information.
• Stakeholder Requests and Feedback
In its 2021 IRP, in addition to PacifiCorp’s stakeholder feedback form process of posting the
forms received from stakeholders as well as PacifiCorp’s response throughout the public-input
process, PacifiCorp has also summarized the stakeholder feedback forms received and how
feedback was considered as part of the 2021 IRP document. PacifiCorp received and responded
to over 450 stakeholder feedback forms in the 2021 IRP. PacifiCorp was able to accommodate
numerous stakeholder requests to develop additional scenarios and sensitivities during the
public-input process. PacifiCorp and stakeholders collaborated to identify potential scenarios,
and scenarios selected for inclusion included an analysis of accelerated coal retirements,
variations of “business-as-usual” cases, alternate DSM bundling methodologies, and other
updates to modeling inputs. A full summary of requests received and considered can be found
in Volume II, Appendix C (Public Input Process).
• Public-Input Meetings
PacifiCorp began its public-input process for the 2021 IRP development cycle much earlier
than prior IRP development cycles with a series of three public-input meetings that were
technical workshops on the Conservation Potential Assessment to inform development of
PacifiCorp’s demand-side management planning assumptions. In addition, due to the
pandemic that emerged during the 2021 IRP development cycle, PacifiCorp was able to pivot
and continue robust stakeholder participation throughout its public-input meeting process by
holding the meetings via Microsoft Teams platform and phone conference. This enabled the
option for video connectivity when available and simultaneous viewing of meeting material
via the online platform. See Volume II, Appendix C (Public Input Process) for more
information.
Supplemental Studies
PacifiCorp’s 2021 IRP relies on numerous supplemental studies that support the derivation of
specific modeling assumptions critical to development of its long-term resource plan. A
description of these studies, discussed in more detail in 2021 IRP and appendices filed with the
2021 IRP, is provided below. Additional source files and information may also be located for some
studies on PacifiCorp’s IRP webpage at the following location:
www.pacificorp.com/energy/integrated-resource-plan.html
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
21
• Capacity Contribution
The capacity contribution of a resource is dependent on the other components in a portfolio,
and PacifiCorp’s portfolio development process is based on achieving reliable system
operation using the aggregate contributions of each resource in the portfolio, rather than
focusing on an individual estimate. For reporting, the capacity factor approximation method
(CF Method) was used to identify marginal capacity contribution values for individual resource
options, based on a portfolio similar to the preferred portfolio.
• Conservation Potential Assessment
An updated conservation potential assessment (CPA) prepared by Applied Energy Group
(commissioned by PacifiCorp) and the Energy Trust of Oregon was prepared to develop DSM
resource potential and cost assumptions specific to PacifiCorp’s service territory. The CPA
supports the cost and DSM savings data used during the portfolio-development process.
• Energy Storage Potential Evaluation
Energy storage resources can provide a variety of grid services since they are highly flexible,
with the ability to respond to dispatch signals and act as both a load and a resource. This
evaluation, refreshed for the 2021 IRP, provides details on these grid services and on how
energy storage resources can be configured and sited to maximize the benefits they provide.
• Flexible Reserve Study
This study, updated for the 2021 IRP, evaluates the need for flexible resources resulting from
the variability and uncertainty in load, wind, solar, and other generation resources. The study
produces an estimate of flexible reserve needs for each hour that accounts for the specific
load, wind, and solar resources being evaluated. Reserve costs associated with meeting these
flexible reserve needs are also estimated.
• Plant Water Consumption Study
This study provides updated data on the water consumption of PacifiCorp-owned generating
facilities by fuel type and by state in which the facility is located.
• Private Generation Resource Assessment
This supplemental study, prepared by Guidehouse (formerly Navigant Consulting, Inc.), was
refreshed for the 2021 IRP to produce updated private generation penetration forecasts for solar
photovoltaic, small-scale wind, small-scale hydro, combined heat and power reciprocating
engines, and combined heat and power micro-turbines specific to PacifiCorp’s service
territory. The private generation penetration forecasts from this study are applied as a reduction
to forecasted load throughout the IRP modeling process and used in developing assumptions
for the low private generation sensitivity and high generation sensitivity cases.
• Smart Grid
PacifiCorp has included an update on its Smart Grid efforts with a focus on transmission and
distribution systems and customer information.
• Stochastic Parameter Update
PacifiCorp’s preferred portfolio-selection process relies, in part, on stochastic risk analysis
using Monte Carlo random sampling of stochastic variables. Stochastic variables include
natural gas and wholesale electricity prices, load, hydro generation, and unplanned thermal
outages. For the 2021 IRP, PacifiCorp updated its stochastic parameter input assumptions with
more current historical data.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
22
• Renewable Resources Assessment
A study on renewable resources and energy storage was commissioned to support PacifiCorp’s
2021 Integrated Resource Plan (IRP). The 2020 Renewable Resources Assessment, prepared
by Burns & McDonnell Engineering Company, Inc. (BMcD) is screening-level in nature and
includes a comparison of technical capabilities, capital costs, and operations and maintenance
costs that are representative of renewable energy and storage technologies. BMcD evaluated
energy storage options of Pumped Hydro Energy Storage, Compressed Air Energy Storage,
Lithium-Ion Battery, Flow Battery, as well as wind and solar and combinations of these
resource types.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
23
Action Plan
The 2021 IRP action plan identifies specific resource actions. PacifiCorp will take over the next two-to-four years to deliver resources
included in the preferred portfolio. Action items are based on the type and timing of resources in the preferred portfolio, findings from
analysis completed during the development of the 2021 IRP, and other resource activities described in the 2021 IRP. Table 1.2 details
specific 2021 IRP action items by category.
Table 1.2 – 2021 IRP Action Plan
Action Item 1. Existing Resource Actions
1a
Colstrip Units 3 and 4:
• PacifiCorp will continue to work closely with co-owners to seek the most cost-effective path forward toward the
2021 IRP preferred portfolio target exit date of December 31, 2025.
1b
Craig Unit 1:
• PacifiCorp will continue to work closely with co-owners to seek the most cost-effective path forward toward the
2021 IRP preferred portfolio target exit date of December 31, 2025.
1b
Naughton Units 1 and 2:
• PacifiCorp will initiate the process of retiring Naughton Units 1-2 by the end of December 2025, including
completion of all required regulatory notices and filings.
• By the end of Q2 2023, PacifiCorp will confirm transmission system reliability assessment and year-end 2025
retirement economics in 2023 IRP filing.
• By the end of Q4 2023, PacifiCorp will initiate the process with the Wyoming Public Service Commission for
approval of a reverse request for proposals for a potential sale of Naughton Units 1 and 2.
• By the end of Q4 2023, PacifiCorp will administer termination, amendment, or close-out of existing permits,
contracts, and other agreements.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
24
1c
Jim Bridger Units 1 and 2 Gas Conversion:
• PacifiCorp will initiate the process of ending coal-fueled operations and seeking permitting for a natural-gas
conversion by 2024, including completion of all required regulatory notices and filings.
• By the end of Q2 2022, PacifiCorp will finalize an employee transition plan.
• By the end of Q2 2022, PacifiCorp will develop a community action plan in coordination with community leaders.
• By the end of Q4 2023, PacifiCorp will administer termination, amendment, or close-out of existing permits,
contracts, and other agreements.
• By the end of Q4, 2023, PacifiCorp will remove units 1 and 2 from Washington’s allocation of electricity.
1d
Carbon Capture, Utilization, and Sequestration/Wyoming House Bill 200 Compliance:
• PacifiCorp issued a carbon capture, utilization, and sequestration (CCUS) request for expression of interest (REOI)
on June 29, 2021. PacifiCorp will complete the 2021 CCUS REOI process and utilize any new relevant
information. Additional model sensitivities will be run accordingly.
• PacifiCorp will issue a CCUS Request for Proposals (RFP) in 2022. The 2021 CCUS REOI responses will inform
the scope of the CCUS RFP.
• A completed CCUS Front End Engineering & Design Study (FEED Study) based on a new CCUS technology was
submitted to PacifiCorp in July 2021 for Dave Johnston Unit 2. Third-party review of the FEED Study will be
completed by Q1 2022, and model sensitivities will subsequently be run as needed, with FEED Study assumptions
and inputs as appropriate.
• Subject to finalization of rules by the Wyoming Public Service Commission (WPSC) to implement House Bill 200
(HB 200), the Wyoming Low Carbon Energy Standard (anticipated by Q4 2021), by March 31, 2022, PacifiCorp
will file with the WPSC an initial CCUS application to establish intermediate CCUS standards and requirements.
• Subject to finalization of rules by the WPSC to implement HB 200, the Wyoming Low Carbon Energy Standard
(anticipated by Q4 2021), PacifiCorp will submit for WPSC approval a final plan with its proposed energy portfolio
standard for dispatchable and reliable low-carbon electricity, its plan for achieving the standard, and a target date of
no later than July 1, 2030.
1e
Regional Haze Compliance:
• Following the resolution of first planning period regional haze compliance disputes, and the submission of second
planning period regional haze state implementation plans, PacifiCorp will evaluate and model any emission control
retrofits, emission limitations, or utilization reductions that are required for coal units.
• PacifiCorp will continue to engage with the Environmental Protection Agency, state agencies, and stakeholders to
achieve second planning period regional haze compliance outcomes that improve Class I visibility, provide
environmental benefits, and are cost effective.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
25
Action Item 2. New Resource Actions
2a
Customer Preference Request for Proposals:
• Consistent with Utah Community Renewable Energy Act, PacifiCorp continues to work with eligible communities
to develop program to achieve goal of being net 100 percent renewable by 2030; PacifiCorp anticipates filing an
application for approval of the program with the Utah Public Service Commission in 2022, which may necessitate
issuance of a request for proposals to procure resources within the action plan window.
2b
Acquisition and Repowering of Foote Creek II-IV and Rock River I:
• In Q3 2021, PacifiCorp will pursue necessary regulatory approvals to authorize the acquisition and repowering of
Foote Creek II-IV in order to issue repowering contracts in Q1 2022 in support of a late 2023 in-service date.
• In Q1 2022, PacifiCorp will pursue necessary regulatory approvals to authorize the acquisition and repowering of
Rock River I following the expiration of the existing power purchase agreement in order to issue repowering
contracts in Q3 2022 to support a late 2024 in-service date.
2c
NatriumTM Demonstration Project:
• PacifiCorp will continue to monitor key TerraPower milestones for development and will make regulatory filings,
as applicable.
• By the end of 2022, PacifiCorp will finalize commercial agreements for the NatriumTM project.
• Q1 2022, PacifiCorp will develop a community action plan in coordination with community leaders.
• By 2025, PacifiCorp will begin training operators.
• PacifiCorp will continue to monitor key TerraPower milestones for development and will make regulatory filings,
as applicable, including, but not limited to, a request for the Oregon Public Utility Commission to explicitly
acknowledge an alternative acquisition method consistent with OAR 860-089-0100(3)(c), and a request for a
waiver of a solicitation for a significant energy resource decision consistent with Utah statute 54-17-501.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
26
2d
2022 All-Source Request for Proposals:
• PacifiCorp will issue an all-source Request for Proposals (RFP) to procure resources that can achieve commercial
operations by the end of December 2026.
• In September 2021, PacifiCorp will notify the Public Utility Commission of Oregon, the Public Service Commission
of Utah, and the Washington Utilities and Transportation Commission, of PacifiCorp’s need for an independent
evaluator.
• In October 2021, PacifiCorp will file a draft all-source RFP with applicable state utility commissions.
• In January 2022, PacifiCorp expects to receive approval of the all-source RFP from applicable state utility
commissions and issue the RFP to the market.
• In Q2 2022, PacifiCorp will identify an initial shortlist in advance of annual Cluster Request Window.
• In Q1 2023, PacifiCorp will identify a final shortlist from the all-source RFP, and file for approval of the final
shortlist in Oregon, file, certificate of public convenience and necessity (CPCN) applications, as applicable.
• By Q2 2023 PacifiCorp will execute definitive agreements with winning bids from the all-source RFP.
• By Q4 2025-2026, winning bids from the all-source RFP are expected to achieve commercial operation. Resources
must have commercial operation date of December 31, 2026, or earlier.
2e
2020 All-Source Request for Proposals:
• PacifiCorp filed for approval of the final shortlist in Oregon in June 2021.
• In September 2021, PacifiCorp will file CPCN applications in Wyoming, as applicable, for final shortlist.
• In Q4 2021, PacifiCorp will make a filing in Utah for significant energy resources on final shortlist.
Action Item 3. Transmission Action Items
3a
Energy Gateway South Segment F (Aeolus-Clover 500 kV transmission line):
• By Q2 2022, obtain Utah and Wyoming Certificates of Public Convenance and Necessity.
• By the end of Q1 2022, Bureau of Land Management notice to proceed to construct Energy Gateway South.
• In Q3 2024, construction of Energy Gateway South is expected to be completed and placed in service.
3b
Energy Gateway West, Segment D.1 (Windstar-Shirley Basin 230 kV transmission line):
• By Q2 2022, obtain conditional Wyoming Certificate of Public Convenance and Necessity
• By Q3 2022 complete ROW easement acquisition and option full Wyoming CPCN
• In Q3 2024, construction of Energy Gateway West segment D.1 to be completed and placed in service.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
27
3c
Boardman-to-Hemingway (500 kV transmission line):
• Continue to support the project under the conditions of the Boardman-to-Hemingway Transmission Project (B2H)
Joint Permit Funding Agreement.
• Continue to participate in the development and negotiations of the construction agreement.
• Continue to participate in “pre-construction” activities in support of the 2026 in-service date.
• Continue negotiations for plan of service post B2H for parties to the permitting agreement.
3d Initiate Local Reinforcement Projects as identified with the addition of new resources per the preferred portfolio, and
follow-on requests for proposal successful bids
3e Continue permitting support for Gateway West segments D.3 and E.
Action Item 4. Demand-Side Management (DSM) Actions
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
28
4a
Energy Efficiency Targets:
• PacifiCorp will acquire cost-effective Class 2 DSM (energy efficiency) resources targeting annual system energy
and capacity selections from the preferred portfolio as summarized below. PacifiCorp’s state-specific processes for
planning for DSM acquisitions is provided in Appendix D in Volume II of the 2021 IRP.
• PacifiCorp will pursue cost-effective energy efficiency resources as summarized in the table below:
• PacifiCorp will pursue cost-effective Class 1 (demand response) resources targeting annual system capacity1
selections from the preferred portfolio2 as summarized in the table below:
1 Capacity impacts for demand response include both summer and winter impacts within a year.
2A portion of cost-effective demand response resources identified in the 2021 preferred portfolio are expected to be acquired through a
previously issued demand response RFP soliciting resources identified in the 2019 IRP. PacifiCorp will pursue all cost-effective demand
response resources identified as incremental to resources subsequently procured under the previously issued RFP in compliance with state
level procurement requirements.
Action Item 5. Market Purchases
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
29
5a
Market Purchases:
• Acquire short-term firm market purchases for on-peak delivery from 2021-2023 consistent with the Risk
Management Policy and Energy Supply Management Front Office Procedures and Practices. These short-term firm
market purchases will be acquired through multiple means: Balance of month and day-ahead brokered transactions
in which the broker provides a competitive price.
• Balance of month, day-ahead, and hour-ahead transactions executed through an exchange, such as the
Intercontinental Exchange, in which the exchange provides a competitive price.
• Prompt-month, balance-of-month, day-ahead, and hour-ahead non-brokered bi-lateral transactions.
Action Item 6. Renewable Energy Credit (REC) Actions
6a
Renewable Portfolio Standards (RPS):
• PacifiCorp will pursue unbundled REC RFPs and purchases to meet its state RPS compliance requirements.
• As needed, issue RFPs seeking then current-year or forward-year vintage unbundled RECs that will qualify in
meeting California RPS targets through 2024.
6b Renewable Energy Credit Sales:
• Maximize the sale of RECs that are not required to meet state RPS compliance obligations.
PACIFICORP – 2021 IRP CHAPTER 1 – EXECUTIVE SUMMARY
30
PACIFICORP – 2021 IRP CHAPTER 2 – INTRODUCTION
31
CHAPTER 2 – INTRODUCTION
PacifiCorp files an Integrated Resource Plan (IRP) on a biennial basis with the state utility
commissions of Utah, Oregon, Washington, Wyoming, Idaho, and California. This IRP fulfills the
company’s commitment to develop a long-term resource plan that considers cost, risk, uncertainty,
and the long-run public interest. It was developed through a collaborative public-input process
with involvement from regulatory staff, advocacy groups, and other interested parties. As the
owner of the IRP and its action plan, all policy judgments and decisions concerning the IRP are
ultimately made by PacifiCorp in light of its obligations to its customers, regulators, and
shareholders.
PacifiCorp’s selection of the 2021 IRP preferred portfolio is supported by comprehensive data
analysis and an extensive public-input process, described in the chapters that follow. PacifiCorp’s
2021 preferred portfolio continues to include substantial new renewables, facilitated by
incremental transmission investments, demand-side management (DSM) resources, and for the
first time, significant battery storage resources and advanced nuclear. By the end of 2024, the 2021
IRP preferred portfolio includes the 2020 All-Source RFP final shortlist resources including 1,792
MW of wind, 1,302 MW of solar additions, and 697 MW of battery storage capacity – 497 MW
paired with solar and a 200 MW standalone battery. During this time, the preferred portfolio also
includes the acquisition and repowering of Rock River 1 (49 MW) and Foote Creek II-IV (43 MW)
wind projects. Through the end of 2026, the 2021 IRP preferred portfolio includes an additional
745 MW of wind and an additional solar co-located with storage.
To facilitate the delivery of new renewable energy resources to PacifiCorp customers across the
West, the preferred portfolio includes the construction of a 416-mile 500-kilovolt (kV)
transmission line known as Gateway South connecting southeastern Wyoming and northern Utah,
the 59-mile 230 kV transmission line in eastern Wyoming known as Gateway West Segment D.1,
and the 500 kV, 290-mile transmission line across eastern Oregon and southwestern Idaho known
as Boardman to Hemingway (B2H).
Other significant studies conducted to support analysis in the 2021 IRP include:
• An updated demand-side management resource conservation potential assessment;
• A private generation study for PacifiCorp’s service territory;
• A renewable resources assessment;
• An assessment of smart grid technologies;
• Updated stochastic parameters; and
• An updated load and resource balance.
This chapter outlines the components of the 2021 IRP, summarizes the role of the IRP, and
provides an overview of the public-input process.
PACIFICORP – 2021 IRP CHAPTER 2 – INTRODUCTION
32
2021 Integrated Resource Plan Components
The basic components of PacifiCorp’s 2021 IRP include:
• Assessment of the planning environment, market trends and fundamentals, legislative and
regulatory developments, and current procurement activities (Chapter 3).
• Description of PacifiCorp’s transmission planning efforts and activities (Chapter 4).
• Discussion of PacifiCorp’s commitment to serve customers reliably, and summary of the
company’s actions to ensure all-weather resource adequacy, wildfire mitigation planning,
and transmission planning to support power flow reliability. (Chapter 5)
• Load and resource balance on a capacity and energy basis and determination of the load
and energy positions for the front ten years of the twenty-year planning horizon (Chapter
6).
• Profile of resource options considered for addressing future capacity and energy needs
(Chapter 7).
• Description of the IRP modeling, including a description of the portfolio development
process, cost and risk analysis, and preferred portfolio selection process (Chapter 8).
• Presentation of IRP modeling results and selection of PacifiCorp’s preferred portfolio
(Chapter 9).
• Presentation of PacifiCorp’s 2021 IRP action plan linking the company’s preferred
portfolio with specific implementation actions, including an accompanying resource
acquisition path analysis and discussion of resource procurement risks (Chapter 10).
The IRP appendices, included as a Volume II, contain the items listed below:
• Load Forecast Details (Volume II, Appendix A),
• IRP Regulatory Compliance (Volume II, Appendix B),
• Public Input (Volume II, Appendix C),
• Demand Side Management Resources (Volume II, Appendix D),
• Smart Grid (Volume II, Appendix E),
• Flexible Reserve Study (Volume II, Appendix F),
• Plant Water Consumption Study (Volume II, Appendix G),
• Stochastic Parameters (Volume II, Appendix H),
• Capacity Expansion Results (Volume II, Appendix I)
• Stochastic Simulation Results (Volume II, Appendix J),
• Capacity Contribution (Volume II, Appendix K),
• Private Generation Study (Volume II, Appendix L),
• Renewable Resources Assessment (Volume II, Appendix M),
• Energy Storage Potential Evaluation (Volume II, Appendix N),
• Washington Clean Energy Action Plan (Volume II, Appendix O),
• RFP Overview (Volume II, Appendix P); and
• Acronyms (Volume II, Appendix Q)
To promote transparency PacifiCorp is also providing data discs for the 2021 IRP. These discs
support and provide additional details for the analysis described within the document. Data discs
containing confidential information are provided separately under non-disclosure agreements, or
specific protective orders in docketed proceedings.
PACIFICORP – 2021 IRP CHAPTER 2 – INTRODUCTION
33
The Role of PacifiCorp’s Integrated Resource Planning
PacifiCorp’s IRP establishes a plan that will deliver adequate and reliable electricity supply at a
reasonable cost and in a manner “consistent with the long-run public interest.”1 In this way, the
IRP serves as a roadmap for determining and implementing PacifiCorp’s long-term resource
strategy. In doing so, it accounts for state commission IRP requirements, the current view of the
planning environment, corporate business goals, and uncertainty. As a business planning tool, it
supports informed decision-making on resource procurement by providing an analytical
framework for assessing resource investment tradeoffs, including supporting request for proposal
bid evaluation efforts. As an external communications tool, the IRP engages numerous
stakeholders in the planning process and guides them through the key decision points leading to
PacifiCorp’s preferred portfolio of generation, demand-side, and transmission resources.
Public-Input Process
The IRP standards and guidelines for certain states require PacifiCorp to have a public-input
process allowing stakeholder involvement in all phases of plan development. PacifiCorp organized
five state meetings and held 18 public-input meetings, some of which spanned two days to facilitate
information sharing, collaboration, and expectations for the 2021 IRP. The topics covered all facets
of the IRP process, ranging from specific input assumptions to the portfolio modeling and risk
analysis strategies employed.
Table 2.1 lists the public input meetings/conferences and highlights major agenda items covered.
Volume II, Appendix C Public-Input Process provides more details concerning the public-input
process.
1 The Public Utility Commission of Oregon and Public Service Commission of Utah cite “long-run public interest” as
part of their definition of integrated resource planning. Public interest pertains to adequately quantifying and capturing
for resource evaluation any resource costs external to the utility and its ratepayers. For example, the Public Service
Commission of Utah cites the risk of future internalization of environmental costs as a public interest issue that should
be factored into the resource portfolio decision-making process.
PACIFICORP – 2021 IRP CHAPTER 2 – INTRODUCTION
34
Table 2.1 – IRP Public-Input Meetings
Meeting Type Date Main Agenda Items
State Meeting 7/22/20 Utah state stakeholder comments
State Meeting 7/22/20 Washington state stakeholder comments
State Meeting 7/23/20 Wyoming state stakeholder comments
State Meeting 7/24/20 Oregon state stakeholder comments
CPA Technical
Workshop 1/21/20
Conservation Potential Assessment (CPA) Overview, Key Changes and
Updates for the 2021 CPA, Market Characterization and Baseline
Development, Measure Characterization and Potential Estimation, 2021
CPA Work Plan
CPA Technical
Workshop 2/18/20 Energy Efficiency, Measure List Changes, Demand Response, Resource
Options and Examples
CPA Technical
Workshop 4/16/20
Conservation Potential Assessment Schedule and Milestones, Stakeholder
Feedback, Recap of Key Discussion Topics From Prior Workshops,
Drivers of difference in Forecasted Potential by State
General Meeting (2-Day)
6/18/20 Stakeholder Feedback Form Update, CPA Update, Optimization Modeling
and Modeling Update, Modeling Energy Storage
6/19/20 2019 IRP Highlights/ 2021 IRP Topics and Timeline, Request for Proposal
Update, Transmission Overview and Update
General Meeting (2-Day)
7/30/20 Load Forecast Update, Distribution System Planning, Supply-side
Resource Study Efforts, Coal Studies Discussion
7/31/20
Environmental Policy, Renewable Portfolio Standards, DMS Bundling
Portfolio Methodology, Private Generation Study, Stakeholder Feedback
Form Recap
CPA Technical
Workshop 8/28/20 2021 CPA Process Review, Energy Efficiency Potential Draft Results,
Demand Response Potential Draft Results
General Meeting 9/17/20
Supply-side Resources, Portfolio Development Discussion, State Policy
Update, Conservation Potential Assessment Update, Stakeholder Feedback
Form Recap
General Meeting 10/22/20 General Updates, Summary of Oregon Energy Efficiency Analysis Results
General Meeting 11/16/20 Plexos Benchmark and Modeling Assumptions
General Meeting 12/3/20 Conservation Potential Assessment, DSM Bundling Methodology,
Updated Portfolio Matrix and Analysis
General Meeting 1/29/21 Energy Efficiency Bundling Methodology, Renewable Shaping,
Stakeholder Feedback Form Recap
General Meeting 2/10/21 Discussion of current status of IRP, proposed updates to schedule.
General Meeting 4/23/21 Portfolio Modeling process update, Stakeholder Feedback Form Recap
General Meeting 6/25/21 Update on Key Activities and Presentation of Indicative Case
General Meeting 7/30/21 Discussion of Portfolio Optimization and Modeling Discussion
General Meeting 8/6/21 Continued Discussion of Portfolio Results
General Meeting 8/27/21 Presentation of 2021 IRP results
In addition to the public-input meetings, PacifiCorp used other channels to facilitate resource
planning-related information sharing and stakeholder input throughout the IRP process. The IRP
webpage can be found at the following location: www.pacificorp.com/energy/integrated-resource-
plan.html, an e-mail “mailbox” (irp@pacificorp.com), and a dedicated IRP phone line (503-813-
5245) to support communications and inquiries among participants. Additionally, a stakeholder
feedback form was used to provide opportunities for stakeholders to submit additional input and
ask questions throughout the 2021 IRP public-input process. The submitted forms, as well as
PACIFICORP – 2021 IRP CHAPTER 2 – INTRODUCTION
35
PacifiCorp’s responses to these feedback forms are located on the PacifiCorp’s IRP website:
www.pacificorp.com/energy/integrated-resource-plan/comments.html. A summary of stakeholder
feedback forms received, and company response was provided during the public-input meetings.
PACIFICORP – 2021 IRP CHAPTER 2 – INTRODUCTION
36
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
37
CHAPTER 3 – PLANNING ENVIRONMENT
CHAPTER HIGHLIGHTS
• In 2009 Appalachia (mostly Pennsylvania and West Virginia), produced almost no natural
gas; by late 2013 it was producing almost 12 billion cubic feet per day (BCF/D) and by end-
of-year 2020, Appalachia was producing over 35 BCF/D. In short, supply from Appalachia
continues to grow as volumes and costs prove to be, respectively, higher and lower than
anticipated. Today, Appalachia accounts for 34 percent of the nation’s gas supply, and by
2040 is expected to account for 44 percent, spurred by increased drilling efficiencies and
rising demand. Day-ahead 2020 Henry Hub prices averaged $2.03/Million British thermal
units (MMBtu), down 77 percent from 2008 prices.
• Federal and state tax credits, declining capital costs, and improved technology performance
have put wind and solar “in the money” in areas of high potential. As such, wind and solar
will likely dominate U.S. capacity additions for the next decade. To better integrate these
resources into the larger grid requires more flexible generation, transmission, new storage
technologies, and market design changes.
• In 2019, the Washington Legislature approved the Clean Energy Transformation Act
(CETA), which requires that 100% of electricity sales in Washington be 100% renewable
and non-emitting by 2045. The Phase I rulemakings – governing the planning processes –
were completed as of December 2020, and this IRP meets the requirements outlined in the
law and subsequent rules.
• In 2021, Washington passed the Climate Commitment Act, which establishes a cap-and-
trade program to be implemented by no later than 2023 through the regulatory rulemaking
process. The Climate Commitment Act does not modify any of PacifiCorp’s obligations
under CETA, and utility allowances within the cap-and-trade program are aligned with the
CETA renewable energy requirements. The legislation allows – but does not require –
linkage with cap-and-trade programs in jurisdictions outside of Washington State.
• In 2021, Oregon passed House Bill 2021, which directs utilities to reduce emissions levels
below 2010-2012 baseline levels by 80% by 2030, 90% by 2035, and 100% by 2040.
Utilities will also convene a Community Benefits and Impacts Advisory Group.
PacifiCorp’s 2023 IRP will include modeling to support House Bill 2021.
• PacifiCorp and the California Independent System Operator Corporation (CAISO) launched
the voluntary energy imbalance market (EIM) November 1, 2014, the first western energy
market outside of California. The EIM has produced significant monetary benefits ($1.42
billion total footprint-wide benefits as of August 2, 2021). A significant contributor to EIM
benefits is transfers across balancing authority areas, providing access to lower-cost supply,
while factoring in the cost of compliance with greenhouse gas emissions regulations when
energy is transferred into the CAISO balancing authority area.
• Beginning in early 2019, PacifiCorp along with other Northwest Power Pool (NWPP)
member entities and the Northwest Power Pool itself engaged in the development and
implementation of a regional Resource Adequacy (RA) Program as a mechanism to assure
a high likelihood of adequate supply to meet customer demand under a wide array of
scenarios. This program includes two components, a Forward Showing (FS) planning
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
38
mechanism and an Operational Program (Ops Program) to help Participants that are
experiencing extreme events meet customer demand. The program is designed to be
supplemental and complementary to those processes and requirements. Program planning
is scheduled to continue throughout 2022, with a proposed implementation date in 2024.
• Near-term procurement activities focused on three areas—the purchase and sale of
renewable energy credits, and the purchase or procurement of new renewable and battery
resources, and the procurement of new demand response resources.
Introduction
This chapter profiles the major external influences that affect PacifiCorp’s long-term resource
planning and recent procurement activities. External influences include events and trends affecting
the economy, wholesale power and natural gas prices, and public policy and regulatory initiatives
that influence the environment in which PacifiCorp operates.
Major issues in the power industry include resource adequacy and associated standards for the
Western Electricity Coordinating Council (WECC). Future natural gas prices, the role of gas-fired
generation, the roll of emerging technologies, and the declining net costs of renewables and battery
technologies also play a role in the selection of the portfolio that best achieves least-cost, least-risk
planning objectives.
On the government policy and regulatory front, a further significant issue in the power industry
and facing PacifiCorp continues to be planning for eventual, but highly uncertain, climate change
policies. This chapter provides discussion on climate change policies as well as a review of
significant policy developments for currently regulated pollutants. This chapter also provides
updates on the status of renewable portfolio standards and resource procurement activities.
Wholesale Electricity Markets
PacifiCorp’s system does not operate in an isolated market. Operations and costs are tied to a larger
electric system known as the Western Interconnection which functions, on a day-to-day basis, as
a geographically dispersed marketplace. Each month, millions of megawatt-hours of energy are
traded in the wholesale electricity market. These transactions yield economic efficiency by
ensuring that resources with the lowest operating cost are serving demand throughout the region
and by providing reliability benefits that arise from a larger portfolio of resources.
PacifiCorp actively participates in the wholesale market by making purchases and sales to
minimize costs and to keep its supply portfolio in balance with customers’ expectations. This
interaction with the market takes place on time scales ranging from sub-hourly to years in advance.
Without the wholesale market, PacifiCorp – or any other load serving entity – would need to
construct or own an unnecessarily large margin of supplies that would go unused in all but the
most unusual circumstances and would substantially diminish its capability to cost effectively
match delivery patterns to the profile of customer demand.
The benefits of access to an integrated wholesale market have grown with the increased penetration
of intermittent generation such as solar and wind. Intermittent generation can come online and go
offline abruptly in congruence with changing weather conditions. Federal and state (where
applicable) tax credits, declining capital costs, and improved technology performance have put
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
39
wind and solar “in the money” in areas of high potential. As such, wind and solar will continue to
play a dominant role in power supply options over the next decade. To better integrate these
resources into the larger grid requires more flexible generation, transmission, new storage
technologies, and market design changes.
Regarding transmission, there are long-haul, renewable-driven transmission projects in advanced
development in the U.S. WECC. These lines ultimately connect areas of high renewable potential
and low population density to areas of high population density with less renewable potential. This
includes PacifiCorp’s proposed 416-mile high-voltage 500-kilovolt (kV) Gateway South project
and the 59-mile high-voltage 230-kV Gateway West Segment D.1 project—both with an online
date by the end of 2024. These transmission projects will provide greater system-wide flexibility
and will provide east-west transfer capability.
Similarly, several transmission projects propose to provide east-to-west transfer capability to allow
greater integration of intermittent resources. Gateway West – a series of transmission projects
currently in the permitting process – would add east-to-west transfer capability on PacifiCorp’s
system.1 Boardman-to-Hemingway (B2H), a joint effort with Idaho Power Company, a 290-mile
high-voltage 500-kilovolt transmission between the Hemingway substation in southwestern Idaho
and the Pacific Northwest with an online date by the end of 2026. Additionally, TransWest
Express, a 730-mile line high-voltage 500-kilovolt transmission line from southwest Wyoming
through Colorado and Utah to Nevada’s Hoover Dam is anticipated to begin construction in once
the Bureau of Land Management issues a notice to proceed, with a projected online date in the
mid-2020s.
The intermittency of renewable generation has also given rise to a greater need for fast-responding
and long-duration storage, which is essential for grid stability and resiliency. Pumped storage has
been the traditional storage option and there are multiple projects being developed throughout the
West. Of remaining mechanical, thermal, and chemical storage options, lithium-ion (Li-ion)
batteries have shown the most promise in terms of cost and performance improvement. In 2013,
the California Public Utility Commission (CPUC) required investor-owned utilities to procure
1,325 MW of storage by 2020; that requirement has been satisfied. Utility-scale four-hour battery
storage modules have fallen considerably in price, and costs are expected to continue to decline as
electric vehicle manufacturing drives further innovation. To date, nine states have implemented
energy storage targets or mandates, with another one state seriously considering implementation.2
In California, the world’s largest Li-ion battery, 400 MW, is scheduled to go online at Pacific Gas
& Electric (PG&E)’s Moss Landing Power Plant in 2021.3 Hybrid co-located solar photovoltaic
(SPV) and battery systems are now in Hawaii, Arizona, Nevada, California, and Texas. In March
2019, Florida Power & Light Company announced a plan to build the world's largest solar-powered
battery system with 409 MW of capacity serving the customers in late 2021.
In 2018, the Federal Energy Regulatory Commission (FERC) directed regional transmission
organizations (RTO) and independent system operators (ISO) to develop market rules for the
1 Additional information on Gateway West projects can be found in Volume I, Chapter 4 (Transmission).
2 California, New Jersey, New York, Massachusetts, Oregon, Nevada, Virginia, Connecticut, and Maine have either
mandated or set energy storage targets, while Arizona is considering the implementation of targets.
3 Phase II of Moss Landing is expected to reach a capacity of 1,600MWh/400MW in Fall 2021.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
40
participation of energy storage in wholesale energy, capacity, and ancillary services markets4. The
FERC gave operators nine months to file tariffs and another year to implement – essentially
opening wholesale markets to energy storage. Operators’ proposed tariffs have varied substantially
among regions with PJM requiring a 10-hour continuous discharge capability while New England
requires a continuous 2-hour capability. Later, in May 2019, the FERC issued an order generally
affirming the earlier order to establish reforms to remove barrier to the participation of electric
storage resources in certain organized wholesale markets. As part of its 2021 IRP, PacifiCorp is
evaluating the cost effectiveness of several energy storage systems, including pumped storage,
stand-alone li-on batteries, as well as co-located solar and co-located wind.5
Increased renewable generation has also contributed to the need for balancing sub-hourly demand
and supply across a broader and more diverse market. For balancing purposes, PacifiCorp
combined its resources with those of the CAISO through the creation of the EIM. The EIM became
operational November 1, 2014, and as of August 2021 has seen NV Energy, Puget Sound Energy,
Arizona Public Service, Portland General Electric, Powerex, Idaho Power, Balancing Authority of
Northern California, Salt River Project, Seattle City Light, Los Angeles Department of Water and
Power, Northwestern Energy, and Public Service Company of New Mexico join the EIM. Avista
Utilities, Tucson Electric Power, Tacoma Power, and Bonneville Power Administration plan to
join in 2022. The multi-service area footprint brings greater resource and geographical diversity
allowing for increased reliability and cost savings in balancing generation with demand using 15-
minute interchange scheduling and five-minute dispatch. CAISO’s role is limited to the sub-hourly
scheduling and dispatching of participating EIM generators. CAISO does not have any other grid
operator responsibilities for PacifiCorp’s service areas. As part of other EIM participant entities,
PacifiCorp is also participating in the CAISO stakeholder process to establish and Expanded Day-
Ahead Market (EDAM), tentatively targeted to go-live in 2022.
As with all markets, electricity markets are faced with a wide range of uncertainties. In February
2021, winter storm Uri caused an unprecedented decline in marketed natural gas production of
186.7 billion cubic feet (Bcf), or 24.1% in Texas, comparing with previous month. This decline
contributed significantly to the largest monthly decline in natural gas production on record in the
Lower 48 states. This weather event caused widespread disruptions in energy supply and demand,
including extended electric power blackouts in Texas.
Market participants routinely study demand uncertainties driven by weather and overall economic
conditions. The North American Electric Reliability Corporation (NERC) publishes an annual
assessment of regional power reliability and any number of data services are available that track
the status of new resource additions6. In its latest assessment, published December 2020, the NERC
indicates that WECC region has adequate resources through 2030. However, the NERC’s
probabilistic studies indicate that in each of the WECC’s sub-regions’ (except Alberta), resource
adequacy is at risk during off peak hours, starting as early as 2021.7
4162 FERC ¶ 61,127 United States of American Federal Energy Regulatory Commission, 18 CFR Part 35 [Docket
Nos. RM16-23-000; AD16-20-000; Order No. 841] Electric Storage Participation in Markets Operated by Regional
Transmission Organizations and Independent System Operator (Issued February 15, 2018)
5 Solar or wind resources coupled with battery storage.
6 2020 Long-term Reliability Assessment, December 2020, North American Electric Reliability Assessment
7 A discussion of regional resource adequacy efforts can be found in Volume I, Chapter 5 (Reliability and
Resiliency)
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
41
In addition to reliability planning, there are externalities that can heavily influence the direction of
future prices. One such uncertainty is the evolution of natural gas prices over the course of the IRP
planning horizon. Given the increased role of natural gas-fired generation, gas prices are a critical
determinant of western electricity prices, and this trend is expected to continue over the term of
this plan’s decision horizon. Another critical uncertainty that weighs heavily on the 2021 IRP, as
in past IRPs, is the uncertainty surrounding future greenhouse gas policies, both federal and/or
state. PacifiCorp’s official forward price curve (OFPC) does not assume a federal carbon dioxide
(CO2) policy, but other price scenarios developed for the IRP consider impacts of potential future
federal CO2 emission policies. However, PacifiCorp’s OFPC does include enforceable state
climate programs that have been signed into law8.
Natural Gas Uncertainty
Since 2008, North American natural gas markets have undergone a remarkable paradigm shift. As
shown in Figure 3.1, Henry Hub day-ahead gas prices hit a high of $13.31/MMBtu on July 2, 2008
and a low of $1.49/MMBtu on March 4, 2016. Day-ahead prices averaged $8.86/MMBtu in 2008,
dropped to $3.94 in 2009, and have averaged $2.72 since 2015. Day-ahead 2020 Henry Hub prices
averaged $2.03/MMBtu, down 77 percent from 2008 prices. The relative price placidity since
2009, labeled the “Shale Gale”, reflects a story of supply – mostly that of Appalachian and, later,
Permian supply9.
In 2009, Appalachia (mostly Pennsylvania and West Virginia), produced almost no natural gas;
by late 2013 it was producing almost 12 BCF/D and by end-of-year 2020, Appalachia was
producing over 35 BCF/D. In short, supply from Appalachia continues to grow as volumes and
costs prove to be, respectively, higher and lower than anticipated. Today, Appalachia accounts for
34 percent of the nation’s gas supply, and by 2040 is expected to account for 44 percent, spurred
by increased drilling efficiencies and rising demand.
8 A forecast of California carbon allowance prices is used as a proxy for future cap-and-trade allowance auction
prices. Oregon’s House Bill 2020, establishing a Climate Policy Office and directing it to adopt an Oregon Climate
Action Program by rule is still in Committee and has not yet been signed into law.
9 Other significant shale gas plays include: Eagle Ford (TX); Haynesville (LA/TX); Niobrara (CO/WY); and the
Bakken (ND/MT).
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
42
Figure 3.1 – Henry Hub Day-Ahead Gas Price History
Source: Thomson Reuters as cited by the Energy Information Administration at:
www.eia.gov/dnav/ng/hist/rngwhhdD.htm.
Historically, depletion of conventional mature resources largely offset unconventional resource
growth, but as shale gas “came into its own,” production gains outpaced depletion. Figure 3.2
through Figure 3.4 shows natural gas by source and location.
Figure 3.2 – U.S. Dry Natural Gas Production (Trillion Cubic Feet)
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
43
Figure 3.3 – Lower 48 States Shale Plays
Source: U.S. Department of Energy, Energy Information Administration
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
44
Figure 3.4 – Plays Accounting for Natural Gas Production Growth 2011 -2020
Source: Drilling Productivity Report, May 17, 2021, U.S. Department of Energy, Energy Information Administration
Figure 3.5 shows Henry Hub NYMEX futures, as of June 30, 2021. Natural gas futures show a
high price, $3.17/MMBtu in 2022, which offers the “signal-to-drill” to the natural gas producers.
But as producers chase production efficiencies the “signal-to-drill” price becomes lower. While
the futures decline in the short term to reflect the ramp-up in the natural gas production, the annual
futures rise after 2024 due to export and domestic demand growth.
But, for the next decade low-cost natural gas will come from oil-targeted plays, especially in the
Permian Basin. West Texas Intermediate two-year futures are currently hovering around
$72/barrel, 68% more than 2020, reflecting the increasing demand as global economy continues
to recover. It is more than enough to spur oil-targeted drilling in western Canada, the Permian, and
Bakken. In the Bakken break even costs are below $50/barrel, while in the Permian, break-even
costs range from $26/barrel to $50/barrel. Moreover, producers are “front-loading” oil production
which releases a disproportionately large amount of associated gas. Front-loading involves drilling
closely spaced “child” wells to quickly boost initial oil production but the resulting decrease in
well pressure also releases inordinate quantities of associated gas.10 This is especially true of
Permian Basin oil wells, whose output naturally contains 20 to 50 percent natural gas. Permian
Basin production had peaked at 12.8 Bcf/d in March 2020, following several years of rapid growth.
Output from the basin then fell due to the oil price collapse and the onset of the COVID-19
pandemic in early 2020. Since then, production has started to rebound.
10 Note that while front-loading increases initial production it often shortens productive well life.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
45
In 2016, following crude’s price collapse, U.S. production fell to 8.8 million barrels of oil per day
(MMbpd11) from a high of 9.6 MMbpd in 2015. In 2018, U.S. production averaged 10.9 MMbpd,
hitting an all-time high of 11.97 MMBpd in December 2018. In 2020, the COVID-19 pandemic
triggered an unprecedented demand shock in the oil industry, leading to a historic market collapse
in oil prices. In addition, an oil price war between Russia and Saudi Arabia erupted in March when
the two nations failed to reach a consensus on oil production levels. The oversupply of oil led to
an unprecedented collapse in oil prices in April 2020, forcing the contract futures price for West
Texas Intermediate (WTI) to plummet from $18 a barrel to around -$37 a barrel. By the summer
of 2020, oil prices began to rebound as nations emerged from lockdown and OPEC agreed to
significant cuts in crude oil production. Since the end of 2020, as optimism over the possible rollout
of multiple COVID-19 vaccines buoyed the market, the global demand recovery has led the oil
prices increasing continuously, which led to the increased oil production. Moreover, the EIA
estimated that as of May 2021, 6,521 wells remain drilled but uncompleted; these wells can be put
into production quickly and represent a significant source of supply12. U.S. production can ramp
up very quickly.
This resiliency of supply coupled with the flexibility to quickly ramp up production will shorten
the length of asynchronous supply and demand cycles. Unexpected weather-induced demand
spikes or supply disruptions will still whipsaw prices for short periods of time. But Liquefied
Natural Gas (LNG) startups, outages or dial backs could swing prices for longer periods given the
magnitude of volumes coupled with locational concentration13. US LNG exports have recovered
from the summer 2020 weakness after global fundamentals tightened in winter 2020/21. Summer
feed gas normally bound for liquefaction would then be diverted onto the U.S. market, depressing
prices. The summer 2021 dial back will act to also moderate winter prices by increasing storage
and the likelihood of entering winter with an overhang. Although U.S. LNG tends to be the
marginal global supplier, buyers are interested in U.S. LNG due to its low-cost natural gas supply
and contract flexibility. Of note, even oil-rich Saudi Arabia has entered into a 20-year supply
agreement for U.S. LNG. The imported LNG is expected to be used to replace Saudi Arabia’s oil-
fired power generation, thereby freeing up oil for export. U.S. LNG exports are projected to
increase in 2022 because of commissioning of additional LNG trains at Sabine Pass and Calcasieu
Pass. To summarize, the key drivers of U.S. demand are: 1) LNG exports, 2) Mexican exports, and
3) power generation. Of the three, power generation is by far the largest, but exports (especially
LNG) are the fastest growing.
11 MMbpd: Million barrels per day.
12 EIA does not distinguish between oil and gas wells since over 50 percent of wells produce both.
13 Current and expected facilities are mostly concentrated in the Gulf Coast.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
46
Figure 3.5 – Henry Hub NYMEX Futures
Stronger oil prices and a recovering economy should enable the natural gas production to return to
strong growth in 2022-2023. Associated and Appalachian gas production rebounded faster than
expected in late 2020, following price-induced shut-ins earlier that year. However, as pipeline
projects become increasingly difficult to build in the Appalachian region, supply growth there will
be constrained after 2026, with strong associated gas and Haynesville production growth keeping
prices low. Rocky Mountain production gets squeezed by western Canadian, lower-48 associated
gas, and Appalachian volumes. In the Northwest, where natural gas markets are influenced by
production and imports from Canada, prices at Sumas have traded at a premium relative to AECO.
This is likely to continue as AECO loses market share to Appalachia in serving AECO’s Ontario
and Midwest markets. In short, the challenge in gauging the uncertainty in natural gas markets will
be one of timing. The North American natural gas supply curve continues to flatten as production
efficiencies expose an ever-increasing resilient, flexible, and low-cost resource base. In such a
world, managing long-term boom and bust cycles is not as crucial as managing shorter-term market
perturbations.
PacifiCorp’s Multi-State Process
PacifiCorp is a multi-state utility that provides retail electric service to nearly 2 million customers
across six states. The costs of providing this retail electric service to customers is recovered
through retail rates established in regulatory proceedings in each state. To ensure states receive the
appropriate allocation of costs and benefits from PacifiCorp’s integrated system, the collaborative
multi-state process (MSP) has been used to address allocation issues. This collaborative process
has led to the development and adoption of a series of inter-jurisdictional cost-allocation methods
over time.
The underlying principle of each of the historic inter-jurisdictional cost-allocation methods has
been the use of PacifiCorp’s system as a single whole: except for distribution, all states are served
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
$/
M
M
B
t
u
Annual Strip as of June 30, 2021
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
47
from a common portfolio of assets, including generation assets, which enabled the company to
leverage economies of scale to plan and operate in a way that resulted in cost savings for all
customers. Recently, state energy policies across the states served by the company have challenged
this principle. For example, requirements to remove coal-fired generation from rates in certain
states will necessarily result in some states being allocated the costs and benefits of coal-fired
generation while other states are not. Similarly, diverging state polices related to implementation
of the Public Utilities Regulatory Policy Act of 1978, retail choice, private generation, and
incorporation of societal externalities in resource planning challenge the long-standing practice of
planning for a single, integrated system.
In December 2019, PacifiCorp filed the most recent inter-jurisdictional cost-allocation
methodology, known as the 2020 Protocol. Five of PacifiCorp’s six retail states agreed that the
methodology outlined in the 2017 protocol should continue, with certain modifications.14 The
guiding principles underlying the 2020 Protocol are as follows:
- Provide a long-term, durable solution;
- Follow cost-causation principles;
- Minimize rate impacts at implementation;
- Allow for state autonomy for new resource portfolio selection;
- Maintain and optimize system-wide benefits and joint dispatch to the extent possible;
- Enable compliance with state policies;
- Ensure credit-supportive financial outcome; and
- Provide the company with a reasonable opportunity to recover its costs.
Under those principles, the 2020 Protocol represented a fundamental shift in how the company
proposed to address inter-jurisdictional cost allocation, with the ultimate goal of moving away
from the concept of a common generation resource portfolio with dynamic allocation factors and
toward a cost-allocation protocol with fixed allocation factors for generation resources and state-
specific resource portfolios. In support of that change, the 2020 Protocol used a gradual transition
approach that relies on the continuation of historic protocols during an interim period (January 1,
2020 through December 31, 2023 or upon the resolution of all remaining cost-allocation issues),
with a series of modifications:
- Cost-allocation procedures that will be implemented during the interim period
(implemented issues);
- Cost-allocation procedures that are agreed to but that will not take effect until after the
Interim Period (resolved issues); and
- Cost-allocation procedures that parties to the 2020 Protocol will continue to work to
resolve during the interim period (framework issues).
Before the end of the interim period, assuming the resolution of all framework issues, a new cost
allocation method – incorporating implemented issues, resolved issues and the final resolution of
the framework issues – will be presented to state commissions for approval. This is anticipated to
occur no later than year-end 2023.
14 California, Idaho, Oregon, Utah, and Wyoming parties agreed to the extension of the methodology. As part of the
agreement, Washington signed a Memorandum of Understanding that would continue negotiations toward
Washington joining a common cost allocation methodology amongst all six states.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
48
List of Implemented Issues
1. States’ Decisions to Exit Coal-Fueled Interim Period Resources: including
methodology regarding allocation of costs at closure, treatment of exit orders, exit dates,
and common closures, as well as the process to establish exit dates for Hayden Units 1
and 2.
2. Reassignment of Coal-Fueled Interim Period Resources: Includes the process,
methodology, and effects of commission decisions on the potential reassignment of coal-
fueled resources from a state which has issued an exit order to states that do not have exit
orders.
3. Decommissioning Costs: specifies the timing of a contractor-assisted engineering study
of decommissioning costs and appropriate decommissioning cost reserve requirements
for Jim Bridger, Dave Johnston, Hunter, Huntington, Naughton, Wyodak, Hayden, and
Colstrip. This item also specifies the allocation of decommissioning costs.
4. Qualifying Facilities: outlines a superseding framework, in which existing qualifying
facilities will remain system assigned and allocated – subject to any future limited
realignment – until the end of 2029, after which time they will be assigned and allocated
to the state that has jurisdiction over qualifying facility pricing. During the interim
period, qualifying facilities will continue to be allocated, while after the interim period,
qualifying facilities will be directly assigned to the state that has jurisdiction over
qualifying facility pricing.
List of Resolved Issues
1. Generation Costs: including the share of resources assigned to serve load in each state.
Interim resources will continue to have a fixed allocation, and new resources that begin
operation before the end of the interim period will use the same methodology. New
resources that begin operation after the interim period will be subject to future
determination as part of the framework issues.
2. Transmission Costs: will continue to be allocated on the System Transmission factor,
except as addressed as part of the “new resource assignment” framework issue.
3. Distribution Costs: will be directly allocated to states where distribution facilities are
located.
4. System Overhead Costs: Will continue to be allocated based on the System Overhead
factor but will also be subject to allocation based partially on the System Capacity, System
Energy, and System Gross Plant Distribution factors.
5. Administrative and General: will be directly allocated to states, if possible.
6. Other Allocation Issues: modifies the allocation of certain existing miscellaneous issues.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
49
7. Demand-Side Management Programs: will be allocated to the state in which the
investment is made, and benefits will flow back to each state through net power costs or
through reduced or delayed future capacity need.
8. State-Specific Initiatives: Will be allocated and assigned to the state adopting the
initiative.
Update on 2020 Protocol and Status of Framework Issues
Following the filing of PacifiCorp’s 2020 Protocol, Oregon, Idaho, Wyoming, Utah, and
Washington have issued approval. Quarterly MSP meetings continue for parties to work through
the framework issues in advance of the 2023 timeframe. The current framework issues as agreed
upon in the 2020 Protocol are as follows:
1. Resource Planning and New Resource Assignment – The continued operation,
planning, and dispatch of the Company’s system as an integrated six-state system will
likely be beneficial to PacifiCorp customers. However, as state energy policy continues to
evolve, requiring the exclusion of certain generating resources, it appears infeasible to
continue serving customers with a common generation portfolio and dynamically
allocated system costs. As such, PacifiCorp will work to meet its legal requirements as a
public utility in each state in a risk-adjusted, least-cost manner, while striving to mitigate
cost impacts in other states. Parties to the MSP are working to develop a planning process
that 1) optimizes risk-adjusted, least-cost resource portfolios on a system basis to the
extent practicable while meeting individual state requirements and maintaining
reliability; and 2) assigns benefits and allocates costs of specific new resources added to
meet an individual state’s needs. As of September 2021, these discussions are ongoing as
part of the MSP framework process.
2. Net Power Costs and Nodal Pricing Model – The Nodal Pricing Model is a method to
track the costs and benefits of resource portfolios which may differ for each state, and to
maintain the benefits of system dispatch as much as practicable. After the interim period
when states may no longer participate in a common resource portfolio, the Nodal Pricing
Model may be used to track cost causation and receipt of benefits by each state for
ratemaking purposes. PacifiCorp worked with a third-party vendor to implement the Nodal
Pricing Model, and it is currently being used for day-ahead scheduling. Use of the Nodal
Pricing Model for net power costs and other applicable ratemaking proceedings may be
proposed after the interim period.
3. Special Contracts – PacifiCorp will work directly with special contract customers to
develop one or more proposals for consideration of parties. PacifiCorp will make best
efforts to present a proposal to parties by September 1, 2021, with the intention of
incorporating a proposal into the post-interim period method.
4. Limited Realignment – During the interim period, parties have agreed to investigate the
potential for limited realignment of interim period resources, primarily related to the
transition of certain state energy policy away from coal-fueled resources. These discussions
are ongoing as part of the MSP process.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
50
5. Post-Interim Period Capital Additions for Coal-Fueled Interim Period Resources –
For coal-fueled resources for which there are differing state exit dates or when exit dates
differ from the depreciable life, this issue provides a process for determining the cost
allocation for capital investments made subsequent to the interim period and prior to the
state exit dates. PacifiCorp has provided a straw proposal as part of the 2020 Protocol filing,
and discussions are ongoing.
Analysis of “Outstanding Material Disagreements”
In compliance with Wyoming Public Service Commission Order in Docket No. 9000-144-XI-19
(Record No. 15280), PacifiCorp includes this analysis of any material disagreements regarding
cost allocation at the time of the preparation and filing of the 2021 IRP.
PacifiCorp has not identified any outstanding material disagreements, and notes that the
framework issue discussions are proceeding as indicated in the executed agreement as part of the
2020 Protocol. If these discussions evolve into disagreements – or if there is no agreement by the
end of the interim period on December 31, 2023 – PacifiCorp may quantify the risks and potential
impacts to retail rates of such a disagreement as part of a future IRP or other regulatory filing.
The Future of Federal Environmental Regulation and Legislation
The inauguration of a new federal administration and the convening of the 117th U.S. Congress in
January 2021 provides a backdrop of potentially changing federal energy policy within
PacifiCorp’s 2021 IRP cycle. Although the exact nature of these potential changes is not known at
the time of filing, the company notes that changes to energy policy may impact the portfolio
selection process in the 2021 IRP and in future IRPs. PacifiCorp actively monitors federal
legislative requirements and participates in rulemaking processes by filing comments on various
proposals, participating in scheduled hearings, and providing assessments of proposals.
Among potential federal legislative priorities under consideration, PacifiCorp notes that there have
been some emerging themes:
• The extension and/or expansion of production and investment tax credits: In February
2021, California Representative Mike Thompson introduced the Growing Renewable
Energy and Efficiency Now (GREEN) Act, which would increase the federal solar
investment tax credit and provide investment tax credits for battery storage and electric
vehicles.
In April 2021, Oregon Senator Ron Wyden introduced the Clean Energy for America Act
(CEAA), which proposed to provide tax incentives for clean electricity technologies and
grid improvements, including transportation electrification and energy efficiency.
In Spring 2021, the Biden Administration released the American Jobs Plan, a $2 trillion
infrastructure plan that included proposals that would expand the investment tax credit to
incentivize the buildout of high-voltage capacity power lines and potentially extend the
investment and production tax credits for clean energy generation and storage.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
51
• A federal clean energy standard and/or renewable portfolio standard: In addition to
the potential expansion and extension of tax credits, the American Jobs Plan included
provisions to set a national clean electricity standard, which would transition the electricity
sector to be carbon-pollution free by 2035.
In March 2021, the House Committee on Energy and Commerce introduced the Climate
Leadership and Environmental Action for our Nation’s (CLEAN) Future Act, which would
require electricity suppliers to provide 100 percent clean energy by 2035 as part of a
national clean electricity standard.
As of August 2021, these potential policy decisions continue to be discussed, details continue to
evolve, and to date no new comprehensive federal energy policy requirements have been
implemented. Most recently, the United States Congress has continued negotiations a bipartisan
infrastructure bill, which may contain a federal clean energy standard, production and investment
tax credits, or both. PacifiCorp will continue to closely monitor emerging federal legislation and
requirements.
Federal Policy Update
New Source Performance Standards for Carbon Emissions – Clean Air Act §
111(b)
New Source Performance Standards (NSPS) are established under the Clean Air Act for certain
industrial sources of emissions determined to endanger public health and welfare. On August 3,
2015, the United States Environmental Protection Agency (EPA) issued a final rule limiting CO2
emissions from coal-fueled and natural-gas-fueled power plants. New natural-gas-fueled power
plants can emit no more than 1,000 pounds of CO2 per megawatt-hour (MWh). New coal-fueled
power plants can emit no more than 1,400 pounds of CO2/MWh. The final rule largely exempts
simple cycle combustion turbines from meeting the standards. On December 6, 2018, the EPA
proposed to revise the NSPS for greenhouse gas emissions from new, modified, and reconstructed
fossil fuel-fired power plants. EPA’s proposal would replace EPA’s 2015 determination that
carbon capture and storage technology was the best system of emissions reduction for new coal
units. The comment period for the proposed revisions closed in March 2019. In January 2021, the
EPA issued the final rule. However, in April 2021, at the request of the EPA as directed by the
Biden Administration, the D.C. Circuit vacated and remanded the January 2021 final rule.
Carbon Emission Guidelines for Existing Sources – Clean Air Act § 111(d)
On August 3, 2015, EPA issued a final rule, referred to as the Clean Power Plan (CPP), regulating
CO2 emissions from existing power plants.
On February 9, 2016, the U.S. Supreme Court issued a stay of the CPP suspending implementation
of the rule pending the outcome of the merits of litigation before the D.C. Circuit Court of Appeals.
On October 10, 2017, EPA proposed to repeal the CPP and on August 21, 2018, proposed the
Affordable Clean Energy (ACE) rule to replace the CPP. The ACE rule sets forth a list of
“candidate technologies” that states can use to reduce greenhouse gas emissions at coal-fueled
power plants. The ACE rule was finalized June 19, 2019, replacing the CPP. On January 19, 2021,
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
52
the D.C. Circuit vacated the ACE rule and directed the EPA to proceed with new rulemaking for
the control of carbon emissions from electric utility coal-fired boilers.
Credit for Carbon Oxide Sequestration – Internal Revenue Service (IRS) § 45Q
In 2008, the Internal Revenue Service issued a tax credit for carbon oxide sequestration under
section 45Q to incentivize carbon capture and sequestration (CCS) investments. The tax credit is
computed per metric ton (tonne) of qualified carbon oxide captured and sequestered.15 Carbon
oxide can either be permanently disposed of in secure geological storage or the carbon oxide can
be utilized – typically as a tertiary injectant in enhanced oil recovery (EOR).
The Bipartisan Budget Act of 2018 reformed 45Q for carbon capture equipment that is placed in
service on or after February 9, 2018, increasing the credit amount from $10/tonne to $35/tonne for
utilization and from $20/tonne to $50/tonne for storage.16 This Act also removed the limit on the
amount of tax credits that could be awarded for CCS, and, instead, requires a minimum amount of
carbon oxide to be capture annually and is available for 12 years from the date the carbon capture
equipment is originally placed into service.17
Clean Air Act Criteria Pollutants – National Ambient Air Quality Standards
The Clean Air Act requires EPA to set National Ambient Air Quality Standards (NAAQS) for six
criteria pollutants that have the potential of harming human health or the environment. The
NAAQS are rigorously vetted by the scientific community, industry, public interest groups, and
the general public, and establish the maximum allowable concentration allowed for each “criteria”
pollutant in outdoor air. The six pollutants are carbon monoxide, lead, ground-level ozone,
nitrogen dioxide (NOX), particulate matter (PM), and sulfur dioxide (SO2). The standards are set
at a level that protects public health with an adequate margin of safety. If an area is determined to
be out of compliance with an established NAAQS standard, the state is required to develop a state
implementation plan for that area. And that plan must be approved by EPA. The plan is developed
so that once implemented, the NAAQS for the pollutant of concern will be achieved.
In October 2015, EPA issued a final rule modifying the standards for ground-level ozone from 75
parts per billion (ppb) to 70 ppb. On November 16, 2017, the EPA designated all counties where
PacifiCorp’s coal facilities are located (Lincoln, Sweetwater, Converse and Campbell Counties in
Wyoming; and Emery County in Utah) as “Attainment.” On June 4, 2018, the EPA designated Salt
Lake County and part of Utah County where the PacifiCorp Lake Side and Gadsby gas facilities
are located as “Marginal Nonattainment.” A marginal designation is the least stringent
classification for a nonattainment area and does not require a formal State Implementation Plan
(SIP).Utah submitted its strategy for meeting the standard to EPA in May of 2021.
In April 2017, the EPA Administrator signed a final action to reclassify the Salt Lake City and
Provo PM2.5 nonattainment area from moderate to serious. PacifiCorp’s Lake Side and Gadsby
facilities were identified as major sources subject to Utah’s serious nonattainment area SIP for
PM2.5 and PM2.5 precursors. On April 27, 2017, PacifiCorp submitted a best-available control
15 Before February 9, 2018, the tax credit was strictly for CO2.
16 The tax credit reaches $35/tonne and $50/tonne in 2026.
17 For an electric generating facility, a minimum of 500,000 tonnes of qualified carbon oxide must be captured per
year to receive the 45Q tax credit. Construction of the qualified facility must begin before January 1, 2026.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
53
measure technology analysis for Lake Side and Gadsby to the Utah Division of Air Quality for
review. On January 2, 2019, the Utah Air Quality Board adopted source specific emission limits
and operating practices in the SIP which incorporated the current emission and operating limits for
the Lake Side and Gadsby facilities.
Regional Haze
EPA’s regional haze rule, finalized in 1999, requires states to develop and implement plans to
improve visibility in certain national park and wilderness areas. On June 15, 2005, EPA issued
final amendments to its regional haze rule to require emission controls known as the Best Available
Retrofit Technology (BART) for industrial facilities meeting certain regulatory criteria with
emissions that have the potential to affect visibility. The regulated pollutants include fine
particulate matter (PM), nitrogen oxide (NOX), sulfur dioxide (SO2), certain volatile organic
compounds, and ammonia. The 2005 amendments included final guidelines, known as BART
guidelines, for states to use in determining which facilities must install controls and the type of
controls the facilities must use. States were given until December 2007 to develop their
implementation plans, in which states were responsible for identifying the facilities that would
have to reduce emissions under BART guidelines, as well as establishing BART emissions limits
for those facilities. States are also required to periodically update or revise their implementation
plans to reflect current visibility data and an effective long-term strategy for achieving reasonable
progress toward visibility goals. In January 2017 EPA issued a final rule updating requirements
for the first periodic update to the state implementation plans (SIP). EPA required states to submit
their second periodic SIP update by July 31, 2021, unless granted an extension.
The regional haze rule is intended to achieve natural visibility conditions by 2064 in specific
National Parks and Wilderness Areas, many of which are in the western United States where
PacifiCorp owns and operates several coal-fired generating units (Utah, Wyoming, Colorado and
Montana as well as Arizona, where a PacifiCorp-owned coal unit ceased operating in 2020).
On August 20, 2019, EPA issued a final guidance document on the technical aspects of developing
regional haze SIPs for the second implementation period of the Regional Haze Program. EPA
issued additional guidance through a memorandum on July 8, 2021, that emphasizes the 4-factor
reasonable progress analysis for the second planning period and the reduced weight of visibility as
a factor in the second planning period.
Utah Regional Haze
In May 2011, the state of Utah issued a regional haze SIP requiring the installation of SO2, NOx
and PM controls on Hunter Units 1 and 2 and Huntington Units 1 and 2. In December 2012, the
EPA approved the SO2 portion of the Utah regional haze SIP and disapproved the NOX and PM
portions. EPA’s approval of the SO2 SIP was appealed by environmental advocacy groups to the
Tenth Circuit Court of Appeals (Tenth Circuit). In addition, PacifiCorp and the state of Utah
appealed EPA’s disapproval of the NOX and PM SIP. PacifiCorp and the state’s appeals were
dismissed, and the SO2 appeal was denied by the Tenth Circuit. In June 2015, the state of Utah
submitted a revised SIP to EPA for approval with an alternative BART NOx analysis incorporating
a requirement for PacifiCorp to retire Carbon Units 1 and 2, crediting NOX controls previously
installed on Hunter Unit 3, and concluding that no incremental controls (beyond those included in
the May 2011 SIP and already installed) were required at the Hunter and Huntington units. On
June 1, 2016, EPA issued a final rule to partially approve and partially disapprove Utah’s regional
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
54
haze SIP and propose a federal implementation plan (FIP). The FIP required the installation of
selective catalytic reduction (SCR) controls by August 4, 2021, at four of PacifiCorp’s units in
Utah, including Hunter Units 1 and 2 and Huntington Units 1 and 2. On September 2, 2016, the
state of Utah and PacifiCorp filed petitions for administrative and judicial review of EPA’s final
rule, followed by a motion to stay the effective date of the final rule.
On June 30, 2017, Utah and PacifiCorp provided new information to EPA, again requesting
reconsideration. EPA responded on July 14, 2017, indicating its intent to reconsider its FIP. EPA
also filed a motion with the Tenth Circuit to stay EPA’s FIP and hold the litigation in abeyance
pending the rule’s reconsideration. On September 11, 2017, the Tenth Circuit granted the petition
for stay and the request for abatement. The compliance deadline of the FIP and the litigation were
stayed pending EPA’s reconsideration, and EPA was required to file periodic status reports with
the Court.
Utah and PacifiCorp worked with EPA to develop a revised Utah Regional Haze SIP, based on the
new CAMx modeling. The Utah Air Quality Board approved the revised SIP on June 24, 2019,
and the SIP Revision was submitted to EPA for review on July 3, 2019. On December 3, 2019,
Utah submitted a supplement to EPA with a minor SIP revision relating to PM 2.5.
On January 10, 2020, the EPA published its proposed approval of the Utah SIP Revision and
withdrawal of the FIP requirements for the Hunter and Huntington plants to install SCR on Hunter
Units 1 and 2 and Huntington Units 1 and 2. After receiving public comments and holding a public
hearing in the Price area on February 12, 2020, EPA issued final approval of the Utah SIP Revision
and FIP withdrawal on November 27, 2020. The final rule credits existing NOX emission controls
at the Hunter and Huntington plants as well as NOX and PM emission reductions provided by the
closure of the Carbon plant in 2015. Based on the newly approved plan, EPA also withdrew the
2016 FIP requirements to install selective catalytic reduction (SCR) control technology on Hunter
Units 1 and 2 and Huntington Units 1 and 2. On January 11, 2021, the Tenth Circuit granted Utah,
PacifiCorp, and EPA’s motion to dismiss the Utah regional haze petitions.
Environmental advocacy groups filed a petition for review objecting to the revised Utah regional
haze SIP on January 20, 2021, in the Tenth Circuit. At EPA’s request, the Tenth Circuit abated the
petition on February 4, 2021, while EPA considers the petition under the new Biden
administration’s guidelines. The state of Utah, PacifiCorp and co-owners of the Hunter plant filed
motions to intervene, which remain under advisement until the abatement is lifted.
The Western Regional Air Partnership (WRAP) is currently developing the modeling that the state
will use for the implementation of the second planning period. Utah will use a ‘Q/d’ screening
level of 10 to determine which sources will be evaluated for reasonable progress controls under
the rule. On April 21, 2020, PacifiCorp submitted a Regional Haze Reasonable Progress Analysis
for the second planning period to the Utah Department of Environmental Quality for PacifiCorp’s
Huntington and Hunter plants. The analysis was requested by the State as part of its Second
Planning Period SIP development process. PacifiCorp’s analysis included a proposal to implement
reasonable progress emission limits for NOx and SO2 on the Hunter and Huntington units to meet
second planning period requirements. On October 20, 2020, PacifiCorp submitted a follow-up
letter in response to questions from the Utah Department of Environmental Quality (Utah DEQ)
about proposed emission reductions and costs for control technology. Utah DEQ and PacifiCorp
are engaged in ongoing discussions regarding evaluations and requirements for emission
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
55
reductions and control technologies.
Wyoming Regional Haze
On January 10, 2014, EPA issued a final rule partially approving and partially disapproving the Wyoming
SIP. The final rule required installation of the following NOX and PM controls at PacifiCorp facilities
for regional haze first planning period:
• Naughton Units 1 and 2: BART is LNB/OFA
• Naughton Unit 3 by December 31, 2014: SCR equipment and a baghouse
• Jim Bridger Unit 3 by December 31, 2015: SCR equipment
• Jim Bridger Unit 4 by December 31, 2016: SCR equipment
• Jim Bridger Unit 2 by December 31, 2021: SCR equipment
• Jim Bridger Unit 1 by December 31, 2022: SCR equipment
• Dave Johnston Unit 3: SCR within five years or a commitment to shut down in 2027
• Wyodak: SCR equipment within five years
Wyodak – PacifiCorp and the state of Wyoming petitioned EPA’s final action several requiring
SCR at Wyodak. PacifiCorp and other parties successfully requested a stay of EPA’s final rule
relating to the Wyoming SIP pending resolution of the petition. PacifiCorp subsequently submitted
a request for reconsideration to EPA and is currently engaged in a settlement process with EPA and
Wyoming. The EPA, state of Wyoming and PacifiCorp signed a Settlement Agreement for
Wyodak on December 16, 2020. EPA published the Settlement Agreement in the Federal Register
requesting public comment on January 4, 2021. PacifiCorp submitted formal comments to the EPA
on March 5, 2021, in support of the Wyodak Settlement Agreement. The public comment period
was extended through July 6, 2021. EPA did not proceed with final approval of the Settlement
Agreement and has engaged Wyoming and PacifiCorp regarding paths for resolution.
Naughton - In its 2014 rule, EPA approved Wyoming’s determination that BART for Units 1 and
2 was LNB/OFA. EPA also indicated support for the conversion of the Naughton Unit 3 to natural
gas in lieu of retrofitting the unit with SCR and stated that it would expedite consideration of the
gas conversion once the state of Wyoming submitted the requisite SIP amendment. Wyoming
submitted its Regional Haze SIP amendment regarding Naughton Unit 3 to EPA on November 28,
2017. On March 7, 2017, Wyoming issued PacifiCorp a permit for Unit 3’s conversion to natural
gas, which allowed operation of Unit 3 on coal through January 30, 2019. PacifiCorp ceased coal
operation on Unit 3 on January 30, 2019, as required by the permit. EPA’s final rule approval of
Wyoming’s SIP revision for Naughton Unit 3 gas conversion was published in the Federal
Register on March 21, 2019, with an effective date of April 22, 2019. Naughton Unit 3 currently
operates on natural gas. Environmental groups petitioned EPA’s approval of LNB/OFA as BART
for Units 1 and 2 in the Tenth Circuit. Like the Wyodak petition, that petition was stayed by the
court and remains stayed.
Jim Bridger - SCR was installed on Jim Bridger Units 3 and 4 by the dates required by Wyoming
in state law and by EPA in the 2014 final rule. On February 5, 2019, PacifiCorp submitted to
Wyoming an application and proposed SIP revision instituting plant-wide variable average
monthly-block pound per hour NOx and SO2 emission limits, in addition to an annual combined
NOx and SO2 limit, on all four Jim Bridger boilers in lieu of the requirement to install SCR on
Units 1 and 2. The proposed SIP revision demonstrates that the proposed limits are more cost
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
56
effective while leading to better modeled visibility than the SCR installation on Units 1 and 2
required in the federally approved SIP.
Wyoming’s proposed approval of the SIP revision was published for public comment July 20,
2019, through August 23, 2019. On May 5, 2020, the Wyoming Department of Environmental
Quality issued permit P0025809 with PacifiCorp’s proposed monthly and annual NOx and SO2
emission limits. Under the permit, the new emission limits become effective January 1, 2022.
Wyoming submitted a corresponding regional haze SIP revision to EPA on May 14, 2020. EPA
has not taken formal action responding to the SIP revision. Discussions between EPA, Wyoming,
and PacifiCorp regarding the SIP revision and regional haze compliance at Jim Bridger are
ongoing.
WRAP performed the modeling that the state will use for the implementation of the second
planning period. On March 31, 2020, PacifiCorp submitted a four-factor reasonable progress
analysis to Wyoming which analyzed PacifiCorp’s Naughton, Jim Bridger, Dave Johnston, and
Wyodak plants. The four-factor analyses will be used by the state in its development of the SIP for
the regional haze second planning period.
Arizona Regional Haze
The state of Arizona issued a regional haze SIP requiring, among other things, the installation of
SO2, NOX and PM controls on Cholla Unit 4, which is owned by PacifiCorp and operated by
Arizona Public Service. EPA approved in part and disapproved in part the Arizona SIP and issued
a FIP requiring the installation of SCR equipment on Cholla Unit 4. PacifiCorp filed an appeal
regarding the FIP as it relates to Cholla Unit 4, and the Arizona Department of Environmental
Quality and other affected Arizona utilities filed separate appeals of the FIP as related to their
interests. For the Cholla FIP requirements, the court stayed the appeals while parties attempted to
agree on an alternative compliance approach.
In July 2016, the EPA issued a proposed rule to approve an alternative Arizona SIP, which included
the option to convert Cholla 4 to a natural gas-fired unit or retire the unit by in 2025. EPA approved
the revised SIP on March 27, 2017. The final action allowed Cholla Unit 4 to utilize coal until
April 30, 2025, with an option to convert to gas by July 31, 2025. Cholla Unit 4 was retired in
December 2020.
Colorado Regional Haze
The Colorado regional haze SIP required SCR controls at Craig Unit 2 and Hayden Units 1 and 2.
In addition, the SIP required the installation of selective non-catalytic reduction (SNCR)
technology at Craig Unit 1 by 2018. Environmental groups appealed EPA’s action, and PacifiCorp
intervened in support of EPA. In July 2014, parties to the litigation other than PacifiCorp entered
into a settlement agreement that requires installation of SCR equipment at Craig Unit 1 in 2021.
In February 2015, the State of Colorado submitted a revised SIP to EPA for approval. As part of a
further agreement between the owners of Craig Unit 1, state and federal agencies, and parties to
previous settlements, the owners of Craig agreed to retire Unit 1 by December 31, 2025, or, to
convert the unit to natural gas by August 31, 2023. The Colorado Air Quality Board approved the
agreement on December 15, 2016. Colorado submitted the corresponding SIP amendment to EPA
Region 8 on May 17, 2017. EPA approved the SIP on July 5, 2018.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
57
Mercury and Hazardous Air Pollutants
The Mercury and Air Toxics Standards (MATS) became effective April 16, 2012. The MATS rule
required that new and existing coal-fueled facilities achieve emission standards for mercury, acid
gases and other non-mercury hazardous air pollutants. Existing sources were required to comply
with the new standards by April 16, 2015. However, individual sources may have been granted up
to one additional year, at the discretion of the Title V permitting authority, to complete installation
of controls or for transmission system reliability reasons. By April 2015, PacifiCorp had taken the
required actions to comply with MATS across its generation facilities. On April 25, 2016, the EPA
published a Supplemental Finding that determined that it is appropriate and necessary to regulate
under the MATS rule which addressed the Supreme Court decision.
On February 7, 2019, the EPA published a reconsideration of the Supplemental Finding in which
it proposed to find that it is not appropriate and necessary to regulate hazardous air pollutants,
reversing the Agency’s prior determination. In May 2020, the EPA published its decision to repeal
the appropriate and necessary findings in the MATS rule regarding regulation of electric utility
steam generating units, and to retain the rule’s current emission standards. The rule took effect in
July 2020. Several petitions for review were filed in the D.C. Circuit by parties challenging and
supporting the EPA's decision to rescind the appropriate and necessary finding. Until litigation over
the rule is exhausted, PacifiCorp cannot fully determine the potential impacts of the changes to the
MATS rule.
Coal Combustion Residuals
In May 2010, the EPA released a proposed rule to regulate the management and disposal of coal
combustion byproducts under the Resource Conservation and Recovery Act (RCRA). The final
rule became effective October 19, 2015. The final rule regulates coal combustion byproducts as
non-hazardous waste under RCRA Subtitle D and establishes minimum nationwide standards for
the disposal of coal combustion residuals (CCR). Under the final rule, surface impoundments and
landfills utilized for coal combustion byproducts may need to be closed unless they can meet the
more stringent regulatory requirements. The final rule requires regulated entities to post annual
groundwater monitoring and corrective action reports. The first of these reports was posted to
PacifiCorp’s coal combustion rule compliance data and information websites in March 2018.
Based on the results in those reports, additional action was required under the rule. At the time the
rule was published in April 2015, PacifiCorp operated 18 surface impoundments and seven
landfills that contained CCR. Before the effective date in October 2015, nine surface
impoundments and three landfills were either closed or repurposed to no longer receive CCR and
hence are not subject to the final rule.
Multiple parties filed challenges over various aspects of the final rule in 2015, resulting in
settlement of some of the issues and subsequent regulatory action by the EPA, including subjecting
inactive surface impoundments to regulation. In response to legal challenges and court actions,
EPA, in March 2018, issued a proposal to address provisions of the final CCR rule that were
remanded back to the agency. The proposal included provisions that establish alternative
performance standards for owners and operators of CCR units located in states that have approved
permit programs or are otherwise subject to oversight through a permit program administered by
the EPA. The first phase of the CCR rule amendments was made effective in August 2018 (the
"Phase 1, Part 1 rule"). In addition to adopting alternative performance standards and revising
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
58
groundwater performance standards for certain constituents, the EPA extended the deadline by
which facilities must initiate closure of unlined ash ponds exceeding a groundwater protection
standard and impoundments that do not meet the rule's aquifer location restrictions to October
2020.
Following the March 2019 submittal of competing motions from environmental groups, EPA
finalized its Holistic Approach to Closure: Part A rule ("Part A rule") in September 2020. The rule
reclassified compacted-soil lined surface impoundments from "lined" to "unlined," established a
deadline of April 11, 2021, by which all unlined surface impoundments must initiate closure, and
revised the alternative closure provisions to grant facilities additional time to initiate closure in
order to manage CCR and non-CCR waste streams either due to a lack of alternative capacity or
due to a commitment to close the coal-fueled operating unit and complete closure of unlined
impoundments by a date certain. The Part A rule also revised certain requirements regarding annual
groundwater monitoring and corrective action reports and publicly accessible CCR internet sites.
A provision in Part A allows demonstrations to be submitted to the EPA allowing for operation of
unlined CCR ponds beyond the April 11, 2021, deadline for initiation of closure. PacifiCorp has
submitted alternative closure demonstrations for the Naughton South Ash Pond and the Jim
Bridger FGD Pond 2. PacifiCorp anticipates a response and determination from EPA on both
demonstrations before the end of 2021.
On October 16, 2020, the EPA released the pre-publication version of the final Holistic Approach
to Closure: Part B rule ("Part B rule"). The Part B rule finalizes a two-step process, as set forth in
the March 2020 proposal, allowing facilities to request approval to continue operating an existing
unlined CCR surface impoundment with an alternate liner system. The other provisions that were
contained in the Part B proposal, including (1) options to use CCR during closure of a CCR unit,
(2) an additional closure-by-removal option and (3) new requirements for annual closure progress
reports, were not finalized with the Part B rule. These options will be addressed by the EPA in a
subsequent rulemaking action. In addition to the Part A and Part B rules, the EPA has proposed
the Phase II rule, the federal CCR permit program rule, and the advanced notice of proposed
rulemaking for legacy impoundments. Until the proposals are finalized and fully litigated,
PacifiCorp cannot determine whether additional action may be required.
Separately, on August 10, 2017, the EPA issued proposed permitting guidance on how states' coal
combustion residuals permit programs should comply with the requirements of the final rule as
authorized under the December 2016 Water Infrastructure Improvements for the Nation Act. To
date, none of the states in which PacifiCorp operates has submitted an application to the EPA for
approval of state permitting authority. The state of Utah adopted the federal final rule in September
2016, which required PacifiCorp to submit permit applications for two of its landfills by March
2017. It is anticipated that the state of Utah will submit an application to EPA for approval of its
coal combustion residuals permit program prior to the end of 2022. In 2019, the state of Wyoming
proposed to adopt state rules which incorporate the final federal rule by reference. Wyoming
finalized its rule in late 2020 and is waiting on legislative approval, likely in 2022, before submitting an
application to the EPA to implement a state permit program.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
59
Water Quality Standards
Cooling Water Intake Structures
The federal Water Pollution Control Act (“Clean Water Act”) establishes the framework for
maintaining and improving water quality in the United States through a program that regulates,
among other things, discharges to and withdrawals from waterways. The Clean Water Act requires
that cooling water intake structures reflect the “best technology available for minimizing adverse
environmental impact” to aquatic organisms. In May 2014, EPA issued a final rule, effective
October 2014, under § 316(b) of the Clean Water Act to regulate cooling water intakes at existing
facilities. The final rule established requirements for electric generating facilities that withdraw
more than two million gallons per day, based on total design intake capacity, of water from waters
of the United States and use at least 25 percent of the withdrawn water exclusively for cooling
purposes. PacifiCorp’s Dave Johnston generating facility withdraws more than two million gallons
per day of water from waters of the U.S. for once-through cooling applications. Jim Bridger,
Naughton, Gadsby, Hunter, and Huntington generating facilities currently use closed-cycle
cooling towers and withdraw more than two million but less than 125 million gallons of water per
day. The rule includes impingement (i.e., when fish and other aquatic organisms are trapped
against screens when water is drawn into a facility’s cooling system) mortality standards and
entrainment (i.e., when organisms are drawn into the facility) standards. The standards will be set
on a case-by-case basis to be determined through site-specific studies and will be incorporated into
each facility’s discharge permit.
Rule-required permit application requirements (PARs) have been submitted to the appropriate
permitting authorities for the Jim Bridger, Naughton, Gadsby, Hunter and Huntington plants. As
the five facilities utilize closed-cycle recirculating cooling water systems (cooling towers)
exclusively for equipment cooling, it is expected that state agencies will require no further action
from PacifiCorp to comply with the rule-required standards.
Because Dave Johnston utilizes once-through cooling with withdrawal rates greater than 125
million gallons per day, the facility has been required to conduct more rigorous permit application
requirements. The Dave Johnston permit application requirements were submitted to the Wyoming
Water Quality Division on May 31, 2019. The application proposed that no modifications to the
intake structure were required; however, upon review of the submittal and subsequent issuance of a
draft permit for public notice, the Water Quality Division has indicated that PacifiCorp may be
required to select and implement an approved 316(b) impingement mortality compliance option by
December 31, 2023. As the final Dave Johnston Wyoming Pollutant Discharge Elimination
System permit has yet to be issued which is expected to include 316(b) impingement mortality
(IM) compliance requirements, it is anticipated that the December 31, 2023 IM technology
implementation date will be adjusted to compensate for the actual permit issuance date.
Effluent Limit Guidelines
In November 2015, the EPA published final effluent limitation guidelines and standards for the
steam electric power generating sector which, among other things, regulate the discharge of bottom
ash transport water, fly ash transport water, combustion residual leachate and non-chemical metal
cleaning wastes. These guidelines, which had not been revised since 1982, were revised in
response to the EPA's concerns that the addition of controls for air emissions has changed the
effluent discharged from coal- and natural gas-fueled generating facilities. Under the originally
promulgated guidelines, permitting authorities were required to include the new limits in each
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
60
impacted facility's National Pollutant Discharge Elimination System permit upon renewal with the
new limits to be met as soon as possible, beginning November 1, 2018 and fully implemented by
December 31, 2023.
On April 5, 2017, a request for reconsideration and administrative stay of the guidelines was filed
with the EPA. EPA granted the request for reconsideration and extended certain compliance dates
for flue gas desulfurization wastewater and bottom ash transport water limits until November 1,
2020.
On November 22, 2019, EPA proposed updates to the 2015 rule, specifically addressing flue gas
desulfurization wastewater and bottom ash transport water. Those proposals were formalized in
rule when the EPA administrator signed the Reconsideration Rule, and it was published in the
Federal Register on October 13, 2020. The rule eases selenium limits on flue gas desulfurization
wastewater, eases the zero-discharge requirements on bottom ash transport water associated with
blowdown of ash handling systems, allows a two-year time extension to meet flue gas
desulfurization wastewater requirements, and includes additional subcategories to both wastewater
categories.
Most of the issues raised by this rule are already being addressed at PacifiCorp facilities through
compliance with the coal combustion residuals rule and are not expected to impose significant
additional requirements on the facilities. The Dave Johnston plant anticipates achieving
compliance with the rule by issuing a notice of planned participation for subcategorization, or by
installation and operation of a bottom ash recycle system that would enable long-term compliance
with the Reconsideration Rule.
Renewable Generation Regulatory Framework
Regulatory and permitting requirements for renewable energy projects are addressed at federal,
state, and local levels. All wind projects in the United States must comply with federal regulations
for wildlife impacts, aviation safety, clean water, communication systems, and Department of
Defense impacts. Eagle Incidental Take Permits (EITPs), including associated surveys,
monitoring, and compensatory mitigation, are necessary for wind projects that may result in take
of bald or golden eagles. State and county regulations often address localized topics such as road
and traffic concerns, community economic impacts, viewshed requirements, sage-grouse
stipulations, wind turbine location guidelines, and land use and zoning restrictions. Solar projects
must comply with federal and state regulations that restrict disturbance of certain flora and fauna
and are subject to local planning and zoning regulations for land use. Storm water pollution
prevention plans for renewable projects are usually required on a state level to control sediment
runoff during construction and all renewable projects must comply with the Clean Water Act rules
which are controlled at the federal level. Renewable energy projects located on federally managed
lands are subject to National Environmental Policy Act (NEPA) review, which may include
cultural and biological resource surveys, assessment of potential impacts, public comment periods,
and avoidance/minimization/mitigation efforts. Power lines associated with renewable energy
projects, including collector lines at the project site and grid-connecting transmission lines, may
also be subject to environmental regulations, review, stipulations, or permits.
The wind projects constructed as part of PacifiCorp’s Energy Vision 2020 initiative for example,
(TB Flats, Ekola Flats, and Cedar Springs) were required to obtain permits from the State of
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
61
Wyoming’s Industrial Siting Division which required extensive studies of the conditions of the
site, coordination with state agencies in the development process, and forecast of impacts from the
project. Renewable energy projects in the State of Wyoming that meet the Industrial Siting
Division’s size or capital thresholds must obtain approval before they can begin construction. Most
wind project developers coordinate with federal and/or state authorities to evaluate and mitigate
potential impacts to birds or other wildlife species, particularly eagles, migratory birds, and bats,
during the wind turbine siting process to minimize wildlife impacts and potential operational risks.
Greater sage-grouse are currently managed by the states, and renewable energy projects and
associated transmission lines would require state agency review; stipulations or mitigation
requirements vary by state and project impacts. Because the generation capabilities of renewable
energy projects are site specific and can vary greatly between different sites, understanding the
specific permit requirements for each site is critical to developing a successful project.
Tax Extender Legislation
On Dec. 27, 2020, President Trump signed into law the Taxpayer Certainty and Disaster Relief
Act of 2020. Among other things, the bill extended and expanded certain alternative energy tax
credits. Notable as relating to the 2021 IRP, the renewable electricity production tax credit (PTC)
was extended by one year for certain qualifying facilities; for wind facilities that begin construction
during 2021, the credit continues to be equal to 60% of the full value of the PTC. The energy tax
credit (ITC) was extended by two years for certain qualifying facilities; the bill extends the 26%
ITC for solar energy property that begins construction during 2021 and 2022, before being phased
down further.
The energy tax credit was expanded to cover offshore wind facilities; generally, any offshore wind
project that on which construction after December 31, 2017, and before January 1, 2026, will
qualify for a 30% ITC. And, finally, the credit for carbon dioxide sequestration was extended to
cover facilities that begin construction by the end of 2025. Additional schedules detailing the
phase-out of the wind PTC and solar ITC are provided as follows:
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
62
Table 3.1 – Tax Extender Legislation and Phaseout of PTC and ITC
State Policy Update
California
Under the authority of the Global Warming Solutions Act, the California Air Resources Board
(CARB) adopted a greenhouse gas cap-and-trade program in October 2011, with an effective date
of January 1, 2012; compliance obligations were imposed on regulated entities beginning in 2013.
The first auction of greenhouse gas allowances was held in California in November 2012, and the
second auction in February 2013. PacifiCorp is required to sell, through the auction process, its
directly allocated allowances and purchase the required allowances necessary to meet its
compliance obligations.
In May 2014, CARB approved the first update to the Assembly Bill (AB) 32 Climate Change
scoping plan, which defined California’s climate change priorities for the next five years and set
the groundwork for post-2020 climate goals. In April 2015, Governor Brown issued an executive
order to establish a mid-term reduction target for California of 40 percent below 1990 levels by
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
63
2030. CARB has subsequently been directed to update the AB 32 scoping plan to reflect the new
interim 2030 target and previously established 2050 target.
In 2002, California established a RPS requiring investor-owned utilities to increase procurement
from eligible renewable energy resources. California’s RPS requirements have been accelerated
and expanded a number of times since its inception. Most recently, in September 2018, Governor
Jerry Brown signed into law the 100 Percent Clean Energy Act of 2018, Senate Bill (SB) 100,
which requires utilities to procure 60 percent of their electricity from renewables by 2030 and
enabled all the state’s agencies to work toward a longer-term planning target for 100 percent of
California’s electricity to come from renewable and zero-carbon resources by December 31, 2045.
Oregon
In 2007, the Oregon Legislature passed House Bill (HB) 3543 – Global Warming Actions, which
establishes greenhouse gas reduction goals for the state that: (1) end the growth of Oregon
greenhouse gas emissions by 2010; (2) reduce greenhouse gas levels to ten percent below 1990
levels by 2020; and (3) reduce greenhouse gas levels to at least 75 percent below 1990 levels by
2050. In 2009, the legislature passed SB 101, which requires the Public Utility Commission of
Oregon (OPUC) to submit a report to the legislature before November 1 of each even-numbered
year regarding the estimated rate impacts for Oregon’s regulated electric and natural gas
companies of meeting the greenhouse gas reduction goals of ten percent below 1990 levels by
2020 and 15 percent below 2005 levels by 2020. The OPUC submitted its most recent report
November 1, 2014.
In 2007, Oregon enacted Senate Bill (SB) 838 establishing an RPS requirement in Oregon. Under
SB 838, utilities are required to deliver 25 percent of their electricity from renewable resources by
2025. On March 8, 2016, Governor Kate Brown signed SB 1547-B, the Clean Electricity and Coal
Transition Plan, into law. SB 1547-B extends and expands the Oregon RPS requirement to 50
percent of electricity from renewable resources by 2040 and requires that coal-fueled resources are
eliminated from Oregon’s allocation of electricity by January 1, 2030. The increase in the RPS
requirements under SB 1547-B is staged—27 percent by 2025, 35 percent by 2030, 45 percent by
2035, and 50 percent by 2040. The bill changes the renewable energy certificate (REC) life to five
years, while allowing RECs generated from the effective date of the bill passage until the end of
2022 from new long-term renewable projects to have unlimited life. The bill also includes
provisions to create a community solar program in Oregon and encourage greater reliance on
electricity for transportation.
On March 10, 2020, Oregon Governor Kate Brown issued Executive Order 20-04 (EO 20-04),
which directs state agencies to take actions to reduce and regulate greenhouse gas emissions.
EO 20-04 establishes emissions reduction goals for Oregon and directs certain state agencies to
take specific actions to reduce emissions and mitigate the impacts of climate change. EO 20-04
also provides overarching direction to state agencies to exercise their statutory authority to help
achieve Oregon's climate goals.
In 2021, Oregon passed House Bill 2021, which directs utilities to reduce emissions levels below
2010-2012 baseline levels by 80% by 2030, 90% by 2035, and 100% by 2040. Utilities will also
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
64
convene a Community Benefits and Impacts Advisory Group. PacifiCorp’s 2023 IRP will include
modeling to support House Bill 2021.
Washington
In November 2006, Washington voters approved Initiative 937 (I-937), the Washington Energy
Independence Act, which imposes targets for energy conservation and the use of eligible
renewable resources on electric utilities. Under I-937, utilities must supply 15 percent of their
energy from renewable resources by 2020. Utilities must also set and meet energy conservation
targets starting in 2010.
In 2008, the Washington Legislature approved the Climate Change Framework E2SHB 2815,
which establishes the following state greenhouse gas emissions reduction limits: (1) reduce
emissions to 1990 levels by 2020; (2) reduce emissions to 25 percent below 1990 levels by 2035;
and (3) by 2050, reduce emissions to 50 percent below 1990 levels or 70 percent below
Washington’s forecasted emissions in 2050.
In July 2015, Governor Inslee released an executive order that directed the Washington
Department of Ecology to develop new rules to reduce carbon emissions in the state. In December
2017, Washington’s Superior Court concluded that the Department of Ecology did not have the
authority to impose the Clean Air Rule without legislative approval. As a result, the Department
of Ecology has suspended the rule’s compliance requirements.
In 2019, the Washington Legislature approved the Clean Energy Transformation Act (CETA)
which requires utilities to eliminate coal-fired resources from Washington rates by December 31,
2025, be carbon neutral by January 1, 2030, and establishes a target of 100 percent of its electricity
from renewable and non-emitting resources by 2045.
In 2021, Washington passed the Climate Commitment Act, which establishes a cap-and-trade
program to be implemented by no later than 2023 through the regulatory rulemaking process. The
Climate Commitment Act does not modify any of PacifiCorp’s obligations under CETA, and
utility allowances within the cap-and-trade program are aligned with the CETA renewable energy
requirements. The legislation allows – but does not require – linkage with cap-and-trade programs
in jurisdictions outside of Washington State.
Utah
In March 2008, Utah enacted the Energy Resource and Carbon Emission Reduction Initiative,
which includes provisions to require utilities to pursue renewable energy to the extent that it is cost
effective. It sets out a goal for utilities to use eligible renewable resources to account for 20 percent
of their 2025 adjusted retail electric sales.
On March 10, 2016, the Utah legislature passed SB 115–The Sustainable Transportation and
Energy Plan (STEP). The bill supports plans for electric vehicle infrastructure and clean coal
research in Utah and authorizes the development of a renewable energy tariff for new Utah
customer loads. The legislation establishes a five-year pilot program to provide mandated funding
for electric vehicle infrastructure and clean coal research, and discretionary funding for solar
development, utility-scale battery storage, and other innovative technology and air quality
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
65
initiatives. The legislation also allows PacifiCorp to recover its variable power supply costs
through an energy balancing account and establishes a regulatory accounting mechanism to
manage risks and provide planning flexibility associated with environmental compliance or other
economic impairments that may affect PacifiCorp’s coal-fueled resources in the future. The
deferrals of variable power supply costs went into effect in June 2016, and implementation and
approval of the other programs was completed by January 1, 2017.
On March 11, 2020, the Utah Legislature passed HB 396, Electric Vehicle Charging Infrastructure
Amendments, that enables PacifiCorp to create an Electrical Vehicle Infrastructure Program, with
a maximum funding from customers of $50 million for all costs and expenses. The legislation
allows PacifiCorp to own and operate electric vehicle charging stations and to provide investments
in make-ready infrastructure to interested customers.
Wyoming
On March 8, 2019, Wyoming Senate File 0159 (SF 159) was passed into law. SF 159 limits the
recovery costs for the retirement of coal fired electric generation facilities, provides a process for
the sale of an otherwise retiring coal fired electric generation facility, exempts a person purchasing
an otherwise retiring coal fired electric generation facility from regulation as a public utility;
requires purchase of electricity generated from purchased retiring coal fired electric generation
facility (as specified in final bill); and provides an effective date.
Cost recovery associated with electric generation built to replace a retiring coal fired generation
facility shall not be allowed by the Wyoming Public Service Commission unless the Commission
has determined that the public utility made a good faith effort to sell the facility to another person
prior to its retirement and that the public utility did not refuse a reasonable offer to purchase the
facility or the Commission determines that, if a reasonable offer was received, the sale was not
completed for a reason beyond the reasonable control of the public utility.
Under SF 159 electric public utilities, other than cooperative electric utilities, shall be obligated to
purchase electricity generated from a coal fired electric generation facility purchased under
agreement approved by the Commission, provided the otherwise retiring coal fired electric
generation facility offers to sell some or all of the electricity from the facility to an electric public
utility, the electricity is sold at a price that is no greater than the purchasing electric utility’s
avoided cost, the electricity is sold under a power purchase agreement, and the Commission
approves a 100 percent cost recovery in rates for the cost of the power purchase agreement and the
agreement is 100 percent allocated to the public utility’s Wyoming customers unless otherwise
agreed to by the public utility.
In March 2020, the Wyoming legislature passed House Bill 200 (HB 200), Reliable and
Dispatchable Low-Carbon Energy Standards. HB 200 requires the Wyoming Public Service
Commission to put in place a standard for each public utility specifying a percentage of electricity
to be generated from coal-fired generation utilizing carbon capture technology by 2030. The
requirement would only apply to generation allocated to Wyoming customers. HB 200 will require
each public utility to demonstrate in its IRP the steps taken to achieve the electricity generation
standard established by the Commission and will allow rate recovery of costs incurred by a public
utility that utilizes coal-fired generation with carbon capture technology installed.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
66
Greenhouse Gas Emission Performance Standards
California, Oregon and Washington have greenhouse gas emission performance standards
applicable to all electricity generated in the state or delivered from outside the state that is no higher
than the greenhouse gas emission levels of a state-of-the-art combined cycle natural gas generation
facility. The standards for Oregon and California are currently set at 1,100 lb CO2/MWh, which is
defined as a metric measure used to compare the emissions from various greenhouse gases based
on their global warming potential. In September 2018, the Washington Department of Commerce
issued a new rule lowering the emissions performance standard to 925 lb CO2/MWh.
Renewable Portfolio Standards
An RPS requires a retail seller of electricity to include in its resource portfolio a certain amount of
electricity from renewable energy resources, such as wind, geothermal and solar energy. The
retailer can satisfy this obligation by using renewable energy from its own facilities, purchasing
renewable energy from another supplier’s facilities, using Renewable Energy Credits (RECs) that
certify renewable energy has been generated, or a combination of all of these.
RPS policies are currently implemented at the state level and vary considerably in their renewable
targets (percentages), target dates, resource/technology eligibility, applicability of existing plants
and contracts, arrangements for enforcement and penalties, and use of RECs.
In PacifiCorp’s service territory, California, Oregon, and Washington have each adopted a
mandatory RPS, and Utah has adopted a RPS goal. Each of these states’ legislation and
requirements are summarized in Table 3.2, with additional discussion below.
Table 3.2 – State RPS Requirements
California Oregon Washington Utah
Legislation • Senate Bill 1078 (2002)
• Assembly Bill 200 (2005)
• Senate Bill 107 (2006)
• Senate Bill 2 First
Extraordinary Session (2011)
• Senate Bill 350 (2015)
• Senate Bill 100 (2018)
• Senate Bill 838 Oregon
Renewable Energy Act
(2007)
• House Bill 3039 (2009)
• House Bill 1547-B (2016)
• Initiative Measure No.
937 (2006)
• SB 5400 (2013)
• Senate Bill 202 (2008)
Requirement
or Goal
• 20% by December 31, 2013
• 25% by December 31, 2016
• 33% by December 31, 2020
• 44% by December 31, 2024
• 52% by December 31, 2027
• 60% by December 31, 2030
and beyond
• Planning target of 100%
renewable and zero-carbon
by 2045
* Based on the retail load for a
three-year compliance period
• 5% by December 31, 2011
• 15% by December 31, 2015
• 20% by December 31, 2020
• 27% by December 31, 2025
• 35% by December 31, 2030
• 45% by December 31, 2035
• 50% by December 31, 2040
* Based on the retail load for
that year
• 3% by January 1, 2012
• 9% by January 1, 2016
• 15% by January 1,
2020 and beyond
* Annual targets are
based on the average of
the utility’s load for the
previous two years
• Goal of 20% by 2025
(must be cost
effective)
• Annual targets are
based on the
adjusted18 retail sales
for the calendar year
36 months before the
target year
18 Adjustments for generated or purchased from qualifying zero carbon emissions and carbon capture storage and
DSM.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
67
California
California originally established its RPS program with passage of SB 1078 in 2002. Several bills
that have since been passed into law to amend the program. In the 2011 First Extraordinary Special
Session, the California Legislature passed SB 2 (1X) to increase California’s RPS to 33 percent
by 2020.19 SB 2 (1X) also expanded the RPS requirements to all retail sellers of electricity and
publicly owned utilities. In October 2015, SB 350, the Clean Energy and Pollution Reduction Act,
was signed into law.20 SB 350 established a greenhouse gas reduction target of 40 percent below
1990 levels by 2030 and 80 percent below 1990 levels by 2050 and expanded the state’s
renewables portfolio standard to 50 percent by 2030. In September 2018, the signing of SB 100,
the Clean Energy Act of 2018, further expanded and accelerated the California RPS to 60 percent
by 2030 and directed the state’s agencies to plan for a longer-term goal of 100 percent of total
retail sales of electricity in California to come from eligible renewable and zero-carbon resources
by December 31, 2045.
SB 2 (1X) created multi-year RPS compliance periods, which were expanded by SB 100. The
California Public Utilities Commission approved compliance periods and corresponding RPS
procurement requirements, which are shown in Table 3.3 below.
Table 3.3 – California Compliance Period Requirements
Compliance Period Procurement Quantity Requirement Calculation
Compliance Period 1 (2011-2013) (20% * 2011 Retail Sales) + (20% * 2012 Retail Sales)
+ (20% * 2013 Retail Sales)
Compliance Period 2 (2014-2016) (21.7% * 2014 Retail Sales) + (23.3% * 2015 Retail Sales)
+ (25% * 2016 Retail Sales)
Compliance Period 3 (2017-2020) (27% * 2017 Retail Sales) + (29% * 2018 Retail Sales)
+ (31% * 2019 Retail Sales) + (33% * 2020 Retail Sales)
Compliance Period 4 (2021-2024) (35.8% * 2021 Retail Sales) + (38.5% * 2022 Retail Sales) + (41.3% * 2023 Retail Sales) + (44% * 2024 Retail Sales)
Compliance Period 5 (2025-2027) (47% * 2025 Retail Sales) + (50% * 2026 Retail Sales)
+ (52% * 2027 Retail Sales)
Compliance Period 6 (2028-2030) (54.7% * 2028 Retail Sales) + (57.3% * 2029 Retail Sales)
+ (60% * 2030 Retail Sales)
SB 2 (1X) established new “portfolio content categories” for RPS procurement, which delineated
the type of renewable product that may be used for compliance and also set minimum and
maximum limits on certain procurement content categories that can be used for compliance.
Portfolio Content Category 1 includes eligible renewable energy and RECs that meet either of the
following criteria:
Have a first point of interconnection with a California balancing authority, have a first
point of interconnection with distribution facilities used to serve end users within a
California balancing authority area, or are scheduled from the eligible renewable
energy resource into a California balancing authority without substituting electricity
from another source;11 or
Have an agreement to dynamically transfer electricity to a California balancing
19 www.leginfo.ca.gov/pub/11-12/bill/sen/sb_0001-0050/sbx1_2_bill_20110412_chaptered.pdf
20 leginfo.legislature.ca.gov/faces/billNavClient.xhtml?bill_id=201520160SB350
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
68
authority.
Portfolio Content Category 2 includes firmed and shaped eligible renewable energy resource
electricity products providing incremental electricity and scheduled into a California balancing
authority.
Portfolio Content Category 3 includes eligible renewable energy resource electricity products, or
any fraction of the electricity, including unbundled renewable energy credits that do not qualify
under the criteria of Portfolio Content Category 1 or Portfolio Content Category 2.21
Additionally, the CPUC established the balanced portfolio requirements for contracts executed
after June 1, 2010. The balanced portfolio requirements set minimum and maximum levels for the
Procurement Content Category products that may be used in each compliance period as shown in
Table 3.4.
Table 3.4 – California Balanced Portfolio Requirements
California RPS Compliance Period Balanced Portfolio Requirement
Compliance Period 1 (2011-2013) Category 1 – Minimum of 50% of Requirement
Category 3 – Maximum of 25% of Requirement
Compliance Period 2 (2014-2016) Category 1 – Minimum of 65% of Requirement
Category 3 – Maximum of 15% of Requirement
Compliance Period 3 (2017-2020)
Compliance Period 4 (2021-2024)
Compliance Period 5 (2025-2027)
Compliance Period 6 (2028-2030)
Category 1 – Minimum of 75% of Requirement
Category 3 – Maximum of 10% of Requirement
In December 2011, the CPUC confirmed that multi-jurisdictional utilities, such as PacifiCorp, are
not subject to the percentage limits in the three portfolio content categories. PacifiCorp is required
to file annual compliance reports with the CPUC and annual procurement reports with the
California Energy Commission (CEC). Neither SB 350 nor SB 100 changed the portfolio content
categories for eligible renewable energy resources or the portfolio balancing requirements
exemption provided to PacifiCorp. For utilities subject to the portfolio balancing requirements, the
CPUC extended the compliance period 3 requirements through 2030.
The full California RPS statute is listed under Public Utilities Code Section 399.11-399.32.
Additional information on the California RPS can be found on the CPUC and CEC websites.
Qualifying renewable resources include solar thermal electric, photovoltaic, landfill gas, wind,
biomass, geothermal, municipal solid waste, energy storage, anaerobic digestion, small
hydroelectric, tidal energy, wave energy, ocean thermal, biodiesel, and fuel cells using renewable
fuels. Renewable resources must be certified as eligible for the California RPS by the CEC and
tracked in the Western Renewable Energy Generation Information System (WREGIS).
21 A REC can be sold either “bundled” with the underlying energy or “unbundled” as a separate commodity from the
energy itself into a separate REC trading market.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
69
Oregon
Oregon established the Oregon RPS with passage of SB 838 in 2007. The law, called the Oregon
Renewable Energy Act, was adopted in June 2007, and provides a comprehensive renewable
energy policy for the state.22 Subject to certain exemptions and cost limitations established in the
Oregon Renewable Energy Act, PacifiCorp and other qualifying electric utilities must meet a target
of at least 25 percent renewable energy by 2025. In March 2016, the Legislature passed SB 1547,23
also referred to as Oregon’s Clean Electricity and Coal Transition Act. In addition to requiring
Oregon to transition off coal by 2030, the new law doubled Oregon’s RPS requirements, which
are to be staged at 27 percent by 2025, 35 percent by 2030, 45 percent by 2035, and 50 percent by
2040 and beyond. Other components of SB 1547 include:
• Development of a community solar program with at least 10 percent of the program
capacity reserved for low-income customers.
• A requirement that by 2025, at least eight percent of the aggregate electric capacity
of the state’s investor-owned utilities must come from small-scale renewable projects
under 20 megawatts.
• Creates new eligibility for pre-1995 biomass plants and associated thermal co-
generation. Under the previous law, pre-1995 biomass was not eligible until 2026.
• Direction to the state’s investor-owned utilities to propose plans encouraging greater
reliance on electricity in all modes of transportation, to reduce carbon emissions.
• Removal of the Oregon Solar Initiative mandate.24
SB 1547 also modified the Oregon REC banking rules as follows:
• RECs generated before March 8, 2016, have an unlimited life.
• RECs generated during the first five years for long-term projects coming online
between March 8, 2016, and December 31, 2022, have an unlimited life.
• RECs generated on or after March 8, 2016, from resources that came online
before March 8, 2016, expire five years beyond the year the REC was
generated.
• RECs generated beyond the first five years for long-term projects coming online
between March 8, 2016, and December 31, 2022, expire five years beyond the year
the REC is generated.
• RECs generated from projects coming online after December 31, 2022, expire five
years beyond the year the REC is generated.
• Banked RECs can be surrendered in any compliance year regardless of vintage
(eliminates the “first-in, first-out” provision under SB 838).
To qualify as eligible, the RECs must be from a resource certified as Oregon RPS eligible by the
Oregon Department of Energy and tracked in WREGIS.
22 www.leg.state.or.us/07reg/measpdf/sb0800.dir/sb0838.en.pdf
23 olis.leg.state.or.us/liz/2016R1/Downloads/MeasureDocument/SB1547/Enrolled
24 In 2009, Oregon passed House Bill 3039, also called the Oregon Solar Initiative, requiring that on or before
January 1, 2020, the total solar photovoltaic generating nameplate capacity must be at least 20 megawatts from all
electric companies in the state. The Public Utility Commission of Oregon determined that PacifiCorp’s share of the
Oregon Solar Initiative was 8.7 megawatts.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
70
Qualifying renewable energy sources can be located anywhere in the United States portion of the
Western Electricity Coordinating Council geographic area, and a limited amount of unbundled
renewable energy credits can be used toward the annual compliance obligation. Eligible renewable
resources include electricity generated from wind, solar photovoltaic, solar thermal, wave, tidal,
ocean thermal, geothermal, certain types of biomass and biogas, municipal solid waste, and
hydrogen power stations using anhydrous ammonia.
Electricity generated by a hydroelectric facility is eligible if the facility is not located in any
federally protected areas designated by the Pacific Northwest Electric Power and Conservation
Planning Council as of July 23, 1999, or any area protected under the federal Wild and Scenic
Rivers Act, P.L. 90-542, or the Oregon Scenic Waterways Act, ORS 390.805 to 390.925; or if the
electricity is attributable to efficiency upgrades made to the facility on or after January 1, 1995,
and up to 50 average megawatts of electricity per year generated by a certified low-impact
hydroelectric facility owned by an electric utility and up to 40 average megawatts of electricity per
year generated by certified low-impact hydroelectric facilities not owned by electric utilities.
PacifiCorp files an annual RPS compliance report by June 1 of every year and a renewable
implementation plan on or before January 1 of even-numbered years, unless otherwise directed by
the Public Utility Commission of Oregon. These compliance reports and implementation plans are
available on PacifiCorp’s website.25
The full Oregon RPS statute is listed in Oregon Revised Statutes (ORS) Chapter 469A and the
solar capacity standard is listed in ORS Chapter 757. The Public Utility Commission of Oregon
rules are in Oregon Administrative Rules (OAR) Chapter 860 Division 083 for the RPS and OAR
Chapter 860 Division 084 for the solar photovoltaic program. The Oregon Department of Energy
rules are under OAR Chapter 330 Division 160.
Utah
In March 2008, Utah’s governor signed Utah SB 202, the Energy Resource and Carbon Emission
Reduction Initiative.26 The Energy Resource and Carbon Emission Reduction Initiative is codified
in Utah Code Title 54 Chapter 17. Among other things, this law provides that, beginning in the
year 2025, 20 percent of adjusted retail electric sales of all Utah utilities be supplied by renewable
energy if it is cost effective. Retail electric sales will be adjusted by deducting the amount of
generation from sources that produce zero or reduced carbon emissions and for sales avoided
because of energy efficiency and demand side management programs. Qualifying renewable
energy sources can be located anywhere in the Western Electricity Coordinating Council areas,
and unbundled renewable energy credits can be used for up to 20 percent of the annual qualifying
electricity target.
Eligible renewable resources include electricity from a facility or upgrade that becomes
operational on or after January 1, 1995, that derives its energy from wind, solar photovoltaic, solar
thermal electric, wave, tidal or ocean thermal, certain types of biomass and biomass products,
landfill gas or municipal solid waste, geothermal, waste gas and waste heat capture or recovery,
and efficiency upgrades to hydroelectric facilities if the upgrade occurred after January 1, 1995.
Up to 50 average megawatts from a certified low-impact hydro facility and in-state geothermal
25 www.pacificpower.net/ORrps
26 le.utah.gov/~2008/bills/sbillenr/sb0202.pdf
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
71
and hydro generation without regard to operational online date may also be used toward the target.
To assist solar development in Utah, solar facilities located in Utah receive credit for 2.4 kilowatt-
hours of qualifying electricity for each kWh of generation.
Under the Carbon Reduction Initiative, PacifiCorp is required to file a progress report by January 1
of each of the years 2010, 2015, 2020 and 2024.
PacifiCorp filed its most recent progress report on December 31, 2019. This report showed that
the company is positioned to meet its 20 percent target requirement of approximately 4.8 million
megawatt-hours of renewable energy in 2025 from existing company-owned and contracted
renewable energy sources.
In 2027, the legislation requires a commission report to the Utah Legislature, which may contain
any recommendation for penalties or other action for failure to meet the 2025 target. The legislation
requires that any recommendation for a penalty must provide that the penalty funds be used for
demand side management programs for the customers of the utility paying the penalty.
Washington
In November 2006, Washington voters approved I-937, a ballot measure establishing the Energy
Independence Act, which is an RPS and energy efficiency requirement applied to qualifying
electric utilities, including PacifiCorp.27 The law requires that qualifying utilities procure at least
three percent of retail sales from eligible renewable resources or RECs by January 1, 2012 through
2015; nine percent of retail sales by January 1, 2016 through 2019; and 15 percent of retail sales
by January 1, 2020, and every year thereafter.
Eligible renewable resources include electricity produced from water, wind, solar energy,
geothermal energy, landfill gas, wave, ocean, or tidal power, gas from sewage treatment facilities,
biodiesel fuel with limitation, and biomass energy based on organic byproducts of the pulp and
wood manufacturing process, animal waste, solid organic fuels from wood, forest, or field
residues, or dedicated energy crops. Qualifying renewable energy sources must be located in the
Pacific Northwest or delivered into Washington on a real-time basis without shaping, storage, or
integration services. The only hydroelectric resource eligible for compliance is electricity
associated with efficiency upgrades to hydroelectric facilities. Utilities may use eligible renewable
resources, RECs, or a combination of to meet the RPS requirement.
PacifiCorp is required to file an annual RPS compliance report by June 1 of every year with the
Washington Utilities and Transportation Commission (WUTC) demonstrating compliance with
the Energy Independence Act. PacifiCorp’s compliance reports are available on PacifiCorp’s
website.28
The WUTC adopted final rules to implement the initiative; the rules are listed in the Revised Code
of Washington (RCW) 19.285 and the Washington Administrative Code (WAC) 480-109.
27 www.secstate.wa.gov/elections/initiatives/text/I937.pdf
28 www.pacificpower.net/report
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
72
REC Management Practices
PacifiCorp provides the following summary of REC management practices in compliance with
Order 20-186 in Oregon. The company intends to maximize the value of RECs for customers either
through retirement for compliance purposes or monetization through sales. As a multi-state utility,
PacifiCorp has Renewable Portfolio Standards in Washington, Oregon, and California, and a
Renewable Portfolio Goal in 2025 in Utah. PacifiCorp generally retains and retires RECs allocated
to Washington, Oregon, and California for compliance purposes, but requests flexibility to manage
its RECs based on opportunities it sees in the market, which may include selling RECs at a
favorable price and acquiring RECs at a lower price. The company maximizes the sale of RECs
allocated to Utah, Idaho, and Wyoming and allocates the revenue from those sales to those states.
Clean Energy Standards
Washington
In 2019, Governor Jay Inslee signed into law Senate Bill 5116, the Clean Energy Transformation
Act. Under the law, Washington utilities are required to be carbon neutral by January 1, 2030 and
institute a planning target of 100 percent clean electricity by 2045. The bill establishes four-year
compliance periods beginning January 1, 2030 and requires utilities to use electricity from
renewable resources and non-emitting electric generation in an amount equal to 100 percent of the
retail electric load over each compliance period. Through December 31, 2044, an electric utility
may satisfy up to 20 percent of its compliance obligation with an alternative compliance option
such as the purchase of unbundled RECs.
Oregon
In July 2021, Oregon Governor Kate Brown signed into law House Bill 2021, which set emissions
reduction targets for utilities and electricity providers. Under the law, retail electricity providers
shall reduce greenhouse gas emissions by 80 percent below baseline emissions levels by 2030, by
90 percent below baseline emissions level by 2035, and by 100 percent below baseline emissions
levels by 2040.
California
In 2018, California passed Senate Bill 100 – known as the “100 percent Clean Energy Act of
2018,” which sets a 2045 goal of powering all retail electricity sold in California with renewable
and zero-carbon resources. The law also updates the state’s Renewables Portfolio Standard to
ensure that by 2030 at least 60 percent of California’s electricity is renewable.
Wyoming
In March 2020, the Wyoming governor signed House of Representatives Enrolled Act No. 79,
which requires the WPSC to adopt a low-carbon standard to specify a percentage of an electric
utility's electricity to be generated from coal-fueled generation utilizing carbon capture technology
by no later than 2030. The bill allows electric utilities to implement a surcharge not to exceed 2%
of customer bills to recover costs to comply with the standard. The WPSC is establishing the
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
73
standard and requirements to implement the law through a rulemaking process expected to be
completed before the end of 2021.
Transportation Electrification
The electric transportation market is in an emerging state,29 and plug-in electric vehicles (EV)
currently comprise a negligible share of PacifiCorp’s load. This rapidly evolving market represents
a potential driver of future load growth and those impacts managed proactively, provide an
opportunity to increase the efficiency of the electrical system and provide benefits for all
PacifiCorp customers. In addition, increased adoption of electric transportation has the ability to
improve air quality, reduce noise pollution, reduce greenhouse gas emissions, improve public health
and safety, and create financial benefits for drivers, which can be a particular benefit for low- and
moderate-income populations.
To help manage and understand the potential future load growth impacts of electric transportation
PacifiCorp is investing to support EV fast chargers along key corridors, develop workplace
charging programs, research new rate designs and implement time-of-use pricing pilots, create
partnerships for smart mobility programs and develop opportunities for customers in our rural
communities. Our investments include the Oregon Clean Fuels programs as well as pilot programs
approved and filed with the OPUC equaling over $12 million in TE investment. This includes
infrastructure, education and outreach and innovative e mobility projects. As of the end of 2020,
PacifiCorp had supported installation of over 2,100 EV ports throughout the territory
Electric vehicle load is reflected in the Company’s load forecast. PacifiCorp continues to actively
engage with local, regional, and national stakeholders and participate in state regulatory processes
that can inform future planning and load forecasting efforts for electric vehicles
Hydroelectric Relicensing
The issues involved in relicensing hydroelectric facilities are multifaceted. They involve numerous
federal and state environmental laws and regulations, and the participation of numerous
stakeholders including agencies, Native American tribes, non-governmental organizations, and
local communities and governments.
The value of relicensing hydroelectric facilities is continued availability of energy, capacity, and
ancillary services associated with hydroelectric generation. Hydroelectric projects can often
provide unique operational flexibility because they can be called upon to meet peak customer
demands almost instantaneously and back up intermittent renewable resources such as wind. In
addition to operational flexibility, hydroelectric generation does not have the emissions concerns
of thermal generation and can also often provide important ancillary services, such as spinning
reserve and voltage support, to enhance the reliability of the transmission system.
On September 27, 2019, the FERC issued a new license order for the Prospect No. 3 Hydroelectric
Project, a 7.2 MW project located in southern Oregon. The license period is 40 years. Conditions
29 As of June 2019, the market share of plug-in electric vehicles was two
percent: www.nada.org/WorkArea/DownloadAsset.aspx?id=21474858563
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
74
of the license are consistent with the Commission’s previous environmental analysis. Pursuant to
the new license, PacifiCorp will implement increased minimum flows downstream of the diversion
dam, replace the project’s wood-stave flowline and sag-pipe, upgrade and construct new wildlife
crossings over the waterway, and prepare and implement various monitoring and management
plans.
On March 19, 2021, the FERC issued a new license order for the Weber Hydroelectric Project, a
3.85 MW project located in north central Utah. The license period is 40 years. Conditions of the
license are consistent with the Commission’s previous environmental analysis and similar to
previous license conditions. Pursuant to the new license, PacifiCorp will construct a new fish ladder
at the diversion dam, complete recreation site improvements, annually provide four 4-hour
whitewater boater flow releases and prepare and implement various monitoring and management
plans.
The FERC hydroelectric relicensing process can be extremely political and often controversial.
The process itself requires that the project’s impacts on the surrounding environment and natural
resources, such as fish and wildlife, be scientifically evaluated, followed by development of
proposals and alternatives to mitigate those impacts. Stakeholder consultation is conducted
throughout the process. If resolution of issues cannot be reached in this process, litigation often
ensues, which can be costly and time-consuming. The usual alternative to relicensing is
decommissioning. Both choices, however, can involve significant costs.
FERC has sole jurisdiction under the Federal Power Act to issue new operating licenses for non-
federal hydroelectric projects on navigable waterways, federal lands, and under other criteria.
FERC must find that the project is in the broad public interest. This requires weighing, with “equal
consideration,” the impacts of the project on fish and wildlife, cultural resources, recreation, land
use, and aesthetics against the project’s energy production benefits. Because some of the
responsible state and federal agencies have the ability to place mandatory conditions in the license,
FERC is not always in a position to balance the energy and environmental equation. For example,
the National Oceanic and Atmospheric Administration Fisheries agency and the U.S. Fish and
Wildlife Service have the authority in the relicensing process to require installation of fish passage
facilities (fish ladders and screens) and to specify their design. This is often the largest single
capital investment that will be considered in relicensing and can significantly impact project
economics. Also, because a myriad of other state and federal laws come into play in relicensing,
most notably the Endangered Species Act and the Clean Water Act, agencies’ interests may
compete or conflict with each other, leading to potentially contrary or additive licensing
requirements. PacifiCorp has generally taken a proactive approach towards achieving the best
possible relicensing outcome for its customers by engaging in negotiations with stakeholders to
resolve complex relicensing issues. In some cases, settlement agreements are achieved which are
submitted to FERC for incorporation into a new license. FERC welcomes license applications that
reflect broad stakeholder involvement or that incorporate measures agreed upon through multi-
party settlement agreements. History demonstrates that with such support, FERC generally accepts
proposed new license terms and conditions reflected in settlement agreements.
Potential Impact
Relicensing hydroelectric facilities involves significant process costs. The FERC relicensing
process takes a minimum of five years and may take longer, depending on the characteristics of
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
75
the project, the number of stakeholders, and issues that arise during the process. As of December
31, 2020, PacifiCorp had incurred approximately $5 million in costs for license implementation
and ongoing hydroelectric relicensing, which are included in construction work- in-progress on
PacifiCorp's Consolidated Balance Sheet. As current or upcoming relicensing and settlement
efforts continue for the Cutler and other hydroelectric projects, additional process costs are being
or will be incurred that will need to be recovered from customers. Hydroelectric relicensing costs
have and will continue to have a significant impact on overall hydroelectric generation cost. Such
costs include capital investments and related operations and maintenance costs associated with fish
passage facilities, recreational facilities, wildlife protection, water quality, cultural and flood
management measures. Project operational and flow-related changes, such as increased in-stream
flow requirements to protect aquatic resources, can also directly result in lost generation. Much of
these relicensing and settlement costs relate to PacifiCorp’s three largest hydroelectric projects:
Lewis River, Klamath River, and North Umpqua.
Treatment in the IRP
The known or expected operational impacts related to FERC orders and settlement commitments
are incorporated in the projection of existing hydroelectric resources discussed in Volume I,
Chapter 7 (Resource Options).
PacifiCorp’s Approach to Hydroelectric Relicensing
PacifiCorp continues to manage the hydroelectric relicensing process by pursuing interest-based
resolutions or negotiated settlements as part of relicensing. PacifiCorp believes this proactive
approach, which involves meeting agency and others’ interests through creative solutions, is the
best way to achieve environmental improvement while balancing customer costs and risks.
PacifiCorp also has reached agreements with licensing stakeholders to decommission projects
where that has been the most cost-effective outcome for customers.
Utah Rate Design Information
Current rate designs in Utah have evolved over time based on orders and direction from the Public
Service Commission of Utah and settlement agreements between parties during general rate cases.
Most recently, current rates and rate design changes were adopted in Docket No. 13-035-184. The
goals for rate design are (generally) to reflect the cost to serve customers and to provide price
signals to encourage economically efficient usage. This is consistent with resource planning goals
that balance consideration of costs, risk, and long-run public policy goals. PacifiCorp currently has
a number of rate design elements that take into consideration these objectives, in particular, rate
designs that reflect cost differences for energy or demand during different time periods and that
support the goals of acquiring cost-effective energy efficiency.
Residential Rate Design
Residential rates in Utah are comprised of a customer charge and energy charges. The customer
charge is a monthly charge that provides limited recovery of customer-related costs incurred to
serve customers regardless of usage. All other remaining costs are recovered through volumetric-
based energy charges. Energy charges for residential customers are designed with an inclining-tier
rate structure so high usage during a billing month is charged a higher rate. This gives customers
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
76
a price signal to encourage reduced consumption. Additionally, energy charges are differentiated
by season with higher rates in the summer when the costs to serve are higher. Residential customers
also have an option for time-of-day rates. Time-of-day rates have a surcharge for usage during the
on-peak periods and a credit for usage during the off-peak periods. This rate structure provides an
additional price signal to encourage customers to use less energy during the daily on-peak periods
when energy costs are higher. As of Spring 2021, less than one percent of customers have opted
to participate in the time-of-day rate option.
Changes in residential rate design include a critical peak pricing program or an expansion of time-
of-use rates. These types of rate designs will be discussed in more detail in Volume I, Chapter 7
(Resource Options). As part of the STEP legislation enacted in SB 115, the company developed a
pilot time-of-use program to encourage off-peak charging of electric vehicles for residential
customers. The results of this pilot may inform future rate design offerings. Any changes in
standard residential rate design or institution of optional rate options to support energy efficiency
or time-differentiated usage should be balanced with the recovery of fixed costs to ensure price
signals are economically efficient and do not unduly shift costs to other customers.
With the growth in the number of customers adopting private distributed generation, rates have
begun to evolve to address the change in usage requirements and ensure appropriate cost recovery
from these customers. A deeper consideration of the implications of current rates and rate designs
is necessary to address growing issues with private generation and ensure the appropriate price
signals are set for the changing circumstances. As a result of a settlement in Docket No. 14-035-
114, new customer generators in Utah receive export credits that are valued at a different rate than
retail rates as part of a transition program.
Commercial and Industrial Rate Design
Commercial and industrial rates in Utah include customer charges, facilities charges, power
charges (for usage over 15 kW) and energy charges. As with residential rates, customer charges
and facilities charges are generally intended to recover costs that do not vary with energy usage.
Power charges are applied to a customer’s monthly demand on a kW basis and are intended to
recover the costs associated with demand or capacity needs. Energy charges are applied to the
customer’s metered usage on a kWh basis. All commercial and industrial rates employ seasonal
variations in power and/or energy charges with higher rates in the summer months to reflect the
higher costs to serve during the summer peak period. Additionally, for customers with load 1,000
kW or more, rates are further differentiated by on-peak and off-peak periods for both power and
energy charges. For commercial and industrial customers with load less than 1,000 kW, the
company offers two optional time-of-day rates—one that differentiates energy rates for on- and
off-peak usage, and one that differentiates power charges by on- and off-peak usage.
Irrigation Rate Design
Irrigation rates in Utah are comprised of an annual customer charge, a monthly customer charge,
a seasonal power charge, and energy charges. The annual and monthly customer charges provide
some recovery of customer-related costs incurred to serve customers regardless of usage. All other
remaining costs are recovered through a seasonal power charge and energy charges. The power
charge is for the irrigation season only and is designed to recover demand-related costs and to
encourage irrigation customers to control and reduce power consumption. Energy charges for
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
77
irrigation customers are designed with two options. One is a time-of-day program with higher rates
for on-peak consumption than for off-peak consumption. Irrigation customers also have an option
to participate in a third-party operated Irrigation Load Control Program. Customers are offered a
financial incentive to participate in the program and give the company the right to interrupt service
to the participating customers when energy costs are higher.
Energy Imbalance Market
PacifiCorp and the CAISO launched the EIM November 1, 2014. The EIM is a voluntary market
and the first western energy market outside of California. NV Energy began participating in
December 2015, Arizona Public Service and Puget Sound Energy began participating in October
2016, and Portland General Electric began participating in October 2017. Idaho Power and
Powerex began participating in April 2018, and the Balancing Authority of Northern California
(BANC)1 began participating in April 2019. Seattle City Light (SCL) and Salt River Project (SRP)
began participating in April 2020, and 2021 saw the addition of NorthWestern Energy, Los
Angeles Department of Water & Power, Public Service Company of New Mexico, and Turlock
Irrigation District. The EIM footprint now includes portions of Arizona, California, Idaho, Nevada,
Oregon, Utah, Washington, Wyoming, and extends to the border with Canada. PacifiCorp
continues to work with the CAISO, existing and prospective EIM entities, and stakeholders to
enhance market functionality and support market growth.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
78
Figure 3.6 – Energy Imbalance Market Expansion
The EIM has produced significant monetary benefits ($1.42 billion total footprint-wide benefits as
of August 2021), quantified in the following categories: (1) more efficient dispatch, both inter-
and intra-regional, by automating dispatch every 15 minutes and every five minutes within and
across the EIM footprint; (2) reduced renewable energy curtailment by allowing balancing
authority areas to export or reduce imports of renewable generation that would otherwise need to
be curtailed; and (3) reduced need for flexibility reserves in all EIM balancing authority areas, also
referred to as diversity benefits, which reduces cost by aggregating load, wind, and solar variability
and forecast errors of the EIM footprint.
A significant contributor to EIM benefits is transfers across balancing authority areas, providing
access to lower-cost supply, while factoring in the cost of compliance with greenhouse gas
emissions regulations when energy is transferred into the CAISO balancing authority area to serve
California load. The transfer volumes are therefore a good indicator of a portion of the benefits
attributed to the EIM. Transfers can take place in both the five and 15-minute market dispatch
intervals.
After development and expansion of the EIM in the west, a natural next question is – are there
continued opportunities to increase economic efficiency and renewable integration beyond the
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
79
scope of EIM but short of a fully regional independent system operator? PacifiCorp believes the
answer may be yes, but several items that are critical to its success will need creative solutions;
resource sufficiency, transmission utilization, voluntary nature and governance. The concept of
extending day-ahead market services is a current CAISO stakeholder initiative, which also aligns
with the CAISO’s day-ahead market enhancement stakeholder initiative. The Extended Day-
Ahead Market (EDAM) stakeholder initiative is expected to continue working through
transmission utilization, resource sufficiency, governance and congestion management in 2021.
Recent Resource Procurement Activities
PacifiCorp issued and will issue multiple requests for proposals (RFP) to secure resources or
transact on various energy and environmental attribute products. Table 3.5 summarizes recent RFP
activities.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
80
Table 3.5 – PacifiCorp’s Requests for Proposal Activity
RFP RFP Objective Status Issued Completed
2017 Renewable
Energy Credits RFP
Purchase renewable energy
credits for Oregon Schedule
272 participation
Closed
August 2017
September 2017
2017 Renewable
RFP
Purchase new or repowered
wind renewable energy Closed September 2017 November 2018
2017 Solar RFP Purchase solar renewable
energy Closed November 2017 March 2018
2017 Market
Resource RFP
Purchase firm power for
PacifiCorp’s western
balancing authority
Closed
November 2017
November 2017
2018 Oregon
Community Solar
RFP
Purchase solar energy or
Oregon Community Solar
Ongoing
July 2018
On hold pending
final program
rules
2018 Renewable
Energy Credits RFP
Purchase renewable energy
credits for Oregon Schedule
272 participation
Closed
August 2018
September 2018
2019R Utah RFP
Purchase new renewable
energy for specific customers
under Utah Schedule 32 or
34
Ongoing
March 2019
Fall 2019
Renewable energy
credits (Sale) Excess system RECs Ongoing Based on
specific need Ongoing
2019 Capacity and
Energy Supply RFP
Purchase capacity and energy
supply Ongoing June 4, 2019 Ongoing
Renewable energy
credits (Purchase) Oregon compliance needs Ongoing Based on
specific need Ongoing
Renewable energy
credits (Purchase)
Washington compliance
needs Ongoing Based on
specific need Ongoing
Renewable energy
credits (Purchase) California compliance needs Ongoing Based on
specific need Ongoing
Short-term Market
(Sales) System balancing Ongoing Based on
specific need Ongoing
2020 All-Source
RFP
Seeking resources consistent
with the 2019 IRP’s least cost
resource portfolio
Ongoing
July 2020
Ongoing
2021 DR RFP
Oregon compliance and
purchase of cost-effective
flexible capacity
On-
going January 2021
Ongoing
2020 All-Source RFP
PacifiCorp's 2020 All Source RFP ("2020AS RFP") was filed for approval with the Utah PSC and
the Oregon PUC in April 2020. In July 2020, the Utah PSC and the Oregon PUC approved the
2020AS RFP, and PacifiCorp issued the 2020AS RFP to market. The 2020AS RFP sought bids for
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
81
resources capable of coming online by the end of 2024 up to the level of resources identified in
PacifiCorp's 2019 IRP. Bids were submitted in August 2020. An initial shortlist was identified in
October 2020. The initial shortlist includes a total of 6,982 MWs of new generation and storage
capacity. Of the total, 5,652 MWs are new generation resources (represented by 3,173 MWs of
solar generation and 2,479 MWs of wind generation) and an additional 1,330 MWs of new battery
storage assets, which includes 1,130 MWs of solar collocated battery storage and 200 MWs of
stand-alone battery storage.
The final shortlist of winning bids was identified by June 2021 and is comprised of 1,792 MW of
wind generation, 95 MW of solar generation, 1,211 MW of solar generation collocated storage and
200 MW of stand-alone battery storage; 590 MW of wind generation is being contracted as a build
and transfer to PacifiCorp with the balance of the generation contracted through long-term power
purchase agreements.
PacifiCorp is finalizing both build and transfer and power purchase agreement updated drafts that
will be forwarded to all final shortlisted participants prior to September 1, 2021. Contract
negotiations are expected to proceed into early Q1 2022. All necessary final state regulatory
approvals and proceedings are expected to be complete by Q2 2022.
2021 DR RFP
PacifiCorp’s 2019 IRP identified the addition of 178 MW of DR system wide by 2029 as resource
additions of a least cost least risk long term resource plan. To acquire the DR resource needs
identified in the 2019 IRP, the company issued a DR RFP for cost effective DR resources.
Successful initial short list bids from this DR RFP joined final bids from the AS 2020 RFP for a
combined analysis in the 2021 IRP to determine the optimal acquisition of resources to meet
system needs. On February 8, 2021, PacifiCorp issued an RFP soliciting proposals from
implementation contractors for Demand Response (DR) resources. Although a variety of programs
were eligible for consideration, of most interest to PacifiCorp were programs located in Oregon
and/or Washington with the following focus:
1) Non-Residential Curtailment
2) Residential and/or Small Commercial Smart Thermostat or Water Heaters
3) Irrigation load control
The final shortlist of bids was identified in June 2021 and includes over 600 MW of capacity
during the planning horizon. PacifiCorp is finalizing the procurement and negotiation of demand
response resources following the completion of 2021 IRP. Contract negotiations and program
filings are expected to conclude in Q4 of 2021. All necessary state regulatory approvals and
proceedings are expected to be complete in the winter and spring of 2022.
PACIFICORP – 2021 IRP CHAPTER 3 – PLANNING ENVIRONMENT
82
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
83
CHAPTER 4 – TRANSMISSION
CHAPTER HIGHLIGHTS
• PacifiCorp’s planned transmission projects help facilitate a transitioning resource portfolio and
comply with reliability requirements, while providing sufficient flexibility necessary to ensure
existing and future resources can meet customer demand cost effectively and reliably.
• Given the long lead time needed to site, permit, and construct new transmission lines, these
projects need to be planned well in advance of resource additions.
• PacifiCorp’s transmission planning and benefits evaluation efforts adhere to regulatory and
compliance requirements and respond to commission and stakeholder requests for a robust
evaluation process and clear criteria for evaluating transmission additions.
• The 2021 IRP preferred portfolio includes the Energy Gateway South transmission line - a new
416-mile high-voltage 500-kilovolt transmission line and associated infrastructure running from
the new Aeolus substation near Medicine Bow, Wyoming, to the Clover substation near Mona,
Utah. The 2021 preferred portfolio also includes the Energy Gateway West Subsegment D.1
project - a new 59-mile high-voltage 230-kilovolt transmission line from the Shirley Basin
substation in southeastern Wyoming to the Windstar substation near Glenrock, Wyoming. Both
transmission lines will come online by the end of 2024.
• The 2021 IRP preferred portfolio also includes the Boardman to Hemingway line - an
approximately 290-mile high-voltage 500-kilovolt transmission line and associated
infrastructure running from the proposed Longhorn substation near Boardman, Oregon and the
Hemingway substation near Melba, Idaho, which will come online in 2026.
• Further, the 2021 IRP preferred portfolio includes near-term transmission upgrades in Utah and
Washington. Ongoing investment in transmission infrastructure in Idaho, Oregon, Utah,
Washington, and Wyoming will facilitate continued and long-term growth in new resources
needed to serve our customers. While construction of the balance of future Energy Gateway
segments (i.e., Gateway West segments D.3, and E is beyond the scope of acknowledgement
for this IRP, these segments are expected to deliver future benefits for our customers and for
the region. Thus, continued permitting of these segments is warranted to ensure that PacifiCorp
is well positioned to advance these projects at the appropriate time.
Introduction
PacifiCorp’s bulk transmission network is a high-value asset that is designed to reliably transport
electric energy from a broad array of generation resources (owned or contracted generation
including market purchases) to load centers. There are many benefits associated with a robust
transmission network, some of which are set forth below:
1. Reliable delivery of diverse energy supply to continuously changing customer demands
under a wide variety of system operating conditions.
2. Ability to always meet aggregate electrical demand and customers’ energy requirements,
taking into account scheduled outages and the ability to maintain reliability during
unscheduled outages.
3. Ability to meet changing regulatory requirements as states move towards a renewable
energy future.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
84
4. Economic dispatch of resources within PacifiCorp’s diverse system.
5. Economic transfer of electric power to and from other systems as facilitated by the
company’s participation in the market, which reduces net power costs and provides
opportunities to maintain resource adequacy at a reasonable cost.
6. Access to some of the nation’s best wind and solar resources, which provides opportunities
to develop geographically diverse low-cost renewable assets.
7. Protection against market disruptions where limited transmission can otherwise constrain
energy supply.
8. Ability to meet obligations and requirements of PacifiCorp’s Open Access Transmission
Tariff (OATT).
PacifiCorp’s transmission network is highly integrated with other transmission systems in the west
and provides the critical infrastructure needed to serve our customers cost effectively and reliably.
Consequently, PacifiCorp’s transmission network is a critical component of the IRP process.
PacifiCorp has a long history of providing reliable service in meeting the bulk transmission needs
of the region. This valued asset will become even more critical as the regional resource mix
transitions to accommodate increasing levels of variable generation from renewable resources that
will be used to serve the growing energy needs of our customers.
Regulatory Requirements
Open Access Transmission Tariff
Consistent with the requirements of its OATT, approved by the Federal Energy Regulatory
Commission (FERC), PacifiCorp plans and builds its transmission system based on two customer-
type agreements—network customer or point-to-point transmission service. For network
customers, PacifiCorp uses ten-year load-and-resource (L&R) forecasts supplied by the customer,
as well as network transmission service requests to facilitate development of transmission plans.
Each year, PacifiCorp solicits L&R data from each of its network customers to determine future
L&R requirements for all transmission network customers. The bulk of PacifiCorp’s network
customer needs comes from the company’s Energy Supply Management (ESM) function, which
supplies energy and capacity for PacifiCorp’s retail customers. Other network customers include
Utah Associated Municipal Power Systems, Utah Municipal Power Agency, Deseret Power
Electric Cooperative (including Moon Lake Electric Association), Bonneville Power
Administration (BPA), Basin Electric Power Cooperative, Black Hills Power, Tri-State Generation
& Transmission, the United States Department of the Interior Bureau of Reclamation, and the
Western Area Power Administration.
PacifiCorp uses its customers’ L&R forecasts and best available information, including
transmission service and generation interconnection requests, as factors to determine the need and
timing for investments in the transmission system. If customer L&R forecasts change significantly,
PacifiCorp may consider alternative deployment scenarios or schedules for transmission system
investments, as appropriate. In accordance with FERC guidelines, PacifiCorp is able to reserve
transmission network capacity based on these data. PacifiCorp’s experience, however, is that the
lengthy planning, permitting and construction timeline required to deliver significant transmission
investments, as well as the typical useful life of these facilities, is well beyond the 10-year
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
85
timeframe of L&R forecasts.1 A 20-year planning horizon and ability to reserve transmission
capacity to meet existing and forecasted need over that timeframe is more consistent with the time
required to plan for and build large-scale transmission projects, and PacifiCorp supports clear
regulatory acknowledgement of this reality and corresponding policy guidance.
For point-to-point transmission service, the OATT requires PacifiCorp to grant service on existing
transmission infrastructure using existing capacity or to build transmission system infrastructure
as required to provide the service. The required action is determined with each point-to-point
transmission service request through FERC-approved study processes that identify the
transmission need.
Reliability Standards
PacifiCorp is required to meet mandatory FERC, North American Electric Reliability Corporation
(NERC), and Western Electricity Coordinating Council (WECC) reliability standards and
planning requirements. The operation of PacifiCorp’s transmission system also responds to
requests issued by California Independent System Operator (CAISO) RC West as the NERC
Reliability Coordinator. The company conducts annual system assessments to confirm minimum
levels of system performance during a wide range of operating conditions, from serving loads with
all system elements in service to extreme conditions where portions of the system are out of
service. Factored into these assessments are load growth forecasts, operating history, seasonal
performance, resource additions or removals, new transmission asset additions, and the largest
transmission and generation contingencies. Based on these analyses, PacifiCorp identifies any
potential system deficiencies and determines the infrastructure improvements needed to reliably
meet customer loads. NERC planning standards define reliability of the interconnected bulk
electric system in terms of adequacy and security. Adequacy is the electric system’s ability to
always meet aggregate electrical demand for customers. Security is the electric system’s ability to
withstand sudden disturbances or unanticipated loss of system elements. Increasing transmission
capacity often requires redundant facilities to meet NERC reliability criteria.
This chapter provides:
• Justification supporting acknowledgement of PacifiCorp’s plan to construct the Gateway
South, Gateway West segment D.1 and Boardman-to-Hemingway transmission lines.
Support for PacifiCorp’s plan to continue permitting the balance of Gateway West;
• Key background information on the evolution of the Energy Gateway Transmission
Expansion Plan; and
• An overview of PacifiCorp’s investments in recent short-term system improvements that
have improved reliability, helped to maximize efficient use of the existing system, and
enabled the company to defer the need to invest in larger-scale transmission infrastructure.
Generation Interconnection Queue Reform
In 2019, PacifiCorp initiated a public stakeholder process to review possible generation
interconnection tariff reform transitioning from a serial queue process to a cluster study process.
1 For example, PacifiCorp’s application to begin the Environmental Impact Statement (EIS) process for the Gateway
West segment of its Energy Gateway Transmission Expansion Project was filed with the Bureau of Land Management
(BLM) in 2007. A partial Record of Decision (ROD) was received in late April 2013, and a supplemental ROD was
received in January 2017.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
86
In May of 2020 the Federal Energy Regulatory Commission (FERC) issued an order approving
the transition and in the same year PacifiCorp initiated the first cluster study process, the
“transitional cluster study”. The transitional study was initiated in October of 2020 and completed
in March of 2021, the first annual cluster study process was initiated in April of 2021 and is
planned to complete in November of 2021. Subsequent study processes will be initiated annually
beginning in April.
PacifiCorp’s serial queue interconnection process, based on the pro forma tariff generation
interconnection procedures, presented significant challenges in meeting the goals of FERC Order
No. 2003 due to a large number of Interconnection Requests in the company’s queue competing to
serve PacifiCorp load. There was additional concern at the state commission level that the serial
process inhibited wholesale competition. The main feature the interconnection cluster approach is
its prioritization of commercial readiness over queue position in the interconnection process—i.e.,
a change from a “first-come, first-served” to a “first-ready, first-served” approach. To do this,
generator developers are required to demonstrate sufficient progress toward commercial operation
before submitting a formal Interconnection Request and entering a Cluster. This process of
increasing the requirements for obtaining a queue position in this way increases the likelihood that
only projects that are likely to be commercially viable enter the interconnection process.
In the transition cluster study 56 requests totaling approximately 4260 megawatts were entered
into the process and evaluated, of those 24 projects moved beyond the initial cluster study phase.
These requests represented a mix of solar, hydro, solar and storage, battery storage, wind,
geothermal and nuclear resources. In the first annual cluster study, under process now, 59 requests
were received totaling approximately 12,037 megawatts with 52 currently remaining in the
process. These requests represent a mix of solar, solar and storage, battery storage, pumped
storage, wind, wind and storage and geothermal resources.
Aeolus to Bridger/Anticline
In 2018, PacifiCorp received the necessary state regulatory approvals, state and local permits, and
private rights-of-way to construct the Aeolus-to-Bridger/Anticline sub-segment D.2 of Gateway
West. Construction began in April 2019 and was completed in October 2020 and energized in
November 2020.
Aeolus-to-Mona (Gateway South)
The 2021 PacifiCorp IRP preferred portfolio includes the Aeolus-to-Mona (Clover substation)
transmission segment (Energy Gateway South or Segment F).
To facilitate the delivery of new renewable energy resources to PacifiCorp customers across the
West, the preferred portfolio includes significant transmission investment. Specifically, the 2021
IRP preferred portfolio includes the Energy Gateway South transmission line - a new 416-mile,
high-voltage 500-kilovolt transmission line and associated infrastructure running from the new
Aeolus substation near Medicine Bow, Wyoming, to the Clover substation near Mona, Utah. The
2021 preferred portfolio also includes the Energy Gateway West Subsegment D.1 project - a new
59 mile high-voltage 230-kilovolt transmission line from the Shirley Basin substation in
southeastern Wyoming to the Windstar substation near Glenrock, Wyoming. Both transmission
lines come online by the end of 2024.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
87
Timing of construction is driven by the phase-out schedule of federal production tax credits
(PTCs), particularly the 2024 in-service requirements for 60 percent PTC eligibility, and potential
risk associated with the termination of the BLM permit for non-use. In addition to supporting
renewable resource additions in PacifiCorp’s generation portfolio, qualifying them for PTCs, the
new transmission segment will increase transfer capability out of eastern Wyoming.
Gateway West – Continued Permitting
In addition to the Windstar-to-Populus line (Energy Gateway Segment D), the Gateway West
transmission project also includes the Populus-to-Hemingway transmission segment (Energy
Gateway Segment E). While PacifiCorp is not requesting acknowledgement of a plan to construct
these segments in this IRP, the company will continue to permit the projects.
Windstar to Populus (Segment D)
The Windstar-to-Populus transmission project consists of three key sub-segments:
• D1—A single-circuit 230-kV line
that will run approximately 59 miles
between the existing Windstar
substation in eastern Wyoming and the
Aeolus substation near Medicine Bow,
Wyoming, which includes a loop-in to
the existing Shirley Basin 230-kV
substation;
• D2—A single-circuit 500-kV line completed October 2020 and energized November 2020
and
• D3—A single-circuit 500-kV line running approximately 200 miles between the new
Anticline substation and the Populus substation in southeast Idaho.
Populus to Hemingway (Segment E)
The Populus-to-Hemingway transmission project consists
of two single-circuit 500-kV lines that run approximately
500 miles between the Populus substation in eastern Idaho
to the Hemingway substation in western Idaho.
The Gateway West project would enable PacifiCorp to
more efficiently dispatch system resources, improve
performance of the transmission performance of the
transmission system performance (i.e., reduce line losses), improve reliability, and enable access
to a diverse range of new resource alternatives over the long term.
Under the National Environmental Policy Act, the BLM has completed the EIS for the Gateway
West project. The BLM released its final EIS on April 26, 2013, followed by the ROD on
November 14, 2013, providing a right-of-way grant for all of Segment D and most of Segment E
of the project. The BLM chose to defer its decision on the western-most portion of Segment E of
the project located in Idaho in order to perform additional review of the Morley Nelson Snake
Figure 4.1 - Segment D
Figure 4.2 - Segment E
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
88
River Birds of Prey Conservation Area. Specifically, the sections of Gateway West that were
deferred for a later ROD include the sections of Segment E from Midpoint to Hemingway and
Cedar Hill to Hemingway. A ROD for these final sections of Segment E was issued on January
19, 2017 and a right-of-way grant was issued on August 8, 2018.
Plan to Continue Permitting – Gateway West
The Gateway West transmission projects continue to offer benefits under multiple, future resource
scenarios. To ensure the Company is well positioned to advance the projects, it is prudent for
PacifiCorp to continue to permit the balance of Gateway West transmission projects. The Records
of Decision and rights-of-way grants contain many conditions and stipulations that must be met
and accepted before a project can move to construction. PacifiCorp will continue the work
necessary to meet these requirements and will continue to meet regularly with the Bureau of Land
Management to review progress.
Request for Acknowledgement for Boardman-to-Hemingway
The 2021 IRP preferred portfolio also includes an approximately 290-mile high-voltage 500-
kilovolt transmission line known as Boardman-to-Hemingway to come online by 2026. Further,
the 2021 IRP preferred portfolio further includes near-term transmission upgrades in Utah and
Washington. Ongoing investment in transmission infrastructure in Idaho, Oregon, Utah,
Washington, and Wyoming will facilitate continued and long-term growth in new renewable
resources.
PacifiCorp continues to participate in the project under the Joint Funding Permitting Agreement
with Idaho Power and BPA. In accordance with this agreement, PacifiCorp is responsible for its
share of the costs associated with federal and state permitting activities and other pre-construction
activities agreed to in the updated agreement.
Idaho Power’s 2019 IRP identifies the Boardman-to-Hemingway transmission line (B2H) as a
preferred resource to meet its capacity needs, reflecting a need for the project in 2026 to avoid a
deficit in load-serving capability in peak-load periods. Given the status of ongoing permitting
activities and the construction period, Idaho Power expects the in-service date for the transmission
line to be in 2026 or beyond.
The BLM released its ROD for B2H on November 17, 2017. The ROD allows BLM to grant right-
of-way to Idaho Power for the construction, operation, and maintenance of the B2H Project on
BLM-administered land. The BLM right-of-way grant was executed on January 9, 2018.
For all lands crossed in Oregon, Idaho Power must receive a site certificate from the Energy
Facility Siting Council (EFSC) prior to constructing and operating the proposed transmission line.
The Oregon Department of Energy (ODOE) serve as staff members to EFSC facilitating the review
of the site certificate application process. ODOE and EFSC both review Idaho Power’s application
to ensure compliance with state energy facility siting standards. The project has been issued a
Proposed Order approving the project, with the next step the completion of the Contested Case
proceeding, which is expected to conclude in 2022.
The U.S. Forest Service (USFS) issued a separate ROD on November 9, 2018 for lands
administered by the USFS based on the analysis in the final EIS. The USFS ROD approves the
issuance of a special-use authorization for a portion of the project that crosses the Wallowa-
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
89
Whitman National Forest. The U.S. Department of the Navy issued a ROD on September 25, 2019
in support of construction of a portion of the B2H project on 7.1 miles of the Naval Weapons
Systems Training Facility in Boardman, Oregon.
Factors Supporting Acknowledgement
PacifiCorp’s existing transmission path between the two balancing areas (PACW and PACE)
consists of a single line (Midpoint Idaho to Summer Lake Oregon) fully used during key operating
periods, including winter peak periods in the Pacific Northwest and summer peak in the
Intermountain West. PacifiCorp has invested in the permitting of the B2H project because of the
strategic value of connecting the two regions. As a potential owner in the project, PacifiCorp would
be able to use its bidirectional capacity to increase reliability and to enable more efficient use of
existing and future resources for its customers. The following lists additional B2H benefits:
• Customers: PacifiCorp continues to invest to meet customers’ needs, making only critical
investments now to ensure future reliability, security, and safety. The B2H project will
bolster reliability, security, and safety for PacifiCorp customers as the regional supply mix
transitions.
• Renewables: The B2H project has been identified as a strategic project that can facilitate
the transfer of geographically diverse renewable resources, in addition to other resources,
across PacifiCorp’s two balancing authority areas. Transmission line infrastructure, like
B2H, is needed to maintain a robust electrical grid while integrating clean, renewable
energy resources across the Pacific Northwest and Mountain West states. The 2019 IRP
preferred portfolio includes accelerated coal retirements and investment in transmission
infrastructure that will facilitate adding over 6,400 megawatt (MW) of new renewable
resources by the end of 2023, with nearly 11,000 MW of new renewable resources over
the 20-year planning period through 2030. Coupled with renewable additions coal unit
retirements in the 2019 IRP preferred portfolio will reduce coal-fueled generation
capacity by over 1,000 MW by the end of 2023, nearly 1,500 MW by the end of 2025,
nearly 2,800 MW by 2030 and nearly 4,500 MW by 2038. To support the addition of the
new renewable resources typically located remotely from load centers and retirement of
coal resources requires continued investment in a robust transmission system required to
move resources across and between both PacifiCorp balancing areas.
• Regional Benefit: PacifiCorp, as a past member of the regional planning entity Northern
Tier Transmission Group (NTTG), supported the inclusion of B2H in the NTTG 2018-
2019 regional plan. PacifiCorp as a current member of the regional planning organization
NorthernGrid has supported the inclusion of B2H into the 2020-2021 regional plan. From
a regional perspective, the B2H project is a cost-effective investment that will provide
regional solutions to identified regional needs. The project resolves possible system issues
as identified in the NTTG 2018-2019 draft regional plan. This plan shows system issues
depicted by heat maps, refer to figure 33, for the regional transmission line without B2H
and with B2H, refer to figure 34 in the NTTG report. Figure 34 in the NTTG report shows
the removal of system issues graphically.
• Balancing Area Operating Efficiencies: PacifiCorp operates and controls two balancing
areas. After the addition of B2H and portions of Gateway West, more transmission capacity
will exist between PacifiCorp’s two balancing areas, providing the ability to increase
operating efficiencies. B2H will provide PacifiCorp 300 MW of additional west-to-east
capability and 600 MW of east-to-west capability to move resources between PacifiCorp’s
two balancing authority areas.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
90
• Regional Resource Adequacy: PacifiCorp is participating in the ongoing effort to evaluate
and develop a regional resource adequacy program with other utilities that are members of
the Northwest Power Pool. The B2H project is anticipated to provide incremental
transmission infrastructure that will broaden access to a more diverse resource base, which
will provide opportunities to reduce the cost of maintaining adequate resource supplies in
the region.
• Grid Reliability and Resiliency: The Midpoint-to-Summer Lake 500-kV transmission
line is the only line connecting PacifiCorp’s east and west control areas. The loss of this
line has the potential to reduce transfers by 1,090 MW. When B2H is built, the new
transmission line will provide redundancy by adding an additional 1,000 MW of capacity
between the Hemingway substation and the Pacific Northwest. This additional asset would
mitigate the impact when the existing line is lost.
• Oregon and Washington Renewable Portfolio Standards and Other State Legislation:
New legislation and rules for recently passed legislation are being developed to meet state-
specific policy objectives that are expected to drive the need for additional renewable
resources. As these laws are enacted and rules are developed, PacifiCorp will evaluate how
the B2H transmission line can help facilitate meeting state policy objectives by providing
incremental access to geographically diverse renewable resources and other flexible
capacity resources that will be needed to maintain reliability. PacifiCorp believes that
investment in transmission infrastructure projects, like B2H and other Energy Gateway
segments, are necessary to integrate and balance intermittent renewable resources cost
effectively and reliably.
• Energy Imbalance Market (EIM): PacifiCorp was a leader in implementing the western
EIM. The real-time market helps optimize the electric grid, which lowers costs, enhances
reliability, and more effectively integrates resources. PacifiCorp believes the B2H project
could help advance the objectives of the EIM and has the potential of benefitting PacifiCorp
customers and the broader region.
• Grid Reliability: The loss of the Hemingway–Summer Lake 500-kV transmission line,
the only 500-kV connection between the Pacific Northwest and Idaho Power, during peak
summer load is one of the most severe possible contingencies the Idaho Power transmission
system can experience. Once Hemingway–Summer Lake 500-kV disconnects, the transfer
capability of the Idaho to Northwest path is reduced by over 700 MW in the west-to-east
direction. After the addition of B2H, there will be two major 500-kV connections between
the Pacific Northwest and Idaho Power. The Hemingway–Summer Lake 500-kV outage
would become much less severe to Idaho Power’s transmission system. Additionally, loss
of the Hemingway–Summer Lake 500-kV line with heavy east-to-west power transfer out
of Idaho to the Pacific Northwest results in significant system impacts. In this disturbance,
an existing remedial action scheme (power system logic used to protect power system
equipment) will disconnect over 1,000 MW of generation at the Jim Bridger Power Plant
to reduce path transfers and protect bulk transmission lines and apparatus. Due to the
magnitude of the generation loss, recovery from this disturbance can be extremely difficult.
After the addition of B2H, this enormous amount of generation shedding will no longer be
required. With two 500-kV lines between Idaho and the Pacific Northwest, the loss of one
can be absorbed by the other. Keeping 1,000 MW of generation on the system for major
system outages is important for grid stability.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
91
Next Steps
Given the extensive list of benefits noted above, PacifiCorp is committed to participating in the
Boardman-to-Hemingway project in accordance with the terms of the Joint Funding Permitting
Agreement through Oregon’s permitting process and will continue to work with Idaho Power in
the development and negotiations of the definitive agreement for the construction and ownership
of the new line. PacifiCorp continues to evaluate the benefits to PacifiCorp’s customers prior to
commitment of entering into a project construction agreement. Additionally, PacifiCorp will
continue to review possible benefits of the project as it continues to participate in project
development activities, including moving forward with preliminary construction and construction
agreement negotiations.
Energy Gateway Transmission Expansion Plan
Introduction
Given the long–lead time required to successfully site, permit and construct major new
transmission lines, these projects need to be planned well in advance. The Energy Gateway
Transmission Expansion Plan is the result of several robust local and regional transmission
planning efforts that are ongoing and have been conducted multiple times over a period of several
years. The purpose of this section is to provide important background information on the
transmission planning efforts that led to PacifiCorp’s proposal of the Energy Gateway
Transmission Expansion Plan.
Background
Until PacifiCorp’s announcement of Energy Gateway in 2007, its transmission planning efforts
traditionally centered on new resource additions identified in the IRP. With timelines of seven to
ten years or more required to site, permit, and build transmission, this traditional planning approach
was proving to be problematic, leading to a perpetual state of transmission planning and new
transmission capacity not being available in time to be viable for meeting customer needs. The
existing transmission system has been at capacity for several years, and new capability is necessary
to enable new resource development.
The Energy Gateway Transmission Expansion Plan, formally announced in May 2007, has origins
in numerous local and regional transmission planning efforts discussed further below. Energy
Gateway was designed to ensure a reliable, adequate system capable of meeting current and future
customer needs. Importantly, given the changing resource picture, its design supports multiple
future resource scenarios by connecting resource-rich areas and major load centers across
PacifiCorp’s multi-state service area. In addition, the ability to use these resource-rich areas helps
position PacifiCorp to meet current state renewable portfolio requirements. Energy Gateway has
since been included in all relevant local, regional and interconnection-wide transmission studies.
Planning Initiatives
Energy Gateway is the result of robust local and regional transmission planning efforts. PacifiCorp
has participated in numerous transmission planning initiatives, both leading up to and since Energy
Gateway’s announcement. Stakeholder involvement has played an important role in each of these
initiatives, including participation from state and federal regulators, government agencies, private
and public energy providers, independent developers, consumer advocates, renewable energy
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
92
groups, policy think tanks, environmental groups, and elected officials. These studies have shown
a critical need to alleviate transmission congestion and move constrained energy resources to
regional load centers throughout the west, and include:
• Rocky Mountain Area Transmission Study
Recommended transmission expansions
overlap significantly with Energy Gateway
configuration, including:
o Bridger system expansion similar to
Gateway West.
o Southeast Idaho to southwest Utah
expansion akin to Gateway Central
and Sigurd to Red Butte.
o Improved east-west connectivity
similar to Energy Gateway Segment
H alternatives.
• Western Governors’ Association Transmission Task Force Report
Examined the transmission needed to
deliver the largely remote generation
resources contemplated by the Clean and
Diversified Energy Advisory Committee.
This effort built upon the transmission
previously modeled by the Seams Steering
Group-Western Interconnection and
included transmission necessary to support a
range of resource scenarios, including high
efficiency, high renewables and high coal
scenarios. Again, for PacifiCorp’s system,
the transmission expansion that supported
these scenarios closely resembled Energy Gateway’s configuration.
• Western Regional Transmission Expansion Partnership (WRTEP)
The WRTEP was a group of six utilities working with four western governors’ offices to
evaluate the proposed Frontier Transmission Line. The Frontier Line was proposed to
connect California and Nevada to Wyoming’s Powder River Basin through Utah. The
utilities involved were PacifiCorp, Nevada Power, Pacific Gas & Electric, San Diego Gas
& Electric, Southern California Edison, and Sierra Pacific Power.
• Northern Tier Transmission Group Transmission Planning Reports
“The analyses presented in this
Report suggest that well-
considered transmission
upgrades, capable of giving LSEs
greater access to lower cost
generation and enhancing fuel
diversity, are cost-effective for
consumers under a variety of
reasonable assumptions about
natural gas prices.”
“The Task Force observes that
transmission investments
typically continue to provide
value even as network
conditions change. For example,
transmission originally built to
the site of a now obsolete
power plant continues to be
used since a new power plant is
often constructed at the same
location.”
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
93
In the 2018-2019 NTTG Draft Regional
Transmission Plan, sub segments of Energy
Gateway (both Gateway West and
Gateway South) were listed as necessary to
provide acceptable system performance.
The study also established that the amount
of new Wyoming wind generation that is
added over time can impact the
transmission system reliability west of
Wyoming. Additionally, three interregional
projects were included in the study the Southwest Inter-tie Project (SWIP North), Cross
Tie and TransWest Express, which showed that all three projects relied on Energy
Gateway to attain their full transfer capability rating.
• WECC/Reliability Assessment Committee (RAC) Annual Reports and Western
Interconnection Transmission Path
Utilization Studies
These analyses measure the historical use of
transmission paths in the west to provide
insight into where congestion is occurring and
assess the cost of that congestion. The Energy
Gateway segments were included in the analyses
that support these studies, alleviating several points
of significant congestion on the system, including
Path 19 (Bridger West) and Path 20
(Path C).
Energy Gateway Configuration
To address constraints identified on PacifiCorp’s transmission system, as well as meeting system
reliability requirements discussed further below, the recommended bulk electric transmission
additions took on a consistent footprint, which is now known as Energy Gateway. This expansion
plan establishes a triangle of reliability that spans Utah, Idaho and Wyoming with paths extending
into Oregon and Washington. This plan contemplates geographically diverse resource locations
based on environmental constraints, economic generation resources, and federal and state energy
policies.
Since Energy Gateway’s initial announcement in 2007, this series of projects has continued to be
vetted through multiple public transmission planning forums at the local, regional and Western
Interconnection level. In accordance with the local planning requirements in PacifiCorp’s OATT,
Attachment K, PacifiCorp has conducted numerous public meetings on Energy Gateway and
transmission planning in general. Meeting notices and materials are posted publicly on
PacifiCorp’s Attachment K Open Access Same-time Information System (OASIS) site. PacifiCorp
is also a member of NorthernGrid regional planning organization and WECC’s Reliability
Assessment Committee and was a member of Northern Tier Transmission Group (NTTG) regional
planning organization.
“Path 19 [Bridger] is the most
heavily loaded WECC path in the
study…. Usage on this path is
currently of interest due to the
high number of requests for
transmission service to move
renewable power to the West
from the Wyoming area.”
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
94
These groups continually evaluate PacifiCorp’s transmission plan in their efforts to develop and
refine the optimal regional and interconnection-wide plans. Please refer to PacifiCorp’s OASIS
site for information and materials related to these public processes.2
Additionally, an extensive 18-month stakeholder process on Gateway West and Gateway South
was conducted. This stakeholder process was conducted in accordance with WECC Regional
Planning Project Review guidelines and FERC OATT planning principles, and was used to
establish need, assess benefits to the region, vet alternatives, and eliminate duplication of projects.
Meeting materials and related reports can be found on PacifiCorp’s Energy Gateway OASIS site.
Energy Gateway’s Continued Evolution
The Energy Gateway Transmission Expansion Plan is the product of years of ongoing local and
regional transmission planning efforts with significant customer and stakeholder involvement.
Since its announcement in May 2007, Energy Gateway’s scope and scale have continued to evolve
to meet the future needs of PacifiCorp customers and the requirements of mandatory transmission
planning standards and criteria. Additionally, PacifiCorp has improved its ability to meet near-
term customer needs through a limited number of smaller-scale investments that maximize
efficient use of the current system and help defer, to some degree, the need for larger capital
investments like Energy Gateway (see the following section titled “Efforts to Maximize Existing
System Capability”). The IRP process, as compared to transmission planning, can result in
frequent changes in the least-cost, least-risk resource plan driven by changes in the planning
environment (i.e., market conditions, cost and performance of new resource technologies, etc.).
Near-term fluctuations in the resource plan do not always support the longer-term development
needs of transmission infrastructure, or the ability to invest in transmission assets in time to meet
customer needs. Together, however, the IRP and transmission planning processes complement
each other by helping PacifiCorp optimize the timing of its transmission and resource investments
to deliver cost-effective and reliable energy to our customers.
While the core tenets for Energy Gateway’s design have not changed, the project configuration
and timing continue to be reviewed and modified to coincide with the latest mandatory
transmission system reliability standards and performance requirements, annual system reliability
assessments, input from several years of federal and state permitting processes, and changes in
generation resource planning and our customers’ forecasted demand for energy.
As originally announced in May 2007, Energy Gateway consisted of a combination of single- and
double-circuit 230-kV, 345-kV and 500-kV lines connecting Wyoming, Idaho, Utah, Oregon and
Nevada. In response to regulatory and industry input regarding potential regional benefits of
“upsizing” the project capacity (for example, maximized use of energy corridors, reduced
environmental impacts and improved economies of scale), PacifiCorp included in its original plan
the potential for doubling the project’s capacity to accommodate third-party and equity partnership
interests. During late 2007 and early 2008, PacifiCorp received in excess of 6,000 MW of requests
for incremental transmission service across the Energy Gateway footprint, which supported the
upsized configuration. PacifiCorp identified the costs required for this upsized system and offered
transmission service contracts to queue customers. These queue customers, however, were unable
to commit due to the upfront costs and lack of firm contracts with end-use customers to take
delivery of future generation and withdrew their requests. In parallel, PacifiCorp pursued several
potential partnerships with other transmission developers and entities with transmission proposals
2 http://www.oatioasis.com/ppw/index.html
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
95
in the Intermountain Region. Due to the significant upfront costs inherent in transmission
investments, firm partnership commitments also failed to materialize, leading PacifiCorp to pursue
the current configuration with the intent of only developing system capacity sufficient to meet the
long-term needs of its customers.
In 2010, PacifiCorp entered into memorandums of understanding to explore potential joint-
development opportunities with Idaho Power Company on its Boardman-to-Hemingway project
and with Portland General Electric Company (PGE) on its Cascade Crossing project. One of the
key purposes of Energy Gateway is to better integrate PacifiCorp’s east and west balancing
authority areas, and Gateway Segment H from western Idaho into southern Oregon was originally
proposed to satisfy this need. However, recognizing the potential mutual benefits and value for
customers of jointly developing transmission, PacifiCorp has pursued these potential partnership
opportunities as a potential lower-cost alternative.
In 2011, PacifiCorp announced the indefinite postponement of the Gateway South 500-kV segment
between the Mona substation in central Utah and Crystal substation in Nevada. This extension of
Gateway South, like the double-circuit configuration discussed above, was a component of the
upsized system to address regional needs if supported by queue customers or partnerships.
However, despite significant third-party interest in the Gateway South segment to Nevada, there
was a lack of financial commitment needed to support the upsized configuration.
In 2012, PacifiCorp determined that one new 230-kV line between the Windstar and Aeolus
substations and a rebuild of the existing 230-kV line were feasible, and that the second new
proposed 230-kV line and proposed 500-kV line planned between Windstar and Aeolus would be
eliminated. This decision resulted from PacifiCorp’s ongoing focus on meeting customer needs,
taking stakeholder feedback and land-use limitations into consideration, and finding the best
balance between cost and risk for customers. In January 2012, PacifiCorp signed the Boardman to
Hemingway Permitting Agreement with Idaho Power Company and BPA that provides for the
PacifiCorp’s participation through the permitting phase of the project. The Boardman-to-
Hemingway project was pursued as an alternative to PacifiCorp’s originally proposed transmission
segment from eastern Idaho into southern Oregon (Hemingway to Captain Jack). Idaho Power
leads the permitting efforts on the Boardman-to-Hemingway project, and PacifiCorp continues to
support these activities under the conditions of the Boardman to Hemingway Transmission Project
Joint Permit Funding Agreement. The proposed line provides additional connectivity between
PacifiCorp’s west and east balancing authority areas and supports the full projected line rating for
the Gateway projects at full build out. PacifiCorp plans to continue to support the project under
the Permit Funding Agreement and will assess next steps post-permitting based on customer need
and possible benefits.
In January 2013, PacifiCorp began discussions with PGE regarding changes to its Cascade
Crossing transmission project and potential opportunities for joint development or firm capacity
rights on PacifiCorp’s Oregon system. PacifiCorp further notes that it had a memorandum of
understanding with PGE for the development of Cascade Crossing that was terminated by its own
terms. PacifiCorp had continued to evaluate potential partnership opportunities with PGE once it
announced its intention to pursue Cascade Crossing with BPA. However, because PGE decided to
end discussions with BPA and instead pursue other options, PacifiCorp is not actively pursuing
this opportunity. PacifiCorp continues to look to partner with third parties on transmission
development as opportunities arise.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
96
In May 2013, PacifiCorp completed the Mona-to-Oquirrh project. In November 2013, the BLM
issued a partial ROD providing a right-of-way grant for all of Segment D and most of Segment E
of Energy Gateway. The agency chose to defer its decision on the western-most portion of Segment
E of the project located in Idaho in order to perform additional review of the Morley Nelson Snake
River Birds of Prey Conservation Area. Specifically, the sections of Gateway West that were
deferred for a later ROD include the sections of Segment E from Midpoint to Hemingway and
Cedar Hill to Hemingway.
In May 2015, the Sigurd-to-Red Butte project was completed and placed in service.
In December 2016, the BLM issued its ROD and right-of-way grant for the Gateway South project.
In January 2017, the BLM issued its ROD and right-of-way grant, previously deferred as part of
the November 2013 partial ROD, for the sections of Segment E from Midpoint to Hemingway and
Cedar Hill to Hemingway.
Finally, the timing of Energy Gateway segments is regularly assessed and adjusted. While
permitting delays have played a significant role in the adjusted timing of some segments (e.g.,
Gateway West, Gateway South, and Boardman to Hemingway), PacifiCorp has been proactive in
deferring in-service dates as needed due to permitting schedules, moderated load growth, changing
customer needs, and system reliability improvements.
PacifiCorp will continue to adjust the timing and configuration of its proposed transmission
investments based on its ongoing assessment of the system’s ability to meet customer needs, its
compliance with mandatory reliability standards, and the stipulations in its project permits.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
97
Figure 4.3 – Energy Gateway Transmission Expansion Plan
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
98
Table 4.1 – Energy Gateway Transmission Expansion Plan
Segment & Name Description
Approximate
Mileage Status and Scheduled In-Service
(A)
Wallula-McNary 230 kV, single circuit 30 mi • Status: completed
• Placed in-service: January 2019
(B)
Populus-Terminal 345 kV, double circuit 135 mi • Status: completed
• Placed in-service: November 2010
(C)
Mona-Oquirrh
500 kV single circuit
345 kV double circuit 100 mi • Status: completed
• Placed in-service: May 2013
Oquirrh-Terminal 345 kV double circuit 14 mi • Status: rights-of-way acquisition underway
• Scheduled in-service: 2026
(D1)
Windstar-Aeolus
New 230 kV single circuit
Re-built 230 kV single
circuit
59 mi • Status: permitting underway
• Scheduled in-service: 2024
(D2)
Aeolus-
Bridger/Anticline
500 kV single circuit 140 mi • Status: completed
• Placed in-service: November 2020
(D3)
Bridger/Anticline-
Populus
500 kV single circuit 200 mi • Status: permitting underway
• Scheduled in-service: 2027 earliest
(E)
Populus-Hemingway 500 kV single circuit 500 mi • Status: permitting underway
• Scheduled in service: 2030 earliest
(F)
Aeolus-Mona 500 kV single circuit 416 mi • Status: permitting underway
• Scheduled in-service: 2024
(G)
Sigurd-Red Butte 345 kV single circuit 170 mi • Status: completed
• Placed in-service: May 2015
(H)
Boardman-
Hemingway
500 kV single circuit 290 mi
• Status: pursuing joint-development and/or firm
capacity opportunities with project sponsors
• Scheduled in-service: 2026
Efforts to Maximize Existing System Capability
In addition to investing in the Energy Gateway transmission projects, PacifiCorp continues to
make other system improvements that have helped maximize efficient use of the existing
transmission system and defer the need for larger-scale, longer-term infrastructure investment.
Despite limited new transmission capacity being added to the system over the last 20 to 30 years,
PacifiCorp has maintained system reliability and maximized system efficiency through other
smaller-scale, incremental projects.
System-wide, PacifiCorp has instituted more than 155 grid operating procedures and 17 remedial
action schemes to maximize the existing system capability while managing system risk. In
addition, PacifiCorp has been an active participant in the Energy Imbalance Market since
November 2014. By August 2021, 15 participants have joined the EIM. By broadening the pool
of lower-cost resources that can be accessed to balance load system requirements, enhances
reliability and reduces costs across the entire EIM Area. In addition, the automated system is
able to identify and use available transmission capacity to transfer the dispatched resources,
enabling more efficient use of the available transmission system.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
99
Transmission System Improvements Placed In-Service Since the 2019 IRP
PacifiCorp East (PACE) Control Area
1. Salt Lake Valley Area
• Install a new circuit switcher in series with the bus-tie circuit breaker at 90th South
substation
o Project driver is to correct NERC Standard TPL-001-4 Category P2-4
deficiency identified in PacifiCorp’s 2017 NERC TPL Assessment for a bus tie
breaker internal fault event that results in the loss of the entire 90th South 138-
kV substation.
o Benefits include mitigating the risk of thermal overloads and voltage issues and
eliminating the potential loss of load at the entire 90th South 138-kV South
substation for a bus tie failure event, and resolution of the NERC TPL-001-4
Category P2-4 deficiency.
2. Utah Valley Area
• Upgrade the 345-138 kV transformer at Spanish Fork substation
o Project driver is to correct NERC Standard TPL-001-4 Category P1 and P3
deficiencies identified in PacifiCorp’s 2017 NERC TPL Assessment resulting
from an outage of Spanish Fork 345-138 kV transformer #4 (N-1) and multiple
double contingency outages (N-1-1) that result in thermal overloads on
numerous substation transformers and transmission lines.
o Benefits include mitigating the risk of thermal overloads and low voltage issues,
additional capacity to address projected load growth, improved transmission
reliability and resolution of the NERC TPL-001-4 Category P1 and P3
deficiencies.
3. Goshen Idaho Area
• Install a new 161-kV line from Goshen to Sugarmill substations
o Project driver is to address the single contingency (N-1) and multiple
contingency (N-1-1) issues present in the Sugarmill-Rigby area and the large
amount of load shedding risk identified in the 2016 Goshen Area Planning
Study that proposed adding a new 161-kV line from Goshen to Sugarmill and
then from Sugarmill to Rigby substation to allow a looped configuration during
heavy summer load conditions.
o Benefits include mitigating the risk of thermal overloads and voltage issues and
eliminating the loss of up to 150 MW of load for N-1 outages and up to 300
MW for N-1-1 outages.
4. East Utah Area
• Construct the new Naples 138-12.5 kV substation
o Project driver is to correct NERC Standard TPL-001-4 Category P6 deficiencies
identified in PacifiCorp’s 2016 NERC TPL Assessment resulting in multiple
double contingencies causing low 138-kV system voltages in the Vernal area.
o Benefits include mitigating the risk of low voltage issues and resolution of the
NERC Standard TPL-001-4 Category P6 deficiencies.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
100
PacifiCorp West (PACW) Control Area
1. Yakima Washington Area
• Construct a new 230-kV transmission line from BPA’s Vantage substation to
PacifiCorp’s Pomona Heights substation
o Project driver is to correct the NERC Standard TPL-002 deficiency identified
in PacifiCorp’s 2011 TPL Assessment for the loss of a single 230-kV line.
o Benefits include mitigating the risk of thermal overloads and low voltage issues,
adding additional capacity to address projected load growth, improving
transmission reliability and resolution of the NERC TPL-002 deficiencies.
2. Yreka California Area
• Install an additional 115-69 kV transformer at Yreka substation located
o Project driver is to correct low voltage conditions under normal operating
conditions during heavy summer loading periods due to inadequate voltage
regulation on the 69-kV system served from Yreka substation, as identified in
the 2013 Yreka-Mt Shasta Area Study.
o Benefits include the ability to provide 69-kV voltage regulation by the new 115-
69 kV transformers load tap changer, allows the use of load drop compensation
feature to further improve the transmission voltage profile over the long term,
and making the exiting non-LTC transformer available as an installed spare for
immediate service restoration when needed.
3. Walla Walla Washington Area
• Replace the existing 115-69 kV, 20 MVA transformer with a 115-69 kV, 50 MVA
transformer at Dry Gulch substation
o Project driver is to correct NERC Standard TPL-001-4 Category P2 deficiency
identified in PacifiCorp’s 2015 NERC TPL Assessment for a 115-kV bus fault
at Dry Gulch substation.
o Benefits include having 69-kV capacity and voltage regulation capability to
operate in a normal open configuration to eliminate thermal overloads and low
voltage conditions, eliminating the 69-kV loop in parallel with the 230-kV and
500-kV main grid system that impacted the 69-kV system for outages on the
main grid system, removing the Tucannon 69-kV line from the WECC Path 6
definition, and resolving the NERC TPL-001-4 P2 deficiency.
Planned Transmission System Improvements
PacifiCorp East (PACE) Control Area
1. Central Wyoming Area
• Upgrade the 345-230 #2 transformer at Jim Bridger substation
o Project driver is to correct NERC Standard TPL-001-4 Category P1 and P3
deficiencies identified in PacifiCorp’s 2017 NERC TPL Assessment resulting
for a 345-kV or 230-kV bus fault (P1) and for the loss of a generator and both
Jim Bridger 345-230 kV transformers #1 and #3 (P3) that will result in thermal
overload of existing Jim Bridger 345-230 kV #2 transformer.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
101
o Benefits include mitigating the risk of thermal overloads and resolution of the
NERC TPL-001-4 Category P1 and P3 deficiencies.
2. Goshen Idaho Area
• Install a third 345-161 kV transformer at Goshen substation
o Project driver is to correct NERC Standard TPL-001-4 Category P1 (N-1)
deficiency identified in PacifiCorp’s 2016 Goshen Area Study resulting in
thermal overload of the remaining 345-161 kV transformer at Goshen
substation.
o Benefits include mitigating the risk of thermal overloads and resolution of the
NERC Standard TPL-001-4 Category P1 deficiency.
• Install a new 161-kV line from Sugarmill to Rigby substations located in Idaho
o Project driver is to address the single contingency (N-1) and multiple
contingency (N-1-1) issues present in the Sugarmill-Rigby area and the large
amount of load shedding risk identified in the 2016 Goshen Area Planning
Study that proposed adding a new 161-kV line from Goshen to Sugarmill
(completed) and then from Sugarmill to Rigby substation (still to complete) to
allow a looped configuration during heavy summer load conditions.
o Benefits include mitigating the risk of thermal overloads and voltage issues and
eliminating the loss of up to 150 MW of load for N-1 outages and up to 300
MW for N-1-1 outages.
3. Utah & Idaho – Upgrade Program – Backup Bus Differential Relays
• Install backup bus differential relays at various substations located in Utah and Idaho
o Project driver is to correct the NERC Standard TPL-001-4 Category P5-5
deficiencies identified in PacifiCorp’s 2015 NERC TPL Assessments resulting
in multiple contingencies for faults plus bus differential relays failure to operate
that cause delayed fault clearing due to the failure of a non-redundant relay
installation.
o Benefits include mitigating the risk of delayed clearing of all transmission line
connected to specific buses that would lead to thermal overloads and voltage
issues, ensuring that critical differential bus protection has the required relay
redundancy, improving reliability to the impacted substations and their
connected transmission lines, and resolution of the NERC TPL-001-4 Category
P5-5 deficiencies.
4. Utah, Idaho & Wyoming - Upgrade Program – Replace Over-dutied Circuit Breakers
• Replace breakers identified as over-dutied with higher-capability breakers in various
substations located in Idaho, Utah, and Wyoming
o Project driver is to correct NERC Standard TPL-001-4 Requirement R2.3
deficiencies identified in PacifiCorp’s 2015-2018 NERC TPL Assessment
resulting in the identification of 13 over-dutied breakers.
o Benefits include eliminating the risk of over-dutied breakers failing under fault
interruption conditions that pose safety and reliability risks, and the resolution
of the NERC TPL-001-4 Requirement R2.3 deficiencies.
5. Goshen Idaho Area
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
102
• Rebuild and convert an existing 69-kV line to 161-kV to establish a new 161-kV source
at Rexburg substation in Idaho
o Project driver is to improve 69-kV capacity and voltage regulation served from
Rigby substation by converting an existing 69-kV line to 161 kV to create a
161-kV source at Rexburg substation through a new 161-69 kV transformer
installation. The project also will include a new six breaker 69-kV ring bus at
Rexburg substation that includes terminating two existing 69-kV lines and one
new 69-kV line.
o Benefits include establishing a new 161-kV source in the area, providing
additional 69-kV capacity, improving 69-kV voltage regulation and reliability
to customers served from the 69-kV system.
6. Park City Utah Area
• Install a 9-mile, 138-kV transmission line between Midway and Jordanelle substations
in Utah
o Project drivers are projected load growth and reliability improvements which
required of extension of the 138-kV line from Jordanelle-to-Midway substation.
o Benefits are the established new 138-kV loop, additional capacity to address
projected load growth and improved transmission reliability.
7. Salt Lake Valley Utah Area
• Install two capacitor banks at Magna Substation and rebuild the Tooele – Pine Canyon
138 kV transmission line
o Project driver is to correct N-1 contingency overload and low voltage issues at
Magna substation and on the Tooele – Pine Canyon 138 kV line from consistent
load growth and new block loads.
o Benefits include mitigating the risk of thermal overloads and low voltage issues,
adding additional capacity to address projected load growth and improve
transmission reliability
PacifiCorp West (PACW) Control Area
1. Albany/Corvallis Oregon Area
• Replace conductor on the 115-kV line between Hazelwood substation and BPA’s
Albany substation and construct a new 115-kV ring bus at Hazelwood substation.
o Project driver is to correct NERC Standard TPL-001-4 Category P6 deficiencies
for an outage on the transformers at Fry substation and reduce load loss
exposure from various other N-1-1 contingencies.
o Benefits include mitigating the risk of thermal overloads and voltage issues,
improving transmission reliability, reducing the complexity of operating
procedures for remaining N-1-1 contingencies and resolution of a number of
NERC TPL-001-4 Category P6 deficiencies.
2. Medford Oregon Area
• Construct one new 500-230 kV substation called Sams Valley
o Project driver is to correct NERC Standard TPL-002-4 deficiencies for the loss
of a single 230-kV line and for N-1-1 and N-2 outages to 230-kV lines that were
initially identified in PacifiCorp’s 2010 NERC TPL Assessment and supported
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
103
through subsequent NERC TPL Assessments, and to provide a second 500-kV
source to address load growth in the Southern Oregon region.
o Benefits include adding a second source of 500-kV capacity, adding a new 230-
kV line, improving reliability of the 230-kV network, mitigates the risk of
thermal overloads and low voltage, mitigates the risk of shedding load in
preparation of the second contingency for N-1-1 outages, and resolves the
NERC TPL-001-4 deficiencies.
• Expand the RAS at Meridian substation
o Project driver is to expand the existing RAS to cover three additional N-1-1
contingencies on the southern Oregon 500-kV system and trip additional load
as identified in the 2015 Meridian Area Load Tripping Assessment and the 2017
NERC TPL Assessment.
o Benefit of expanding the RAS will be to avoid relying on the Southern Oregon
Under-Voltage Load Shedding scheme as the primary mitigation for double
contingencies on the 500-kV system.
3. Yakima Washington Area
• Construct a new 115-kV transmission line from Outlook substation to Punkin Center
substation
o Project driver is to correct NERC Standard TPL-001-4 Category P1 deficiencies
identified in the 2016 NERC TPL Assessment for single contingency (N-1)
outages on the 230-kV system serving the Yakima Upper Valley.
o Benefits include mitigating the risk of thermal overloads, resolving an existing
capacity limitation on the 115-kV line, improving transfer capability between
the Upper Valley and the Lower Valley system, and resolution of the NERC
TPL-001-4 Category P1 deficiency.
4. Oregon – Upgrade Program – Replace Over-dutied Circuit Breakers
• Replace breakers identified as over-dutied with higher-capability breakers at Lone Pine
Substation
o Project driver is to correct NERC Standard TPL-001-4 Requirement R2.3
deficiencies identified in PacifiCorp’s 2015-2018 NERC TPL Assessment
resulting in the identification of three over-dutied 115-kV breakers.
o Benefits include eliminating the risk of over-dutied 115-kV breakers failing
under fault interruption conditions that pose safety and reliability risks, and the
resolution of the NERC TPL-001-4 Requirement R2.3 deficiencies.
These investments help maximize the existing system’s capability, improve PacifiCorp’s ability
to serve growing customer loads, improve reliability, increase transfer capacity across WECC
Paths, reduce the risk of voltage collapse and maintain compliance with North American Electric
Reliability Corporation and Western Electricity Coordinating Council reliability standards.
PACIFICORP – 2021 IRP CHAPTER 4 – TRANSMISSION
104
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
105
CHAPTER 5 – RELIABILITY AND RESILIENCY
CHAPTER HIGHLIGHTS
• Regional resource adequacy assessments highlight that there are resource adequacy risks
through the mid-2020s. The addition of variable energy resources replacing traditional
“baseload” resources may act to tighten market supply.
• PacifiCorp’s wildfire mitigation plans, which outline a risk-based, balanced and integrated
approach, contain six critical focus areas of planning and execution for a reliable and resilient
energy future: (1) Risk analysis and drivers, (2) Situational awareness, (3) Inspection and
correction, (4) Vegetation management, (5) System hardening, and (6) Operational practices.
• The 2021 IRP preferred portfolio includes the Energy Gateway South (GWS), Energy Gateway
West Subsegment D.1 (D.1), and Boardman-to-Hemingway (B2H) transmission lines. The
preferred portfolio also includes other transmission upgrades that support the transition to
renewable energy by providing access to low-cost, location-specific renewable resources, and
additional transfer capability, which enables greater use of other low-cost resource options and
relieves stress on current assets.
Introduction
Serving reliably (i.e., keeping the lights on for customers), as well as planning for a resilient system
(i.e., operating through and recovering from a major disruption) is a primary focus for PacifiCorp.
With the increasing retirement of thermal baseload resources, the incorporation of increasing
numbers of intermittent renewable resources, and the impacts of climate change, planning for a
reliable and resilient energy future is more crucial, and more complex, than ever. PacifiCorp
continues to build on a strong track record of serving its customers safely, reliably, and affordably.
The focus on reliability and resiliency spans across several areas of the company: PacifiCorp’s
resource planning and energy supply teams work closely with regional peers and ensure that there
is sufficient supply to serve customers, transmission and distribution teams work to mitigate the
destructive impact of wildfire risk throughout the west and ensure that PacifiCorp is able to deliver
power safely to customers now and in the future.
Supply-Based Reliability
Regional Resource Adequacy
As part of its 2021 IRP, PacifiCorp has conducted a review and evaluation of western resource
adequacy studies and information, including evaluating the Western Electricity Coordinating
Council (WECC) Power Supply Assessment (PSA) to glean trends and conclusions from the
supporting analysis.
In 2020, WECC published and adopted the WECC Reliability Risk Priorities (WRRP), which
outlined four priorities that were deemed to be the most significant to reliability in the western
interconnection. Resource adequacy was identified as one of the four priorities, and in December
2020 WECC published the Western Assessment of Resource Adequacy (WARA), which will
become an annual report in the future. PacifiCorp has reviewed the WARA, which serves as an
interconnection-wide assessment of resource adequacy and uses that assessment as the basis of the
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
106
following discussion. PacifiCorp also reviewed the 2020 North American Electric Reliability
Council (NERC) Long-Term Reliability Assessment and the status of resource adequacy
assessments prepared for the Pacific Northwest by the Pacific Northwest Resource Adequacy
Forum.
WECC Western Assessment of Resource Adequacy Report
The WECC Western Assessment of Resource Adequacy was published on December 18, 2020
and was developed based on data collected from balancing authorities describing their own
demand and supply projections over the next 10 years. The analysis is probabilistic and represents
an hourly assessment of resource adequacy over the study period. The region-wide projections
included in the study were categorized into two scenarios: one in which the region is required to
meet its own demand without assumed reliance on imports, and a second scenario in which the
region can assume that imports will help meet the demand needs of the future. Each scenario was
further sub-divided into three variations:
• Variation 1: Existing Resources (EX) – Includes resources that are in-service and can be
expected to run in future forecasts.
• Variation 2: Tier 1 Resources (T1) – Existing resources including those under construction
and expected to be in-service in the forecasted year.
• Variation 3: Tier 1 and Tier 2 Resources (T12) – Existing and Tier 1 resources including
those in licensing, siting, etc. but not yet in construction.
To inform the study, WECC has developed peaking assumptions and ramp need estimates on
both an interconnection-wide basis, as well as for each planning subregion within the WECC. A
summary of the planning regions and peak assumptions is shown in Table 5.1.
Table 5.1 – Planning Subregions and Peaking Assumptions underlying analysis
Designation Subregion Peaking
Assumption
Ramp1 Peak Load
NWPP-NW2 Northwest Power Pool - Northwest January 51% 39,300MW
NWPP-NE3 Northwest Power Pool – Northeast February 30% 14,800MW
NWPP-C4 Northwest Power Pool – Central July 104% 36,400MW
CAMX5 California and Mexico August 81% 51,300MW
DSW6 Desert Southwest July 100% 25,700MW
PacifiCorp serves load primarily in the NWPP-NW, NWPP-NE, and NWPP-C planning
subregions.
1 Represents needed resource ramp from lowest to highest demand hour of the peak demand day
2 NWPP-NW covers Washington, Oregon, British Columbia, and portions of Montana and Idaho
3 NWPP-NE covers portions of Idaho, Montana, Wyoming, South Dakota, Nebraska, and Alberta
4 NWPP-C covers Nevada, Utah, Colorado, and portions of California, Idaho, and Wyoming
5 CAMX covers the majority of California and Baja California
6 DSW covers Arizona, New Mexico, and portions of Texas and California
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
107
NWPP-NW
• Expected availability of peak-hour resources in 2021: 44,000 MW to meet an expected
peak of 39,300 MW. However, in low-availability scenarios (5% probability), the region
could have only 29,200 MW of resources available to meet peak.
• One Day in Ten Years (ODITY) planning threshold: WECC determines that a planning
reserve margin of 15%is likely sufficient to maintain the median ODITY resource
adequacy threshold. However, as more variable resources continue to be added to the
grid, a larger planning reserve margin may be needed to compensate. WECC estimates
that in the spring, when variability in energy supply and demand is highest, a planning
reserve margin of 40%+ may be appropriate.
• Scenario findings for NWPP-NW generally identify that the subregion may need imports
to ensure system reliability as early as 2021, and the scenario outputs identify hours at
risk of not being able to maintain ODITY threshold of resource adequacy:
Stand-alone:
• Existing Resources: 208 hours
• T1: 195 hours
• T2: 194 hours
Imports:
• Existing Resources: 0 hours
• T1: 0 hours
• T2: 0 hours
NWPP-NE
• Expected availability of peak-hour resources in 2021: 19,600 MW to meet an expected
peak of 14,800 MW. However, in low-availability scenarios (5 percent probability), the
region could have 16,700 MW available, which is still sufficient to meet peak demand.
• ODITY planning threshold: WECC determines that a planning reserve margin of 15% is
likely sufficient to maintain the median ODITY resource adequacy threshold. WECC’s
highest reserve margin is estimated to be approximately 20% to account for potential
limited availability in baseload resources.
• Scenario findings for NWPP-NE identifies that the subregion needs imports to maintain
resource adequacy thresholds. From 2021-2024, WECC finds that in each stand-alone
scenario there are over 4,000 hours per year in which 100+ MW of demand is at risk of
being unserved. The number of hours increase as there is less baseload availability.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
108
Stand-alone
• Existing Resources: 4,200 hours
• T1: 4,200 hours
• T2: 4,200 hours
Imports
• Existing Resources: 0 hours
• T1: 0 hours
• T2: 0 hours
NWPP-C
• Expected availability of peak-hour resources in 2021: 19,600 MW to meet an expected
peak of 14,800 MW. However, in low-availability scenarios (5 percent probability), the
region could have 16,700 MW available, which is still sufficient to meet peak demand.
• ODITY planning threshold: WECC determines that a planning reserve margin of 15% is
likely sufficient to maintain the median ODITY resource adequacy threshold. WECC’s
highest reserve margin is estimated to be approximately 20% to account for potential
limited availability in baseload resources.
• Scenario findings for NWPP-NE identifies that the subregion needs imports to maintain
resource adequacy thresholds. From 2021-2024, WECC finds that in each stand-alone
scenario there are over 4,000 hours per year in which 100+ MW of demand is at risk of
being unserved. The number of hours increase as there is less baseload availability.
Stand-alone
• Existing Resources: 4,200 hours
• T1: 4,200 hours
• T2: 4,200 hours
Imports
• Existing Resources: 0 hours
• T1: 0 hours
• T2: 0 hours
Resource Assumptions
The WARA analysis includes all currently operating resource, with planned retirements included
in the calculation.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
109
The WECC Western Assessment of Resource Adequacy makes the following three
recommendations. Details on how PacifiCorp has incorporated or is considering each
recommendation are also provided.
Recommendation 1: Planning entities and their regulatory authorities should consider
moving away from a fixed planning reserve margin to a probabilistically determined
margin. As variability grows, a dynamic planning reserve margin will better ensure
resource adequacy for all hours.
- PacifiCorp’s 2019 IRP and its 2021 IRP both evaluate the performance of the
selected portfolio of resources in all hours to ensure resource adequacy beyond
the coincident peak.
- PacifiCorp’s 2021 IRP calculates the planning reserve margin for every hour and
identifies the lowest hourly margin by season and year, allowing for greater focus
on the periods and types of conditions that lead to the greatest risk. As portfolios
evolve over time, this automatically identifies the changing periods of risk.
- PacifiCorp’s stochastic reliability modeling has identified that reliability risks
exist in both the summer and the winter under a range of conditions.
Recommendation 2: Planning entities should consider not only how much additional
capacity is needed to mitigate variability, but also the expected availability of the
resource. Understanding the differences in resource type availability is crucial to
performing resource adequacy studies.
- PacifiCorp recognizes that the conditions with the greatest risk can be addressed
with targeted solutions, for instance solar combined with storage is very helpful
for meeting summer requirements.
- PacifiCorp also recognizes that widespread adoption of a targeted solution will
cause risks to evolve, and solutions will need evolve or change to target other
conditions. To help retain flexibility for evolving needs, PacifiCorp increased the
level of storage in its hybrid solar and storage resources to 100% of the solar
nameplate with four-hour duration. But even this results in diminishing returns
for winter needs.
- While four-hour storage provides significant flexibility, for instance to fill in gaps
in typical renewable resource output, uncertainty remains about expected
renewable resource availability under extreme conditions, which are relatively
uncommon. To address this issue, additional analysis of renewable resource
variability and correlation with load will be needed in future IRPs.
Recommendation 3: Planning entities should coordinate their resource planning efforts
on an interconnection-wide basis each year to help ensure they are not all relying on the
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
110
same imports to maintain resource adequacy. This coordination will help subregions
make assumptions about import availability in the context of the entire interconnection.
- PacifiCorp evaluates its planning assumption around availability of markets and
interconnection-wide imports, and has adjusted its forecasted maximum liquidity
at the Mid-Columbia, California-Oregon Border, Nevada-Oregon Border, and
Mona trading hubs as a result. Chapter 7 (Resource Options), as well as the
section in this chapter addressing market availability, include a discussion of
PacifiCorp’s assumed maximum seasonal values for front-office transactions.
NERC Long-Term Resource Adequacy (LTRA)
Resources
As part of the regional reliability assessment to support the 2021 IRP, PacifiCorp reviewed and
incorporated learnings from the NERC LTRA, published in December 2020. The NERC LTRA
organizes resources into two broad categories in its 10-year WECC region reliability assessment:
Anticipated Resources
• Existing generating capacity able to serve peak hour load with firm transmission
• Capacity that is either under construction or has received approved planning requirements
• Firm net capacity transfers with firm contracts
• Less confirmed retirements
Prospective Resources
• Existing capacity that may be available to serve peak hour load, but lacks certainty
associated with firm transmission, peak availability, etc.
• Capacity additions that have been requested but not received approval
• Non-firm net capacity transfers and transfers without firm contracts, but assessed to have
a high probability of future implementation
• Less unconfirmed retirements
Planning Reserve Margin
The LTRA defines “planning reserve margin” as the difference between resources less demand,
divided by demand, as a percentile.
Resources in this calculation are reduced by expected operating limits due to fuel availability,
transmission and environmental limitations. Comparing the anticipated resource-based reserve
margin to the reference planning margin yields one of three risk determinations:
• Adequate: Anticipated reserve margin exceeds the reference margin level
• Marginal: Anticipated reserve margin exceeds the reference margin level, but there are
low expectations in meeting all forecast parameters; alternately, Anticipated reserve
margin is below the reference margin level, but sufficient Tier 2 resources are projected
to cover the shortfall
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
111
• Inadequate: Anticipated reserve margin is significantly less than reference margin level
and load interruption is likely
WECC Subregions
Table 5.2 presents the WECC subregions used for the NERC LTRA. In the data that follows, the
two subregions in Canada are not considered.
Table 5.2 – WECC Subregion Descriptions
Designation Subregion Country Peaking Assumption
CAMX California to Mexico United States Summer
NWPP Northwest Power Pool United States Summer
RMRG Rocky Mountain Reserve Group United States Summer
SRSG Southwest Reserve Sharing Group United States Summer
AB Alberta Canada Winter
BC British Columbia Canada Winter
LTRA WECC Assessment
Table 5.3 through Table 5.5 represent the three types of reserve margins relevant to the WECC
planning reserve margin calculation. In each table, the figures do not include WECC subregions
outside of the United States.
Table 5.3 – NERC LTRA Anticipated Reserve Margin
Anticipated Reserve Margin
U.S. WECC
Subregion
Peaking
Assumption 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
NWPP/RMRG Summer 25.9% 24.6% 23.4% 21.6% 20.8% 17.7% 16.5% 13.5% 11.7% 10.4%
SRSG Summer 18.1% 17.3% 17.0% 14.7% 15.5% 16.8% 16.0% 15.4% 14.4% 13.6%
CAMX Summer 21.4% 27.8% 27.3% 26.8% 22.5% 21.0% 20.6% 19.6% 19.2% 19.2%
Table 5.4 – NERC LTRA Prospective Reserve Margin
Prospective Reserve Margin
U.S. WECC
Subregion
Peaking
Assumption 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
NWPP/RMRG Summer 25.9% 24.8% 24.0% 22.2% 21.5% 18.4% 17.2% 14.2% 12.3% 11.0%
SRSG Summer 18.1% 18.1% 19.5% 17.2% 17.9% 19.2% 18.3% 17.6% 16.6% 15.7%
CAMX Summer 21.4% 35.3% 40.8% 41.7% 37.3% 35.7% 35.2% 34.1% 33.6% 34.8%
Table 5.5 – NERC LTRA Reference Reserve Margin
Reference Planning Reserve Margin
U.S. WECC
Subregion
Peaking
Assumption 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
NWPP/RMRG Summer 15.4% 16.1% 15.2% 15.1% 15.0% 14.9% 14.8% 15.6% 14.7% 14.5%
SRSG Summer 10.9% 11.9% 11.0% 10.8% 10.7% 10.6% 10.5% 11.1% 10.4% 10.3%
CAMX Summer 18.2% 15.8% 19.1% 19.1% 19.1% 19.0% 18.9% 15.7% 18.9% 19.0%
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
112
Using this data, a reserve margin position can be calculated to show project shortfalls, both with
and without the inclusion of prospective resource additions. Table 5.6 reports the reserve margin
differential based on anticipated resources, whereas Table 5.7 reports the reserve margin
differential assuming prospective resources are achieved during the study period. In either table, a
positive percentage represents a margin of overage where WECC is expected to have resources
above the reference margin target; a negative number (highlighted for emphasis) represents a year
where a given subregion is at risk of falling below the reference margin.
Based on this evaluation, potential shortfalls in planning reserve margin show up in the back three
years of the study period and only in the NWPP/RMRG subregion of WECC.
Table 5.6 – Planning Reserve Margin Shortfalls by Subregion with Anticipated Resources
Shortfalls Assuming Anticipated Reserve Margin
U.S. WECC
Subregion
Peaking
Assumption 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
NWPP/RMRG Summer 10.5% 8.5% 8.2% 6.5% 5.8% 2.8% 1.7% -2.1% -3.0% -4.1%
SRSG Summer 7.2% 5.4% 6.0% 3.9% 4.8% 6.2% 5.5% 4.3% 4.0% 3.3%
CAMX Summer 3.2% 12.0% 8.2% 7.7% 3.4% 2.0% 1.7% 3.9% 0.3% 0.2%
Table 5.7 – Planning Reserve Margin Shortfalls by Subregion with Prospective Resources
Shortfalls Assuming Prospective Reserve Margin
U.S. WECC
Subregion
Peaking
Assumption 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
NWPP/RMRG Summer 10.5% 8.7% 8.8% 7.1% 6.5% 3.5% 2.4% -1.4% -2.4% -3.5%
SRSG Summer 7.2% 6.2% 8.5% 6.4% 7.2% 8.6% 7.8% 6.5% 6.2% 5.4%
CAMX Summer 3.2% 19.5% 21.7% 22.6% 18.2% 16.7% 16.3% 18.4% 14.7% 15.8%
Prior Measures
PacifiCorp’s past assessments, relying on calculations incorporated into the WECC PSA, have
reporting a rolling succession of power supply margins, where each year there is a downward trend
in reserve margins extending into the future. The rolling nature of each year’s outcome tells us that
while declining reserve margins are important, the trend line is rarely followed from one year to
the next. Rather, the trend line tends to be pushed forward like a wave, where the future shortage
is not allowed to materialize because of cumulative actions taken within the WECC in recognition
of future need.
Pacific Northwest Resource Adequacy Forum’s Adequacy Assessment
As in the 2019 IRP, the Pacific Northwest Resource Adequacy Forum (later replaced by the
Resource Adequacy Advisory Committee) issued resource adequacy standards in April 2008,
which were subsequently adopted by the Northwest Power and Conservation Council. The
standard calls for assessments three and five years out, conducted every year, and including only
existing resources and planned resources that are already sited and licensed. The current
assessment (issued October 2019) concludes that power supply is expected to be adequate through
2020, with energy and capacity surplus becoming a deficit in 2021 and 2022 at a loss of load
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
113
probability of 10%. This deficit is primarily driven by the retirement of the Boardman and
Centralia coal plants. The assessment includes approximately 550 MW of new capacity scheduled
to come online in 2021.
2021 Northwest Power Plan
The Northwest Power and Conservation Council is currently in the process of finalizing the 2021
Northwest Power Plan, which is expected to be final in early 2022. Although preliminary,
PacifiCorp has been actively participating in the planning process to date, and notes that the draft
findings are similar to what the company has observed through the WECC Western Assessment
of Resource Adequacy and the NERC LTRA, primarily:
• There is a resource adequacy need in the next few years, with up to 1,600 MW of
capacity need by 2023;
• After 2023, even with additional coal-fired generation retirements, adequacy can be
maintained through a high level of expected renewable resource buildout and the
optimization of the existing hydro and gas-fired resource fleet; and
• There is inherent uncertainty driven by the possibility of accelerated loads due to
electrification programs and the uncertainty of WECC-wide resource buildout.
NWPP Resource Adequacy Program
Beginning in early 2019, PacifiCorp along with other Northwest Power Pool (NWPP) member
entities and the Northwest Power Pool itself engaged in the development of a regional Resource
Adequacy (RA) Program as a mechanism to assure a high likelihood of adequate supply to meet
customer demand under a wide array of scenarios.7 This program includes two components, a
forward showing (FS) planning mechanism and an operational program (Ops Program) to help
participants that are experiencing extreme events meet customer demand. The program is intended
to be a starting point and does not solve every issue facing the region, but is an incremental step
toward increased regional coordination, which could better position the region to continue to tackle
these big issues.
The program will focus on creating a capacity RA program with a demonstration of deliverability.
Additional adequacy programs may also be necessary following the implementation of the
capacity program. The region may also benefit from other forms of coordination, and while the
structure and process associated with the program may serve as foundational building blocks to
additional regional coordination, the NWPP and its participants are only working to implement the
capacity RA program at this time. The proposed RA program does not replace or supplant the
resource planning processes used by states or provinces or the regulatory requirements of the
Federal Energy Regulatory Commission (FERC), North America Electric Reliability Corporation
(NERC) or Western Electricity Coordinating Council (WECC). The program is designed to be
supplemental and complementary to those processes and requirements. Program planning is
scheduled to continue throughout 2022, with a proposed implementation date in 2024.
7 https://www.nwpp.org/resources/2021-nwpp-ra-program-detailed-design
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
114
Reliable Service through Unpredictable Weather and Challenging Market
Liquidity
As described in Volume I, Chapter 7 (Resource Options), PacifiCorp, other utilities, and power
marketers who own and operate generation engage in market purchases and sales of electricity on
an ongoing basis to balance the system and maximize the economic efficiency of power system
operations. In addition to reflecting spot market purchase activity and existing long-term purchase
contracts in the IRP portfolio analysis, PacifiCorp models front office transactions (FOT). FOTs
are proxy resources, assumed to be firm, that represent procurement activity made on an on-going
forward basis to help PacifiCorp cover short positions.
Solicitations for FOTs can be made years, quarters or months in advance, however, most
transactions to balance PacifiCorp’s system are made on a balance of month, day-ahead, hour-
ahead, or intra-hour basis. Annual transactions can be available three or more years in advance.
Seasonal transactions are typically delivered during quarters and can be available from one to three
years or more in advance. The terms, points of delivery, and products will all vary by individual
market point.
In developing FOT limits for the 2021 IRP, PacifiCorp reviewed the studies described in the
sections above as part of its assessment of market reliance in addition to consideration of its active
participation in wholesale power markets, its view of physical delivery constraints, and market
liquidity and market depth. The 2021 IRP FOT limits are 1,000 MW in the winter, and 500 MW
in the summer, reduced from 1,425 MW in the 2021 IRP. These reductions are due to an
assumption of zero summer liquidity at COB, NOB, and Mona, as well as decreased liquidity at
Mid-C in both Flat Annual and Heavy Load Hour. Table 5.8 details the assumed market
availability limits.
Table 5.8 – Maximum Available Front Office Transactions by Market Hub
Market Hub/Proxy FOT Product Type
Availability Limit (MW)
2021 2019
Summer Winter Summer Winter
(July) (December) (July) (December)
Mid-Columbia (Mid-C)
Flat Annual or Heavy Load Hour 350 350 Reduced from 400
Heavy Load Hour 150 0 Reduced from 375
California Oregon Border (COB)
Flat Annual or Heavy Load Hour 0 250 Removed in summer only
Nevada Oregon Border (NOB)
Heavy Load Hour 0 100 Removed in summer only
Mona
Heavy Load Hour 0 300 Removed in summer only
Total 500 1,000 1,425 1,425
PacifiCorp’s historical market purchases at times exceeded its 2019 IRP FOT planning limits,
indicating that it was able to find sellers in the market to meet capacity needs. While PacifiCorp
expects to continue to use its transmission access to access markets whenever it is economic to do
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
115
so, planning to rely exclusively on markets and imports at the same levels is becoming riskier as
western resource mix evolves and there is greater reliance on variable and short-duration resources.
Aligned with review of the regional studies discussed above, and the historical market purchases
and transactions, PacifiCorp has selected a peak-season FOT limit of 1,000 MW in the winter and
500 MW for the summer in the 2021 IRP. The company will continue to refine its assessments of
market depth and liquidity for transactions, informed by actual operations, to quantify the risk
associated with the level of market reliance. Several FOT studies are discussed and evaluated in
Volume I, Chapter 8 (Modeling and Portfolio Evaluation Approach) and Chapter 9 (Modeling and
Portfolio Selection Results).
Planning for Load Changes as a Result of Climate Change
Recent weather-based reliability events throughout the United States have underscored the need
for utilities to consider the potential for increasingly extreme weather and the underlying reliability
challenges that may be caused as part of its planning process. PacifiCorp has prepared a climate
change scenario within the 2021 IRP to assess the ways in which climate change may impact
planning assumptions (See Chapter 8, Volume I, Modeling and Portfolio Evaluation Approach).
The following section provides an overview on the load assumptions associated with climate
change projections.
PacifiCorp consulted with the Northwest Power and Conservation Council to collaboratively align
on how to model future peak load need based on changing temperatures throughout PacifiCorp’s
service area. Further, a literature review of various climate change research was performed to
determine a basis for temperatures informing the 2021 IRP climate change scenario. Ultimately,
PacifiCorp’s 2021 IRP climate change scenario relies on projected temperatures as determined by
the United States Bureau of Reclamation (Reclamation) in the West-Wide Climate Risk
Assessments: Hydroclimate Projections Study (Study).8 In addition to temperature projections, the
Reclamation study also provides hydrological projections for waterways throughout PacifiCorp’s
six-state service territory.
Table 5.9 below provides the projected range of temperature change for select sites within
PacifiCorp’s service territory, which were used to model projected temperatures in the 2021 IRP
Washington-required scenario to include the effects of climate change.
8 United States Bureau of Reclamation, March 2016, Managing Water in the West, Technical Memorandum No. 86-
68210-2016-01, West-Wide Climate Risk Assessments: Hydroclimate Projections.
https://www.usbr.gov/climate/secure/docs/2016secure/wwcra-hydroclimateprojections.pdf
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
116
Table 5.9 – Projected Range of Temperature Change in the 2020s and 2050s relative to the
1990s9
Bureau of Reclamation Site
PacifiCorp
Jurisdiction
Assumption
Projected Range of Temperature
Change (°F)
2020s 2050s
Klamath River near Klamath California 1.4 to 2.4 2.6 to 4.4
Snake River Near Heise Idaho 1.6 to 3.1 3.1 to 5.6
Klamath River near Seiad Valley Oregon 1.4 to 2.5 2.7 to 4.5
Green River near Greendale Utah 1.7 to 3.1 3.1 to 5.7
Yakima River at Parker Washington 1.5 to 2.6 2.7 to 5.0
Green River near Greendale Wyoming 1.7 to 3.1 3.1 to 5.7
PacifiCorp used these temperature projections to calculate change in peak loads and energy driven
by temperature change over the next three decades.10
As illustrated in Table 5.10, relative to the 2021 IRP forecast, the climate change scenario results
in summer peaks being higher by approximately 50 MW (<1% higher) over the 2021-2025
timeframe. By 2040, summer peaks are projected to be 318 MW (2.7%) higher than the 2021 IRP
Base.
As illustrated in Table 5.11, increasing winter temperatures results in less heating load, which drive
lower winter peaks. By 2040, winter peaks are projected to be 259 MW (2.3%) lower than the
2021 IRP Base.
As illustrated in Table 5.12, increasing temperatures are driving a slightly lower energy forecast.
This is driven by lower heating loads for Oregon, which is largely offset by increased loads in
Utah.
9 United States Bureau of Reclamation, March 2016, Managing Water in the West, Technical Memorandum No. 86-
68210-2016-01, West-Wide Climate Risk Assessments: Hydroclimate Projections.
https://www.usbr.gov/climate/secure/docs/2016secure/wwcra-hydroclimateprojections.pdf
10 Additional information on methodology behind the peak-load calculation can be found in Volume I, Chapter 6
(Load and Resource Balance) of the 2021 IRP.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
117
Table 5.10 – Change in Summer Coincident Peak Climate Change Scenario vs 2021 IRP Base
(Megawatt-hours), at Generation, pre-DSM
Year Total OR WA CA UT WY ID
2021 53 10 1 (0) 17 17 8
2022 53 11 1 (0) 17 17 8
2023 54 11 1 (0) 17 17 8
2024 55 11 1 (0) 17 17 8
2025 53 11 1 (0) 17 17 7
2026 71 16 3 (0) 26 18 8
2027 89 22 4 (0) 35 18 10
2028 107 28 5 (0) 44 19 11
2029 126 34 7 (0) 53 19 13
2030 139 41 8 - 63 14 14
2031 158 47 10 0 73 14 15
2032 178 54 11 0 82 14 16
2033 198 60 13 0 92 15 18
2034 218 67 14 0 103 15 19
2035 239 74 16 0 113 16 21
2036 245 80 17 0 119 16 14
2037 273 86 19 0 128 16 24
2038 291 91 20 0 137 17 26
2039 301 97 21 0 139 16 28
2040 318 103 22 0 146 16 30
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
118
Table 5.11 – Change in Winter Coincident Peak Climate Change Scenario vs 2021 IRP Base
(Megawatt-hours), at Generation, pre-DSM
Year Total OR WA CA UT WY ID
2021 (126) (90) (10) (3) (15) (4) (4)
2022 (127) (90) (10) (3) (16) (4) (4)
2023 (127) (90) (10) (3) (16) (4) (4)
2024 (128) (90) (10) (3) (16) (4) (4)
2025 (130) (92) (10) (2) (17) (5) (4)
2026 (137) (95) (12) (3) (18) (5) (4)
2027 (143) (97) (14) (3) (19) (6) (5)
2028 (150) (101) (15) (3) (20) (6) (5)
2029 (158) (104) (17) (3) (21) (8) (5)
2030 (162) (107) (19) (3) (22) (6) (5)
2031 (167) (109) (20) (3) (23) (7) (6)
2032 (175) (112) (22) (3) (24) (8) (6)
2033 (182) (115) (23) (3) (25) (9) (6)
2034 (189) (118) (25) (3) (26) (10) (6)
2035 (194) (121) (27) (3) (27) (10) (7)
2036 (201) (124) (28) (4) (28) (12) (7)
2037 (247) (449) (105) (14) 290 24 7
2038 (256) (461) (106) (14) 294 24 8
2039 (261) (472) (107) (15) 300 25 8
2040 (259) (484) (109) (15) 310 30 9
Table 5.12 – Change in Annual Energy Climate Change Scenario vs 2021 IRP Base
(Megawatt-hours), at Generation, pre-DSM
Year Total OR WA CA UT WY ID
2021 (129,280) (171,850) (38,220) (13,050) 76,330 (16,180) 33,690
2022 (129,790) (172,660) (38,030) (13,070) 76,800 (16,410) 33,580
2023 (131,060) (173,320) (37,820) (13,050) 76,400 (16,710) 33,440
2024 (131,500) (173,790) (37,630) (13,050) 76,560 (16,930) 33,340
2025 (131,870) (174,200) (37,470) (13,060) 76,780 (17,130) 33,210
2026 (126,270) (175,670) (37,980) (13,430) 83,670 (17,590) 34,730
2027 (120,520) (177,100) (38,480) (13,790) 90,660 (18,060) 36,250
2028 (114,500) (178,480) (38,950) (14,170) 97,840 (18,520) 37,780
2029 (107,870) (179,490) (39,360) (14,550) 105,200 (18,950) 39,280
2030 (101,020) (180,590) (39,720) (14,920) 112,780 (19,370) 40,800
2031 (93,880) (181,720) (40,060) (15,310) 120,630 (19,750) 42,330
2032 (86,310) (182,800) (40,350) (15,700) 128,740 (20,090) 43,890
2033 (78,250) (183,760) (40,570) (16,080) 137,110 (20,380) 45,430
2034 (69,710) (184,630) (40,750) (16,460) 145,750 (20,640) 47,020
2035 (60,710) (185,420) (40,880) (16,850) 154,690 (20,850) 48,600
2036 (54,280) (186,550) (41,010) (17,150) 161,400 (21,080) 50,110
2037 (47,420) (187,620) (41,090) (17,450) 168,420 (21,280) 51,600
2038 (40,300) (188,630) (41,130) (17,760) 175,600 (21,470) 53,090
2039 (32,870) (189,600) (41,140) (18,070) 182,980 (21,640) 54,600
2040 (25,190) (190,540) (41,110) (18,380) 190,520 (21,810) 56,130
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
119
Weather-Related Impacts to Variable Generation
The effect of extreme weather events associated with climate change is an evolving area of
research that is growing in importance as renewable, intermittent resources dependent upon wind,
solar, and hydrologic conditions comprise an increasing proportion of utility resource portfolios.
Wildfire Impacts
Increased wildfire frequency associated with climate change is expected to have a range of impacts
to intermittent generation sources, including wind, solar, and hydro resources.
Wind generation sites in PacifiCorp’s system are most likely to be subjected to fast moving range
fires. Impacts at wind generation sites from range fires are likely to be limited and short in duration,
as turbines and collector substations are surrounded by gravel surfaces that are fire resistant.
Sensitive turbine equipment is located far above the ground away from damaging heat sources.
Impacts to transmission lines and aboveground collector lines from range fires at wind generation
sites is also anticipated to be minor due to the limited fuels available to cause ignition to wooden
poles. Outage durations are likely to be short when operations staff is required to evacuate a site
in advance of a fire and to curtail generation as a precautionary measure.
Climate change also poses fire risks at solar generation sites, which are also likely to manifest as
range fires given solar projects are typically sited well away from substantial tree stands that could
block solar panels. Impacts could be significant depending on the amount of vegetation at a site,
as generating equipment is close to the ground close to potential fuel sources. If a range fire creates
sufficient heat to impact equipment, resumption of generation will be dependent on the ability to
obtain and install necessary replacement equipment.
Fire impacts at hydro generation sites will be driven primarily by impacts to transmission lines.
Hydro generation sites are typically in heavily forested terrain and serviced by only one or two
transmission lines. An intense forest fire can damage miles of transmission lines that can take
weeks to months to restore to service. If a fire threatens a hydro generation site, the site will be
proactively evacuated with generation units typically taken offline and the facility put into spill to
avoid potential instream flow impacts that could occur with an unplanned unit shutdown resulting
from impacts to local transmission lines. Generation units would be restarted as soon as possible
when conditions permit safe re-entry to provide generation locally until transmission service, if
interrupted, is restored. Fire damage to dams, water conveyance structures, and generating plants
is expected to be minimal. Some damage to local distribution lines and communication
infrastructure upon which hydro generation sources rely is also possible, which could impact
generation restoration timelines.
PacifiCorp outlines its wildfire mitigation strategies later in this document.
Extreme Weather Impacts
Climate change also has the potential to result in increased frequency and magnitude of extreme
weather events. Such changes can result in more frequent and intense precipitation events and
flooding, which could impact hydropower generation and change historic operating practices to
maintain flood control capabilities at projects where flood control benefits are part of project
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
120
operations. Similar to wildfire events, increased flooding has the potential to impact access to
remote hydro facilities. Increased precipitation and reduced snow water equivalent have the
potential to modify runoff patterns impacting hydro generation but is not expected to impact dam
safety at PacifiCorp hydro facilities, which are subject to FERC dam safety requirements that
ensure they are able to safely pass probable maximum flood events. Increases in extreme weather
that results in more frequent flood events has the potential to increase debris loading in river
systems and reservoirs, potentially increasing generation downtime to remove debris that may
reduce inflows to hydro units or reduce flows through fish screens.
Changes to wind patterns and wind speeds, and changes in extreme high and low air temperatures
have the potential to impact wind and solar generation. Extreme high temperatures can raise
ground temperatures, which has the potential to impact collector system capacities at wind and
solar projects and reduce collector system carrying capacity, limiting output, similar to high
temperature impacts to high voltage transmission lines. However, these impacts are not anticipated
to be significant on wind energy resources given peak output is typically observed outside of
summer months. Increasing air temperatures result in lower air densities, which could negatively
impact wind energy output even if wind speeds are unchanged. Lower wind speeds in the summer
relative to historic experience because of extreme high temperatures is also possible. Wind turbines
in PacifiCorp’s fleet generally are protected from extreme low temperatures given the conditions
in which they currently operate, and low temperature protection features are installed in PacifiCorp
turbines where weather conditions warrant their inclusion.
There is limited research on site-specific impacts from extreme weather events and thus how to
plan to improve the resiliency of intermittent generation resources. Resiliency will be enhanced as
planning to ensure site access occurs in response to observed changes in extreme weather events
and as more research is available to locally forecast impacts of climate change and extreme weather
so those impacts can be factored into the resource planning process.
Impacts on wind and solar energy
The impact on renewable energy generation due to extreme weather events and climate change is
an evolving topic. For conclusive trends of climate change impact, data collection specific to
geographic locations is critical. Climate impacts both the demand and supply side of energy. Due
to daily or seasonal changes the demand for energy patterns is changing. On the supply side due
to increasing temperatures and variability in climate parameters it impacts estimated energy
outputs of projects as well as operational costs. However, there are limited studies in the North
American region that quantitatively document the impact of a climate parameter on the future of
wind and solar energy.11 Some broad impacts anticipated from climate change are noted below:12
Wind Energy
• Changes to wind speed: could impact energy assessments
• Changes in temperature: with increased temperatures the air density could reduce energy
outputs
11 Climate change impacts on the energy system: a review of trends and gaps. Cronin, J., Anandarajah, G. &
Dessens, O. Climatic Change volume 151, August 2018.
12 Climate change impacts on renewable energy generation. A review of quantitative projections. Kepa Solaun,
Emilio Cerdá. Renewable and Sustainable Energy Reviews
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
121
• Changes in seasonal or daily wind: could disrupt correlation between wind energy and
grid load demand
• Rising sea levels: could damage offshore wind farm infrastructure
Solar Energy
• Changes in mean temperatures: increased global temperatures could reduce cell
efficiency
• Changes in solar irradiation, dirt, snow, precipitation etc.: increase in these variables
could reduce energy output
Integration of energy storage with wind and solar projects is a way to help make use of generated
energy more efficiently.
Wildfire Risk Mitigation
Despite years of focus on wildfire prevention, wildfires continue to become more frequent and
intense throughout the region. Continued growth of the wildland urban interface and the impacts
of climate change mean that it is imperative that utilities continue to lead the way in implementing
innovative strategies to keep customers and communities safe.
As a leading provider of safe and reliable electricity throughout the west, PacifiCorp has worked
closely with stakeholders and experts to develop wildfire mitigation plans that ensure safe and
reliable service and prioritize customer and community safety. PacifiCorp’s wildfire mitigation
plans, which describe the investments and protocols needed to construct, maintain, and operate
electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire, are
guided by the following core principles:
• Frequency of ignition events related to electric facilities can be reduced by engineering
more resilient systems that experience fewer fault events.
• When a fault event does occur, the impact of the event can be minimized using equipment
and personnel to shorten the duration to isolate the fault event.
• Systems that facilitate situational awareness and operational readiness are central to
mitigating fire risk and its impacts.
• A successful plan must also consider the impact on customers and communities, in the
overall imperative to provide safe, reliable, and affordable electric service.
PacifiCorp’s plans, which outline a risk-based, balanced, and integrated approach, contain six
critical focus areas of planning and execution for a reliable and resilient energy future: (1) Risk
analysis and drivers, (2) Situational awareness, (3) Inspection and correction, (4) Vegetation
management, (5) System hardening, and (6) Operational practices.
The company continues to build on over a century of wildfire mitigation experience and three
decades of information gathering and analysis. PacifiCorp’s planning focus areas above are
intended to ensure that we continue to serve customers safely and reliably. As new analyses,
technologies, practices, network changes, environmental influence or risks are identified, changes
to address them may be incorporated into future iterations of the plans.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
122
Risk Analysis and Drivers
PacifiCorp’s risk evaluation process employs the concept that the risk is essentially the product of
the likelihood of a specific risk event multiplied by the impact of the event. The likelihood, or
probability, of an event is an estimate of a particular event occurring within a given time frame.
The impact of event is an estimate of the effect when an event occurs. Impact can be evaluated
using a variety of factors, including considerations centered on health and safety, the environment,
customer satisfaction, system reliability, the company’s image and reputation, and financial
implications.
A disruption of normal operations on the electrical network, called a “fault” in the industry, could
be a possible ignition source for wildfire. Under certain weather conditions and in the vicinity of
wildland fuels, an ignition can grow into a harmful wildfire, potentially even growing into a
catastrophic fire causing great harm to people and property. This general relationship is shown in
the Figure 5.1.
Figure 5.1 – Wildfire Risk Mitigation Focus Areas
Therefore, PacifiCorp’s risk analysis first concentrates on weather conditions and ignitable fuels,
to identify the geographic areas at the greatest risk of catastrophic fire. The analysis also explores
location specific fire history, recorded causes, the acreage impact of the fires, and the seasonality
of fires. The analysis further considers historical outage data, reflecting the best available data
regarding the potential for faults on the electrical system.
These faults, when experienced during fire risk time periods in locations with the greatest risk for
catastrophic fire, reflect the best available data to utilities to correlate an identifiable event on the
electric network to the risk of utility-related wildfire. There is a logical physical relationship, when
a fault occurs it could result in a spark, thus there is a risk of fire, therefore these events are
classified as ignition risk drivers. An unplanned outage, which is when a line is unintentionally de-
energized, is most often rooted in a fault. Accordingly, the company has closely analyzed the
causes and frequency of outages. This analysis is designed to determine which mitigation strategies
are best suited to minimize fault events, thereby reducing the risk of fire. Additionally, this analysis
highlights geographic locations that present the greatest risk, allowing PacifiCorp to focus efforts.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
123
Situational Awareness
Situational awareness involves knowledge of the conditions that impact the potential for wildfire
ignition and spread. Increasing its situational awareness of such conditions helps an electric utility
implement operational strategies, respond to local conditions, and minimize the wildfire risk by
making mitigation strategies more effective.
Weather Stations
PacifiCorp obtains data regarding local conditions from many sources and uses the data to adjust
its operations in both the short and long term. Local weather data remains a key input to this
process and PacifiCorp’s overall situational awareness capability. To supplement existing local
weather data and conditions, PacifiCorp installs and operates weather stations in high--risk
locations. Additionally, PacifiCorp continues to evaluate the need for additional micro weather
data in areas with a high risk of wildfires that could threaten the public and property to obtain more
granular local weather data. As the company’s overall plan and situational evolves, PacifiCorp
intends to evaluate this program for future expansion should additional or different data be needed.
Meteorology
The ability to gather, interpret, and translate data into an assessment of utility specific risk and
inform decision making protocols is another key component of PacifiCorp’s situational awareness
capability. To support this effort, PacifiCorp has developed a meteorology department within the
company’s broader emergency management department. The objectives of this department are to
supplement the company’s longer term risk analysis capabilities with a real time risk assessment
and forecasting tool, identify and close any forecasting data gaps, manage day to day threats and
risks, and recommend changes to operational protocols during periods of elevated risk.
Inspection and Correction
Inspection and correction programs are the cornerstone of a resilient system. These programs are
tailored to identify conditions that could result in premature failure or potential fault scenarios,
including situations in which the infrastructure may no longer be able to operate per code or
engineered design, or may become susceptible to external factors, such as weather conditions.
PacifiCorp performs inspections on a routine basis as dictated by both state-specific regulatory
requirements and PacifiCorp-specific policies. When an inspection is performed on a PacifiCorp
asset, inspectors use a predetermined list of condition codes and priority levels to describe any
noteworthy observations or potential noncompliance discovered during the inspection. Once
recorded, PacifiCorp uses condition codes to establish the scope of and timeline for corrective
action to make sure that the asset is in conformance with National Electric Safety Code (NESC)
requirements, state-specific code requirements and/or PacifiCorp specific policies. This process is
designed to correct conditions while reducing impact to normal operations.
The historic inspection and correction programs are effective at maintaining regulatory compliance
and managing routine operational risk. They also mitigate some wildfire risk by identifying and
correcting conditions which, if uncorrected, could ignite a fire. Recognizing the growing risk of
wildfire, PacifiCorp plans to supplement its existing programs, in collaboration with state
regulators and stakeholders, to further mitigate the growing wildfire specific operational risks and
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
124
create greater resiliency against wildfires. These changes include the creation of a fire threat
classification for specific conditions, an increase of inspection frequencies in high-risk locations,
and the reduction of correction timeframes for fire threat conditions.
Vegetation Management
Vegetation management is generally recognized as a significant strategy in any Wildfire
Mitigation Plan. Vegetation coming into contact with a power line could be a source of fire
ignition. Thus, reducing vegetation contacts reduces the potential of an ignition originating from
electrical facilities. While it is impossible to eliminate vegetation contacts completely, at least
without radically altering the landscape near power lines, a primary objective of PacifiCorp’s
existing vegetation management program is to minimize contact between vegetation and power
lines. This objective is in alignment with core Wildfire Mitigation Plan efforts, and continuing
dedication to administering existing programs is a solid foundation for PacifiCorp’s Wildfire
Mitigation Plan efforts. To supplement the existing program, PacifiCorp vegetation management
implements additional Wildfire Mitigation Plan strategies such as annual vegetation patrols,
extended clearances, and radial pole clearing in high-risk locations.
System Hardening
PacifiCorp’s electrical infrastructure is engineered, designed and operated in a manner consistent
with prudent utility practice, enabling the delivery of safe, reliable power to all customers. When
installing new assets, PacifiCorp is committed to incorporating the latest technology and
engineered solutions. When conditions warrant, PacifiCorp may engage in strategic system
hardening, which means replacing existing assets (or, in some circumstances, modifying existing
assets using a new design and additional equipment) to make the assets more resilient. Recognizing
the growing risk of wildfire, PacifiCorp plans to supplement existing asset replacement projects
with system hardening programs designed to mitigate specific operational risks associated with
wildfire.
System hardening programs are designed in reference to the equipment on the electrical network
that could be involved in the ignition of a wildfire or be subject to an existing wildfire event. In
general, system hardening programs attempt to reduce the occurrence of events involving the
emission of sparks (or other forms of heat) from electrical facilities or reduce the impact of an
existing wildfire on utility infrastructure. System hardening programs represent the greatest long-
term mitigation tool available for use by electric utilities. The phasing and prioritization of such
programs is therefore focused on locations that present the greatest risk through the line rebuild
program.
Additionally, no single system hardening program mitigates all wildfire risk related to all types of
equipment. Therefore, different system hardening components are grouped together as part of
PacifiCorp’s line rebuild program to address different factors, different circumstances and
different geographic areas. Each project included in the line rebuild program described below,
however, shares the common objective of reducing overall wildfire risk associated with the design
and type of equipment used to construct electrical facilities.
It must be emphasized, however, that system hardening cannot prevent all ignitions, no matter how
much is invested in the electrical network. Equipment does not always work perfectly and, even
when manufactured and maintained properly, can age and fail; in addition, there are external forces
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
125
and factors impacting equipment, including from third parties and natural conditions. Therefore,
PacifiCorp cannot guarantee that a spark or heat coming from equipment owned and operated by
PacifiCorp will never ignite a wildfire. Instead, PacifiCorp seeks to reduce the potential of an
ignition associated with any electrical equipment. To this end, PacifiCorp plans to make
investments with targeted system hardening programs.
Line Rebuild Program
PacifiCorp has evaluated specific areas for system hardening work based on the company’s risk
assessment methodology where bare overhead wire may be replaced with covered conductor.
Where appropriate, poles will either be replaced or made more fire resilient (by fire protective
treatment methods). Additionally, where conductor diameters do not support fault current properly
(due to the limited arc energy they can tolerate), they will be replaced, generally with covered
conductor. In all, the end effect will be more tolerant to incidental contact, while also being certain
to tolerate fault event arc energy levels.
Covered Conductor
Historically, the vast majority of high voltage power lines in the United States, and in PacifiCorp’s
service territory, were installed with bare overhead conductor. As the name “bare” suggests, the
wire is all metal and exposed to the air. For purposes of wildfire mitigation, a new conductor design
has emerged as an industry best practice. Most of the projects in the Line Rebuild Program will
involve the installation of covered conductor. Sometimes, with some variations in products,
covered conductor is also called spacer cable, aerial cable, or tree cable.
The dominant characteristic of covered conductor is that the metal conductor which carries
electricity is sheathed in a plastic covering. As a comparison for the lay person, covered conductor
is like an extension power cord that you might use in your garage. The plastic coating provides
insulation for the energized metal conductor inside the plastic coating. To be clear, covered
conductor is not insulated enough for people to directly handle an energized high voltage power
line (as discussed below). But the principle is the same. The plastic sheathing provides an
insulating effect. It is this insulating effect which reduces the risk of wildfire, by greatly reducing
the number of faults that would have occurred had bare conductor been used.
Variations in covered conductor products have been used in the industry for decades. Due to many
operating constraints, however, use of covered conductor tended to be limited to locations with
extremely dense vegetation where traditional vegetation management was not feasible or efficient.
Recent technological developments, however, have markedly improved covered conductor
products, reducing the operating constraints historically associated with the design. These
advances have improved the durability of the project and reduced the impact of thermal insulation
(i.e. because bare wires are exposed to air, bare wires can cool easier). There are still logistical
challenges with covered conductor. Above all, the wire is heavier, especially when carrying snow
or ice, meaning that more and/or stronger poles may be required when using covered conductor.
And the product itself is more expensive than bare conductor.
The wildfire mitigation benefits of covered conductor are significant. As discussed in the risk
assessment section, a disruption on the electrical network, a fault, can result in emission of spark
or heat that could be a potential source of ignition. Covered conductor greatly reduces the potential
of many kinds of faults. For example, contact from object is major category of real-world faults
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
126
which can cause a spark. Whether it is a tree branch falling into a line or a Mylar balloon carried
by the wind drifting into a line, contact from those objects with energized bare conductor causes
the emission of sparks. If those same objects contact covered conductor, the wire is insulated
enough that there are no sparks. Likewise, many equipment failures are a wildfire risk because the
equipment failure then allows a bare conductor to contact a grounded object. Consequently,
covered conductor greatly reduces the risk of ignition associated with most types of equipment
failure. For example, if a cross arm breaks, the wire held up by the cross arm often falls to the
ground (or low and out of position, so that the wire might be contacting vegetation on the ground
or the pole itself). In those circumstances, a bare conductor can emit sparks (or heat) that can cause
an ignition. The use of covered conductor, in those exact same circumstances, would almost
certainly not lead to an ignition, because the insulation around the wire is sufficient to prevent any
sparks and limit energy flow, even when there is contact with an object.
Covered conductor is especially well suited to reduce the occurrence of faults reasonably linked
with the worst wildfire events. Dry and windy conditions pose the greatest wildfire risks. Wind is
the driving force behind catastrophic wildfire spread. At the same time, wind has distinct and
negative impacts on a power line. The wind blows objects into lines; a strong wind can cause
equipment failure; and even parallel lines slapping in the wind can cause sparks. Covered
conductor specifically reduces the potential of a catastrophic ignition event, because covered
conductor is especially effective at limiting the kinds of faults that occur when it is windy. Taken
together, these substantial benefits warrant the use of covered conductor in areas with a high
wildfire risk.
In sum, at a very basic level, covered conductor is safer overall compared to bare conductor. Not
only does covered conductor reduce the risk of wildfire, it is less dangerous to contact a covered
conductor compared to a similar voltage bare conductor. Combined with the substantial wildfire
mitigation benefits, covered conductor is the preferred design for rebuild projects. There are,
however, unique challenges implicated in making it harder to spot a low-hanging or downed line.
PacifiCorp also evaluated the costs and benefits of underground design for the rebuild projects.
The potential wildfire mitigation benefits are undeniable. While an underground design does not
completely eliminate every ignition potential (i.e., because of above-ground junctions), it is the
most effective design to most dramatically reduce the risk of any utility-related ignition.
Unfortunately, because of cost and operational constraints, the functional realities of underground
construction prevent widespread application as a wildfire mitigation strategy. Nonetheless,
PacifiCorp is using an underground design as part of the rebuild projects when functional and cost-
effective. Through the design process, each rebuild project is assessed to determine whether
sections of the rebuild should be completed with underground construction. As a practical matter,
the great majority of the rebuilds will be covered conductor. This outcome is consistent with
emerging best practices. Utilities in geographic areas with extreme wildfire risk, including in
California and Australia, are trending heavily towards use of covered conductor, with limited
applications of underground construction where appropriate. Indeed, sourcing material for the
planned projects is challenging because of the industry trend towards use of covered conductor as
a primary wildfire mitigation strategy. On a related note, the company remains willing to consider
additional underground applications. Some communities and landowners may prefer, for aesthetic
reasons, to pursue a higher cost underground alternative. Consistent with governing electric service
regulations, PacifiCorp will work with communities or individual landowners who are willing to
pay the incremental cost and obtain the necessary legal entitlements for underground construction,
if covered conductor is the least cost option for a rebuild project.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
127
Non-Wooden Poles
Traditionally, overhead poles are replaced or reinforced within PacifiCorp’s service territory
consistent with state specific requirements and prudent utility practice. When a pole is identified
for replacement, typically through routine inspections and testing, major weather events, or joint
use accommodation projects, a new pole consistent with engineering specifications suitable for the
intended use and design is installed in its place. Engineering specifications typically reflect the use
of wooden poles which is consistent with prudent utility practice and considered safe and
structurally sufficient to support overhead electrical facilities during standard operating conditions.
However, the use of alternate non-wooden construction, such as steel or fiberglass, can provide
additional structural resilience in high-risk locations during wildfire events and, therefore, aid in
restoration efforts.
In addition to the installation of non-wooden solutions as a part of standard replacement programs
or mechanisms in priority locations with increased risk, certain wooden poles may also be replaced
with non-wooden solutions in conjunction with other wildfire mitigation system hardening
programs. For example, as a part of covered conductor installation, the strength of existing poles
is evaluated. In many cases, the strength of existing poles may not be sufficient to accommodate
the additional weight of covered conductor. In these instances, the existing wooden pole is
upgraded to support the increased strength requirements and, when present in high priority
locations, replaced with a non-wooden solution for added resilience.
Non-Expulsion Fuses
Overhead expulsion fuses serve as one of the primary system protection devices on the overhead
system. The expulsion fuse has a small metal element within the fuse body that is designed to melt
when excessive current passes through the fuse body, interrupting the flow of electricity to the
downstream distribution system. Under certain conditions, the melting action and interruption
technique will expel an arc out of the bottom of the fuse tab. To reduce the potential for ignition
resulting from fuse operation, PacifiCorp has identified alternate methodologies and equipment
that do not expel an arc for installation within high-risk locations. PacifiCorp plans to replace
expulsion fuses with non-expulsion fuses as a part of the high-risk locations line rebuild program
in conjunction with the installation of covered conductor.
Operational Practices
System Operations
The manner in which an electrical system is operated can also help mitigate wildfire risk.
PacifiCorp has specific procedures addressing system operations during fire season. These
procedures are designed to reduce the potential for ignition of a fire from sparks emitted when a
line is re-energized with a disturbance still on the line. Recognizing the increasing magnitude of
the wildfire risk, PacifiCorp significantly augmented operating procedures in June 2018 to
incorporate a more conservative approach designed to reduce the potential of fault-based ignitions
on PacifiCorp’s electrical network. From a practical perspective, the procedures implicate two
primary subject areas: (a) settings for automatic reclosers and (b) line testing after lock-out.
Automatic reclosers are currently deployed on various transmission lines and distribution circuits
throughout PacifiCorp’s service territory. When a line trips open, an automatic recloser may
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
128
operate to close the circuit very quickly, so long as the cause of a momentary trip has cleared. The
reclosing function allows PacifiCorp to maintain service on a line that had tripped, rather than
opening the circuit and de-energizing the line. In general, automatic recloser operation is beneficial
because it reduces outages and improves customer reliability. The actual operation of recloser
equipment does not directly present wildfire risk, as the recloser equipment itself does not emit
sparks or otherwise pose an ignition risk.
The operation of automatic reclosers, however, indirectly implicates some degree of ignition risk.
When a fault is detected on the line, a recloser will trip and reclose based on predetermined settings
in an attempt to re-energize the line. If the cause of the fault is no longer present when the device
recloses, the line will re-energize resulting in limited impact to customers. If the cause of the
original fault still remains when the device recloses, however, the original fault may persist and,
depending on the circumstances, potentially result in arcing or an emission of sparks. As a result,
in some limited circumstances, the second fault scenario could lead to a fire ignition. Accordingly,
automatic recloser settings can have a significant impact on wildfire mitigation.
The risk associated with line-testing on overhead lines is very similar. If a breaker has “locked-
out”, meaning that it has opened and no longer conducts electricity, a system operator will
sometimes “test” the line. To test the line, the system operator will close the device, thereby
allowing the line to be re-energized. If the fault has cleared, then the system will run normally. If
the fault has not cleared, the device will lock out again. If the device locks out again, the system
operator then knows that additional investigation or work will be required before the line can be
successfully re-energized. Because faults are often temporary, line-testing can be an efficient tool
to maintain customer reliability. At the same time, line-testing can result in the emission of sparks
if a fault has not yet cleared when the line is tested. Accordingly, a “no-test” policy reduces the
risk of ignition, and a “no-test” policy is applicable in certain circumstances during fire season.
In general, these system operating procedures are more restrictive when wildfire conditions are
elevated. The specific circumstances in which automatic reclosers are disabled and no-test applies,
on both transmission and distribution lines, are fully detailed in the procedures.
Field Operations
During fire season, PacifiCorp modifies the way it operates in the field to further mitigate wildfire
risk. In particular, field operations consider the local weather and geographic conditions that may
create an elevated risk of wildfire. These practices are targeted to reduce the potential of direct or
indirect causes of ignition during planned work activities, fault response and outage restoration.
PacifiCorp personnel working in the field during fire season mitigate wildfire risk through a variety
of tactics. Routine work, such as condition correction and outage response, poses some degree of
ignition risk, and, in certain circumstances, crews modify their work practices and equipment to
decrease this risk. In the extremely unlikely event that a fire ignition occurs while field crews or
other PacifiCorp personnel are working in the field (collectively “field personnel”), such field
personnel are equipped with basic tools to extinguish small fires.
Work Restrictions
PacifiCorp field operations can mitigate some wildfire risk by managing the way that field work
is scheduled and performed. To effectively manage work during fire season, area managers
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
129
regularly review local fire conditions and weather forecasts provided to them as part of
PacifiCorp’s monitoring program – discussed in the situational awareness section below.
During fire season generally, field operations managers are encouraged to defer any nonessential
work at locations with dense and dry wildland vegetation, especially during periods of heightened
fire weather conditions. If essential work needs to be performed in high-risk locations and other
areas with appreciable wildland vegetation, certain restrictions may apply, including:
• Hot Work Restrictions. Field operations managers are encouraged to evaluate whether
work should be performed during a planned interruption, rather than while a line is
energized.
• Time of Day Restrictions. Field operations managers are encouraged to consider using
alternate work hours to accommodate evening and night work when there may be less risk
of ignition.
• Wind Restrictions. Field personnel are encouraged to defer work, if feasible, when there
are windy conditions at a particular work site.
• Driving Restrictions. Field personnel are encouraged to keep vehicles on designated
roads whenever operationally feasible.
Worksite Preparation
If wildland vegetation posing an ignition risk is prevalent at a worksite, and the work to be
performed involves the potential emission of sparks from electrical equipment, field personnel
working during fire season are encouraged to remove vegetation at the work site where allowed in
accordance with land management/agency permit requirements, especially when there is dry or
tall wildland grass. In addition to clearing work, the water truck resources, discussed below, are
strategically assigned to sometimes accompany field personnel working in a wildland area during
fire season, especially in high-risk locations. Depending on local conditions, dry vegetation in the
immediate vicinity may be sprayed with water before work as a preventative measure.
Vehicles
Vehicles can be a source of ignition. As discussed above, field operations personnel are instructed
to stay on designated roads during fire season, as feasible, and to avoid vegetation which could
contact the undercarriage of parked vehicle. To further mitigate any wildfire risk associated with
the use of vehicles, field operations plan to convert, over time, the vehicle exhaust configuration
of work trucks. To accomplish this objective, field operations will strategically convert some
vehicles in districts with the greatest amount of FHCA. Long term, when new vehicles are
purchased, PacifiCorp plans to purchase trucks with a vehicle exhaust configuration which
minimizes ignition risk.
Additional Labor Resources
Some wildfire mitigation activities require the time of field personnel, including in two key areas:
(a) supporting system operations in administering the procedures discussed above and (b)
responding to outages during fire season.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
130
Under normal operating procedures, system operators and field personnel work together daily to
manage the electrical network. In many situations, system operators depend on field personnel to
gather information and assess local conditions. As discussed above, there are system operations
procedures during wildfire season for disabling automatic recloser functions and limiting line-
testing. Consequently, system operators need field personnel to gather information and assess local
conditions during fire season more frequently than would otherwise be required under normal
operating procedures. The requests from system operators may be varied, ranging from a simple
phone call to confirm that it is raining in a particular area, to a much more time-intensive request,
such as a full line patrol on a circuit.
Field personnel may also spend some additional time when responding to an outage during fire
season. After a fault results in an outage, all or part of a circuit might remain de-energized while
restoration work is performed, depending on the design, loading conditions and sectionalizing
capability of the circuit experiencing the outage. Occasionally, additional foreign objects, such as
tree limbs or other debris, can come into contact with the de-energized line and remain undetected
throughout the duration of restoration efforts. Under normal operating procedures and consistent
with prudent utility practices, a line is typically re-energized as soon as restoration work is
complete. Consequently, a re-energized line could immediately experience a new fault if some
contact between the line and foreign object had occurred while restoration work was being
performed. The new fault would, of course, present additional wildfire risk, because of the
potential of a spark being emitted as a result of a fault occurring when the line was re-energized.
To mitigate this risk, field operations may perform some amount of line patrol on certain de-
energized sections of the circuit, notably during fire season and particularly in high-risk locations
dependent on current conditions at the work site and the duration of the restoration work.
Depending on the circumstances, this extra patrol might be done just before or just after re-
energizing the line. Typically, this type of line patrol does not involve a close inspection of any
particular facility; instead, it is a quick visual assessment specifically targeted to identify obvious
foreign objects that may have fallen into the line during restoration work.
Basic Personal Suppression Equipment
Personal safety is the first priority, and PacifiCorp field personnel are encouraged to evacuate and
call 911 if necessary. Field personnel working in high-risk locations maintain the capability to
extinguish a small fire that ignited while they are working in the field. Field personnel should
attempt suppression only if the fire is small enough so that one person can effectively fight the fire
while maintaining their personal safety. All field personnel working in high-risk locations during
fire season will have basic suppression equipment available onsite, because field utility trucks
typically carry the following equipment: (1) fire extinguisher; (2) shovel; (3) Pulaski; (4) water
container; and (5) dust mask. The water container should hold at least five gallons and may be a
pressurized container or a backpack with a manual pump (or other).
Mobile Generators
PacifiCorp has a mobile generator to assist with emergency response efforts. In short, when power
on the electrical network is lost, either proactively or as the result of wildfire damage, a mobile
generator unit can be dispatched to provide power. The generator is transported via tractor trailer
to a specific location based on real-time circumstances. For example, a mobile generator may be
dispatched by the Emergency Operations Center to mitigate the impact of a proactive de-
energization, as discussed in greater detail in the Public Safety Power Shutoff section below. There
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
131
are constraints in connecting the generator, and each deployment is examined on a case-by-case
basis.
Water Truck Resources
PacifiCorp has water trucks that field operations use to mitigate against wildfire risk. For clarity,
these resources are not dispatched to reported fires (i.e., like a fire truck). Instead, PacifiCorp
resources are strategically assigned to accompany field personnel if conditions warrant. For
example, if it is necessary to perform work in high-risk locations during a period in which there is
a Red Flag Warning, PacifiCorp field operations may schedule a water truck to join field personnel
working in the field. As discussed above, the water truck can be used to help prep the site for work.
By watering down dry vegetation in the work area, any chance of an ignition can be minimized.
In the extremely unlikely event there was an ignition, the water truck could be used to assist in the
suppression of a small fire. Field operations currently has eight water trucks for use in such
applications. In addition, the company plans to purchase two water trucks and one trailer.
Transmission-Based Reliability
PacifiCorp is required to meet mandatory FERC, (NERC), and WECC reliability standards and
planning requirements. The operation of PacifiCorp’s transmission system also responds to
requests issued by California Independent System Operator (CAISO) RC West as the NERC
Reliability Coordinator. The company conducts annual system assessments to confirm minimum
levels of system performance during a wide range of operating conditions, from serving loads with
all system elements in service to extreme conditions where portions of the system are out of
service. Factored into these assessments are load growth forecasts, operating history, seasonal
performance, resource additions or removals, new transmission asset additions, and the largest
transmission and generation contingencies. Based on these analyses, PacifiCorp identifies any
potential system deficiencies and determines the infrastructure improvements needed to reliably
meet customer loads. NERC planning standards define reliability of the interconnected bulk
electric system in terms of adequacy and security. Adequacy is the electric system’s ability to meet
aggregate electrical demand for customers at all times. Security is the electric system’s ability to
withstand sudden disturbances or unanticipated loss of system elements. Increasing transmission
capacity often requires redundant facilities to meet NERC reliability criteria.
With the increasing number of variable resources added to the grid throughout the west,
PacifiCorp’s ability to meet federal reliability directives depends increasingly on an interconnected
transmission system across the western states and on the ability to move electricity throughout the
six states served by the company. PacifiCorp’s planning process ensures that the company is
developing a portfolio that balances sufficient supply to serve all PacifiCorp customers with
sufficient resources and transmission to ensure that electricity can be moved from generation
sources to the communities served.
PacifiCorp’s interconnection to other balancing authority areas and participation in the Energy
Imbalance Market provide access to markets and promote affordable and reliable service to
PacifiCorp’s customers. Further, PacifiCorp’s transmission capacity provides benefits to
customers by increasing reliability and allowing additional generation to interconnect to serve
customer load, as well as allowing PacifiCorp flexibility in designing generating resources for
reserve capacity to comply with mandatory reliability standards.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
132
Federal Reliability Standards
The Energy policy Act of 2005 included expanded reliability-related elements of the federal
regulatory structure and directed the FERC to institute mandatory reliability standards that all users
of the bulk electric system (BES) must follow.
FERC delegated the authority to NERC to develop reliability standards to ensure the safe and
reliable operation of the BES in the United States under a variety of operating conditions. These
standards are a federal requirement and are subject to oversight and enforcement by the WECC,
NERC, and FERC. PacifiCorp is subject to compliance audits every three years and may be
required to prove compliance during other reliability initiatives or investigations.
The transmission planning standards (TPL Standards), found within the NERC transmission
reliability standards, specify that transmission system planning performance requirements to
develop a BES that will operate reliably over a broad spectrum of system conditions. They also
require study of a wide range of probable contingencies in both short-term (1-2 years) and long-
term (10 year) scenarios to ensure system reliability. Together with regional planning criteria, such
as those established by the NERC/WECC, and utility-specific planning criteria, the TPL Standards
define the minimum transmission system requirements to safely and reliably serve customers.
In addition to the TPL Standards, PacifiCorp is also required to comply with FERC Order 1000
and completed per Attachment K of the Open Access Transmission Tariff (OATT) which requires
PacifiCorp to participate in regional transmission planning processes that satisfy the transmission
planning principles of FERC Order 890 and produces a regional transmission plan. To meet this
requirement PacifiCorp is a member of the NorthernGrid regional planning association. The
development of the regional transmission plan ensures the regional reliability is maintained and/or
enhanced with the addition of new planned generation and transmission projects while reliably
serving PacifiCorp customers.
Power Flow Analyses and Planning for Generator Retirements
PacifiCorp transmission planning has performed various coal unit retirement assessments
analyzing potential impacts to the transmission system. These studies are performed outside of the
IRP process under PacifiCorp’s OATT processes which includes either 1) a customer request to
perform a consulting study; or 2) a customer request to un-designate a network resource which
then triggers a system impact and facilities study.
Past studies have found that a number of factors are critical in determining transmission system
impacts and necessary mitigation, if any. These factors include: 1) location of the unit(s) to be
retired, 2) the number of units being retired, 3) the size of the units being retired, 4) year of
retirement, and 5) location, size, and type of replacement resources, if any. Based on the location,
number of units, and size of the retired unit/s, studies can identify if the retirement results in either
thermal or voltage issues on the transmission system. A retirement of a coal unit may result in
voltage issues due to lack of reactive support that was previously provided by the retired unit/s. A
retirement may also result in thermal overload of the transmission system due to changes in the
flows post unit retirement. As such, until official notification to PacifiCorp transmission of coal
unit undesignation/retirement is received, all such coal retirement analysis is considered
preliminary.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
133
Transmission Investment to Support Reliability, Resiliency and Ongoing
Investment in Renewables
The 2021 IRP includes the 416-mile long 500-kV GWS transmission line from the Aeolus
substation near Medicine Bow, WY to Clover substation near Mona, Utah. The construction of
GWS directly connects eastern Wyoming to central Utah while enhancing the reliability
throughout the PacifiCorp-served regions. Connecting into the Mona/Clover market hub provides
additional flexibility in the use of least-cost resources from eastern Wyoming or southern Utah to
serve customer load.
The addition of GWS improves reliability in PacifiCorp served regions by relieving the stress on
the transmission system in the respective areas due to additional transmission in the area. For
example, the addition of the GWS line in Wyoming relieves the stress on the underlying 230-kV
transmission system while improving the reliability in that region. Similarly, the addition of the
GWS line in the central Utah area unloads the underlying 345-kV transmission system improving
reliability in that region. Essentially the 500-kV line brings two distant areas close to each other
while maintaining the regional reliability. Utah and the surrounding system will benefit from both
completion of the Gateway Central transmission projects as with increased transfer capability and
increased resilience during outage conditions.
In addition to the GWS, PacifiCorp is also planning to construct the 56-mile-long 230-kV D.1
transmission line from Windstar substation near Glen Rock, WY to Shirley Basin substation near
Medicine Bow, WY. This line provides a new transmission path allowing for renewable resources
development in the area. The addition of this line improves the reliability of the transmission
system during certain identified outage conditions (Dave Johnston to Amasa 230-kV outage or
Amasa – Shirley Basin 230-kV outage). Current generation interconnections with large generator
interconnection agreements (LGIA) in eastern Wyoming show that the D.1 is a prerequisite for
connecting these new resources. Information for those resources can be found on PacifiCorp’s
OASIS web site, under queue numbers; Q0713, 0783, 0784, 0785, 0801, 0802, 0807, 0835 and
0836.
PACIFICORP – 2021 IRP CHAPTER 5 – RELIABILITY AND RESILIENCY
134
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
135
CHAPTER 6 – LOAD AND RESOURCE BALANCE
CHAPTER HIGHLIGHTS
• On both a capacity and energy basis, PacifiCorp calculates load and resource balances from
existing resources, forecasted loads and sales, and reserve requirements. The capacity balance
compares existing resource capability across all hours in both the summer and winter.
• Capacity assessment across more than the coincident peak is necessary due to the evolution of
the company’s portfolio to include more wind, solar, and storage resources. Solar in particular
provides significant output during the summer coincident peak, but no output in many other
summer hours. As a result, summer risks cannot easily be identified by looking at load alone.
Instead, PacifiCorp evaluated the resources available relative to the expected load in every hour,
and the hour with the lowest resources as a percentage of the hourly load in each season
determines the planning reserve margin (PRM) achieved for that season in that year.
• The company’s load obligation is calculated based on projected load less private generation,
energy efficiency savings, and demand response, including interruptible load.
• A 2020 Private Generation Long-Term Resource Assessment (2021-2040) study prepared by
Guidehouse Consulting, Inc. produced estimates on private generation penetration levels
specific to PacifiCorp’s six-state territory. The study provided expected penetration levels by
resource type, along with high and low penetration sensitivities. PacifiCorp’s 2021 IRP load
and resource balance treats base case private generation penetration levels as a reduction in
load.
• After accounting for a minimum 13 percent PRM target, load growth, coal unit retirements from
the preferred portfolio, plus accounting for the level of potential market purchases (front office
transactions, or FOTs) assumed in the 2021 IRP, and after incorporating future energy
efficiency savings from the preferred portfolio, PacifiCorp’s system is capacity deficient (before
adding proxy resources) over both the summer and winter peaks throughout the twenty-year
planning period.
• The uncertainty in the company’s load and resource balance is increasing as PacifiCorp’s
resource portfolio and customer demand evolve over time. While PacifiCorp took steps to better
reflect the relationship between renewable resources and load in the 2021 IRP, uncertainty
remains, particularly with regard to the frequency and characteristics of the relatively extreme
conditions that are most likely to trigger reliability shortfalls.
Introduction
This chapter presents PacifiCorp’s assessment of its load and resource balance. PacifiCorp’s long-
term load forecasts (both energy and coincident peak load) for each state and the system as a whole
are summarized in Volume II, Appendix A (Load Forecast Details). The summary-level system
coincident peak is presented first, followed by a profile of PacifiCorp’s existing resources. Finally,
load and resource balances for capacity and energy are presented. These balances are composed
of a year-by-year comparison of projected loads against the existing resource base, with and
without available FOTs, assumed coal unit retirements and incremental new energy efficiency
savings from the 2021 IRP preferred portfolio, before adding new generating resources.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
136
System Coincident Peak Load Forecast
The system coincident peak load is the annual maximum hourly load on the system. The 2021 IRP
relies on PacifiCorp’s June 2020 load forecast. Table 6.1 shows the annual summer coincident
peak load stated in megawatts (MW) as reported in the capacity load and resource balance before
any load reductions from energy efficiency and private generation. The system summer peak load
grows at a compound growth rate (CAGR) of 0.85 percent over the period 2021 through 2040.
Table 6.1 – Forecasted System Summer Coincident Peak Load in Megawatts, Before Energy
Efficiency and Private Generation (MW)
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
System
10,447
10,646
10,824
10,947
11,089
11,022
11,107
11,227
11,338
11,470
2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
System
11,615
11,748
11,879
12,005
12,141
12,094
12,206
12,345
12,148
12,270
Existing Resources
Thermal Plants
Table 6.2 lists PacifiCorp’s existing coal-fueled plants and Table 6.3 lists existing natural-gas-
fueled plants. The “Retirement Year” reflects the year a resource retires or converts to natural gas
as reflected in the preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
137
Table 6.2 – Coal-Fueled Plants
Plant
PacifiCorp
Percentage
Share (%)
State Gas Conversion/
Retirement Year
Nameplate
Capacity (MW)
Colstrip 3 10 Montana 2025 74
Colstrip 4 10 Montana 2025 74
Craig 1 19 Colorado 2025 82
Craig 2 19 Colorado 2028 79
Dave Johnston 1 100 Wyoming 2027 99
Dave Johnston 2 100 Wyoming 2027 106
Dave Johnston 3 100 Wyoming 2027 220
Dave Johnston 4 100 Wyoming 2027 330
Hayden 1 24 Colorado 2028 44
Hayden 2 13 Colorado 2027 33
Hunter 1 94 Utah 2042 418
Hunter 2 60 Utah 2042 269
Hunter 3 100 Utah 2042 471
Huntington 1 100 Utah 2036 459
Huntington 2 100 Utah 2036 450
Jim Bridger 1 67 Wyoming 2024/2037 354
Jim Bridger 2 67 Wyoming 2024/2037 359
Jim Bridger 3 67 Wyoming 2037 349
Jim Bridger 4 67 Wyoming 2037 351
Naughton 1 100 Wyoming 2025 156
Naughton 2 100 Wyoming 2025 201
Wyodak 80 Wyoming 2039 268
TOTAL – Coal 5,246
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
138
Table 6.3 – Natural-Gas-Fueled Plants
Natural Gas -fueled
PacifiCorp
Percentage
Share (%)
State Assumed End of
Life Year
Nameplate
Capacity (MW)
Chehalis 100 Washington 2043 491
Currant Creek 100 Utah 2045 545
Gadsby 1 100 Utah 2032 64
Gadsby 2 100 Utah 2032 69
Gadsby 3 100 Utah 2032 105
Gadsby 4 100 Utah 2032 40
Gadsby 5 100 Utah 2032 40
Gadsby 6 100 Utah 2032 40
Hermiston 100 Oregon 2036 234
Lake Side 1 100 Utah 2047 551
Lake Side 2 100 Utah 2054 644
Naughton 3 100 Wyoming 2029 247
TOTAL – Natural Gas 3,070
Renewable Resources
Wind
PacifiCorp either owns or purchases under contract 3,811 MW of wind resources.
Table 6.4 shows existing wind facilities owned by PacifiCorp, while Table 6.5 shows existing
wind power-purchase agreements (PPAs).
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
139
Table 6.4 – Owned Wind Resources
Utility-Owned Wind Projects State Capacity (MW)
Cedar Springs II WY 200
Dunlap 1 WY 111
Ekola Flats 1 WY 250
Foote Creek I WY 41
Glenrock I WY 99
Glenrock III WY 39
Goodnoe Hills East WA 94
High Plains WY 99
Leaning Juniper OR 101
Marengo I WA 156
Marengo II WA 78
McFadden Ridge 1 WY 29
Pryor Mountain MT 240
Rolling Hills WY 99
Seven Mile Hill WY 99
Seven Mile Hill II WY 20
TB Flats WY 500
TOTAL – Owned Wind 2,255
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
140
Table 6.5 – Non-Owned Wind Resources
Power Purchase Agreements /
Exchanges PPA or QF State Capacity (MW)
Big Top ORWF QF OR 2.0
BLM Rawlins QF WY 0.1
Butter Creek Power ORWF QF OR 5.0
Cedar Springs III PPA WY 133.0
Cedar Springs PPA PPA WY 199.0
Chopin QF OR 10.0
Combine Hills PPA OR 41.0
Four Corners ORWF QF OR 10.0
Four Mile Canyon ORWF QF OR 10.0
J Bar Ranch QF WY 0.1
Latigo QF UT 60.0
Meadow Creek Project - North Point QF ID 80.0
Meadow Creek Project Five Pine QF ID 40.0
Mountain Power I QF WY 61.0
Mountain Power II QF WY 80.0
Orchard Wind 1 QF OR 10.0
Orchard Wind 2 QF OR 10.0
Orchard Wind 3 QF OR 10.0
Orchard Wind 4 QF OR 10.0
Oregon Trail ORWF QF OR 10.0
Pacific Canyon ORWF QF OR 8.0
Pioneer Park I QF WY 80.0
Power County Park North QF ID 23.0
Power County Park South QF ID 23.0
Rock River I PPA WY 50.0
Sand Ranch ORWF QF OR 10.0
Spanish Fork Park 2 QF UT 19.0
Stateline Exchange WA 175.0
Three Buttes Power (Duke) PPA WY 99.0
Three Mile Canyon QF OR 10.0
Tooele QF UT 1.5
Tooele QF UT 1.7
Top of the World PPA WY 200.0
Wagon Trail ORWF QF OR 3.0
Ward Butte ORWF QF OR 7.0
Wolverine Creek PPA ID 65.0
TOTAL - Purchased Wind 1,556.4
Solar
PacifiCorp has a total of 73 solar projects under contract representing 2,340 MW of nameplate
capacity.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
141
Table 6.6 – Non-Owned Solar Resources
Power Purchase Agreements / Exchanges PPA or QF State Capacity (MW)
Adams QF OR 10.0
Appaloosa Solar IA PPA UT 120.0
Appaloosa Solar IB PPA UT 80.0
BC Solar QF OR 8.0
Bear Creek QF OR 10.0
Beryl QF UT 3.0
Black Cap PPA OR 2.0
Bly QF OR 8.0
Buckhorn QF UT 3.0
Captain Jack QF OR 3.0
Castle Solar (Retail 1) PPA UT 20.0
Castle Solar (Retail 2) PPA UT 20.0
Cedar Valley QF UT 3.0
Chiloquin QF OR 10.0
Cove Mountain PPA UT 58.0
Cove Mtn II PPA UT 122.0
eBay QF UT 0.5
Elbe QF OR 10.0
Elektron Solar 20Yr PPA UT 10.0
Elektron Solar 25Yr PPA UT 70.0
Enterprise QF UT 80.0
Escalante I QF UT 80.0
Escalante II QF UT 80.0
Escalante III QF UT 80.0
Granite Mountain - East QF UT 80.0
Granite Mountain - West QF UT 50.0
Granite Peak QF UT 3.0
Graphite PPA UT 80.0
Greenville QF UT 2.0
Horseshoe Solar PPA UT 75.0
Hunter PPA UT 100.0
Iron Springs QF UT 80.0
Klamath Falls Solar 1 QF UT 1.0
Klamath Falls Solar 2 QF UT 3.0
Laho QF UT 3.0
Milford PPA UT 99.0
Milford2 QF UT 3.0
Milford Flat QF UT 3.0
Millican Solar Energy, LLC PPA OR 60.0
NW2_Neff QF OR 10.0
NW4_Bonanza QF OR 6.0
NW7_EaglePoint QF OR 10.0
NW9_Pendleton QF OR 6.0
Old Mill PPA OR 5.0
OR2_AgateBay QF OR 10.0
OR3_TurkeyHill QF OR 10.0
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
142
Power Purchase Agreements / Exchanges PPA or QF State Capacity (MW)
OR5_Merrill QF OR 8.0
OR6_Lakeview QF OR 10.0
OR8_Dairy QF OR 10.0
OSLH Collier QF OR 10.0
Pavant QF UT 50.0
Pavant II LLC QF UT 50.0
Pavant III LLC PPA UT 20.0
Prineville PPA OR 40.0
Quichapa I QF UT 3.0
Quichapa II QF UT 3.0
Quichapa III QF UT 3.0
Red Hills QF UT 80.0
Rocket PPA UT 80.0
Sage I QF WY 20.0
Sage II QF WY 20.0
Sage III QF WY 18.0
Sigurd PPA UT 80.0
Skysol QF OR 55.0
Solarize Rogue LLC (OR Community Solar) QF OR 0.1
South Milford QF UT 3.0
SunE1 QF UT 3.0
SunE2 QF UT 3.0
SunE3 QF UT 3.0
Sweetwater QF WY 80.0
Three Peaks QF UT 80.0
Tumbleweed QF OR 10.0
Woodline QF OR 8.0
TOTAL – Purchased Solar 2339.6
Geothermal
PacifiCorp owns and operates the Blundell geothermal plant in Utah, which uses naturally created
steam to generate electricity. The plant has a net generation capacity of 34 MW. Blundell is a fully
renewable, zero-discharge facility. The bottoming cycle, which increased the output by 11 MW,
was completed at the end of 2007. The Oregon Institute of Technology added a new small
qualifying facility (QF) using geothermal technologies to produce renewable power for the campus
that is rated at 0.28 MW. PacifiCorp also has a power purchase agreement with the 20 MW Soda
Lake geothermal project located in Nevada, which became operational in November 2019.
Biomass/Biogas
PacifiCorp has biomass/biogas agreements with 12 projects totaling approximately 80 MW of
nameplate capacity.
Renewables Net Metering
Table 6.7 provides a breakdown of net metered capacity and customer counts from data collected
as of August 16, 2021.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
143
Table 6.7 – Net Metering Customers and Capacity
Fuel Solar Wind Gas1/ Hydro Mixed2/
Nameplate (kW) 570,106 853 884 965 1,217
Capacity (percentage
of total) 99.32% 0.15% 0.15% 0.17% 0.21%
Number of customers 65,582 194 4 21 62
Customer (percentage
of total) 99.57% 0.29% 0.01% 0.03% 0.09%
1/ Gas includes: biofuel, waste gas, and fuel cells
2/ Mixed includes projects with multiple technologies, one project is solar and biogas and the others are solar
and wind
Hydroelectric Generation
PacifiCorp owns 1,135 MW of hydroelectric generation capacity and purchases the output from
89 MW of other hydroelectric resources. These resources provide operational benefits such as
flexible generation, spinning reserves and voltage control. PacifiCorp-owned hydroelectric plants
are located in California, Idaho, Montana, Oregon, Washington, Wyoming, and Utah.
The amount of electricity PacifiCorp is able to generate or purchase from hydroelectric plants is
dependent upon a number of factors, including the water content of snowpack accumulations in
the mountains upstream of its hydroelectric facilities and the amount of precipitation that falls in
its watershed. Operational limitations of the hydroelectric facilities are affected by varying water
levels, licensing requirements for fish and aquatic habitat, and flood control, which lead to load
and resource balance capacity values that are different from net facility capacity ratings.
Hydroelectric purchases are categorized into two groups, as shown in Table 6.8.
Table 6.8 – Hydroelectric Contracts
Hydroelectric Contracts L&R Balance Capacity at
System Peak (MW) by Load and Resource Balance Category
Hydroelectric 193
Qualifying Facilities - Hydroelectric 88
Total Contracted Hydroelectric
Resources 280
Table 6.9 provides the capacity for each of PacifiCorp’s owned hydroelectric generation facilities.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
144
Table 6.9 – PacifiCorp Owned Hydroelectric Generation Facilities –Capacities
Plant River System State Capacity (MW)
East
Ashton Bear UT 8
Cutler Bear UT 30
Grace Bear UT 33
Lifton Bear UT 1
Oneida Bear UT 30
Soda Bear UT 14
PCM - North* - UT 9
PCM - South** - UT 1
West
Bend - OR 4
Bigfork Lewis MT 4
Swift 1 Lewis WA 240
Swift 2 Lewis WA 70
Yale Lewis WA 134
Merwin Lewis WA 136
Copco 1 Klamath OR/CA 20
Copco 2 Klamath OR/CA 27
Iron Gate Klamath OR/CA 18
JC Boyle Klamath OR/CA 98
Clear Water 1 Umpqua OR 15
Clear Water 2 Umpqua OR 26
Fish Creek Umpqua OR 11
Lemolo 1 Umpqua OR 29
Lemolo 2 Umpqua OR 33
Slide Creek Umpqua OR 18
Soda Springs Umpqua OR 11
Toketee Rogue OR 43
Eagle Point Rogue OR 3
Prospect 1 Rogue OR 5
Prospect 2 Rogue OR 36
Prospect 3 Rogue OR 7
Prospect 4 Rogue OR 1
Fall Creek - OR 4
Wallowa Falls - OR 1
TOTAL – Hydroelectric before
contracts 1118
Hydroelectric Contracts 280
TOTAL – Hydroelectric 1398
1/ Cowlitz County PUD owns Swift No. 2, and is operated in coordination with the other projects by PacifiCorp
2/ Includes Bend, Fall Creek, and Wallowa Falls
3/ Includes Ashton, Paris, Pioneer, Weber, Stairs, Granite, Snake Creek, Olmstead, Fountain Green, Veyo, Sand Cove,
Viva Naughton, and Gunlock
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
145
Demand-Side Management
For resource planning purposes, PacifiCorp classifies demand-side management (DSM) resources
into four categories. These resources are captured through programmatic efforts that promote
efficient electricity use through various intervention strategies, aimed at changing energy use
during peak periods (load control), timing (price response and load shifting), intensity (energy
efficiency), or behaviors (education and information). The four categories include:
• Class 1 DSM (Demand Response)—Resources from fully dispatchable or scheduled
firm capacity product offerings/programs: Demand Response programs are those for
which capacity savings occur as a result of active company control or advanced scheduling.
Once customers agree to participate in these programs, the timing and persistence of the
load reduction is involuntary on their part within the agreed upon limits and parameters of
the program. Program examples include residential and small commercial central air
conditioner load control programs that are dispatchable, and irrigation load management
and interruptible or curtailment programs (which may be dispatchable or scheduled firm,
depending on the particular program design or event noticing requirements). Savings are
typically only sustained for the duration of the event and there may also be return energy
associated with the program.
• Class 2 DSM (Energy Efficiency)—Resources from non-dispatchable, firm energy
and capacity product offerings/programs: Energy Efficiency programs are energy and
related capacity savings which are achieved through facilitation of technological
advancements in equipment, appliances, structures, or repeatable and predictable voluntary
actions on a customer’s part to manage the energy use at their business or home. These
programs generally provide financial incentives or services to customers to improve the
efficiency of existing or new residential or commercial buildings through: (1) the
installation of more efficient equipment, such as lighting, motors, air conditioners, or
appliances; (2) increasing building efficiency, such as improved insulation levels or
windows; or (3) behavioral modifications, such as strategic energy management efforts at
business or home energy reports for residential customers. The savings are considered firm
over the life of the improvement or customer action.
• Class 3 DSM (Price Response and Load Shifting)—Resources from price-responsive
energy and capacity product offerings/programs: Price response and load shifting
programs seek to achieve short-duration (hour by hour) energy and capacity savings from
actions taken by customers voluntarily, based on a financial incentive or signal. As a result
of their voluntary nature, participation tends to be low and savings are less predictable,
making these resources less suitable to incorporate into resource planning, at least until
their size and customer behavior profile provide sufficient information needed to model
and plan for a reliable and predictable impact. The impacts of these resources may not be
explicitly considered in the resource planning process; however, they are captured naturally
in long-term load growth patterns and forecasts. Program examples include time-of-use
pricing plans, critical peak pricing plans, and inverted block tariff designs. Savings are
typically only sustained for the duration of the incentive offering and, in many cases, loads
tend to be shifted rather than being avoided.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
146
• Class 4 DSM (Education and Information)—Non-incented behavioral-based savings
achieved through broad energy education and communication efforts: Education and
Information programs promote reductions in energy or capacity usage through broad-based
energy education and communication efforts. The program objectives are to help customers
better understand how to manage their energy usage through no-cost actions such as
conservative thermostat settings and turning off appliances, equipment and lights when not
in use. These programs are also used to increase customer awareness of additional actions
they might take to save energy and the service and financial tools available to assist them.
These programs help foster an understanding and appreciation of why utilities seek
customer participation in other programs. Similar to price response and load shifting
resources, the impacts of these programs may not be explicitly considered in the resource
planning process; however, they are captured naturally in long-term load growth patterns
and forecasts. Program examples include company brochures with energy savings tips,
customer newsletters focusing on energy efficiency, case studies of customer energy
efficiency projects, and public education and awareness programs.
PacifiCorp has been operating successful DSM programs since the late 1970s. Over time,
PacifiCorp’s DSM pursuits have expanded to new heights in terms of investment level, state
presence, breadth of DSM resources pursued and resource planning considerations. Work
continues on the expansion of cost-effective program portfolios and savings opportunities in all
states while at the same time adapting programs and measure baselines to reflect the impacts of
advancing state and federal energy codes and standards. In Oregon, PacifiCorp continues to work
closely with the Energy Trust of Oregon to help identify additional resource opportunities, improve
delivery and communication coordination, ensure adequate funding, and provide company support
in pursuit of DSM resource targets.
Table 6.10 summarizes PacifiCorp’s existing DSM programs, their assumed impact, and how they
are treated for purposes of incremental resource planning. Note that since incremental energy
efficiency is determined as an outcome of resource portfolio modeling and is characterized as a
new resource in the preferred portfolio, existing energy efficiency in Table 6.10 is shown as having
zero MW.1 For a summary of current DSM program offerings in each state, refer to Volume II,
Appendix D (Demand-Side Management Resources).
1 The historical effects of previous Class 2 DSM savings are captured in the load forecast before the modeling for new
Class 2 DSM.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
147
Table 6.10 – Existing DSM Resource Summary
Program
Class Description Energy Savings or Capacity at
Generator
Included as
Existing Resources for
2021-2040 Period
1
Residential/small
commercial air
conditioner load control
124 MW summer peak Yes.
Irrigation load
management 205 MW summer peak Yes.
Interruptible contracts 191 MW summer peak Yes.
2 PacifiCorp and Energy
Trust of Oregon
programs
0 MW1/
No. Class 2 DSM programs are
modeled as resource options in the
portfolio development process and
included in the preferred portfolio.
3
Time-based pricing
Energy and capacity impacts are
not available/measured
No. Historical savings from
customer responses to pricing
signals are reflected in the load
forecast.
Inverted rate pricing
Energy and capacity impacts are
not available/measured
No. Historical savings from
customer response to pricing
structure is reflected in load
forecast.
4 Energy education Energy and capacity impacts are
not available/measured
No. Historical savings from
customer participation are reflected
in the load forecast.
1/ Due to the timing of the 2021 IRP load forecast, there is a small amount (68 MW) of existing Class 2 DSM in Table 6.12 (System
Capacity Loads and Resources without Resource Additions).
Private Generation
For the 2021 IRP, PacifiCorp contracted with Guidehouse to update the assessment of private
generation (PG) penetration performed for the 2021 IRP with new market and incentive
developments. The study provided a forecast of adoption for each private generation resource in
each of the six states served by PacifiCorp. Specific technologies studied included solar
photovoltaic, small-scale wind, small-scale hydro, and combined heat and power (CHP) for both
reciprocating engines and micro-turbines.
Guidehouse estimates approximately 1.74 gigawatts (GW) of PG capacity will be installed in
PacifiCorp’s territory from 2021-2040 in the base case scenario. As shown in Figure 6.1, the low
and high scenarios project a cumulative installed capacity of 0.82 GW and 2.66 GW by 2040,
respectively. The main drivers between the different scenarios include variation in technology
costs, system performance, and electricity rate assumptions. The Guidehouse study identifies
expected levels of customer-sited private generation, which is applied as a reduction to
PacifiCorp’s forecasted load for IRP modeling purposes.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
148
Figure 6.1 – Private Generation Market Penetration (MWAC), 2021-2040
Power-Purchase Agreements
PacifiCorp obtains the remainder of its capacity and energy requirements through long-term firm
contracts, short-term firm contracts, and spot market purchases. Figure 6.2 presents the contract
capacity in place for 2021 through 2040. As shown, major capacity reductions in wind purchases
and QF contracts occur. For planning purposes, PacifiCorp assumes interruptible load contracts
are extended through the end of the IRP study period. The renewable wind contracts are shown at
their capacity contribution levels.
Figure 6.2 – Contract Capacity in the 2021 IRP Summer Load and Resource Balance
-400
-200
0
200
400
600
800
1,000
1,200
1,400
MW
Sale Purchase Qualifying Facilities Hydro
Wind Solar Demand Response Net Position
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
149
Load and Resource Balance
Capacity and Energy Balance Overview
The purpose of the load and resource balance is to compare annual obligations with the annual
capability of PacifiCorp’s existing resources, without new generating resource additions. This is
done with two views of the system, the capacity balance and energy balance.
The capacity balance compares generating capability to load obligations across both summer and
winter. In the past, the coincident peak load hour was almost always the hour with the lowest
margin, because the available resource output was comparable in the peak load hour and in other
hours. With the significant penetration of solar resource in PacifiCorp’s portfolio, the hour with
the lowest margin is no longer readily identifiable from load alone, as solar resources have high
availability during the peak load hour but no availability a few hours later when loads are slightly
lower. Wind, storage, hydro, and other resources further complicate the calculation. In light of this,
for the 2021 IRP, PacifiCorp evaluated the balance of generating capability and load obligations
not just during the coincident peak load hour, but across all hours, to identify the winter and
summer hours in each year with the lowest margin as a percentage of load. Under this method,
the reported planning reserve margin is necessarily met in the coincident peak load hour, but the
hour with the lowest margin generally coincides with a period of relatively high load and relatively
low renewable resource output.
For reporting purposes, the capacity balance summarized in this chapter is developed by first
reducing the hourly system load by hourly private generation projections to determine the net
system coincident peak load for each of the first ten years (2021-2030) of the planning horizon.
Interruptible load programs, existing load reduction DSM programs, and new load reduction DSM
programs from the preferred portfolio at the time of the net system coincident peak are further
netted from the peak load forecast to compute the annual peak-hour obligation. Then the annual
firm capacity availability of the existing resources, reflecting assumed coal unit retirements from
the preferred portfolio, is determined. The annual resource deficit or surplus is then computed by
multiplying the obligation by the capacity reserve margin (13% for the 2021 IRP) and then
subtracting the result from existing resources. This view is presented both without and with
uncommitted FOTs.
The energy balance shows the average monthly surplus or deficit of energy over the first ten years
of the planning horizon (2021-2030). The average obligation (load less existing DSM programs,
new DSM programs from the preferred portfolio, and projected private generation) is computed
and subtracted from the average existing resource availability for each month. The usefulness of
the energy balance is limited because it does not address the cost of the available energy. The
economics of adding resources to the system to meet both capacity and energy needs are addressed
during the resource portfolio development process described in Chapter 8 (Modeling and Portfolio
Evaluation Approach).
Load and Resource Balance Components
The capacity and energy balances make use of the same load and resource components in their
calculations. The main component categories consist of the following: resources, obligation,
reserves, position, and available FOTs.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
150
Under the calculations, there are negative values in the table in both the resource and obligation
sections. This is consistent with how resource categories are represented in portfolio modeling.
The resource categories include resources by type—thermal, hydroelectric, renewable, QFs,
purchases, existing demand response, and sales. Categories in the obligation section include load
(net of private generation), interruptible contracts, existing energy efficiency, and new energy
efficiency from the preferred portfolio.
Existing Resources
A description of the resource categories follows:
Thermal
This category includes all thermal plants that are wholly owned or partially owned by PacifiCorp.
The capacity balance counts these plants at their expected availability (after derating for forced
outages and maintenance) weighted based on the expected timing of resource shortfalls during
summer or winter periods. The energy balance also counts them at expected availability but
includes all hours in the year. This includes the existing fleet of coal-fueled units, and six natural-
gas-fueled plants. Presently, these thermal resources account for roughly two thirds of the firm
capacity available in the PacifiCorp system.
All Other Resources
The capacity contribution of wind and solar resources, represented as a percentage of resource
capacity, is a measure of the ability for these resources to reliably meet demand. During the 2021
IRP, PacifiCorp identified that capacity contribution values for wind and solar would vary based
on the penetration levels of these resources, as well as the composition of the rest of a portfolio, in
particular the level of storage capability. To account for these effects, PacifiCorp performed a
reliability analysis on every portfolio that was developed to ensure that the combination of
resources achieved a targeted level of reliability. PacifiCorp also recognizes that other resources
whose expected output varies over the course of each year are also impacted by portfolio changes.
For the purpose of reporting the capacity contribution of all other resources in the load and resource
balance, PacifiCorp first calculated the contribution of long-duration dispatchable resources in the
portfolio, using the methodologies described above. The remaining capacity in the load and
resource balance, up to PacifiCorp’s thirteen percent planning reserve margin, is attributable to the
rest of the resources in PacifiCorp’s portfolio. This remaining capacity was allocated based on
each resource’s hourly available generation during the hours in each winter or summer season
when load exceeded the availability of long-duration dispatchable resources, and was allocated
pro-rata among all resources delivering during such hours. It should be noted that while allocation
of capacity among resources as described in this section is helpful for presenting a load and
resource balance, the allocation to specific resources has no bearing on the reliability or economics
of the preferred portfolio, which reflects the coordinated dispatch of all available resources in every
hour of the year. The economics of resource additions are more closely aligned with marginal or
“last-in” capacity contribution estimates, which are generally lower for resources whose output is
positively correlated with other resources already present in the portfolio. For estimates of
marginal capacity contribution values, please refer to Volume II, Appendix K (Capacity
Contribution).
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
151
Sales
Contracts for the sale of firm capacity and energy are treated the same as all other resources, except
that they have a negative capacity value. The energy balance counts them by expected model
dispatch.
Obligation
The obligation is the total electricity demand that PacifiCorp must serve, consisting of forecasted
retail load less private generation, existing energy efficiency, new energy efficiency from the
preferred portfolio, existing demand response, and interruptible contracts. The following are
descriptions of each of these components:
Load Net of Private Generation
The largest component of the obligation is retail load. In the 2021 IRP, the hourly retail load at a
location is first reduced by hourly private generation at the same location. The system coincident
peak is determined by summing the net loads for all locations (topology bubbles with loads) and
then finding the highest hourly system load by year and season. Loads reported by east and west
BAAs thus reflect loads at the time of PacifiCorp’s coincident system summer and winter peaks.
The energy balance counts the average load on a monthly basis. For simplicity, load net of private
generation is referred to as load in the following sections.
Energy Efficiency (Class 2 DSM)
An adjustment is made to load to remove the projected embedded energy efficiency as a reduction
to load. Due to timing issues with the vintage of the load forecast, there is a level of 2020 energy
efficiency that is not incorporated in the forecast. The 2020 energy efficiency forecast (73 MW)
has been accounted for by adding an existing energy efficiency resource in the load and resource
balance. The energy efficiency line also includes the selected energy efficiency from the 2021 IRP
preferred portfolio. Figure 6.3 shows the energy efficiency for the east and west control areas in
the 2021 IRP preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
152
Figure 6.3 – Energy Efficiency Peak Contribution in Summer Capacity Load and Resource
Balance (reduction to load, in MW)
Demand Response (Class 1 DSM)
Existing demand response program capacity is categorized as a reduction to peak load. Also
included in the demand response category are interruptible contracts. PacifiCorp has had
interruptible contracts for approximately 177 MW of load interruption capability for many years.
These contracts are a key aspect of the retail service provided to the associated customers, and
absent these contracts their demand would likely be different from that included in the load
forecast. To maintain an alignment with the load forecast, these contracts are assumed to continue
indefinitely under their current structure.
Planning Reserve Margin
Planning reserve margin (PRM) represents an incremental capacity requirement, applied as an
increase to the obligation to ensure that there will be sufficient capacity available on the system to
manage uncertain events (i.e., weather, outages) and known requirements (i.e., operating reserves).
Position
The position is the resource surplus or deficit after subtracting obligation plus required reserves
from total resources. While similar, the position calculation is slightly different for the capacity
and energy views of the load and resource balance. Thus, the position calculation for each of the
views will be presented in their respective sections.
Capacity Balance Determination
Methodology
The capacity balance is developed by first determining the system coincident peak load for each
of the first ten years of the planning horizon. Then the annual firm-capacity availability of the
existing resources is determined for each of these annual system summer and winter peak periods,
as applicable, and summed as follows:
Existing Resources = Thermal + Hydro + Renewable + Firm Purchases + Qualifying
Facilities – Firm Sales
(1,800)
(1,600)
(1,400)
(1,200)
(1,000)
(800)
(600)
(400)
(200)
0
East West
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
153
The peak load, interruptible contracts, existing Energy Efficiency, and new Energy Efficiency
from the preferred portfolio are netted together for each of the annual system summer and winter
peaks, as applicable, to compute the annual peak obligation:
Obligation = Load – Demand Response – Interruptible Contracts – New and Existing
Energy Efficiency
The amount of reserves to be added to the obligation is then calculated. This is accomplished by
the net system obligation calculated above multiplied by the 13 percent PRM adopted for the 2021
IRP. The formula for this calculation is:
Planning Reserves = Obligation x PRM
Finally, the annual capacity position is derived by adding the computed reserves to the obligation,
and then subtracting this amount from existing resources, including available FOTs, as shown in
the following formula:
Capacity Position = (Existing Resources + Available FOTs) – (Obligation + Planning
Reserves)
Capacity Balance Results
Table 6.11 and Table 6.12 show the annual capacity balances and component line items for the
summer peak and winter peak, respectively, using a target PRM of 13 percent to calculate the
planning reserve amount. Balances for PacifiCorp’s system as well as the east and west control
areas are shown. While east and west control area balances are broken out separately, the
PacifiCorp system is planned for and dispatched on a system basis. Also note that new QF wind
and solar projects listed earlier in the chapter are reported under the QF line item rather than the
renewables line item.
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
154
Table 6.11 -- Summer Peak – System Capacity Loads and Resources without Resource
Additions
East
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Thermal 5,478 5,466 5,429 5,425 5,459 5,044 5,002 4,293 4,182 3,953
Hydroelectric 86 86 85 69 56 52 51 56 57 52
Renewable 668 690 815 912 709 676 661 718 743 676
Purchase 193 197 202 195 138 141 142 148 143 147
Qualifying Facilities 537 521 515 488 396 357 344 364 372 346
Sale (20)(20)(20)0 0 0 0 0 0 0
East Existing Resources 6,943 6,940 7,026 7,090 6,758 6,271 6,201 5,580 5,498 5,174
Load 7,096 7,246 7,380 7,475 7,583 7,492 7,550 7,643 7,728 7,833
Private Generation (51)(72)(81)(84)(87)(90)(96)(106)(119)(136)
Existing - Demand Response (520)(538)(558)(538)(583)(592)(598)(623)(604)(619)
Existing - Energy Efficiency (43)(45)(46)(45)(49)(49)(50)(52)(50)(52)
New Energy Efficiency (48)(95)(149)(199)(280)(349)(429)(529)(597)(698)
East Total obligation 6,434 6,495 6,546 6,609 6,586 6,411 6,377 6,333 6,358 6,328
Capacity Reserve Margin (13%)836 844 851 859 856 833 829 823 827 823
East Obligation + Reserves 7,271 7,340 7,397 7,468 7,442 7,244 7,206 7,157 7,185 7,151
East Position (327)(400)(371)(378)(684)(974)(1,005)(1,577)(1,687)(1,977)
Available Front Office Transactions 0 0 0 0 0 0 0 0 0 0
West
Thermal 2,139 2,165 2,168 2,144 2,149 2,019 2,015 2,014 2,036 2,035
Hydroelectric 577 567 521 508 407 386 380 420 423 390
Renewable 194 177 185 184 148 139 140 144 144 134
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 158 153 145 141 116 105 87 91 79 71
Sale (109)(76)(76)(54)(44)(42)(41)(44)(44)(41)
West Existing Resources 2,961 2,986 2,945 2,924 2,777 2,608 2,582 2,626 2,638 2,591
Load 3,351 3,400 3,443 3,472 3,506 3,530 3,557 3,584 3,610 3,638
Private Generation (23)(39)(51)(56)(60)(65)(71)(78)(86)(96)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
Existing - Energy Efficiency (24)(25)(26)(25)(27)(28)(28)(29)(28)(29)
New Energy Efficiency (26)(51)(76)(95)(126)(152)(178)(213)(234)(266)
West Total obligation 3,278 3,286 3,290 3,297 3,293 3,286 3,280 3,264 3,262 3,247
Capacity Reserve Margin (13%)426 427 428 429 428 427 426 424 424 422
West Obligation + Reserves 3,704 3,713 3,718 3,725 3,721 3,713 3,707 3,689 3,686 3,669
West Position (743)(726)(773)(801)(943)(1,105)(1,125)(1,063)(1,048)(1,078)
Available Front Office Transactions 500 500 500 500 500 500 500 500 500 500
System
Total Resources 9,904 9,927 9,971 10,014 9,535 8,879 8,783 8,206 8,136 7,764
Obligation 9,712 9,781 9,836 9,906 9,878 9,697 9,657 9,598 9,620 9,575
Planning Reserves (13%)1,263 1,272 1,279 1,288 1,284 1,261 1,255 1,248 1,251 1,245
Obligation + Reserves 10,975 11,053 11,115 11,193 11,162 10,958 10,912 10,845 10,871 10,820
System Position (1,071)(1,126)(1,144)(1,179)(1,627)(2,079)(2,130)(2,639)(2,735)(3,056)
Available Front Office Transactions 500 500 500 500 500 500 500 500 500 500
Uncomitted FOTs to meet remaining Need 1,071 1,126 1,144 500 500 500 500 500 500 500
Net Surplus/(Deficit)0 0 0 (679)(1,127)(1,579)(1,630)(2,139)(2,235)(2,556)
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
155
Table 6.12 (cont.) – Summer Peak System Capacity Loads and Resources without Resource
Additions
East
2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Thermal 3,945 3,955 3,629 3,607 3,613 3,613 2,765 2,759 2,757 2,491
Hydroelectric 47 43 40 40 40 40 57 63 64 58
Renewable 582 525 471 465 465 465 587 595 586 539
Purchase 146 157 145 144 142 144 138 137 136 138
Qualifying Facilities 310 266 220 204 192 162 34 29 12 0
Sale 0 0 0 0 0 0 0 0 0 0
East Existing Resources 5,031 4,947 4,505 4,459 4,452 4,424 3,582 3,583 3,555 3,226
Load 7,938 8,041 8,138 8,232 8,336 8,343 8,413 8,520 8,390 8,488
Private Generation (160)(189)(218)(251)(291)(181)(205)(230)(119)(132)
Existing - Demand Response (615)(660)(609)(604)(598)(607)(582)(579)(574)(581)
Existing - Energy Efficiency (51)(55)(51)(50)(50)(51)(48)(48)(48)(48)
New Energy Efficiency (773)(906)(907)(962)(1,009)(1,039)(1,052)(1,111)(1,170)(1,248)
East Total obligation 6,339 6,231 6,353 6,364 6,388 6,465 6,526 6,552 6,478 6,478
Capacity Reserve Margin (13%)824 810 826 827 830 840 848 852 842 842
East Obligation + Reserves 7,163 7,041 7,179 7,192 7,219 7,306 7,374 7,404 7,320 7,321
East Position (2,132)(2,094)(2,674)(2,732)(2,767)(2,882)(3,792)(3,821)(3,766)(4,094)
Available Front Office Transactions 0 0 0 0 0 0 0 0 0 0
West
Thermal 2,027 2,021 2,024 2,023 2,023 2,031 1,807 456 456 456
Hydroelectric 355 323 301 299 296 298 435 483 485 446
Renewable 117 108 105 92 92 100 129 142 143 128
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 64 49 45 39 37 38 25 22 9 6
Sale (38)(34)(32)(32)(32)(31)(34)(32)(32)(28)
West Existing Resources 2,527 2,468 2,443 2,422 2,417 2,435 2,364 1,072 1,061 1,009
Load 3,676 3,707 3,740 3,773 3,805 3,752 3,793 3,825 3,758 3,782
Private Generation (118)(158)(205)(258)(316)(263)(305)(351)(195)(225)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
Existing - Energy Efficiency (29)(31)(28)(28)(28)(28)(27)(27)(27)(27)
New Energy Efficiency (289)(334)(329)(348)(366)(388)(386)(410)(409)(414)
West Total obligation 3,241 3,184 3,178 3,138 3,095 3,073 3,075 3,038 3,127 3,115
Capacity Reserve Margin (13%)421 414 413 408 402 399 400 395 407 405
East Obligation + Reserves 132 80 84 60 36 12 14 (15)(2)(9)
East Position 2,395 2,388 2,359 2,362 2,381 2,423 2,350 1,087 1,064 1,018
Available Front Office Transactions 500 500 500 500 500 500 500 500 500 500
System
Total Resources 7,558 7,415 6,948 6,881 6,869 6,859 5,946 4,655 4,616 4,235
Obligation 9,580 9,415 9,531 9,502 9,483 9,538 9,601 9,590 9,606 9,593
Planning Reserves (13%)1,245 1,224 1,239 1,235 1,233 1,240 1,248 1,247 1,249 1,247
Obligation + Reserves 10,825 10,639 10,770 10,737 10,716 10,778 10,849 10,836 10,854 10,841
System Position (3,267)(3,225)(3,821)(3,856)(3,847)(3,919)(4,903)(6,182)(6,239)(6,606)
Available Front Office Transactions 500 500 500 500 500 500 500 500 500 500
Uncomitted FOTs to meet remaining Need 500 500 500 500 500 500 500 500 500 500
Net Surplus/(Deficit)(2,767)(2,725)(3,321)(3,356)(3,347)(3,419)(4,403)(5,682)(5,739)(6,106)
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
156
Table 6.12 – Winter Peak System Capacity Loads and Resources without Resource
Additions
East
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Thermal 5,478 5,383 5,540 5,364 5,550 5,057 5,143 4,229 4,140 3,835
Hydroelectric 50 52 46 43 30 31 29 39 42 42
Renewable 765 929 885 860 546 676 639 796 843 802
Purchase 173 169 167 158 115 116 120 125 110 113
Qualifying Facilities 204 225 192 213 105 136 123 208 227 233
Sale (16)(17)(15)0 0 0 0 0 0 0
East Existing Resources 6,654 6,741 6,815 6,638 6,346 6,016 6,054 5,397 5,362 5,025
Load 5,538 5,678 5,800 5,860 5,943 5,874 5,915 6,008 6,081 6,161
Private Generation (0)(1)(2)(2)(3)(4)(5)(6)(7)(8)
Existing - Demand Response (239)(251)(255)(252)(255)(258)(267)(277)(246)(251)
Existing - Energy Efficiency (32)(33)(34)(33)(34)(34)(35)(37)(33)(33)
New Energy Efficiency (39)(74)(109)(143)(181)(213)(259)(309)(308)(356)
East Total obligation 5,229 5,320 5,400 5,429 5,470 5,366 5,349 5,379 5,488 5,512
Capacity Reserve Margin (13%)680 692 702 706 711 698 695 699 713 717
East Obligation + Reserves 5,908 6,011 6,102 6,135 6,181 6,064 6,045 6,079 6,202 6,229
East Position 746 730 713 504 165 (48)10 (682)(839)(1,203)
Available Front Office Transactions 300 300 300 300 300 300 300 300 300 300
West
Thermal 2,205 2,211 2,186 1,930 2,203 2,064 2,060 1,982 2,010 1,991
Hydroelectric 497 518 434 456 320 330 317 410 439 439
Renewable 105 75 69 86 56 63 52 84 92 95
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 53 50 45 54 37 36 19 39 36 33
Sale (88)(71)(59)(45)(32)(33)(32)(38)(41)(40)
West Existing Resources 2,773 2,784 2,675 2,482 2,585 2,461 2,418 2,478 2,536 2,519
Load 3,318 3,358 3,397 3,421 3,449 3,479 3,516 3,550 3,585 3,615
Private Generation (0)(0)(1)(1)(1)(1)(2)(2)(3)(3)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
Existing - Energy Efficiency (23)(24)(24)(24)(24)(24)(25)(26)(23)(24)
New Energy Efficiency (25)(48)(69)(86)(105)(124)(149)(176)(176)(200)
West Total obligation 3,270 3,286 3,304 3,311 3,319 3,329 3,340 3,345 3,384 3,387
Capacity Reserve Margin (13%)425 427 430 430 431 433 434 435 440 440
West Obligation + Reserves 400 379 3,734 3,741 3,750 3,761 3,774 3,780 3,824 3,828
West Position 2,373 2,404 (1,058)(1,260)(1,165)(1,301)(1,356)(1,302)(1,287)(1,309)
Available Front Office Transactions 700 700 700 700 700 700 700 700 700 700
System
Total Resources 9,427 9,525 9,490 9,120 8,930 8,477 8,472 7,875 7,898 7,544
Obligation 8,498 8,605 8,704 8,740 8,789 8,695 8,689 8,725 8,872 8,900
Planning Reserves (13%)1,105 1,119 1,132 1,136 1,143 1,130 1,130 1,134 1,153 1,157
Obligation + Reserves 9,603 9,724 9,836 9,876 9,931 9,825 9,819 9,859 10,025 10,056
System Position (176)(199)(345)(756)(1,001)(1,348)(1,347)(1,984)(2,127)(2,512)
Available Front Office Transactions 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Uncomitted FOTs to meet remaining Need 176 199 345 756 1,000 1,000 1,000 1,000 1,000 1,000
Net Surplus/(Deficit)0 0 0 0 (1)(348)(347)(984)(1,127)(1,512)
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
157
Table 6.13 (cont.) – Winter Peak System Capacity Loads and Resources without Resource
Additions
Figure 6.4 through Figure 6.7 are graphic representations of the above tables for annual capacity
position for the summer system, winter system, east control area, and west control area. Also
shown in the system capacity position graph are available FOTs, which can be used to meet
capacity needs. The market availability assumptions used for portfolio modeling are discussed
further in Chapter 7 (Resource Options).
East
2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Thermal 3,901 3,947 3,646 3,554 3,677 3,411 2,830 2,643 2,783 2,421
Hydroelectric 36 36 34 37 38 43 47 48 52 49
Renewable 665 662 620 668 703 752 782 756 832 778
Purchase 129 129 131 119 109 111 136 133 134 119
Qualifying Facilities 186 178 133 124 119 80 15 13 4 0
Sale 0 0 0 0 0 0 0 0 0 (0)
East Existing Resources 4,917 4,952 4,563 4,501 4,647 4,397 3,811 3,592 3,806 3,368
Load 6,240 6,328 6,415 6,517 6,595 6,672 6,407 6,504 6,589 6,682
Private Generation (9)(10)(12)(13)(14)(16)(33)(37)(41)(45)
Existing - Demand Response (288)(287)(291)(264)(243)(247)(303)(295)(299)(267)
Existing - Energy Efficiency (38)(38)(39)(35)(32)(33)(40)(39)(40)(35)
New Energy Efficiency (446)(480)(513)(494)(481)(504)(659)(695)(758)(726)
East Total obligation 5,459 5,513 5,560 5,711 5,824 5,872 5,372 5,438 5,451 5,609
Capacity Reserve Margin (13%)710 717 723 742 757 763 698 707 709 729
East Obligation + Reserves 6,169 6,230 6,283 6,453 6,581 6,636 6,070 6,145 6,160 6,338
East Position (1,252)(1,277)(1,720)(1,952)(1,935)(2,239)(2,260)(2,553)(2,354)(2,970)
Available Front Office Transactions 300 300 300 300 300 300 300 300 300 300
West
Thermal 2,076 2,053 2,032 2,080 2,072 2,025 1,808 489 490 490
Hydroelectric 373 374 351 388 406 448 481 487 536 503
Renewable 79 79 70 78 78 91 101 104 111 107
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 25 23 19 19 19 19 17 16 13 8
Sale (35)(34)(32)(34)(36)(38)(32)(29)(32)(30)
West Existing Resources 2,519 2,496 2,442 2,531 2,540 2,545 2,376 1,068 1,119 1,078
Load 3,643 3,681 3,721 3,760 3,797 3,826 4,271 4,322 4,375 4,425
Private Generation (4)(4)(5)(6)(7)(8)(9)(11)(12)(13)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
Existing - Energy Efficiency (27)(27)(28)(25)(23)(23)(29)(28)(28)(25)
New Energy Efficiency (252)(271)(293)(283)(276)(293)(372)(385)(409)(369)
West Total obligation 3,360 3,378 3,395 3,446 3,491 3,502 3,861 3,898 3,925 4,018
Capacity Reserve Margin (13%)437 439 441 448 454 455 502 507 510 522
East Obligation + Reserves 185 168 148 165 178 163 130 121 101 153
East Position 2,334 2,328 2,294 2,366 2,362 2,382 2,246 947 1,018 925
Available Front Office Transactions 700 700 700 700 700 700 700 700 700 700
System
Total Resources 7,436 7,449 7,005 7,033 7,186 6,942 6,187 4,660 4,925 4,445
Obligation 8,819 8,891 8,955 9,157 9,315 9,374 9,234 9,336 9,377 9,627
Planning Reserves (13%)1,146 1,156 1,164 1,190 1,211 1,219 1,200 1,214 1,219 1,251
Obligation + Reserves 9,966 10,047 10,119 10,347 10,526 10,593 10,434 10,550 10,595 10,878
System Position (2,530)(2,599)(3,115)(3,314)(3,340)(3,651)(4,247)(5,889)(5,670)(6,433)
Available Front Office Transactions 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Uncomitted FOTs to meet remaining Need 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Net Surplus/(Deficit)(1,530)(1,599)(2,115)(2,314)(2,340)(2,651)(3,247)(4,889)(4,670)(5,433)
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
158
Figure 6.4 – Summer System Capacity Position Trend
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Me
g
a
w
a
t
t
s
West Existing Resources East Existing Resources
Uncommitted FOTs to meet remaining Need Obligation + Reserves
Obligation
East Existing Resources
West Existing Resources
13% Reserves
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
159
Figure 6.5 – Winter System Capacity Position Trend
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Me
g
a
w
a
t
t
s
West Existing Resources East Existing Resources
Uncommitted FOTs to meet remaining Need Obligation + Reserves
Obligation
East Existing Resources
West Existing Resources
13% Reserves
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
160
Figure 6.6 – East Summer Capacity Position Trend
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
Me
g
a
w
a
t
t
s
East Existing Resources East - Uncommitted FOTs to meet remaining Need
East Obligation + Reserves East Total obligation
East Existing Resources
13% Reserves
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
161
Figure 6.7 – West Summer Capacity Position Trend
Energy Balance Determination
Methodology
The energy balance shows the monthly surplus or (deficit) of energy. Please refer to the section on
load and resource balance components for details on how energy for each component is counted.
Existing Resources = Thermal + Hydro + Renewable + Firm Purchases + QF – Sales
The average obligation is computed using the following formula:
Obligation = Load + Firm Sales
The energy position by month is then computed as follows:
Energy Position = Existing Resources – Obligation – Operating Reserve Requirements
Operating Reserve Requirements include spinning and non-spinning reserves, but not regulation
reserves, which are expected to be close to energy neutral over time. As duration-limited resources
such as batteries become a larger portion of the Company’s portfolio, less of the potential output
of thermal resources is likely to be needed to meet Operating Reserve requirements. In addition,
energy storage resources represent a net load, due to their roundtrip efficiency. For the 2021 IRP,
storage resources are not included in the energy balance.
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
Me
g
a
w
a
t
t
s
West Existing Resources West - Uncommitted FOTs to meet remaining Need
West Obligation + Reserves West Total obligation
West Existing Resources
13% Reserves
PACIFICORP – 2021 IRP CHAPTER 6 – LOAD AND RESOURCE BALANCE
162
Energy Balance Results
The capacity position shows how existing resources and loads, accounting for coal unit retirements
and incremental energy efficiency savings from the preferred portfolio, balance during the
coincident peak summer and winter. Outside of these peak periods, PacifiCorp economically
dispatches its resources to meet changing load conditions taking into consideration prevailing
market conditions. In those periods when variable costs of the system resources are less than the
prevailing market price for power, PacifiCorp can dispatch resources that in aggregate exceed
then-current load obligations facilitating off system sales that reduce customer costs. Conversely,
at times when system resource costs fall below prevailing market prices, system balancing market
purchases can be used to meet then-current system load obligations to reduce customer costs. The
economic dispatch of system resources is critical to how PacifiCorp manages net power costs.
Figure 6.8 provides a snapshot of how existing system resources could be used to meet forecasted
load across on-peak and off-peak periods given the assumptions about resource availability and
wholesale power and natural gas prices. At times, resources are economically dispatched above
load levels facilitating net system balancing sales. At other times, economic conditions result in
net system balancing purchases, which occur more often during on-peak periods. Figure 6.8 also
shows how much energy is available from existing resources at any given point in time. Those
periods where all available resource energy falls below forecasted loads are highlighted in red, and
indicate short energy positions without the addition of incremental resources to the portfolio.
Figure 6.8 – System Average Monthly Energy Positions
0
2,000
4,000
6,000
8,000
10,000
12,000
Ja
n
-
2
1
Ap
r
-
2
1
Ju
l
-
2
1
Oc
t
-
2
1
Ja
n
-
2
2
Ap
r
-
2
2
Ju
l
-
2
2
Oc
t
-
2
2
Ja
n
-
2
3
Ap
r
-
2
3
Ju
l
-
2
3
Oc
t
-
2
3
Ja
n
-
2
4
Ap
r
-
2
4
Ju
l
-
2
4
Oc
t
-
2
4
Ja
n
-
2
5
Ap
r
-
2
5
Ju
l
-
2
5
Oc
t
-
2
5
Ja
n
-
2
6
Ap
r
-
2
6
Ju
l
-
2
6
Oc
t
-
2
6
Ja
n
-
2
7
Ap
r
-
2
7
Ju
l
-
2
7
Oc
t
-
2
7
Ja
n
-
2
8
Ap
r
-
2
8
Ju
l
-
2
8
Oc
t
-
2
8
Ja
n
-
2
9
Ap
r
-
2
9
Ju
l
-
2
9
Oc
t
-
2
9
Ja
n
-
3
0
Ap
r
-
3
0
Ju
l
-
3
0
Oc
t
-
3
0
Av
e
r
a
g
e
E
n
e
r
g
y
A
v
a
i
l
a
b
l
e
(
M
W
)
Monthly Energy Balance
Energy at or Below Load Net Balancing Purchase Net Balancing Sale
Energy Shortfall Energy Available Obligation
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
163
CHAPTER 7 – RESOURCE OPTIONS
CHAPTER HIGHLIGHTS
• PacifiCorp developed resource attributes and costs for expansion resources that reflect updated
information from project experience, industry vendors, public meeting comments and studies.
• Resource costs have been generally stable since the previous integrated resource plan (IRP) and
cost increases have been modest to declining.
• Geothermal power-purchase agreements (PPAs) are included as supply-side options in this IRP
and updated to reflect current conditions.
• The combustion turbine types, configurations, and siting locations are identified in the supply-
side resource options table. Performance and costs have been updated.
• Energy storage systems continue to be of interest to PacifiCorp, its stakeholders, and the
industry at large. Options for advanced large batteries (15 megawatts (MW) and larger),
renewable (wind and solar) plus storage, pumped hydro and compressed air energy storage are
included in this IRP.
• The Plexos model is able to endogenously model transmission upgrades.
• PacifiCorp continued to apply cost reduction credits to energy efficiency, reflecting risk
mitigation benefits, transmission and distribution investment deferral benefits, and a ten percent
market price credit for Washington and Oregon as allowed by the Northwest Power Act.
Introduction
This chapter provides background information on the various resources considered in the IRP for
meeting future capacity and energy needs. Organized by major category, these resources consist
of utility-scale supply-side generation, demand-side management (DSM) programs, transmission
resources and market purchases. For each resource category, the chapter discusses the criteria for
resource selection, presents the options and associated attributes, and describes the various
technologies. In addition, for supply-side resources, the chapter describes how PacifiCorp
addressed long-term cost trends and uncertainty in deriving cost figures.
Supply-Side Resources
The list of supply-side resource options reflects the realities evidenced through permitting,
internally generated studies and externally commissioned studies undertaken to better understand
details of available generation resources. Capital costs for some resource options have declined
while others have remained stable compared to the 2019 IRP. Wind and transmission resources
were updated based upon market and performance data gained from construction of the Energy
Vision 2020 project that came out of the 2017 IRP. Energy storage options of at least one MW
continue to be of interest to PacifiCorp, its stakeholders, and the industry at large. PacifiCorp
analyzed options for large pumped hydro projects and utility scale batteries. In response to
stakeholder requests and utility industry trends, PacifiCorp studied multiple different battery
energy storage configurations and combined battery configurations collocated with wind and solar
projects. Solar resource options were updated to include 100 MW and 200 MW single axis tracking
facilities to reflect the industry trend of larger utility-size photovoltaic (PV) systems. A variety of
gas-fueled generating resources were identified after consultation with major suppliers, large
engineering-consulting firm and stakeholders. Combustion turbine types and configurations
remained unchanged because the market continued to improve the ability of existing technology
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
164
to provide firming for variable energy resources. The capital and operating costs of simple and
combined-cycle gas turbine plants have remained relatively low in recent years, with a flat to
slightly decreasing cost trend.1 carbon capture and sequestration (CCS) retrofit costs were updated
using cost data from existing carbon capture facilities, studies and CCS developers. New super
critical pulverized coal-fueled resources received minimal focus during this cycle due to ongoing
environmental, economic, permitting and sociopolitical obstacles.
Derivation of Resource Attributes
The supply-side resource options were developed from a combination of resources. The process
began with the list of major generating resources from the 2019 IRP. This resource list was
reviewed and modified to reflect stakeholder input, new technology developments, environmental
factors, cost dynamics and anticipated permitting requirements. Once the basic list of resources
was determined, the cost-and-performance attributes for each resource were estimated. The
information sources used are listed below, followed by a brief description on how they were used
in the development of the supply-side resource table (SSR), which is used to develop inputs for
IRP modeling:
• Recent (2020) third-party engineering cost and performance estimates;
• Original equipment manufacturers operation and maintenance estimates;
• Developer cost and performance estimates;
• Publicly available cost and performance estimates;
• Actual PacifiCorp or electric utility industry installations, providing current
construction/maintenance costs and performance data with similar resource attributes;
and
• Projected PacifiCorp or electric utility industry installations, providing projected
construction/maintenance costs and performance data of similar or identical resource
options.
Black and Veatch and original equipment manufacturers provided estimated capital costs,
operating and maintenance costs, performance, operating characteristics and planned outage cycles
for simple cycle and combined cycle resources. Carbon capture, utilization and sequestration
(CCUS) costs, revenues, and performance were estimated from existing carbon capture facilities,
studies and CCUS developers. For this IRP cycle, Burns & McDonnell provided information for
solar, wind, and energy storage resources. The Burns & McDonnell study builds upon prior
studies, updates cost and technical information, and adds combined renewables plus energy storage
resource options.
PacifiCorp or industry installations provide a solid basis for capital/maintenance costs and
operating histories. Performance characteristics were adjusted to site-specific conditions identified
in the SSR. For instance, the capacity of combustion turbine-based resources varies with elevation
and ambient temperature and, to a lesser extent, relative humidity. Adjustments were made for
site-specific elevations of actual plants to more generic, regional elevations for future resources.
Examples of actual PacifiCorp installations used to develop the cost-and-performance information
1 While cost-and-performance metrics for gas-fired resources are presented in this chapter, PacifiCorp ultimately did
not allow new gas-fired resources in its portfolio selection process. Please refer to Chapter 8 for a discussion of the
risks PacifiCorp considered when making this planning assumption. A sensitivity case will be developed that
enables new gas-fired proxy resources.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
165
provided in the SSR include operation and maintenance (O&M) costs for PacifiCorp’s Gadsby GE
LM6000PC peaking units and the Lake Side 2 combined cycle plant.
Handling of Technology Improvement Trends and Cost Uncertainties
The capital cost uncertainty for some generation technologies is relatively high. Various factors
contribute to this uncertainty including limited quantity and quality of data sets for new and
emerging technologies that have been demonstrated at utility scale. Despite this uncertainty, the
cost profile between the 2019 IRP and the 2021 IRP has not changed significantly. For example,
Figure 7.1 shows the trend in U.S. steel prices over the period from January 2001 through January
2021. This figure illustrates changes in capital costs of generation resources. The 2021 IRP
includes demolition costs for the first time. Demolition costs are impacted by the salvage of metals,
including steel. Figure 7.2 shows the trend in U.S. carbon steel scrap and illustrates the uncertainty
in demolition costs.
Figure 7.1 – Producer Price Index: Hot Rolled Steel Bars, Plates, and Structural Shapes2
2 U.S. Bureau of Labor Statistics, Producer Price Index by Commodity: Metals and Metal Products: Hot Rolled Steel
Bars, Plates, and Structural Shapes [WPU101704], retrieved from FRED, Federal Reserve Bank of St. Louis;
https://fred.stlouisfed.org/series/WPU101704, June 13, 2021.
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
166
Figure 7.2 – Producer Price Index: Metals and Metal Products: Carbon Steel Scrap3
Prices for solar PV modules and balance of plant costs have been re-baselined since the 2019 IRP
as described later in this chapter. Real prices are projected to continue to decline based upon
technological and manufacturing improvements, but tariffs on Chinese imports and high demand
for PV modules ahead of the phase out of the federal investment tax credits (ITC) for solar projects
creates some degree of uncertainty in the solar market. The 2021 IRP anticipates the cost of new
solar projects to decline approximately five percent per year during next ten years and then to
decline at a rate of approximately one percent per year beginning in year four.
Some generation technologies, such as integrated gasification combined cycle (IGCC), as well as
CCUS technologies, have shown significant cost uncertainty because only a few units have been
built and operated. For example, experience with significant cost overruns on IGCC projects, such
as Southern Company’s Kemper County IGCC plant, illustrate the difficulty in accurately
estimating capital costs of these resource options. Where carbon capture is dependent on revenues
from enhanced oil recovery (EOR) to offset costs, the volatility in the price of oil adds an additional
level of uncertainty. For example, declining oil prices caused NRG Energy’s Petra Nova carbon
capture facility to cease operation. The loss of revenue at Petra Nova illustrates the added
uncertainty of recovering costs through carbon dioxide sales. As these technologies mature and
more facilities are proven at commercial scale, the associated costs may decrease.
3 U.S. Bureau of Labor Statistics, Producer Price Index by Commodity: Metals and Metal Products: Carbon Steel
Scrap [WPU101211], retrieved from FRED, Federal Reserve Bank of St. Louis;
https://fred.stlouisfed.org/series/WPU101211, June 14, 2021.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
167
The potential to provide reduced, reliable capital and operating cost estimates is limited by the
number of installed and successfully operated resources. Reliable cost and performance estimates
are not expected to be realized until the next generation of new plants are built and successfully
operated. As such, future IRPs will be better able to incorporate the potential benefits of future
cost reductions. Given the current emphasis on construction and operating experience associated
with renewable generation, PacifiCorp anticipates the cost benefits for these technologies to be
available sooner. The estimated capital costs are displayed in the SSR along with expected
availability of each technology for commercial utilization.
Solar annual capital cost escalation rates are based on unweighted median scenarios from General
Electric Renewable Energy, the U.S. Energy Administration, and Burns and McDonnell—note,
rates for 2019 and 2020 are adjusted to calibrate levelized costs to be consistent with pricing
received in recent RFPs.
Wind annual capital cost escalation rates are based on estimates provided by Burns and McDonnell
and costs and market information obtained by PacifiCorp during the development and construction
of recent wind projects. All other resources are assumed to escalate at inflation.
Resource Options and Attributes
Table 7.1 lists the cost-and-performance attributes for supply-side resource options designated by
generic, elevation-specific regions where resources could potentially be located:
• 0 feet elevation: international organization for standardization (ISO) conditions (sea level
and 59 degrees F); this is used as a reference for certain modeling purposes.
• 1,500 feet elevation: eastern Oregon/Washington.
• 3,000 feet elevation: southern/central Oregon.
• 4,500 feet elevation: northern Utah, specifically Salt Lake/Utah/Tooele/Box Elder
counties.
• 5,050 feet elevation: central Utah, southern Idaho, central Wyoming.
• 6,500 feet elevation: southwestern Wyoming.
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
168
Table 7.1 – 2021 Supply-Side Resource Table (2020$) (Continued)
Table 7.1 – 2021 Supply-Side Resource Table (2020$) (Continued)
Fuel Resource
Elevation
(AFSL)
Net
Capacity
(MW)
Commercial
Operation Year
Design Life
(yrs)
Base Capital
($/KW)
Var O&M
($/MWh)
Fixed O&M
($/KW-yr)
Average Full Load
Heat Rate (HHV
Btu/KWh)/Efficiency EFOR (%)POR (%)
Water Consumed
(Gal/MWh)
SO2
(lbs/MMBtu)
NOx
(lbs/MMBtu)Hg (lbs/TBTu)CO2 (lbs/MMBtu)
Solar + Storage + Wind
Milford, UT, 200 MW Solar, CF: 30.2% +
BESS: 50% pwr, 4 hours + 200 MW
Wind 5,000 200 2023 25 $ 3,364 $ 268 $ - $ 81.45 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage + Wind
Rock Springs, WY, 200 MW Solar, CF:
27.9% + BESS: 50% pwr, 4 hours + 200
MW Wind 6,400 200 2023 25 $ 3,364 $ 268 $ - $ 81.45 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage + Wind
Yakima, WA, 200 MW Solar, CF: 24.2%
+ BESS: 50% pwr, 4 hours + 200 MW
Wind 1,000 200 2023 25 $ 3,424 $ 268 $ - $ 81.45 85%(b)(b)n/a n/a n/a n/a n/a
Storage Pumped Hydro, Swan Lake. 3600 MWh N/A 400 2027 60 $ 3,095 $ 485 $ - $ 12.50 78%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Goldendale, 14400 MWh N/A 1,200 2028 60 $ 2,833 $ 485 $ - $ 12.50 78%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Seminoe, 7500 MWh N/A 750 2029 80 $ 3,461 $ 485 $ 0.37 $ 16.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Pumped Hydro, Badger Mountain, 4000
MWh N/A 500 2027 80 $ 2,621 $ 485 $ 0.37 $ 28.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Owyhee, 4800 MWh N/A 600 2029 80 $ 3,203 $ 485 $ 0.37 $ 20.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Flat Canyon, 1800 MWh N/A 300 2029 80 $ 4,046 $ 485 $ 0.37 $ 53.33 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Utah PS2, 4000 MWh N/A 500 2027 80 $ 3,237 $ 485 $ 0.37 $ 28.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Utah PS3, 4800 MWh N/A 600 2029 80 $ 3,371 $ 485 $ 0.37 $ 20.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Pumped Hydro, Banner Mountain, 3400
MWh N/A 400 2028 50 $ 3,276 $ 485 $ 0.00 $ 28.50 81%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 150 MW,
600 MWh N/A 150 2024 50 $ 1,954 $ 12 $ 6.50 $ 12.67 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 150 MW,
1200 MWh N/A 150 2024 50 $ 2,189 $ 12 $ 6.50 $ 12.67 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 150 MW,
1800 MWh N/A 150 2024 50 $ 2,445 $ 12 $ 6.50 $ 12.67 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 300 MW,
1200 MWh N/A 300 2024 50 $ 1,557 $ 12 $ 6.50 $ 9.33 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 300 MW,
2400 MWh N/A 300 2024 50 $ 1,692 $ 12 $ 6.50 $ 9.33 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 300 MW,
3600 MWh N/A 300 2024 50 $ 2,016 $ 12 $ 6.50 $ 9.33 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 500 MW,
2000 MWh N/A 500 2024 50 $ 1,549 $ 12 $ 6.50 $ 6.60 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 500 MW,
4000 MWh N/A 500 2025 50 $ 1,762 $ 12 $ 6.50 $ 6.60 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 500 MW,
6000 MWh N/A 500 2025 50 $ 2,010 $ 12 $ 6.50 $ 6.60 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 0.5 MWh N/A 1 2023 20 $ 1,948 $ 55 (a) $ 40.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 1 MWh N/A 1 2023 20 $ 2,058 $ 110 (a) $ 50.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 4 MWh N/A 1 2023 20 $ 3,167 $ 440 (a) $ 70.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 8 MWh N/A 1 2023 20 $ 4,622 $ 880 (a) $ 100.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 50 MW, 200 MWh N/A 50 2023 20 $ 1,820 $ 440 (a) $ 27.60 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 1 MW, 1 MWh N/A 1 2023 20 $ 4,719 $ 12 (a) $ 13.00 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 1 MW, 4 MWh N/A 1 2023 20 $ 5,051 $ 12 (a) $ 13.00 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 1 MW, 8 MWh N/A 1 2023 20 $ 7,291 $ 12 (a) $ 27.00 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 20 MW, 160 MWh N/A 20 2023 20 $ 4,190 $ 12 (a) $ 30.50 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Nuclear Small Modular Reactor 5,000 854 2028 60 $ 5,396 $ 722 $ 6.72 $ 65.03 N/A 5.0 5.0 N/A 0.0000 0.0000 0.0000 0.0000
Hydrogen Non-Emitting Peaker 5,050 206 2030 30 $ 959 $ 2,414 $ 21.29 $ - 9936 2.7 3.9 218.0000 0.0000 0.0000 0.0000 0.0000
Description Resource Characteristics Costs Operating Characteristics Environmental
Fuel Resource
Elevation
(AFSL)
Net
Capacity
(MW)
Commercial
Operation Year
Design Life
(yrs)
Base Capital
($/KW)
Var O&M
($/MWh)
Fixed O&M
($/KW-yr)
Average Full Load
Heat Rate (HHV
Btu/KWh)/Efficiency EFOR (%)POR (%)
Water Consumed
(Gal/MWh)
SO2
(lbs/MMBtu)
NOx
(lbs/MMBtu)Hg (lbs/TBTu)CO2 (lbs/MMBtu)
CCUS for Coal Plants Naughton 2 PC CCUS Retrofit 6,500 155 2026 20 $ 3,930 $ 37 $ 7.30 $ 39.90 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Johnston 2 PC CCUS Retrofit 6,500 82 2026 20 $ 5,314 $ 37 $ 6.10 $ 40.58 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Johnston 4 PC CCUS Retrofit 6,500 254 2026 20 $ 3,877 $ 37 $ 5.69 $ 37.88 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Wyodak PC CCUS Retrofit 6,500 206 2026 20 $ 3,935 $ 37 $ 7.31 $ 39.95 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Bridger 1 PC CCUS Retrofit 6,500 273 2026 20 $ 3,934 $ 37 $ 7.31 $ 39.94 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Bridger 3 PC CCUS Retrofit 6,500 269 2026 20 $ 3,873 $ 37 $ 5.69 $ 37.83 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Bridger 4 PC CCUS Retrofit 6,500 270 2026 20 $ 3,876 $ 37 $ 5.69 $ 37.86 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
Description Resource Characteristics Costs Operating Characteristics Environmental
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
169
Table 7.2 and Table 7.3 present the total resource cost attributes for supply-side resource options
and are based on estimates of the first-year, real-levelized costs for resources, stated in June 2020
dollars. Similar to the approach taken in previous IRPs, it is not currently envisioned that new
combined cycle resources could be economically permitted in northern Utah, specifically Salt
Lake, Utah, Davis, and Box Elder counties due to state implementation plans for these counties
regarding particulate matter of 2.5 microns and less (PM2.5).
A Glossary of Terms and a Glossary of Acronyms from the SSR is summarized in Table 7.4 and
Table 7.5.
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
170
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
171
Table 7.1 – 2021 Supply-Side Resource Table (2020$)
Description Resource Characteristics Costs Operating Characteristics Environmental
Fuel Resource
Elevation
(AFSL)
Net
Capacity
(MW)
Commercial
Operation Year
Design Life
(yrs)
Base Capital
($/KW)
Demolition
Cost ($/kW)
Var O&M
($/MWh)
Fixed O&M
($/KW-yr)
Average Full Load
Heat Rate (HHV
Btu/KWh)/Efficiency EFOR (%)POR (%)
Water Consumed
(Gal/MWh)
SO2
(lbs/MMBtu)
NOx
(lbs/MMBtu)Hg (lbs/TBTu)CO2 (lbs/MMBtu)
Natural Gas SCCT Aero x3 0 169 2025 30 $ 1,463 $ 10 $ 7.44 $ - 9350 2.6 3.9 43.6234 0.0006 0.0090 0.2550 117.0000
Natural Gas Intercooled SCCT Aero x2 0 227 2025 30 $ 1,126 $ 10 $ 5.03 $ - 8800 2.9 3.9 27.0223 0.0006 0.0090 0.2550 117.0000
Natural Gas SCCT Frame "F" x1 0 239 2025 35 $ 699 $ 10 $ 14.16 $ - 9913 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas Brownfield SCCT Frame "F" x1 0 239 2025 35 $ 674 $ 10 $ 14.16 $ - 9913 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas IC Recips x 6 0 111 2026 40 $ 1,938 $ 12 $ 10.39 $ - 8286 2.5 5.0 27.1363 0.0006 0.0288 0.2550 117.0000
Natural Gas CCCT Dry "H", 1x1 0 422 2026 40 $ 1,396 $ 10 $ 1.77 $ - 6343 2.5 3.8 23.5973 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 1x1 0 51 2026 40 $ 470 $ - $ 0.05 $ - 8838 2.5 3.8 22.9547 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", 2x1 0 842 2027 40 $ 1,019 $ 10 $ 1.71 $ - 6361 2.5 3.8 20.1038 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 2x1 0 102 2027 40 $ 357 $ - $ 0.05 $ - 8665 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas Brownfield CCCT Dry "H", DF, 2x1 0 842 2027 40 $ 1,019 $ 10 $ 1.08 $ - 6610 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 1x1 0 615 2026 40 $ 1,065 $ 10 $ 1.48 $ - 6264 2.5 3.8 20.3774 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 1x1 0 63 2026 40 $ 397 $ - $ 0.06 $ - 8769 2.5 3.8 20.1033 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 2x1 0 1,232 2027 40 $ 787 $ 10 $ 1.43 $ - 6251 2.5 3.8 17.8997 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 2x1 0 126 2027 40 $ 309 $ - $ 0.06 $ - 8704 2.5 3.8 17.8427 0.0006 0.0072 0.2550 117.0000
Natural Gas SCCT Aero x3 1,500 159 2025 30 $ 1,551 $ 14 $ 7.89 $ - 9362 2.6 3.9 43.6234 0.0006 0.0090 0.2550 117.0000
Natural Gas Intercooled SCCT Aero x2 1,500 215 2025 30 $ 1,188 $ 14 $ 5.31 $ - 8802 2.9 3.9 27.0223 0.0006 0.0090 0.2550 117.0000
Natural Gas SCCT Frame "F" x1 1,500 227 2025 35 $ 738 $ 14 $ 14.94 $ - 9916 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas Brownfield SCCT Frame "F" x1 1,500 227 2025 35 $ 711 $ 14 $ 14.94 $ - 9916 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas IC Recips x 6 1,500 111 2026 40 $ 1,938 $ 12 $ 10.39 $ - 8286 2.5 5.0 27.1363 0.0006 0.0288 0.2550 117.0000
Natural Gas CCCT Dry "H", 1x1 1,500 397 2026 40 $ 1,484 $ 14 $ 1.88 $ - 6384 2.5 3.8 23.5973 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 1x1 1,500 51 2027 40 $ 470 $ - $ 0.05 $ - 8789 2.5 3.8 22.9547 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", 2x1 1,500 797 2027 40 $ 1,077 $ 14 $ 1.81 $ - 6367 2.5 3.8 20.1038 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 2x1 1,500 102 2026 40 $ 357 $ - $ 0.05 $ - 8713 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas Brownfield CCCT Dry "H", DF, 2x1 1,500 797 2026 40 $ 1,077 $ 14 $ 1.14 $ - 6633 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 1x1 1,500 582 2027 40 $ 1,125 $ 14 $ 1.57 $ - 6264 2.5 3.8 20.3774 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 1x1 1,500 63 2027 40 $ 397 $ - $ 0.06 $ - 8816 2.5 3.8 20.1033 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 2x1 1,500 1,166 2026 40 $ 832 $ 14 $ 1.51 $ - 6249 2.5 3.8 17.8997 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 2x1 1,500 126 2026 40 $ 309 $ - $ 0.06 $ - 8742 2.5 3.8 17.8427 0.0006 0.0072 0.2550 117.0000
Natural Gas SCCT Aero x3 3,000 150 2025 30 $ 1,645 $ 11 $ 8.37 $ - 9380 2.6 3.9 43.6234 0.0006 0.0090 0.2550 117.0000
Natural Gas Intercooled SCCT Aero x2 3,000 203 2025 30 $ 1,260 $ 11 $ 5.63 $ - 8811 2.9 3.9 27.0223 0.0006 0.0090 0.2550 117.0000
Natural Gas SCCT Frame "F" x1 3,000 214 2025 35 $ 779 $ 11 $ 15.79 $ - 9928 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas Brownfield SCCT Frame "F" x1 3,000 214 2025 35 $ 751 $ 11 $ 15.78 $ - 9928 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas IC Recips x 6 3,000 111 2026 40 $ 1,938 $ 12 $ 10.39 $ - 8286 2.5 5.0 27.1363 0.0006 0.0288 0.2550 117.0000
Natural Gas CCCT Dry "H", 1x1 3,000 376 2026 40 $ 1,569 $ 11 $ 1.99 $ - 6387 2.5 3.8 23.5973 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 1x1 3,000 51 2027 40 $ 470 $ - $ 0.05 $ - 8816 2.5 3.8 22.9547 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", 2x1 3,000 750 2027 40 $ 1,144 $ 11 $ 1.92 $ - 6400 2.5 3.8 20.1038 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 2x1 3,000 102 2026 40 $ 357 $ - $ 0.05 $ - 8756 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas Brownfield CCCT Dry "H", DF, 2x1 3,000 750 2026 40 $ 1,144 $ 11 $ 1.21 $ - 6682 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 1x1 3,000 550 2027 40 $ 1,189 $ 11 $ 1.66 $ - 6270 2.5 3.8 20.3774 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 1x1 3,000 63 2027 40 $ 397 $ - $ 0.06 $ - 8837 2.5 3.8 20.1033 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 2x1 3,000 1,103 2026 40 $ 879 $ 11 $ 1.60 $ - 6256 2.5 3.8 17.8997 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 2x1 3,000 126 2026 40 $ 309 $ - $ 0.06 $ - 8763 2.5 3.8 17.8427 0.0006 0.0072 0.2550 117.0000
Natural Gas SCCT Aero x3 5,050 139 2025 30 $ 1,777 $ 12 $ 9.04 $ - 9400 2.6 3.9 43.6234 0.0006 0.0090 0.2550 117.0000
Natural Gas Intercooled SCCT Aero x2 5,050 187 2025 30 $ 1,363 $ 12 $ 6.09 $ - 8816 2.9 3.9 27.0223 0.0006 0.0090 0.2550 117.0000
Natural Gas SCCT Frame "F" x1 5,050 199 2025 35 $ 841 $ 12 $ 17.04 $ - 9936 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas Brownfield SCCT Frame "F" x1 5,050 199 2025 35 $ 811 $ 12 $ 17.03 $ - 9936 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas IC Recips x 6 5,050 111 2026 40 $ 1,938 $ 12 $ 10.39 $ - 8292 2.5 5.0 27.1363 0.0006 0.0288 0.2550 117.0000
Natural Gas CCCT Dry "H", 1x1 5,050 350 2026 40 $ 1,687 $ 12 $ 2.14 $ - 6362 2.5 3.8 23.5973 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 1x1 5,050 51 2026 40 $ 470 $ - $ 0.05 $ - 8545 2.5 3.8 22.9547 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", 2x1 5,050 686 2027 40 $ 1,252 $ 12 $ 2.10 $ - 6487 2.5 3.8 20.1038 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 2x1 5,050 102 2027 40 $ 358 $ - $ 0.05 $ - 9470 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas Brownfield CCCT Dry "H", DF, 2x1 5,050 686 2027 40 $ 1,251 $ 12 $ 1.33 $ - 6874 2.5 3.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 1x1 5,050 504 2026 40 $ 1,299 $ 12 $ 1.81 $ - 6352 2.5 3.8 20.3774 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 1x1 5,050 63 2026 40 $ 397 $ - $ 0.06 $ - 9452 2.5 3.8 20.1033 0.0006 0.0072 0.2550 117.0000
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
172
Table 7.1 – 2021 Supply-Side Resource Table (2020$) (Continued)
Fuel Resource
Elevation
(AFSL)
Net
Capacity
(MW)
Commercial
Operation Year
Design Life
(yrs)
Base Capital
($/KW)
Demolition
Cost ($/kW)
Var O&M
($/MWh)
Fixed O&M
($/KW-yr)
Average Full Load
Heat Rate (HHV
Btu/KWh)/Efficiency EFOR (%)POR (%)
Water Consumed
(Gal/MWh)
SO2
(lbs/MMBtu)
NOx
(lbs/MMBtu)Hg (lbs/TBTu)CO2 (lbs/MMBtu)
Natural Gas CCCT Dry "J", 2x1 5,050 1,004 2027 40 $ 966 $ 12 $ 1.76 $ - 6373 2.5 3.8 17.8997 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 2x1 5,050 126 2027 40 $ 309 $ - $ 0.06 $ - 9456 2.5 3.8 17.8427 0.0006 0.0072 0.2550 117.0000
Natural Gas SCCT Aero x3 6,500 126 2025 30 $ 1,957 $ 13 $ 9.96 $ - 9314 2.6 3.9 43.6234 0.0006 0.0090 0.2550 117.0000
Natural Gas Intercooled SCCT Aero x2 6,500 179 2025 30 $ 1,427 $ 13 $ 6.37 $ - 8786 2.9 3.9 27.0223 0.0006 0.0090 0.2550 117.0000
Natural Gas SCCT Frame "F" x1 6,500 189 2025 35 $ 886 $ 13 $ 17.95 $ - 9930 2.7 3.9 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas Brownfield SCCT Frame "F" x1 6,500 189 2025 35 $ 854 $ 13 $ 17.95 $ - 9930 2.7 5.0 28.4484 0.0006 0.0090 0.2550 117.0000
Natural Gas IC Recips x 6 6,500 111 2026 40 $ 1,937 $ 12 $ 10.39 $ - 8333 2.5 3.8 27.1363 0.0006 0.0288 0.2550 117.0000
Natural Gas CCCT Dry "H", 1x1 6,500 335 2026 40 $ 1,761 $ 13 $ 2.23 $ - 6390 2.5 3.8 23.5973 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 1x1 6,500 51 2027 40 $ 470 $ - $ 0.05 $ - 8857 2.5 3.8 22.9547 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", 2x1 6,500 669 2027 40 $ 1,283 $ 12 $ 2.15 $ - 6399 2.5 3.8 20.1038 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "H", DF, 2x1 6,500 102 2026 40 $ 357 $ - $ 0.05 $ - 8852 2.5 4.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas Brownfield CCCT Dry "H", DF, 2x1 6,500 669 2026 40 $ 1,283 $ 12 $ 1.36 $ - 6724 2.5 5.8 19.7926 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 1x1 6,500 490 2027 40 $ 1,337 $ 12 $ 1.86 $ - 6273 2.5 6.8 20.3774 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 1x1 6,500 63 2027 40 $ 397 $ - $ 0.06 $ - 8864 2.5 7.8 20.1033 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", 2x1 6,500 981 2026 40 $ 988 $ 12 $ 1.80 $ - 6259 2.5 8.8 17.8997 0.0006 0.0072 0.2550 117.0000
Natural Gas CCCT Dry "J", DF, 2x1 6,500 126 2026 40 $ 309 $ - $ 0.06 $ - 8789 2.5 9.8 17.8427 0.0006 0.0072 0.2550 117.0000
Coal SCPC with CCS 4,500 526 2028 40 $ 6,488 $ 127 $ 7.00 $ 72.22 13087 5.0 5.0 1,004.2373 0.0085 0.0700 0.0222 20.5352
Coal IGCC with CCS 4,500 466 2028 40 $ 6,282 $ 60 $ 11.77 $ 58.20 10823 8.0 7.0 394.0678 0.0085 0.0500 0.3333 20.5352
Coal
PC CCS retrofit @ 500 MW pre-retrofit
basis 4,500 -115 2026 20 $ 2,971 $ 37 $ 3.29 $ 28.18 14372 5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
Coal SCPC with CCS 6,500 692 2028 40 $ 7,348 $ 127 $ 7.58 $ 67.09 13242 5.0 5.0 1,004.2373 0.0085 0.0700 0.0222 20.5352
Coal IGCC with CCS 6,500 456 2028 40 $ 7,113 $ 60 $ 14.11 $ 63.40 11047 8.0 7.0 394.0678 0.0085 0.0500 0.3333 20.5352
Coal
PC CCS retrofit @ 500 MW pre-retrofit
basis 6,500 -115 2026 20 $ 2,971 $ 37 $ 3.29 $ 28.18 14372 5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
Geothermal Blundell Dual Flash 90% CF 4,500 35 2021 40 $ 5,708 $ 127 $ 1.16 $ 103.85 N/A 5.0 5.0 10.0000 n/a n/a n/a n/a
Geothermal Greenfield Binary 90% CF 4,500 43 2023 40 $ 5,973 $ 127 $ 1.16 $ 103.85 N/A 5.0 5.0 270.0000 n/a n/a n/a n/a
Geothermal Generic Geothermal PPA 90% CF 4,500 30 2021 20 $ - $ - $ 77.34 $ - N/A 5.0 5.0 270.0000 n/a n/a n/a n/a
Wind
Pocatello, ID, 200 MW Wind, CF: 37.1%
(100% PTC)4,500 200 2024 30 $ 1,365 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Arlington, OR, 200 MW Wind, CF: 37.1%
(100% PTC)1,500 200 2024 30 $ 1,315 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Monticello, UT, 200 MW Wind, CF:
29.5% (100% PTC)4,500 200 2024 30 $ 1,306 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Medicine Bow, WY, 200 MW Wind, CF:
43.6% (100%PTC)6,500 200 2024 30 $ 1,356 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Goldendale, WA, 200 MW Wind, CF:
37.1% (100% PTC)1,500 200 2024 30 $ 1,390 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Pocatello, ID, 200 MW Wind, CF: 37.1%
(60% PTC)4,500 200 2024 30 $ 1,365 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Arlington, OR, 200 MW Wind, CF: 37.1%
(60% PTC)1,500 200 2024 30 $ 1,315 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Monticello, UT, 200 MW Wind, CF:
29.5% (60% PTC)4,500 200 2024 30 $ 1,306 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Medicine Bow, WY, 200 MW Wind, CF:
43.6% (60% PTC)6,500 200 2024 30 $ 1,356 $ 13 $ 0.65 $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind
Goldendale, WA, 200 MW Wnd, CF:
37.1% (60% PTC)1,500 200 2024 30 $ 1,390 $ 13 $ - $ 24.74 N/A (b)(b)n/a n/a n/a n/a n/a
Wind + Storage
Pocatello, ID, 200 MW Wind, CF: 37.1%
+ BESS: 50% pwr, 4 hours 4,500 200 2024 30 $ 2,152 $ 233 $ - $ 37.59 85%(b)(b)n/a n/a n/a n/a n/a
Wind + Storage
Arlington, OR, 200 MW Wind, CF: 37.1%
+ BESS: 50% pwr, 4 hours 1,500 200 2024 30 $ 2,086 $ 233 $ - $ 37.59 85%(b)(b)n/a n/a n/a n/a n/a
Wind + Storage
Monticello, UT, 200 MW Wind, CF:
29.5% + BESS: 50% pwr, 4 hours 4,500 200 2024 30 $ 2,061 $ 233 $ - $ 37.59 85%(b)(b)n/a n/a n/a n/a n/a
Wind + Storage
Medicine Bow, WY, 200 MW Wind, CF:
43.6% + BESS: 50% pwr, 4 hours 6,500 200 2024 30 $ 2,136 $ 233 $ 0.65 $ 37.59 85%(b)(b)n/a n/a n/a n/a n/a
Wind + Storage
Goldendale, WA, 200 MW Wind, CF:
37.1% + BESS: 50% pwr, 4 hours 1,500 200 2024 30 $ 2,211 $ 233 $ - $ 37.59 85%(b)(b)n/a n/a n/a n/a n/a
Solar
Idaho Falls, ID, 100 MW Solar, CF:
26.1% (30% ITC)4,700 100 2023 25 $ 1,429 $ 35 $ - $ 16.20 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Idaho Falls, ID, 200 MW Solar, CF:
26.1% (30% ITC)4,700 200 2023 25 $ 1,302 $ 35 $ - $ 16.10 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Lakeview, OR, 100 MW Solar, CF:
27.6% (30% ITC)4,800 100 2023 25 $ 1,444 $ 35 $ - $ 16.20 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Lakeview, OR, 200 MW Solar, CF:
27.6% (30% ITC)4,800 200 2023 25 $ 1,330 $ 35 $ - $ 16.10 N/A (b)(b)n/a n/a n/a n/a n/a
Resource Characteristics Costs Operating Characteristics EnvironmentalDescription
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
173
Table 7.1 – 2021 Supply-Side Resource Table (2020$) (Continued)
Fuel Resource
Elevation
(AFSL)
Net
Capacity
(MW)
Commercial
Operation Year
Design Life
(yrs)
Base Capital
($/KW)
Var O&M
($/MWh)
Fixed O&M
($/KW-yr)
Average Full Load
Heat Rate (HHV
Btu/KWh)/Efficiency EFOR (%)POR (%)
Water Consumed
(Gal/MWh)
SO2
(lbs/MMBtu)
NOx
(lbs/MMBtu)Hg (lbs/TBTu)CO2 (lbs/MMBtu)
Solar
Milford, UT, 100 MW Solar, CF: 30.2%
(30% ITC)5,000 100 2023 25 $ 1,422 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Milford, UT, 200 MW Solar, CF: 30.2%
(30% ITC)5,000 200 2023 25 $ 1,297 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Rock Springs, WY, 100 MW Solar, CF:
27.9% (30% ITC)6,400 100 2023 25 $ 1,423 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Rock Springs, WY, 200 MW Solar, CF:
27.9% (30% ITC)6,400 200 2023 25 $ 1,297 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Yakima, WA, 100 MW Solar, CF: 24.2%
(30% ITC)1,000 100 2023 25 $ 1,486 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Yakima, WA, 200 MW Solar, CF: 24.2%
(30% ITC)1,000 200 2023 25 $ 1,357 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Idaho Falls, ID, 100 MW Solar, CF:
26.1% (10% ITC)4,700 100 2023 25 $ 1,429 $ 35 $ - $ 16.20 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Idaho Falls, ID, 200 MW Solar, CF:
26.1% (10% ITC)4,700 200 2023 25 $ 1,302 $ 35 $ - $ 16.10 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Lakeview, OR, 100 MW Solar, CF:
27.6% (10% ITC)4,800 100 2023 25 $ 1,444 $ 35 $ - $ 16.20 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Lakeview, OR, 200 MW Solar, CF:
27.6% (10% ITC)4,800 200 2023 25 $ 1,330 $ 35 $ - $ 16.10 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Milford, UT, 100 MW Solar, CF: 30.2%
(10% ITC)5,000 100 2023 25 $ 1,422 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Milford, UT, 200 MW Solar, CF: 30.2%
(10% ITC)5,000 200 2023 25 $ 1,297 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Rock Springs, WY, 100 MW Solar, CF:
27.9% (10% ITC)6,400 100 2023 25 $ 1,423 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Rock Springs, WY, 200 MW Solar, CF:
27.9% (10% ITC)6,400 200 2023 25 $ 1,297 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Yakima, WA, 100 MW Solar, CF: 24.2%
(10% ITC)1,000 100 2023 25 $ 1,486 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar
Yakima, WA, 200 MW Solar, CF: 24.2%
(10% ITC)1,000 200 2023 25 $ 1,357 $ 35 $ - $ 17.60 N/A (b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Idaho Falls, ID, 100 MW Solar, CF:
26.1% + BESS: 50% pwr, 4 hours (30%
ITC)4,700 100 2023 25 $ 2,351 $ 255 $ - $ 30.00 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Idaho Falls, ID, 200 MW Solar, CF:
26.1% + BESS: 50% pwr, 4 hours (30%
ITC)4,700 200 2023 25 $ 2,161 $ 255 $ - $ 28.95 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Lakeview, OR, 100 MW Solar, CF:
27.6% + BESS: 50% pwr, 4 hours (30%
ITC)4,800 100 2023 25 $ 2,329 $ 255 $ - $ 30.00 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Lakeview, OR, 200 MW Solar, CF:
27.6% + BESS: 50% pwr, 4 hours (30%
ITC)4,800 200 2023 25 $ 2,154 $ 255 $ - $ 28.95 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Milford, UT, 100 MW Solar, CF: 30.2% +
BESS: 50% pwr, 4 hours (30% ITC)5,000 100 2023 25 $ 2,283 $ 255 $ - $ 31.40 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Milford, UT, 200 MW Solar, CF: 30.2% +
BESS: 50% pwr, 4 hours (30% ITC)5,000 200 2023 25 $ 2,102 $ 255 $ - $ 30.45 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Rock Springs, WY, 100 MW Solar, CF:
27.9% + BESS: 50% pwr, 4 hours (30%
ITC)6,400 100 2023 25 $ 2,312 $ 255 $ - $ 31.40 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Rock Springs, WY, 200 MW Solar, CF:
27.9% + BESS: 50% pwr, 4 hours (30%
ITC)6,400 200 2023 25 $ 2,128 $ 255 $ - $ 30.45 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Yakima, WA, 100 MW Solar, CF: 24.2%
+ BESS: 50% pwr, 4 hours (30% ITC)1,000 100 2023 25 $ 2,405 $ 255 $ - $ 31.40 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage
Yakima, WA, 200 MW Solar, CF: 24.2%
+ BESS: 50% pwr, 4 hours (30% ITC)1,000 200 2023 25 $ 2,217 $ 255 $ - $ 30.45 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage + Wind
Idah Falls, ID, 200 MW Solar, CF: 26.1%
+ BESS: 50% pwr, 4 hours + 200 MW
Wind 4,700 200 2023 25 $ 3,395 $ 268 $ - $ 82.95 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage + Wind
Lakeview, OR, 200 MW Solar, CF:
27.6% + BESS: 50% pwr, 4 hours + 200
MW Wind 4,800 200 2023 25 $ 3,424 $ 268 $ - $ 82.95 85%(b)(b)n/a n/a n/a n/a n/a
Description Resource Characteristics Costs Operating Characteristics Environmental
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
174
Table 7.1 – 2021 Supply-Side Resource Table (2020$) (Continued)
Fuel Resource
Elevation
(AFSL)
Net
Capacity
(MW)
Commercial
Operation Year
Design Life
(yrs)
Base Capital
($/KW)
Var O&M
($/MWh)
Fixed O&M
($/KW-yr)
Average Full Load
Heat Rate (HHV
Btu/KWh)/Efficiency EFOR (%)POR (%)
Water Consumed
(Gal/MWh)
SO2
(lbs/MMBtu)
NOx
(lbs/MMBtu)Hg (lbs/TBTu)CO2 (lbs/MMBtu)
Solar + Storage + Wind
Milford, UT, 200 MW Solar, CF: 30.2% +
BESS: 50% pwr, 4 hours + 200 MW
Wind 5,000 200 2023 25 $ 3,364 $ 268 $ - $ 81.45 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage + Wind
Rock Springs, WY, 200 MW Solar, CF:
27.9% + BESS: 50% pwr, 4 hours + 200
MW Wind 6,400 200 2023 25 $ 3,364 $ 268 $ - $ 81.45 85%(b)(b)n/a n/a n/a n/a n/a
Solar + Storage + Wind
Yakima, WA, 200 MW Solar, CF: 24.2%
+ BESS: 50% pwr, 4 hours + 200 MW
Wind 1,000 200 2023 25 $ 3,424 $ 268 $ - $ 81.45 85%(b)(b)n/a n/a n/a n/a n/a
Storage Pumped Hydro, Swan Lake. 3600 MWh N/A 400 2027 60 $ 3,095 $ 485 $ - $ 12.50 78%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Goldendale, 14400 MWh N/A 1,200 2028 60 $ 2,833 $ 485 $ - $ 12.50 78%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Seminoe, 7500 MWh N/A 750 2029 80 $ 3,461 $ 485 $ 0.37 $ 16.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Pumped Hydro, Badger Mountain, 4000
MWh N/A 500 2027 80 $ 2,621 $ 485 $ 0.37 $ 28.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Owyhee, 4800 MWh N/A 600 2029 80 $ 3,203 $ 485 $ 0.37 $ 20.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Flat Canyon, 1800 MWh N/A 300 2029 80 $ 4,046 $ 485 $ 0.37 $ 53.33 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Utah PS2, 4000 MWh N/A 500 2027 80 $ 3,237 $ 485 $ 0.37 $ 28.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Pumped Hydro, Utah PS3, 4800 MWh N/A 600 2029 80 $ 3,371 $ 485 $ 0.37 $ 20.00 80%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Pumped Hydro, Banner Mountain, 3400
MWh N/A 400 2028 50 $ 3,276 $ 485 $ 0.00 $ 28.50 81%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 150 MW,
600 MWh N/A 150 2024 50 $ 1,954 $ 12 $ 6.50 $ 12.67 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 150 MW,
1200 MWh N/A 150 2024 50 $ 2,189 $ 12 $ 6.50 $ 12.67 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 150 MW,
1800 MWh N/A 150 2024 50 $ 2,445 $ 12 $ 6.50 $ 12.67 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 300 MW,
1200 MWh N/A 300 2024 50 $ 1,557 $ 12 $ 6.50 $ 9.33 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 300 MW,
2400 MWh N/A 300 2024 50 $ 1,692 $ 12 $ 6.50 $ 9.33 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 300 MW,
3600 MWh N/A 300 2024 50 $ 2,016 $ 12 $ 6.50 $ 9.33 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 500 MW,
2000 MWh N/A 500 2024 50 $ 1,549 $ 12 $ 6.50 $ 6.60 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 500 MW,
4000 MWh N/A 500 2025 50 $ 1,762 $ 12 $ 6.50 $ 6.60 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage
Adiabatic CAES, Hydrostor, 500 MW,
6000 MWh N/A 500 2025 50 $ 2,010 $ 12 $ 6.50 $ 6.60 60%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 0.5 MWh N/A 1 2023 20 $ 1,948 $ 55 (a) $ 40.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 1 MWh N/A 1 2023 20 $ 2,058 $ 110 (a) $ 50.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 4 MWh N/A 1 2023 20 $ 3,167 $ 440 (a) $ 70.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 1 MW, 8 MWh N/A 1 2023 20 $ 4,622 $ 880 (a) $ 100.00 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Li-Ion Battery, , 50 MW, 200 MWh N/A 50 2023 20 $ 1,820 $ 440 (a) $ 27.60 85%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 1 MW, 1 MWh N/A 1 2023 20 $ 4,719 $ 12 (a) $ 13.00 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 1 MW, 4 MWh N/A 1 2023 20 $ 5,051 $ 12 (a) $ 13.00 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 1 MW, 8 MWh N/A 1 2023 20 $ 7,291 $ 12 (a) $ 27.00 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Storage Flow Battery, , 20 MW, 160 MWh N/A 20 2023 20 $ 4,190 $ 12 (a) $ 30.50 70%0.0 0.0 0.0000 0.0000 0.0000 0.0000 0.0000
Nuclear Small Modular Reactor 5,000 854 2028 60 $ 5,396 $ 722 $ 6.72 $ 65.03 N/A 5.0 5.0 N/A 0.0000 0.0000 0.0000 0.0000
Hydrogen Non-Emitting Peaker 5,050 206 2030 30 $ 959 $ 2,414 $ 21.29 $ - 9936 2.7 3.9 218.0000 0.0000 0.0000 0.0000 0.0000
Description Resource Characteristics Costs Operating Characteristics Environmental
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
175
Table 7.1 – 2021 Supply-Side Resource Table (2020$) (Continued)
Fuel Resource
Elevation
(AFSL)
Net
Capacity
(MW)
Commercial
Operation Year
Design Life
(yrs)
Base Capital
($/KW)
Var O&M
($/MWh)
Fixed O&M
($/KW-yr)
Average Full Load
Heat Rate (HHV
Btu/KWh)/Efficiency EFOR (%)POR (%)
Water Consumed
(Gal/MWh)
SO2
(lbs/MMBtu)
NOx
(lbs/MMBtu)Hg (lbs/TBTu)CO2 (lbs/MMBtu)
CCUS for Coal Plants Naughton 2 PC CCUS Retrofit 6,500 155 2026 20 $ 3,930 $ 37 $ 7.30 $ 39.90 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Johnston 2 PC CCUS Retrofit 6,500 82 2026 20 $ 5,314 $ 37 $ 6.10 $ 40.58 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Johnston 4 PC CCUS Retrofit 6,500 254 2026 20 $ 3,877 $ 37 $ 5.69 $ 37.88 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Wyodak PC CCUS Retrofit 6,500 206 2026 20 $ 3,935 $ 37 $ 7.31 $ 39.95 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Bridger 1 PC CCUS Retrofit 6,500 273 2026 20 $ 3,934 $ 37 $ 7.31 $ 39.94 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Bridger 3 PC CCUS Retrofit 6,500 269 2026 20 $ 3,873 $ 37 $ 5.69 $ 37.83 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
CCUS for Coal Plants Bridger 4 PC CCUS Retrofit 6,500 270 2026 20 $ 3,876 $ 37 $ 5.69 $ 37.86 1437200%5.0 5.0 450.0000 0.0050 0.0700 1.2000 20.5352
Description Resource Characteristics Costs Operating Characteristics Environmental
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
176
Table 7.2 - Total Resource Cost for Supply-Side Resource Options
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Resource Description Modeled IRP
Total Capital Cost
1/ Demolition Cost
Payment
Factor 1/
Annual Payment
($/kW-Yr)O&M 1/
Capitalized
Premium
O&M
Capitalized 1/ Gas Transportation 1/ Total
Total Fixed
($/kW-Yr)
SCCT Aero x3 No 0 $1,463 $10 7.497%$110.43 $0.00 1.262%$0.00 $31.94 $31.94 $142.37
Intercooled SCCT Aero x2 No 0 $1,126 $10 7.497%$85.14 $0.00 1.135%$0.00 $30.03 $30.03 $115.17
SCCT Frame "F" x1 No 0 $699 $10 7.049%$49.97 $0.00 0.273%$0.00 $33.77 $33.77 $83.74
Brownfield SCCT Frame "F" x1 No 0 $674 $10 7.049%$48.20 $0.00 0.273%$0.00 $33.77 $33.77 $81.97
IC Recips x 6 No 0 $1,938 $12 7.049%$137.45 $0.00 0.136%$0.00 $28.47 $28.47 $165.92
CCCT Dry "H", 1x1 No 0 $1,396 $10 6.886%$96.84 $0.00 0.146%$0.00 $23.57 $23.57 $120.41
CCCT Dry "H", DF, 1x1 No 0 $470 $0 6.886%$32.34 $0.00 0.000%$0.00 $23.57 $23.57 $55.91
CCCT Dry "H", 2x1 No 0 $1,019 $10 6.886%$70.86 $0.00 0.146%$0.00 $23.62 $23.62 $94.48
CCCT Dry "H", DF, 2x1 No 0 $357 $0 6.886%$24.60 $0.00 0.000%$0.00 $23.62 $23.62 $48.22
Brownfield CCCT Dry "H", DF, 2x1 No 0 $1,019 $10 6.886%$70.83 $0.00 0.000%$0.00 $23.36 $23.36 $94.19
CCCT Dry "J", 1x1 No 0 $1,065 $10 6.886%$73.99 $0.00 0.000%$0.00 $23.36 $23.36 $97.35
CCCT Dry "J", DF, 1x1 No 0 $397 $0 6.886%$27.36 $0.00 0.000%$0.00 $23.36 $23.36 $50.73
CCCT Dry "J", 2x1 No 0 $787 $10 6.886%$54.88 $0.00 0.146%$0.00 $23.36 $23.36 $78.25
CCCT Dry "J", DF, 2x1 No 0 $309 $0 6.886%$21.30 $0.00 0.000%$0.00 $23.36 $23.36 $44.66
SCCT Aero x3 No 1,500 $1,551 $14 7.497%$117.36 $0.00 1.262%$0.00 $31.76 $31.76 $149.12
Intercooled SCCT Aero x2 No 1,500 $1,188 $14 7.497%$90.12 $0.00 1.135%$0.00 $29.91 $29.91 $120.03
SCCT Frame "F" x1 No 1,500 $738 $14 7.049%$52.98 $0.00 0.273%$0.00 $33.71 $33.71 $86.68
Brownfield SCCT Frame "F" x1 No 1,500 $711 $14 7.049%$51.11 $0.00 0.273%$0.00 $33.71 $33.71 $84.82
IC Recips x 6 No 1,500 $1,938 $12 7.049%$137.45 $0.00 0.136%$0.00 $28.47 $28.47 $165.92
CCCT Dry "H", 1x1 No 1,500 $1,484 $14 6.886%$103.13 $0.00 0.146%$0.00 $23.37 $23.37 $126.49
CCCT Dry "H", DF, 1x1 No 1,500 $470 $0 6.886%$32.35 $0.00 0.000%$0.00 $23.37 $23.37 $55.71
CCCT Dry "H", 2x1 No 1,500 $1,077 $14 6.886%$75.15 $0.00 0.146%$0.00 $23.41 $23.41 $98.56
CCCT Dry "H", DF, 2x1 No 1,500 $357 $0 6.886%$24.60 $0.00 0.000%$0.00 $23.41 $23.41 $48.01
Brownfield CCCT Dry "H", DF, 2x1 No 1,500 $1,077 $14 6.886%$75.11 $0.00 0.000%$0.00 $23.17 $23.17 $98.29
CCCT Dry "J", 1x1 No 1,500 $1,125 $14 6.886%$78.43 $0.00 0.000%$0.00 $23.17 $23.17 $101.61
CCCT Dry "J", DF, 1x1 No 1,500 $397 $0 6.886%$27.37 $0.00 0.000%$0.00 $23.17 $23.17 $50.54
CCCT Dry "J", 2x1 No 1,500 $832 $14 6.886%$58.24 $0.00 0.146%$0.00 $23.17 $23.17 $81.41
CCCT Dry "J", DF, 2x1 No 1,500 $309 $0 6.886%$21.30 $0.00 0.000%$0.00 $23.17 $23.17 $44.47
SCCT Aero x3 No 3,000 $1,645 $11 7.497%$124 $0.00 1.262%$0.00 $16.94 $16.94 $141.12
Intercooled SCCT Aero x2 No 3,000 $1,260 $11 7.497%$95 $0.00 1.135%$0.00 $15.94 $15.94 $111.26
SCCT Frame "F" x1 No 3,000 $779 $11 7.049%$56 $0.00 0.273%$0.00 $17.98 $17.98 $73.70
Brownfield SCCT Frame "F" x1 No 3,000 $751 $11 7.049%$54 $0.00 0.273%$0.00 $17.98 $17.98 $71.73
Capital Cost $/kW Fixed Cost
Elevation (AFSL)
Fixed O&M $/kW-Yr
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
177
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Resource Description Modeled IRP Elevation (AFSL)
Total Capital Cost
1/ Demolition Cost
Payment
Factor 1/
Annual
Payment
($/kW-Yr)O&M 1/
Capitalized
Premium
O&M
Capitalized 1/ Gas Transportation 1/ Total
Total Fixed
($/kW-Yr)
IC Recips x 6 No 3,000 $1,938 $12 7.049%$137.45 $0.00 0.136%$0.00 $15.18 $15.18 $152.62
CCCT Dry "H", 1x1 No 3,000 $1,569 $11 6.886%$108.80 $0.00 0.146%$0.00 $23.28 $23.28 $132.08
CCCT Dry "H", DF, 1x1 No 3,000 $470 $0 6.886%$32.35 $0.00 0.000%$0.00 $23.28 $23.28 $55.62
CCCT Dry "H", 2x1 No 3,000 $1,144 $11 6.886%$79.55 $0.00 0.146%$0.00 $12.43 $12.43 $91.98
CCCT Dry "H", DF, 2x1 No 3,000 $357 $0 6.886%$24.60 $0.00 0.000%$0.00 $12.43 $12.43 $37.03
Brownfield CCCT Dry "H", DF, 2x1 No 3,000 $1,144 $11 6.886%$79.51 $0.00 0.000%$0.00 $12.27 $12.27 $91.78
CCCT Dry "J", 1x1 No 3,000 $1,189 $11 6.886%$82.65 $0.00 0.000%$0.00 $12.27 $12.27 $94.92
CCCT Dry "J", DF, 1x1 No 3,000 $397 $0 6.886%$27.37 $0.00 0.000%$0.00 $12.27 $12.27 $39.64
CCCT Dry "J", 2x1 No 3,000 $879 $11 6.886%$61.29 $0.00 0.146%$0.00 $12.28 $12.28 $73.57
CCCT Dry "J", DF, 2x1 No 3,000 $309 $0 6.886%$21.30 $0.00 0.000%$0.00 $12.28 $12.28 $33.58
SCCT Aero x3 No 5,050 $1,777 $12 7.497%$134.18 $0.00 1.262%$0.00 $14.06 $14.06 $148.23
Intercooled SCCT Aero x2 Yes 5,050 $1,363 $12 7.497%$103.10 $0.00 1.135%$0.00 $13.22 $13.22 $116.32
SCCT Frame "F" x1 Yes 5,050 $841 $12 7.049%$60.13 $0.00 0.273%$0.00 $14.93 $14.93 $75.07
Brownfield SCCT Frame "F" x1 Yes 5,050 $811 $12 7.049%$58.00 $0.00 0.273%$0.00 $14.93 $14.93 $72.94
IC Recips x 6 Yes 5,050 $1,938 $12 7.049%$137.45 $0.00 0.136%$0.00 $12.61 $12.61 $150.06
CCCT Dry "H", 1x1 Yes 5,050 $1,687 $12 6.886%$116.98 $0.00 0.146%$0.00 $9.91 $9.91 $126.89
CCCT Dry "H", DF, 1x1 Yes 5,050 $470 $0 6.886%$32.35 $0.00 0.000%$0.00 $9.91 $9.91 $42.26
CCCT Dry "H", 2x1 No 5,050 $1,252 $12 6.886%$87.04 $0.00 0.146%$0.00 $9.93 $9.93 $96.97
CCCT Dry "H", DF, 2x1 No 5,050 $358 $0 6.886%$24.63 $0.00 0.000%$0.00 $9.93 $9.93 $34.56
Brownfield CCCT Dry "H", DF, 2x1 Yes 5,050 $1,251 $12 6.886%$87.00 $0.00 0.000%$0.00 $9.84 $9.84 $96.84
CCCT Dry "J", 1x1 Yes 5,050 $1,299 $12 6.886%$90.28 $0.00 0.000%$0.00 $9.84 $9.84 $100.13
CCCT Dry "J", DF, 1x1 Yes 5,050 $397 $0 6.886%$27.36 $0.00 0.000%$0.00 $9.84 $9.84 $37.21
CCCT Dry "J", 2x1 No 5,050 $966 $12 6.886%$67.34 $0.00 0.146%$0.00 $9.85 $9.85 $77.19
CCCT Dry "J", DF, 2x1 No 5,050 $309 $0 6.886%$21.29 $0.00 0.000%$0.00 $9.85 $9.85 $31.15
SCCT Aero x3 No 6,500 $1,957 $13 7.497%$147.74 $0.00 1.262%$0.00 $9.13 $9.13 $156.86
Intercooled SCCT Aero x2 Yes 6,500 $1,427 $13 7.497%$107.96 $0.00 1.135%$0.00 $8.62 $8.62 $116.58
SCCT Frame "F" x1 Yes 6,500 $886 $13 7.049%$63.37 $0.00 0.273%$0.00 $9.70 $9.70 $73.06
Brownfield SCCT Frame "F" x1 Yes 6,500 $854 $13 7.049%$61.12 $0.00 0.273%$0.00 $9.70 $9.70 $70.82
IC Recips x 6 Yes 6,500 $1,937 $12 7.049%$137.42 $0.00 0.136%$0.00 $8.24 $8.24 $145.66
CCCT Dry "H", 1x1 Yes 6,500 $1,761 $13 6.886%$122.11 $0.00 0.146%$0.00 $20.66 $20.66 $142.77
Fixed O&M $/kW-Yr
Capital Cost $/kW Fixed Cost
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
178
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Resource Description Modeled IRP Elevation (AFSL)
Total Capital Cost
1/ Demolition Cost
Payment
Factor 1/
Annual
Payment
($/kW-Yr)O&M 1/
Capitalized
Premium
O&M
Capitalized 1/ Gas Transportation 1/ Total
Total Fixed
($/kW-Yr)
CCCT Dry "H", DF, 1x1 Yes 6,500 $470 $0 6.886%$32.35 $0.00 0.000%$0.00 $20.66 $20.66 $53.01
CCCT Dry "H", 2x1 No 6,500 $1,283 $12 6.886%$89.23 $0.00 0.146%$0.00 $6.71 $6.71 $95.94
CCCT Dry "H", DF, 2x1 No 6,500 $357 $0 6.886%$24.61 $0.00 0.000%$0.00 $6.71 $6.71 $31.32
Brownfield CCCT Dry "H", DF, 2x1 Yes 6,500 $1,283 $12 6.886%$89.18 $0.00 0.000%$0.00 $6.62 $6.62 $95.80
CCCT Dry "J", 1x1 Yes 6,500 $1,337 $12 6.886%$92.91 $0.00 0.000%$0.00 $6.62 $6.62 $99.53
CCCT Dry "J", DF, 1x1 Yes 6,500 $397 $0 6.886%$27.36 $0.00 0.000%$0.00 $6.62 $6.62 $33.98
CCCT Dry "J", 2x1 No 6,500 $988 $12 6.886%$68.90 $0.00 0.146%$0.00 $6.62 $6.62 $75.53
CCCT Dry "J", DF, 2x1 No 6,500 $309 $0 6.886%$21.30 $0.00 0.000%$0.00 $6.62 $6.62 $27.92
SCPC with CCS No 4,500 $6,488 $127 6.822%$451.29 $72.22 5.541%$4.00 $0.00 $76.23 $527.52
IGCC with CCS No 4,500 $6,282 $60 7.389%$468.60 $58.20 0.000%$0.00 $0.00 $58.20 $526.80
PC CCS retrofit @ 500 MW pre-retrofit basis Yes 4,500 $2,971 $37 6.822%$205.19 $28.18 5.541%$1.56 $0.00 $29.74 $234.92
SCPC with CCS No 6,500 $7,348 $127 6.822%$509.92 $67.09 5.541%$3.72 $0.00 $70.80 $580.72
IGCC with CCS No 6,500 $7,113 $60 7.389%$530.01 $63.40 0.000%$0.00 $0.00 $63.40 $593.41
PC CCS retrofit @ 500 MW pre-retrofit basis Yes 6,500 $2,971 $37 6.822%$205.19 $28.18 5.541%$1.56 $0.00 $29.74 $234.92
Blundell Dual Flash 90% CF Yes 4,500 $5,708 $127 6.273%$366.02 $103.85 0.875%$0.91 $0.00 $104.76 $470.77
Greenfield Binary 90% CF Yes 4,500 $5,973 $127 6.273%$382.70 $103.85 0.000%$0.00 $0.00 $103.85 $486.55
Generic Geothermal PPA 90% CF Yes 4,500 $0 $0 6.273%$0.00 $0.00 0.000%$0.00 $0.00 $0.00 $0.00
Pocatello, ID, 200 MW Wind, CF: 37.1% (100% PTC)Yes 4,500 $1,365 $13 6.979%$96.14 $24.74 0.000%$0.00 $0.00 $24.74 $120.88
Arlington, OR, 200 MW Wind, CF: 37.1% (100% PTC)Yes 1,500 $1,315 $13 6.979%$92.67 $24.74 0.000%$0.00 $0.00 $24.74 $117.41
Monticello, UT, 200 MW Wind, CF: 29.5% (100% PTC)Yes 4,500 $1,306 $13 6.979%$92.05 $24.74 0.000%$0.00 $0.00 $24.74 $116.79
Medicine Bow, WY, 200 MW Wind, CF: 43.6% (100%PTC)Yes 6,500 $1,356 $13 6.979%$95.54 $24.74 0.000%$0.00 $0.00 $24.74 $120.28
Goldendale, WA, 200 MW Wind, CF: 37.1% (100% PTC)Yes 1,500 $1,390 $13 6.979%$97.89 $24.74 0.000%$0.00 $0.00 $24.74 $122.63
Pocatello, ID, 200 MW Wind, CF: 37.1% (60% PTC)Yes 4,500 $1,365 $13 6.979%$96.14 $24.74 0.000%$0.00 $0.00 $24.74 $120.88
Arlington, OR, 200 MW Wind, CF: 37.1% (60% PTC)Yes 1,500 $1,315 $13 6.979%$92.67 $24.74 0.000%$0.00 $0.00 $24.74 $117.41
Monticello, UT, 200 MW Wind, CF: 29.5% (60% PTC)Yes 4,500 $1,306 $13 6.979%$92.05 $24.74 0.000%$0.00 $0.00 $24.74 $116.79
Medicine Bow, WY, 200 MW Wind, CF: 43.6% (60% PTC)Yes 6,500 $1,356 $13 6.979%$95.54 $24.74 0.000%$0.00 $0.00 $24.74 $120.28
Goldendale, WA, 200 MW Wnd, CF: 37.1% (60% PTC)Yes 1,500 $1,390 $13 6.979%$97.89 $24.74 0.000%$0.00 $0.00 $24.74 $122.63
Pocatello, ID, 200 MW Wind, CF: 37.1% + BESS: 50% pwr, 4 hours Yes 4,500 $2,152 $233 6.979%$166.45 $37.59 2.902%$1.09 $0.00 $38.68 $205.13
Arlington, OR, 200 MW Wind, CF: 37.1% + BESS: 50% pwr, 4 hours Yes 1,500 $2,086 $233 6.979%$161.82 $37.59 2.902%$1.09 $0.00 $38.68 $200.50
Monticello, UT, 200 MW Wind, CF: 29.5% + BESS: 50% pwr, 4 hours Yes 4,500 $2,061 $233 6.979%$160.06 $37.59 2.902%$1.09 $0.00 $38.68 $198.74
Medicine Bow, WY, 200 MW Wind, CF: 43.6% + BESS: 50% pwr, 4 hours Yes 6,500 $2,136 $233 6.979%$165.29 $37.59 2.902%$1.09 $0.00 $38.68 $203.97
Goldendale, WA, 200 MW Wind, CF: 37.1% + BESS: 50% pwr, 4 hours Yes 1,500 $2,211 $233 6.979%$170.52 $37.59 2.902%$1.09 $0.00 $38.68 $209.20
Idaho Falls, ID, 100 MW Solar, CF: 26.1% (30% ITC)Yes 4,700 $1,429 $35 6.839%$100.09 $16.20 1.379%$0.22 $0.00 $16.42 $116.52
Idaho Falls, ID, 200 MW Solar, CF: 26.1% (30% ITC)Yes 4,700 $1,302 $35 6.839%$91.44 $16.10 1.379%$0.22 $0.00 $16.32 $107.77
Lakeview, OR, 100 MW Solar, CF: 27.6% (30% ITC)Yes 4,800 $1,444 $35 6.839%$101.18 $16.20 1.379%$0.22 $0.00 $16.42 $117.61
Lakeview, OR, 200 MW Solar, CF: 27.6% (30% ITC)Yes 4,800 $1,330 $35 6.839%$93.38 $16.10 1.379%$0.22 $0.00 $16.32 $109.70
Milford, UT, 100 MW Solar, CF: 30.2% (30% ITC)Yes 5,000 $1,422 $35 6.839%$99.67 $17.60 1.379%$0.24 $0.00 $17.84 $117.51
Milford, UT, 200 MW Solar, CF: 30.2% (30% ITC)Yes 5,000 $1,297 $35 6.839%$91.11 $17.60 1.379%$0.24 $0.00 $17.84 $108.95
Rock Springs, WY, 100 MW Solar, CF: 27.9% (30% ITC)Yes 6,400 $1,423 $35 6.839%$99.70 $17.60 1.379%$0.24 $0.00 $17.84 $117.55
Rock Springs, WY, 200 MW Solar, CF: 27.9% (30% ITC)Yes 6,400 $1,297 $35 6.839%$91.07 $17.60 1.379%$0.24 $0.00 $17.84 $108.91
Yakima, WA, 100 MW Solar, CF: 24.2% (30% ITC)Yes 1,000 $1,486 $35 6.839%$104.04 $17.60 1.379%$0.24 $0.00 $17.84 $121.88
Yakima, WA, 200 MW Solar, CF: 24.2% (30% ITC)Yes 1,000 $1,357 $35 6.839%$95.20 $17.60 1.379%$0.24 $0.00 $17.84 $113.04
Idaho Falls, ID, 100 MW Solar, CF: 26.1% (10% ITC)Yes 4,700 $1,429 $35 6.839%$100.09 $16.20 1.379%$0.22 $0.00 $16.42 $116.52
Idaho Falls, ID, 200 MW Solar, CF: 26.1% (10% ITC)Yes 4,700 $1,302 $35 6.839%$91.44 $16.10 1.379%$0.22 $0.00 $16.32 $107.77
Lakeview, OR, 100 MW Solar, CF: 27.6% (10% ITC)Yes 4,800 $1,444 $35 6.839%$101.18 $16.20 1.379%$0.22 $0.00 $16.42 $117.61
Lakeview, OR, 200 MW Solar, CF: 27.6% (10% ITC)Yes 4,800 $1,330 $35 6.839%$93.38 $16.10 1.379%$0.22 $0.00 $16.32 $109.70
Milford, UT, 100 MW Solar, CF: 30.2% (10% ITC)Yes 5,000 $1,422 $35 6.839%$99.67 $17.60 1.379%$0.24 $0.00 $17.84 $117.51
Milford, UT, 200 MW Solar, CF: 30.2% (10% ITC)Yes 5,000 $1,297 $35 6.839%$91.11 $17.60 1.379%$0.24 $0.00 $17.84 $108.95
Rock Springs, WY, 100 MW Solar, CF: 27.9% (10% ITC)Yes 6,400 $1,423 $35 6.839%$99.70 $17.60 1.379%$0.24 $0.00 $17.84 $117.55
Rock Springs, WY, 200 MW Solar, CF: 27.9% (10% ITC)Yes 6,400 $1,297 $35 6.839%$91.07 $17.60 1.379%$0.24 $0.00 $17.84 $108.91
Capital Cost $/kW Fixed Cost
Fixed O&M $/kW-Yr
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
179
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Resource Description No Elevation (AFSL)
Total Capital Cost
1/ Demolition Cost
Payment
Factor 1/
Annual Payment
($/kW-Yr)O&M 1/
Capitalized
Premium
O&M
Capitalized 1/ Gas Transportation 1/ Total
Total Fixed
($/kW-Yr)
Idaho Falls, ID, 100 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (30% ITC)Yes 4,700 $2,351 $255 6.839%$178.25 $30.00 1.379%$0.41 $0.00 $30.41 $208.66
Idaho Falls, ID, 200 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (30% ITC)Yes 4,700 $2,161 $255 6.839%$165.25 $28.95 1.379%$0.40 $0.00 $29.35 $194.60
Yakima, WA, 100 MW Solar, CF: 24.2% (10% ITC)Yes 1,000 $1,486 $35 6.839%$104.04 $17.60 1.379%$0.24 $0.00 $17.84 $121.88
Yakima, WA, 200 MW Solar, CF: 24.2% (10% ITC)Yes 1,000 $1,357 $35 6.839%$95.20 $17.60 1.379%$0.24 $0.00 $17.84 $113.04
Lakeview, OR, 100 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (30% ITC)Yes 4,800 $2,329 $255 6.839%$176.71 $30.00 1.379%$0.41 $0.00 $30.41 $207.12
Lakeview, OR, 200 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (30% ITC)Yes 4,800 $2,154 $255 6.839%$164.74 $28.95 1.379%$0.40 $0.00 $29.35 $194.09
Milford, UT, 100 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (30% ITC)Yes 5,000 $2,283 $255 6.839%$173.58 $31.40 1.379%$0.43 $0.00 $31.83 $205.41
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (30% ITC)Yes 5,000 $2,102 $255 6.839%$161.21 $30.45 1.379%$0.42 $0.00 $30.87 $192.08
Rock Springs, WY, 100 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (30% ITC)Yes 6,400 $2,312 $255 6.839%$175.57 $31.40 1.379%$0.43 $0.00 $31.83 $207.40
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (30% ITC)Yes 6,400 $2,128 $255 6.839%$163.01 $30.45 1.379%$0.42 $0.00 $30.87 $193.88
Yakima, WA, 100 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (30% ITC)Yes 1,000 $2,405 $255 6.839%$181.91 $31.40 1.379%$0.43 $0.00 $31.83 $213.74
Yakima, WA, 200 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (30% ITC)Yes 1,000 $2,217 $255 6.839%$169.05 $30.45 1.379%$0.42 $0.00 $30.87 $199.92
Idaho Falls, ID, 100 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (10% ITC)Yes 4,700 $2,351 $255 6.839%$178.25 $30.00 1.379%$0.41 $0.00 $30.41 $208.66
Idaho Falls, ID, 200 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (10% ITC)Yes 4,700 $2,161 $255 6.839%$165.25 $28.95 1.379%$0.40 $0.00 $29.35 $194.60
Lakeview, OR, 100 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (10% ITC)Yes 4,800 $2,329 $255 6.839%$176.71 $30.00 1.379%$0.41 $0.00 $30.41 $207.12
Lakeview, OR, 200 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (10% ITC)Yes 4,800 $2,154 $255 6.839%$164.74 $28.95 1.379%$0.40 $0.00 $29.35 $194.09
Milford, UT, 100 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (10% ITC)Yes 5,000 $2,283 $255 6.839%$173.58 $31.40 1.379%$0.43 $0.00 $31.83 $205.41
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (10% ITC)Yes 5,000 $2,102 $255 6.839%$161.21 $30.45 1.379%$0.42 $0.00 $30.87 $192.08
Rock Springs, WY, 100 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (10% ITC)Yes 6,400 $2,312 $255 6.839%$175.57 $31.40 1.379%$0.43 $0.00 $31.83 $207.40
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (10% ITC)Yes 6,400 $2,128 $255 6.839%$163.01 $30.45 1.379%$0.42 $0.00 $30.87 $193.88
Yakima, WA, 100 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (10% ITC)Yes 1,000 $2,405 $255 6.839%$181.91 $31.40 1.379%$0.43 $0.00 $31.83 $213.74
Yakima, WA, 200 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (10% ITC)Yes 1,000 $2,217 $255 6.839%$169.05 $30.45 1.379%$0.42 $0.00 $30.87 $199.92
Idah Falls, ID, 200 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours + 200 MW Wind No 4,700 $3,395 $268 6.839%$250.50 $82.95 1.379%$1.14 $0.00 $84.09 $334.59
Lakeview, OR, 200 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours + 200 MW Wind No 4,800 $3,424 $268 6.839%$252.44 $82.95 1.379%$1.14 $0.00 $84.09 $336.53
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours + 200 MW Wind No 5,000 $3,364 $268 6.839%$248.37 $81.45 1.379%$1.12 $0.00 $82.57 $330.95
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours + 200 MW Wind No 6,400 $3,364 $268 6.839%$248.33 $81.45 1.379%$1.12 $0.00 $82.57 $330.90
Yakima, WA, 200 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours + 200 MW Wind No 1,000 $3,424 $268 6.839%$252.46 $81.45 1.379%$1.12 $0.00 $82.57 $335.04
Pumped Hydro, Swan Lake. 3600 MWh Yes N/A $3,095 $485 6.251%$223.78 $12.50 0.000%$0.00 $0.00 $12.50 $236.28
Pumped Hydro, Goldendale, 14400 MWh Yes N/A $2,833 $485 6.251%$207.43 $12.50 0.000%$0.00 $0.00 $12.50 $219.93
Pumped Hydro, Seminoe, 7500 MWh Yes N/A $3,461 $485 6.111%$241.13 $16.00 0.000%$0.00 $0.00 $16.00 $257.13
Pumped Hydro, Badger Mountain, 4000 MWh Yes N/A $2,621 $485 6.111%$189.78 $28.00 0.000%$0.00 $0.00 $28.00 $217.78
Pumped Hydro, Owyhee, 4800 MWh Yes N/A $3,203 $485 6.111%$225.33 $20.00 0.000%$0.00 $0.00 $20.00 $245.33
Pumped Hydro, Flat Canyon, 1800 MWh Yes N/A $4,046 $485 6.111%$276.88 $53.33 0.000%$0.00 $0.00 $53.33 $330.22
Pumped Hydro, Utah PS2, 4000 MWh Yes N/A $3,237 $485 6.111%$227.44 $28.00 0.000%$0.00 $0.00 $28.00 $255.44
Pumped Hydro, Utah PS3, 4800 MWh Yes N/A $3,371 $485 6.111%$235.63 $20.00 0.000%$0.00 $0.00 $20.00 $255.63
Pumped Hydro, Banner Mountain, 3400 MWh Yes N/A $3,276 $485 6.479%$243.64 $28.50 0.000%$0.00 $0.00 $28.50 $272.14
Adiabatic CAES, Hydrostor, 150 MW, 600 MWh No N/A $1,954 $12 7.497%$147.40 $12.67 0.000%$0.00 $0.00 $12.67 $160.06
Adiabatic CAES, Hydrostor, 150 MW, 1200 MWh No N/A $2,189 $12 7.497%$165.01 $12.67 0.000%$0.00 $0.00 $12.67 $177.67
Adiabatic CAES, Hydrostor, 150 MW, 1800 MWh No N/A $2,445 $12 7.497%$184.22 $12.67 0.000%$0.00 $0.00 $12.67 $196.89
Adiabatic CAES, Hydrostor, 300 MW, 1200 MWh No N/A $1,557 $12 7.497%$117.65 $9.33 0.000%$0.00 $0.00 $9.33 $126.98
Adiabatic CAES, Hydrostor, 300 MW, 2400 MWh No N/A $1,692 $12 7.497%$127.79 $9.33 0.000%$0.00 $0.00 $9.33 $137.12
Adiabatic CAES, Hydrostor, 300 MW, 3600 MWh No N/A $2,016 $12 7.497%$152.05 $9.33 0.000%$0.00 $0.00 $9.33 $161.38
Adiabatic CAES, Hydrostor, 500 MW, 2000 MWh Yes N/A $1,549 $12 7.497%$117.06 $6.60 0.000%$0.00 $0.00 $6.60 $123.66
Adiabatic CAES, Hydrostor, 500 MW, 4000 MWh Yes N/A $1,762 $12 7.497%$132.99 $6.60 0.000%$0.00 $0.00 $6.60 $139.59
Adiabatic CAES, Hydrostor, 500 MW, 6000 MWh Yes N/A $2,010 $12 7.497%$151.61 $6.60 0.000%$0.00 $0.00 $6.60 $158.21
Li-Ion Battery, , 1 MW, 0.5 MWh No N/A $1,948 $55 8.676%$173.74 $40.00 0.000%$0.00 $0.00 $40.00 $213.74
Li-Ion Battery, , 1 MW, 1 MWh No N/A $2,058 $110 8.676%$188.13 $50.00 0.000%$0.00 $0.00 $50.00 $238.13
Non-Emitting Peaker Yes 5,050 $959 $2,414 7.497%$252.85 $0.00 0.000%$0.00 $0.00 $0.00 $252.85
Li-Ion Battery, , 50 MW, 200 MWh Yes N/A $1,820 $440 8.676%$196.05 $27.60 0.000%$0.00 $0.00 $27.60 $223.65
Flow Battery, , 1 MW, 1 MWh No N/A $4,719 $12 8.676%$410.44 $13.00 0.000%$0.00 $0.00 $13.00 $423.44
Flow Battery, , 1 MW, 4 MWh No N/A $5,051 $12 8.676%$439.29 $13.00 0.000%$0.00 $0.00 $13.00 $452.29
Flow Battery, , 1 MW, 8 MWh No N/A $7,291 $12 8.676%$633.58 $27.00 0.000%$0.00 $0.00 $27.00 $660.58
Flow Battery, , 20 MW, 160 MWh Yes N/A $4,190 $12 8.676%$364.59 $30.50 0.000%$0.00 $0.00 $30.50 $395.09
Small Modular Reactor Yes 5,000 $5,396 $722 6.733%$411.88 $65.03 5.687%$3.70 $0.00 $68.73 $480.61
Non-Emitting Peaker Yes 5,050 $959 $2,414 7.497%$252.85 $0.00 0.000%$0.00 $0.00 $0.00 $252.85
Capital Cost $/kW Fixed Cost
Fixed O&M $/kW-Yr
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
180
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Resource Description Modeled IRP Elevation (AFSL)
Total Capital and
Environmental Cost
1/ Demolition Cost
Payment
Factor 1/
Annual
Payment
($/kW-Yr)O&M 1/
Capitalized
Premium
O&M
Capitalized 1/ Gas Transportation 1/ Total
Total Fixed
($/kW-Yr)
Brownfield Site
Utah (Hunter, Huntington)
Brownfield SCCT Frame "F" x1 Yes 5,050 $811 $12 7.049%$58.00 0.00 0.273%$0.00 $14.93 $14.93 $72.94
Intercooled SCCT Aero x2 Yes 5,050 $1,363 $12 7.497%$103.10 0.00 1.135%$0.00 $13.22 $13.22 $116.32
Brownfield CCCT Dry "H", DF, 2x1 Yes 5,050 $1,251 $12 6.886%$87.00 0.00 0.000%$0.00 $9.84 $9.84 $96.84
CCCT Dry "J", 1x1 Yes 5,050 $1,299 $12 6.886%$90.28 0.00 0.000%$0.00 $9.84 $9.84 $100.13
Milford, UT, 200 MW Solar, CF: 30.2% (10% ITC)Yes 5,000 $1,297 $35 6.839%$91.11 17.60 1.379%$0.24 $0.00 $17.84 $108.95
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (30% ITC)Yes 5,000 $2,102 $255 6.839%$161.21 30.45 1.379%$0.42 $0.00 $30.87 $192.08
Wyoming (Bridger, Johnston, Wyodak)
Brownfield SCCT Frame "F" x1 Yes 6,500 $854 $13 7.049%$61.12 0.00 0.273%$0.00 $9.70 $9.70 $70.82
Intercooled SCCT Aero x2 Yes 6,500 $1,427 $13 7.497%$107.96 0.00 1.135%$0.00 $8.62 $8.62 $116.58
Brownfield CCCT Dry "H", DF, 2x1 Yes 6,500 $1,283 $12 6.886%$89.18 0.00 0.000%$0.00 $6.62 $6.62 $95.80
CCCT Dry "J", 1x1 Yes 6,500 $1,337 $12 6.886%$92.91 0.00 0.000%$0.00 $6.62 $6.62 $99.53
Medicine Bow, WY, 200 MW Wind, CF: 43.6% (60% PTC)Yes 6,500 $1,356 $13 6.979%$95.54 24.74 0.000%$0.00 $0.00 $24.74 $120.28
Medicine Bow, WY, 200 MW Wind, CF: 43.6% + BESS: 50% pwr, 4 hours Yes 6,500 $2,136 $233 6.979%$165.29 37.59 2.902%$1.09 $0.00 $38.68 $203.97
Rock Springs, WY, 200 MW Solar, CF: 27.9% (10% ITC)Yes 6,400 $1,297 $35 6.839%$91.07 17.60 1.379%$0.24 $0.00 $17.84 $108.91
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (30% ITC)Yes 6,400 $2,128 $255 6.839%$163.01 30.45 1.379%$0.42 $0.00 $30.87 $193.88
Naughton 1 PC CCUS Retrofit Yes 6,500 $3,939 $37 8.920%$354.70 39.99 5.541%$2.22 $0.00 $42.21 $396.91
Naughton 2 PC CCUS Retrofit Yes 6,500 $3,930 $37 8.920%$353.83 39.90 5.541%$2.21 $0.00 $42.11 $395.94
Johnston 2 PC CCUS Retrofit Yes 6,500 $5,314 $37 8.920%$477.27 40.58 5.541%$2.25 $0.00 $42.83 $520.10
Johnston 4 PC CCUS Retrofit Yes 6,500 $3,877 $37 8.920%$349.16 37.88 5.541%$2.10 $0.00 $39.97 $389.13
Wyodak PC CCUS Retrofit Yes 6,500 $3,935 $37 9.010%$357.86 39.95 5.541%$2.21 $0.00 $42.16 $400.02Bridger 1 PC CCUS Retrofit Yes 6,500 $3,934 $37 8.920%$354.24 39.94 5.541%$2.21 $0.00 $42.15 $396.39
Bridger 3 PC CCUS Retrofit Yes 6,500 $3,873 $37 9.010%$352.29 37.83 5.541%$2.10 $0.00 $39.93 $392.22
Bridger 4 PC CCUS Retrofit Yes 6,500 $3,876 $37 9.010%$352.56 37.86 5.541%$2.10 $0.00 $39.96 $392.52
Fixed O&M $/kW-Yr
Capital Cost $/kW Fixed Cost
0
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
181
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($) Credits
Resource Description Capacity Factor 2/Total Fixed ($/MWh)
Storage
Efficiency $/mmBtu $/MWh O&M 1/
Capitalized
Premium O&M Capitalized
1/
Integration Cost
1/ Total Resource Cost
PTC Tax Credits / ITC (Solar
Only) / 45Q Tax Credits (CCUS
Only)
Total Resource Cost -
with PTC / ITC / 45Q
Credits
SCCT Aero x3 0 33%$49.25 N/A 2.97$ 27.77$ 7.44$ 11.48%0.85$ -$ $85.32 -$ $85.32
Intercooled SCCT Aero x2 0 33%$39.84 N/A 2.97$ 26.13$ 5.03$ 11.48%0.58$ -$ $71.58 -$ $71.58
SCCT Frame "F" x1 0 33%$28.97 N/A 2.97$ 29.44$ 14.16$ 13.23%1.87$ -$ $74.44 -$ $74.44
Brownfield SCCT Frame "F" x1 0 33%$28.36 N/A 2.97$ 29.44$ 14.16$ 13.23%1.87$ -$ $73.83 -$ $73.83
IC Recips x 6 0 33%$57.40 N/A 2.97$ 24.61$ 10.39$ 8.73%0.91$ -$ $93.30 -$ $93.30
CCCT Dry "H", 1x1 0 78%$17.62 N/A 2.97$ 18.84$ 1.77$ 10.21%0.18$ -$ $38.41 -$ $38.41
CCCT Dry "H", DF, 1x1 0 12%$53.19 N/A 2.97$ 26.25$ 0.05$ 0.00%-$ -$ $79.49 -$ $79.49
CCCT Dry "H", 2x1 0 78%$13.83 N/A 2.97$ 18.89$ 1.71$ 10.79%0.18$ -$ $34.61 -$ $34.61
CCCT Dry "H", DF, 2x1 0 12%$45.87 N/A 2.97$ 25.73$ 0.05$ 0.00%-$ -$ $71.65 -$ $71.65
Brownfield CCCT Dry "H", DF, 2x1 0 78%$13.78 N/A 2.97$ 19.63$ 1.08$ 10.21%0.11$ -$ $34.61 -$ $34.61
CCCT Dry "J", 1x1 0 78%$14.25 N/A 2.97$ 18.60$ 1.48$ 10.21%0.15$ -$ $34.49 -$ $34.49
CCCT Dry "J", DF, 1x1 0 12%$48.26 N/A 2.97$ 26.05$ 0.06$ 0.00%-$ -$ $74.36 -$ $74.36
CCCT Dry "J", 2x1 0 78%$11.45 N/A 2.97$ 18.57$ 1.43$ 10.79%0.15$ -$ $31.60 -$ $31.60
CCCT Dry "J", DF, 2x1 0 12%$42.48 N/A 2.97$ 25.85$ 0.06$ 0.00%-$ -$ $68.39 -$ $68.39
SCCT Aero x3 1,500 33%$51.59 N/A 2.97$ 27.81$ 7.89$ 11.48%0.91$ -$ $88.19 -$ $88.19
Intercooled SCCT Aero x2 1,500 33%$41.52 N/A 2.97$ 26.14$ 5.31$ 11.48%0.61$ -$ $73.58 -$ $73.58
SCCT Frame "F" x1 1,500 33%$29.99 N/A 2.97$ 29.45$ 14.94$ 13.23%1.98$ -$ $76.36 -$ $76.36
Brownfield SCCT Frame "F" x1 1,500 33%$29.34 N/A 2.97$ 29.45$ 14.94$ 13.23%1.98$ -$ $75.71 -$ $75.71
IC Recips x 6 1,500 33%$57.40 N/A 2.97$ 24.61$ 10.39$ 8.73%0.91$ -$ $93.30 -$ $93.30
CCCT Dry "H", 1x1 1,500 78%$18.51 N/A 2.97$ 18.96$ 1.88$ 10.21%0.19$ -$ $39.54 -$ $39.54
CCCT Dry "H", DF, 1x1 1,500 12%$53.00 N/A 2.97$ 26.10$ 0.05$ 0.00%-$ -$ $79.15 -$ $79.15
CCCT Dry "H", 2x1 1,500 78%$14.42 N/A 2.97$ 18.91$ 1.81$ 10.79%0.19$ -$ $35.34 -$ $35.34
CCCT Dry "H", DF, 2x1 1,500 12%$45.67 N/A 2.97$ 25.88$ 0.05$ 0.00%-$ -$ $71.60 -$ $71.60
Brownfield CCCT Dry "H", DF, 2x1 1,500 78%$14.38 N/A 2.97$ 19.70$ 1.14$ 10.21%0.12$ -$ $35.35 -$ $35.35
CCCT Dry "J", 1x1 1,500 78%$14.87 N/A 2.97$ 18.60$ 1.57$ 10.21%0.16$ -$ $35.20 -$ $35.20
CCCT Dry "J", DF, 1x1 1,500 12%$48.08 N/A 2.97$ 26.18$ 0.06$ 0.00%-$ -$ $74.32 -$ $74.32
CCCT Dry "J", 2x1 1,500 78%$11.91 N/A 2.97$ 18.56$ 1.51$ 10.79%0.16$ -$ $32.15 -$ $32.15
CCCT Dry "J", DF, 2x1 1,500 12%$42.30 N/A 2.97$ 25.96$ 0.06$ 0.00%-$ -$ $68.32 -$ $68.32
SCCT Aero x3 3,000 33%$48.82 N/A 3.21$ 30.11$ 8.37$ 11.48%0.96$ -$ $88.26 -$ $88.26
Intercooled SCCT Aero x2 3,000 33%$38.49 N/A 3.21$ 28.28$ 5.63$ 11.48%0.65$ -$ $73.05 -$ $73.05
SCCT Frame "F" x1 3,000 33%$25.49 N/A 3.21$ 31.87$ 15.79$ 13.23%2.09$ -$ $75.24 -$ $75.24
Brownfield SCCT Frame "F" x1 3,000 33%$24.81 N/A 3.21$ 31.87$ 15.78$ 13.23%2.09$ -$ $74.55 -$ $74.55
Elevation
(AFSL)
Levelized Fuel
Convert to $/MWh
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
182
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)*
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)Credits
Resource Description Capacity Factor 3/Total Fixed($/MWh)Storage Efficiency $/mmBtu $/MWh O&M 1/ Capitalized Premium O&M Capitalized
1/
Integration Cost 1/ Total Resource Cost
PTC Tax Credits / ITC (Solar
Only) / 45Q Tax Credits (CCUS
Only)
Total Resource Cost -
with PTC / ITC / 45Q
Credits
IC Recips x 6 3,000 33%$52.80 N/A 3.21$ 26.60$ 10.39$ 8.73%0.91$ -$ $90.69 -$ $90.69
CCCT Dry "H", 1x1 3,000 78%$19.33 N/A 3.21$ 20.50$ 1.99$ 10.21%0.20$ -$ $42.02 -$ $42.02
CCCT Dry "H", DF, 1x1 3,000 12%$52.92 N/A 3.21$ 28.30$ 0.05$ 0.00%-$ -$ $81.26 -$ $81.26
CCCT Dry "H", 2x1 3,000 78%$13.46 N/A 3.21$ 20.55$ 1.92$ 10.79%0.21$ -$ $36.13 -$ $36.13
CCCT Dry "H", DF, 2x1 3,000 12%$35.23 N/A 3.21$ 28.11$ 0.05$ 0.00%-$ -$ $63.39 -$ $63.39
Brownfield CCCT Dry "H", DF, 2x1 3,000 78%$13.43 N/A 3.21$ 21.45$ 1.21$ 10.21%0.12$ -$ $36.22 -$ $36.22
CCCT Dry "J", 1x1 3,000 78%$13.89 N/A 3.21$ 20.13$ 1.66$ 10.21%0.17$ -$ $35.84 -$ $35.84
CCCT Dry "J", DF, 1x1 3,000 12%$37.71 N/A 3.21$ 28.37$ 0.06$ 0.00%-$ -$ $66.14 -$ $66.14
CCCT Dry "J", 2x1 3,000 78%$10.77 N/A 3.21$ 20.08$ 1.60$ 10.79%0.17$ -$ $32.62 -$ $32.62
CCCT Dry "J", DF, 2x1 3,000 12%$31.94 N/A 3.21$ 28.13$ 0.06$ 0.00%-$ -$ $60.13 -$ $60.13
SCCT Aero x3 5,050 33%$51.28 N/A 3.13$ 29.42$ 9.04$ 11.48%1.04$ -$ $90.78 -$ $90.78
Intercooled SCCT Aero x2 5,050 33%$40.24 N/A 3.13$ 27.59$ 6.09$ 11.48%0.70$ -$ $74.62 -$ $74.62
SCCT Frame "F" x1 5,050 33%$25.97 N/A 3.13$ 31.10$ 17.04$ 13.23%2.25$ -$ $76.36 -$ $76.36
Brownfield SCCT Frame "F" x1 5,050 33%$25.23 N/A 3.13$ 31.10$ 17.03$ 13.23%2.25$ -$ $75.62 -$ $75.62
IC Recips x 6 5,050 33%$51.91 N/A 3.13$ 25.95$ 10.39$ 8.73%0.91$ -$ $89.16 -$ $89.16
CCCT Dry "H", 1x1 5,050 78%$18.57 N/A 3.13$ 19.91$ 2.14$ 10.21%0.22$ -$ $40.84 -$ $40.84
CCCT Dry "H", DF, 1x1 5,050 12%$40.21 N/A 3.13$ 26.75$ 0.05$ 0.00%-$ -$ $67.00 -$ $67.00
CCCT Dry "H", 2x1 5,050 78%$14.19 N/A 3.13$ 20.31$ 2.10$ 10.79%0.23$ -$ $36.82 -$ $36.82
CCCT Dry "H", DF, 2x1 5,050 12%$32.88 N/A 3.13$ 29.64$ 0.05$ 0.00%-$ -$ $62.57 -$ $62.57
Brownfield CCCT Dry "H", DF, 2x1 5,050 78%$14.17 N/A 3.13$ 21.51$ 1.33$ 10.21%0.14$ -$ $37.15 -$ $37.15
CCCT Dry "J", 1x1 5,050 78%$14.65 N/A 3.13$ 19.88$ 1.81$ 10.21%0.18$ -$ $36.53 -$ $36.53
CCCT Dry "J", DF, 1x1 5,050 12%$35.39 N/A 3.13$ 29.58$ 0.06$ 0.00%-$ -$ $65.03 -$ $65.03
CCCT Dry "J", 2x1 5,050 78%$11.30 N/A 3.13$ 19.95$ 1.76$ 10.79%0.19$ -$ $33.19 -$ $33.19
CCCT Dry "J", DF, 2x1 5,050 12%$29.63 N/A 3.13$ 29.60$ 0.06$ 0.00%-$ -$ $59.28 -$ $59.28
SCCT Aero x3 6,500 33%$54.26 N/A 3.09$ 28.78$ 9.96$ 11.48%1.14$ -$ $94.14 -$ $94.14
Intercooled SCCT Aero x2 6,500 33%$40.33 N/A 3.09$ 27.15$ 6.37$ 11.48%0.73$ -$ $74.58 -$ $74.58
SCCT Frame "F" x1 6,500 33%$25.27 N/A 3.09$ 30.68$ 17.95$ 13.23%2.38$ -$ $76.29 -$ $76.29
Brownfield SCCT Frame "F" x1 6,500 33%$24.50 N/A 3.09$ 30.68$ 17.95$ 13.23%2.38$ -$ $75.51 -$ $75.51
IC Recips x 6 6,500 33%$50.39 N/A 3.09$ 25.75$ 10.39$ 8.73%0.91$ -$ $87.43 -$ $87.43
CCCT Dry "H", 1x1 6,500 78%$20.89 N/A 3.09$ 19.75$ 2.23$ 10.21%0.23$ -$ $43.10 -$ $43.10
CCCT Dry "H", DF, 1x1 6,500 12%$50.43 N/A 3.09$ 27.37$ 0.05$ 0.00%-$ -$ $77.85 -$ $77.85
Elevation
(AFSL)
Levelized Fuel
Convert to $/MWh
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
183
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Convert to $/MWh
Credits
Resource Description Capacity Factor 3/Total Fixed ($/MWh)
Storage
Efficiency $/mmBtu $/MWh O&M 1/
Capitalized
Premium O&M Capitalized
1/
Integration Cost
1/ Total Resource Cost
PTC Tax Credits / ITC (Solar
Only) / 45Q Tax Credits (CCUS
Only)
Total Resource Cost -
with PTC / ITC / 45Q
Credits
CCCT Dry "H", 2x1 6,500 78%$14.04 N/A 3.09$ 19.77$ 2.15$ 10.79%0.23$ -$ $36.20 -$ $36.20
CCCT Dry "H", DF, 2x1 6,500 12%$29.79 N/A 3.09$ 27.35$ 0.05$ 0.00%-$ -$ $57.20 -$ $57.20
Brownfield CCCT Dry "H", DF, 2x1 6,500 78%$14.02 N/A 3.09$ 20.78$ 1.36$ 10.21%0.14$ -$ $36.30 -$ $36.30
CCCT Dry "J", 1x1 6,500 78%$14.57 N/A 3.09$ 19.38$ 1.86$ 10.21%0.19$ -$ $36.00 -$ $36.00
CCCT Dry "J", DF, 1x1 6,500 12%$32.32 N/A 3.09$ 27.39$ 0.06$ 0.00%-$ -$ $59.77 -$ $59.77
CCCT Dry "J", 2x1 6,500 78%$11.05 N/A 3.09$ 19.34$ 1.80$ 10.79%0.19$ -$ $32.38 -$ $32.38
CCCT Dry "J", DF, 2x1 6,500 12%$26.56 N/A 3.09$ 27.16$ 0.06$ 0.00%-$ -$ $53.78 -$ $53.78
SCPC with CCS 4,500 90%$66.91 N/A 1.96$ 25.65$ 7.00$ 0.00%-$ -$ $99.56 -$ $99.56
IGCC with CCS 4,500 86%$69.93 N/A 1.96$ 21.21$ 11.77$ 11.52%1.36$ -$ $104.27 -$ $104.27
PC CCS retrofit @ 500 MW pre-retrofit basis 4,500 90%$29.80 N/A 1.96$ 28.17$ 3.29$ 0.00%-$ -$ $61.26 -$ $61.26
SCPC with CCS 6,500 90%$73.66 N/A 1.96$ 25.95$ 7.58$ 0.00%-$ -$ $107.19 -$ $107.19
IGCC with CCS 6,500 86%$78.77 N/A 1.96$ 21.65$ 14.11$ 11.52%1.63$ -$ $116.15 -$ $116.15
PC CCS retrofit @ 500 MW pre-retrofit basis 6,500 90%$29.80 N/A 1.96$ 28.17$ 3.29$ 0.00%-$ -$ $61.26 -$ $61.26
Blundell Dual Flash 90% CF 4,500 90%$59.71 N/A -$ -$ 1.16$ 0.00%-$ -$ $60.87 (16.12)$ $44.75
Greenfield Binary 90% CF 4,500 90%$61.71 N/A -$ -$ 1.16$ 0.00%-$ -$ $62.88 (16.12)$ $46.75
Generic Geothermal PPA 90% CF 4,500 90%$0.00 N/A -$ -$ 77.34$ 0.00%-$ -$ $77.34 (16.12)$ $61.22
Pocatello, ID, 200 MW Wind, CF: 37.1% (100% PTC)4,500 37%$37.19 N/A -$ -$ -$ 0.00%-$ 0.93$ $38.12 (16.12)$ $22.00
Arlington, OR, 200 MW Wind, CF: 37.1% (100% PTC)1,500 37%$36.13 N/A -$ -$ -$ 0.00%-$ 0.93$ $37.05 (16.12)$ $20.93
Monticello, UT, 200 MW Wind, CF: 29.5% (100% PTC)4,500 30%$45.20 N/A -$ -$ -$ 0.00%-$ 0.93$ $46.13 (16.12)$ $30.00
Medicine Bow, WY, 200 MW Wind, CF: 43.6% (100%PTC)6,500 44%$31.49 N/A -$ -$ -$ 0.00%-$ 0.93$ $32.42 (16.12)$ $16.30
Goldendale, WA, 200 MW Wind, CF: 37.1% (100% PTC)1,500 37%$37.73 N/A -$ -$ -$ 0.00%-$ 0.93$ $38.66 (16.12)$ $22.54
Pocatello, ID, 200 MW Wind, CF: 37.1% (60% PTC)4,500 37%$37.19 N/A -$ -$ -$ 0.00%-$ 0.93$ $38.12 (9.67)$ $28.45
Arlington, OR, 200 MW Wind, CF: 37.1% (60% PTC)1,500 37%$36.13 N/A -$ -$ -$ 0.00%-$ 0.93$ $37.05 (9.67)$ $27.38
Monticello, UT, 200 MW Wind, CF: 29.5% (60% PTC)4,500 30%$45.20 N/A -$ -$ -$ 0.00%-$ 0.93$ $46.13 (9.67)$ $36.45
Medicine Bow, WY, 200 MW Wind, CF: 43.6% (60% PTC)6,500 44%$31.49 N/A -$ -$ 0.65$ 0.00%-$ 0.93$ $33.07 (9.67)$ $23.40
Goldendale, WA, 200 MW Wnd, CF: 37.1% (60% PTC)1,500 37%$37.73 N/A -$ -$ -$ 0.00%-$ 0.93$ $38.66 (9.67)$ $28.99
Pocatello, ID, 200 MW Wind, CF: 37.1% + BESS: 50% pwr, 4 hours 4,500 37%$63.12 85%-$ -$ -$ 0.00%-$ 0.93$ $64.05 (16.12)$ $47.92
Arlington, OR, 200 MW Wind, CF: 37.1% + BESS: 50% pwr, 4 hours 1,500 37%$61.69 85%-$ -$ -$ 0.00%-$ 0.93$ $62.62 (16.12)$ $46.50
Monticello, UT, 200 MW Wind, CF: 29.5% + BESS: 50% pwr, 4 hours 4,500 30%$76.90 85%-$ -$ -$ 0.00%-$ 0.93$ $77.83 (16.12)$ $61.71
Medicine Bow, WY, 200 MW Wind, CF: 43.6% + BESS: 50% pwr, 4 hours 6,500 44%$53.40 85%-$ -$ 0.65$ 0.00%-$ 0.93$ $54.98 (16.12)$ $38.86
Goldendale, WA, 200 MW Wind, CF: 37.1% + BESS: 50% pwr, 4 hours 1,500 37%$64.37 85%-$ -$ -$ 0.00%-$ 0.93$ $65.30 (16.12)$ $49.18
Idaho Falls, ID, 100 MW Solar, CF: 26.1% (30% ITC)4,700 26%$50.96 N/A -$ -$ -$ 0.00%-$ 0.70$ $51.67 (10.96)$ $40.70
Idaho Falls, ID, 200 MW Solar, CF: 26.1% (30% ITC)4,700 26%$47.13 N/A -$ -$ -$ 0.00%-$ 0.70$ $47.84 (9.99)$ $37.85
Lakeview, OR, 100 MW Solar, CF: 27.6% (30% ITC)4,800 28%$48.64 N/A -$ -$ -$ 0.00%-$ 0.70$ $49.35 (10.48)$ $38.86
Lakeview, OR, 200 MW Solar, CF: 27.6% (30% ITC)4,800 28%$45.37 N/A -$ -$ -$ 0.00%-$ 0.70$ $46.08 (9.66)$ $36.42
Milford, UT, 100 MW Solar, CF: 30.2% (30% ITC)5,000 30%$44.42 N/A -$ -$ -$ 0.00%-$ 0.70$ $45.12 (9.43)$ $35.69
Milford, UT, 200 MW Solar, CF: 30.2% (30% ITC)5,000 30%$41.18 N/A -$ -$ -$ 0.00%-$ 0.70$ $41.89 (8.60)$ $33.28
Rock Springs, WY, 100 MW Solar, CF: 27.9% (30% ITC)6,400 28%$48.10 N/A -$ -$ -$ 0.00%-$ 0.70$ $48.80 (10.21)$ $38.58
Rock Springs, WY, 200 MW Solar, CF: 27.9% (30% ITC)6,400 28%$44.56 N/A -$ -$ -$ 0.00%-$ 0.70$ $45.27 (9.31)$ $35.96
Yakima, WA, 100 MW Solar, CF: 24.2% (30% ITC)1,000 24%$57.49 N/A -$ -$ -$ 0.00%-$ 0.70$ $58.20 (12.30)$ $45.90
Yakima, WA, 200 MW Solar, CF: 24.2% (30% ITC)1,000 24%$53.32 N/A -$ -$ -$ 0.00%-$ 0.70$ $54.03 (11.23)$ $42.80
Idaho Falls, ID, 100 MW Solar, CF: 26.1% (10% ITC)4,700 26%$50.96 N/A -$ -$ -$ 0.00%-$ 0.70$ $51.67 (0.52)$ $51.15
Idaho Falls, ID, 200 MW Solar, CF: 26.1% (10% ITC)4,700 26%$47.13 N/A -$ -$ -$ 0.00%-$ 0.70$ $47.84 (0.47)$ $47.36
Lakeview, OR, 100 MW Solar, CF: 27.6% (10% ITC)4,800 28%$48.64 N/A -$ -$ -$ 0.00%-$ 0.70$ $49.35 (0.50)$ $48.85
Lakeview, OR, 200 MW Solar, CF: 27.6% (10% ITC)4,800 28%$45.37 N/A -$ -$ -$ 0.00%-$ 0.70$ $46.08 (0.46)$ $45.62
Milford, UT, 100 MW Solar, CF: 30.2% (10% ITC)5,000 30%$44.42 N/A -$ -$ -$ 0.00%-$ 0.70$ $45.12 (0.45)$ $44.67
Milford, UT, 200 MW Solar, CF: 30.2% (10% ITC)5,000 30%$41.18 N/A -$ -$ -$ 0.00%-$ 0.70$ $41.89 (0.41)$ $41.48
Rock Springs, WY, 100 MW Solar, CF: 27.9% (10% ITC)6,400 28%$48.10 N/A -$ -$ -$ 0.00%-$ 0.70$ $48.80 (0.48)$ $48.31
Rock Springs, WY, 200 MW Solar, CF: 27.9% (10% ITC)6,400 28%$44.56 N/A -$ -$ -$ 0.00%-$ 0.70$ $45.27 (0.44)$ $44.82
Idaho Falls, ID, 100 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (30% ITC)4,700 26%$91.26 85%-$ -$ -$ 0.00%-$ 0.70$ $91.97 (18.04)$ $73.92
Levelized Fuel
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Elevation
(AFSL)
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
184
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Convert to $/MWh
Credits
Resource Description Capacity Factor 3/Total Fixed ($/MWh)
Storage
Efficiency $/mmBtu $/MWh O&M 1/
Capitalized
Premium O&M Capitalized
1/
Integration Cost
1/ Total Resource Cost
PTC Tax Credits / ITC (Solar
Only) / 45Q Tax Credits (CCUS
Only)
Total Resource Cost -
with PTC / ITC / 45Q
Credits
Idaho Falls, ID, 200 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (30% ITC)4,700 26%$85.11 85%-$ -$ -$ 0.00%-$ 0.70$ $85.82 (16.59)$ $69.23
Yakima, WA, 100 MW Solar, CF: 24.2% (10% ITC)1,000 24%$57.49 N/A -$ -$ -$ 0.00%-$ 0.70$ $58.20 (0.58)$ $57.61
Yakima, WA, 200 MW Solar, CF: 24.2% (10% ITC)1,000 24%$53.32 N/A -$ -$ -$ 0.00%-$ 0.70$ $54.03 (0.53)$ $53.50
Lakeview, OR, 100 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (30% ITC)4,800 28%$85.67 85%-$ -$ -$ 0.00%-$ 0.70$ $86.37 (16.90)$ $69.47
Lakeview, OR, 200 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (30% ITC)4,800 28%$80.28 85%-$ -$ -$ 0.00%-$ 0.70$ $80.98 (15.63)$ $65.35
Milford, UT, 100 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (30% ITC)5,000 30%$77.65 85%-$ -$ -$ 0.00%-$ 0.70$ $78.35 (15.14)$ $63.21
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (30% ITC)5,000 30%$72.60 85%-$ -$ -$ 0.00%-$ 0.70$ $73.31 (13.94)$ $59.37
Rock Springs, WY, 100 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (30% ITC)6,400 28%$84.86 85%-$ -$ -$ 0.00%-$ 0.70$ $85.56 (16.60)$ $68.96
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (30% ITC)6,400 28%$79.33 85%-$ -$ -$ 0.00%-$ 0.70$ $80.03 (15.28)$ $64.75
Yakima, WA, 100 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (30% ITC)1,000 24%$100.83 85%-$ -$ -$ 0.00%-$ 0.70$ $101.53 (19.90)$ $81.62
Yakima, WA, 200 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (30% ITC)1,000 24%$94.31 85%-$ -$ -$ 0.00%-$ 0.70$ $95.01 (18.35)$ $76.66
Idaho Falls, ID, 100 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (10% ITC)4,700 26%$91.26 85%-$ -$ -$ 0.00%-$ 0.70$ $91.97 (0.86)$ $91.11
Idaho Falls, ID, 200 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours (10% ITC)4,700 26%$85.11 85%-$ -$ -$ 0.00%-$ 0.70$ $85.82 (0.79)$ $85.03
Lakeview, OR, 100 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (10% ITC)4,800 28%$85.67 85%-$ -$ -$ 0.00%-$ 0.70$ $86.37 (0.80)$ $85.57
Lakeview, OR, 200 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours (10% ITC)4,800 28%$80.28 85%-$ -$ -$ 0.00%-$ 0.70$ $80.98 (0.74)$ $80.24
Milford, UT, 100 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (10% ITC)5,000 30%$77.65 85%-$ -$ -$ 0.00%-$ 0.70$ $78.35 (0.72)$ $77.63
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (10% ITC)5,000 30%$72.60 85%-$ -$ -$ 0.00%-$ 0.70$ $73.31 (0.66)$ $72.65
Rock Springs, WY, 100 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (10% ITC)6,400 28%$84.86 85%-$ -$ -$ 0.00%-$ 0.70$ $85.56 (0.79)$ $84.78
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (10% ITC)6,400 28%$79.33 85%-$ -$ -$ 0.00%-$ 0.70$ $80.03 (0.73)$ $79.31
Yakima, WA, 100 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (10% ITC)1,000 24%$100.83 85%-$ -$ -$ 0.00%-$ 0.70$ $101.53 (0.94)$ $100.59
Yakima, WA, 200 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours (10% ITC)1,000 24%$94.31 85%-$ -$ -$ 0.00%-$ 0.70$ $95.01 (0.87)$ $94.14
Idah Falls, ID, 200 MW Solar, CF: 26.1% + BESS: 50% pwr, 4 hours + 200 MW Wind 4,700 26%$146.34 85%-$ -$ -$ 0.00%-$ 0.70$ $147.05 -$ $147.05
Lakeview, OR, 200 MW Solar, CF: 27.6% + BESS: 50% pwr, 4 hours + 200 MW Wind 4,800 28%$139.19 85%-$ -$ -$ 0.00%-$ 0.70$ $139.90 -$ $139.90
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours + 200 MW Wind 5,000 30%$125.10 85%-$ -$ -$ 0.00%-$ 0.70$ $125.80 -$ $125.80
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours + 200 MW Wind 6,400 28%$135.39 85%-$ -$ -$ 0.00%-$ 0.70$ $136.10 -$ $136.10
Yakima, WA, 200 MW Solar, CF: 24.2% + BESS: 50% pwr, 4 hours + 200 MW Wind 1,000 24%$158.04 85%-$ -$ -$ 0.00%-$ 0.70$ $158.75 -$ $158.75
Pumped Hydro, Swan Lake. 3600 MWh N/A 38%$71.93 78%-$ -$ -$ 0.00%-$ -$ $71.93 -$ $71.93
Pumped Hydro, Goldendale, 14400 MWh N/A 50%$50.21 78%-$ -$ -$ 0.00%-$ -$ $50.21 -$ $50.21
Pumped Hydro, Seminoe, 7500 MWh N/A 42%$70.45 80%-$ -$ 0.37$ 0.00%-$ -$ $70.82 -$ $70.82
Pumped Hydro, Badger Mountain, 4000 MWh N/A 33%$74.58 80%-$ -$ 0.37$ 0.00%-$ -$ $74.95 -$ $74.95
Pumped Hydro, Owyhee, 4800 MWh N/A 33%$84.02 80%-$ -$ 0.37$ 0.00%-$ -$ $84.39 -$ $84.39
Pumped Hydro, Flat Canyon, 1800 MWh N/A 25%$150.78 80%-$ -$ 0.37$ 0.00%-$ -$ $151.15 -$ $151.15
Pumped Hydro, Utah PS2, 4000 MWh N/A 33%$87.48 80%-$ -$ 0.37$ 0.00%-$ -$ $87.85 -$ $87.85
Pumped Hydro, Utah PS3, 4800 MWh N/A 33%$87.54 80%-$ -$ 0.37$ 0.00%-$ -$ $87.91 -$ $87.91
Pumped Hydro, Banner Mountain, 3400 MWh N/A 35%$87.72 81%-$ -$ 0.00$ 0.00%-$ -$ $87.72 -$ $87.72
Adiabatic CAES, Hydrostor, 150 MW, 600 MWh N/A 17%$109.63 60%-$ -$ 6.50$ 0.00%-$ -$ $116.13 -$ $116.13
Adiabatic CAES, Hydrostor, 150 MW, 1200 MWh N/A 33%$60.85 60%-$ -$ 6.50$ 0.00%-$ -$ $67.35 -$ $67.35
Adiabatic CAES, Hydrostor, 150 MW, 1800 MWh N/A 50%$44.95 60%-$ -$ 6.50$ 0.00%-$ -$ $51.45 -$ $51.45
Adiabatic CAES, Hydrostor, 300 MW, 1200 MWh N/A 17%$86.97 60%-$ -$ 6.50$ 0.00%-$ -$ $93.47 -$ $93.47
Adiabatic CAES, Hydrostor, 300 MW, 2400 MWh N/A 33%$46.96 60%-$ -$ 6.50$ 0.00%-$ -$ $53.46 -$ $53.46
Adiabatic CAES, Hydrostor, 300 MW, 3600 MWh N/A 50%$36.84 60%-$ -$ 6.50$ 0.00%-$ -$ $43.34 -$ $43.34
Adiabatic CAES, Hydrostor, 500 MW, 2000 MWh N/A 17%$84.70 60%-$ -$ 6.50$ 0.00%-$ -$ $91.20 -$ $91.20
Adiabatic CAES, Hydrostor, 500 MW, 4000 MWh N/A 33%$47.81 60%-$ -$ 6.50$ 0.00%-$ -$ $54.31 -$ $54.31
Adiabatic CAES, Hydrostor, 500 MW, 6000 MWh N/A 50%$36.12 60%-$ -$ 6.50$ 0.00%-$ -$ $42.62 -$ $42.62
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Elevation
(AFSL)
Levelized Fuel
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTION
185
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Table 7.2 – Total Resource Cost for Supply-Side Resource Options (Continued)
Convert to $/MWh
Credits
Resource Description Capacity Factor 3/Total Fixed ($/MWh)
Storage
Efficiency $/mmBtu $/MWh O&M 1/
Capitalized
Premium O&M Capitalized
1/
Integration Cost
1/ Total Resource Cost
PTC Tax Credits / ITC (Solar
Only) / 45Q Tax Credits (CCUS
Only)
Total Resource Cost -
with PTC / ITC / 45Q
Credits
Li-Ion Battery, , 1 MW, 0.5 MWh N/A 2%$1,171.19 85%-$ -$ Included in FOM 0.00%-$ -$ $1,171.19 -$ $1,171.19
Li-Ion Battery, , 1 MW, 1 MWh N/A 4%$652.41 85%-$ -$ Included in FOM 0.00%-$ -$ $652.41 -$ $652.41
Li-Ion Battery, , 1 MW, 4 MWh N/A 17%$262.28 85%-$ -$ Included in FOM 0.00%-$ -$ $262.28 -$ $262.28
Li-Ion Battery, , 1 MW, 8 MWh N/A 33%$197.73 85%-$ -$ Included in FOM 0.00%-$ -$ $197.73 -$ $197.73
Li-Ion Battery, , 50 MW, 200 MWh N/A 17%$153.19 85%-$ -$ Included in FOM 0.00%-$ -$ $153.19 -$ $153.19
Flow Battery, , 1 MW, 1 MWh N/A 4%$1,160.11 70%-$ -$ Included in FOM 0.00%-$ -$ $1,160.11 -$ $1,160.11
Non-Emitting Peaker 5,050 33%$87.47 0%26.72$ 265.54$ 21.29$ 0.00%-$ -$ $374.30 -$ $374.30
Flow Battery, , 20 MW, 160 MWh N/A 33%$135.30 70%-$ -$ Included in FOM 0.00%-$ -$ $135.30 -$ $135.30
Small Modular Reactor 5000 86%64.12$ N/A -$ -$ 6.72$ 0.00%-$ -$ $70.84 -$ $70.84
Non-Emitting Peaker 5050 33%87.47$ 0%26.72$ 265.54$ 21.29$ 0.00%-$ -$ $374.30 -$ $374.30
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)
Elevation
(AFSL)
Levelized Fuel
Supply Side Resource Options
Mid-Calendar Year 2020 Dollars ($)Credits
Resource Description Capacity Factor 3/ Total Fixed($/MWh) Storage Efficiency ¢/mmBtu $/MWh O&M 1/ Capitalized Premium O&M Capitalized 1/ Integration Cost / CO2 Revenues Total Resource Cost
PTC Tax Credits / ITC (Solar
Only) / 45Q Tax Credits (CCUS
Only)
Total Resource Cost -with PTC / ITC / 45Q Credits
Brownfield Site
Utah
Brownfield SCCT Frame "F" x1 5050 33%$25.23 N/A 3.13$ 31.10$ 17.03$ 13.23%2.25$ -$ $75.62 -$ $75.62
Intercooled SCCT Aero x2 5050 33%$40.24 N/A 3.13$ 27.59$ 6.09$ 11.48%0.70$ -$ $74.62 -$ $74.62
Brownfield CCCT Dry "H", DF, 2x1 5050 78%$14.17 N/A 3.13$ 21.51$ 1.33$ 10.21%0.14$ -$ $37.15 -$ $37.15
CCCT Dry "J", 1x1 5050 78%$14.65 N/A 3.13$ 19.88$ 1.81$ 10.21%0.18$ -$ $36.53 -$ $36.53
Milford, UT, 200 MW Solar, CF: 30.2% (10% ITC)5000 30%$41.18 N/A -$ -$ -$ 0.00%-$ 0.70$ $41.89 (0.41)$ $41.48
Milford, UT, 200 MW Solar, CF: 30.2% + BESS: 50% pwr, 4 hours (30% ITC)5,000 30%$72.60 85%-$ -$ -$ 0.00%-$ 0.70$ $73.31 (13.94)$ $59.37
Wyoming
Brownfield SCCT Frame "F" x1 6500 33%$24.50 N/A 3.09$ 30.68$ 17.95$ 13.23%2.38$ -$ $75.51 -$ $75.51
Intercooled SCCT Aero x2 6500 33%$40.33 N/A 3.09$ 27.15$ 6.37$ 11.48%0.73$ -$ $74.58 -$ $74.58
Brownfield CCCT Dry "H", DF, 2x1 6500 78%$14.02 N/A 3.09$ 20.78$ 1.36$ 10.21%0.14$ -$ $36.30 -$ $36.30
CCCT Dry "J", 1x1 6500 78%$14.57 N/A 3.09$ 19.38$ 1.86$ 10.21%0.19$ -$ $36.00 -$ $36.00
Medicine Bow, WY, 200 MW Wind, CF: 43.6% (60% PTC)6,500 44%$31.49 N/A -$ -$ 0.65$ 0.00%-$ 0.93$ $33.07 $33.07
Medicine Bow, WY, 200 MW Wind, CF: 43.6% + BESS: 50% pwr, 4 hours 6,500 44%$53.40 85%-$ -$ 0.65$ 0.00%-$ 0.93$ $54.98 $54.98
Rock Springs, WY, 200 MW Solar, CF: 27.9% (10% ITC)6400 28%$44.56 N/A -$ -$ -$ 0.00%-$ 0.70$ $45.27 (0.44)$ $44.82
Rock Springs, WY, 200 MW Solar, CF: 27.9% + BESS: 50% pwr, 4 hours (30% ITC)6,400 28%$79.33 85%-$ -$ -$ 0.00%-$ 0.70$ $80.03 (15.28)$ $64.75
Naughton 1 PC CCUS Retrofit 6,500 85%$53.31 0%2.28$ 32.77$ 7.32$ 0.00%-$ (12.28)$ $81.12 (25.79)$ $55.33
Naughton 2 PC CCUS Retrofit 6,500 85%$53.17 0%2.28$ 32.77$ 7.30$ 0.00%-$ (12.28)$ $80.97 (25.79)$ $55.18
Johnston 2 PC CCUS Retrofit 6,500 85%$69.85 0%0.99$ 14.23$ 6.10$ 0.00%-$ (12.28)$ $77.90 (25.79)$ $52.11
Johnston 4 PC CCUS Retrofit 6,500 85%$52.26 0%0.99$ 14.23$ 5.69$ 0.00%-$ (12.28)$ $59.91 (25.79)$ $34.12
Wyodak PC CCUS Retrofit 6,500 85%$53.72 0%1.14$ 16.38$ 7.31$ 0.00%-$ (12.28)$ $65.14 (25.79)$ $39.35
Bridger 1 PC CCUS Retrofit 6,500 85%$53.24 0%2.12$ 30.47$ 7.31$ 0.00%-$ (12.28)$ $78.74 (25.79)$ $52.95
Bridger 3 PC CCUS Retrofit 6,500 85%$52.68 0%2.12$ 30.47$ 5.69$ 0.00%-$ (12.28)$ $76.56 (25.79)$ $50.77
Bridger 4 PC CCUS Retrofit 6,500 85%$52.72 0%2.12$ 30.47$ 5.69$ 0.00%-$ (12.28)$ $76.60 (25.79)$ $50.81
Elevation
(AFSL)
Convert to $/MWh
Variable Costs
($/MWh)
Levelized Fuel
PACIFICORP - 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
186
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
187
Additionally, total resource costs were prepared for three natural gas-fired combined cycle
combustion turbine resource options at an elevation of 5,050 feet at varying capacity factors to
show how these costs are affected by dispatch. Table 7.3 shows the total resource cost results for
this analysis.
Table 7.3 - Total Resource Cost, for various Capacity Factors ($/MWh, 2018$)
Table 7.4 - Glossary of Terms from the SSR
Term Description
Fuel Primary fuel used for electricity generation or storage.
Resource Primary technology used for electricity generation or storage.
Elevation (afsl) Average feet above sea level for the proxy site for the given resource.
Net Capacity (MW)
For natural gas-fired generation resources, the Net Capacity is the net
dependable capacity (net electrical output) for a given technology, at
the given elevation, at the annual average ambient temperature in a
"new and clean" condition.
Commercial
Operation Year
The resource availability year is the earliest year the technology
associated with the given generating resource is commercially available
for procurement and installation. The total implementation time is the
number of years necessary to implement all phases of resource
development and construction: site selection, permitting, maintenance
contracts, IRP approval, RFP process, owner’s engineering,
construction, commissioning and grid interconnection.
Design Life (years)
Average number of years the resource is expected to be "used and
useful,” based on various factors such as manufacturer’s guarantees,
fuel availability and environmental regulations.
Base Capital ($/kW)
Total capital expenditure in dollars per kilowatt-hour ($/kW) for the
development and construction of a resource including: direct costs
(equipment, buildings, installation/overnight construction,
commissioning, contractor fees/profit and contingency), owner's costs
(land, water rights, permitting, rights-of-way, design engineering, spare
parts, project management, legal/financial support, grid interconnection
costs, owner’s contingency), and financial costs (allowance for funds
used during construction (AFUDC), capital surcharge, property taxes
and escalation during construction, if applicable).
Total Resource Cost ($/MWh)
Capacity Factor CCCT 40%78%94%
Capacity Factor Duct Fire 10%12%22%
CCCT Dry "G/H", 1x1 $68.15 $46.45 $42.56
CCCT Dry "G/H", DF, 1x1 $75.94 $66.85 $46.20
CCCT Dry "G/H", 2x1 $56.24 $40.30 $37.45
CCCT Dry "G/H", DF, 2x1 $66.11 $58.66 $41.75
CCCT Dry "J/HA.02", 1x1 $61.02 $42.68 $39.39
CCCT Dry "J/HA.02", DF, 1x1 $69.63 $61.57 $43.25
CCCT Dry, "J/HA.02" 2X1 $51.14 $37.57 $35.14
CCCT Dry "J/HA.02", DF, 2X1 $61.64 $54.91 $39.63
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
188
Term Description
Var O&M ($/MWh)
Includes real levelized variable operating costs such as combustion
turbine maintenance, water costs, boiler water/circulating water
treatment chemicals, pollution control reagents, equipment
maintenance and fired hour fees in dollars per megawatt hour ($/MWh).
Fixed O&M ($/kW-
year)
Includes labor costs, combustion turbine fixed maintenance fees,
contracted services fees, office equipment and training.
Demolition Cost
($/kW)
Total cost to decommission and demolish the generating unit at the end
of life in dollars per kilowatt ($/kW).
Full Load Heat Rate
HHV (Btu/kWh)
Net efficiency of the resource to generate electricity for a given heat
input in a "new and clean" condition on a higher heating value basis.
EFOR (%) Estimated Equivalent Forced Outage Rate, which includes forced
outages and derates for a given resource at the given site.
POR (%) Estimated Planned Outage Rate for a given resource at the given site.
Water Consumed
(gal/MWh)
Average amount of water consumed by a resource for make-up, cooling
water make-up, inlet conditioning and pollution control.
SO2 (lbs/MMBtu) Expected permitted level of sulfur dioxide (SO2) emissions in pounds
of sulfur dioxide per million Btu of heat input.
NOx (lbs/MMBtu) Expected permitted level of nitrogen oxides (NOx) (expressed as NO2)
in pounds of NOx per million Btu of heat input.
Hg (lbs/TBtu) Expected permitted level of mercury emissions in pounds per trillion
Btu of heat input.
CO2 (lbs/MMBtu) Pounds of carbon dioxide (CO2) emitted per million Btu of heat input.
Table 7.5 - Glossary of Acronyms Used in the Supply-Side Resources
Acronyms Description
AFSL Average Feet (Above) Sea Level
CAES Compressed Air Energy Storage
CCCT Combined Cycle Combustion Turbine
CCUS Carbon Capture Utilization and Sequestration
CF Capacity Factor
CSP Concentrated Solar Power
DF Duct Firing
IC Internal Combustion
IGCC Integrated Gasification Combined Cycle
ISO International Organization for Standardization (Temp = 59 F/15 C,
Pressure = 14.7 psia/1.013 bar)
Li-Ion Lithium Ion
NCM Nickel Cobalt Manganese (sub-chemistry of Li-Ion)
PPA Power Purchase Agreement
PC CCS Pulverized Coal equipped with Carbon Capture and Sequestration
PHES Pumped Hydro Energy Storage
PV Poly-Si Photovoltaic modules constructed from poly-crystalline silicon
semiconductor wafers
Recip Reciprocating Engine
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
189
SCCT Simple Cycle Combustion Turbine
SCPC Super-Critical Pulverized Coal
Resource Option Descriptions
The following are brief descriptions of each of the resources listed in Table 7.1.
Natural Gas, Simple Combined Cycle Turbine (SCCT) Aero x 3 – a resource based on three
General Electric LM6000PF-Sprint simple cycle aero-derivative combustion turbines fueled on
natural gas. The scope would include selective catalytic reduction systems and oxidation catalysts
to reduce NOx and carbon monoxide/volatile organic compounds (VOC) emissions.
Natural Gas, Intercooled SCCT Aero x 2 – a resource based on two General Electric
LMS100PA+ simple cycle aero-derivative intercooled combustion turbine fueled on natural gas.
Scope would include selective catalytic reduction systems and oxidation catalysts to reduce NOx
and carbon monoxide/VOC emissions. An air-cooled intercooler is assumed.
Natural Gas, SCCT Frame "F" x 1 – a resource based on one General Electric 7FA.05 simple
cycle frame type combustion turbine fueled on natural gas. Scope would include selective catalytic
reduction systems and oxidation catalysts to reduce NOx and carbon monoxide/VOC emissions.
Brownfield SCCT Frame “F” x1 - a resource located at an existing generating facility based on
one General Electric 7FA.05 simple cycle frame type combustion turbine fueled on natural gas.
Scope would include selective catalytic reduction systems and oxidation catalysts to reduce NOx
and carbon monoxide/VOC emissions.
Natural Gas, Internal Combustion (IC) Recips x 6 – a resource based on six Wartsila 18V50SG
reciprocating engines fueled on natural gas. Scope would include selective catalytic reduction
systems and oxidation catalysts to reduce NOx and carbon monoxide/VOC emissions.
Natural Gas, Combined Cycle Combustion Turbine (CCCT) Dry "H", 1x1 – a combined
cycle resource based on one frame-type General Electric 7HA.01 combustion turbine, one 3-
pressure heat recovery steam generator and one steam turbine. Scope would include selective
catalytic reduction systems and oxidation catalysts to reduce NOx and carbon monoxide/VOC
emissions. Steam from the steam turbine is condensed in an air-cooled condenser.
Natural Gas, CCCT Dry "H", DF, 1x1 – an option that can be added to a combined cycle plant
to increase its capacity by the addition of duct burners in the heat recovery steam generator. This
increases the amount of steam generated in the heat recovery steam generator. The amount of duct
firing is up to the owner. Depending on the amount of duct firing added, the size of the steam
turbine, steam turbine generator and associated feed water, steam condensing and cooling systems
may need to be increased. This description also applies to the following technologies that are listed
on Table 7.1: CCCT Dry "G/H", DF, 2x1; CCCT Dry "J/HA.02", DF, 1x1; CCCT Dry "J/HA.02",
DF, 2x1.
Natural Gas, CCCT Dry "H", 2x1 - a combined cycle resource based on two frame-type General
Electric 7HA.01 combustion turbines, two 3-pressure heat recovery steam generators and one
steam turbine. Scope would include selective catalytic reduction systems and oxidation catalysts
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
190
to reduce NOx and carbon monoxide/VOC emissions. Steam from the steam turbine is condensed
in an air cooled condenser.
Brownfield CCCT Dry “H”, DF, 2X1 - a resource located at an existing generating facility based
on a combined cycle resource using two frame-type General Electric 7HA.01 combustion turbines,
two 3-pressure heat recovery steam generators with duct firing and one steam turbine. Scope would
include selective catalytic reduction systems and oxidation catalysts to reduce NOx and carbon
monoxide/VOC emissions. Steam from the steam turbine is condensed in an air-cooled condenser.
Natural Gas, CCCT Dry "J", 1x1 - a combined cycle resource based on one frame-type General
Electric 7HA.02 combustion turbine (air-cooled), one 3-pressure heat recovery steam generator
and one steam turbine. Scope would include selective catalytic reduction systems and oxidation
catalysts to reduce NOx and carbon monoxide/VOC emissions. Steam from the steam turbine is
condensed in an air-cooled condenser.
Natural Gas, CCCT Dry "J", 2x1 - a combined cycle resource based on two frame-type General
Electric 7HA.02 combustion turbines (air-cooled), two 3-pressure heat recovery steam generators
and one steam turbine. Scope would include selective catalytic reduction systems and oxidation
catalysts to reduce NOx and carbon monoxide/VOC emissions. Steam from the steam turbine is
condensed in an air-cooled condenser.
Coal, Super-critical Pulverized Coal (SCPC) with CCUS – conventional coal-fired generation
resource including a supercritical boiler (up to 4000 psig) using pulverized coal with all emission
controls including scrubber, fabric filters (baghouse), mercury control, selective catalytic reduction
(SCR) and CCUS to reduce carbon dioxide emissions by 90 percent.
Coal, PC CCUS pre-retrofit at 500 MW – a retrofit of an existing conventional coal-fired boiler
and steam turbine resource. Costs include the reduction in plant output due to higher auxiliary
power requirements and reduced steam turbine output and would remove carbon dioxide by 90
percent and provide a marginal improvement in other emissions.
Coal, IGCC with CCUS – an advanced IGCC resource to facilitate lower CCUS costs. An IGCC
plant produces a synthetic fuel gas from coal using an advanced oxygen blown gasifier and burning
the synthetic fuel gas in a conventional combustion turbine combined cycle power facility. The
IGCC would utilize the latest advanced combustion turbine technology and provide fuel gas
cleanup to achieve ultra-low emissions of sulfur dioxide, nitrogen oxides using SCR systems,
mercury and particulate. Carbon dioxide would be removed from the synthetic fuel gas before
combustion thereby reducing carbon dioxide emissions by more than 90 percent.
Wind, 4.0 MW turbine 37 percent Net Capacity Factor (NCF) WA/OR/ID – a wind resource
based on 4.0 MW wind turbines located in Washington, Oregon or Idaho with an estimated annual
net capacity factor of 37 percent. The scope would include developing, permitting, engineering,
procuring equipment and constructing a wind farm.
Wind, 4.0 MW turbine 29 percent NCF UT – a wind resource based on 4.0 MW wind turbines
located in Utah with an estimated annual net capacity factor of 29 percent. The scope would
include developing, permitting, engineering, procuring equipment and constructing a wind farm.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
191
Wind, 4.0 MW turbine 43 percent NCF WY – a wind resource based on 4.0 MW wind turbines
located in Wyoming with an estimated annual net capacity factor of 43 percent.
Wind + Energy Storage – a wind resource as described above paired with a 4-hour battery with
50% of the power capacity of the wind resource. The batteries paired with wind resources in the
previous IRP had 25% of the power of the wind resources.
Solar, PV Single Axis Tracking in ID, OR, UT, WA, and WY with NCF between 24.2 and
30.2 percent depending upon location (1.30 MWdc/MWac) – a large utility scale (100 MW or
200 MW) solar photovoltaic resource using crystalline silica solar panels in a single axis tracking
system located in Idaho Falls, Idaho; Lakeview, Oregon; Milford, Utah; Rock Springs, WY; and
Yakima, Washington.
Solar + Energy Storage – a solar resource as described above paired with a 4-hour battery with
50% of the power capacity of the solar resource. The batteries paired with solar resources in the
previous IRP had 25% of the power of the solar resources.
Storage, Pumped Hydro Storage – a range (300 - 1,200 MW) of pumped storage systems using
a combination of natural and constructed water storage combined with elevation difference to
enable a system capable of discharging the rated capacity for 8 to 12 hours. Total development
time is estimated at 6 –to 8 years due to various progress on permitting. The recharge ratio for this
resource is 78 to 81 percent. Actual pumped hydro storage projects within PacifiCorp’s territory
were analyzed.
Storage, Lithium Ion Battery – a battery technology of lithium ion batteries located on
PacifiCorp owned property. Based on current commercial options such a system is modeled with
an acquisition and implementation schedule of one year. The recharge ratio for this storage
resource is 85 percent.
Storage, Flow Battery – a battery technology based vanadium RedOx or other flow battery types.
Based on current commercial options such a system is modeled with an acquisition and
implementation schedule of one year. The recharge ratio for this storage resource is 70 percent.
Storage, CAES – compressed air energy storage (CAES) system consists of air storage reservoir
pressurized by a compressor similar to a conventional gas turbine compression section but driven
by an electric motor coupled with an adiabatic power generation turbine. The compressed air
powers the adiabatic turbine. Off-peak energy is used to compress air into the storage reservoir. A
system size of 500 MW is assumed. The air storage reservoir is assumed to be solution mined to
size. No natural gas is required to generate power. The recharge ratio for this storage resource is
55 percent . The CAES resource modeled in the 2019 and prior IRP’s was a diabatic system which
differed from this resource in that it required burning fuel in the power generation turbine similar
to a gas turbine engine.
Nuclear, Advanced Fission – removed from the list of resource options due to lack of progress
by the developers.
Nuclear, Small Modular Reactor – such systems hold the promise of being built off-site and
transported to a location at lower cost than traditional nuclear facilities. A nominal 884 MW
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
192
concept is included. It is recognized that this concept is still in the design and licensing stage and
is not commercially available requiring approximately 7 years for availability.
Resource Types
Renewables
PacifiCorp retained Burns & McDonnell Engineering Company (BMcD) to evaluate various
renewable energy resources in support of the development of the 2021 IRP and associated resource
acquisition portfolios and/or products. The 2020 Renewable Resources Assessment and Summary
Tables (Assessment) (See Volume II, Appendix M) is screening-level in nature and includes a
comparison of technical capabilities, capital costs, and O&M costs that are representative of
renewable energy and storage technologies listed below. The Assessment contains preliminary
information in support of the long-term power supply planning process. Any technologies of
interest to PacifiCorp shall be followed by additional detailed studies during procurement proposal
evaluation to further investigate each technology and its direct application within the owner’s long-
term plans.
• Single Axis Tracking Solar
• Onshore Wind
• Energy Storage
o Pumped hydro energy storage (PHES)
o CAES
o Li-Ion Battery
o Flow Battery
• Solar + Energy Storage
• Wind + Energy Storage
Each renewable resource is defined within the Assessment. General assumptions, technology
specific assumptions and cost inclusions and exclusions are described within the Assessment. The
following paragraphs discuss highlights from the Assessment, a comparison to previous IRP data
and additional assessment performed by PacifiCorp.
Costs
The following costs which were excluded from the renewables costs estimates were added by
PacifiCorp:
• AFUDC
• Escalation
• Sales tax
• Property taxes and insurance
• Utility demand costs
Solar
The BMcD Assessment includes 100 MW, and 200 MW single axis tracking (SAT), PV options
evaluated at five locations within the PacifiCorp services area. The 2021 IRP differs from the
previous IRP in the following ways:
• Idaho, Washington and Wyoming solar resource costs were extrapolated from the previous
IRP to scale similarly to the Oregon and Utah solar resource cost changes.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
193
• The 5 MW option was removed and the 50 MW option for each of the five locations was
increased to 100 MW based upon industry trends of building larger solar facilities.
• The DC to AC ratio was reduced from 1.46 to 1.30 based upon industry trends.
Solar costs (including forecasted costs) used for the 2021 IRP closely match the forecasted costs
from the 2019 IRP through 2024 at which point the new linear forecast indicates costs may
continue to decrease more rapidly than forecasted in the 2019 IRP. The increase from the 2017
IRP Update is partially due to a different assumed design. The inverter loading ratio results in a
higher base capital cost, but a lower levelized cost of energy (LCOE). In addition to the different
design basis two significant events have occurred with respect to solar costs since the 2017 IRP.
In late September 2017 the International Trade Commission passed a finding of injury to US solar
manufacturers. A significant increase in solar prices in the US occurred following the ITC ruling.
Solar costs have since resumed a declining trend, though at a reduced rate of decline. On January
22, 2018, the United States levied a 30 percent tariff on solar imports. The tariff covers both
imported solar cells and solar modules. The tariff is expected to last for four years falling by five
percent annually, dropping to a 15 percent tariff in 2021. At the time the tariff was levied solar
prices briefly halted their decline from the peak price which occurred after the ITC ruling.
Figure 7.3 shows a history of capital costs and a forecast used in the SSR for PV resources in Utah
and Oregon. The forecast data for the PV costs were provided via NREL data on an annual basis.
The dotted lines show the forecast from the 2019 IRP. The NREL forecast has changed to a linear
decline over the next ten years. The data from prior IRP’s was based on a 50 MW scale; however,
the 50 MW scale is no longer included as a resource option. The dashed lines show the costs for
100 MW, while the solid line indicates the price forecast at the 200 MW scale. It appears that the
economy of scale has shifted to the larger (200 MW) scale plants.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
194
Figure 7.3 – History of SSR PV Cost & Forecast
Wind
Wind energy has been one of the most cost-effective new generation resources for PacifiCorp’s
customers in recent IRPs and led to PacifiCorp’s Energy Vision 2020 initiative. Energy Vision
2020 included the repowering of existing wind facilities, three new wind projects, a new 500-kV
transmission line, and upgrades to existing infrastructure to deliver the new wind generation to
PacifiCorp’s customers. The three new wind projects added 1,150 MW of new wind power to
PacifiCorp’s generation resources. The wind market knowledge gained by PacifiCorp during the
construction of the Energy Vision 2020 wind projects has been combined with the information in
the BMcD Assessment to inform the wind costs in the 2021 IRP. Changes in the federal production
tax credits (PTCs) for wind projects will also impact the market conditions for wind project in the
coming years.
The BMcD Assessment uses a 200 MW project size that can be realized within most wind
development areas in PacifiCorp’s service territory and large enough to achieve economies of
scale. Multiple 200 MW projects can be selected within the IRP models to meet larger generation
needs. The net capacity factors for onshore wind generating facilities in the states of Idaho, Oregon,
Utah, Washington, and Wyoming reflect strong wind resources that are achievable within or near
PacifiCorp’s service areas. BMcD relied on publicly available data and proprietary computational
programs to complete the net capacity factor characterization. Generic project locations were
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
195
selected by the company based on viable wind project locations where there are favorable wind
profiles. Although the size of wind turbines in the SSR has increased from 3.6 MW to 4.0 MW the
cost for utility scale wind farms in the 2021 IRP is very similar to the costs in the 2019 IRP.
Federal PTCs were extended in December 2020 to allow wind projects that begin construction in
2021 and complete construction before December 31, 2024 to qualify for a 60% of the full tax
credit amount. Wind projects that started construction in 2016 and 2017 were granted an extra year
to complete construction and qualify for production tax credits due to Covid 19. The 2016 and
2017 projects must now be completed by 2021 and 2022 respectively. Wind construction activity
is expected to remain strong through 2024 due to the PTC extensions. Burns & McDonnell
estimates the cost of wind projects will decrease by approximately 15 percent over the next ten
years as shown in Figure 7.4, while other estimates indicate the levelized cost of energy for wind
production could decline as much as 20 percent over the next ten years. The progressive national
goals for renewable energy being put in place by the Biden administration could help sustain
growth in the wind industry over the next decade and beyond.
Offshore Wind
Offshore wind holds the promise of high production capacity but faces various risks and costs that
are higher than onshore wind projects. The most promising offshore wind regimes are located
approximately 10 to 20 miles from the coast and will require underwater electric transmission lines
to connect to the shore. New offshore wind projects will have to bear the cost of underwater
transmission lines and any land-based transmission upgrades that are required to interconnect the
project to the grid. Offshore wind turbines along the Pacific coast will need to be built on floating
bases due to water depths that are hundreds of meters deep, as compared to offshore wind
developments in shallower waters along the Atlantic coast. Floating offshore wind turbines are
much less common than seabed-mounted offshore wind turbines that can be built in ocean waters
up to 60 meters deep. Interest in offshore wind along the Pacific coast has increased during the
past year and the advancement of two areas for offshore wind development along the coast of
California by the US Department of the Interior was a significant step forward in the development
process. PacifiCorp is reviewing offshore wind studies and reports and may include offshore wind
as a resource in the SSR for the 2023 IRP.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
196
Figure 7.4 – History of SSR Wind Costs & Forecast
Solar and Wind Capital Costs
Capital cost estimates for wind resources in the IRP are based upon a combination of information
sources including the Burns & McDonnell study, communications with wind equipment suppliers
and construction companies, and from PacifiCorp’s experience with active and recently completed
wind construction projects. All wind resources are specified in 200 MW blocks, but the model can
choose multiple blocks or a fractional amount of a block.
Solar and Wind Resource Capacity Factors and Energy Shapes
Resource options in the topology bubbles are assigned capacity factors based upon historic or
expected project performance. Assigned capacity values for solar resources are 24% in
Washington, 26% in Idaho, 27% in Oregon and Wyoming, and 30% in Utah. Assigned capacity
factor values for wind resources are 43 percent in Wyoming, 37 percent in Washington, Oregon
and Idaho, and 29 percent in Utah. Capacity factor is a separate modeled parameter from the capital
cost and is used to scale wind energy used in IRP modeling The hourly generation shape reflects
average hourly wind variability. The hourly generation shape is repeated for each year of the
simulation.
Geothermal
Geothermal resources can produce base-load energy and have high reliability and availability.
However, geothermal resources have significantly higher development costs and exploration risks
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
197
than other renewable technologies such as wind and solar. PacifiCorp has commissioned several
studies of geothermal options during the past ten years to determine if additional sources of
production can be added to the company’s generation portfolio in a cost-effective manner. A 2010
study commissioned by PacifiCorp and completed by Black & Veatch focused on geothermal
projects near to PacifiCorp’s service territory that were in advanced phases of development and
could demonstrate commercial viability. PacifiCorp commissioned Black & Veatch to perform
additional analysis of geothermal projects in the early stages of development and a report was
issued in 2012. An evaluation of the PacifiCorp’s Roosevelt Hot Springs geothermal resource was
commissioned in 2013. The geothermal capital costs in the 2019 supply side resource option are
built on the understanding gained from these earlier reports, publicly available capital costs from
the Geothermal Resources Council and publicly available prices for energy supplied under power
purchase agreements.
The cost recovery mechanisms currently available to PacifiCorp as a regulated electric utility are
not compatible with the inherent risks associated with the development of geothermal resources
for power generation. The primary risks of geothermal development are dry holes, well integrity
and insufficient resource adequacy (flow, temperature and pressure). These risks cannot be fully
quantified until wells are drilled and completed. The cost to validate total production capability of
a geothermal resource can be as high as 35 percent of total project costs. Exploration test wells
typically cost between $500,000 and $1.5 million per well. Full production and injection wells cost
between $4-5 million per well. Variations in the permeability of subsurface materials can
determine whether wells in proximity are commercially viable, lacking in pressure or temperature,
or completely dry with no interconnectivity to a geothermal resource. As a regulated utility subject
to the public utility commissions of six states, PacifiCorp is not compensated nor incentivized to
engage in these inherently risky development efforts.
To mitigate the financial risks of geothermal development, PacifiCorp would use an RFP process
to obtain market proposals for geothermal power purchase agreements or build-own-transfer
project agreement structures. Geothermal developers, external to PacifiCorp, have the flexibility
to structure project pricing to include all development risks. Through an RFP process, PacifiCorp
could choose the geothermal project with the lowest cost offered by the market and avoid
considerable risk for the company and its customers. Several geothermal projects submitted
proposals in response to the 2016 Oregon Renewables RFP, but none of the geothermal projects
were selected as a new PacifiCorp generation source. In the event PacifiCorp identifies a
geothermal asset that appears to be economically attractive but also determines that there is a
significant possibility of development risk that the market will not economically absorb,
PacifiCorp may approach state regulators with estimates of resource development costs and risks
associated to obtain approval for a mechanism to address risks such as dry holes. Because public
utility commissions typically do not allow recovery of expenditures which do not result in a direct
benefit to customers, and at least one state has a statute that precludes cost recovery of any asset
that is not considered to be “used and useful,” obtaining a mechanism to recover geothermal
development costs may be difficult.
Energy Storage
The Burns and McDonnell Assessment discusses three energy storage resource options: 1) PHES),
2) CAES, and 3) battery storage. Battery storage was also considered in combination with solar
and wind. The addition of wind plus storage and solar plus storage created a large number of new
resource options in the SSR. To mitigate the impact of the additional information less emphasis
was placed on the various battery chemistries. Two of the three pumped hydro projects included
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
198
in both the 2017 and 2019 IRP’s showed modest capital cost declines while one showed a modest
cost increase. The capital cost for CAES showed a 24 percent cost decrease, despite the change
technology change from an adiabatic system to a diabatic system. No forecasts have been used for
pumped hydro and CAES. Both technologies are expected to have a flat forecast despite the recent
movement in costs. Error! Reference source not found. shows a history of capital costs and a
forecast used in the SSR for Li-Ion and flow battery resources. The dotted lines show the forecast
from the 2019 IRP. The data from prior IRP’s was based on a 1 MW scale; however, the 1 MW
scale is no longer included as a resource option. The dashed lines show the 2020 costs for 100 MW
scale, while the solid line indicates the price forecast at the 50 MW scale, indicating a significant
economy-of-scale benefit. Battery costs are expected to continue to decline for the next ten years.
Due to the complexity and maturity of the battery market, O&M costs continue to be an area of
some uncertainty.
Figure 7.5 – History of SSR Battery Energy Storage System Costs & Forecast
PacifiCorp and its Berkshire Hathaway Energy affiliates continuously monitor and evaluate
technical developments in the utility power industry, including energy storage technologies
(lithium-ion and flow batteries, pumped storage hydro and hybrid energy-storage solutions),
nuclear and carbon capture technologies. With the ever-advancing technological developments,
market conditions, and regulatory environment, it is critical that PacifiCorp understand when
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
199
developing technologies and other opportunities become sufficiently established in the
marketplace that they can be implemented with minimal risk to PacifiCorp’s system customers.
Fortune Business Insights estimates the global battery energy storage market size stood at $7.06
billion in 2019 and is anticipated to reach $19.74 billion by 2027, at a CAGR of 20.4%. The growth
and technological advancements in lithium-ion batteries for the electric vehicle markets have
resulted in technological advancements and cost reductions that also stand to benefit the electric
utility market. PacifiCorp has monitored the use of lithium-ion battery storage in the electric utility
market and believes based on its analysis and experience that the technology is mature enough for
large scale deployment.
PacifiCorp has experience in all aspects of battery storage project development and execution
including, budgeting, proforma, tax credits, siting, permitting, interconnection, engineering,
equipment procurement, construction, project controls, quality assurance, commissioning,
operation, and maintenance. PacifiCorp has utilized this expertise in 1) the development of proxy
resources for the integrated resource plans since 2009, 2) the development of the use cases and
specifications outlined in the 2020 all source request for proposal and 3) in the execution and
construction of two battery storage demonstration projects and a third of which is in design
development.
PacifiCorp has included consideration of battery storage in its IRP as a system resource since 2009.
Since then, PacifiCorp actively monitored developments in battery storage and its cost, use, and
application to our system resource planning. By 2015 battery storage became a more viable
resource alternative, and PacifiCorp assigned an internal subject matter expert to track, review and
evaluate ongoing and emerging developments in the battery storage market and the value that
energy storage could provide to our customers.
PacifiCorp also leverages the broader Berkshire Hathaway Energy platform of companies
including NV Energy and MidAmerican Energy to collaborate and share experiences and lessons
learned regarding battery energy storage technology and capturing the value of energy storage. NV
Energy has been a leader in battery storage implementation having signed contracts for more than
1 gigawatt of solar and 100 MW of storage in 2018 and an additional 1.2 gigawatts of solar and
590 MW of batteries contracted in 2019, and having further implemented residential, small and
large commercial and industrial energy storage customer programs,[1] and having installed several
transmission and distribution pilot projects.
In addition to leveraging the experience of its peer utilities, PacifiCorp has engaged the expertise
of market-leading 3rd party technical experts including WSP, Black & Veatch, Power Engineers,
FlexGen, Tesla and other leading battery consultants and suppliers to develop its proxy resource
assumptions, develop its procurement specifications, evaluate bidders and design and construct
utility-owned transmission and distribution facilities.
In 2019, PacifiCorp’s IRP process identified approximately 700 megawatts of battery storage as a
part of its least-cost portfolio and 2019 IRP action plan and worked to incorporate battery storage
resources into the resulting 2020 all-source request for proposal. Leading up to the inclusion of
battery storage in the 2020 all-source request for proposal, PacifiCorp developed a preferred
supplier list, standard specifications, and system control schemes for battery storage facilities. In
[1] https://www.nvenergy.com/cleanenergy/energy-storage/storage-faqs
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
200
the request for proposal, PacifiCorp outlined battery storage use cases and required functionality
to ensure battery storage proposals value was captured through battery energy storage bids. Finally,
PacifiCorp engaged outside legal expertise in the structuring of contracting terms and conditions
to mitigate any remaining delivery risk to its customers. Such outside legal expertise brings in
battery storage contracting knowledge and experience from both within and outside the Berkshire
Hathaway Energy.
PacifiCorp procurement and operational experience with battery storage projects
PacifiCorp completed the Panguitch Solar and Battery Storage project in Utah in 2020 as a utility-
owned and operated transmission and distribution upgrade deferral project. In 2019-2020,
PacifiCorp partnered with Sonnen, Inc. and the Wasatch Group to complete The Soleil Lofts
Residential Apartment Project, a network of solar powered battery storage systems for the benefit
of the apartment community and PacifiCorp’s customers. PacifiCorp is currently completing the
development and design for a second transmission and distribution upgrade deferral project in
Oregon to install a battery storage project at the Oregon Institute of Technology in Klamath Falls,
which is scheduled for completion in 2022. These three projects demonstrate the capability and
validate the value battery storage provides to the electrical grid through peak shifting in order to
defer the cost to upgrade regional transmission and distribution lines. PacifiCorp had complete
turnkey responsibility for the Panguitch Solar and Battery Storage facility and will similarly be
responsible for the Oregon Institute of Technology facility. The Soleil Lofts facilities were
developed, constructed and owned by a 3rd party, but are being dispatched by PacifiCorp’s Energy
Supply Management Group for the benefit of PacifiCorp’s system.
Panguitch Solar and Battery Storage Project
To correct voltage issues experienced during peak loading conditions on a portion of PacifiCorp’s
system in southern Utah, a stationary battery system and photovoltaic solar array was installed on
a distribution circuit out of the Panguitch substation located in Garfield County, Utah. This project
will alleviate peak loading on the power transformer, improve voltage conditions, and defer costs
associated with upgrading the upstream 69-kV sub-transmission system under a traditional poles
and wires build-out. The Panguitch project was a 650-kilowatt photovoltaic solar field and one
megawatt, five-hour battery system in central Utah. PacifiCorp with Black & Veatch and battery
supplier FlexGen developed multiple operating modes to demonstrate the full range and
capabilities of 684 Samsung lithium-ion batteries and how different control modes affect energy
system operation.
The Utah Public Service Commission approved the Panguitch battery storage project (1 MW, 5
MWh) under the Sustainable Transportation and Energy Plan/Utah Innovative Technologies
(STEP/UIT) program December 29, 2016. The solar photovoltaic component (650 kW) of the
project was separately funded by the company’s Blue Sky program. PacifiCorp completed the
purchase of a ten-acre project site in October 2017. Construction began in July 2019 and was
completed in late 2019. Commercial operations began in 2020.
Since commercial operations began, the company has worked with the battery provider to refine
the control algorithms to enable charging of the battery only from the on-site solar generation
facility. The company is currently collecting solar and battery charge/discharge data from the site
to further optimize operational performance.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
201
Soleil Lofts Residential Apartment Project
Soleil Lofts, located in Herriman, Utah is an all-electric, net-zero development, that will generate
as much electricity as it uses through rooftop solar panels backed up with battery storage.
PacifiCorp collaborated with the Soleil Lofts residential apartment project to develop a behind the
meter application of battery systems. This project is the largest utility-managed residential battery
demand response solution in the United States. PacifiCorp with Sonnen, Inc. and the Wasatch
Group completed a network of solar powered battery storage systems for the benefit of the
apartment community and PacifiCorp’s customers. The project features over 630 individuals
Sonnen ecoLinx batteries, totaling 12.6 MWh of solar energy storage that is managed by
PacifiCorp. The batteries provide emergency back-up power, daily management of peak energy
use, and demand response for the overall management of the electric grid and demonstrating a way
to expand residential renewable power capacity.
Oregon Institute of Technology
Oregon House Bill (HB) 2193, passed in June of 2015 directed electric companies in Oregon to
identify and evaluate potential energy storage technologies. PacifiCorp has commenced a project
to engineer, design, procure, interconnect, and commission a 2 MW (6 MWh) battery storage
project on the campus of the Oregon Institute of Technology (“OIT”) in Klamath Falls,
Oregon. Design and procurement activities are underway in parallel with the generation
interconnection review process. The project is expected to go into service in early 2023.
PacifiCorp has contracted Kiewit Engineering as the Owner’s engineer, Power Engineers as the
Engineer of Record, and is working with supply vendors to secure a final purchase agreement.
Once the design is complete a construction contractor will be selected via competitive bid.
PacifiCorp’s engineering and management team are also working with OIT to provide a student
learning experience by partnering with OIT student groups who will be working with the project
team during the design and construction of the project.
Outside Engineering Support for Battery Storage Procurement and Operations
In preparation for the 2020 all-source request for proposal which resulted from the resource need
action items in the 2019 IRP process, PacifiCorp engaged WSP to 1) develop preferred use case
and technical specifications for collocated and stand-alone storage resource bids, 2) evaluate the
technical bid responses, and 3) update the generating-resource power purchase agreements to
include battery storage terms and conditions and relevant exhibits needed for a collocated resource
and storage power purchase agreement.
WSP is a globally recognized professional services firm with a 130-year history. WSP’s primary
inputs have been in a supporting role, assisting in the development of revised specification specific
to wind and solar farm equipment and installations including accompanying battery storage
facilities. Specific to battery storage, WSP has been influential in assisting PacifiCorp in the
development of Li-battery specifications and has participated in the development of operating and
contractual parameters that will become part of our revised power purchase agreement contract
template in the 2020AS RFP contracting process.
A summary of WSP team members, their role and years of experience is provided in Table 7.6.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
202
Table 7.6 – WSP Team Roles and Years of Experience
Role # Years of
Experience
Principal-In-Charge 19
Project Manager 27
BESS / SCADA Expert 7
BESS Constructability and Operations 29
BESS / Electrical Engineering (US) 9
BESS / Electrical Engineering (CAN) 7
BESS Systems Engineer 6
As stated above, PacifiCorp has been actively monitoring developments in battery storage since
2009 with support through the broader Berkshire Hathaway Energy platform of companies
including NV Energy and MidAmerican Energy and through the engagement of market-leading
companies like WSP, Black & Veatch, Power Engineers, FlexGen, Tesla. Further, PacifiCorp is
actively evaluating and pursuing new control systems that will both integrate and optimize battery
storage, and other electronically controlled distributed assets, to further assure both maximum
customer benefit and improved system flexibility and stability for years to come. With each new
battery storage resource added to on our system, we gain additional depth and experience that we
then apply to the next cycle of integrated resource planning and subsequent resource procurement.
Natural Gas
A variety of natural gas-fueled generating resources are included in the SSR. The variety of natural
gas resources were selected to provide for generating performance and services essential to safe
and reliable operation of the energy grid. Performance, cost and operating characteristics for each
resource were provided at elevations of 1,500, 3,000, 5,050 and 6,500 feet above mean sea level,
representative of geographic areas in which the resource could be located. Performance, cost and
operating characteristics were also provided at zero feet above mean sea level and 59 °F (ISO
conditions) as a reference. The essential services provided by the resource are firming for variable
energy resources, intermediate and base generation.
Three simple cycle combustion turbine options and one reciprocating engine option could provide
peaking generating services. Peaking generating services require the ability to start and reach near
full output in less than ten minutes. Peaking generating services also require the ability in increase
(ramp up) and decrease (ramp down) very quickly in response to sudden changes in power demand
as well as increases and decreases in production from intermittent power sources. Peaking
generation provide the ability to meet peak power demand that exceed the capacity of intermediate
and base generation. Peak generation also provide reserves to meet system upsets.
Options for firming and peaking resources included in the supply side resources are: 1) three each
General Electric (GE) LM6000 PF aero-derivative simple cycle combustion turbines, 2) two each
GE LMS 100PA+ aero-derivative simple cycle combustion turbines, 3) one each GE 7F frame
simple cycle combustion turbine, and 4) six each Wasilla 18V50SG reciprocating internal
combustion engines. All of these options are highly flexible and efficient. Higher heating value
heat rates for the resource ranged from 9,936 Btu/kW-hr for the SCCT Frame “F” to 8,286 Btu/kW-
hr for the 18V50SG engines. Installation of high temperature oxidation catalysts for carbon
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
203
monoxide (CO) control and a selective catalytic reduction (SCR) system for NOx control would
be available for these resources.
Eight combined cycle combustion turbine options could provide firming, intermediate and base
generating service. Firming generating service requires resources that can increase and decrease
generation to replace decreases and increases in generation from variable energy resources.
Intermediate generating service requires resources that are able to efficiently operate at production
rates well below full production in compliance with air emissions regulations for long periods of
time. Intermediate generating service also require the ability to change production rates quickly.
Intermediate generation services provide cost effective means of providing power demand that is
greater than base load and lower than peak demands. Base generating service requires a highly
cost effective that is capable of operating at full production for long periods of time. Base
generation provides for the minimum level of power demand over a day or longer period of time
at a very low cost.
Options for intermediate and base generation were based on two size classes of engines. The “H”
size was represented by a GE HA.01. The “J” was represented by the GE HA.02. Each engine was
arranged in a one combustion turbine to one steam turbine (1x1) and a two-combustion turbine to
one steam turbine (2x1) configuration to obtain four resource options. The combined cycle
resources offered high heating value heat rates from 6,352 to 6,487 Btu/kW-hr. Installation of
oxidation catalysts for CO control and SCR systems for NOx control is expected. All of the
combined cycle options included dry cooling allowing them to be located in areas with water
resource concerns.
Duct Firing (DF) of the combined cycle is shown in the SSR table. Duct firing is not a stand-alone
resource option but is considered to be an available option for any combined cycle configuration
and represents a low-cost option to add peaking capability at relatively high efficiency and also a
mechanism to recover lost power generation capability at high ambient temperatures. Duct firing
is shown in the SSR table as a fixed value for each combined cycle combination. In practice the
amount of duct firing is a design consideration which is selected during the development of
combined cycle generating facilities.
While equipment provided by specific manufacturers were used to for cost-and-performance
information in the SSR table, more than one manufacturer produces these types of equipment. The
costs and performance used here is representative of the cost and performance that would be
expected from any of the manufacturers. Final selection of a manufacturer’s equipment would be
made based on a bid process.
Coal
Coal resources are shown in the SSR table as new supercritical pulverized coal (PC) boilers and
IGCC located in Utah and Wyoming at an existing site. Both resource types include CO2 capture
and compression needed for transportation. The standard design technology for PC boilers is
supercritical technology (compared to subcritical). Supercritical technology is generally more cost-
effective because it has a higher efficiency (resulting in a lower overall emissions intensity), has
better load following capability, faster ramp rates, uses less water and requires less steel for
construction. As such, there is a greater competitive marketplace for large supercritical boilers than
for subcritical boilers, and large boiler manufacturers only offer supercritical boilers in the 500-
plus MW sizes. A new coal-fueled generating facility would be subject to carbon dioxide emissions
limits (1,400 lbs per megawatt-hour gross) under the Federal New Source Performance Standards
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
204
(NSPS) for Greenhouse Gases (GHG). These emission limits are only achievable if a coal-fueled
generating facility is equipped with CCUS technology; however, this imposes a significant cost
for both new and existing coal resources. Based on this requirement, only coal resource options
that include CCUS technology are included in the SSR table. The capital and O&M costs for new
coal-fuel generation options were updated by escalating corresponding costs used in the 2019 IRP.
The CCUS retrofit costs were updated using information from existing carbon capture facilities,
relevant studies and CCUS developers.
Carbon Capture Utilization and Sequestration
There are a limited number of commercial-scale carbon capture projects in operation around the
world. Most have been installed in conjunction with a planned carbon dioxide end use of injection
for EOR. There are only two major utility-scale CCUS retrofit projects on coal plants in North
America that have been operated commercially. SaskPower’s Boundary Dam Power Station Unit
3 (115 MW net), located in Saskatchewan, Canada, was retrofitted with an amine-based carbon
capture system and entered commercial operation in October 2014. The captured carbon dioxide
is piped 41 miles to the Weyburn field to be used for EOR. Any carbon dioxide not used for EOR
is sequestered at the Aquistore research project. The total cost of the project was approximately
$1.24 billion (including approximately $200 million through federal grants). In July 2016, the plant
reached a major milestone when it demonstrated that over 1,100,000 tons of carbon dioxide had
been captured.
NRG Energy installed a 240 MW equivalent flue gas slipstream amine-based carbon capture
system on W.A. Parish Generating Station Unit 8 that went into commercial operation in January
2017. The project, named the Petra Nova Project, was a joint venture between NRG Energy and
JX Nippon Oil & Gas Exploration, and cost approximately $1 billion. Approximately $195 million
of federal funding in grants was awarded to the project as part of the Clean Coal Power Initiative
Program (CCPI), a cost-shared collaboration between the federal government and private industry.
The Petra Nova Project included a retrofit of an existing coal-fueled plant using amine-based
system and captured approximately 5,200 short tons per day when operating at full capacity.4
Captured carbon dioxide was transported through an 81-mile pipeline and used for EOR at the
West Ranch Oilfield, located on the Gulf Coast of Texas. It is the largest carbon capture retrofit of
a pulverized coal plant in the world. The amine-based capture system utilizes Mitsubishi's
proprietary KM CDR Process® and uses its KS-1™ amine solvent. Due to low demand for and
price of oil in 2020, NRG Energy announced Petra Nova would be placed in a reserve shutdown
effective May 1, 2020.5 In January 2021, the Electric Reliability Council of Texas received a
Notification of Suspension of Operations (NSO) for Petra Nova Power.6 The NSO stated the
resource would be mothballed indefinitely as of June 26, 2021.7
To address the availability and viability of commercial sequestration near PacifiCorp coal
generation resources, three PacifiCorp power plants participated in federally funded research to
conduct a Phase I pre-feasibility study, which was awarded in 2016, for carbon capture and storage.
4 W.A. Parish Post-Combustion CO2 Capture and Sequestration Demonstration Project Final Scientific/Technical
Report; March 31, 2020.
5 Petra Nova status update | NRG Energy
6 W-A012721-01 Notification of Suspension of Operations (NSO) for Petra Nova Power I LLC (PNPI_GT2)
(ercot.com)
7 A March 2021 notice was issued, moving up the date to suspend operations to June 1, 2021. W-A012721-03 Date
of suspension of operations changed - Indefinite Mothball Status of Petra Nova Power I LLC (PNPI_GT2)
(ercot.com)
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
205
A grant from the U.S. Department of Energy (DOE) to the University of Wyoming was used to
assess the storage of carbon dioxide in the Rock Springs Uplift, a geologic formation located
adjacent to the Jim Bridger Plant in southwest Wyoming. Similar funding was allocated to the
University of Utah to study the feasibility of long-term carbon dioxide storage in the San Rafael
Swell near the Hunter and Huntington plants in central Utah. Both projects showed that geological
formations exist near the plants that may support carbon sequestration, though further studies
would be required. Neither site was selected by the U.S. DOE for an advanced study in the Phase
II of the grant program.
PacifiCorp issued a request for expression of interest to potential CCUS counterparties on
September 7, 2018. The request focused on possible deployment of CCUS technologies at
PacifiCorp’s Dave Johnston generating facility, including utilization of EOR. On February 28,
2019, PacifiCorp received Phase I feasibility studies from three respondent parties. On April 23,
2019, the participants were notified they could opt to progress to a Phase II front-end engineering
and design (FEED) study at their discretion. Only one of the parties expressed intent to complete
a FEED study. No participants received DOE funds to support Phase II studies. PacifiCorp remains
open to evaluate any CCUS project proposal that may arise from these efforts. As part of its
ongoing CCUS evaluation, PacifiCorp issued a new request for expression of interest (REOI) for
CCUS on June 29, 2021 to identify and engage with any interested parties to explore the feasibility
and design of CCUS facilities to remove carbon dioxide from exhaust gases for PacifiCorp’s
Wyoming coal-fueled generation, and subsequently utilize and/or sequester all removed carbon
dioxide. Responses to the REOI will be a precursor to a PacifiCorp issuing a request for proposal
(RFP) for CCUS projects.
PacifiCorp continues to monitor and evaluate current and emerging CCUS technologies for
possible retrofit application on its existing coal-fired resources, as well as their applicability for
future fossil fueled plants that could serve as cost-effective alternatives to IGCC plants. An option
to capture carbon dioxide at an existing coal-fired unit has been included in the SSR. Due to the
high capital cost of implementing CCUS on coal-fueled generation (both on a retrofit basis and for
new resources) and applicable tax credits, CCUS was not considered viable in previous IRPs.
Capital cost, transportation infrastructure, availability of commercial sequestration (non-EOR)
sites, long-term liabilities for sequestration, and the lack of availability of federal funding continue
to contribute to the risk and uncertainty of CCUS.
Coal Plant Efficiency Improvements
Fuel efficiency gains for existing coal plants, which are manifested as lower plant heat rates, are
realized by: (1) continuous operations improvement, (2) monitoring the quality of the fuel supply,
and (3) upgrading components if economically justified. Efficiency improvements can result in a
smaller emissions footprint for a given level of plant capacity, or the same footprint when plant
capacity is increased.
The efficiency of generating units, primarily measured by the heat rate (the ratio of heat input to
energy output) degrades gradually as components wear over time. During operation, controllable
process parameters are adjusted to optimize the unit’s power output compared to its heat input.
Typical overhaul work that contributes to improved efficiency includes (1) major equipment
overhauls of the steam generating equipment and combustion/steam turbine generators, (2)
overhauls of the cooling systems and (3) overhauls of the pollution control equipment.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
206
When economically justified, efficiency improvements are obtained through major component
upgrades of the electricity generating equipment. The most notable examples of upgrades resulting
in greater generating capacity are steam turbine upgrades. Turbine upgrades can consist of adding
additional rows of blades to the rearward section of the turbine shaft (generically known as a
“dense pack” configuration), but can also include replacing existing blades, replacing end seals,
and enhancing seal packing media. Currently PacifiCorp has no plans to make any major steam
turbine or generator upgrades over the next 10 years.
Nuclear
PacifiCorp revisited the NuScale Small Modular Reactor (SMR), but used nth-of-a-kind pricing
rather than the 1st-of-a-kind pricing previously used for the plant being developed for construction
at the Idaho National Lab site. NuScale provided an update on their design, licensing and costs.
NuScale’s update resulted in a significant decline in the capital cost number for the Small Modular
Reactor (SMR) resource option. Blue Castle Holdings (BCH) again did not provide updated
pricing, therefore the advanced reactor option based on the AP1000 design was eliminated from
the resource options.
NuScale is developing an advanced reactor design in the SMR category. Although it is an FOAK
technology, the design has inherent safety features which support reduced capital costs and
operating cost estimates. PacifiCorp has a seat on the NuScale advisory board; however PacifiCorp
has no monetary interest in NuScale or the SMR project being developed for the Idaho National
Lab site. PacifiCorp added five percent contingency and ten percent delay costs due to the lack of
maturity for the technology. Details of NuScale’s SMR can be found at www.nuscalepower.com.
PacifiCorp’s capital cost estimates include a 10.36 percent owner’s cost for the NuScale resource.
PacifiCorp’s 2021 IRP includes the NatriumTM advanced nuclear demonstration project: a molten
sodium-cooled nuclear reactor paired with a molten salt thermal energy storage tank. Both the
reactor and the molten salt energy storage generate power through a single steam turbine.
At this time, the specific cost and performance assumptions for the NatriumTM advanced nuclear
demonstration project are confidential and are not summarized in the SSR. The demonstration
project has three primary elements: a nuclear reactor that produces heat, a steam generator to
convert heat to electricity, and a molten salt tank to store heat. Operating characteristics of this
facility are summarized as follows:
• 345 MW of baseload energy production at a 92.5% capacity factor
• Maximum output of 500 MW
• Minimum output of 100 MW
• A ramp rate of approximately 40 MW per minute from min to max
• Molten salt storage supports maximum output of 500 MW for a 5.5-hour duration (max
output then drops to 345 MW until output is reduced and more heat can be stored)
• Maximum storage efficiency is 99%
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
207
Demand-Side Resources
Resource Options and Attributes
Source of Demand-Side Management Resource Data
PacifiCorp conducted a Conservation Potential Assessment (CPA) with for 2021-2040, which
provided DSM resource opportunity estimates for the 2021 IRP. The study was conducted by
Applied Energy Group (AEG) on behalf of the company. The CPA provided a broad estimate of
the size, type, location and cost of demand-side resources.8 For the purpose of integrated resource
planning, the DSM information from the CPA was converted into supply curves by type of
resource (i.e. energy-based energy efficiency and demand response) for modeling against
competing supply-side alternatives.
Demand-Side Management Supply Curves
DSM resource supply curves are a compilation of point estimates showing the relationship between
the cumulative quantity and cost of resources, providing a representative look at how much of a
particular resource can be acquired at a particular price point. Resource modeling utilizing supply
curves allows the selection of least-cost resources (e.g. products and quantities) based on each
resource’s competitiveness against alternative resource options. Due to the timing of the 2021 IRP
planning and modeling, PacifiCorp had established, funded and begun acquiring 2021 DSM
program acquisition targets. To ensure that the 2021 IRP analysis is consistent with existing
planned energy efficiency acquisition levels (i.e., Class 2 DSM), expected DSM savings in each
state were fixed for calendar year 2021. Beyond 2021, the model optimized DSM selections.
As with supply-side resources, the development of DSM supply curves requires specification of
quantity, availability, and cost attributes. Attributes specific to DSM curves include:
• Resource quantities available in each year either in terms of megawatts or megawatt-hours,
recognizing that some resources may come from stock additions not yet built, and that elective
resources cannot all be acquired in the first year of the planning period;
• Persistence of resource savings (e.g., energy efficiency equipment measure lives);
• Seasonal availability and hours available (e.g., irrigation load control programs);
• The hourly shape of the resource (e.g., load shape of the resource); and
• Levelized resource costs (e.g., dollars per kilowatt per year for energy efficiency, or dollars
per megawatt-hour over the resource’s life for demand response resources).
Once developed, DSM supply curves are treated like discrete supply-side resources in the IRP
modeling environment.
Demand Response: DSM Capacity Supply Curves
The potential and costs for demand response resources were provided at the state level, with
impacts specified separately for summer and winter peak periods. To acquire resource needs
identified in the 2019 IRP, the company issued the All Source (AS) 2020 RFP for large scale
resources and subsequently issued a demand response (DR) RFP for DR resources. Successful
initial short list bids from this DR RFP joined final bids from the AS 2020 RFP for a combined
analysis in the 2021 IRP to determine the optimal acquisition of resources to meet system needs.
8 The 2021 Conservation Potential Study is available on PacifiCorp’s demand-side management web page.
www.pacificorp.com/energy/integrated-resource-plan/support.html.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
208
In 2022, where competitive bids overlapped with measures in the conservation potential
assessment (CPA), competitive bids were substituted for demand response measures identified in
the CPA to avoid double counting of demand response resources in the IRP and reflect resource
characteristics and current pricing. In 2023 and beyond RFP and CPA resources were modeled
together to assess the upper limit on demand response opportunities and value within the IRP given
limitations on front office transactions. Resource price differences between states for similar
resources reflect differences in each market, such as irrigation pump size and hours of operation,
as well as product performance differences.
Table 7.7 and Table 7.8 show the summary level demand response resource supply curve
information, by control area. For additional detail on demand response resource assumptions used
to develop these supply curves, see Volume 3 of the 2021 CPA.9 Potential shown is incremental
to the existing DSM resources identified in Table 7.7 For existing program offerings, it is assumed
that the PacifiCorp could begin acquiring incremental potential in 2021. For resources representing
new product offerings, it is assumed PacifiCorp could begin acquiring potential in 2022,
accounting for the time required for program design, regulatory approval, vendor selection, etc.
Table 7.7 – Demand Response Program Attributes West Control Area10,*
Summer Winter
Product
20-Year
Potential
(MW)
Average
Levelized
Cost
($/kW-
yr)
20-Year
Potential
(MW)
Average
Levelized
Cost
($/kW-yr)
Res - EV DLC 14 $144 15 $145
Res - Home Energy Management System 14 $84 5 $166
Res – HVAC DLC 11 $181 58 $61
Res – Pool Pump DLC 0.3 $521 0.3 $524
Res – Water Heater DLC 1 $62 2 $29
Res – Smart Thermostat 63 $31 23 $65
Res – Grid Interactive Water Heaters 18 $141 60 $61
Res –Battery DLC 50 $69 50 $69
C&I –Battery DLC 47 $48 47 $48
C&I – Grid Interactive Water Heaters 4 $93 8 $51
C&I – HVAC DLC 4 $141 8 $51
C&I – Pool Pump DLC 4 $330 2 $364
C&I – Smart Thermostats 0 $20 0 $301
C&I – Water Heater DLC 8 $48 5 $43
C&I – Third Party 62 $273 56 $335
Ag – Irrigation DLC 8 $51 0 $0
* Average levelized cost weighted by the 20-year cumulative potential in each state
9 The CPA can be found at: www.pacificorp.com/energy/integrated-resource-plan/support.html.
10 Demand response resources derived from the demand response RFP are not included to protect confidential 3rd
party pricing information.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
209
Table 7.8 – Demand Response Program Attributes East Control Area11
Summer Winter
Product
20-Year
Potential
(MW)
Levelized
Cost
($/kW-
yr)
20-Year
Potential
(MW)
Levelized
Cost
($/kW-yr)
Res - EV DLC 210 $62 210 $62
Res - Home Energy Management System 1 $971 1 $1,020
Res – HVAC DLC 42 $94 63 $192
Res – Pool Pump DLC 0.3 $585 0.3 $585
Res – Water Heater DLC 2 $142 6 $63
Res – Grid Interactive Water Heaters 16 $288 54 $124
Res –Battery DLC 210 $62 210 $62
C&I –Battery DLC 92 $61 92 $61
C&I – Grid Interactive Water Heaters 7 $201 12 $140
C&I – HVAC DLC 4 $313 9 $355
C&I – Pool Pump DLC 0 $247 0 $225
C&I – Smart Thermostats 9 $50 5 $177
C&I – Water Heater DLC 1 $92 1 $65
C&I – Third Party 146 $217 117 $304
Ag – Irrigation DLC 13 $65 0 $0
Average levelized cost weighted by the 20-year cumulative potential in each state
Energy Efficiency DSM, Energy Supply Curves
The 2021 CPA provided the information to fully assess the potential contribution from DSM
energy efficiency resources over the IRP planning horizon. The CPA analysis accounts for known
changes in building codes, advancing equipment efficiency standards, market transformation,
resource cost changes, changes in building characteristics and state-specific resource evaluation
considerations (e.g., cost-effectiveness criteria).
DSM energy efficiency resource potential was assessed by state down to the individual measure
and building levels (e.g., specific appliances, motors, lighting configurations for residential
buildings, and small offices). The CPA provided DSM energy efficiency resource information at
the following granularity:
• State: Washington, California, Idaho, Utah, Wyoming12
• Measure:
– 98 residential measures
– 138 commercial measures
– 96 industrial measures
– 25 irrigation measures
11 Demand response resources derived from the demand response RFP are not included to protect confidential 3rd
party pricing information.
12 Oregon’s DSM potential was assessed in a separate study commissioned by the Energy Trust of Oregon.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
210
• Facility type:13
– Six residential facility types
– 28 commercial facility types
– 34 industrial facility types
– Two irrigation facility type
The 2021 CPA levelized total resource costs over the study period at PacifiCorp’s cost of capital,
consistent with the treatment of supply-side resources. Costs include measure costs and a state-
specific adder for program administrative costs for all states except Utah and Idaho. Consistent
with regulatory mandates, Utah and Idaho DSM energy efficiency resource costs were levelized
using utility costs instead of total resource costs (i.e. incentive and a state specific adder for
program administration costs).
The technical potential for all DSM energy efficiency resources across all states except Oregon
over the twenty-year CPA planning horizon totaled 15.1 million MWh.14 The technical potential
represents the total universe of possible savings before adjustments for what is likely to be realized
(i.e. technical achievable potential). When the achievable assumptions described below are
considered the technical potential is reduced to a technical achievable potential for modeling
consideration of 10.8 million MWh for all five states. The technical achievable potential for all six
states for modeling consideration is 13.8 million MWh. The technical achievable potential,
representing available potential at all costs, is provided to the IRP model for economic screening
relative to supply-side alternatives.
Despite the granularity of DSM energy efficiency resource information available, it was
impractical to model the resource supply curves at this level of detail. The combination of measures
by building type and state generated almost 30,000 separate permutations or distinct measures that
could be modeled using the supply curve methodology. To reduce the resource options for
consideration without losing the overall resource quantity available or its relative cost, resources
were consolidated into bundles, using ranges of levelized costs and net cost of capacity to reduce
the number of combinations to a more manageable number.
Bundle development began with the energy efficiency technical potential identified by the 2021
CPA. To account for the practical limits associated with acquiring all available resources in any
given year, the technical potential by measure was adjusted to reflect the amount that is realistically
achievable over the 20-year planning horizon. Consistent with the Northwest Power and
Conservation Council’s achievability assumptions in the Draft 2021 Power Plan as, which
typically assume that 85% of the technical potential could be acquired over the 20-year period.15
13 Facility type includes such attributes as existing or new construction, single or multi-family. Facility types represent
a combination of market segment and vintage and are more fully described in in the Analysis Approach in Volume 1,
Chapter 2, of the2021 CPA.
14 The identified technical potential represents the cumulative impact of DSM measure installations in the 20th year of
the study period for California, Idaho, Washington, Wyoming, and Utah. This may differ from the sum of individual
years’ incremental impacts due to the introduction of improved codes and standards over the study period. ETO
provides PacifiCorp with technical achievable potential.
15 The Northwest’s achievability assumptions include savings realized through improved codes and standards and
market transformation, and thus, applying them to identified technical potential represents an aggressive view of
what could be achieved through utility DSM programs.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
211
For Oregon, the company does not assess potential for the Energy Trust of Oregon (ETO). Neither
PacifiCorp nor the ETO performed an economic screening of measures in the development of the
DSM energy efficiency supply curves used in the development of the 2021 IRP, allowing resource
opportunities to be economically screened against supply-side alternatives in a consistent manner
across PacifiCorp’s six states.
Twenty-seven cost bundles were available across six states (including Oregon), which equates to
189 DSM energy efficiency resource supply curves. Table 7.9 shows the 20-year MWh potential
for DSM energy efficiency levelized cost bundles, designated by ranges of $/MWh.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
212
Table 7.9 – 20-Year Total Incremental Energy Efficiency Potential by Cost Bundle (MWh)
Bundle California Idaho Oregon Utah Washington Wyoming
Annual Measures 1
(Best) 14,907 117,483 663,976 3,046,586 257,744 953,035
Annual Measures 2 4,243 44,907 505,973 433,935 48,147 111,397
Annual Measures 3 -
Weather 1,719 24,887 52,257 119,916 30,747 17,654
Annual Measures 3 -
Non-Weather 536 15,254 72,949 60,729 7,632 18,527
Annual Measures 4 -
Weather 8,277 17,602 - 292,054 52,506 20,573
Annual Measures 4 -
Non-Weather 1,342 3,696 54,515 69,006 10,602 11,610
Annual Measures 5 -
Weather 3,011 22,106 22,753 42,323 26,355 4,037
Annual Measures 5 -
Non-Weather 2,199 5,247 82,199 32,067 16,103 7,847
Annual Measures 6 -
Weather 1,009 10,212 - 258,334 16,538 10,418
Annual Measures 6 -
Non-Weather 141 1,251 18,600 37,860 57,595 20,163
Summer Measures 7
- Weather 2,894 16,837 121,477 150,336 26,229 8,448
Summer Measures 7
- Non-Weather 255 3,401 64,074 11,160 3,073 7,642
Summer Measures 8
- Weather 7,927 18,140 22,924 256,041 37,761 10,953
Summer Measures 8
- Non-Weather 2,519 5,038 120,418 98,283 11,727 24,612
Summer Measures 9
- Weather 10,299 11,455 6,642 267,252 31,988 8,213
Summer Measures 9
- Non-Weather 3,025 2,590 25,851 24,055 21,127 17,602
Summer Measures
10 - Weather 6,237 11,849 48,133 185,206 37,902 9,705
Summer Measures
10 - Non-Weather 796 1,013 35,465 57,507 10,818 12,551
Summer Measures
11 - Weather 7,184 9,700 12,889 237,866 26,380 12,295
Summer Measures
11 - Non-Weather 1,967 9,487 12,737 173,013 59,880 43,670
Highest Cost
Measures 76,185 162,172 270,159 1,196,598 320,867 279,849
Winter Measures 6 3,170 12,130 166,645 96,308 16,389 6,885
Winter Measures 5 4,291 2,895 215,250 111,172 21,021 24,665
Winter Measures 4 15,298 2,583 195,188 35,337 7,507 7,734
Winter Measures 3 550 5,466 79,514 77,771 5,149 15,857
Winter Measures 2 105 7,864 106,755 45,286 6,320 19,939
Winter Measures 1
(Best) - 3,215 33,265 34,164 406 5,647
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
213
Cost credits afforded to DSM energy efficiency resources include the following:
• A state-specific transmission and distribution investment deferral cost credit (Table 7.10)
• Stochastic risk reduction credit of $3.59/MWh16
• Northwest Power Act 10-percent credit (Oregon and Washington resources only)17
Table 7.10 – State-specific Transmission and Distribution Credits
State
Transmission
Deferral Value
($/KW-year)
Distribution
Deferral Value
($/KW-year)
Total
California $6.34 $11.06 $17.40
Oregon $6.34 $13.38 $19.72
Washington $6.34 $16.86 $23.20
Idaho $6.34 $16.72 $23.06
Utah $6.34 $13.20 $19.54
Wyoming $6.34 $7.48 $13.82
The bundle is split by weather dependent and non-weather dependent measures and their net cost
of capacity ($/kw-yr) cost for the group of measures in the cost bins. In specifying the bundle cost
breakpoints, narrow cost ranges were defined for the lower-cost resources to ensure cost accuracy
for the bundles considered more likely to be selected during the resource selection phase of the
IRP.
PacifiCorp relies on simulated load shapes tied to weather stations in PacifiCorp’s service territory.
Weather is a major driver of PacifiCorp’s load and in any given month weather results in a range
of high and low load conditions. Weather also impacts the hourly timing of energy efficiency
savings particularly for measures that are weather dependent. For the 2021 IRP, PacifiCorp chose
to reshape daily energy efficiency volumes to better align with seasonal variations in the load
forecast. The highest demand for weather-sensitive end use loads is expected to occur at the time
of the winter and summer peaks in PacifiCorp’s service territory. For weather dependent measures,
the highest daily simulated savings were mapped to the highest to lowest load days to align with
the load forecast. To capture the time-varying impacts of energy efficiency resources, each bundle
uses an annual 8,760 hourly load shape specifying the portion of the maximum capacity available
in any hour of the year. These shapes are created by spreading measure-level annual energy savings
over 8,760 load shapes, differentiated by state, sector, market segment, and end use accounting for
the hourly variance of energy efficiency impacts by measure. These hourly impacts are then
aggregated for all measures in a given bundle to create a single weighted average load shape for
that bundle.
16 PacifiCorp developed this credit from two sets of production dispatch simulations of a given resource portfolio, and
each set has two runs with and without DSM. One simulation is on deterministic basis and another on stochastic basis.
Differences in production costs between the two sets of simulations determine the dollar per MWh stochastic risk
reduction credit.
17 The formula for calculating the $/MWh Power Act credit is: (Bundle price - ((First year MWh savings x market
value x 10%) + (First year MWh savings x T&D deferral x 10%))/First year MWh savings. The levelized forward
electricity price for the Mid-Columbia market is used as the proxy market value.
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
214
Distribution Efficiency
PacifiCorp continues to develop its CYME CYMDIST® (power flow software) investment in
ways that improve engineering response time and, indirectly, distribution system efficiency. In the
last biennial period, more than 300 large (Level 2 and Level 3) distributed energy resource (DER)
applications were studied in CYME. This resulted in more than 29 MW (nameplate) of approved
private generation across the company. Any energy savings resulting from these approvals across
the service territory has not been determined.
This distribution energy efficiency activities were not modeled as potential resources in this
IRP.
Transmission Resources
In developing resource portfolios for the 2021 IRP, PacifiCorp included modeling to endogenously
select transmission options, in consideration of relevant costs and benefits. These costs are
influenced by the type, timing, location, and amount of new resources as well as any assumed
resource retirements, as applicable, in any given portfolio. Additional information can be found in
Volume I, Chapter 8 (Modeling and Portfolio Evaluation Approach).
Market Purchases
PacifiCorp and other utilities engage in purchases and sales of electricity on an ongoing basis to
balance the system and maximize the economic efficiency of power system operations. In addition
to reflecting spot market purchase activity and existing long-term purchase contracts in the IRP
portfolio analysis, PacifiCorp modeled front office transactions (FOT). FOTs are proxy resources,
assumed to be firm, that represent procurement activity made on an on-going forward basis to help
the company cover short positions.
As proxy resources, FOTs represent a range of purchase transaction types. They are usually
standard products, such as heavy load hour (HLH), light load hour (LLH), and super peak (hours
ending 13 through 20) and typically rely on standard enabling agreements as a contracting vehicle.
FOT prices are determined at the time of the transaction, usually via an exchange or third-party
broker, and are based on the then-current forward market price for power. An optimal mix of these
purchases would include a range of volumes and terms for these transactions.
Solicitations for FOTs can be made years, quarters or months in advance, however, most
transactions made to balance PacifiCorp’s system are made on a balance of month, day-ahead,
hour-ahead, or intra-hour basis. Annual transactions can be available three or more years in
advance. Seasonal transactions are typically delivered during quarters and can be available from
one to three years or more in advance. The terms, points of delivery, and products will all vary by
individual market point.
Three FOT types were included for portfolio analysis in the 2021 IRP: an annual flat product, a
HLH July for summer, and a HLH December for winter product. An annual flat product reflects
energy provided to PacifiCorp at a constant delivery rate over all the hours of a year. The HLH
transactions represent purchases received 16 hours per day, six days per week for July and
December. Table 7.11 shows the FOT resources included in the IRP models, identifying the market
hub, product type, annual megawatt capacity limit, and availability. PacifiCorp develops its FOT
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
215
limits based upon its active participation in wholesale power markets, its view of physical delivery
constraints, market liquidity and market depth, and with consideration of regional resource supply
(see Volume I, Chapter 5 for an assessment of western resource adequacy). Prices for FOT
purchases are associated with specific market hubs and are set to the relevant forward market
prices, time period, and location, plus appropriate wheeling charges, as applicable. Additional
discussion of how FOTs are modeled during the resource portfolio development process of the
IRP is included in Volume I, Chapter 8 (Modeling and Portfolio Evaluation Approach).
Table 7.11 - Maximum Available Front Office Transaction Quantity by Market Hub
Market Hub/Proxy FOT Product Type
Available over Study Period
Megawatt Limit and Availability
(MW)
Summer
(July)
Winter
(December)
Mid-Columbia (Mid-C)
350 350 Flat Annual ("7x24") or
Heavy Load Hour ("6X16")
Heavy Load Hour ("6X16") 150 0
California Oregon Border (COB)
Flat Annual ("7x24") or 0 250
Heavy Load Hour ("6X16")
Nevada Oregon Border (NOB) 0 100 Heavy Load Hour ("6X16")
Mona 0 300 Heavy Load Hour ("6X16")
PACIFICORP – 2021 IRP CHAPTER 7 – RESOURCE OPTIONS
216
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
217
CHAPTER 8 – MODELING AND PORTFOLIO
EVALUATION APPROACH
CHAPTER HIGHLIGHTS
• The Integrated Resource Plan (IRP) modeling approach is used to assess the comparative cost,
risk, and reliability attributes of resource portfolios.
• PacifiCorp used the Plexos Long-Term planning model (LT model) to produce unique resource
portfolios across a range of different planning cases. Informed by the public-input process,
PacifiCorp identified case assumptions that were used to produce optimized resource
portfolios, each one unique regarding the type, timing, location, and amount of new resources
that could be pursued to serve customers over the next 20 years.
• PacifiCorp used the Plexos Medium-Term schedule (MT model) to perform stochastic risk
analysis of the portfolios. Each portfolio was evaluated for cost and risk among three natural
gas price scenarios (low, medium, and high) and three carbon dioxide (CO2) price scenarios
(zero, medium, high). An additional CO2 policy scenario was developed to evaluate
performance assuming a price signal that aligns with the social cost of greenhouse gases (SC-
GHG). Taken together, there are five distinct price-policy scenarios (medium gas/medium
CO2, medium gas/zero CO2, high gas/high CO2, low gas/zero CO2, and the social cost of
greenhouse gases).
• A primary function of the MT model is to calculate an optimized risk-adjustment, representing
the relative risk of a portfolio under unfavorable stochastic conditions for that portfolio.
• Each portfolio was evaluated in the Short-Term model (ST model) to establish system costs
for each portfolio over the entire 20-year planning period. The ST model accounts for resource
availability and system requirements at an hourly level, producing reliability and resource
value outcomes as well as a present-value revenue requirement (PVRR) which serves as the
basis for selecting least-cost least-risk portfolios.
• The MT model risk-adjustment was added to the system cost determined by the ST model to
calculate a final “risk-adjusted” PVRR measure of system cost.
• A selection of portfolios were analyzed using the other four price-policy scenarios in the ST
and MT models to evaluate how each portfolio performs under differing market/policy
conditions.
• Taking into consideration stakeholder comments and regulatory requirements, PacifiCorp
produced additional studies that examine the potential impact of portfolio options on the
system.
• Informed by comprehensive modeling, PacifiCorp’s preferred portfolio selection process
involves evaluating cost and risk metrics reported from the ST and MT models, comparing
resource portfolios based on expected costs, low-probability high-cost outcomes, reliability,
CO2 emissions and other criteria.
Introduction
IRP modeling is used to assess the comparative cost, risk, and reliability attributes of different
resource portfolios, each meeting reliability requirements. These portfolio attributes form the basis
of an overall quantitative portfolio performance evaluation.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
218
The first section of this chapter describes the screening and evaluation processes for portfolio
selection. Following sections summarize portfolio risk analyses, document key modeling
assumptions, and describe how this information is used to select the preferred portfolio. The last
section of this chapter describes the cases examined at each modeling and evaluation step. The
results of PacifiCorp’s modeling and portfolio analysis are summarized in Volume I, Chapter 9 –
Modeling and Portfolio Selection Results.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
219
Modeling and Evaluation Steps
Figure 8.1 summarizes the modeling and evaluation steps for the 2021 IRP, highlighted in green.
The steps are (1) portfolio development, and (2) portfolio screening. The result of the final
screening step is selection of the preferred portfolio.
Figure 8.1 – Portfolio Evaluation Steps within the IRP Process
For each modeling and evaluation step, PacifiCorp developed unique resource portfolios, analyzed
deterministic cost and stochastic risk metrics for each portfolio, and selected, based on comparative
cost and risk metrics, the specific portfolios considered in the next modeling and evaluation step.
The outcomes of each can inform the need for additional studies to test or refine assumptions in a
subsequent screening analysis.
Action Plan
Portfolio
Development
Candidate
Portfolios
Preferred
Portfolio
Preferred Portfolio
Selection
Resource Portfolio
Development (LT)
Reliability
Assessment (MT, ST)
Including loads, prices, supply-side resources,
fuel costs, granularity adjustment, and reliability
adjustment, etc.
Key Planning
Assumptions and
Uncertainties
Cost and Risk
Analysis (ST, MT)
Portfolio Selection
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
220
Figure 8.2 provides additional process detail regarding these portfolio processing elements,
followed by descriptions of each element.
Figure 8.2 – Portfolio Production Process
Resource Portfolio Development
All IRP models are configured and loaded with the best available information at the time a model
run is produced. This information is fed into the LT model, which is used to produce resource
portfolios with sufficient capacity to be reliable on a 20-year aggregated granularity basis.
Reliability Assessment
Resource portfolios developed by the LT model are simulated in the ST model to quantify
reliability shortfalls at an hourly level. The ST model also supports the assessment of each
resource’s net system value, inclusive of resources that are not part of the specific portfolio being
examined. This allows for the refinement of each portfolio according to a highly granular view of
its needs and at the same time provides the data necessary to optimally select additional resources
when needed to resolve shortfalls. The reliability-adjusted portfolio is then rerun through the ST
model to create an optimal dispatch which considers all resource availability and system
requirements at an hourly level, inclusive of individual resource operations and market purchases.
Cost and Risk Analysis
Resource portfolios developed by the LT model and adjusted for reliability by the ST model are
simulated in the MT model to produce metrics that support comparative cost and risk analysis
among the different resource portfolio alternatives. Stochastic risk modeling of resource portfolio
alternatives is performed using Monte Carlo sampling of stochastic variables across the 20-year
study horizon, which include load, natural gas and wholesale electricity prices, hydro generation,
and unplanned thermal outages. The MT results are used to calculate a risk adjustment which is
combined with ST model system costs to achieve a final risk-adjusted PVRR to guide portfolio
selection.
Portfolio Selection
The portfolio selection process is based on modeling results from the resource portfolio
development and cost and risk analysis steps. The screening criteria are based on the PVRR of
system costs, assessed across a range of price-policy scenarios on a deterministic basis and on an
upper-tail stochastic risk basis. Portfolios are ranked using a risk-adjusted PVRR metric, a metric
that combines the deterministic PVRR with upper-tail stochastic risk PVRR. The final selection
process considers cost-risk rankings, robustness of performance across pricing scenarios and other
Reliability Assessment
LT Expansion
Plan Assess
Reliability
MT Stochastics
Calculate Shortfalls
and Resource Value
Optimize Final Portfolio
Optimize
System
(ST Model)
Set Spanning
conditions
(MT Model)
Optimize
System
(ST Model)
Set Spanning
conditions
(MT Model)
Risk-adjusted
PVRR
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
221
supplemental modeling results, including reliability and CO2 emissions data as an indicator of risks
associated with greenhouse gas emissions.
Resource Portfolio Development
Resource expansion plan modeling, performed with the LT model, is used to produce resource
portfolios with sufficient capacity to achieve reliability over the 20-year study horizon. Each
resource portfolio is refined for reliability at an hourly granularity during the reliability assessment
development step. Each subsequent portfolio is uniquely characterized by the type, timing,
location, and amount of new resources in PacifiCorp’s system over time. These resource portfolios
reflect a combination of planning assumptions such as resource retirements, CO2 prices, wholesale
power and natural gas prices, load growth net of assumed private generation penetration levels,
cost and performance attributes of potential transmission upgrades, and new and existing resource
cost and performance data, including assumptions for new supply-side resources and incremental
demand-side management (DSM) resources. Changes to these input variables cause changes to the
resource mix, which influences system costs and risks. New to this IRP is using the LT model to
consider the retirement of coal endogenously.
Long-Term (LT) Capacity Expansion Model
In the 2021 IRP, the LT model is used to establish an initial portfolio under expected conditions
(medium gas, medium CO2), and then modified for each case, based on study parameters, to
eliminate shortfalls and maintain reliability. The LT model operates by minimizing operating costs
for existing and prospective new resources, subject to system load balance, reliability, and other
constraints.1 Over the 20-year planning horizon, the model optimizes resource additions subject to
resource costs and load constraints. These constraints include seasonal loads, operating reserves
and regulation reserves plus a minimum capacity reserve margin for each load area represented in
the model.
The initial resource portfolio developed with the LT model is appropriately reliable to its
granularity and performance limitations. Operating reserve requirements include contingency
reserves, which are calculated as 3% of load and 3% of generation. The capacity reserve margin
in the 2021 IRP is set at a “floor” of 13% at each load area in the topology, as provided in Figure
8.3.
In the event that an early retirement of an existing generating resource is assumed or selected for
a given planning scenario, the LT model will select additional resources as required to meet loads
plus reliability requirement in each period and location.
To accomplish these optimization objectives, the LT model performs a least-cost dispatch for
existing and potential planned generation, while considering cost and performance of existing
contracts and new DSM alternatives within PacifiCorp’s transmission system. Resource dispatch
is based on representative data blocks for each of the 12 months of every year. Dispatch also
determines optimal electricity flows between zones and includes spot market transactions for
system balancing. The model minimizes the system PVRR, which includes the net present value
1 LT model performance limits the granularity at which the model can be run. For the 2021 IRP there is an
additional reliability assessment performed in the ST model to ensure that final portfolios meet reliability
requirements.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
222
cost of existing contracts, market purchase costs, market sale revenues, generation costs (fuel,
fixed and variable operation and maintenance, decommissioning, emissions, unserved energy, and
unmet capacity), costs of DSM resources, amortized capital costs for existing coal resources and
potential new resources, and costs for potential transmission upgrades.
Key modeling elements and inputs for the LT capacity expansion model include the following:
Transmission System
PacifiCorp uses a transmission topology that captures major load centers, generation resources,
and market hubs interconnected via firm transmission paths. Transfer capabilities across
transmission paths are based upon the firm transmission rights of PacifiCorp’s merchant function,
including transmission rights from PacifiCorp’s transmission function and other regional
transmission providers.
Figure 8.3 – Transmission System Model Topology
Transmission Costs
In developing resource portfolios for the 2021 IRP, PacifiCorp included modeling to endogenously
select transmission options, in consideration of relevant costs and benefits. These costs are
influenced by the type, timing, location, and amount of new resources as well as any assumed
resource retirements, as applicable, in any given portfolio.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
223
Resource Adequacy
In its 2021 IRP, PacifiCorp used the Plexos capacity reserve margin (CRM) setting in the LT
model to establish a minimum 13% requirement for each topology location containing load. The
capacity reserve margin applies in all periods and must be met by available resources within that
area or imports from adjacent areas with excess resources available, subject to transmission
constraints. This treatment is an improvement on a traditional planning reserve margin which
accounts only for peak load capacity met by an estimated firm capacity contribution. Additionally,
the 2021 IRP directly modeled operating reserve requirements in expansion plan model runs,
which ensures that expansion resources selected to CRM requirements will also meet operating
contingency spin and non-spin reserve requirements. Taken together, these reliability requirements
ensure that PacifiCorp has sufficient resources to meet load in all periods, recognizing the
uncertainty for load fluctuation and extreme weather conditions, fluctuation of variable generation
resources, a possibility for unplanned resource outages, and reliability requirements to carry
sufficient contingency and regulating reserves.
Granularity and Reliability Adjustments
As detailed during the 2021 IRP public-input process, the granularity adjustment reflects the
difference in economic value between an hourly 8760 cost calculation in ST modeling, and the
four-block per month representation used in the LT model.
This adjustment is needed because resources with high variable costs that are rarely dispatched
may provide a large value in a few intervals in the ST study, while not dispatching in any of the 4
LT model blocks. Also, storage resources allow for arbitrage among high value and low value
hours in each day; however, the four-block granularity smooths out many of the storage arbitrage
opportunities.
In parallel with the granularity adjustment, the reliability adjustment addresses unmet capacity
needs by hour in the LT model portfolio selection. Much of the peak load hour requirements in
mid-afternoon in the summer are adequately met by solar resources. However, resource
requirements are driven by portfolio-dependent net load peaks (load less renewable resource
output), which are harder for the LT model to identify.
While the granularity and reliability adjustments help direct the LT model to more cost-effective
resources and a more reliable portfolio, the LT model cannot guarantee reliability at an hourly
operational level. Marginal benefits decline as any resource type becomes a larger share of a
portfolio, as it saturates the need in the hours it is available. A similar effect occurs with storage,
where each incremental MW of system storage capacity must cover a longer duration.
As a consequence of the performance limitations of capacity expansion optimization, the ST model
is leveraged to refine the portfolio to achieve a final balanced and reliable mix of resources, as
described under the Cost and Risk Analysis section of this analysis, further below.
New Resource Options
Demand-Side Management
Energy efficiency (Class 2 DSM) resources are characterized with supply curves that represent
achievable technical potential of the resource by state, by year, and by measures specific to
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
224
PacifiCorp’s service territory. For modeling purposes, these data are aggregated into cost bundles.
Each cost bundle of the energy efficiency supply curves specifies the aggregate energy savings
profile of all measures included within the cost bundle. Each cost bundle has both a summer and
winter capacity contribution based on aggregate energy savings during on-peak hours in July and
December aligning with periods where PacifiCorp is most likely to exhibit capacity shortfalls.
Demand response (Class 1 DSM) resources, representing direct load control capacity resources,
are also characterized with supply curves representing achievable technical potential by state and
by year for specific direct load control program categories (i.e., air conditioning, irrigation, and
commercial curtailment). Operating characteristics include variables such as total number of hours
per year and hours per event that the demand response resource is available.
Wind and Solar Resources
Certain wind and solar resources are dispatchable by the model up to fixed energy profiles that
vary by day and month. The fixed energy profiles for wind and solar resources represent expected
monthly generation levels such that half of the time actual monthly generation would fall below
expected levels, and half of the time actual monthly generation would be above expected levels
assuming no curtailments.
The ability for wind and solar resources, to reliably meet demand over time is impacted by the
forecasted profiles, along with mix of other resources in the portfolio. The use of resource
availability to meet requirements in all periods allows the model to endogenously account for
declining capacity contribution due to the increasing penetration of resources with similar dispatch
patterns.
Non-Emitting Resources
Two non-CO2-emitting thermal resources are considered: advanced nuclear projects and non-
emitting peaking units. Advanced nuclear resources are characterized by continuous operation and
substantial storage in the form of heat stored as molten salt. In contrast, non-emitting peaking
resources are designed to run infrequently to support system reliability by dispatching only when
needed to meet shortfalls. The non-emitting peaking resource is assumed to use a non-CO2 emitting
fuel such as hydrogen.
Energy Storage Resources
Energy storage resources are distinguished from other resources by the following three attributes:
• Energy take – generation or extraction of energy from a storage reservoir for a specified
period;
• Energy return – energy used to fill (or charge) a storage reservoir; and
• Storage cycle efficiency – an indicator of the energy loss involved in storing and extracting
energy over the course of the take-return cycle.
Modeling energy storage resources requires specification of the size of the storage reservoir,
defined in gigawatt-hours. The model dispatches a storage resource to optimize energy used by the
resource subject to constraints such as storage-cycle efficiency, the daily balance of take and return
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
225
energy, and variable costs (for example, the cost of natural gas for expanding air with gas turbine
expanders).
Market Purchases
Market purchases are transactions by the company’s front office represent short-term firm
agreements for physical delivery of power. PacifiCorp is active in the western wholesale power
markets and routinely makes short-term firm market purchases for physical deliveries on a forward
basis (i.e., future months or quarters, balance of month, day-ahead, and hour-ahead). These
transactions are used to balance PacifiCorp’s system as market and system conditions become
more certain when the time between an effective transaction date and real time delivery is reduced.
Balance of month and day-ahead physical firm market purchases are most routinely acquired
through a broker or an exchange, such as the Intercontinental Exchange (ICE). Hour-ahead
transactions can also be made through an exchange. For these types of transactions, the broker or
the exchange provides a competitive price. Non-brokered transactions can also be used to make
firm market purchases among a wide range of forward delivery periods.
From a modeling perspective, it is not feasible to incorporate all of the short-term firm physical
power products, which differ by delivery pattern and delivery period, that are available through
brokers, exchanges, and non-brokered transactions. However, considering that PacifiCorp
routinely uses these types of firm transactions, which obligate the seller to back the transaction
with reserves when balancing its system, it is important that the contribution of short-term firm
market purchases is accounted for in the portfolio-development process. For capacity expansion
optimization modeling, market purchases contribute capacity toward meeting the 2021 IRP’s
capacity reserve margin and supply energy to meet system needs.
Capital Costs
Annual capital recovery factors are used to convert capital investment dollars into nominal
levelized revenue requirement costs. All capital costs evaluated in the IRP are converted to
nominal levelized revenue requirement costs. Use of nominal levelized revenue requirement costs
is an established methodology for analyzing capital-intensive resource decisions among resource
alternatives that have unequal lives and/or when it is not feasible to capture operating costs and
benefits over the entire life of any given resource. To achieve this, the nominal levelized revenue
requirement method spreads the return of investment (book depreciation), return on investment
(equity and debt), property taxes and income taxes over the life of the investment. The result is an
annuity or annual payment that remains constant such that the PVRR is identical to the PVRR of
the nominal requirement when using the same nominal discount rate.
General Assumptions
Study Period and Date Conventions
PacifiCorp executes its 2021 IRP models for a 20-year period beginning January 1, 2021 and
ending December 31, 2040. Future IRP resources reflected in model simulations are given an in-
service date of January 1st of a given year, except for coal unit natural gas conversions, which are
given an in-service date of June 1st of a given year, recognizing the desired need for these
alternatives to be available during the summer peak load period.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
226
Inflation Rates
The 2029 IRP simulations and cost data reflect PacifiCorp’s corporate inflation rate schedule
unless otherwise noted. A single annual escalation rate value of 2.155 percent is assumed. This
escalation rate reflects the average of annual inflation rate projections for the period 2021 through
2040, using PacifiCorp’s September 2020 inflation curve. PacifiCorp’s inflation curve is a straight
average of forecasts for the Gross Domestic Product inflator and the Consumer Price Index.
Discount Factor
The discount rate used in present-value calculations is based on PacifiCorp’s after-tax weighted
average cost of capital (WACC). The value used for the 2021 IRP is 6.88 percent. The use of the
after-tax WACC complies with the Public Utility Commission of Oregon’s IRP guideline 1a,
which requires that the after-tax WACC be used to discount all future resource costs.2 PVRR
figures reported in the 2021 IRP are reported in 2021 dollars.
CO2 Price Scenarios
PacifiCorp used four different CO2 price scenarios in the 2021 IRP—zero, medium, high, and a
price forecast that aligns with the social cost of greenhouse gases. The medium and high scenario
are derived from expert third-party multi-client “off-the-shelf” subscription services. Both
scenarios apply a CO2 price as a tax beginning 2025.
PacifiCorp also incorporated the social cost of greenhouse gas in compliance with RCW
19.280.030. Social cost of greenhouse gas emissions are assumed to start in 2021. The social cost
of greenhouse gases is applied such that the price for the SC-GHG is reflected in market prices
and dispatch costs for the purposes of developing each portfolio (i.e., incorporated into capacity
expansion optimization modeling). Aligned with Washington staff suggested treatment, system
operations also include the SC-GHG once the portfolios are determined, presenting the risk that
this operational assumption will not be aligned with actual market forces (i.e., market transactions
at the Mid-Columbia market do not reflect the social cost of greenhouse gases and PacifiCorp does
not directly incur emission costs at the price assumed for the social cost of greenhouse gases).
2 Public Utility Commission of Oregon, Order No. 07-002, Docket No. UM 1056, January 8, 2007.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
227
Figure 8.4 – CO2 Prices Modeled by Price-Policy Scenarios
Wholesale Electricity and Natural Gas Forward Prices
For 2021 IRP modeling purposes, five electricity price forecasts were used: the official forward
price curve (OFPC) and four scenarios. Unlike scenarios, which are alternative spot price forecasts,
the OFPC represents PacifiCorp’s official quarterly outlook. The OFPC is compiled using market
forwards, followed by a market-to-fundamentals blending period that transitions to a pure
fundamentals-based forecast.
At the time PacifiCorp’s 2021 IRP modeling inputs were prepared, the March 2021 OFPC was the
most current OFPC available. For both gas and electricity, starting with the prompt month, the
front 36 months of the OFPC reflects market forwards at the close of a given trading day.3 As such,
these 36 months are market forwards as of March 2021. The blending period (months 37 through
48) is calculated by averaging the month-on-month market forward from the prior year with the
month-on-month fundamentals-based price from the subsequent year. The fundamentals portion
of the natural gas OFPC reflects an expert third-party multi-client “off-the-shelf” price forecast.
The fundamentals portion of the electricity OFPC reflects prices as forecast by AURORAXMP4
(Aurora), a WECC-wide market model. Aurora uses the expert third-party natural gas price
forecast to produce a consistent electricity price forecast for market hubs in which PacifiCorp
participates. PacifiCorp updates its natural gas price forecasts each quarter for the OFPC and, as a
corollary, the electricity OFPC is also updated.
3 The March 2021 OFPC prompt month is May 2021; April 2021 would be traded as “balance of month” when the
OFPC is released.
4 AURORAXMP is a proprietary production cost simulation model, developed by Energy Exemplar, LLC.
$0$10$20$30$40$50$60$70$80$90$100$110$120$130$140$150$160
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Medium High Societal Cost
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
228
Scenarios pairing medium gas prices with alternative CO2 price assumptions reflect OFPC
forwards through April 2024 before transitioning to a pure fundamentals forecast. Scenarios using
high or low gas prices, regardless of CO2 price assumptions, do not incorporate any market
forwards since scenarios are designed to reflect an alternative view to that of the market. As such,
the low and high natural gas price scenarios are purely fundamental forecasts. Low and high natural
gas price scenarios are also derived from expert third-party multi-client “off-the-shelf”
subscription services.
PacifiCorp’s OFPC for electricity and each of its five scenarios were developed from one of three
(medium, low, high) underlying expert third-party natural gas price forecasts in conjunction with
one of four CO2 price scenarios.5 The OFPC used in the 2021 IRP does not assume any CO2 policy
or tax in conjunction with its medium gas price forecast. However, PacifiCorp’s 2021 IRP
“medium case” price forecast is not the OFPC but a scenario that couples medium gas with a
medium CO2 price, applied for forecasting purposes as a tax. Thus, the 2021 IRP medium case
differs from that of the March 2021 OFPC by assuming a medium CO2 price starting in 2025. This
medium CO2 price serves as a proxy for a potential future CO2 policy.
Figure 8.5 summarizes the five wholesale electricity price forecasts and three natural gas price
forecasts used in the base and scenario cases for the 2021 IRP.
Figure 8.5 – Nominal Wholesale Electricity and Natural Gas Price Scenarios
Cost and Risk Analysis
Short-Term (ST) Schedule Model
The ST model uses the same common input assumptions described for the LT model with
additional data provided by two other Plexos models. The LT model results provide the initial
capacity expansion plan, and the MT model provides an optimized set of spanning conditions.
Spanning conditions are constraints that must be observed across periods of time that extend
beyond the ST model’s ability to “see” as it chronologically optimizes several days of hourly data
at a time (e.g., an annual emissions limit). The MT model is able to determine for each month how
each spanning condition is allocated for the ST model’s use. The result is that even though the ST
5Zero CO2, medium CO2 price, high CO2 price, and a social based cost of CO2.
$-
$1
$2
$3
$4
$5
$6
$7
$8
$9
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
$/
M
M
B
t
u
Natural Gas Prices
Henry Hub
Medium Low High
$-
$20
$40
$60
$80
$100
$120
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
$/
M
W
h
Wholesale Electricity Prices
Average of Palo Verde and Mid-C (Flat)
Mgas_0CO2 Mgas_MCO2 Hgas_HCO2
Lgas_0CO2 Mgas_SCO2
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
229
model is focused on hourly details and cannot simultaneously account for limitations that span
across every hour in a year, the model will nonetheless appropriately adhere to an annual
constraint.
Reliability Assessment and System Cost
The ST model begins with an portfolio from the LT model that has not yet been refined to reflect
the reliability needs of a particular study (e.g., a particular sensitivity or price-policy scenario).
The ST model is first run at an hourly level for 20 years in order to retrieve two critical pieces of
data: 1) shortfalls by hour, and 2) the value of every potential resource to the system.
This information is used to determine the most cost-effective resource additions needed to meet
reliability shortfalls, leading to a reliability-modified portfolio. The ST model is then run again
with the modified portfolio to calculate an initial PVRR which is risk-adjust by outcomes of MT
model stochastics.
Resource Value
Plexos calculates a locational marginal price (LMP) specific to each area in each hour that is based
on supply and demand in that area and available imports and exports on transmission links to
adjacent areas. This is also known as a shadow price. Plexos also calculates the marginal price
specific to ancillary services (i.e., operating reserves) in each hour. Plexos then multiplies these
prices by a generator’s energy and operating reserve provision for each hour and reports the total
as a resource’s estimated revenue. In an organized market, this would represent the expected
payments based on market-clearing prices.
When variable costs (such as fuel, emissions, and VOM) are subtracted out, the result is a
resource’s “net revenue”. Net revenue provides a clear model-optimized assessment of every
resource’s value to the system, which is then used to assess resource additions needed to preserve
reliable operation of the system.
While the net revenue approach is demonstrably superior to past resource value measures,
especially as it is evaluated simultaneously for all potential resources, modeling capabilities, net
revenue has limitations that should be acknowledged. Net revenue represents the value of the last
MW of capacity from a given resource – as resources grow larger, the average value from the first
MW of capacity to the last MW of capacity will tend to be somewhat higher than the reported
marginal value. Conversely, adding more of a particular resource will result in declining values.
While marginal prices will be very high in hours with supply shortfalls, this only indirectly
contributes to reliable operation by helping to identify beneficial replacement resources. Once
sufficient resources are added, shortfalls will mostly be eliminated and marginal prices will again
reflect the variable cost of an available resource.
Portfolio Refinements
While a large number of resource options are evaluated, new generation resources are mostly
restricted to two circumstances: replacement resources at retiring generators, and new resources at
locations with interconnection or transmission upgrade options.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
230
These interconnection and transmission upgrade options are limited and can be expensive.
Replacing existing thermal generators with resources that provide only a portion of their
interconnection capacity in “firm” capacity creates a need for additional interconnection capacity
elsewhere, and a key strategy is maximizing the “firmness” of each MW of interconnection
capacity to provide greater value. For this reason, the modeling of combined solar and storage
resources now reflects storage with capacity equal to 100% of solar nameplate, and four-hour
duration—up from 25% of solar capacity in the 2019 IRP, and 50% of capacity as discussed early
in the 2021 IRP public-input process. This allows a collocated solar resource to shift more energy
accumulated during periods of high solar radiance, increasing its effective capacity contribution.
Portfolio Cost
The second run of the ST model optimizes the reliability-adjusted portfolio to reflect least-cost
operations while meeting all requirements and adhering to modeled constraints. The ST model’s
hourly granularity means that this system cost will be highly accurate, taking into account
operational nuances that are obscured in the less granular LT and MT models. This in turn means
that when evaluating the constellation of all competitive portfolios, the comparison will be based
on appropriate relationships among all system components to yield an accurate PVRR.
Additional Measures
● Annual and energy not served (ENS)
● Annual CO2 emissions.
Medium-Term (MT) Schedule Model
The MT model uses the same common input assumptions described for LT and ST models with
additional data provided by the LT and ST model results (e.g., the capacity expansion portfolio).
While the LT and ST models supply an optimized portfolio for each case, the MT model is able to
bring the advantages of stochastic-driven risk metrics to the evaluation of the studies. While
deterministic ST system cost results are the most precise available due the hourly granularity, the
MT model provides the necessary data to calculate a stochastic risk metric for each case, which is
then added to the ST system cost outcomes to produce the risk-adjusted PVRR for each case.
Cost and Risk Analysis
Once unique resource portfolios are developed using the LT and ST models, additional modeling
is performed to produce metrics that support comparative cost and risk analysis among the
different resource portfolio alternatives. Stochastic risk modeling of resource portfolio alternatives
is performed with the MT model.
The stochastic simulation in the MT model produces a dispatch solution that accounts for
chronological commitment and dispatch constraints. The MT simulation incorporates stochastic
risk in its production cost estimates by using the Monte Carlo sampling of stochastic variables,
which include load, wholesale electricity and natural gas prices, hydro generation, and thermal
unit outages.
The stochastic parameters used in the MT model for the 2021 IRP are developed with a short-run
mean reverting process, whereby mean reversion represents a rate at which a disturbed variable
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
231
returns to its expected value. Stochastic variables may have log-normal or normal distribution as
appropriate. The log-normal distribution is often used to describe prices because such distribution
is bounded on the low end by zero and has a long, asymmetric "tail" reflecting the possibility that
prices could be significantly higher than the average. Unlike prices, load generally does not have
such skewed distribution and is generally better described by a normal distribution. Volatility and
mean reversion parameters are used for modeling the volatilities of the variables, while accounting
for seasonal effects. Correlation measures how much the random variables tend to move together.
Stochastic Model Parameter Estimation
Stochastic parameters are developed with econometric modeling techniques. The short-run
seasonal stochastic parameters are developed using a single period auto-regressive regression
equation (commonly called an AR(1) process). The standard error of the seasonal regression
defines the short run volatility, while the regression coefficient for the AR(1) variable defines the
mean reversion parameter. Loads and commodity prices are mean-reverting in the short term. For
instance, natural gas prices are expected to hover around a moving average within a given month
and loads are expected to hover near seasonal norms. These built-in responses are the essence of
mean reversion. The mean reversion rate tells how fast a forecast will revert to its expected mean
following a shock. The short-run regression errors are correlated seasonally to capture inter-
variable effects from informational exchanges between markets, inter-regional impacts from
shocks to electricity demand and deviations from expected hydroelectric generation performance.
The stochastic parameters are used to drive the stochastic processes of the following variables:
• Representative natural gas prices for PacifiCorp’s east and west balancing authority areas;
• Electricity market prices for Mid-C, COB, Four Corners, and Palo Verde;
• Loads for California, Idaho, Oregon, Utah, Washington and Wyoming regions; and
• Hydro generation.
Volume II, Appendix H – Stochastic Parameters discusses the methodology for developing the
stochastic parameters for the 2021 IRP.
For unplanned thermal outages, PacifiCorp assumes a uniform distribution around an expected
rate. For existing units, the expected unplanned outage rates by unit are based on its historical
performance. For new resources, the unplanned outage rates are as specified for those resources as
listed in the supply-side resource table in Volume I, Chapter 7 – Resource Options. Table 8.1
through Table 8.8 summarize updated stochastic parameters and seasonal price correlations for the
2021 IRP.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
232
Table 8.1 – Short-Term Load Stochastic Parameters
Table 8.2 – Short-Term Gas Price Parameters
Short-Term
Volatility
CA/OR
without
Portland
Portland ID UT WA WY
Winter 2021 IRP 0.045 0.041 0.038 0.023 0.052 0.016
Spring 2021 IRP 0.039 0.038 0.066 0.030 0.039 0.018
Summer 2021 IRP 0.043 0.059 0.057 0.051 0.053 0.017
Fall 2021 IRP 0.041 0.037 0.045 0.033 0.042 0.018
Short-Term Mean
Reversion
CA/OR
without
Portland
Portland ID UT WA WY
Winter 2021 IRP 0.154 0.165 0.177 0.281 0.147 0.226
Spring 2021 IRP 0.214 0.242 0.258 0.519 0.157 0.272
Summer 2021 IRP 0.197 0.265 0.148 0.307 0.212 0.234
Fall 2021 IRP 0.290 0.277 0.198 0.202 0.234 0.241
Short-Term Volatility East Gas West Gas
Winter 2021 IRP 0.115 0.166
Spring 2021 IRP 0.091 0.203
Summer 2021 IRP 0.099 0.131
Fall 2021 IRP 0.101 0.171
Short-Term Mean Reversion East Gas West Gas
Winter 2021 IRP 0.061 0.031
Spring 2021 IRP 0.160 0.140
Summer 2021 IRP 0.503 0.287
Fall 2021 IRP 0.046 0.022
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
233
Table 8.3 – Short-Term Electricity Price Parameters
Table 8.4 – Winter Season Price Correlation
Table 8.5 – Spring Season Price Correlation
Short-Term Volatility Four Corners COB Mid-
Columbia Palo Verde
Winter 2021 IRP 0.132 0.163 0.198 0.121
Spring 2021 IRP 0.172 0.288 0.630 0.138
Summer 2021 IRP 0.220 0.339 0.260 0.202
Fall 2021 IRP 0.174 0.173 0.160 0.150
Short-Term Mean
Reversion Four Corners COB Mid-
Columbia Palo Verde
Winter 2021 IRP 0.089 0.070 0.090 0.086
Spring 2021 IRP 0.180 0.258 0.461 0.151
Summer 2021 IRP 0.312 0.395 0.196 0.146
Fall 2021 IRP 0.197 0.178 0.120 0.163
Natural
Gas East
Four
Corners COB Mid -
Columbia Palo Verde Natural
Gas West
Natural Gas East 1.000
Four Corners 0.413 1.000
COB 0.377 0.620 1.000
Mid - Columbia 0.320 0.540 0.757 1.000
Palo Verde 0.492 0.791 0.586 0.564 1.000
Natural Gas West 0.344 0.235 0.302 0.288 0.248 1.000
Natural
Gas East
Four
Corners COB Mid -
Columbia Palo Verde Natural
Gas West
Natural Gas East 1.000
Four Corners 0.197 1.000
COB 0.141 0.339 1.000
Mid - Columbia 0.102 0.424 0.638 1.000
Palo Verde 0.223 0.630 0.327 0.276 1.000
Natural Gas West 0.563 0.195 0.215 0.168 0.097 1.000
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
234
Table 8.6 – Summer Season Price Correlation
Table 8.7 – Fall Season Price Correlation
Table 8.8 – Hydro Short-Term Stochastic
Short Term Volatility Short-Term Mean Reversion
Winter 2021 IRP 0.274 0.722
Spring 2021 IRP 0.189 0.433
Summer 2021 IRP 0.210 1.149
Fall 2021 IRP 0.298 0.368
Figure 8.6 and
Figure 8.7 show annual electricity prices at the first, 10th, 25th, 50th, 75th, 90th, and 99th
percentiles for Mid-C and Palo Verde market hubs based on a Monte Carlo simulation using short-
term volatility and mean reversion parameters. For Mid-C electricity prices, differences between
the first and 99th percentiles range from $21.64/MWh to $79.88/MWh during the 20-year study
Natural
Gas East
Four
Corners COB Mid -
Columbia Palo Verde Natural
Gas West
Natural Gas East 1.000
Four Corners 0.066 1.000
COB 0.161 0.224 1.000
Mid - Columbia 0.116 0.233 0.797 1.000
Palo Verde 0.056 0.440 0.453 0.542 1.000
Natural Gas West 0.674 0.035 0.103 0.075 -0.003 1.000
Natural
Gas East
Four
Corners COB Mid -
Columbia Palo Verde Natural
Gas West
Natural Gas East 1.000
Four Corners 0.207 1.000
COB 0.251 0.289 1.000
Mid - Columbia 0.225 0.279 0.596 1.000
Palo Verde 0.165 0.609 0.401 0.435 1.000
Natural Gas West 0.359 0.129 0.203 0.226 0.160 1.000
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
235
period. For Palo Verde electricity prices, the difference between the first and 99th percentiles range
from $26.57/MWh to $99.34/MWh.
Figure 8.6 – Simulated Annual Mid-C Electricity Market Prices
Figure 8.7 – Simulated Annual Palo Verde Electricity Market Prices
Figure 8.8 and Figure 8.9 show annual electricity prices at the first, 10th, 25th, 50th, 75th, 90th, and
99th percentiles for west and east natural gas prices. For west natural gas prices, differences
between the first and 99th percentiles range from $1.85/ Million British thermal units (MMBtu) to
$7.22/MMBtu during the 20-year study period. For east natural gas prices, differences between
the first and 99th percentiles range from $2.00/MMBtu to $7.64/MMBtu.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
236
Figure 8.8 – Simulated Annual Western Natural Gas Market Prices
Figure 8.9 - Simulated Annual Eastern Natural Gas Market Prices
Figure 8.10 through
Figure 8.15 show annual loads by load area and for PacifiCorp’s system at the first, 10th, 25th, 50th,
75th, 90th, and 99th percentiles based on a Monte Carlo simulation using short-term volatility and
mean reversion parameters. For Idaho (Goshen) load, the annual differences between the first and
99th percentiles range from 192 gigawatt-hours (GWh) to 348 GWh. For Utah load, the annual
difference ranges from 1,204 GWh to 2,772 GWh. For Wyoming load, the annual difference
ranges from 137 GWh to 271 GWh. For Oregon/California load, annual differences range from
746 GWh to 1,528 GWh. For Washington load, the annual difference ranges from 315 GWh to
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
237
557 GWh. For PacifiCorp’s system load, the annual difference ranges from 2,386 GWh to 4,354
GWh.
Figure 8.10 - Simulated Annual Idaho (Goshen) Load
Figure 8.11 - Simulated Annual Utah Load
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
238
Figure 8.12 - Simulated Annual Wyoming Load
Figure 8.13 - Simulated Annual Oregon/California Load
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
239
Figure 8.14 - Simulated Annual Washington Load
Figure 8.15 - Simulated Annual System Load
Figure 8.16 shows hydro generation at the first, 10th, 25th, 50th, 75th, 90th, and 99th percentiles based
on a Monte Carlo simulation using short-term volatility and mean reversion parameters. PacifiCorp
can dispatch its hydro generation on a limited basis to meet load and reserve obligations. The
parameters developed for the hydro stochastic process approximate the volatility of hydro
conditions as opposed to variations due to dispatch. The drop in 2021 is due to the assumed
decommissioning of the Klamath River projects. Annual differences in hydro generation between
the first and 99th percentiles range from 253 GWh to 512 GWh.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
240
Figure 8.16 - Simulated Annual Hydro Generation
Monte Carlo Simulation
During model execution, the MT model makes time-path-dependent Monte Carlo draws for each
stochastic variable based on input parameters. The Monte Carlo draws are percentage deviations
from the expected forward value of each variable. The Monte Carlo draws of the stochastic
variables among all resource portfolios modeled are the same, which allows for a direct
comparison of stochastic results among all resource portfolios being analyzed. In the case of
natural gas prices, electricity prices, and regional loads, the MT model applies Monte Carlo draws
on a daily basis. In the case of hydroelectric generation, Monte Carlo draws are applied on a weekly
basis.
Stochastic Portfolio Performance Measures
Stochastic simulation results for each unique resource portfolio are summarized, enabling direct
comparison among resource portfolio results during the preferred portfolio selection process. The
cost and risk stochastic measures reported from the MT model include:
● Stochastic mean PVRR
● Upper-tail Mean PVRR
● 5th, 90th and 95th percentile PVRR
● Standard deviation
● Risk-adjustment (5% of the 95th percentile)
Stochastic Mean PVRR
The stochastic mean PVRR is the average of system net variable operating costs among 50
iterations, combined with the nominal levelized capital costs and fixed costs corresponding to the
LT model for any given resource portfolio. The net variable cost from stochastic simulations,
expressed as a net present value, includes system costs for fuel, variable O&M, long term contracts,
system balancing market purchase expenses and sales revenues, reserve deficiency costs, and ENS
costs applicable when available resources fall short of load obligations. Capital costs for new and
existing resources are calculated on a nominal-levelized basis. Other components in the stochastic
3,300
3,400
3,500
3,600
3,700
3,800
3,900
4,000
4,100
4,200
GW
h
99th 90th 75th mean 25th 10th 1st
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
241
mean PVRR include CO2 emission costs for any scenarios that include a CO2 price assumption.
The stochastic mean PVRR, limited by performance constraints of the MT model, is not used
directly in portfolio selection; instead, the more granular ST PVRR serves as the base measure of
net system cost, modified appropriately by stochastic risk.
Upper-Tail Mean PVRR
The upper-tail mean PVRR is a measure of high-end stochastic cost risk. This measure is derived
by identifying the Monte Carlo iterations with the three highest production costs on a net present
value basis. The portfolio’s fixed costs, taken from the LT model, are added to these three
production costs, and the arithmetic average of the resulting PVRRs is computed.
5th and 95th Percentile PVRR
The 5th and 95th percentile PVRRs are also reported from the 50 Monte Carlo iterations. These
measures capture the extent of upper-tail (high cost) and lower-tail (low cost) stochastic outcomes.
As described above, the 95th percentile PVRR is used to derive the high-end cost risk premium for
the risk-adjusted mean PVRR measure. The 5th percentile PVRR is reported for informational
purposes.
Production Cost Standard Deviation
To capture production cost volatility risk, PacifiCorp uses the standard deviation of the stochastic
production cost from the 50 Monte Carlo iterations. The production cost is expressed as a net
present value of annual costs over the period 2021 through 2040. This measure meets Oregon IRP
guidelines to report a stochastic measure that addresses the variability of costs in addition to a
measure addressing the severity of bad outcomes.
Risk-Adjustment
The MT model outcomes of the 50 stochastic samples are used to calculate a risk-adjustment
measuring the relative risk of low-probability, high-cost outcomes. This measure is calculated as
five percent of system variable costs from the 95th percentile. This metric expresses a low-
probability portfolio cost outcome as a risk premium based on 50 Monte Carlo simulations for
each resource portfolio and applied to the hourly-granularity deterministic PVRR. The rationale
behind the risk-adjusted PVRR is to have a consolidated cost indicator for portfolio ranking,
combining the most precise available system cost and high-end cost-risk concepts.
Forward Price Curve Scenarios
Preferred portfolio variants developed during the portfolio-development process are analyzed in
the MT model with up to five price-policy scenarios. Price assumptions for each of these scenarios
are subject to short-term volatility and mean reversion stochastic parameters when used in the MT
model. The approach for producing wholesale electricity and natural gas price scenarios used for
MT model simulations is identical to the approach used to develop price scenarios for the portfolio-
development process.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
242
Other Plexos Modeling Methods and Assumptions
Transmission System
The base transmission topology shown in Figure 8.3 is used in each of the three Plexos models,
LT, ST and MT. Any transmission upgrades selected by LT and ST model processes that provide
incremental transfer capability among bubbles in this topology are part of the portfolio and thus
included in the MT stochastics and final ST optimizations.
Resource Adequacy
The CRM is a portfolio selection driver adequate to the capabilities of the LT model. Consistent
with past IRPs use of a PRM, the CRM is not used once the initial portfolio is established. This is
because ST reliability modifications to the portfolio rely on hourly resource availability and system
requirements to directly determine reliability shortfalls and any additional resource need at the
hourly level. MT stochastic model runs optimize unit commitment and dispatch logic on the
resulting fixed portfolio to meet all requirements, including operating reserve and regulation
reserves.
Energy Storage Resources
Storage resources such as battery energy storage systems (BESS), compressed air energy storage
(CAES), and flow storage have many potential advantages, including storage for frequency regulation,
grid stabilization, transmission loss reduction, reduced transmission congestion, renewable energy
smoothing, spinning reserve, peak-shaving, load-levelling, transmission and distribution deferral, and
asset utilization.
Each of the Plexos models (LT/MT/ST) dispatch storage resources endogenously, subject to their
constraints, for example requirements to charge from onsite solar or for the combined solar and storage
output and reserves to remain within a single interconnection limit. The model can deploy energy
storage for the most cost-effective uses, including any combination of load ramping and leveling,
reserve carrying, and to complement the benefits of renewable resource additions, particularly co-
located renewables.
Other Cost and Risk Considerations
In addition to reviewing the risk-adjustment, ENS, and CO2 emissions data, PacifiCorp considers
other cost and risk metrics in its comparative analysis of resource portfolios. These metrics include
fuel source diversity, and customer rate impacts.
Fuel Source Diversity
PacifiCorp considers relative differences in resource mix among portfolios by comparing the
capacity of new resources in portfolios by resource type, differentiated by fuel source. PacifiCorp
also provides a summary of fuel source diversity differences among top performing portfolios
based on forecasted generation levels of new resources in the portfolio. Generation share is
reported among thermal resources, renewable resources, storage resources, DSM resources and
market purchases.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
243
Customer Rate Impacts
To derive a rate impact measure, PacifiCorp computes the change in nominal annual revenue
requirement from top performing resource portfolios (with lowest risk adjusted mean PVRRs)
relative to a benchmark portfolio selected during the final preferred portfolio screening process.
Annual revenue requirement for these portfolios is based on the risk adjusted PVRR results from
the models and capital costs on a nominal levelized basis. While this approach provides a
reasonable representation of relative differences in projected total system revenue requirement
among portfolios, it is not a prediction of future revenue requirement for rate-making purposes.
Market Reliance
To assess market reliance risk, PacifiCorp quantifies market purchases for each portfolio allowing
comparisons among cases in Chapter 9 – modeling and Portfolio Selection Results. In the 2021
IRP market purchase become increasingly constricted compared to past IRPs, as described in
Volume I, Chapter 7 – Resource Options.
Portfolio Selection
Portfolios are measured for relative performance with regard to system costs, risk-adjusted system
costs, ENS and CO2 emissions. The risk adjusted PVRR accounts for relative upper tail stochastic
risk among portfolios.
Each portfolio under examination at a given step in the analysis is compared on the basis of cost-
risk metrics, and the least-cost, least-risk portfolio is chosen. Risk metrics examined include upper-
tail PVRR, risk-adjusted PVRR, ENS and emissions. As noted above, market reliance risk was
also evaluated. The comparisons of outcomes are detailed, ranked and assessed in the next chapter.
Additional quantitative analysis can be performed to further assess the relative differences among
top-performing portfolios; qualitative analysis can also be considered where appropriate during
portfolio selection on the basis of known factors that could not be readily captured in models.
Final Evaluation and Preferred Portfolio Selection
Due to the lengthy nature of the IRP cycle, the final step is the last opportunity to consider whether
top-performing portfolios merit additional study based on observations in the model results across
all studies, additional sensitivities, possible updates driven by recent events, and additional
stakeholder feedback. Additional sensitivities may refine the portfolio selection based on portfolio
optimization and cost and risk analysis steps. For the 2021 IRP this includes additional analysis to
assess the impacts of new natural gas resources, and energy efficiency methodologies based on
levelized cost of energy (LCOE) bundling as compared to capacity contribution bundling.
During the final screening process, the results of any further resource portfolio developments will
be ranked by risk-adjusted PVRR, the primary metric used to identify top performing portfolios.
Portfolio rankings are reported for the five price-policy price curve scenarios. Resource portfolios
with the lowest risk-adjusted PVRR receive the highest rank. Final screening also considers system
cost PVRR data from the Plexos models and other comparative portfolio analysis. At this stage,
PacifiCorp reviews additional metrics from the models looking to identify if ENS and CO2
emissions results can be used to differentiate portfolios that might be closely ranked on a risk-
adjusted PVRR basis.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
244
Case Definitions
Case definitions specify a combination of planning assumptions used to develop each unique
resource portfolio analyzed in the 2021 IRP, organized here into major development categories:
• Initial Portfolios
o P02 (optimized coal retirements)
o P03 (coal retired by 2030)
o BAU1 (end-of-life coal retirements)
o BAU2 (2019 IRP coal retirements)
• Preferred Portfolio Selection
o Top Performing Portfolio
o Preferred Portfolio Variants
• Washington Required Portfolios and Sensitivities6
Additional portfolio detail can be found in Volume II, Appendix I – Capacity Expansion Results.
Initial Portfolios
Informed by the public-input process, these cases build diversity around varying key retirement
dates. These portfolios explore potentially significant interactions among retirement options
including the potential to convert coal units to natural gas operations, retire units prior to end-of-
life, install carbon-capture equipment on coal-fired facilities, retire units at end-of-life, or cease all
coal-fired operations by year 2030. Potential trade-offs among these options are captured in the
relative strengths of each unique portfolio in how it interacts with the optimized selection of proxy
resources throughout the planning horizon. The initial portfolios also consider how resource
selections change with price-policy assumptions that deviate from the medium natural gas price
and medium CO2 price assumptions used to develop many resource portfolios. All of the initial
portfolios rely on the combined capabilities of three optimization models within Plexos, the LT
model, MT model and ST model, new to PacifiCorp in the 2021 IRP cycle.
There are considerable stranded-cost risks associated with planning a system that is reliant on new
natural gas resources with depreciable lives ranging between 30 to 40 years (i.e., a new gas-fired
resource placed in service in 2030 would be depreciated as late as 2070). Further, when considering
current state policies, it is not feasible to assume new natural gas resources can obtain the permits
needed to site and operate such a facility in many parts of PacifiCorp’s service territory. Finally,
PacifiCorp has observed that there is very limited development activity for new natural gas
facilities. This was most recently evident in the 2020AS RFP, which did not result in a single bid
for new natural gas resources. Therefore, new natural gas proxy resources were not made available
for selection in any of Initial Portfolios.
Portfolios generated with SCGHG price-policy assumptions are consistent with RCW19.280.030
in Washington.
6 Informational portfolios that are not eligible for selection as the preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
245
Table 8.9 provides the initial portfolio definitions for this IRP. Additional information, including
coal unit retirement assumptions, are provided for each case in Volume II, Appendix I – Capacity
Expansion Results.
Table 8.9 – Initial Portfolio Case Definitions
Case
Type(a)
Price-
Policy Existing Coal(b) Existing
Gas(b)
Other Existing
Resources(b)
Proxy
Resources(c)
P02 MM Optimized End of Life End of Life No New Gas
P02 MN Optimized End of Life End of Life No New Gas
P02 LN Optimized End of Life End of Life No New Gas
P02 HH Optimized End of Life End of Life No New Gas
P02 SCGHG Optimized End of Life End of Life No New Gas
P03 MM Retired by 2030 End of Life End of Life No New Gas
P03 MN Retired by 2030 End of Life End of Life No New Gas
P03 LN Retired by 2030 End of Life End of Life No New Gas
P03 HH Retired by 2030 End of Life End of Life No New Gas
P03 SCGHG Retired by 2030 End of Life End of Life No New Gas
BAU1 MM End of Life End of Life End of Life No New Gas
BAU1 MN End of Life End of Life End of Life No New Gas
BAU1 LN End of Life End of Life End of Life No New Gas
BAU1 HH End of Life End of Life End of Life No New Gas
BAU1 SCGHG End of Life End of Life End of Life No New Gas
BAU2 MM 2019 IRP 2019 IRP 2019 IRP No New Gas
BAU2 MN 2019 IRP 2019 IRP 2019 IRP No New Gas
BAU2 LN 2019 IRP 2019 IRP 2019 IRP No New Gas
BAU2 HH 2019 IRP 2019 IRP 2019 IRP No New Gas
BAU2 SCGHG 2019 IRP 2019 IRP 2019 IRP No New Gas
(a) “P” refers generically to “portfolio”; “BAU” refers to “business as usual”, a designation derived from stakeholder
feedback recommending the BAU1 and BAU2 series of cases.
(b) Aligned with the intent of the BAU2 study requests, the designation “2019 IRP” means that existing resources maintain
2019 retirement assumption except where updated information has changed known planning.
(c) Optimized proxy portfolio selections exclude new gas proxy resources except for gas-conversion of specific existing coal
resources.
All initial portfolios consider variations in retirement timing, the impact of regional haze
compliance operating limits and options for gas conversion or CCUS retrofit for certain units. The
initial portfolios differ based on planning assumptions around coal unit retirement options and
retirement timing.
P02 (optimized coal retirements)
P02 portfolios are fully optimized using the best available input data and assumptions regarding
requirements and constraints. The P02-MM case represents a reasonably likely future that assumes
medium gas prices and a medium CO2 price proxy for future federal policy. In this series, coal
retirement timing is optimized, whereas other existing resources are assumed to operate through
end of life; contracts expire at the end of their term. Proxy resource selections exclude new gas-
fueled additions except in the case of a coal-to-gas conversion of an existing resource. Based on
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
246
the logic of optimization modeling, P02 cases are expected to perform well compared to other case
types within the same price-policy environment assumptions given that the models will have the
most latitude to find a low-cost portfolio solution. The P02 series of cases includes a unique
portfolio developed under each of the five price-policy scenarios.
P03 (coal retired by 2030)
These P03 cases feature the retirement of all coal resources by 2030 using an optimized retirement
strategy within the first nine years of the planning horizon. Other existing resources are assumed
to operate through end of life; contracts expire at the end of their term. Proxy resource selections
exclude new gas-fueled additions except in the case of a coal-to-gas conversion of an existing coal
resource. In contrast to the P02 series, described above, the P03 series is expected to be relatively
costly as the pre-2030 retirement strategy prevents the models from optimizing coal retirements in
the last half of the planning horizon. The P03 series of cases includes a unique portfolio developed
under each of the five price-policy scenarios.
Business as Usual Cases
During the 2021 IRP public input process, four stakeholder feedback forms requested specific
“Business as Usual” (BAU) Cases:
Table 8.10 – Business as Usual Study Requests
Requesting Party Requested Case Summary
Wyoming Office of Consumer Advocate
(Form 037)
Begin with current generation and transmission
portfolio and reflect analysis on customer
impacts of changes to portfolio to accommodate
load growth and environmental compliance
obligations. Exclude early coal retirement as that
is analyzed elsewhere in the IRP.
Wyoming Public Service Commission (Form 045)
Carry forward the 2019 IRP preferred portfolio,
with updates due to regulatory changes, no
additional assumed early retirements, and
exclude externalities that are not currently
required by law to be evaluated.
Renewable Northwest (Form 046)
Include a BAU case that incorporates reliability
issues in California, Front Office Transaction
assumptions and state energy policy.
Joint Parties (Utah Association of Energy Users,
Utah Division of Public Utilities, Wyoming
Industrial Energy Consumers, and Wyoming
Office of Consumer Advocate (Form 058)
Two BAU cases – one based on the 2019 IRP
preferred portfolio and one based on the 2017
IRP Update preferred portfolio with all
commitments since the 2019 IRP included in BAU
case.
Based on this feedback, PacifiCorp planned to develop two stakeholder-defined BAU case series,
termed “BAU1” and “BAU2”.
BAU1 (end-of-life coal retirements)
The retirement strategy for BAU1 cases assumes existing assets will operate through the end of
their life operating life (no early retirement), including coal and non-coal resources; contracts
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
247
expire at the end of their term. Proxy resource selections exclude new gas-fueled additions except
in the case of a coal-to-gas conversion of an existing coal resource. The BAU1 series of cases
includes a unique portfolio developed under each of the five price-policy scenarios.
BAU2 (2019 IRP coal retirements)
BAU2 cases target portfolios that are reasonably aligned with the 2019 IRP preferred portfolio.
Existing resource assumptions will differ from the 2019 IRP retirement assumption only where
required to align with updated information, such as anticipated retirement dates for the minority-
owned Colstrip and Hayden facilities. Proxy resources can change to optimally meet load, ensuring
sufficient capacity and energy to accommodate changes in load from the 2019 IRP. Such proxy
resource selections exclude new gas-fueled additions and new coal-to-gas conversions are
disallowed. The BAU2 series of cases includes a unique portfolio developed under each of the five
price-policy scenarios.
Preferred Portfolio Selection Cases
Certain additional cases were developed directly from the top-performing case (P02-MM) based
on analysis of portfolios from the twenty initial cases as described above to evaluate the impacts
of specific future scenarios not considered elsewhere, but which may be adopted into the preferred
portfolio if the analysis warrants their inclusion. In the 2021 IRP, there are eight preferred portfolio
selection cases referred to as the “P02 Variants” as shown in Table 8.11:
Table 8.11 – Preferred Portfolio Variants
Portfolio Description
P02a-JB1-2 GC Excludes gas conversion of Jim Bridger Units 1 and 2
P02b-No B2H Excludes Boardman-to-Hemingway transmission segment
P02c-No GWS Excludes the Energy Gateway South transmission segment
P02d-No RFP Excludes 2020 All-Source Request for Proposals Final Shortlist
and the Energy Gateway South transmission segment
P02e-No NUC Excludes the NatriumTM advanced nuclear demonstration project
P02f-No NAU25 Excludes the early retirement of Naughton Units 1 and 2
P02g-CCUS
Includes Carbon Capture Utilization and Sequestration (CCUS)
retrofit of Dave Johnston Unit 4 in response to Wyoming House
Bill 200
P02h-JB3-4 RET Includes early retirement of Jim Bridger Units 3 and 4 in
response to stakeholder feedback
Each variant case begins with inputs and assumptions identical to the preferred portfolio (P02-
MM-CETA), which is the top performing portfolio (P02-MM) with adjustments required for
Washington’s Clean Energy Transformation Act (CETA).
P02a-JB1-2 GC
Starting with the assumption of the P02-MM-CETA portfolio, this portfolio is re-optimized with
added assumption that coal-to-gas conversions are disallowed, requiring an alternate strategy to
maintain system reliability.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
248
P02b-No B2H
In this sensitivity the transmission segments associated with the Boardman-to-Hemingway project
are removed along with 600 MW (nameplate) of enabled resources. The portfolio is re-optimized
in the absence of these projects, requiring an alternate strategy to maintain system reliability.
P02c-No GWS
The Energy Gateway South and associated D.17 projects enable 1,930 MW (nameplate) of
interconnected resources; approximately 1,641 MW of this interconnection capability is occupied
by projects identified in the All-Source 2020 RFP. In the P02c-No GWS case, both the
transmission project and enabled final shortlist wind bids from the All-source 2020 RFP are
removed. The portfolio is re-optimized in the absence of these projects, requiring an alternate
strategy to maintain system reliability.
P02d-No RFP
Similar to P02c-No GWS, the ‘No RFP’ case eliminates the Energy Gateway South and D.1
transmission projects, but also removes all final shortlist bids from the All-source 2020 RFP (not
just the wind bids enabled by GWS and D.1). The portfolio is re-optimized in the absence of these
projects, requiring an alternate strategy to maintain system reliability.
P02e-No NUC
The ‘No Nuc’ case removes the NatriumTM demonstration project in 2028 from the preferred
portfolio and re-optimizes proxy resources to maintain reliability. As the purpose of the sensitivity
is evaluate the system value of the NatriumTM demonstration project, proxy nuclear resources are
still allowed in the later years of the planning horizon in order to meet load and reliability
requirements at a reasonable cost. This results in a portfolio that targets the system value
contribution of the individual demonstration project.
P02f-No NAU25
The retirements of Naughton unit 1 and Naughton unit 2 in 2025 are assumed in the preferred
portfolio. This sensitivity evaluates the cost and risk merits of this strategy by disallowing these
two early retirements, re-optimizing the portfolio, and comparing outcomes.
P02g-CCUS
In response to Wyoming House Bill 200, this sensitivity includes the CCUS retrofit of Dave
Johnston Unit 4. The CCUS installation is assumed to occur in 2026 and also assumes the life of
Dave Johnston Unit 4 could be extended beyond the end of the planning horizon.
P02h-JB3-4 RET
The P02h-JB3-4 RET sensitivity tests the potential system cost or benefit of retiring Jim Bridger
unit 3 and Jim Bridger unit 4 prior to end-of-life. Based on the selected early retirement dates, the
portfolio is re-optimized in the absence of these projects, requiring an alternate strategy to maintain
system reliability.
7 Refer to Volume I, Chapter 4 – Transmission for details regarding these projects.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
249
Washington Required Portfolios
Washington’s CETA legislation requires utilities to conduct three scenarios:
• Alternative Lowest Reasonable Cost - WAC 480-100-620(10)(a) instructs utilities to
“describe the alternative lowest reasonable cost and reasonably available portfolio that the
utility would have implemented if not for the requirement to comply” with CETA’s Clean
Energy Transformation Standards. This sensitivity including the requirement to use the
social cost of greenhouse gases (SCGHG) price-policy assumption in the resource
acquisition decision. In Chapter 9 – Modeling and Portfolio Selection Results, the company
will analyze this portfolio in the context of both CETA and non-CETA complaint
outcomes.
• Climate Change - WAC 480-100-620(10)(b) instructs utilities to “incorporate the best
science available to analyze impacts including, but not limited to, changes in snowpack,
streamflow, rainfall, heating and cooling degree days, and load changes resulting from
climate change.” Please see Appendix A for additional detail regarding the climate change
scenario.
• Maximum Customer Benefit - WAC 480-100-620(10)(c) instructs utilities to “model the
maximum amount of customer benefits described in RCW 19.405.040(8) prior to balancing
against other goals.” The maximum customer benefit scenario focuses on adding
distributed generation, demand response, and energy efficiency in Washington, as well as
avoiding high-voltage transmission upgrades in PacifiCorp’s Yakima and Walla Walla
communities to minimize burdens and maximize benefits to Washington customers.
Washington load forecast reflects the high private generation forecast. The portfolio
assumes the social cost of greenhouse gas price-policy scenario and includes all available
Washington energy efficiency and demand response.
Sensitivity Case Definitions
PacifiCorp identified eight sensitivities outlined in Table 8.12 and discussed further in Volume I,
Chapter 9 – Modeling and Portfolio Selection Results.
Table 8.12 – Sensitivity Case Definitions
Case Description Load
Forecast
Private
Generation Resources CO2 Policy
S-01 High Load High Base Optimized Medium gas / Medium CO2
S-02 Low Load Low Base Optimized Medium gas / Medium CO2
S-03 1 in 20 Load Growth 1 in 20 Base Optimized Medium gas / Medium CO2
S-04 New Proxy Gas Allowed Base Base Optimized Medium gas / Medium CO2
S-05 Business Plan Base Base Align first three years Medium gas / Medium CO2
S-06 Levelized Cost of Energy
Efficiency Bundles Base Base Optimized Medium gas / Medium CO2
S-07 High Private Generation Base High Optimized Medium gas / Medium CO2
S-08 Low Private Generation Base Low Optimized Medium gas / Medium CO2
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
250
Load Sensitivities (S01, S02, S03)
PacifiCorp includes three different load forecast sensitivities. The high load forecast sensitivity
(S01) reflects optimistic economic growth assumptions from IHS Global Insight and high Utah
and Wyoming industrial loads. The low load forecast sensitivity (S02) reflects pessimistic
economic growth assumptions from IHS Global Insight and low Utah and Wyoming industrial
loads. The low and high industrial load forecasts focus on increased uncertainty in industrial loads
further out in time. To capture this uncertainty, PacifiCorp modeled 1,000 possible annual loads
for each year based on the standard error of the medium scenario regression equation. The low and
high industrial load forecast is taken from 5th and 95th percentile.
The third load forecast sensitivity (S03) is a 1-in-20 (5 percent probability) extreme weather
scenario. The 1-in-20 peak weather scenario is defined as the year for which the peak has the
chance of occurring once in 20 years. This sensitivity is based on 1-in-20 peak weather for July in
each state. Figure 17 compares the low, high, and 1-in-20 load sensitivities, net of base case private
generation levels, alongside the base case load forecast.
New Proxy Gas (S04)
In this sensitivity, new gas peaking resources replace non-emitting peaking resources and new
combined cycle combustion turbines replace advanced nuclear resources.
Business Plan Sensitivity (S05)
Case S05 complies with the Utah requirement to perform a business plan sensitivity consistent
with the commission’s order in Docket No. 15-035-04. Over the first three years, resources align
with those assumed in PacifiCorp’s 2020 Business Plan. Beyond the first three years of the study
period, unit retirement assumptions are aligned with those identified in the preferred portfolio. All
other resource selections are optimized using the Plexos models.
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
251
Figure 17 - Load and Private Generation Sensitivity Assumptions
Levelized Cost of Energy Efficiency Bundles (S06)
For the 2021 IRP, PacifiCorp reshaped the daily volumes from energy efficiency to better align
with the load forecast. This creates a realistic representation of the relationship between load and
weather-sensitive energy efficiency resource options. This sensitivity tests the effectiveness of this
methodology change in terms of efficiency and as measured by cost and risk metrics.
Private Generation Sensitivities (S07, S08)
Two private generation sensitivities are analyzed. As compared to base private generation
penetration levels that incorporated annual reductions in technology costs, the high private
55,000
60,000
65,000
70,000
75,000
80,000
GW
h
System Energy Load
Base 1 in 20 High Load Low Load High PG Low PG
9,000
9,500
10,000
10,500
11,000
11,500
12,000
12,500
13,000
13,500
MW
Coincident System Peak Load
Base 1 in 20 High Load Low Load High PG Low PG
PACIFICORP – 2021 IRP CHAPTER 8 – MODELING AND PORTFOLIO EVALUATION APPROACH
252
generation sensitivity (S07) reflects more aggressive technology cost reduction assumptions,
greater technology performance levels, and higher retail electricity rates. In contrast, the low
private generation sensitivity (S08) reflects lesser reductions in technology costs, reduced
technology performance levels, and lower retail electricity rates.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
253
CHAPTER 9 – MODELING AND PORTFOLIO
SELECTION RESULTS
CHAPTER HIGHLIGHTS
• Using cost and risk metrics to evaluate a wide range of resource portfolios, PacifiCorp selected
a preferred portfolio reflecting a bold vision shared with our customers for a future where
energy is delivered affordably, reliably and with increasingly reduced greenhouse gas
emissions.
• By the end of 2024, the 2021 IRP preferred portfolio includes the 2020 All-Source RFP final
shortlist resources including 1,792 MW of wind, 1,302 MW of solar additions, and 697 MW
of battery storage capacity – 497 MW paired with solar and a 200 MW standalone battery.
During this time, the preferred portfolio also includes the acquisition and repowering of Rock
River 1 (49 MW) and Foote Creek II-IV (43 MW) wind projects. and 4,290 MW of incremental
energy efficiency and 2,448 MW of new direct load control resources.
• To facilitate the delivery of new renewable energy resources to PacifiCorp customers across
the West, the preferred portfolio includes significant transmission investments. Specifically,
the 2021 IRP preferred portfolio includes the Energy Gateway South (GWS) transmission
line—a new 416-mile, high-voltage 500-kilovolt transmission line and associated
infrastructure running from the new Aeolus substation near Medicine Bow, Wyoming, to the
Clover substation near Mona, Utah. The 2021 preferred portfolio also includes the Energy
Gateway West Subsegment D.1 project (D.1)—a new 59-mile high-voltage 230-kilovolt
transmission line from the Shirley Basin substation in southeastern Wyoming to the Windstar
substation near Glenrock, Wyoming. Both transmission lines come online by the end of 2024.
• The 2021 IRP preferred portfolio also includes a 290-mile high-voltage 500-kilovolt
transmission line known as Boardman-to-Hemingway (B2H) to come online in 2026.
• Further, the 2021 IRP preferred portfolio includes near-term and long-term transmission
upgrades across the system that will facilitate continued and long-term growth in new resources
needed to reliably serve our customers.
• This is the first PacifiCorp IRP that includes new advanced nuclear and non-emitting peaking
resources as part of its least-cost, least-risk preferred portfolio. The 500 MW advanced nuclear
NatriumTM demonstration project will come online by summer 2028. Through 2040, the 2021
IRP preferred portfolio includes 1,000 MW of additional advanced nuclear resources and 1,226
MW of non-emitting peaking resources.
• Driven in part by ongoing cost pressures on existing coal-fired facilities and dropping costs for
new resource alternatives, of the 22 coal units currently serving PacifiCorp customers, the
preferred portfolio includes retirement of 14 of the units by 2030 and 19 of the units by the end
of the planning period in 2040. Coal-fueled generation capacity is reduced by 1,300 MW by
the end of 2025, 2,211 MW by 2030, and over 4,000 MW by 2040. The preferred portfolio
also reflects 1,554 MW of natural gas retirements through 2040.
• In the 2021 IRP preferred portfolio, Jim Bridger Units 1 and 2 are converted to natural gas-
fueled peaking units in 2024, providing a low-cost reliable resource for meeting load and
reliability requirements. There are no new natural gas resources in the preferred portfolio.
• The preferred portfolio shows an overall decline in reliance on wholesale market firm
purchases in the 2021 IRP preferred portfolio relative to the market purchases included in
the 2019 IRP preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
254
• The 2021 IRP preferred portfolio reflects PacifiCorp’s on-going efforts to provide cost-
effective clean-energy solutions for our customers and accordingly reflects a continued
trajectory of declining carbon dioxide (CO2) emissions. As compared to the 2019 IRP,
projected CO2 emissions in 2026 are down 26 percent. By 2030, average annual CO2
emissions are down 34 percent relative to the 2019 IRP preferred portfolio, and down 52
percent in 2035. By the end of the planning horizon, system CO2 emissions are projected
to fall from 39.1 million tons in 2021 to 4.8 million tons in 2040—a reduction of 88 percent.
Introduction
This chapter reports modeling and portfolio selection results for the resource portfolios developed
with a broad range of input assumptions informed by the Plexos modeling. Using model data from
the portfolio-development process and subsequent cost and risk analysis of unique portfolio
alternatives, the following discussion describes PacifiCorp’s preferred portfolio selection process
and presents the 2021 IRP preferred portfolio.
This chapter is organized around the portfolio development, modeling and evaluation steps
identified in the previous chapter and covers the portfolio, cost and risk analysis for the: (1) initial
portfolios; (2) the variants of the top performing initial portfolio and (3) the preferred portfolio
selection. The final preferred portfolio selection is informed by all relevant modeling results. This
chapter also presents modeling results for additional scenarios required under Washington’s Clean
Energy Transformation Act (CETA) that, while informative, were not considered eligible for
selection as the preferred portfolio.
Results of resource portfolio cost and risk analysis from each step are presented in the following
discussion of PacifiCorp’s portfolio evaluation processes. Stochastic modeling results are also
summarized in Volume II, Appendix J – Stochastic Simulation Results.
Initial Portfolio Development
The following discussion begins with an examination of initial portfolios exploring variations in
retirement timing, the impact of regional haze compliance operating limits and options for gas
conversion or carbon capture utilization and sequestration (CCUS) retrofit for certain units. The
initial portfolios differ based on planning assumptions around coal unit retirement options and
retirement timing. This includes a fully optimized view of potential retirements (P02), a partially
optimized view of early retirements that requires all coal units to be retired by 2030 (P03), fixed
retirements based on end-of-life operating assumptions (BAU1) and forced retirements consistent
with the 2019 IRP preferred portfolio (BAU2).
Following the initial portfolios, PacifiCorp examined variants of the top-performing case with
eight additional portfolios referred to as the P02-MM variants. All portfolios are examined with a
granular assessment of reliability requirements through the production of hourly deterministic ST
studies for every year over the 20-year planning horizon. Similar to the initial portfolios, this
provides twenty years of hourly ST reliability assessment data used to inform the portfolios and
ensure they are reliable.
As discussed in Volume I, Chapter 8 (Modeling and Portfolio Evaluation Approach), PacifiCorp
evaluated eight variants of the top-performing P02-MM initial portfolio. Final selection of the top-
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
255
performing portfolio and preferred portfolio selection also included an assessment of compliance
with CETA.
Initial Portfolio Development
The following tables and figures present resource additions and system costs for the initial
portfolios. Additional information is provided for all cases in Volume II, Appendix I (Capacity
Expansion Results), including resource portfolio results showing new resource capacity and
changes to existing resource capacity by year.
Initial Portfolios Thermal Retirements
Figure 9.1 summarizes the cumulative nameplate coal and gas retirements, including retirement of
units converted or converting to gas-fueled peaking resources by case over the near-term, mid-
term, and long-term among the initial portfolio cases. Note, in reporting cumulative capacity in
this figure, the mid-term results include capacity retired in the near-term, and similarly, the long-
term results include capacity retired in the near-term and in the mid-term. Unit-specific retirement
dates for each case can be found in Volume II, Appendix I (Capacity Expansion Results).
Through 2026, coal unit retirement capacity ranges from 230 MW (BAU1 portfolios which assume
end-of-life retirements) to 2,909 MW (P03 that assumes all coal units retire by 2030 and
specifically, the P03-HH and P03-SCGHG portfolios). By the end of the planning horizon, coal
retirements are similar among nearly all cases with exception of P03 which includes the early
retirement of Hunter Units 1-3 as part of the planning assumption to retire all units by 2030. There
is slight variation in timing of coal retirements among P02 and P03. Coal retirement timing
assumptions with the BAU1 and BAU2 cases are fixed based on the planning assumption end-of-
life (BAU1) and the 2019 IRP preferred portfolio retirement timing (BAU2). By the end of the
planning horizon, coal retirements are the same among P02, BAU1 and BAU2 cases with a total
of over 4,000 MW retired by 2040 (19 of PacifiCorp’s 22 units). P03 includes retirement of Hunter
Units 1-3 that are accelerated from end-of-life in 2042 to a 2029 retirement.
Not shown on the chart below, gas retirements are the same among all cases and include retirement
of the gas-fueled Naughton Unit 3 at the end of 2029, Gadsby Units 1-6 at the end of 2032,
Hermiston at the end of 2036, and the gas-fueled Jim Bridger Units 1 and 2 at the end of 2037.
This represents a total of 1,554 MW of gas retirements through 2040.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
256
Figure 9.1 – Initial Portfolios Thermal Retirements (MW)
Initial Portfolios New Renewables and Non-Emitting Resources
Figure 9.2 reports the nameplate capacity of new renewables and non-emitting resource additions
for each initial portfolio. Through 2025, all portfolios include the 2020 All-Source RFP final
shortlist resources including 1,792 MW of wind, 1,302 MW of solar additions, and 697 MW of
battery storage capacity – 497 MW paired with solar and a 200 MW standalone battery. They also
include the acquisition and repowering of Rock River 1 (49MW) and Foote Creek II-IV (43 MW)
wind projects. In 2026, all cases include an additional 745 MW of wind and additional solar and
storage ranging from 600 MW up to 1,090 MW. All cases include GWS and D.1 in 2024 along
with 1,641 MW of new wind in eastern Wyoming.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
257
All cases include B2H in 2026 along with 600 MW of new co-located solar and storage. All cases
include the 500 MW NatriumTM demonstration project in 2028. Through 2040, total new
renewable capacity including new wind, new solar and new solar collocated with storage ranges
between 6,794 MW and 10,306 MW. Through 2040, total new nuclear and non-emitting peaking
resource capacity ranges between 2,010 MW and 4,277 MW.
Figure 9.2 – Initial Portfolios New Renewables and Non-Emitting Resources (MW)
Initial Portfolios New Storage Resources
Figure 9.3 summarizes cumulative nameplate capacity of new storage resources for each initial
portfolio. Through 2025, all cases include the 2020 All-Source RFP final shortlist resources
including 697 MW of battery storage capacity – 497 MW paired with solar and a 200 MW
standalone battery. More storage resources are accelerated into the mid-term among those cases
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
258
that have higher levels of accelerated coal and gas retirements. Through 2040, total storage
selections range between 5,404 MW (P02-LN) and 7,531 MW (P03-MM) including storage co-
located with solar, standalone battery and a 500 MW pumped storage project selected in all cases
in 2040.
Figure 9.3 – Initial Portfolios New Storage Resources (MW)
Initial Portfolios Demand-Side Management (DSM) Resources
Figure 9.4 summarizes aggregated Demand-Side Management (DSM) selections by case. DSM
selections continue to be relatively stable among all cases however, variations do occur among
price-policy assumptions relative to CO2. Through 2030, energy efficiency selections range
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
259
between 1,845 MW (Case BAU1-LN) and 2,589 (Case BAU2-SC); demand response selections
range between 918 MW (Case BAU2-HH) and 1,469 MW (Cases BAU-1 MM, BAU-2 MM, P-
03 MM). More demand response resources are accelerated into the mid-term among those cases
that have higher levels of accelerated coal and gas retirements. Through 2040, energy efficiency
selections range between 3,605 MW (Case BAU1-MN) and 5,249 (Case BAU2-SC); demand
response selections range between 1,752 MW (Case BAU2-HH) and 2,458 MW (Case BAU2-
MM).
Figure 9.4 – Initial Portfolios Demand-Side Management Resources (MW)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
260
CO2 Emissions
Figure 9.5 reports cumulative CO2 emissions for each initial portfolio. Total CO2 emissions across
the initial portfolios are stable under the medium gas, medium CO2 (MM) price policy conditions,
averaging 372 million tons over the 20-year planning period. Emissions are generally higher in
cases with no CO2 price, averaging 427 million tons in low gas, no CO2 (LN) and medium gas, no
CO2 (MN) price-policy conditions. Under high gas, high CO2 (HH) price environments, emissions
average 323 million tons. The lowest emissions are reported under the social cost of greenhouse
gas (SCGHG) price-policy portfolios, averaging 195 million tons. Emissions across all cases range
from 171 million tons (P03-SCGHG) to 550 million tons (P02-MN).
Figure 9.5 – Initial Portfolios CO2 Emissions (Million Tons)
Table 9.1 to Table 9.5 present cost and risk results for the initial portfolios across five price-policy
scenarios, including the deterministic present value revenue requirement (PVRR), the risk-
adjusted PVRR, the amount of energy not served (ENS) as a percentage of load, and total CO2
emissions.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
261
As shown in Table 9.1, the medium gas/medium CO2 price-policy scenario, P02 outperforms other
cases on a PVRR basis, risk-adjusted PVRR, and ENS. While P02 has higher cumulative CO2
emissions, P03 has a risk-adjusted cost that is $1.7b higher than P02. Emissions levels are similar
among the P02, BAU1, and BAU2 portfolios.
Table 9.1 – Initial Portfolios Cost and Risk Results Summary (Medium Gas/Medium CO2)
As shown in Table 9.2, In the low gas/no CO2 price-policy scenario, P02 outperforms other cases
on cost and ENS and has comparable emissions to BAU1 and BAU2. P02 cumulative CO2
emissions are higher than in P03, driven by P03 retirement assumptions of retiring all coal by
2030, which has a risk-adjusted cost that is $2.5b higher than P02. Emissions levels are similar
among the P02, BAU1, and BAU2 portfolios.
Table 9.2 – Initial Portfolios Cost and Risk Results Summary (Low Gas/No CO2)
As shown in Table 9.3, In the medium gas/no CO2 price-policy scenario, P02 outperforms other
cases on costs and ENS and has comparable emissions to BAU1 and BAU2. P02 cumulative CO2
emissions are higher than in P03, driven by P03 retirement assumptions of retiring all coal by
2030, which has a risk-adjusted cost that is $3.5b higher than P02.
Table 9.3 – Initial Portfolios Cost and Risk Results Summary (Medium Gas/No CO2)
As shown in Table 9.4, In the high gas/high CO2 price-policy scenario, P02 outperforms other
cases on costs and ENS and has comparable emissions to P03, the case with lowest emissions,
which has a risk-adjusted cost that is $1.0b higher than P02.
P VRR
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
ST P VRR
plus 5% of
95th
Stochastic
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
Average
Annual
ENS, 2021-
2040 % of
Average
Load
Change
from
Lowest
ENS
P ortfolio Rank
Total CO2
Emissions,
2021-2040
(Thousand
Tons)
Change
from
Lowest
Emission
P ortfolio Rank
P 02 25,794 $0 1 26,151 $0 1 0.0049%0.00000%1 398,953 97,568 4
P03 27,566 $1,772 4 27,848 $1,696 4 0.0051%0.00021%2 301,385 0 1
BAU1 26,839 $1,045 3 27,172 $1,021 3 0.0051%0.00021%3 395,123 93,738 3
BAU2 26,691 $897 2 27,026 $875 2 0.0053%0.00037%4 391,900 90,515 2
Case - M M
ST Value Risk Adjusted ENS Average P ercent of Load CO2 Emissions
P VRR
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
ST P VRR
plus 5% of
95th
Stochastic
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
Average
Annual
ENS, 2021-
2040 % of
Average
Load
Change
from
Lowest
ENS
P ortfolio Rank
Total CO2
Emissions,
2021-2040
(Thousand
Tons)
Change
from
Lowest
Emission
P ortfolio Rank
P02 21,973 $0 1 22,224 $0 1 0.0053%$0 1 472,867 172,908 4
P03 24,582 $2,609 4 24,744 $2,520 4 0.0055%$0 2 299,959 0 1
BAU1 22,426 $453 2 22,635 $411 2 0.0058%$0 4 447,378 147,419 2
BAU2 22,452 $479 3 22,707 $483 3 0.0057%$0 3 466,064 166,105 3
Case - LN
ST Value Risk Adjusted ENS Average P ercent of Load CO2 Emissions
P VRR
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
ST P VRR
plus 5% of
95th
Stochastic
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
Average
Annual
ENS, 2021-
2040 % of
Average
Load
Change
from
Lowest
ENS
P ortfolio Rank
Total CO2
Emissions,
2021-2040
(Thousand
Tons)
Change
from
Lowest
Emission
P ortfolio Rank
P02 21,994 $0 1 22,228 $0 1 0.0049%$0 1 540,688 224,270 4
P03 25,588 $3,594 4 25,752 $3,523 4 0.0053%$0 3 316,418 0 1
BAU1 22,471 $477 3 22,649 $420 2 0.0052%$0 2 517,882 201,464 2
BAU2 22,432 $439 2 22,674 $445 3 0.0055%$0 4 537,670 221,252 3
Case - M N
ST Value Risk Adjusted ENS Average P ercent of Load CO2 Emissions
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
262
Table 9.4 – Initial Portfolios Cost and Risk Results Summary (High Gas/High CO2)
In the medium gas/social cost of greenhouse gas scenario, P02 outperforms other cases on cost
except for P03, outperforms P03 and BAU2 on ENS, and ties BAU1 on ENS. P02 emissions are
comparable to P03 emissions, the case with lowest emissions. P03 retires all coal by 2030 and has
a risk-adjusted cost that is $178m lower than P02.
Table 9.5 – Initial Portfolios Cost and Risk Results Summary (Med Gas/Social Cost and
Greenhouse Gas)
Based on these findings, PacifiCorp identified P02-MM as the top-performing portfolio at this
stage of the portfolio-development process. PacifiCorp developed and analyzed additional
portfolios as variants of P02-MM, as described in the following section.
P02 Variant Portfolios
Eight P02 variant portfolios were developed from the top-performing P02-MM portfolio to analyze
key resources and in response to stakeholder interest. The P02 variant portfolios are summarized
in the Table 9.6.
P VRR
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
ST P VRR
plus 5% of
95th
Stochastic
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
Average
Annual
ENS, 2021-
2040 % of
Average
Load
Change
from
Lowest
ENS
P ortfolio Rank
Total CO2
Emissions,
2021-2040
(Thousand
Tons)
Change
from
Lowest
Emission
P ortfolio Rank
P02 27,464 $0 1 27,965 $0 1 0.0056%$0 1 283,845 5,527 2
P03 28,643 $1,179 2 29,002 $1,037 2 0.0059%$0 3 278,317 0 1
BAU1 29,280 $1,815 4 29,776 $1,810 4 0.0056%$0 2 365,205 86,888 4
BAU2 28,856 $1,391 3 29,356 $1,391 3 0.0060%$0 4 363,367 85,050 3
Case - HH
ST Value Risk Adjusted ENS Average P ercent of Load CO2 Emissions
P VRR
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
ST P VRR
plus 5% of
95th
Stochastic
($ m)
Change
from
Lowest
Cost
P ortfolio
($ m)Rank
Average
Annual
ENS, 2021-
2040 % of
Average
Load
Change
from
Lowest
ENS
P ortfolio Rank
Total CO2
Emissions,
2021-2040
(Thousand
Tons)
Change
from
Lowest
Emission
P ortfolio Rank
P02 38,371 $80 2 39,290 $178 2 0.0068%$0 1 184,121 13,417 2
P03 38,291 $0 1 39,112 $0 1 0.0110%$0 3 170,704 0 1
BAU1 40,356 $2,065 4 41,393 $2,281 4 0.0102%$0 2 214,365 43,662 4
BAU2 40,154 $1,863 3 41,196 $2,084 3 0.0137%$0 4 209,299 38,595 3
Case - SCGHG
ST Value Risk Adjusted ENS Average P ercent of Load CO2 Emissions
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
263
Table 9.6 – P02 Variant Portfolios
Case Description
P02a – JB1-2 No GC Excludes gas conversion of Jim Bridger Units 1 and 2
P02b – No B2H Excludes Boardman-to-Hemingway transmission segment
P02c – No GWS Excludes the Energy Gateway South transmission segment
P02d – No RFP Excludes 2020 All-Source Request for Proposals Final Shortlist and the
Energy Gateway South transmission segment
P02e – No Nuc Excludes the NatriumTM advanced nuclear demonstration project
P02f – No Nau 25 Excludes the early retirement of Naughton Units 1 and 2
P02g – CCUS Includes Carbon Capture Utilization and Sequestration (CCUS) retrofit of
Dave Johnston Unit 4 in response to Wyoming House Bill 200
P02h – JB 3-4 Retire Includes early retirement of Jim Bridger Units 3 and 4 in response to
stakeholder feedback
P02 Variant Portfolios Portfolio Summary
Coal and Gas Retirements
Figure 9.6 summarizes cumulative nameplate coal and gas retirements for the P02 variant
portfolios over the near-term, mid-term, and long-term. Note, in reporting cumulative capacity in
this figure and the similar figures that follow, the mid-term results include capacity retired in the
near-term, and similarly, the long-term results include capacity retired in the near-term and in the
mid-term. Unit-specific retirement dates for each case can be found in Volume II, Appendix I
(Capacity Expansion Results). Through 2026, total coal retirements range between 944 MW (P02e
– No Nau 25) and 1,302 MW (P02-MM and all other P02 variant portfolios). Through the end of
2030, coal retirements range between 1,882 MW (P02g – CCUS) and 2,911 MW (P02h – JB 3-4
Retire). Through 2040, total coal retirements are 4,088 MW in each case with exception of P02g
– CCUS, which totals 3,758 MW resulting from the CCUS retrofit of Dave Johnston Unit 4.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
264
Figure 9.6 – P02 Variant Portfolios Coal and Gas Retirements (MW)
New Renewable and Non-Emitting Resources
Figure 9.7 summarizes the capacity of new renewables and non-emitting resource additions for
each of the P02 variant portfolios. P02b excludes B2H in 2026 along with 600 MW of new co-
located solar and storage. P02c (no GWS or D.1) excludes 1,641 MW of new wind in eastern
Wyoming. P02d (no RFP bids, no GWS, and no D.1) results in the lowest new renewable additions,
excluding 1,792 MW of wind, 1,302 MW of solar additions, and 697 MW of battery storage
capacity. P02e excludes the 500 MW NatriumTM demonstration project in 2028, resulting in the
lowest nuclear resource additions across the horizon at 1,000 MW in 2038; P02e also has the
highest non-emitting peaking additions, at 1,638 MW.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
265
Figure 9.7 – P02 Variant Portfolios New Renewables and Non-Emitting Resources (MW)
New Storage Resources
Figure 9.8 summarizes the capacity of new storage resource additions for each of the P02 variant
portfolios. P02d-No RFP adds the least total battery resource in the absence of the All-Source RFP
resources, and the GWS and D.1 transmission lines. This is due to larger additions of advance
nuclear and non-emitting peaking units needed to meet system requirements. With the removal of
large dispatchable resources, such as the NatriumTM demonstration project (P02e-No Nuc) or the
Jim Bridger plant (P02h-JB 3-4 Retire), there are higher selections of storage to maximize the
value of renewable additions.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
266
Figure 9.8 – P02 Variant Portfolios New Storage Resources (MW)
P02 Variant Portfolios Demand-Side Management Resources
Figure 9.9 summarizes aggregated DSM selections by case. DSM selections remain relatively
consistent among P02 variants and range between 1,669 MW and 1,709 MW through 2026.
Through 2040, energy efficiency selections and demand response total investments are consistent
among the P02 variant portfolios.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
267
Figure 9.9 – P02 Variant Portfolios Demand-Side Management Resources (MW)
CO2 Emissions
Figure 9.10 reports cumulative CO2 emissions for each of the P02 variant portfolios. Total CO2
emissions through 2026 are very stable, ranging between 205 million tons (P02a-JB1-2 GC) and
220 million tons (P02d-No RFP). Through 2040, cumulative CO2 emissions range between 369
million tons (P02h-JB3-4 Retire) and 476 (P02d-No RFP GWS) million tons.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
268
Figure 9.10 – P02 Variant Portfolios CO2 Emissions Summary (Million Tons)
Figure 9.11 shows the annual emissions profile for the P02-MM portfolio and the eight P02 variant
portfolios through the end of the planning period in 2040.
Figure 9.11 – Annual CO2 Emissions Among P02 Variant Portfolios
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
269
P02 Variants Portfolio Discussion
Jim Bridger Unit 1 and Unit 2 Gas Conversion Variant (P02a-JB 1-2 GC)
The P02a-JB 1-2 No GC portfolio is a variant of the P02-MM portfolio that eliminates the gas
conversion of Jim Bridger Units 1 and 2. When this variant is compared to the P02-MM portfolio,
changes in proxy resources and system costs driven by the gas conversion of Jim Bridger Units 1
and 2 can be isolated.
Figure 9.12 shows the cumulative (at left) and incremental (at right) portfolio changes when the
gas conversion of Jim Bridger Units 1 and 2 is eliminated from the P02-MM portfolio. A positive
value indicates an increase in resources and a negative value indicates a decrease in resources when
the conversion is eliminated. Without the gas conversion, the model optimizes the next-best
selection and indicates that Jim Bridger Units 1 and 2 retire at the end of 2023 and an additional
700 MW of solar co-located with storage is added in 2024. Over 600 MW of non-emitting peakers
displace a similar amount of solar co-located with storage over the 2031-2037 timeframe. In 2038,
considering Jim Bridger Units 1 and 2 were already retired at the end of 2023, the case without
gas conversion avoids an advanced nuclear resource and non-emitting peaker resources that are
required in the P02-MM portfolio when the converted units would have otherwise retired.
Figure 9.12 – Increase/(Decrease) in Proxy Resources when the Jim Bridger Gas
Conversion is Eliminated from the P02-MM portfolio.
Figure 9.13 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when the gas conversion of Jim Bridger Units 1 and 2 is eliminated from the
P02-MM portfolio. The graph on the left shows annual changes in cost by category and the graph
on right shows annual net changes in total costs (the solid black line) and the cumulative present-
value revenue requirement differential (PVRR(d)) over time (the dashed black line).1 Through
2040, the PVRR(d) shows that the portfolio without gas conversion of Jim Bridger Units 1 and 2
is $447 million higher cost than the P02-MM portfolio. On a risk-adjusted basis, which factors in
the risk associated with low-probability, high-cost events through stochastic simulations, the
portfolio without gas conversion is $469 million higher cost than the P02-MM portfolio.
The key drivers to this result are consistent with changes in resources between the two portfolios.
The portfolio without gas conversion retires Jim Bridger Units 1 and 2 at the end of 2023 (the next
1 The PVRR(d) represents the differential in revenue requirement costs relative to the P02-MM portfolio.
-800
-600
-400
-200
0
200
400
600
800
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Nuclear Solar+Storage Non-Emitting Peaker Converted Gas
-800
-600
-400
-200
0
200
400
600
800
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Nuclear Solar+Storage Non-Emitting Peaker Converted Gas
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
270
best alternative to gas conversion), which triggers the addition of 700 MW of solar co-located with
storage in 2024. The initial capital associated with the 700 MW solar resource paired with 700
MW of 4-hour storage is $2,890/kW. The initial capital required to convert Jim Bridger Units 1
and 2 to natural gas is about $25/kW.
Figure 9.13 – Increase/(Decrease) in System Costs when the Jim Bridger Gas Conversion is
Eliminated from the P02-MM portfolio.
Table 9.7 summarizes the PVRR(d) of the P02a-JB 1-2 No GC portfolio relative to the P02-MM
portfolio under a range of different price-policy scenarios. The portfolio that eliminates gas
conversion for Jim Bridger Units 1 and 2 is significantly higher cost than the P02-MM portfolio
across each of the price-policy scenarios. This trend holds true for both the ST PVRR and the risk-
adjusted PVRR results. Both portfolios, as measured by ENS, are very reliable among all price-
policy scenarios. Emissions are slightly higher when Jim Bridger Units 1 and 2 are converted to
natural gas (approximately 1-2 percent relative to the case without gas conversion). In aggregate,
these results support the inclusion of the Jim Bridger Unit 1 and 2 gas conversion in the preferred
portfolio.
Table 9.7 – PVRR(d) of the P02a-JB 1-2 No GC Portfolio Relative to the P02-MM Portfolio
Under Varying Price-Policy Scenarios.
($400)
($300)
($200)
($100)
$0
$100
$200
$300
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Costs Emissions
Net Market Transactions Transmission
$477
($200)
($100)
$0
$100
$200
$300
$400
$500
$600
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02a-MM-MM $26,271 $26,620 0.0049%390,206
P02a-MM-LN $23,126 $23,322 0.0051%427,277
P02a-MM-MN $22,916 $23,095 0.0049%504,386
P02a-MM-HH $29,198 $29,684 0.0050%360,636
P02a-MM-SCGHG $39,991 $41,000 0.0097%206,732
Change from P02-MM-MM $477 $469 0.0000%(8,747)
Change from P02-MM-LN $534 $529 -0.0003%(8,857)
Change from P02-MM-MN $495 $486 0.0000%(6,982)
Change from P02-MM-HH $418 $404 0.0001%(7,915)
Change from P02-MM-SCGHG $353 $335 0.0003%(1,918)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
271
Boardman-to-Hemingway Variant (P02b-No B2H)
The P02b-No B2H portfolio is a variant of the P02-MM portfolio that eliminates the B2H
transmission line. When this variant is compared to the P02-MM portfolio, changes in proxy
resources and system costs driven by the removal of the B2H transmission line can be isolated.
Figure 9.14 shows the cumulative (at left) and incremental (at right) portfolio changes when the
B2H transmission line is eliminated from the P02-MM portfolio. A positive value indicates an
increase in resources and a negative value indicates a decrease in resources when the transmission
line is eliminated. Without B2H, 405 MW of wind and 200 MW of solar co-located with storage
is removed from the portfolio in 2026. Approximately 200 MW of storage capacity is removed
from eastern Wyoming in 2029, which must be replaced by just over 200 MW of non-emitting
peaking capacity in 2030.
Figure 9.14 – Increase/(Decrease) in Proxy Resources when the B2H Transmission Line is
Eliminated from the P02-MM portfolio.
Figure 9.15 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when the B2H transmission line is eliminated from the P02-MM portfolio.
The graph on the left shows annual changes in cost by category and the graph on right shows
annual net changes in total costs (the solid black line) and the cumulative PVRR(d) of changes to
net system costs over time (the dashed black line). Through 2040, the PVRR(d) shows that the
portfolio without the B2H transmission line is $388 million higher cost than the P02-MM portfolio.
On a risk-adjusted basis, which factors in the risk associated with low-probability, high-cost events
through stochastic simulations, the portfolio without B2H is $453 million higher cost than the P02-
MM portfolio.
Without the B2H transmission line, the cost for proxy resources is reduced consistent with the
changes in the resource portfolio. However, the reduction in resources results in an increase in net
market costs, indicating that without the B2H transmission line, the system would be more
dependent on the market. With fewer renewable resources, output from coal and gas resources
increase, emissions increase, and the associated costs from higher fossil-fueled generation and
emissions also increase. The increase in transmission costs is driven by the incremental costs to
reliably serve increasing load in central Oregon. The B2H transmission line provides more
flexibility and increased load-serving capability on the 500-kV transmission system into the central
Oregon load pocket. Without the B2H transmission line, additional resources would need to be
sited in southern Oregon that could be called upon to maintain reliable operations of the broader
transmission system in the region. The analysis assumes that 725 MW of incremental 4hour battery
-1000
-800
-600
-400
-200
0
200
400
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Battery Solar+Storage Wind Non-Emitting Peaker
-700
-600
-500
-400
-300
-200
-100
0
100
200
300
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Battery Solar+Storage Wind Non-Emitting Peaker
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
272
resources and other transmission upgrades would be needed in southern Oregon if the B2H
transmission line is not built. The transmission cost savings reflect the fact that these investments
would be avoided if B2H is built.
Figure 9.15 – Increase/(Decrease) in System Costs when the B2H Transmission Line is
Eliminated from the P02-MM portfolio.
Table 9.8 summarizes the PVRR(d) of the P02b-No B2H portfolio relative to the P02-MM
portfolio under a range of different price-policy scenarios. Eliminating the B2H transmission line
increases the ST PVRR and the risk-adjusted PVRR all price-policy scenarios Removal of B2H
also results in higher emissions (emissions increase by approximately 5 percent in the MM price-
policy scenario). Note, that both portfolios, as measured by ENS results, are very reliable among
all price-policy scenarios. While the cost increase from B2H in the LN price-policy scenario is low
relative to other price-policy scenarios, it is more likely than not that there will be some form of
policy that will impute a cost on greenhouse gas emissions. It is also unlikely that gas prices will
remain low for decades to come. In aggregate, these results support the inclusion of the B2H
transmission line in the preferred portfolio.
Table 9.8 – PVRR(d) of the P02b-No B2H Portfolio Relative to the P02-MM Portfolio Under
Varying Price-Policy Scenarios.
($200)
($100)
$0
$100
$200
$300
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Costs Emissions
Net Market Transactions Transmission
$388
$0
$50
$100
$150
$200
$250
$300
$350
$400
$450
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02b-MM-MM $26,181 $26,605 0.0050%418,015
P02b-MM-LN $22,622 $22,874 0.0054%456,553
P02b-MM-MN $22,575 $22,822 0.0050%527,710
P02b-MM-HH $29,521 $30,102 0.0050%387,960
P02b-MM-SCGHG $41,089 $42,223 0.0117%228,728
Change from P02-MM-MM $388 $453 0.0001%19,062
Change from P02-MM-LN $30 $81 0.0001%20,419
Change from P02-MM-MN $154 $213 0.0000%16,342
Change from P02-MM-HH $742 $822 0.0001%19,408
Change from P02-MM-SCGHG $1,450 $1,557 0.0023%20,078
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
273
Energy Gateway South and Sub-Segment D.1 Variant (P02c-No GWS)
The P02c-No GWS portfolio is a variant of the P02-MM portfolio that eliminates the GWS and
D.1 transmission lines. Because wind bids selected to the 2020AS RFP final shortlist that are
located in eastern Wyoming cannot interconnect without these two transmission lines,2 these
resources are also eliminated from the P02c-No GWS portfolio. When this variant is compared to
the P02-MM portfolio, changes in proxy resources and system costs driven by the removal of the
GWS and D.1 transmission lines can be isolated.
Figure 9.16 shows the cumulative (at left) and incremental (at right) portfolio changes when the
GWS and D.1 transmission line are eliminated from the P02-MM portfolio. A positive value
indicates an increase in resources and a negative value indicates a decrease in resources when the
transmission lines are eliminated. Without GWS and D.1, 2020AS RFP wind resources are
removed from the portfolio in 2024 (shown as a reduction in 2025, the first full year these resources
would be online). An additional 289 MW of wind is eliminated in 2030. In 2034, the absence of
the new wind resources triggers the addition of an additional advanced nuclear plant that displaces
solar co-located with storage resources. The lack of resource additions with the removal of wind
resources in the portfolio without GWS and D.1 signals an increase in market reliance.
Figure 9.16 – Increase/(Decrease) in Proxy Resources when the GWS and D.1 Transmission
Lines are Eliminated from the P02-MM portfolio.
Figure 9.17 shows how market purchases change when the GWS and D.1 transmission lines are
removed from the portfolio. With fewer resources, market purchases on an annual basis increase
by nearly 20% if GWS and D.1 are removed from the portfolio. Consequently, there is elevated
market-reliance risk if the GWS and D.1 transmission lines are not built.
2 Examination of this variant focuses on the estimated impacts to resource procurement, market purchases, and
system costs, but ignores the elimination of GWS and D.1 transmission lines would interfere with PacifiCorp
transmission’s ability to provide nearly 2,500 MW of requests for transmission and interconnection service governed
by multiple FERC-jurisdictional executed contracts.
-3000
-2500
-2000
-1500
-1000
-500
0
500
1000
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Nuclear Solar+Storage Wind Energy Efficiency
-2000
-1500
-1000
-500
0
500
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Nuclear Solar+Storage Wind Energy Efficiency
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
274
Figure 9.17 – Increase/(Decrease) Market Purchases in the P02-MM and P02c-No GWS
Portfolios.
When GWS, D.1, and the associated 2020AS RFP wind resources are removed from the portfolio,
the costs associated with new resources decline. The cost for transmission is also reduced. This
reduction in transmission cost is net of the cost required to build a new 230-kV line to
accommodate PacifiCorp’s obligation to provide firm point-to-point transmission service to a
third-party transmission customer. The 230-kV alternative is not avoidable if GWS is not built.
Further, the $1.4 billion cost assumed for this alternative is the minimum cost for the alternative
considering that it includes only the upgrades required to grant a single transmission service
request. Additional costs would be incurred to accommodate additional requests for
interconnection service. To accommodate all of these requests, it is likely the alternative would be
to construct GWS.
When the GWS and D.1 transmission lines are removed from the portfolio, coal and gas generation
is increased, which increases variable costs for existing fossil-fired resources and the associated
cost for increased emissions. Further, the system becomes more reliant on the market as shown by
increased market costs. As noted above, this not only increases costs to the system, but it also
introduces incremental market-reliance risk, which is not captured in PVRR results. The increase
in system costs that occurs in 2034 coincides with the period where production tax credits
associated with new wind in the P02-MM portfolio roll off and when there is a shift in the resource
mix between the two cases (without GWS, D.1, and the associated 2020AS RFP wind, an
additional advanced nuclear facility is required).
Figure 9.18 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when the GWS and D.1 transmission lines are eliminated from the P02-MM
portfolio. The graph on the left shows annual changes in cost by category and the graph on right
shows annual net changes in total costs (the solid black line) and the cumulative PVRR(d) of
changes to net system costs over time (the dashed black line). Through 2040, the PVRR(d) shows
that the portfolio without the GWS and D.1 transmission lines is $156 million higher cost than the
P02-MM portfolio. On a risk-adjusted basis, which factors in the risk associated with low-
probability, high-cost events through stochastic simulations, the portfolio without the GWS and
D.1 transmission lines is $288 million higher cost than the P02-MM portfolio. The risk-adjusted
results indicate that the GWS and D.1 transmission lines add significant risk mitigation benefits
associated with volatility in market prices, loads, hydro generation, and unplanned outages.
0
200
400
600
800
1,000
1,200
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
aM
W
P02-MM P02c-No GWS
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
275
Figure 9.18 – Increase/(Decrease) in System Costs when the GWS and D.1 Transmission
Lines are Eliminated from the P02-MM portfolio.
Table 9.9 summarizes the PVRR(d) of the P02c-No GWS portfolio relative to the P02-MM
portfolio under a range of different price-policy scenarios. System costs increase when GWS and
D.1 are removed from the portfolio in MM, HH, and SCGG price-policy scenarios. Conversely,
costs decrease in the LN and MN price-policy scenarios. Without GWS and D.1, emissions from
PacifiCorp’s fossil-fueled resources increase considerably—ranging from 8.4% in the MN price-
policy scenario to 17.8% in the SCGG price-policy scenario. As discussed earlier, it is more likely
than not that there will be some form of policy action taken to impute a cost or penalty on
greenhouse gas emissions. It is also unlikely gas prices will be suppressed for many decades to
come, as assumed in the LN price-policy scenario. Further, cost-and-risk results indicate that there
is a tremendous opportunity cost of not building these transmission lines should policies develop
that impose costs on greenhouse gas emissions. This is seen with the disproportionate increase in
costs under HH and SCGG price-policy scenarios relative to the size of cost reductions in the
unlikely LN and MN price-policy scenarios. Considering the removal of GWS and D.1 increases
system costs among the MM, HH, and SCGG price-policy scenarios, significantly increases
emissions and associated costs and risks, and significantly increases market-reliance risk, this
analysis supports including GWS, D.1, and the associated 2020AS RFP wind resources in the
preferred portfolio.
($400)
($300)
($200)
($100)
$0
$100
$200
$300
$400
$500
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Costs Emissions
Net Market Transactions Transmission
$156
($40)
($20)
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
276
Table 9.9 – PVRR(d) of the P02c-No GWS Portfolio Relative to the P02-MM Portfolio Under
Varying Price-Policy Scenarios.
2020AS RFP Variant (P02d-No RFP)
The P02d-No RFP GWS portfolio is a variant of the P02-MM portfolio that eliminates all 2020AS
RFP resources, including the GWS and D.1 transmission lines. When this variant is compared to
the P02-MM portfolio, changes in proxy resources and system costs driven by the removal of the
2020AS RFP resources can be isolated.
Figure 9.19 shows the cumulative (at left) and incremental (at right) portfolio changes when the
2020AS RFP resources are eliminated from the P02-MM portfolio. A positive value indicates an
increase in resources and a negative value indicates a decrease in resources when the 2020AS RFP
resources and the GWS and D.1 transmission lines are eliminated. Without 2020AS RFP
resources, an additional 400 MW of solar co-located with storage is added to the portfolio in 2026.
In 2029, 549 MW of storage is removed. In 2030, 149 MW of storage is added concurrent with
the removal of 389 MW of wind. In 2033, an additional advanced nuclear resource displaces 500
MW of solar co-located with storage. The lack of resource additions with the removal of 2020AS
RFP resources signals an increase in market reliance.
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02c-MM-MM $25,949 $26,439 0.0052%445,607
P02c-MM-LN $21,864 $22,151 0.0005%484,784
P02c-MM-MN $22,056 $22,349 0.0051%554,193
P02c-MM-HH $29,739 $30,408 0.0051%413,739
P02c-MM-SCGHG $42,235 $43,512 0.0157%245,883
Change from P02-MM-MM $156 $288 0.0002%46,654
Change from P02-MM-LN ($727)($642)-0.0048%48,650
Change from P02-MM-MN ($365)($261)0.0002%42,825
Change from P02-MM-HH $960 $1,128 0.0002%45,187
Change from P02-MM-SCGHG $2,596 $2,847 0.0063%37,233
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
277
Figure 9.19 – Increase/(Decrease) in Proxy Resources when 2020AS RFP Resources are
Eliminated from the P02-MM portfolio.
Figure 9.20 shows how market purchases change when the 2020AS RFP resources are removed
from the portfolio. With fewer resources, market purchases on an annual basis increase by as much
as 45% in 2025. From 2025 through 2040, market purchase volumes are, on average, 30% higher
than the market purchases in the P02-MM portfolio. Consequently, there is elevated market-
reliance risk without the 2020AS RFP resources.
Figure 9.20 – Increase/(Decrease) Market Purchases in the P02-MM and P02d-No RFP
Portfolios.
Figure 9.21 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when 2020AS RFP resources are eliminated from the P02-MM portfolio. The
graph on the left shows annual changes in cost by category and the graph on right shows annual
net changes in total costs (the solid black line) and the cumulative PVRR(d) of changes to net
system costs over time (the dashed black line). Through 2040, the PVRR(d) shows that the
portfolio without 2020AS RFP resources is $1,063 billion higher cost than the P02-MM portfolio.
On a risk-adjusted basis, which factors in the risk associated with low-probability, high-cost events
through stochastic simulations, the portfolio without the 2020AS RFP resources is $1,293 billion
higher cost than the P02-MM portfolio.
-5000
-4000
-3000
-2000
-1000
0
1000
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Nuclear Battery Solar Solar+Storage Wind Energy Efficiency
-2500
-2000
-1500
-1000
-500
0
500
1000
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Nuclear Battery Solar Solar+Storage Wind Energy Efficiency
0
200
400
600
800
1,000
1,200
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
aM
W
P02-MM P02c-No RFP
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
278
When the 2020AS RFP resources are removed from the portfolio, the costs associated with new
resources decline. The cost for transmission is also reduced. As is the case in the portfolio that
removes GWS and D.1 (but retains all 2020AS RFP resources not dependent upon these
transmission lines), this reduction in transmission cost is net of the cost required to build a new
230-kV line to accommodate PacifiCorp’s obligation to provide firm point-to-point transmission
service to a third-party transmission customer. The 230-kV alternative is not avoidable if GWS is
not built, and the $1.4 billion cost assumed for this alternative is the minimum cost considering
that it focuses on the upgrades required to grant a single transmission service request. Additional
costs would be incurred to accommodate additional requests for interconnection service. To
accommodate all of these requests, it is likely the alternative would be to construct GWS.
When the 2020AS RFP bids are removed from the portfolio, coal and gas generation is increased,
which increases variable costs for existing fossil-fired resources and the associated cost for
increased emissions. Further, the system becomes more reliant on the market as shown by
increased market costs. As noted above, this not only increases costs to the system, but it also
introduces incremental market-reliance risk, which is not captured in PVRR results. The increase
in costs in 2025 reflect a sizeable deficiency that would need to be covered with additional market
purchases. The deficiency cost is grouped with the proxy resource costs in the chart at left, which
essentially offsets new resource cost savings in that year.
Figure 9.21 – Increase/(Decrease) in System Costs when 2020AS RFP Resources are
Eliminated from the P02-MM portfolio.
Table 9.10 summarizes the PVRR(d) of the P02d-No RFP GWS portfolio relative to the P02-MM
portfolio under a range of different price-policy scenarios. System costs increase significantly
when 2020AS RFP resources are removed from the portfolio in all but the LN price-policy
scenario. Without the RFP resources, emissions from PacifiCorp’s fossil-fueled resources increase
considerably—ranging from 12.5% in the MN price-policy scenario to 34.7% in the SCGG price-
policy scenario. As discussed earlier, it is more likely than not that there will be policy actions
taken to impute a cost or penalty on greenhouse gas emissions. It is also unlikely that gas prices
will be suppressed for many decades to come, as assumed in the LN price-policy scenario. Further,
cost-and-risk results indicate that there is a tremendous opportunity cost of not pursuing the RFP
resources along with the associated investments in the GWS and D.1 transmission lines should
policies develop impose costs on greenhouse gas emissions. This is seen with the disproportionate
increase in costs under HH and SCGG price-policy scenarios relative to the size of cost reductions
in the unlikely LN price-policy scenario. Further, each of cases that remove 2020AS RFP resources
show a more notable decline in reliability, as measured by the ENS metric. Considering the
removal of 2020AS RFP bids and the associated investment in the GWS and D.1 transmission
($600)
($400)
($200)
$0
$200
$400
$600
$800
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Costs Emissions
Net Market Transactions Transmission
$1,063
$0
$200
$400
$600
$800
$1,000
$1,200
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
279
lines increases system costs among all but the LN price-policy scenario, significantly increases
emissions and associated costs, and significantly increases market-reliance risk, this analysis
supports including 2020AS RFP resources in the preferred portfolio.
Table 9.10 – PVRR(d) of the P02d-No RFP GWS Portfolio Relative to the P02-MM Portfolio
Under Varying Price-Policy Scenarios.
NatriumTM Demonstration Project Variant (P02e-No Nuc)
The P02e-No Nuc portfolio is a variant of the P02-MM portfolio that eliminates the NatriumTM
advanced nuclear demonstration project. When this variant is compared to the P02-MM portfolio,
changes in proxy resources and system costs driven by the removal of the demonstration project
can be isolated.
Figure 9.22 shows the cumulative (at left) and incremental (at right) portfolio changes when the
NatriumTM demonstration project is eliminated from the P02-MM portfolio. A positive value
indicates an increase in resources and a negative value indicates a decrease in resources when the
project is eliminated. Without the NatriumTM demonstration project, 348 MW of solar co-located
with storage is added to the portfolio in 2026 and an additional 240 MW is added in 2030. In 2037,
a non-emitting peaker displaces solar+battery resource capacity.
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02d-MM-MM $26,857 $27,445 0.0208%476,318
P02d-MM-LN $22,246 $22,605 0.0265%515,934
P02d-MM-MN $22,655 $23,036 0.0208%575,308
P02d-MM-HH $31,178 $31,973 0.0206%445,220
P02d-MM-SCGHG $45,770 $47,228 0.0537%281,014
Change from P02-MM-MM $1,063 $1,293 0.0159%77,364
Change from P02-MM-LN ($346)($188)0.0211%79,800
Change from P02-MM-MN $234 $426 0.0159%63,939
Change from P02-MM-HH $2,399 $2,693 0.0157%76,669
Change from P02-MM-SCGHG $6,131 $6,563 0.0443%72,364
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
280
Figure 9.22 – Increase/(Decrease) in Proxy Resources when the NatriumTM Demonstration
Project is Eliminated from the P02-MM portfolio.
Figure 9.23 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when the NatriumTM demonstration project eliminated from the P02-MM
portfolio. The graph on the left shows annual changes in cost by category and the graph on right
shows annual net changes in total costs (the solid black line) and the cumulative PVRR(d) of
changes to net system costs over time (the dashed black line). Through 2040, the PVRR(d) shows
that the portfolio without the demonstration project is $133 million higher cost than the P02-MM
portfolio. On a risk-adjusted basis, which factors in the risk associated with low-probability, high-
cost events through stochastic simulations, the portfolio without the demonstration project is $158
million higher cost than the P02-MM portfolio.
When the NatriumTM advanced nuclear demonstration project is removed from the portfolio, the
cost for new proxy resources increases in 2026 with the addition of more solar+battery resources.
Over this period, fossil-fueled generation decreases, which reduced operating costs and emissions
costs. Beginning 2028, removing the NatriumTM demonstration project reduces new proxy
resource costs. More than offsetting these cost savings are increased costs from fossil-fueled
generation, emissions, and net market transactions.
Figure 9.23 – Increase/(Decrease) in System Costs when the NatriumTM Demonstration
Project is Eliminated from the P02-MM portfolio.
Table 9.11 summarizes the PVRR(d) of the P02e-No Nuc portfolio relative to the P02-MM
portfolio under a range of different price-policy scenarios. System costs increase when the
-400
-200
0
200
400
600
800
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Nuclear Solar+Storage Non-Emitting Peaker
-500
-400
-300
-200
-100
0
100
200
300
400
500
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Nuclear Solar+Storage Non-Emitting Peaker
($200)
($150)
($100)
($50)
$0
$50
$100
$150
$200
$250
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Costs Emissions
Net Market Transactions Transmission
$133
($40)
($20)
$0
$20
$40
$60
$80
$100
$120
$140
$160
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
281
NatriumTM demonstration project is removed from the portfolio in all but the LN and MN price-
policy scenarios, which show an incremental reduction in costs on a deterministic basis. The cost
reduction for the LN price-policy erodes by $12 million on a risk-adjusted basis, while the MN
price-policy scenario breaks even with P02-MM when adjusted for risk. Without the demonstration
project, emissions from PacifiCorp’s fossil-fueled resources increase by about 2% to 3%,
depending upon the price-policy scenario. Both portfolios, as measured by ENS results, are very
reliable among all price-policy scenarios. In aggregate, these results support the inclusion of the
NatriumTM advanced nuclear demonstration project in the preferred portfolio.
Table 9.11 – PVRR(d) of the P02e-No Nuc Portfolio Relative to the P02-MM Portfolio Under
Varying Price-Policy Scenarios.
Naughton Units 1 and 2 Retirement Variant (P02f-No Nau 25)
The P02f-No Nau 25 portfolio is a variant of the P02-MM portfolio that maintains continued coal-
fueled operation of Naughton Units 1 and 2 through the end of 2029. When this variant is compared
to the P02-MM portfolio, changes in proxy resources and system costs driven by the removal of
the demonstration project can be isolated.
Figure 9.24 shows the cumulative (at left) and incremental (at right) portfolio changes when
Naughton Units 1 and 2 continue operating as coal-fueled resources through 2029. A positive value
indicates an increase in resources and a negative value indicates a decrease in resources when the
project is eliminated. With continued coal-fueled operations at Naughton Units 1 and 2, 549 MW
of 4-hour storage capacity is removed from the portfolio in 2029. When Naughton Units 1 and 2
subsequently retire at the end of 2029, 339 MW of wind is removed from the portfolio, a non-
emitting peaker is added to the portfolio along with additional solar co-located with storage and
standalone storage.
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02e-MM-MM $25,927 $26,309 0.0049%408,473
P02e-MM-LN $22,510 $22,723 0.0054%446,547
P02e-MM-MN $22,404 $22,609 0.0049%521,098
P02e-MM-HH $29,112 $29,644 0.0049%377,010
P02e-MM-SCGHG $40,139 $41,203 0.0090%215,640
Change from P02-MM-MM $133 $158 0.0000%9,520
Change from P02-MM-LN ($82)($70)0.0000%10,413
Change from P02-MM-MN ($17)($0)0.0000%9,730
Change from P02-MM-HH $333 $364 0.0000%8,459
Change from P02-MM-SCGHG $501 $537 -0.0004%6,990
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
282
Figure 9.24 – Increase/(Decrease) in Proxy Resources when Naughton Units 1 and 2 Continue
Operating as Coal-Fueled Resources through 2029.
Figure 9.25 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when Naughton Units 1 and 2 continue operating as coal-fueled resources
through 2029. The graph on the left shows annual changes in cost by category and the graph on
right shows annual net changes in total costs (the solid black line) and the cumulative PVRR(d) of
changes to net system costs over time (the dashed black line). Through 2040, the PVRR(d) shows
that the portfolio that operates Naughton Units 1 and 2 through 2029 is $54 million higher cost
than the P02-MM portfolio. On a risk-adjusted basis, which factors in the risk associated with low-
probability, high-cost events through stochastic simulations, the portfolio that operates Naughton
Units 1 and 2 through 2029 is $66 million higher cost than the P02-MM portfolio.
When Naughton Units 1 and 2 continue operating as coal-fueled resources through 2029, changes
in system costs are largely tied to changes in the operating cost of these two units through 2028.
In 2029, the reduction in proxy resource costs is caused by the displacement of incremental solar
co-located with storage. This is partially offset by increased costs from fossil-fueled resources and
emissions. Beyond 2030, changes in the resource mix lead to reduced proxy resource costs.
However, over this time, fossil-fueled resource costs increase, emissions costs increase, and the
net cost of market transactions increase.
Figure 9.25 – Increase/(Decrease) in System Costs when Naughton Units 1 and 2 Continue
Operating as Coal-Fueled Resources through 2029.
-1000
-800
-600
-400
-200
0
200
400
600
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Coal Battery Solar+Storage Wind Non-Emitting Peaker
-800
-600
-400
-200
0
200
400
600
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Coal Battery Solar+Storage Wind Non-Emitting Peaker
($100)
($50)
$0
$50
$100
$150
$200
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Costs Emissions
Net Market Transactions Transmission
$54
($60)
($40)
($20)
$0
$20
$40
$60
$80
$100
$120
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
283
Table 9.12 summarizes the PVRR(d) of the P02f-No Nau 25 portfolio relative to the P02-MM
portfolio under a range of different price-policy scenarios. System costs increase when Naughton
Units 1 and 2 continue to operate as coal-fueled resources through 2029 in the MM, HH, and
SCGG price-policy scenarios. Conversely, costs decrease in the LN and MN price-policy
scenarios. If Naughton Units 1 and 2 do not retire at the end of 2025, emissions from PacifiCorp’s
fossil-fueled resources increase by about 2%. It is more likely than not that there will be some
form of policy action taken to impute a cost or penalty on greenhouse gas emissions, even when
considered through the 2029 time frame. It is also unlikely gas prices will be suppressed for the
next decade, as assumed in the LN price-policy scenario. Further, cost-and-risk results indicate
that there is a tremendous opportunity cost of continuing to operate Naughton Units 1 and 2 as
coal-fueled resources should policies develop that impose costs on greenhouse gas emissions. This
is seen with the disproportionate increase in costs under HH and SCGG price-policy scenarios
relative to the size of cost reductions in the unlikely LN and MN price-policy scenarios.
Considering the continued coal operations of Naughton Units 1 and 2 increases system costs
among the MM, HH, and SCGG price-policy scenarios, significantly increases emissions and
associated costs and risks, this analysis supports retiring Naughton Units 1 and 2 at the end of
2025.
Table 9.12 – PVRR(d) of the P02f-No Nau Portfolio Relative to the P02-MM Portfolio Under
Varying Price-Policy Scenarios.
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02f-MM-MM $25,848 $26,217 0.0050%405,395
P02f-MM-LN $22,503 $22,710 0.0054%442,821
P02f-MM-MN $22,372 $22,565 0.0049%518,642
P02f-MM-HH $28,968 $29,484 0.0049%374,781
P02f-MM-SCGHG $40,017 $41,068 0.0098%213,910
Change from P02-MM-MM $54 $66 0.0001%6,442
Change from P02-MM-LN ($89)($83)0.0001%6,687
Change from P02-MM-MN ($49)($45)0.0000%7,274
Change from P02-MM-HH $189 $204 0.0000%6,230
Change from P02-MM-SCGHG $378 $402 0.0004%5,260
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
284
Dave Johnston Unit 4 CCUS Variant (P02g-CCUS)
The P02g-CCUS portfolio is a variant of the P02-MM portfolio that forces a CCUS retrofit on
Dave Johnston Unit 4 in 2026 to enable the project to qualify for existing tax credits. When this
variant is compared to the P02-MM portfolio, changes in proxy resources and system costs driven
by the CCUS retrofit can be isolated. Because CCUS was not selected as a least-cost resource
option in the P02-MM portfolio, this variant was produced to evaluate a means to comply with
Wyoming House Bill 200 (HB 200). HB 200 was passed by the Wyoming Legislature in March
2020, and it requires the Wyoming Public Service Commission to establish a standard that
specifies a percentage of electricity that must be generated from coal-fired generation using carbon
capture technology by 2030, subject to an incremental cost limitation of 2% of Wyoming
customers’ total bill to comply with the standard.
For modeling purposes, PacifiCorp chose to force a CCUS retrofit (amine based post-combustion
+ enhanced oil recovery) at Dave Johnston Unit 4 for the following reasons:
• There are no complications with co-ownership as would be the case with Wyodak or the
Jim Bridger units
• CCUS at Dave Johnston Unit 4 would not require a new lined coalcombustion residual
impoundment as would be the case at the Naughton coal units
• Expectation of lower costs associated with necessary inlet NOX and SO2 controls relative
to Dave Johnston Units 1 and 2
• Dave Johnston Unit 3 has a federal closure commitment under EPA’s regional haze rule.
Installation of CCUS at Dave Johnston Unit 4 would be expected to meet preliminary HB
200 targets
This modeling assumption does not mean PacifiCorp has determined Dave Johnston Unit 4 is the
only site for a CCUS retrofit. As described in the 2021 IRP action plan, PacifiCorp is engaged in
a request for expressions of interest process and will soon be issuing a request for proposals that
will help identify candidates for potential CCUS retrofits and help refine cost-and-performance
assumptions.
Figure 9.26 shows the cumulative (at left) and incremental (at right) portfolio changes when the
CCUS retrofit is installed on Dave Johnston Unit 4 relative to the P02-MM portfolio. A positive
value indicates an increase in resources and a negative value indicates a decrease in resources when
the CCUS retrofit is installed. With the installation of CCUS in 2026, there is a net reduction of
capacity due to the parasitic load associated with the carbon capture equipment.3 Beyond 2027,
when Dave Johnston is retired in the P02-MM portfolio, there is an increase in coal capacity
through the remainder of the study period. The extended life of Dave Johnston Unit 4, with a
CCUS retrofit installed, displaces 149 MW of standalone storage in 2029 and 359 MW of wind in
2030.
3 Upon installation of the carbon capture equipment, Dave Johnston Unit 4’s rating is 254 MW. As a coal-fired
facility without carbon capture equipment, Dave Johnston Unit 4’s rating is 330 MW.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
285
Figure 9.26 – Increase/(Decrease) in Proxy Resources when CCUS is Installed on Dave
Johnston Unit 4 in 2026.
Figure 9.27 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when CCUS is installed on Dave Johnston Unit 4 in 2026. The graph on the
left shows annual changes in cost by category and the graph on right shows annual net changes in
total costs (the solid black line) and the cumulative PVRR(d) of changes to net system costs over
time (the dashed black line). Through 2040, the PVRR(d) shows that the portfolio with CCUS
installed on Dave Johnston Unit 4 project is $271 million higher cost than the P02-MM portfolio.
On a risk-adjusted basis, which factors in the risk associated with low-probability, high-cost events
through stochastic simulations, the portfolio with the Dave Johnston Unit 4 CCUS retrofit is $235
million higher cost than the P02-MM portfolio.
On an ST PVRR basis, capital cost assumptions for the CCUS retrofit at Dave Johnston Unit 4
would need to decrease by approximately 33% to achieve break-even economics in the MM price-
policy scenario—initial capital would need to drop from $1.14 billion to $761 million.
Alternatively, the enhanced-oil recovery revenue stream assumed in this analysis (from a credit-
worthy counterparty) would need to increase by approximately 84% to achieve break-even
economics under the MM price-policy scenario. Prices for enhanced-oil recovery in the company’s
analysis start at $19.25/ton in 2026 and grow to $27.51 by 2040.
When the CCUS retrofit is installed in 2026, the carbon capture technology increases the costs
associated with Dave Johnston Unit 4. This shows up as increased fixed costs for coal and gas
resources in the chart at left. This is partially offset by reduced emissions costs. Beginning in the
2029-to-2030-time frame, avoided proxy resource costs add to the emissions cost savings.
-600
-500
-400
-300
-200
-100
0
100
200
300
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Coal Battery Wind
-400
-300
-200
-100
0
100
200
300
400
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Coal Battery Wind
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
286
Figure 9.27 – Increase/(Decrease) in System Costs when CCUS is Installed on Dave Johnston
Unit 4 in 2026.
Table 9.13 summarizes the PVRR(d) of the P02g-CCUS portfolio relative to the P02-MM portfolio
under a range of different price-policy scenarios. The portfolio that includes the CCUS retrofit at
Dave Johnston Unit 4 is higher cost than the P02-MM portfolio across each of the price-policy
scenarios. This trend holds true for both the ST PVRR and the risk-adjusted PVRR results. Both
portfolios, as measured by ENS, are very reliable among all price-policy scenarios. Emissions are
slightly lower when CCUS is installed on Dave Johnston Unit 4 (approximately 1% relative to the
P02-MM portfolio). The magnitude of the increased cost in the portfolio that includes a CCUS
retrofit on Dave Johnston Unit 4 in 2026, which would be situs-assigned to Wyoming customers,
is expected to exceed the cost containment language set forth in HB 200, and for this reason, it is
not included in the preferred portfolio. Nonetheless, PacifiCorp recognizes that this analysis is
driven by a wide range of assumptions specific to the cost and commercial structure of CCUS
opportunities. Consequently, PacifiCorp has established an action plan with a CCUS action item
to continue with the on-going request for expressions of interest process initiated this year and to
proceed with a request for proposals process that will help identify potential sites, costs, and
commercial structures that will allow us to update this analysis in the 2023 IRP.
Table 9.13 – PVRR(d) of the P02g-CCUS Portfolio Relative to the P02-MM Portfolio Under
Varying Price-Policy Scenarios.
($300)
($200)
($100)
$0
$100
$200
$300
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Costs Emissions
Net Market Transactions Transmission
$271
($50)
$0
$50
$100
$150
$200
$250
$300
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02g-MM-MM $26,065 $26,387 0.0048%394,448
P02g-MM-LN $22,860 $23,025 0.0054%431,634
P02g-MM-MN $22,741 $22,894 0.0048%506,715
P02g-MM-HH $28,932 $29,389 0.0049%364,436
P02g-MM-SCGHG $39,763 $40,744 0.0091%207,527
Change from P02-MM-MM $271 $235 -0.0001%(4,506)
Change from P02-MM-LN $269 $232 0.0000%(4,500)
Change from P02-MM-MN $320 $285 -0.0001%(4,654)
Change from P02-MM-HH $153 $109 0.0000%(4,115)
Change from P02-MM-SCGHG $124 $79 -0.0003%(1,122)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
287
Jim Bridger Units 3 and 4 Retirement Variant (P02h-JB3-4 Retire)
The P02h-JB3-4 Retire portfolio is a variant of the P02-MM portfolio that forces Jim Bridger Units
3 and 4 to retire before 2030 with the most optimal timing as determined by the Plexos model.
When this variant is compared to the P02-MM portfolio, changes in proxy resources and system
costs driven by the early retirement of Jim Bridger Units 3 and 4 can be isolated.
Figure 9.28 shows the cumulative (at left) and incremental (at right) portfolio changes when Jim
Bridger Units 3 and 4 are retired early. A positive value indicates an increase in resources and a
negative value indicates a decrease in resources when the project is eliminated. When required to
choose the most economic retirement date before 2030 for Jim Bridger Units 3 and 4, the portfolio
with the early retirements retires Jim Bridger Unit 3 at the end of 2026 and retires Jim Bridger
Unit 4 at the end of 2029. When Jim Bridger Unit 3 retires, 200 MW of solar co-located with
storage is added to the portfolio. When Jim Bridger Unit 4 retires, an additional advanced nuclear
resource is added in 2030. These additions displace a 2038 advanced nuclear resource and a 2038
non-emitting peaker, which are included in the P02-MM portfolio. Note, the chart at right does
not indicate there is an increase in coal capacity. This bar indicates that the loss of coal capacity
that would otherwise occur in the P02-MM portfolio with the retirement of Jim Bridger Units 3
and 4 at the end of 2037 does not occur in the P02h-JB3-4 Retire portfolio because those
retirements already occurred at the end of 2026 and 2029.
Figure 9.28 – Increase/(Decrease) in Proxy Resources when Jim Bridger Units 3 and 4 are
Forced to Retire before 2030.
Figure 9.29 summarizes changes in system costs, based on ST model results using MM price-
policy assumptions, when Jim Bridger Units 3 and 4 are forced to retire before 2030. The graph
on the left shows annual changes in cost by category and the graph on right shows annual net
changes in total costs (the solid black line) and the cumulative PVRR(d) of changes to net system
costs over time (the dashed black line). Through 2040, the PVRR(d) shows that the portfolio with
the accelerated retirement of Jim Bridger Units 3 and 4 is $95 million higher cost than the P02-
MM portfolio. On a risk-adjusted basis, which factors in the risk associated with low-probability,
high-cost events through stochastic simulations, the portfolio with the early retirement of Jim
Bridger Units 3 and 4 is $60 million higher cost than the P02-MM portfolio.
When Jim Bridger Units 3 and 4 retire early, there is a reduction in system costs associated with
reduced fixed and variable expenses from fossil-fueled generation and reduced emissions
-800
-600
-400
-200
0
200
400
600
800
In
s
t
a
l
l
e
d
M
W
Cumulative Portfolio Changes
Coal Nuclear Solar+Storage Non-Emitting Peaker
-800
-600
-400
-200
0
200
400
600
800
In
s
t
a
l
l
e
d
M
W
Incremental Portfolio Changes
Coal Nuclear Solar+Storage Non-Emitting Peaker
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
288
expenses. These cost savings are more than offset by higher proxy resource costs from incremental
solar co-located with storage and incremental advanced nuclear resources.
Figure 9.29 – Increase/(Decrease) in System Costs when Jim Bridger Units 3 and 4 are
Forced to Retire Before 2030.
Table 9.14 summarizes the PVRR(d) of the P02h-JB3-4 Retire portfolio relative to the P02-MM
portfolio under a range of different price-policy scenarios. System costs increase when Jim Bridger
Units 3 and 4 retire early in the MM, LN, and MN price-policy scenarios. Conversely, costs
decrease in the HH and SCGHG price-policy scenarios. If Jim Bridger Units 3 and 4 retire early,
emissions from PacifiCorp’s fossil-fueled resources are reduced by about 7%. While it is more
likely than not that there will be some form of policy taken to impute a cost or penalty on
greenhouse gas emissions, the company’s analysis captures this risk in its MM price policy
assumptions. In this case, early retirement of Jim Bridger Units 3 and 4 increases system costs by
$60 million on a risk-adjusted basis. And while emissions costs and risks are higher with continue
operation of Jim Bridger Units 3 and 4, there are many resource choices in the P02-MM portfolio
that greatly mitigate this risk. Further, considering that the early retirements were selected in 2026
(Jim Bridger Unit 3) and 2029 (Jim Bridger Unit 4), there is sufficient time to continue to evaluate
the potential early retirement of these two units in the 2023 IRP. This would be particularly
important if base case carbon prices are projected to increase from current levels. For these reasons,
the early retirement of Jim Bridger Units 3 and 4 is not included in the preferred portfolio.
($400)
($300)
($200)
($100)
$0
$100
$200
$300
$400
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Annual Change in Cost by Line Item
Coal & Gas Fixed Coal & Gas Variable
Proxy Resource Fixed Emissions
Net Market Transactions Transmission
$95
($150)
($100)
($50)
$0
$50
$100
$150
$200
20
2
1
20
2
2
20
2
3
20
2
4
20
2
5
20
2
6
20
2
7
20
2
8
20
2
9
20
3
0
20
3
1
20
3
2
20
3
3
20
3
4
20
3
5
20
3
6
20
3
7
20
3
8
20
3
9
20
4
0
Net Differnce In Total System Cost
Net Cost/(Benefit)Cumulative PVRR(d)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
289
Table 9.14 – PVRR(d) of the P02h-JB3-4 Retire Portfolio Relative to the P02-MM Portfolio
Under Varying Price-Policy Scenarios.
Portfolio Development Conclusions
P02-MM remains the top performing portfolio among the P02 variant portfolios and was further
assessed relative to CETA requirements, described further in a later section.
Preferred Portfolio Selection
Final Preferred Portfolio Selection
P02-MM entered the final evaluations as the top-performing portfolio for preferred portfolio
selection.
P02-MM was subsequently evaluated using the targets established by CETA4. CETA establishes
specific targets for utilities serving customers in Washington including:
• By 2025, utilities remove coal-fueled generation from Washington’s allocation of
electricity;5
• By 2030, Washington retail sales are carbon-neutral;
o 80 percent from long-term system resources6
o 20 percent from alternative compliance using purchase of Unbundled Renewable
Energy Credits (REC)7s;
• By 2045, Washington’s retail sales are 100 percent renewable and non-carbon-emitting
4 RCW 19.405
5 RCW 19.405.030(1)(a)
6 RCW 19.405.040(1)(a)(ii) requires utilities to “use electricity from renewable resources and non-emitting electric
generation in an amount equal to one hundred percent of the utilities retail electric loads over each multiyear
compliance period.”
7 RCW 19.405.020(38)
PVRR ($m)
ST PVRR + 5% of 95th
Stochastic ($m)ENS Average % of Load
CO2 Emissions 2021-
2040 (Thousand Tons)
P02-MM-MM $25,794 $26,151 0.0049%398,953
P02-MM-LN $22,592 $22,793 0.0054%436,134
P02-MM-MN $22,421 $22,609 0.0049%511,369
P02-MM-HH $28,779 $29,280 0.0049%368,551
P02-MM-SCGHG $39,639 $40,665 0.0094%208,650
P02h-MM-MM $25,889 $26,212 0.0050%369,493
P02h-MM-LN $22,972 $23,152 0.0054%405,192
P02h-MM-MN $22,873 $23,044 0.0050%472,422
P02h-MM-HH $28,604 $29,057 0.0051%341,025
P02h-MM-SCGHG $39,376 $40,349 0.0103%201,974
Change from P02-MM-MM $95 $60 0.0001%(29,460)
Change from P02-MM-LN $380 $359 0.0000%(30,942)
Change from P02-MM-MN $452 $435 0.0001%(38,947)
Change from P02-MM-HH ($175)($223)0.0002%(27,527)
Change from P02-MM-SCGHG ($262)($317)0.0009%(6,676)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
290
Evaluation of the P02-MM portfolio against the CETA targets required certain modeling
assumptions to account for uncertainties related to the future of interjurisdictional cost allocation
among the PacifiCorp states and resolution of outstanding CETA implementation issues.
PacifiCorp currently allocates costs and benefits, including resource costs and benefits, to
Washington according to the Washington Inter-Jurisdictional Allocation Methodology (WIJAM).
The WIJAM expires December 31, 2023, and negotiations are underway among all six states to
determine the next inter-jurisdictional allocation methodology. In addition to future inter-
jurisdictional uncertainty, certain CETA implementation issues remain unresolved. 8, 9
In addition to assumptions regarding how energy is allocated across PacifiCorp’s six-state system,
PacifiCorp also made assumptions regarding the amount of renewable and non-emitting resources
that is eligible to apply toward the 80 percent “primary” compliance obligation. For purposes of
meeting primary compliance, PacifiCorp assumed that eligible generation was limited to energy
generated from long-term resources located on PacifiCorp’s system where both the energy and
RECs were: 1) acquired at the same time; and 2) allocated to Washington customers under the
applicable interjurisdictional allocation mechanism.
By 2025, PacifiCorp will remove all coal-fired generation from Washington’s allocation of
electricity. By 2030, the Chehalis natural gas-fueled plant is the only Washington-located thermal
resource operating on the system; all other existing and new resources in the P02-MM top-
performing portfolio are renewable or non-emitting. Thus, all system energy allocated to
Washington from a renewable or non-emitting resource contributes to meeting the CETA targets.10
This includes the renewable and non-emitting resources in the P02-MM top-performing portfolio.
Upon evaluation relative to the 2030 CETA target, a shortfall of roughly 69 MW of annual capacity
was identified in 2030 (the highest shortfall year), with significantly smaller shortfalls identified
in the years between 2030-2033. Under a four-year compliance window for the time period 2030
– 2033, an average annual shortfall of 49 MW was identified. This shortfall is addressed with a
Washington-situs assigned 160 MW wind and solar resource co-located with storage located in
Yakima, Washington.
This shortfall includes lower capacity requirements from incremental demand-side management
resources specific to Washington identified from the P02-SCGHG portfolio. In 2030, there was a
reconfiguration of 160 MW of system solar collocated with storage located in Yakima,
Washington in P02-MM, the top-performing portfolio, to become a Washington-situs assigned
160 MW resource that also includes wind, collocated with the solar and storage resource. This
Washington-situs assigned resource maximizes usage of transmission interconnection availability
at this location.
8 PacifiCorp is a multi-state utility, serving customers in California, Idaho, Oregon, Utah, Washington, and
Wyoming. PacifiCorp operates and plans its system on an integrated, six-state basis.
9 For existing resources and new resources added through the end of 2023, the energy from system resources was
allocated to states consistent with the 2020 Protocol and Washington Inter-Jurisdictional Allocation
Methodology. For resources added to the system in 2024 and beyond, assignment of energy, costs and benefits
followed a potential framework, subject to the ongoing Multi-State Process discussions, that enables compliance
with CETA (and Oregon law) through reassignment of certain thermal resources. These resource allocation
assumptions are used to assess the generation and allocation of Renewable Energy Credits (REC) state Renewable
Portfolio Standard (RPS) compliance.
10 This is limited to system energy where Washington is also allocated the associated RECs.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
291
These portfolio differences to P02-MM to meet the requirements of CETA result in the 2021 IRP
preferred portfolio, P02-MM-CETA. As CETA establishes a target in 2045 that retail sales are 100
percent renewable or non-emitting that is outside of the 20-year IRP planning horizon,
extrapolation was done that shows the P02-MM-CETA preferred portfolio meets the requirements.
The P02-MM-CETA results in a PVRR(d) relative to P02-MM, the top-performing portfolio is
$164m.
Table 9.15 - PVRR(d) of the P02-MM-CETA Portfolio Under Varying Price-Policy Scenarios
below shows the PVRR and risk-adjusted PVRR, ENS as a percentage of load, and CO2 emissions
for the 2021 IRP preferred portfolio under five price-policy scenarios.
Table 9.15 - PVRR(d) of the P02-MM-CETA Portfolio Under Varying Price-Policy Scenarios
Customer Rate Pressure
Figure 9.30 shows the difference in the cumulative PVRR, as an indicator of rate pressure over
time, among the initial portfolios discussed earlier in this chapter relative to the 2021 IRP preferred
portfolio, P02-MM-CETA applying medium gas, medium CO2 price-policy assumptions. All
Portfolios P03, BAU1 and BAU2 trend higher in costs over the planning horizon relative to P02-
MM-CETA whereas P02 trends lower in costs notably, as it does not include Washington-situs
assigned resources relative to the requirements of CETA.
Case ST PVRR
($m)
Risk-Adjusted
PVRR
($m)
ENS Average
Percent of
Load
CO2
Emissions
(Thousand
Tons)
P02-MM-CETA-LN 22,773 22,974 0.0054%436,414
P02-MM-CETA-MN 22,605 22,793 0.0049%510,115
P02-MM-CETA 25,963 26,315 0.0049%398,597
P02-MM-CETA-HH 28,951 29,448 0.0049%368,927
P02-MM-CETA-SC 39,910 40,934 0.0103%213,233
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
292
Figure 9.30 – Change in the Cumulative PVRR relative to P02-MM-CETA
The 2021 IRP Preferred Portfolio
PacifiCorp’s selection of the 2021 IRP preferred portfolio, P02-MM-CETA, is supported by
comprehensive data analysis and an extensive public-input process, described in the chapters that
follow. Figure 9.31 shows that PacifiCorp’s 2021 preferred portfolio continues to include
substantial new renewables, facilitated by incremental transmission investments, DSM resources,
significant storage resources, and for the first time, advanced nuclear.
By the end of 2024, the 2021 IRP preferred portfolio includes the 2020 All-Source RFP final
shortlist resources. These projects include 1,792 MW of wind, 1,302 MW of solar additions, and
697 MW of battery storage capacity—497 MW paired with solar and a 200 MW standalone
battery. During this time, the preferred portfolio also includes the acquisition and repowering of
Rock River I (49 MW) and Foote Creek II-IV (43 MW) wind projects located in Wyoming.
Through the end of 2026, the 2021 IRP preferred portfolio includes an additional 745 MW of wind
and an additional 600 MW solar co-located with storage. The 2021 IRP preferred portfolio includes
the 500 MW advanced nuclear NatriumTM demonstration project, which will come online by
summer 2028. Through 2040, the 2021 IRP preferred portfolio includes 1,000 MW of additional
advanced nuclear resources and 1,226 MW of non-emitting peaking resources.
Over the 20-year planning horizon, the 2021 IRP preferred portfolio includes 3,628 MW of new
wind and 5,628 MW of new solar co-located with storage.
($500)
($250)
$0
$250
$500
$750
$1,000
$1,250
$1,500
$1,750
$2,000
$2,250
$
M
i
l
i
o
n
s
P02-MM P03-MM BAU1-MM BAU2-MM
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
293
Figure 9.31 – 2021 IRP Preferred Portfolio (All Resources)
To facilitate the delivery of new renewable energy resources to PacifiCorp customers across the
West, the preferred portfolio includes additional transmission investment. Specifically, the 2021
IRP preferred portfolio includes the GWS—a new 416-mile, high-voltage 500-kilovolt
transmission line and associated infrastructure running from the new Aeolus substation near
Medicine Bow, Wyoming, to the Clover substation near Mona, Utah. The 2021 preferred portfolio
also includes the D.1 transmission line—a new 59-mile high-voltage 230-kilovolt transmission
line from the Shirley Basin substation in southeastern Wyoming to the Windstar substation near
Glenrock, Wyoming. Both transmission lines will come online by the end of 2024.
The 2021 IRP preferred portfolio also includes a 290-mile high-voltage 500-kilovolt B2H
transmission line, which connects Boardman in Oregon to Hemming in Idaho. B2H is
expected to come online in 2026. Further, the 2021 IRP preferred portfolio includes near-term
and long-term transmission upgrades across the system that will facilitate continued and long-
term growth in new resources needed to serve our customers. Table 9.16 summarizes the
incremental transmission projects included in the 2021 IRP preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
294
Table 9.16 – Transmission Projects Included in the 2021 IRP Preferred Portfolio1,2,*
1 - TTC = total transfer capability. The scope and cost of transmission upgrades are planning estimates. Actual scope and costs will
vary depending upon the interconnection queue, the transmission service queue, the specific location of any given generating
resource and the type of equipment proposed for any given generating resource.
2 - Energy Gateway South is modeled in the 2021 IRP as a contingent option with bids in the 2020 All-Source Request for Proposals.
Other transmission options prior to 2026 are not modeled as transmission requirements and costs are accounted for in the 2020 All-
Source Request for Proposals transmission cluster study for all other resource bids.
* - Reclaimed transmission is committed with resources with a commercial operation date later than the date of retirement.
New Solar Resources
The 2021 IRP preferred portfolio includes 1,302 MW of new solar by the end of 2024 and 1,902
MW by the end of 2026. Through 2040, more than 5,600 MW of new solar is online as shown in
Figure 9.32.
Year Resource(s)From To Description
2025 1,641 MW RFP Wind (2025)Aeolus WY Clover Enables 1,930 MW of interconnection with 1700
MW of TTC: Energy Gateway South
2026 615 MW Wind (2026)Enables 615 MW of interconnection: Albany OR area
reinforcement
130 MW Wind (2026)
450 MW Wind (2032)
650 MW Battery (2037)
2026 600 MW Solar+Storage (2026)Borah-Populous Hemingway Enables 600 MW of interconnection with 600 MW
of TTC: B2H Boardman-Hemingway
2028 41 MW Solar+Storage (2028)
377 MW Solar+Storage (2030)
Enables 460 MW of interconnection: Medford area
reinforcement
2030 160 MW Solar+Wind+Storage (2030)
20 MW Solar+Storage (2030)
Enables 180 MW of interconnection: Yakima local
area reinforcement
2031 820 MW Solar+Storage (2031)
206 MW Non-Emitting Peaker (2033)
Enables 1040 MW of interconnection: Northern UT
345 kV reinforcement
2033 400 MW Non-Emitting Peaker (2033)
1100 MW Solar+Storage (2033)Southern UT Northern UT
Enables 1500 MW of interconnection with 800 MW
TTC: Spanish Fork - Mercer 345 kV; New Emery –
Clover 345 kV
Reclaimed transmission upon retirement of Dave
Johnston Plant
2028*500 MW Adv Nuclear (2028)Southwest Wyoming
Transmission Area
Reclaimed transmission upon retirement of Naughton
1 & 2
Transmission Area
Bridger WY
2029*549 MW Battery (2029)Eastern Wyoming
Transmission Area
2026
Within Willamette Valley OR Transmission Area
2040 Central OR Willamette Valley
Within Southern OR Transmission Area
156 MW Solar+Storage (2040)
500 MW Pumped Storage (2040)
Enables 2080 MW of interconnection with 1950
MW TTC; Portland Coast area reinforcement,
Willamette Valley and Southerm Oregon
Yakima WA Transmission Area
Northern UT Transmission Area
Portland North Coast
Willamette Valley
Southern Oregon
Enables 980 MW of interconnection with 1500 MW
of TTC
Reclaimed transmission upon retirement of Wyodak Transmission Area
2037 909 MW Solar+Storage (2037)Reclaimed transmission upon retirement of
Huntington 1 & 2
2038 412 MW Non-Emitting Peaker (2038)
1000 MW Adv Nuclear (2038)Transmission Area
2040 206 MW Non-Emitting Peaker (2040)
60 MW Wind (2040)
Eastern Wyoming
Reclaimed transmission upon retirement of Jim
Bridger Plant
Southern Utah
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
295
Figure 9.32 – 2021 IRP Preferred Portfolio New Solar Capacity*
*Note: 2021 IRP solar capacity shown in the figure includes solar resources coming via the 2020 All-Source Request
for Proposals by the end of 2024. Resources are shown in the first full year of operation (the year after the year-online
dates).
New Wind Resources
As shown in Figure 9.33, by the end of 2024, PacifiCorp’s 2021 IRP preferred portfolio includes
1,792 MW of new wind generation resulting from the 2020 All-Source RFP and the acquisition
and repowering of Rock River I (49 MW) and Foote Creek II-IV (43 MW). Through the end of
2026, the 2021 IRP preferred portfolio includes an additional 745 MW of new wind and more than
3,700 MW of new wind by 2040.
Figure 9.33 – 2021 IRP Preferred Portfolio New Wind Capacity*
*Note: Wind additions shown are incremental to Energy Vision 2020 and other projects that have come online over
the past few years. Resources are shown in the first full year of operation (the year after year-end online dates).
New Storage Resources
New storage resources in the 2021 IRP preferred portfolio are summarized in Figure 9.34. The
2021 IRP preferred portfolio includes nearly 700 MW of battery storage by the end of 2024 – 200
MW of which is a standalone battery and the remaining portion paired with solar resources
resulting from the 2020 All-Source RFP. Through 2040, the 2021 IRP includes 4,781 MW of
storage co-located with solar resources,1,400 MW of standalone battery, and 500 MW of pumped
hydro.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
296
Figure 9.34 – 2021 IRP Preferred Portfolio New Storage Capacity*
*Note: Resources are shown in the first full year of operation (the year after the year-end online dates).
Other Non-Emitting Resources
This is the first PacifiCorp IRP that includes new advanced nuclear and non-emitting peaking
resources as part of its least-cost, least-risk preferred portfolio. As shown in Figure 9.35, the 500
MW advanced nuclear NatriumTM demonstration project will come online by summer 2028.
Through 2040, the 2021 IRP preferred portfolio includes 1,000 MW of additional advanced
nuclear resources and 1,226 MW of non-emitting peaking resources.
Figure 9.35 – 2021 IRP Other Non-Emitting Resources Capacity
*Note: Resources are shown in the first full year of operation (the year after the year-end online dates).
Demand-Side Management
PacifiCorp evaluates new DSM opportunities, which includes both energy efficiency and direct
load control programs, as a resource that competes with traditional new generation and wholesale
power market purchases when developing resource portfolios for the IRP. Consequently, the load
forecast used as an input to the IRP does not reflect any incremental investment in new energy
efficiency programs; rather, the load forecast is reduced by the selected additions of energy
efficiency resources in the IRP. Figure 9.36 shows that PacifiCorp’s load forecast before
incremental energy efficiency savings has increased relative to projected loads used in the 2019
IRP. On average, forecasted system load is up 2.2 percent and forecasted coincident system peak
is up 1.1 percent when compared to the 2019 IRP. Over the planning horizon, the average annual
growth rate, before accounting for incremental energy efficiency improvements, is 1.21 percent
for load and 0.73 percent for peak. Changes to PacifiCorp’s load forecast are driven by higher
projected demand from data centers driving up the commercial forecast and an increased
residential forecast.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
297
Figure 9.36 – Load Forecast Comparison between Recent IRPs (Before Incremental Energy
Efficiency Savings)
DSM resources continue to play a key role in PacifiCorp’s resource mix. Figure 9.37 compares
total energy efficiency capacity savings in the 2021 IRP preferred portfolio relative to the 2019
IRP preferred portfolio and includes 4,290 MW by the end of the planning period.
In addition to continued investment in energy efficiency programs, the preferred portfolio shows
an increasing role for incremental direct load control programs. The chart to the right in Figure
9.37 compares cumulative capacity of direct load control program capacity in the 2021 IRP
preferred portfolio relative to the 2019 IRP preferred portfolio and does not include capacity from
existing programs. In the 2021 IRP, direct load control resources previously identified in the 2019
IRP and solicited via a demand response RFP, were modeled in addition to resources from the
CPA assessing the upper limit of demand response opportunities and value within the IRP. This
allowed for the evaluation of real-time resources as a substitute for front office transactions. The
2021 IRP has a cumulative capacity of direct load control programs reaching 2,448 MW by 2040—
an over 400% increase over the planning horizon from the 2019 IRP.
Figure 9.37 – 2021 IRP Preferred Portfolio Energy Efficiency (Class 2 DSM) and Direct Load
Control Capacity (Class 1 DSM)
Wholesale Power Market Prices and Purchases
Figure 9.38 shows that the 2021 IRP’s base case forecast for natural gas prices has decreased along
with a decrease in wholesale power prices for most years relative to those in the 2019 IRP. These
forecasts are based on prices observed in the forward market and on projections from third-party
experts. The lower power prices observed in the 2021 IRP are primarily driven by the assumption
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
298
of lower natural gas prices than what was assumed in the 2019 IRP. Wholesale power prices are
higher in 2027 to 2031 because of higher inflation impacting new resource costs. Moreover, the
2021 IRP assumed lower natural gas prices than the 2019 IRP as Henry Hub in particular, is
softened by limited pipeline expansion lowering liquefied natural gas exports. While not shown in
the figure below, the 2021 IRP also evaluated low and high price scenarios when evaluating the
cost and risk of different resource portfolios.
Figure 9.38 – Comparison of Power Prices and Natural Gas Prices in Recent IRPs
Figure 9.39 shows an overall decline in reliance on wholesale power market firm purchases in the
2021 IRP preferred portfolio relative to the wholesale power market purchases included in the
2019 IRP preferred portfolio. In particular, reliance on wholesale power market purchases during
summer peak periods averages 366 MW per year over the 2020-2027 timeframe—down 60 percent
from wholesale power market purchases identified in the 2019 IRP preferred portfolio. This
reduction in wholesale power market purchases coincides with the period over which there are
resource adequacy concerns in the region. Further, PacifiCorp is actively participating in regional
efforts to develop day-ahead markets and a resource adequacy program that will help unlock
regional diversity and facilitate market transactions over the long term.
Figure 9.39 – 2021 IRP Preferred Portfolio Market Purchases
Coal and Gas Retirements/Gas Conversions
Coal resources have been an important resource in PacifiCorp’s resource portfolio for many
years. However, there have been material changes in how PacifiCorp has been operating these
assets (i.e., by lowering operating minimums and optimizing dispatch through the EIM) that
has enabled the company to reduce fuel consumption and associated costs and emissions, and
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
299
instead buy increasingly low-cost, zero-emissions renewable energy from market participants
across the West, which is accessed by our expansive transmission grid. PacifiCorp’s coal
resources will continue to play a pivotal role in following fluctuations in renewable energy as
the remaining coal units approach retirement dates. Driven in part by ongoing cost pressures
on existing coal-fired facilities and dropping costs for new resource alternatives, of the 22 coal
units currently serving PacifiCorp customers, the preferred portfolio includes retirement of 14
of the units by 2030 and 19 of the units by the end of the planning period in 2040. As shown
in Figure 9.40, coal unit retirements/gas peaker conversions in the 2021 IRP preferred portfolio
will reduce coal-fueled generation capacity by 1,300 MW by the end of 2025, over 2,200 MW
by 2030, and over 4,000 MW by 2040.
Coal unit retirements scheduled under the preferred portfolio include:
• 2023 = Jim Bridger Units 1-2, converted to natural gas peakers in 2024 (same retirement
year for Jim Bridger 1 in 2019 IRP and instead of 2028 for Jim Bridger 2 in the 2019 IRP).
• 2025 = Naughton Units 1-2 (same as 2019 IRP)
• 2025 = Craig Unit 1 (same as 2019 IRP)
• 2025 = Colstrip Units 3-4 (instead of 2027 in the 2019 IRP)
• 2027 = Dave Johnston Units 1-4 (same as 2019 IRP)
• 2027 = Hayden Unit 2 (instead of 2030 in the 2019 IRP)
• 2028 = Craig Unit 2 (instead of 2026 in the 2019 IRP)
• 2028 = Hayden Unit 1 (instead of 2030 in the 2019 IRP)
• 2036 = Huntington Units 1-2 (same as 2019 IRP)
• 2037 = Jim Bridger Units 3-4 (same as 2019 IRP)
• 2039 = Wyodak (same as 2019 IRP but outside of 2019 IRP planning horizon)
Figure 9.40 – 2021 IRP Preferred Portfolio Coal Retirements/Gas Conversions*
* Note: Coal retirements are assumed to occur by the end of the year before the year shown in the graph. The graph
shows the year in which the capacity will not be available for meeting summer peak load. All figures represent
PacifiCorp’s ownership share of jointly owned facilities.
In addition to the coal unit retirements outlined above, the preferred portfolio reflects 1,554 MW
natural gas retirements through 2040. This includes Naughton Unit 3 at the end of 2029, Gadsby
at the end of 2032, Hermiston at the end of 2036, and Jim Bridger Units 1 and 2 at the end of 2037.
Carbon Dioxide Emissions
The 2021 IRP preferred portfolio reflects PacifiCorp’s on-going efforts to provide cost-effective
clean-energy solutions for our customers and accordingly reflects a continued trajectory of
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
300
declining carbon dioxide (CO2) emissions. PacifiCorp’s emissions have been declining and
continue to decline related to several factors including PacifiCorp’s participation in the EIM,
which reduces customer costs and maximizes use of clean energy; PacifiCorp’s on-going transition
to clean-energy resources including new renewable resources, new advanced nuclear resources,
new non-emitting resources, storage, transmission, and Regional Haze compliance that capitalizes
on flexibility.
The chart on the left in Figure 9.41 compares projected annual CO2 emissions between the 2021
IRP and 2019 IRP preferred portfolios. In this graph, emissions are not assigned to market
purchases or sales, and in 2026, annual CO2 emissions are down 26 percent relative to the 2019
IRP preferred portfolio. By 2030, average annual CO2 emissions are down 34 percent relative to
the 2019 IRP preferred portfolio, and down 52 percent in 2035. By the end of the planning horizon,
system CO2 emissions are projected to fall from 39.1 million tons in 2021 to 4.8 million tons in
2040—a reduction of 88 percent.
The chart on the right in Figure 9.41 includes historical data, assigns emissions at a rate of 0.4708
tons CO2 equivalent per MWh to market purchases (with no credit to market sales), includes
emissions associated with specified purchases, and extrapolates projections out through 2050. This
graph demonstrates that relative to a 2005 baseline, system CO2 equivalent emissions are down 53
percent in 2025, 74 percent in 2030, 83 percent in 2035, 92 percent in 2040, 94 percent in 2045,
and 98 percent in 2050.
Figure 9.41 – 2021 IRP Preferred Portfolio CO2 Emissions and PacifiCorp CO2 Equivalent
Emissions Trajectory*
*Note: PacifiCorp CO2 equivalent emissions trajectory reflects actual emissions through 2020 from owned facilities,
specified sources and unspecified sources. From 2021 through the end of the twenty-year planning period in 2040,
emissions reflect those from the 2021 IRP preferred portfolio with emissions from specified sources reported in CO2
equivalent. Market purchases are assigned a default emission factor (0.4708 short tons CO2e/MWh) – emissions from
sales are not removed. Beyond 2040, emissions reflect the rolling average emissions of each resource from the 2021
IRP preferred portfolio through the life of the resource. The emissions trajectory does not incorporate clean energy
targets set forth in Oregon House Bill 2021 or any other state-specific emissions trajectories. PacifiCorp expects these
targets, and an Oregon-specific emissions trajectory, to be incorporated following the 2023 integrated resource plan
when PacifiCorp is required under the bill to file a Clean Energy Plan.
Monthly CO2 emissions are available for the preferred portfolio as shown in Figure 9.42 below.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
301
Figure 9.42 – Monthly CO2 emissions per year for the preferred portfolio
Renewable Portfolio Standards
Figure 9.43 shows PacifiCorp’s renewable portfolio standard (RPS) compliance forecast for
California, Oregon, and Washington after accounting for new renewable resources in the preferred
portfolio. While these resources are included in the preferred portfolio as cost-effective system
resources and are not included to specifically meet RPS targets, they nonetheless contribute to
meeting RPS targets in PacifiCorp’s western states.
Oregon RPS compliance is achieved through 2040 with the addition of new renewable resources
and transmission in the 2021 IRP preferred portfolio. Washington RPS compliance is achieved
with the benefit of increased system renewable resources beginning 2021 as well as additional
resources procured that meet the state’s Clean Energy Transformation Act. Under PacifiCorp’s
2020 Protocol, and the Washington Interjurisdictional Allocation Methodology, Washington’s
RPS position is improved by receiving a system share of renewable resources across the
PacifiCorp’s system.
The California RPS compliance position will be met with owned and contracted renewable
resources, as well as REC purchases throughout the 2021 IRP study period. The ramping RPS
requirement results in an increased need for unbundled REC purchases to meet the annual and
compliance period targets in 2021-2040. New renewable resources and transmission in the 2021
IRP preferred portfolio mitigate that shortfall, but the company may need to purchase
approximately 200,000 RECs in compliance periods 4 and 5, 2021-2024 and 2025-2028,
respectively. Beyond 2028, the company may need to purchase 200,000-300,000 RECs per year
to meet the ramping RPS.
0
1
1
2
2
3
3
4
4
5
To
n
s
(
m
i
l
l
i
o
n
s
)
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
302
While not shown in Figure 9.43, PacifiCorp meets the Utah 2025 state target to supply 20 percent
of adjusted retail sales with eligible renewable resources with existing owned and contracted
resources and new renewable resources and transmission in the 2021 IRP preferred portfolio.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
303
Figure 9.43 – Annual State RPS Compliance Forecast
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
RE
C
s
(
T
h
o
u
s
a
n
d
s
)
Oregon RPS
Unbundled Surrendered Bundled SurrenderedUnbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement
0
200
400
600
800
RE
C
s
(
T
h
o
u
s
a
n
d
s
)
California RPS
Unbundled Surrendered Bundled SurrenderedUnbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement
0
500
1,000
1,500
2,000
RE
C
s
(
T
h
o
u
s
a
n
d
s
)
Washington RPS
Unbundled Surrendered Bundled SurrenderedUnbundled Bank Surrendered Bundled Bank SurrenderedYear-end Unbundled Bank Balance Year-end Bundled Bank BalanceShortfallRequirement
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
304
Capacity and Energy
Figure 9.44 displays how preferred portfolio resources meet PacifiCorp’s capacity needs over time.
Through 2040, PacifiCorp meets its capacity needs, including a 13% planning reserve margin,
through incremental acquisition of wind and solar resources and hybrid renewables (with storage)
enabled by investment in transmission infrastructure, nuclear resources, strand alone storage
resources, new DSM, non-emitting peaker resources, and wholesale power market purchases.
Figure 9.44 – Meeting PacifiCorp’s Capacity Needs with Preferred Portfolio Resources
Figure 9.45 and Figure 9.46 show how PacifiCorp’s system energy and nameplate capacity mix is
projected to change over time. In developing these figures, purchased power is reported in
identifiable resource categories where possible. Energy mix figures are based upon base price
curve assumptions. Renewable capacity and generation reflect categorization by technology type
and not disposition of renewable energy attributes for regulatory compliance requirements.11 On
an energy basis, coal generation drops to 25 percent by 2027, falls to 9 percent by 2032, and
declines to only 1 percent by the end of the planning period. On a capacity basis, coal resources
drop to 18 percent by 2027, fall to 11 percent by 2032, and decline to 3 percent by the end of the
11The projected PacifiCorp 2021 IRP preferred portfolio “energy mix” is based on energy production and not
resource capability, capacity or delivered energy. All or some of the renewable energy attributes associated with
wind, biomass, geothermal and qualifying hydro facilities in PacifiCorp’s energy mix may be: (a) used in future
years to comply with renewable portfolio standards or other regulatory requirements; (b) sold to third parties in the
form of renewable energy credits or other environmental commodities; or (c) excluded from energy purchased.
PacifiCorp’s 2021 IRP preferred portfolio energy mix includes owned resources and purchases from third parties.
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Me
g
a
w
a
t
t
s
Existing - Physical Assets ***Existing - Long Term Contracts, PPA's and DSM
Nuclear Storage **
Firm Market Purchases Renewables
DSM Non-Emitting Peakers
Obligation + Reserves *
Existing -Physical Assets ***
Existing -Long Term
Contracts, PPA's and DSM
New -DSMFirm Market
Purchases
Obligation + Reserves *
* Includes 13% Capacity Reserve Margin, Sales and Non-Owned Reserves
** Includes the storage component of wind and solar collocated with storage
*** Includes retirements, and gas conversions
Storage **
Non-Emitting
Peakers
Nuclear
Renewables
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
305
planning period. Reduced energy and capacity from coal is offset primarily by increased energy
and capacity from renewable and storage resources, nuclear resources, DSM resources, and to a
smaller extent later in the plan, non-emitting peaker resources.
Figure 9.45 – Projected Energy Mix with Preferred Portfolio Resources.
Figure 9.46 – Projected Capacity Mix with Preferred Portfolio Resources
Detailed Preferred Portfolio
Table 9.17 provides line-item detail of PacifiCorp’s 2021 IRP preferred portfolio showing new
resource capacity along with changes in existing resource capacity through the 20-year planning
horizon. Table 9.18 shows line-item detail of PacifiCorp’s peak load and resource capacity balance
for summer, including preferred portfolio resources, over the 20-year planning horizon. Table 9.19
shows line-item detail of PacifiCorp’s peak load and resource capacity balance for winter,
including preferred portfolio resources, over the twenty-year planning horizon.
49%47%43%42%
29%26%25%20%18%15%11%9%8%7%6%6%5%1%1%1%
12%13%17%12%
15%12%13%13%13%12%12%13%11%11%11%12%10%10%11%10%
5%5%4%
4%
4%
4%4%4%4%4%3%3%3%3%3%3%3%3%3%3%
4.1%4.0%3.9%3.8%3.7%3.6%3.6%3.5%3.5%3.4%8.3%8.3%8.0%
1.2%
1.6%1.5%1.5%3.3%3.0%3.2%3.3%2.8%3.0%3.0%3.1%2.2%2.5%2.4%2.0%
24%24%26%31%
41%47%46%46%45%49%53%54%58%57%57%56%58%56%56%56%
3%3%4%4%5%6%6%7%7%8%8%8%9%9%9%10%10%11%
1.9%1.9%1.8%1.8%1.6%1.4%1.5%1.4%1.6%1.6%1.6%1.5%1.5%1.5%1.5%1.5%1.5%1.5%1.5%1.5%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Coal Gas Existing Purchases Hydroelectric
Nuclear Storage Renewable Energy Efficiency
Demand Response Non-Emitting Peaker Front Office Transactions
31%31%30%26%22%18%18%15%14%12%11%11%9%9%9%9%7%3%3%3%
18%18%18%
15%13%
12%12%12%11%9%8%8%6%6%6%6%5%5%5%5%
8%8%7%
6%
5%
4%4%4%4%4%3%3%3%3%3%3%3%3%3%3%
1.9%1.8%1.7%1.5%1.4%1.3%1.3%1.2%1.2%1.2%3.4%3.4%3.3%
2.2%
3.0%5.0%4.9%5.0%6.9%8.1%9.6%9.4%11.1%11.0%10.9%10.8%13.9%13.7%13.2%14.2%
34%32%34%39%46%51%50%50%48%51%53%52%54%53%53%52%53%52%52%51%
3%4%4%4%5%6%7%7%7%8%8%8%9%9%9%9%10%10%
3.5%4.3%5.5%5.7%5.2%4.9%5.1%5.4%5.5%5.3%4.9%5.0%4.9%5.0%5.4%5.7%5.7%6.0%6.2%6.7%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Coal Gas Existing Purchases Hydroelectric
Nuclear Storage Renewable Energy Efficiency
Demand Response Non-Emitting Peaker Front Office Transactions
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
306
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
307
Table 9.17 – PacifiCorp’s 2021 IRP Preferred Portfolio
Summary Portfolio Capacity by Resource Type and Year, Installed MW
Installed Capacity, MW
Resource 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Total
Expansion Options
Gas - CCCT - - - - - - - - - - - - - - - - - - - - -
Gas- Peaking - - - - - - - - - - - - - - - - - - - - -
NonEmitting Peaker - - - - - - - - - - - - 402 - - - - 618 - 206 1,226
DSM - Energy Efficiency 157 138 144 164 186 211 238 263 279 304 301 293 272 249 221 195 189 171 160 156 4,290
DSM - Demand Response - 123 242 184 79 63 69 80 78 77 82 50 213 70 160 125 183 159 108 302 2,448
Renewable - Wind 49 - 151 43 1,641 745 - - - 489 - 450 - - - - - - - 60 3,628
Renewable - Wind+Storage - - - - - - - - - 160 - - - - - - - - - - 160
Renewable - Utility Solar - - - 95 - - - - - - - - - - - - - - - - 95
Renewable - Utility Solar+Storage - - - 752 455 600 - 83 - 558 820 - 1,100 - - - 1,009 - - 156 5,533
Renewable - Battery, Wind+Storage - - - - - - - - - - - - - - - - - - - - -
Renewable - Battery, Solar+Storage - - - 239 258 600 - 42 - 558 820 - 1,100 - - - 1,009 - - 156 4,781
Renewable - Geothermal - - - - - - - - - - - - - - - - - - - - -
Battery - Stand Alone - - - 200 - - - - 549 1 - - - - - - 650 - - - 1,400
Storage - CAES - - - - - - - - - - - - - - - - - - - - -
Storage - Pumped Hydro - - - - - - - - - - - - - - - - - - - 500 500
Nuclear - - - - - - - 345 - - - - - - - - - 690 - - 1,035
Nuclear Storage - - - - - - - 155 - - - - - - - - - 310 - - 465
Front Office Transactions 385 412 427 383 498 231 287 285 363 394 395 459 538 703 578 747 863 1,025 1,052 1,176 560
Existing Unit Changes
Coal Plant End-of-life Retirements - - - - - (230) - (788) (123) - - - - - - - (909) (699) - (268) (3,018)
Coal Early Retirements - - - - - (357) - - - - - - - - - - - - - - (357)
Coal - CCUS - - - - - - - - - - - - - - - - - - - - -
Coal - Gas Conversions - - - 713 - - - - - - - - - - - - - (713) - - -
Coal Plant ceases running as Coal - - - (713) - - - - - - - - - - - - - - - - (713)
Gas Plant End-of-life Retirements - - - - - - - - - (247) - - (356) - - - (237) - - - (840)
Retire - Hydro - - (163) - - - - - - - - - - - - - - - - - (163)
Retire - Wind - (10) - - - - - - - - - - - - - - - - - - (10)
Expire - Wind PPA - - - (41) - (65) - - (99) (200) - - - - - - - - - - (405)
Retire - Solar - - - - - - - - - - - - - - - - (18) - - - (18)
Expire - Solar PPA - - - - - - - (2) - - - (8) - - - - (73) - - - (83)
Expire - QF - (2) - (50) - - (29) - (83) (0) - (81) (181) (91) (19) (208) (744) (30) (100) (92) (1,712)
Retire - Other - - - - - - - - - - - - - - - - - (32) - - (32)
Expire - Other - 11 - 32 (91) - - - - - - - - - - - - - - - (49)
Total 591 673 802 2,001 3,025 1,798 565 463 964 2,094 2,419 1,162 3,088 931 940 858 1,923 1,497 1,220 2,350
PACIFICORP – 2021 IRP CHAPTER 9 - MODELING AND PORTFOLIO SELECTION RESULTS
308
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
309
Table 9.18 – Preferred Portfolio Summer Capacity Load and Resource Balance (2021-2030)
East
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Thermal 5,478 5,466 5,429 5,425 5,459 5,044 5,002 4,293 4,182 3,953
Hydroelectric 86 86 85 69 56 52 51 56 57 52
Renewable 668 690 815 912 709 676 661 718 743 676
Purchase 193 197 202 195 138 141 142 148 143 147
Qualifying Facilities 537 521 515 488 396 357 344 364 372 346
Sale (20)(20)(20)0 0 0 0 0 0 0
East Existing Resources 6,943 6,940 7,026 7,090 6,758 6,271 6,201 5,580 5,498 5,174
Front Office Transactions 0 0 0 0 0 0 0 0 0 0
NonEmitting Peaker 0 0 0 0 0 0 0 0 0 0
Wind 6 6 35 47 298 280 283 331 328 387
Wind+Storage 0 0 0 0 0 0 0 0 0 0
Solar 0 0 0 32 25 24 24 27 27 25
Solar+Storage 0 0 0 334 513 388 377 401 397 350
Storage 1 1 1 148 104 58 56 50 162 126
Nuclear 0 0 0 0 0 0 0 248 250 224
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
East Planned Resources 7 7 36 561 940 750 740 1,056 1,164 1,112
East Total Resources 6,950 6,947 7,062 7,651 7,698 7,020 6,940 6,636 6,661 6,286
Load 7,096 7,246 7,380 7,475 7,583 7,492 7,550 7,643 7,728 7,833
Private Generation (51)(72)(81)(84)(87)(90)(96)(106)(119)(136)
Existing - Demand Response (520)(538)(558)(538)(583)(592)(598)(623)(604)(619)
New Demand Response 0 (86)(192)(231)(274)(301)(329)(375)(397)(438)
Existing - Energy Efficiency (43)(45)(46)(45)(49)(49)(50)(52)(50)(52)
New Energy Efficiency (48)(95)(149)(199)(280)(349)(429)(529)(597)(698)
East Total obligation 6,434 6,410 6,353 6,378 6,311 6,110 6,048 5,958 5,961 5,890
East Reserve Margin 8%8%11%20%22%15%15%11%12%7%
West
Thermal 2,139 2,165 2,168 2,144 2,149 2,019 2,015 2,014 2,036 2,035
Hydroelectric 577 567 521 508 407 386 380 420 423 390
Renewable 194 177 185 184 148 139 140 144 144 134
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 158 153 145 141 116 105 87 91 79 71
Sale (109)(76)(76)(54)(44)(42)(41)(44)(44)(41)
West Existing Resources 2,961 2,986 2,945 2,924 2,777 2,608 2,582 2,626 2,638 2,591
Front Office Transactions 1,064 972 747 8 0 0 0 0 0 0
NonEmitting Peaker 0 0 0 0 0 0 0 0 0 0
Wind 0 0 0 0 0 177 177 211 194 189
Wind+Storage 0 0 0 0 0 0 0 0 0 39
Solar 0 0 0 0 0 0 0 0 0 0
Solar+Storage 0 0 0 147 119 522 511 564 526 775
Storage 0 0 0 0 0 0 0 0 0 0
Nuclear 0 0 0 0 0 0 0 0 0 0
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
West Planned Resources 1,064 972 747 154 119 699 688 775 720 1,003
West Total Resources 4,025 3,959 3,691 3,079 2,897 3,307 3,270 3,401 3,358 3,594
Load 3,351 3,400 3,443 3,472 3,506 3,530 3,557 3,584 3,610 3,638
Private Generation (23)(39)(51)(56)(60)(65)(71)(78)(86)(96)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
New Demand Response 0 (45)(127)(179)(238)(276)(310)(355)(369)(411)
Existing - Energy Efficiency (24)(25)(26)(25)(27)(28)(28)(29)(28)(29)
New Energy Efficiency (26)(51)(76)(95)(126)(152)(178)(213)(234)(266)
West Total obligation 3,278 3,241 3,163 3,117 3,054 3,010 2,970 2,910 2,893 2,835
West Reserve Margin 23%22%17%-1%-5%10%10%17%16%27%
System
Total Resources 10,975 10,905 10,753 10,730 10,595 10,328 10,210 10,037 10,020 9,880
Obligation 9,712 9,651 9,516 9,495 9,366 9,120 9,017 8,868 8,854 8,726
Capacity Reverve Margin (13%)1,263 1,255 1,237 1,234 1,218 1,186 1,172 1,153 1,151 1,134
Obligation + Reserves 10,975 10,905 10,753 10,730 10,583 10,306 10,190 10,021 10,005 9,860
System Position 0 0 0 0 12 22 21 16 15 20
Reserve Margin 13%13%13%13%13%13%13%13%13%13%
PACIFICORP – 2021 IRP CHAPTER 9 - MODELING AND PORTFOLIO SELECTION RESULTS
310
Table 9.18 (cont’d) – Preferred Portfolio Summer Capacity Load and Resource Balance
(2031-2040)
East
2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Thermal 3,945 3,955 3,629 3,607 3,613 3,613 2,765 2,759 2,757 2,491
Hydroelectric 47 43 40 40 40 40 57 63 64 58
Renewable 582 525 471 465 465 465 587 595 586 539
Purchase 146 157 145 144 142 144 138 137 136 138
Qualifying Facilities 310 266 220 204 192 162 34 29 12 0
Sale 0 0 0 0 0 0 0 0 0 0
East Existing Resources 5,031 4,947 4,505 4,459 4,452 4,424 3,582 3,583 3,555 3,226
Front Office Transactions 0 0 0 0 0 0 0 0 0 0
NonEmitting Peaker 0 0 369 369 368 371 373 375 374 562
Wind 360 322 308 326 307 305 419 461 463 439
Wind+Storage 0 0 0 0 0 0 0 0 0 0
Solar 22 20 18 17 16 15 19 20 19 17
Solar+Storage 677 604 951 929 906 870 1,364 1,377 1,383 1,228
Storage 131 115 99 99 99 104 119 124 93 86
Nuclear 198 181 161 166 163 165 231 260 262 242
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
East Planned Resources 1,388 1,242 1,906 1,906 1,859 1,829 2,525 2,615 2,594 2,573
East Total Resources 6,419 6,189 6,411 6,365 6,311 6,253 6,107 6,199 6,149 5,799
Load 7,938 8,041 8,138 8,232 8,336 8,343 8,413 8,520 8,390 8,488
Private Generation (160)(189)(218)(251)(291)(181)(205)(230)(119)(132)
Existing - Demand Response (615)(660)(609)(604)(598)(607)(582)(579)(574)(581)
New Demand Response (468)(521)(570)(593)(627)(673)(705)(740)(771)(849)
Existing - Energy Efficiency (51)(55)(51)(50)(50)(51)(48)(48)(48)(48)
New Energy Efficiency (773)(906)(907)(962)(1,009)(1,039)(1,052)(1,111)(1,170)(1,248)
East Total obligation 5,871 5,710 5,784 5,771 5,762 5,792 5,820 5,812 5,707 5,630
East Reserve Margin 9%8%11%10%10%8%5%7%8%3%
West
Thermal 2,027 2,021 2,024 2,023 2,023 2,031 1,807 456 456 456
Hydroelectric 355 323 301 299 296 298 435 483 485 446
Renewable 117 108 105 92 92 100 129 142 143 128
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 64 49 45 39 37 38 25 22 9 6
Sale (38)(34)(32)(32)(32)(31)(34)(32)(32)(28)
West Existing Resources 2,527 2,468 2,443 2,422 2,417 2,435 2,364 1,072 1,061 1,009
Front Office Transactions 0 0 0 0 0 0 0 0 0 0
NonEmitting Peaker 0 0 0 0 0 0 0 573 573 577
Wind 168 241 230 239 228 248 338 371 374 348
Wind+Storage 39 32 31 31 33 33 45 49 50 47
Solar 0 0 0 0 0 0 0 0 0 0
Solar+Storage 670 594 515 503 489 484 576 584 587 583
Storage 0 0 0 0 0 0 78 84 95 387
Nuclear 0 0 0 0 0 0 0 508 509 475
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
West Planned Resources 877 868 775 773 750 765 1,038 2,168 2,188 2,417
West Total Resources 3,404 3,336 3,219 3,195 3,166 3,200 3,401 3,240 3,249 3,426
Load 3,676 3,707 3,740 3,773 3,805 3,752 3,793 3,825 3,758 3,782
Private Generation (118)(158)(205)(258)(316)(263)(305)(351)(195)(225)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
New Demand Response (441)(485)(461)(469)(488)(519)(512)(531)(544)(594)
Existing - Energy Efficiency (29)(31)(28)(28)(28)(28)(27)(27)(27)(27)
New Energy Efficiency (289)(334)(329)(348)(366)(388)(386)(410)(409)(414)
West Total obligation 2,800 2,699 2,717 2,669 2,607 2,554 2,563 2,507 2,584 2,521
West Reserve Margin 22%24%18%20%21%25%33%29%26%36%
System
Total Resources 9,823 9,524 9,630 9,560 9,477 9,453 9,509 9,438 9,398 9,225
Obligation 8,671 8,410 8,500 8,440 8,369 8,346 8,383 8,319 8,291 8,150
Capacity Reverve Margin (13%)1,127 1,093 1,105 1,097 1,088 1,085 1,090 1,081 1,078 1,060
Obligation + Reserves 9,798 9,503 9,605 9,537 9,457 9,431 9,473 9,400 9,369 9,210
System Position 25 22 25 23 21 22 35 38 29 15
Reserve Margin 13%13%13%13%13%13%13%13%13%13%
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
311
Table 9.19 – Preferred Portfolio Winter Capacity Load and Resource Balance (2021-2030)
East
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Thermal 5,478 5,383 5,540 5,364 5,550 5,057 5,143 4,229 4,140 3,835
Hydroelectric 50 52 46 43 30 31 29 39 42 42
Renewable 765 929 885 860 546 676 639 796 843 802
Purchase 173 169 167 158 115 116 120 125 110 113
Qualifying Facilities 204 225 192 213 105 136 123 208 227 233
Sale (16)(17)(15)0 0 0 0 0 0 0
Transfers (277)(267)(247)(535)(275)(79)(99)(588)(561)(369)
East Existing Resources 6,378 6,474 6,568 6,104 6,071 5,937 5,955 4,809 4,802 4,657
Front Office Transactions 0 0 0 0 0 0 0 0 0 0
NonEmitting Peaker 0 0 0 0 0 0 0 0 0 0
Wind 12 14 52 69 362 398 406 499 533 686
Wind+Storage 0 0 0 0 0 0 0 0 0 0
Solar 0 0 0 17 6 9 8 14 16 16
Solar+Storage 0 0 0 201 205 178 169 235 247 242
Storage 1 1 1 128 83 55 52 51 179 153
Nuclear 0 0 0 0 0 0 0 217 231 233
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
East Planned Resources 13 15 53 415 657 640 636 1,017 1,206 1,331
East Total Resources 6,391 6,489 6,621 6,518 6,728 6,577 6,591 5,825 6,008 5,987
Load 5,538 5,678 5,800 5,860 5,943 5,874 5,915 6,008 6,081 6,161
Private Generation (0)(1)(2)(2)(3)(4)(5)(6)(7)(8)
Existing - Demand Response (239)(251)(255)(252)(255)(258)(267)(277)(246)(251)
New Demand Response 0 (76)(164)(198)(218)(239)(268)(304)(293)(323)
Existing - Energy Efficiency (32)(33)(34)(33)(34)(34)(35)(37)(33)(33)
New Energy Efficiency (39)(74)(109)(143)(181)(213)(259)(309)(308)(356)
East Total obligation 5,229 5,244 5,237 5,231 5,251 5,127 5,081 5,076 5,195 5,189
East Reserve Margin 22%24%26%25%28%28%30%15%16%15%
West
Thermal 2,205 2,211 2,186 1,930 2,203 2,064 2,060 1,982 2,010 1,991
Hydroelectric 497 518 434 456 320 330 317 410 439 439
Renewable 105 75 69 86 56 63 52 84 92 95
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 53 50 45 54 37 36 19 39 36 33
Sale (88)(71)(59)(45)(32)(33)(32)(38)(41)(40)
Transfers 277 267 247 535 275 79 99 588 561 369
West Existing Resources 3,049 3,051 2,922 3,017 2,860 2,540 2,517 3,066 3,097 2,887
Front Office Transactions 163 62 5 0 0 0 0 0 0 0
NonEmitting Peaker 0 0 0 0 0 0 0 0 0 0
Wind 0 0 0 0 0 85 79 120 125 135
Wind+Storage 0 0 0 0 0 0 0 0 0 30
Solar 0 0 0 0 0 0 0 0 0 0
Solar+Storage 0 0 0 46 22 252 232 325 315 479
Storage 0 0 0 0 0 0 0 0 0 0
Nuclear 0 0 0 0 0 0 0 0 0 0
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
West Planned Resources 163 62 5 46 22 337 311 445 441 643
West Total Resources 3,212 3,113 2,927 3,063 2,882 2,878 2,828 3,511 3,538 3,530
Load 3,318 3,358 3,397 3,421 3,449 3,479 3,516 3,550 3,585 3,615
Private Generation (0)(0)(1)(1)(1)(1)(2)(2)(3)(3)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
New Demand Response 0 (33)(91)(129)(159)(186)(216)(248)(238)(263)
Existing - Energy Efficiency (23)(24)(24)(24)(24)(24)(25)(26)(23)(24)
New Energy Efficiency (25)(48)(69)(86)(105)(124)(149)(176)(176)(200)
West Total obligation 3,270 3,253 3,213 3,182 3,160 3,142 3,123 3,098 3,146 3,124
West Reserve Margin -2%-4%-9%-4%-9%-8%-9%13%12%13%
System
Total Resources 9,603 9,602 9,548 9,581 9,609 9,454 9,419 9,336 9,546 9,518
Obligation 8,498 8,497 8,450 8,412 8,411 8,269 8,205 8,174 8,341 8,314
Capacity Reverve Margin (13%)1,105 1,105 1,098 1,094 1,093 1,075 1,067 1,063 1,084 1,081
Obligation + Reserves 9,603 9,602 9,548 9,506 9,505 9,344 9,271 9,236 9,425 9,394
System Position 0 0 0 75 105 110 148 100 120 123
Reserve Margin 13%13%13%14%14%14%15%14%14%14%
PACIFICORP – 2021 IRP CHAPTER 9 - MODELING AND PORTFOLIO SELECTION RESULTS
312
Table 9.19 (cont’d) – Preferred Portfolio Winter Capacity Load and Resource Balance
(2031-2040)
East
2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Thermal 3,901 3,947 3,646 3,554 3,677 3,411 2,830 2,643 2,783 2,421
Hydroelectric 36 36 34 37 38 43 47 48 52 49
Renewable 665 662 620 668 703 752 782 756 832 778
Purchase 129 129 131 119 109 111 136 133 134 119
Qualifying Facilities 186 178 133 124 119 80 15 13 4 0
Sale 0 0 0 0 0 0 0 0 0 (0)
Transfers (415)(387)(518)(468)(504)(416)(541)(472)(804)(382)
East Existing Resources 4,502 4,566 4,045 4,034 4,142 3,981 3,270 3,120 3,002 2,986
Front Office Transactions 0 0 0 0 0 0 0 0 0 0
NonEmitting Peaker 0 2 378 378 379 375 376 376 381 567
Wind 595 570 555 619 654 706 736 725 807 778
Wind+Storage 0 0 0 0 0 0 0 0 0 0
Solar 12 13 11 11 11 12 13 13 13 12
Solar+Storage 429 427 629 689 699 776 969 942 1,008 936
Storage 142 140 120 138 147 157 125 113 88 83
Nuclear 202 197 182 202 209 236 241 240 265 249
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
East Planned Resources 1,380 1,349 1,875 2,036 2,099 2,263 2,459 2,408 2,563 2,626
East Total Resources 5,882 5,915 5,920 6,070 6,241 6,244 5,729 5,528 5,565 5,612
Load 6,240 6,328 6,415 6,517 6,595 6,672 6,407 6,504 6,589 6,682
Private Generation (9)(10)(12)(13)(14)(16)(33)(37)(41)(45)
Existing - Demand Response (288)(287)(291)(264)(243)(247)(303)(295)(299)(267)
New Demand Response (398)(414)(483)(461)(449)(488)(654)(669)(713)(705)
Existing - Energy Efficiency (38)(38)(39)(35)(32)(33)(40)(39)(40)(35)
New Energy Efficiency (446)(480)(513)(494)(481)(504)(659)(695)(758)(726)
East Total obligation 5,061 5,099 5,078 5,250 5,375 5,384 4,718 4,769 4,738 4,904
East Reserve Margin 16%16%17%16%16%16%21%16%17%14%
West
Thermal 2,076 2,053 2,032 2,080 2,072 2,025 1,808 489 490 490
Hydroelectric 373 374 351 388 406 448 481 487 536 503
Renewable 79 79 70 78 78 91 101 104 111 107
Purchase 1 1 1 1 1 1 1 1 1 1
Qualifying Facilities 25 23 19 19 19 19 17 16 13 8
Sale (35)(34)(32)(34)(36)(38)(32)(29)(32)(30)
Transfers 415 387 518 468 504 416 541 472 804 382
West Existing Resources 2,934 2,883 2,960 2,999 3,044 2,961 2,917 1,541 1,923 1,459
Front Office Transactions 0 0 0 0 0 0 0 560 59 420
NonEmitting Peaker 0 0 0 0 0 0 15 581 582 571
Wind 111 176 164 182 178 209 232 246 266 254
Wind+Storage 24 24 23 25 24 29 32 34 37 35
Solar 0 0 0 0 0 0 0 0 0 0
Solar+Storage 359 355 294 317 325 357 364 358 385 394
Storage 0 0 0 0 0 1 94 88 111 399
Nuclear 0 0 0 0 0 0 13 480 531 487
Geothermal 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0 0 0 0 0 0
West Planned Resources 494 555 480 524 527 597 748 2,347 1,970 2,561
West Total Resources 3,428 3,438 3,441 3,523 3,571 3,557 3,666 3,887 3,893 4,020
Load 3,643 3,681 3,721 3,760 3,797 3,826 4,271 4,322 4,375 4,425
Private Generation (4)(4)(5)(6)(7)(8)(9)(11)(12)(13)
Existing - Demand Response 0 0 0 0 0 0 0 0 0 0
New Demand Response (327)(336)(350)(328)(331)(354)(449)(458)(480)(460)
Existing - Energy Efficiency (27)(27)(28)(25)(23)(23)(29)(28)(28)(25)
New Energy Efficiency (252)(271)(293)(283)(276)(293)(372)(385)(409)(369)
West Total obligation 3,033 3,042 3,045 3,118 3,160 3,148 3,412 3,440 3,445 3,558
West Reserve Margin 13%13%13%13%13%13%7%13%13%13%
System
Total Resources 9,310 9,353 9,360 9,593 9,812 9,801 9,395 9,415 9,458 9,632
Obligation 8,095 8,141 8,122 8,368 8,536 8,532 8,131 8,209 8,183 8,462
Capacity Reverve Margin (13%)1,052 1,058 1,056 1,088 1,110 1,109 1,057 1,067 1,064 1,100
Obligation + Reserves 9,147 9,200 9,178 9,455 9,645 9,641 9,188 9,276 9,247 9,562
System Position 163 153 182 138 167 160 207 139 211 70
Reserve Margin 15%15%15%15%15%15%16%15%16%14%
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
313
Washington Clean Energy Transformation Act Required Scenarios
Washington’s CETA legislation requires utilities to conduct three scenarios:
• Alternative Lowest Reasonable Cost - WAC 480-100-620(10)(a) instructs utilities to
“describe the alternative lowest reasonable cost and reasonably available portfolio that the
utility would have implemented if not for the requirement to comply” with CETA’s Clean
Energy Transformation Standards.
• Climate Change - WAC 480-100-620(10)(b) instructs utilities to “incorporate the best
science available to analyze impacts including, but not limited to, changes in snowpack,
streamflow, rainfall, heating and cooling degree days, and load changes resulting from
climate change.”
• Maximum Customer Benefit - WAC 480-100-620(10)(c) instructs utilities to “model the
maximum amount of customer benefits described in RCW 19.405.040(8) prior to balancing
against other goals.”
In this section, PacifiCorp discusses each of these portfolio outcomes relative to the preferred
portfolio P02-MM-CETA. Note, that the Alternative Lowest Reasonable Cost scenario is also
discussed relative to the P02-MM portfolio.
Alternative Lowest Reasonable Cost
WAC 480-100-620(10)(a) instructs utilities to “describe the alternative lowest reasonable cost and
reasonably available portfolio that the utility would have implemented if not for the requirement
to comply” with CETA’s Clean Energy Transformation Standards and must include the social cost
of greenhouse gases (SCGHG) in the resource acquisition decision. In the absence of a requirement
to assume SCGHG during portfolio development, the alternative lowest reasonable cost portfolio
is P02-MM, and what we would have implemented but for CETA requirements. The preferred
portfolio, P02-MM-CETA, adds a present value revenue requirement of $164m compared to P02-
MM to meet CETA requirements. Accounting for the requirement to include the SCGHG price-
policy assumption in portfolio development, the alternate scenario becomes the same as an
SCGHG portfolio run under the medium gas, medium CO2 price-policy scenario. Comparing this
Alternative Lowest Reasonable Cost case to the preferred portfolio (P02-MM-CETA) yields a
PVRR(d) system cost of $182m.
PACIFICORP – 2021 IRP CHAPTER 9 - MODELING AND PORTFOLIO SELECTION RESULTS
314
Figure 9.47 – Cumulative Portfolio Resource Changes P02-SCGHG Compared to the 2021
IRP Preferred Portfolio
Climate Change
The Washington climate change scenario includes an updated load forecast to incorporate regional
studies on potential temperature change (and associated impact to demand and energy). Relative
to the 2021 IRP forecast, the climate change scenario results in summer peaks being higher by
approximately 50 MW (<1% higher) over the 2021-2025 timeframe. By 2040, summer peaks are
projected to be 318 MW (2.7%) higher than the 2021 IRP Base. Higher winter temperatures result
in less heating load, which are driving lower winter peaks. By 2040, winter peaks are projected to
be 259 MW (2.3%) lower than the 2021 IRP Base. Please see Appendix A for additional detail
regarding the climate change scenario.
The scenario also includes analysis of impacts from climate change (precipitation, streamflow,
etc.) on Lewis River hydroelectric generating facilities, resulting in a reduction of approximately
7% in energy production, relative to the 2021 IRP base. Compared to the preferred portfolio, the
climate change scenario increases system costs by $14.6 billion, driven in large part by the SCGHG
price-policy assumption.
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
315
Figure 9.48 – Cumulative Portfolio Resource Changes, Climate Change Portfolio
Compared to the 2021 IRP Preferred Portfolio
Maximum Customer Benefit
The maximum customer benefit scenario focuses on adding distributed generation, demand
response, and energy efficiency in Washington, as well as avoiding high-voltage transmission
upgrades in PacifiCorp’s Yakima and Walla Walla communities to minimize burdens and
maximize benefits to Washington customers. Washington load forecast reflects the high private
generation forecast. The portfolio assumes the social cost of greenhouse gas price-policy scenario,
and includes all available Washington energy efficiency and demand response. 335 MW of needed
Yakima resource is assumed to be small scale PVS, adjusting operating costs and mitigating
transmission costs. Due to higher DSM selections, it was not necessary to create a hybrid Yakima
resource by adding 160 MW of co-located wind to the selected PVS resource in year 2030. As a
result, a 160 MW reduction in wind capacity is visible in the cumulative changes graph beginning
2030 relative to the preferred portfolio. The Maximum customer benefits sensitivity increases costs
by $16.9 billion relative to the preferred portfolio, driven primarily by the SCGHG price-policy
assumption and the inclusion of all available DSM.
-4000
-3000
-2000
-1000
0
1000
2000
3000
In
s
t
a
l
l
e
d
M
W
Cumulative Changes to P02-MM-CETA
Coal Gas Contracts QF
Hydro Nuclear Hydro Storage Battery
Solar Solar+Storage Wind Wind+Storage
Geothermal Energy Efficiency Demand Response Non-Emitting Peaker
Converted Gas
PACIFICORP – 2021 IRP CHAPTER 9 - MODELING AND PORTFOLIO SELECTION RESULTS
316
Figure 9.49 – Cumulative Portfolio Resource Changes, Maximum Customer Benefit
Portfolio Compared to the 2021 IRP Preferred Portfolio
Additional Sensitivity Analysis
In addition to the resource portfolios developed and studied as part of the portfolio-development
process that supports selection of the preferred portfolio, sensitivity cases will be completed to
better understand how certain modeling assumptions influence the resource mix and timing of
future resource additions. These sensitivity cases are useful in understanding how PacifiCorp’s
resource plan would be affected by changes to uncertain planning assumptions and to address how
alternative resources and planning paradigms affect system costs and risk.
Table 9.20 lists additional sensitivity studies to be performed for the 2021 IRP. To isolate the
impact of a given planning assumption, all sensitivity cases will be evaluated as a variant of the
BAU1 and BAU2 portfolios along with the preferred portfolio (P02-MM-CETA).
-200
-100
0
100
200
300
400
In
s
t
a
l
l
e
d
M
W
Cumulative Changes to P02-MM-CETA
Coal Gas Contracts QF
Hydro Nuclear Hydro Storage Battery
Solar Solar+Storage Wind Wind+Storage
Geothermal Energy Efficiency Demand Response Non-Emitting Peaker
Converted Gas
PACIFICORP – 2021 IRP CHAPTER 9 – MODELING AND PORTFOLIO SELECTION RESULTS
317
Table 9.20 – Summary of Additional Sensitivity Cases
Case Description Risk-Adjusted
PVRR ($m) Load Private Gen CO2 Policy
S-01 High Load High Base Medium gas / Medium CO2
S-02 Low Load Low Base Medium gas / Medium CO2
S-03 1 in 20 Load Growth 1 in 20 Base Medium gas / Medium CO2
S-04 New Proxy Gas Allowed Base Base Medium gas / Medium CO2
S-05 Business Plan Base Base Medium gas / Medium CO2
S-06 Levelized Cost of Energy Efficiency
Bundles Base Base Medium gas / Medium CO2
S-07 High Private Generation Base High Medium gas / Medium CO2
S-08 Low Private Generation Base Low Medium gas / Medium CO2
PacifiCorp will file a supplemental filing to its 2021 IRP filing that includes discussion and results
of these sensitivities. The supplemental filing will also be posted to PacifiCorp’s IRP webpage at
the following location: www.pacificorp.com/energy/integrated-resource-plan.
PACIFICORP – 2021 IRP CHAPTER 9 - MODELING AND PORTFOLIO SELECTION RESULTS
318
PACIFICORP - 2021 IRP CHAPTER 10 – ACTION PLAN
319
CHAPTER 10 – ACTION PLAN
CHAPTER HIGHLIGHTS
• The 2021 Integrated Resource Plan (IRP) action plan identifies steps that PacifiCorp will take
over the next two-to-four years to deliver resources in the preferred portfolio.
• PacifiCorp’s 2021 IRP action plan includes action items for existing resources, new resources,
transmission, demand-side management (DSM) resources, short-term firm market purchases,
and the purchase and sale of renewable energy credits (RECs).
• The 2021 IRP acquisition path analysis provides insight on how changes in the planning
environment might influence future resource procurement activities. Key uncertainties
addressed in the acquisition path analysis include load, private generation, changes in available
resources, and carbon dioxide (CO2) emission polices.
• PacifiCorp further discusses how it can mitigate procurement delay risk, summarizes planned
procurement activities tied to the action plan, assesses trade-offs between owning or purchasing
third-party power, discusses its hedging practices, and identifies the types of risks borne by
customers and the types of risks borne by shareholders.
Introduction
PacifiCorp’s 2021 IRP action plan identifies the steps the company will take over the next two-to-
four years to deliver its preferred portfolio, with a focus on the front ten years of the planning
horizon. Associated with the action plan is an acquisition path analysis that anticipates potential
major regulatory actions and other trigger events during the action plan time frame that could
materially impact resource acquisition strategies.
The 2021 IRP action plan is based on the latest and most accurate information available at the time
portfolios are being developed and analyzed on cost and risk metrics. PacifiCorp recognizes that
the preferred portfolio, upon which the action plan is based, is developed in an uncertain and
evolving planning environment and that resource acquisition strategies need to be regularly
evaluated as planning assumptions change.
Resource information used in the 2021 IRP, such as capital and operating costs, are based upon
recent cost-and-performance data. However, it is important to recognize that resources identified
in the plan include proxy resources, which act as a guide for resource procurement and not as a
commitment. Resources evaluated as part of procurement initiatives may vary from the proxy
resources identified in the plan with respect to resource type, timing, size, cost, and location.
PacifiCorp recognizes the need to support and justify resource acquisitions consistent with then-
current laws, regulatory rules and requirements, and commission orders.
In addition to presenting the 2021 IRP action plan, reporting on progress in delivering the prior
action plan, and presenting the 2021 IRP acquisition path analysis, This chapter also includes
discussion of the following resource procurement topics:
• Procurement delays;
• IRP action plan linkage to the business plan;
• Resource procurement strategy;
PACIFICORP - 2021 IRP CHAPTER 10 – ACTION PLAN
320
• Assessment of owning assets vs. purchasing power;
• Managing carbon risk for existing plants;
• Purpose of hedging; and
• Treatment of customer and investor risks.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
321
The 2021 IRP Action Plan
The 2021 IRP action plan identifies specific actions PacifiCorp will take over roughly the next two-to-four years to deliver its preferred
portfolio. Action items are based on the size, type and timing of resources in the preferred portfolio, findings from analysis completed over
the course of portfolio modeling, and feedback received by stakeholders in the 2021 IRP public-input process. Table 10.1 details specific
2021 IRP action items by resource category.
Table 10.1 – 2021 IRP Action Plan
Action Item 1. Existing Resource Actions
1a
Colstrip Units 3 and 4:
• PacifiCorp will continue to work closely with co-owners to seek the most cost-effective path forward toward the 2021
IRP preferred portfolio target exit date of December 31, 2025.
1b
Craig Unit 1:
• PacifiCorp will continue to work closely with co-owners to seek the most cost-effective path forward toward the 2021
IRP preferred portfolio target exit date of December 31, 2025.
1b
Naughton Units 1 and 2:
• PacifiCorp will initiate the process of retiring Naughton Units 1-2 by the end of December 2025, including
completion of all required regulatory notices and filings.
• By the end of Q2 2023, PacifiCorp will confirm transmission system reliability assessment and year-end 2025
retirement economics in 2023 IRP filing.
• By the end of Q4 2023, PacifiCorp will initiate the process with the Wyoming Public Service Commission for
approval of a reverse request for proposals for a potential sale of Naughton Units 1 and 2.
• By the end of Q4 2023, PacifiCorp will administer termination, amendment, or close-out of existing permits, contracts,
and other agreements.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
322
1c
Jim Bridger Units 1 and 2 Gas Conversion:
• PacifiCorp will initiate the process of ending coal-fueled operations and seeking permitting for a natural-gas
conversion by 2024, including completion of all required regulatory notices and filings.
• By the end of Q2 2022, PacifiCorp will finalize an employee transition plan.
• By the end of Q2 2022, PacifiCorp will develop a community action plan in coordination with community leaders.
• By the end of Q4 2023, PacifiCorp will administer termination, amendment, or close-out of existing permits,
contracts, and other agreements.
• By the end of Q4, 2023, PacifiCorp will remove units 1 and 2 from Washington’s allocation of electricity.
1d
Carbon Capture, Utilization, and Sequestration/Wyoming House Bill 200 Compliance:
• PacifiCorp issued a carbon capture, utilization, and sequestration (CCUS) request for expression of interest (REOI)
on June 29, 2021. PacifiCorp will complete the 2021 CCUS REOI process and utilize any new relevant information.
Additional model sensitivities will be run accordingly.
• PacifiCorp will issue a CCUS Request for Proposals (RFP) in 2022. The 2021 CCUS REOI responses will inform the
scope of the CCUS RFP.
• A completed CCUS Front End Engineering & Design Study (FEED Study) based on a new CCUS technology was
submitted to PacifiCorp in July 2021 for Dave Johnston Unit 2. Third-party review of the FEED Study will be
completed by Q1 2022, and model sensitivities will subsequently be run as needed, with FEED Study assumptions
and inputs as appropriate.
• Subject to finalization of rules by the Wyoming Public Service Commission (WPSC) to implement House Bill 200
(HB 200), the Wyoming Low Carbon Energy Standard (anticipated by Q4 2021), by March 31, 2022, PacifiCorp will
file with the WPSC an initial CCUS application to establish intermediate CCUS standards and requirements.
• Subject to finalization of rules by the WPSC to implement HB 200, the Wyoming Low Carbon Energy Standard
(anticipated by Q4 2021), PacifiCorp will submit for WPSC approval a final plan with its proposed energy portfolio
standard for dispatchable and reliable low-carbon electricity, its plan for achieving the standard, and a target date of no
later than July 1, 2030.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
323
1e
Regional Haze Compliance:
• Following the resolution of first planning period regional haze compliance disputes, and the submission of second
planning period regional haze state implementation plans, PacifiCorp will evaluate and model any emission control
retrofits, emission limitations, or utilization reductions that are required for coal units.
• PacifiCorp will continue to engage with the Environmental Protection Agency, state agencies, and stakeholders to
achieve second planning period regional haze compliance outcomes that improve Class I visibility, provide
environmental benefits, and are cost effective.
Action Item 2. New Resource Actions
2a
Customer Preference Request for Proposals:
• Consistent with Utah Community Renewable Energy Act, PacifiCorp continues to work with eligible communities to
develop program to achieve goal of being net 100 percent renewable by 2030; PacifiCorp anticipates filing an
application for approval of the program with the Utah Public Service Commission in 2022, which may necessitate
issuance of a request for proposals to procure resources within the action plan window.
2b
Acquisition and Repowering of Foote Creek II-IV and Rock River I:
• In Q3 2021, PacifiCorp will pursue necessary regulatory approvals to authorize the acquisition and repowering of
Foote Creek II-IV in order to issue repowering contracts in Q1 2022 in support of a late 2023 in-service date.
• In Q1 2022, PacifiCorp will pursue necessary regulatory approvals to authorize the acquisition and repowering of
Rock River I following the expiration of the existing power purchase agreement in order to issue repowering
contracts in Q3 2022 to support a late 2024 in-service date.
2c
NatriumTM Demonstration Project:
• PacifiCorp will continue to monitor key TerraPower milestones for development and will make regulatory filings, as
applicable.
• By the end of 2022, PacifiCorp will finalize commercial agreements for the NatriumTM project.
• Q1 2022, PacifiCorp will develop a community action plan in coordination with community leaders.
• By 2025, PacifiCorp will begin training operators.
• PacifiCorp will continue to monitor key TerraPower milestones for development and will make regulatory filings, as
applicable, including, but not limited to, a request for the Oregon Public Utility Commission to explicitly
acknowledge an alternative acquisition method consistent with OAR 860-089-0100(3)(c), and a request for a waiver
of a solicitation for a significant energy resource decision consistent with Utah statute 54-17-501.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
324
2d
2022 All-Source Request for Proposals:
• PacifiCorp will issue an all-source Request for Proposals (RFP) to procure resources that can achieve commercial
operations by the end of December 2026.
• In September 2021, PacifiCorp will notify the Public Utility Commission of Oregon, the Public Service Commission
of Utah, and the Washington Utilities and Transportation Commission, of PacifiCorp’s need for an independent
evaluator.
• In October 2021, PacifiCorp will file a draft all-source RFP with applicable state utility commissions.
• In January 2022, PacifiCorp expects to receive approval of the all-source RFP from applicable state utility commissions
and issue the RFP to the market.
• In Q2 2022, PacifiCorp will identify an initial shortlist in advance of annual Cluster Request Window.
• In Q1 2023, PacifiCorp will identify a final shortlist from the all-source RFP, and file for approval of the final shortlist
in Oregon, file, certificate of public convenience and necessity (CPCN) applications, as applicable.
• By Q2 2023 PacifiCorp will execute definitive agreements with winning bids from the all-source RFP.
• By Q4 2025-2026, winning bids from the all-source RFP are expected to achieve commercial operation. Resources
must have commercial operation date of December 31, 2026, or earlier.
2e
2020 All-Source Request for Proposals:
• PacifiCorp filed for approval of the final shortlist in Oregon in June 2021.
• In September 2021, PacifiCorp will file CPCN applications in Wyoming, as applicable, for final shortlist.
• In Q4 2021, PacifiCorp will make a filing in Utah for significant energy resources on final shortlist.
Action Item 3. Transmission Action Items
3a
Energy Gateway South Segment F (Aeolus-Clover 500 kV transmission line):
• By Q2 2022, obtain Utah and Wyoming Certificates of Public Convenance and Necessity.
• By the end of Q1 2022, Bureau of Land Management notice to proceed to construct Energy Gateway South.
• In Q3 2024, construction of Energy Gateway South is expected to be completed and placed in service.
3b
Energy Gateway West, Segment D.1 (Windstar-Shirley Basin 230 kV transmission line):
• By Q2 2022, obtain conditional Wyoming Certificate of Public Convenance and Necessity
• By Q3 2022 complete ROW easement acquisition and option full Wyoming CPCN
• In Q3 2024, construction of Energy Gateway West segment D.1 to be completed and placed in service.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
325
3c
Boardman-to-Hemingway (500 kV transmission line):
• Continue to support the project under the conditions of the Boardman-to-Hemingway Transmission Project (B2H)
Joint Permit Funding Agreement.
• Continue to participate in the development and negotiations of the construction agreement.
• Continue to participate in “pre-construction” activities in support of the 2026 in-service date.
• Continue negotiations for plan of service post B2H for parties to the permitting agreement.
3d Initiate Local Reinforcement Projects as identified with the addition of new resources per the preferred portfolio, and
follow-on requests for proposal successful bids
3e Continue permitting support for Gateway West segments D.3 and E.
Action Item 4. Demand-Side Management (DSM) Actions
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
326
4a
Energy Efficiency Targets:
• PacifiCorp will acquire cost-effective Class 2 DSM (energy efficiency) resources targeting annual system energy and
capacity selections from the preferred portfolio as summarized below. PacifiCorp’s state-specific processes for
planning for DSM acquisitions is provided in Appendix D in Volume II of the 2021 IRP.
• PacifiCorp will pursue cost-effective energy efficiency resources as summarized in the table below:
• PacifiCorp will pursue cost-effective Class 1 (demand response) resources targeting annual system capacity1
selections from the preferred portfolio2 as summarized in the table below:
1 Capacity impacts for demand response include both summer and winter impacts within a year.
2A portion of cost-effective demand response resources identified in the 2021 preferred portfolio are expected to be acquired through a
previously issued demand response RFP soliciting resources identified in the 2019 IRP. PacifiCorp will pursue all cost-effective demand
response resources identified as incremental to resources subsequently procured under the previously issued RFP in compliance with state
level procurement requirements.
Action Item 5. Market Purchases
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
327
5a
Market Purchases:
• Acquire short-term firm market purchases for on-peak delivery from 2021-2023 consistent with the Risk
Management Policy and Energy Supply Management Front Office Procedures and Practices. These short-term firm
market purchases will be acquired through multiple means: Balance of month and day-ahead brokered transactions in
which the broker provides a competitive price.
• Balance of month, day-ahead, and hour-ahead transactions executed through an exchange, such as the
Intercontinental Exchange, in which the exchange provides a competitive price.
• Prompt-month, balance-of-month, day-ahead, and hour-ahead non-brokered bi-lateral transactions.
Action Item 6. Renewable Energy Credit (REC) Actions
6a
Renewable Portfolio Standards (RPS):
• PacifiCorp will pursue unbundled REC RFPs and purchases to meet its state RPS compliance requirements.
• As needed, issue RFPs seeking then current-year or forward-year vintage unbundled RECs that will qualify in
meeting California RPS targets through 2024.
6b Renewable Energy Credit Sales:
• Maximize the sale of RECs that are not required to meet state RPS compliance obligations.
Progress on Previous Action Plan Items
This section describes progress that has been made on previous action plan items documented in the 2019 IRP filed with state commissions
on October 18, 2019. Many of these action items have been superseded in some form by items identified in the 2021 IRP action plan. The
status for all action items from the 2019 IRP is summarized in Table 10.2.
Table 10.2 – 2019 IRP Action Plan Status Update
Action
Item 3. Existing Resource Actions Status
1a
Naughton Unit 3:
• PacifiCorp will complete the gas conversion of Naughton
Unit 3, including completion of all required regulatory
This action is complete. PacifiCorp filed an amended
certificate of public convenience and necessity (CPCN)
notice with the Wyoming Public Service Commission on
11/21/2019. The notice requested a determination that a
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
328
notices and filings, in 2020. Initiate procurement of
materials in Q4 2019. Conversion completed in 2020.
CPCN was not required to convert the unit to natural gas.
The Commission approved the notice by a letter order
issued on 11/27/2019. Gas conversion was complete in
July 2020.
1b
Cholla Unit 4:
• PacifiCorp will initiate the process of retiring Cholla Unit
4, including all required regulatory notices and filings, as
soon as practicable, but will remove Cholla Unit 4 from
service no later than January 2023 and earlier if possible.
• PacifiCorp will continue to coordinate with the plant
operator to transition employees, develop plans to cease
plant operations, safely remove the unit from service,
finalize decommissioning plans and confirm joint-
ownership obligations; complete required regulatory
notices and filings; administer termination, amendment, or
close-out of existing permits, contracts and other
agreements; and coordinate with state and local
stakeholders as appropriate.
• By the end of Q1 2020, the plant operator will be
requested to develop plans to cease plant operations,
safely remove the unit from service, finalize
decommissioning plans, and confirm joint-ownership
obligations.
• By the end of Q2 2020, the plant operator will be
requested to file required transmission interconnection and
transmission services unit retirement notices/request for
study.
• By the end of Q4 2020, PacifiCorp will finalize an
employee transition agreement with the plant operator.
Cholla Unit 4 regulatory, compliance, environmental,
transmission, permits, operations, and other associated
closure communications and requirements were
performed throughout 2020. Cholla Unit 4 was retired on
12/31/2020.
PacifiCorp continues to work with the operator on joint-
owner obligations, transition, and decommissioning plans.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
329
1c
Jim Bridger Unit 1:
• PacifiCorp will initiate the process of retiring Jim Bridger
Unit 1 by the end of December 2023, including
completion of all required regulatory notices and filings.
By the end of Q2 2020, file a request with PacifiCorp
transmission to study the year-end 2023 retirement of Jim
Bridger Unit 1. By the end of Q2 2021, confirm
transmission system reliability assessment and year-end
2023 retirement economics in 2021 IRP filing.
• By the end of Q2 2021, finalize an employee transition
plan.
• By the end of Q2 2021, develop a community action plan
in coordination with community leaders.
• By the end of Q4 2021, initiate the process with the
Wyoming Public Service Commission for approval of a
reverse request for proposals for a potential sale of Jim
Bridger Unit 1.
• By the end of Q4 2023, administer termination,
amendment, or close-out of existing permits, contracts,
and other agreements.
Finalizing plans for the process of retiring Jim Bridger Unit
1 are dependent on the preferred portfolio of the 2021 IRP,
which will be filed by September 1, 2021. Jim Bridger
regulatory, compliance, environmental, permits,
operations, and other associated closure impacts will be
addressed as required by state laws.
The request to study Jim Bridger Unit 1 retirement was
received in Q1 2021 by PacifiCorp transmission. The
results are posted to OASIS.
The employee transition plan and community action plan
are ongoing.
The initiation of a process for approval of a reverse request
for proposals for potential sale of Jim Bridger 1 is
dependent on the preferred portfolio of the 2021 IRP. If the
outcome of the 2021 IRP continues to show customer
benefits to retire the unit at the end of 2023, PacifiCorp will
file an application with the Wyoming Public Service
Commission in Q4 2021 to initiate the process to solicit a
buyer for the unit, in accordance with the administrative
rules adopted by the commission to implement Wyo. Stat.
37-2-133 and 37-3-117.
1d
Naughton Units 1-2:
• PacifiCorp will initiate the process of retiring Naughton
Units 1-2 by the end of December 2025, including
completion of all required regulatory notices and filings.
PacifiCorp is proceeding with this action item on schedule.
Additional information on this action item is included in
the 2021 action plan.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
330
By the end of Q2 2022, file a request with PacifiCorp
transmission to study the year-end 2025 retirement of
Naughton Units 1 and 2.
• By the end of Q2 2022, finalize an employee transition
plan.
• By the end of Q2 2022, develop a community action plan
in coordination with community leaders.
• By the end of Q2 2023, confirm transmission system
reliability assessment and year-end 2025 retirement
economics in 2023 IRP filing.
• By the end of Q4 2023, initiate the process with the
Wyoming Public Service Commission for approval of a
reverse request for proposals for a potential sale of
Naughton Units 1 and 2.
• By the end of Q4 2023, administer termination,
amendment, or close-out of existing permits, contracts,
and other agreements.
1e
Craig Unit 1:
• The plant operator will be requested to administer
termination, amendment, or close-out of existing permits,
contracts, and other agreements to support retiring Craig
Unit 1, including completion of all required regulatory
notices and filings, by the end of December 2025.
PacifiCorp is proceeding with this action item on schedule.
Action
Item 4. New Resource Actions Status
2a
Customer Preference Request for Proposals:
• PacifiCorp will work with customers to achieve their
respective resource preference requirements. By the end of
Q4 2019, sign a fifteen year 80 megawatt (MW) Power
PacifiCorp signed a long-term 80 MW PPA for six Utah
Schedule 34 customers.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
331
Purchase Agreement (PPA) for Utah solar for six Utah
Schedule 34 customers. By the end of Q4 2019, sign two
20-year PPAs of approximately 80 MW for a large Utah
Schedule 34 customer. Monitor the finalization of rules by
the Public Service Commission of Utah for House Bill
(HB) 411 (anticipated by the end of Q1 2020), that provides
a path forward for development of a program for
participating communities to begin procuring renewable
resources.
PacifiCorp signed four long-term PPAs (75 MW, 80 MW,
120 MW & 80 MW) for a large Utah Schedule 34
customer.
PacifiCorp signed a long-term 20 MW PPA for a large
Utah Schedule 32 customer.
Rules for Utah HB 411 were finalized by the Public
Service Commission of Utah providing a path forward for
development of a program to meet the communities’
goals. PacifiCorp is currently working with the
consortium of customers to develop the program.
2b
All Source Request for Proposals:
• PacifiCorp will issue an all-source request for proposals
(RFP) to procure resources that can achieve commercial
operations by the end of December 2023.
• By the end of Q4 2019, file a request for interconnection
queue reform with the Federal Energy Regulatory
Commission (FERC) and make state filings to initiate the
process of identifying an independent evaluator.
• In Q1 2020, file a draft all-source RFP with the Public
Utility Commission of Oregon, the Public Service
Commission of Utah, and the Washington Utilities and
Transportation Commission, as applicable.
• In Q2 2020, receive approval from FERC to reform the
interconnection queue.
• In Q2 2020, receive approval of the all-source RFP from
applicable state regulatory commissions and issue the RFP
to the market.
A draft of PacifiCorp's 2020 All-Source RFP ("2020AS
RFP") was filed for approval with the Utah PSC and the
Oregon PUC in April 2020. In July 2020, the Utah PSC
and the Oregon PUC approved the 2020AS RFP, and
PacifiCorp issued the 2020AS RFP to market. The
2020AS RFP sought bids for resources capable of coming
online by the end of 2024 up to the level of resources
identified in PacifiCorp's 2019 IRP. Bids were submitted
in August 2020. An initial shortlist was identified in
October 2020. The initial shortlist included a total of
6,982 MWs of new generation and storage capacity. Of
the total, 5,652 MWs are new generation resources
(represented by 3,173 MWs of solar generation and 2,479
MWs of wind generation) and an additional 1,330 MWs
of new battery storage assets, which includes 1,130 MWs
of solar collocated battery storage and 200 MWs of stand-
alone battery storage. The final shortlist of winning bids
was filed in Oregon in June 2021. PacifiCorp is finalizing
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
332
• In Q3 2020, identify a preliminary final shortlist from the
all-source RFP and initiate transmission interconnection
studies consistent with queue reform as approved by FERC.
• In Q2 2021, identify a final shortlist from the all-source
RFP, and file for approval of the final shortlist in Oregon,
file, certificate of public convenience and necessity
(CPCN) applications, as applicable.
• By Q2 2022 execute definitive agreements with winning
bids from the all-source RFP.
• By Q4 2023, winning bids from the all-source RFP achieve
commercial operation.
both build and transfer and power purchase agreement
updated drafts that will be forwarded to all final
shortlisted participants prior to September 1, 2021.
Contract negotiations are expected to proceed into early
Q1 2022. All necessary final state regulatory approvals
and proceedings are expected to be complete by Q2 2022.
On January 31, 2020, as amended March 13, 2020,
PacifiCorp submitted revisions to its Open Access
Transmission Tariff (OATT) to implement revisions to its
interconnection process. PacifiCorp proposed revisions to
its Large Generator Interconnection Procedures, Small
Generator Interconnection Procedures, and associated
appendices, including the Large Generator
Interconnection Agreement and Small Generator
Interconnection Agreement. On May 12, 2020, the FERC
issued an order accepting the proposed Tariff revisions,
subject to condition. As a result of the acceptance,
PacifiCorp’s interconnection process changed from a
serial, first =-come, first-served process, to a first-ready,
first-served interconnection process. The prospective
interconnection processes use cluster studies, under which
interconnection requests received during an annual
“Cluster Request Window” are studied in groups (as
opposed to serially and individually). The revised
interconnection process should allow commercially-ready
projects to proceed on a more accelerated basis while
allowing less-developed projects to have access to non-
binding estimates of cost responsibility and time to
construct to assist with preliminary siting decisions.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
333
Action
Item 3. Transmission Action Items
3a
Energy Gateway South:
• By December 31, 2023, PacifiCorp will seek to build the
approximately 400-mile, 500-kilovolt (kV) transmission
line from the Aeolus substation near Medicine Bow,
Wyoming to the Clover substation near Mona, Utah.
• By Q2 2021, receive the final CPCN from the Wyoming
Public Service Commission and the Public Service
Commission of Utah (initial filing dates for the CPCN to
be determined after stakeholder engagement).
• By the end of Q4 2021, issue full notice to proceed to
construct Energy Gateway South.
• In Q4 2023, construction of Energy Gateway South is
completed and placed in service.
Energy Gateway South has been moved to a target in-
service date of Q4 2024.
This action item has been superseded by the Energy
Gateway South Action in the 2021 action plan.
3b
Utah Valley Reinforcements:
• Utah Valley Reinforcements: As necessary to facilitate
interconnection of customer-preference resources,
PacifiCorp will proceed with system reinforcements in the
Utah Valley.
• In Q2 2020, complete the Spanish Fork 345 kV/138 kV
transformer upgrade.
• In Q4 2020, complete rebuild of approximately five miles
of the Spanish Fork-Timp138 kV line in the Utah Valley.
In-service dates have been revised based on current project
schedules as follows:
• In Q1 2021, PacifiCorp completed the Spanish Fork
345 kV/138 kV transformer upgrade. The completion
date for the transformer upgrade was shifted to 2021
due to outage constraints on the line. The remaining
scope to complete improvements at a third-party
owned substation will be completed in fall 2021.
• In Q2 2021, PacifiCorp will complete rebuild of
approximately five miles of the Spanish Fork-
Timp138 kV line in the Utah Valley. The completion
of this project shifted to 2021 due to delays in steel
pole deliveries.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
334
3c
Northern Utah Reinforcements:
• Rebuild two miles of the Morton Court –Fifth West 138
kV line.
• Loop existing Populus Terminal 345 kV line into both
Bridger and Ben Lomond; build 345 kV yard with
345/138 transformer and 138 kV yard buildout at Bridger
plus ancillary 345 kV and 230 kV circuit breakers at Ben
Lomond.
• Complete identified plan of service supporting 2019 IRP
preferred portfolio for resource additions in northern Utah.
Transmission cluster studies are underway and final short
list RFP results will be available no later than June 2021
which could impact final project schedules.
The rebuild of two miles of the Morton Court –Fifth West
138 kV line is scheduled for Q4 2023.
The project to loop existing Populus Terminal 345 kV
line into both Bridger and Ben Lomond; build 345 kV
yard with 345/138 transformer and 138 kV yard buildout
at Bridger plus ancillary 345 kV and 230 kV circuit
breakers at Ben Lomond is now scheduled for Q4 2023.
3d
Utah South Reinforcements:
• Develop plan of service in support of 2019 IRP preferred
portfolio for resource additions in southern Utah.
• Complete rebuild of the Mona –Clover #1 & #2 345 kV
lines.
• Identify route and terminals for new approximately 70-
mile 345 kV line in southern/central Utah.
• Yakima Washington Reinforcements: To facilitate
interconnection of preferred portfolio resources in the
Yakima area, PacifiCorp will proceed with protection
system and remedial action scheme upgrades to local 230
kV and 115 kV substations not otherwise included in
network upgrade requirements for generator
interconnection requests.
• In Q2 2020, complete the Vantage-Pomona Heights 230
kV line (in process).
In-service dates have been revised based on current project
schedules. Cluster studies continue and final short list RFP
results will be available no later than June 2021 which
could impact final project schedules. Washington action
items are addressed in PacifiCorp’s response to item 3e
below.
In Q3 2024 PacifiCorp is scheduled complete rebuild of
the Mona –Clover #1 & #2 345 kV lines.
In Q2 2026 PacifiCorp is scheduled to identify route and
terminals for new approximately 70-mile 345 kV line in
southern/central Utah.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
335
• By Q2 2022, establish the type and location of new
resources and finalize project scope, as necessary.
3e
Yakima Washington Reinforcements:
• To facilitate interconnection of preferred portfolio
resources in the Yakima area, PacifiCorp will proceed
with protection system and remedial action scheme
upgrades to local 230 kV and 115 kV substations not
otherwise included in network upgrade requirements for
generator interconnection requests.
• In Q2 2020, complete the Vantage-Pomona Heights 230
kV line (in process).
• By Q2 2022, establish the type and location of new
resources and finalize project scope, as necessary.
The cluster studies are underway and final short list RFP
results will be available no later than June 2021 which
could impact final project schedules.
The Vantage-Pomona Heights 230kV line was completed
in Q3 2020.
3f
Boardman to Hemmingway:
• Continue to support the project under the conditions of the
Boardman to Hemingway Transmission Project (B2H)
Joint Permit Funding Agreement.
• Continue to participate in the development and
negotiations of the construction agreement.
• Continue analysis in efforts to identify customer benefits
that may include contributions to reliability,
interconnection of additional resources, geographical
diversity of intermittent resources, Energy Imbalance
Market, and resource adequacy.
• Continue negotiations for plan of service post B2H for
parties to the permitting agreement.
Negotiations with partners are ongoing. PacifiCorp
continues to study this transmission segment as part of its
2021 IRP.
3g Energy Gateway West: Energy Gateway West Segment D.2 was completed in Q4
2020. The other action items remain on schedule.
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
336
• Energy Gateway West Segment D.2, continue
construction with target in-service date of 12/31/2020.
• Continue permitting for the Energy Gateway transmission
plan, with near term targets as follows:
• For Segments D.3, and E, continue funding of the required
federal agency permitting environmental consultant
actions required as part of the federal permits. Also,
continue to support the projects by providing information
and participating in public outreach.
This action item has been superseded by the Energy
Gateway West Action in the 2021 action plan.
Action
Item 4. Demand-Side Management (DSM) Actions Status
4a
Energy Efficiency Targets:
• PacifiCorp will acquire cost-effective Class 2 DSM
(energy efficiency) resources targeting annual system
energy and capacity selections from the preferred portfolio
as summarized below. PacifiCorp’s state-specific
processes for planning for DSM acquisitions will be
provided in Appendix D in Volume II of the 2019 IRP.
* Note, Class 2 DSM capacity figures reflect projected maximum annual hourly energy
savings, which is similar to a nameplate rating for a supply-side resource.
• Energy Efficiency Bundling: PacifiCorp will continue to
evaluate alternate bundling methodologies of Class 2
DSM in the 2019 IRP.
• Direct-Load Control: PacifiCorp will acquire cost-
effective Class 1 DSM (i.e., demand response) in Utah
In October 2020, the Utah PSC approved a new
Wattsmart battery demand response program. With the
addition of this new program and program modifications
occurring with Cool Keeper and Irrigation Load Control,
the Company is currently on track to achieve the
incremental capacity.
Energy Efficiency Targets
2019 reporting indicates the company acquired 506 GWh
of energy efficiency system wide. This equates to 113
MW of capacity reductions.
Preliminary 2020 reporting indicates the company
acquired 561 GWh of energy efficiency system wide.
This equates to 138 MW of capacity reductions.
Year Annual Incremental Energy (GWh) Annual Incremental Capacity (MW)
2019 562 126
2020 536 132
2021 538 133
2022 571 143
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
337
targeting approximately 29 MW of incremental capacity
from 2020 through 2023.
Coupling preliminary 2020 reporting with 2019 actuals,
acquired 1,067 GWh of energy efficiency over the two
years. This equates to capacity reductions of 251 MW
(using the same GWh/MW relationship)
PacifiCorp continues to evaluate alternative bundling
methodologies as part of the 2021 IRP process, and
presented its methodology at the January 29, 2021 IRP
public-input meeting.
At the end of January 2021, PacifiCorp issued a demand
response RFP to identify the potential acquisition of cost-
effective flexible capacity. The final shortlist of bids was
identified in June 2021 and includes over 600 MW of
capacity during the planning horizon. PacifiCorp is
finalizing the procurement and negotiation of demand
response resources following the completion of 2021 IRP.
Contract negotiations and program filings are expected to
conclude in Q4 of 2021. All necessary state regulatory
approvals and proceedings are expected to be complete in
the winter and spring of 2022.
Action
Item 5. Front Office Transactions Status
5a
Market Purchases:
• Acquire short-term firm market purchases for on-peak
delivery from 2019-2021 consistent with the Risk
Management Policy and Energy Supply Management
Front Office Procedures and Practices. These short-term
Market purchases, inclusive of day-ahead, balance of
month, prompt, and forward hedging transactions, but not
accounting for any offsetting hedging sales, were made
for on peak delivery in the following periods and at the
following quantities:
PACIFICORP - 2021 IRP CHAPTER 10 –ACTION PLAN
338
firm market purchases will be acquired through multiple
means: Balance of month and day-ahead brokered
transactions in which the broker provides a competitive
price.
• Balance of month, day-ahead, and hour-ahead transactions
executed through an exchange, such as the
Intercontinental Exchange, in which the exchange
provides a competitive price.
• Prompt-month, balance-of-month, day-ahead, and hour-
ahead non-brokered bi-lateral transactions.
2019: 350 to 2561 MW
2020: 650 to 2720 MW
2021: 125 to 1150 MW
Market purchases are made in accordance with the Risk
Management Policy and Energy Supply Management
Front Office Procedures and Practices and include a mix
of the transaction types identified in item 5a.
Action
Item 6. Renewable Energy Credit Actions Status
6a
Renewable Portfolio Standards (RPS):
• PacifiCorp will pursue unbundled RFPs to meet its state
RPS compliance requirements.
• As needed, issue RFPs seeking then current-year vintage
unbundled RECs that will qualify in meeting California
RPS targets through 2020. As needed, issue RFPs seeking
then current-year or forward-year vintage unbundled
RECs that will qualify in meeting Washington RPS
targets.
PacifiCorp will continue to evaluate the need for
unbundled RECs and issue RFPs to meet its state RPS
compliance requirements as needed for both California
and Washington. Most recently, PacifiCorp issued an RFP
for RECs in 2019 to meet its state RPS compliance
requirements.
6b
Renewable Energy Credit Sales:
• Maximize the sale of RECs that are not required to
meet state RPS compliance obligations.
PacifiCorp issued reverse RFPs in April 2019, March
2020, and February 2021. PacifiCorp will continue to
engage in bilateral REC sales and issue reverse RFPs to
maximize the sale of RECs that are not required to meet
state RPS compliance obligations.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
339
Acquisition Path Analysis
Resource and Compliance Strategies
PacifiCorp worked with stakeholders to define its portfolio development process and cost and risk
analysis in the 2021 IRP. This analysis reflects a combination of specific planning assumptions
related to key uncertainties addressed in the acquisition path analysis include load, private
generation, changes in available resources, and CO2 emission polices. PacifiCorp will further
analyze sensitivity cases on planning assumptions related primarily to the load forecasts and
private generation penetration levels. The array of planning assumptions that define the studies
used to develop resource portfolios provides the framework for a resource acquisition path analysis
by evaluating how resource selections are impacted by changes to planning assumptions.
Given current load expectations, portfolio modeling performed for the 2021 IRP shows the
resource acquisition path in the preferred portfolio is robust among a wide range of policy and
market conditions, particularly in the near-term, when cost-effective renewable resources that
qualify for federal income tax credits, market purchases, and energy efficiency and demand
response resources are consistently selected. Further, the procurement processes associated with
these resource actions are well underway. With regard to renewable resource acquisition, the
portfolio development modeling performed in the 2021 IRP shows that new renewable resource
needs are driven primarily by economics and reliability. Beyond load, CO2 policy also influences
resource selections in the 2021 IRP. For these reasons, the acquisition path analysis focuses on
economic, load, reliability, and environmental policy trigger events that would require alternative
resource acquisition strategies. For each trigger event, PacifiCorp identifies the planning scenario
assumption affecting both short-term (2021-2030) and long-term (2031-2040) resource strategies.
Acquisition Path Decision Mechanism
The Public Service Commission of Utah requires that PacifiCorp provide “[a] plan of different
resource acquisition paths with a decision mechanism to select among and modify as the future
unfolds.”1 PacifiCorp’s decision mechanism is centered on the IRP process and ongoing updates
to the IRP modeling tools between IRP cycles. The same modeling tools used in the IRP are also
used to evaluate and inform the procurement of resources. The IRP models are used on a macro-
level to evaluate alternative portfolios and futures as part of the IRP process, and then on a micro-
level to evaluate the economics and system benefits of individual resources as part of the supply-
side resource procurement and demand-side management target-setting/valuation processes.
PacifiCorp uses the IRP development process, and the IRP modeling tools to serve as decision
support tools to guide prudent resource acquisition paths that maintain system reliability at a
reasonable cost. Table 9.3 summarizes PacifiCorp’s 2021 IRP acquisition path analysis, which
provides insight on how changes in the planning environment might influence future resource
procurement activities. Changes in procurement activities driven by changes in the planning
environment will ultimately be reflected in future IRPs and resource procurement decisions.
1 Public Service Commission of Utah, In the Matter of Analysis of an Integrated Resource Plan for PacifiCorp,
Report and Order, Docket No. 90-2035-01, June 1992, p. 28.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
340
Table 10.3 – Near-term and Long-term Resource Acquisition Paths
Trigger Event
Planning
Scenario(s)
Near-Term Resource
Acquisition Strategy
(2021-2030)
Long Term Resource
Acquisition Strategy
(2031-2040)
Higher sustained
load growth
High economic
drivers accounting
for 95% prediction
interval.
• In 2026, there is an
increase of 5 percent
higher sustained load
growth than the base case
forecast, resulting in an
increase in peak capacity
requirements of 545 MW
increasing further to nearly
600 MW in 2030.
• Within the action plan
window, there would be no
change to the resource
procurement strategy
focused on an all-source
RFP and incremental
transmission upgrades.
• The higher peak capacity
requirements relative to the
base case forecast results in
additional resource need,
increased market reliance
and/or shifts in timing of
planned resources or coal
unit retirements.
• In 2040, there is an increase
of 7 percent higher sustained
load growth than the base case
forecast, resulting in an
increase in peak capacity
requirements of 890 MW.
• The higher peak capacity
requirements relative to the
base case forecast results in
additional resource need,
increased market reliance
and/or shifts in timing of
planned resources or coal unit
retirements.
Lower sustained
load growth
Low economic
drivers accounting
for 95% prediction
interval.
• In 2026, there is 6 percent
lower sustained load
growth than the base case
forecast, resulting in a
decrease in peak capacity
requirements of 628 MW
decreasing further 861 MW
in 2030.
• Within the action plan
window, there would be no
change to the resource
procurement strategy
focused on an all-source
RFP and incremental
transmission upgrades.
• The lower peak capacity
requirements relative to the
base case forecast results in
a reduction in resource
need, decreased market
reliance and/or shifts in
timing of planned
resources or coal unit
retirements.
• In 2040, there is a 7 percent
lower sustained load growth
than the base case forecast,
resulting in a decrease in peak
capacity requirements of 890
MW.
• The lower peak capacity
requirements relative to the
base case forecast results in a
reduction in resource need,
decreased market reliance
and/or shifts in timing of
planned resources or coal unit
retirements.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
341
Trigger Event
Planning
Scenario(s)
Near-Term Resource
Acquisition Strategy
(2021-2030)
Long Term Resource
Acquisition Strategy
(2031-2040)
Higher sustained
private generation
penetration levels
More aggressive
technology cost
reductions,
improved
technology
performance, and
higher electricity
retail rates
• In 2026, peak capacity
requirements are lower by
53 MW due to higher
sustained private
generation levels relative to
the base case forecast.
• In 2030, peak capacity
requirements are lower by
249 MW due to higher
sustained private
generation levels relative to
the base case forecast.
• Within the action plan
window, there would be no
change to the resource
procurement strategy
focused on an all-source
RFP and incremental
transmission upgrades.
• Small changes to the
portfolio would require
minimal changes to the
resource acquisition
strategy.
• In 2040, peak capacity
requirements are lower by 172
MW due to higher sustained
private generation levels
relative to the base case
forecast.
• Small changes to the portfolio
would require minimal
changes to the resource
acquisition strategy.
• Timing differences in
resource capacity would need
to be assessed in procurement
processes to achieve the
appropriate balance of energy
and capacity.
Lower sustained
private generation
penetration levels
Less aggressive
technology cost
reductions, reduced
technology
performance, and
lower electricity
retail rates
• In 2026, peak capacity
requirements are higher by
31 MW due to lower
sustained private
generation levels relative to
the base case forecast.
• In 2030, peak capacity
requirements are higher by
61 MW due to lower
sustained private
generation levels relative to
the base case forecast.
• Within the action plan
window, there would be no
change to the resource
procurement strategy
focused on an all-source
RFP and incremental
transmission upgrades.
• Small changes to the
portfolio would require
minimal changes to the
resource acquisition
strategy.
• In 2040, peak capacity
requirements are higher by
342 MW due to lower
sustained private generation
levels relative to the base case
forecast.
• Timing differences in
resource capacity would need
to be assessed in procurement
processes to achieve the
appropriate balance of energy
and capacity.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
342
Trigger Event
Planning
Scenario(s)
Near-Term Resource
Acquisition Strategy
(2021-2030)
Long Term Resource
Acquisition Strategy
(2031-2040)
High CO2 prices
with accelerated
coal retirements
Fossil-fired
generation is faced
with a high CO2
price beginning in
2025 at $22.57/ton
and reaching
$102.48/ton by
2040 that drives all
coal to be retired by
2030
• Within the action plan
window, there would be no
change to the resource
procurement strategy
focused on an all-source
RFP and incremental
transmission upgrades.
• Accelerate timing of new
resource additions
including an advanced
nuclear resource from 2038
to 2030 and 1,009 MW of
solar co-located with
storage from 2037 to 2024
through 2028 with an
additional 330 MW added
over that time period.
Accelerate a non-emitting
peaking unit from 2040 to
2030 with two additional
non-emitting peaking units
added in that year.
• Increase procurement of
market purchases with the
potential for accelerated
coal retirements.
• Increase procurement of
energy efficiency: energy
efficiency capacity is
accelerated and increases
by 108 MW by 2030.
• Through 2040, new non-
emitting peaking capacity is
increased by 412 MW.
• Through 2040, energy
efficiency is increased by 111
MW and solar co-located with
solar capacity is increased by
over 330 MW.
• Through 2040, market
purchases increase by an
average of 381 MW.
No NatriumTM
Advanced Nuclear
Demonstration
Project in 2028
See Volume 1,
Chapter 9,
Modeling and
Portfolio Selection
Results, P02e-No
Nuc portfolio
• Without the NatriumTM
demonstration project, 348
MW of solar co-located
with storage is added to the
portfolio in 2026 and an
additional 240 MW is
added in 2030.
• Higher costs and emissions
result from increased
fossil-fueled generation,
emissions and net market
transactions.
• In 2037, a non-emitting
peaker displaces solar co-
located with storagesolar co-
located with storage resource
capacity.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
343
Trigger Event
Planning
Scenario(s)
Near-Term Resource
Acquisition Strategy
(2021-2030)
Long Term Resource
Acquisition Strategy
(2031-2040)
No Boardman-to-
Hemingway (B2H)
transmission
segment in 2026
See Volume 1,
Chapter 9,
Modeling and
Portfolio Selection
Results, P02b-No
B2H portfolio
• Within the action plan
window, there would be no
change to the resource
procurement strategy
focused on an all-source
RFP and incremental
transmission upgrades.
• Without B2H, 405 MW of
wind and 200 MW of solar
co-located with storage is
removed from the portfolio
in 2026. Approximately
200 MW of storage
capacity is removed from
eastern Wyoming in 2029,
which must be replaced by
just over 200 MW of non-
emitting peaking capacity
in 2030.
• A reduction in resources
results in increased reliance
on the market and higher
emissions from an increase
in coal and gas generation.
• Reduced flexibility and
load-serving capability of
the transmission system.
• 725 MW of incremental 4-
hour battery resources and
other transmission upgrades
would be needed in southern
Oregon if the B2H
transmission line is not built.
Procurement Delays
The main procurement risk is an inability to procure resources in the required timeframe to meet
the least-cost, least-risk mix of resources identified in the preferred portfolio. There are various
reasons why a particular proxy resource cannot be procured in the timeframe identified in the 2019
IRP. There may not be any cost-effective opportunities available through an RFP, the successful
RFP bidder may experience delays in permitting and/or default on their obligations, or there might
be a material and sudden change in the market for fuel and materials. Moreover, there is always
the risk of unforeseen environmental or other electric utility regulations that may influence the
PacifiCorp’s entire resource procurement strategy.
Possible paths PacifiCorp could take in the event of a procurement delay or sudden change in
procurement need can include combinations of the following:
• In circumstances where PacifiCorp is engaged in an active RFP where a specific bidder is
unable to perform, alternative bids can be pursued.
• PacifiCorp can issue an emergency RFP for a specific resource and with specified
availability.
• PacifiCorp can seek to negotiate an accelerated delivery date of a potential resource with
the supplier/developer.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
344
• PacifiCorp can seek to procure near-term purchased power and transmission until a
longer-term alternative is identified, acquired through customized market RFPs,
exchange transactions, brokered transactions or bi-lateral, sole source procurement.
• Accelerate acquisition timelines for direct load control programs.
• Procure and install temporary generators to address some or all of the capacity needs.
• Temporarily drop below its planning reserve margin.
• Implement load control initiatives, including calls for load curtailment via existing load
curtailment contracts.
IRP Action Plan Linkage to Business Planning
The 2021 IRP includes a sensitivity that complies with the Utah requirement to perform a business
plan sensitivity case consistent with the commission’s order in Docket No. 15-035-04. This order
sets forth the following parameters for this sensitivity case:
• Over the first three years, resources align with those assumed in PacifiCorp’s December
2020 Business Plan.
• Beyond the first three years of the study period, unit retirement assumptions are aligned
with the preferred portfolio.
• All other resources are optimized.
PacifiCorp will file a supplemental filing to its 2021 IRP filing that includes discussion and results
of the sensitivities outlined in Volume I, Chapter 9 – Modeling and Portfolio Selection Results,
including a discussion of this business plan sensitivity case summarizing portfolio differences
between the business plan sensitivity case and the 2021 IRP preferred portfolio, including changes
to the resource mix, present value revenue requirement of system costs, and implications on the
near-term action plan. The supplemental filing will also be posted to PacifiCorp’s IRP webpage at
the following location: www.pacificorp.com/energy/integrated-resource-plan.
Resource Procurement Strategy
To acquire resources outlined in the 2021 IRP action plan, PacifiCorp intends to continue using
competitive solicitation processes in accordance with applicable laws, rules, and/or guidelines in
each of the states in which PacifiCorp operates. PacifiCorp will also continue to pursue
opportunistic acquisitions identified outside of a competitive procurement process that provide
economic benefits to customers. Regardless of the method for acquiring resources, PacifiCorp will
support its resource procurement activities with the appropriate financial analysis using then-
current assumptions for inputs such as load forecasts, commodity prices, resource costs, and policy
developments. Any such financial analysis will account for any applicable long-term system
benefits with least-cost, least-risk planning principles in mind. The sections below profile the
general procurement approaches for the key resource categories covered in the 2021 IRP action
plan.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
345
Renewable Resources, Storage Resources, and Dispatchable Resources
PacifiCorp will use a competitive RFPs to procure supply-side resources consistent applicable
laws, rules, and/or guidelines in each of the states in which PacifiCorp operates. In Oregon and
Utah, these state requirements involve the oversight of an independent evaluator. In Washington,
an independent evaluator may be used if benchmark resources (PacifiCorp built and owned
resources) are being considered after consultation with Washington staff and stakeholders. The
all-source RFPs outline the types of resources being pursued, defines specific information required
of potential bidders and details both price and non-price scoring metrics that will be used to
evaluate proposals.
Renewable Energy Credits
PacifiCorp uses shelf RFPs as the primary mechanism under which REC RFPs and reverse REC
RFPs will be issued to the market. The shelf RFPs are updated to define the product definition,
timing, and volume and further provide schedule and other applicable criteria to bidders.
Demand-Side Management
PacifiCorp offers a robust portfolio of Class 1 (demand response and direct-load control) and Class
2 (energy efficiency) DSM programs and initiatives, most of which are offered in multiple states,
depending on size of the opportunity and the need. Programs are reassessed on a regular bases.
PacifiCorp provides Class 4 DSM offerings, and has continued wattsmart outreach and
communications. Educating customers regarding energy efficiency and load management
opportunities is an important component of PacifiCorp’s long-term resource acquisition plan.
PacifiCorp will continue to evaluate how to best incorporate potential Class 1 DSM programs into
the broader all-source RFP process discussed above.
Assessment of Owning Assets versus Purchasing Power
As PacifiCorp acquires new resources, it will need to determine whether it is better to own a
resource or purchase power from another party. While the ultimate decision will be made at the
time resources are acquired, and will primarily be based on cost, there are other considerations that
may be relevant.
With owned resources, PacifiCorp is in a better position to control costs, make life extension
improvements (as was implemented with the wind repower project), use the site for additional
resources in the future, change fueling strategies or sources (as was implemented for the Naughton
Unit 3 gas conversion and as planned for Jim Bridger Units 1 and 2), efficiently address plant
modifications that may be required as a result of changes in environmental or other laws and
regulations, and use the plant at embedded cost as long as it remains economic. In addition, by
owning a plant, PacifiCorp can hedge itself against the uncertainty of third-party performance
consistent with the terms and conditions outlined in a power-purchase agreement over time.
Alternately and depending on contractual terms, purchasing power from a third party in a long-
term contract may help mitigate and may avoid liabilities associated with closure of a plant. A
long-term power-purchase agreement relinquishes control of construction cost, schedule, ongoing
costs and environmental and regulatory compliance. Power-purchase agreements can also protect
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
346
and cap the buyer’s exposure to events that may not cover actual seller financial impacts. However,
credit rating agencies can impute debt associated with long-term resource contracts that may result
from a competitive procurement process, and such imputation may affect PacifiCorp’s credit ratios
and credit rating.
Managing Carbon Risk for Existing Plants
CO2 reduction regulations at the federal, regional, or state levels could prompt PacifiCorp to
continue to look for measures to lower CO2 emissions of fossil-fired power plants through cost-
effective means. The cost, timing, and compliance flexibility afforded by CO2 reduction rules will
impact what types of measures might be cost effective and practical from operational and
regulatory perspectives. As evident in the 2021 IRP, known and prospective environmental
regulations can impact utilization of resources and investment decisions.
Compliance strategies will be affected by how and whether states or the federal government choose
to implement greenhouse gas policies. State or federal frameworks could impute a carbon tax or
implement a cap-and-trade framework. Under a cap-and-trade policy framework, examples of
factors affecting carbon compliance strategies include the allocation of emission allowances, the
cost of allowances in the market, and any flexible compliance mechanisms such as opportunities
to use carbon offsets, allowance/offset banking and borrowing, and safety valve mechanisms.
Under a CO2 tax framework, the tax level and details around how the tax might be assessed would
affect compliance strategies.
To lower the emission levels for existing fossil-fired power plants, options include changes in plant
dispatch, unit retirements, changing the fuel type, deployment of plant efficiency improvement
projects, and adoption of new technologies such as CO2 capture with sequestration. As mentioned
above, plant CO2 emission risk may also be addressed by acquiring offsets or other environmental
attributes that could become available in the market under certain regulatory frameworks.
PacifiCorp’s compliance strategies will evolve and continue to be reassessed in future IRP cycles
as market forces and regulatory outcomes evolve.
Purpose of Hedging
While PacifiCorp focuses every day on minimizing net power costs for customers, the company
also focuses every day on mitigating price risk to customers, which is done through hedging
consistent with a robust risk management policy. For years PacifiCorp has followed a consistent
hedging program that limits risk to customers, has tracked risk metrics assiduously and has
diligently documented hedging activities. PacifiCorp’s risk management policy and hedging
program exists to achieve the following goals: (1) ensure reliable sources of electric power are
available to meet PacifiCorp’s customers’ needs; (2) reduce volatility of net power costs for
PacifiCorp’s customers. PacifiCorp does not engage in a material amount of proprietary trading
activities. Hedging is done solely for the purpose of limiting financial losses due to unfavorable
wholesale market changes. Hedging modifies the potential losses and gains in net power costs
associated with wholesale market price changes. The purpose of hedging is not to reduce or
minimize net power costs. PacifiCorp cannot predict the direction or sustainability of changes in
forward prices. Therefore, PacifiCorp hedges, in the forward market, to reduce the volatility of net
power costs consistent with good industry practice as documented in the company’s risk
management policy.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
347
Risk Management Policy and Hedging Program
PacifiCorp’s risk management policy and hedging program were designed to follow electric
industry best practices and are reviewed at least annually by the company’s risk oversight
committee. The risk oversight committee includes PacifiCorp representatives from the front office,
finance, risk management, treasury, and legal department. The risk oversight committee makes
recommendations to the president of Pacific Power, who ultimately must approve any change to
the risk management policy.
The main components of PacifiCorp’s risk management policy and hedging program are natural
gas percent hedged volume limits and power volume hedge limits. These limits force PacifiCorp
to monitor the open positions it holds in power and natural gas on behalf of its customers on a
daily basis and limit the size of short positions by prescribed time frames in order to reduce
customer exposure to price concentration and price volatility. The hedge program requires
purchases of natural gas and power at fixed prices in gradual stages in advance of when it is
required to reduce the size of short positions and associated customer risk.
Dollar cost averaging is the term used to describe gradually hedging over a period of time rather
than all at once. This method of hedging, which is widely used by many utilities, captures
time diversification and eliminates speculative bursts of market timing activity. Its use means that
at times PacifiCorp buys at relatively higher prices and at other times relatively lower prices,
essentially capturing an array of prices at many levels. While doing so, PacifiCorp steadily and
adaptively meets its hedge goals through the use of this technique while staying within power
volume hedge limits and natural gas percent hedge volume limits.
Cost Minimization
While hedging does not minimize net power costs, PacifiCorp takes many actions to minimize net
power costs for customers. First, the company is engaged in integrated resource planning to plan
resource acquisitions that are anticipated to provide the lowest cost resources to our customers in
the long-run. PacifiCorp then issues competitive requests for proposals to assure that the resources
we acquire are the lowest cost resources available on a risk-adjusted basis. In operations,
PacifiCorp optimizes its portfolio of resources on behalf of customers by maintaining and
operating a portfolio of assets that diversifies customer exposure to fuel, power market and
emissions risk and utilize an extensive transmission network that provides access to markets across
the western United States. Independent of any natural gas and electric price hedging activity, to
provide reliable supply and minimize net power costs for customers, PacifiCorp commits
generation units daily, dispatches in real time all economic generation resources and all must-take
contract resources, serves retail load, and then sells any excess generation to generate wholesale
revenue to reduce net power costs for customers. PacifiCorp also purchases power when it is less
expensive to purchase power than to generate power from our owned and contracted resources.
Hedging cannot be used to minimize net power costs. Hedging does not produce a different
expected outcome than not hedging and therefore cannot be considered a cost minimization tool.
Hedging is solely a tool to mitigate customer exposure to net power cost volatility and the risk of
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
348
adverse price movement. However, PacifiCorp does minimize the cost of hedging by transacting
in liquid markets and utilizing robust protections to mitigate the risk of counterparty default.
Portfolio
PacifiCorp has a short position in natural gas because of its ownership of gas-fired electric
generation that requires it to purchase large quantities of natural gas to generate electricity to serve
its customers. PacifiCorp may have short or long positions in power depending on the shortfall or
excess of the company’s total generation capacity relative to customer load requirements at a given
point in time.
Instruments
PacifiCorp’s hedging program allows the use of several instruments including financial swaps,
fixed price physical and options for these products. PacifiCorp chooses instruments that generally
have greater liquidity and lower transaction costs.
Treatment of Customer and Investor Risks
The IRP standards and guidelines in Utah require that PacifiCorp “identify which risks will be
borne by ratepayers and which will be borne by shareholders.” This section addresses this
requirement. Three types of risk are covered: stochastic risk, capital cost risk, and scenario risk.
Stochastic Risk Assessment
Several of the uncertain variables that pose cost risks to different IRP resource portfolios are
quantified in the IRP production cost model using stochastic statistical tools. The variables
addressed with such tools include retail loads, natural gas prices, wholesale electricity prices,
hydroelectric generation, and thermal unit availability. Changes in these variables that occur over
the long-term are typically reflected in normalized revenue requirements and are thus borne by
customers. Unexpected variations in these elements are normally not reflected in rates, and are
therefore borne by investors unless specific regulatory mechanisms provide otherwise.
Consequently, over time, these risks are shared between customers and investors. Between rate
cases, investors bear these risks. Over a period of years, changes in prudently incurred costs will
be reflected in rates and customers will bear the risk.
Capital Cost Risks
The actual cost of a generating or transmission asset is expected to vary from the cost assumed in
the IRP. State commissions may determine that a portion of the cost of an asset was imprudent and
therefore should not be included in the determination of rates. The risk of such a determination is
borne by investors. To the extent that capital costs vary from those assumed in this IRP for reasons
that do not reflect imprudence by PacifiCorp, the risks are borne by customers.
Scenario Risk Assessment
Scenario risk assessment pertains to abrupt or fundamental changes to variables that are
appropriately handled by scenario analysis as opposed to representation by a statistical process or
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
349
expected-value forecast. The single most important scenario risks of this type facing PacifiCorp
continues to be government actions related to emissions and changes in load and transmission
infrastructure. These scenario risks relate to the uncertainty in predicting the scope, timing, and
cost impact of emission and policies and renewable standard compliance rules.
To address these risks, PacifiCorp evaluates resources in the IRP and for competitive procurements
using a range of CO2 policy assumptions consistent with the scenario analysis methodology
adopted for PacifiCorp’s 2021 IRP portfolio development and evaluation process. The company’s
use of IRP sensitivity analysis covering different resource policy and cost assumptions also
addresses the need for consideration of scenario risks for long-term resource planning. The extent
to which future regulatory policy shifts do not align with PacifiCorp’s resource investments
determined to be prudent by state commissions is a risk borne by customers.
PACIFICORP – 2021 IRP CHAPTER 10 – ACTION PLAN
350