HomeMy WebLinkAbout20210325Order_No_34971.pdfORDER NO. 34971 1
Office of the Secretary
Service Date
March 25, 2021
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
This matter comes before the Commission on PacifiCorp’s dba Rocky Mountain Power
(“Company”) unopposed motion for stay (“Motion”). By way of background, on December 3,
2020, the Company applied to extend its energy sales agreement with Amy Family Holdings, LLC
(“Seller”) for one year. The point of the one-year extension was to allow the Company and Seller
to complete upgrades for a new stand-alone interconnection agreement. After the Company filed
its Application to extend the agreement’s term, however, the Seller significantly progressed on the
new interconnection provisions to the point the Company is confident the Seller now can complete
the interconnection before the energy sales agreement expires. The Company has thus moved the
Commission to Stay its Application to extend the energy sale agreement’s term for one-year
because the Company believes the extension may no longer be necessary.
Having reviewed the Company’s Motion, the Commission finds it reasonable to grant
the Company’s Motion.
O R D E R
IT IS HEREBY ORDERED that the Company’s Motion is granted. This case is stayed.
If the Seller has not completed its interconnection requirements by October 15, 2021, the Company
must seek continuance in this case to allow the Commission to fully process its Application before
the December 31, 2021 expiration.
IT IS FURTHER ORDERED that parties should continue to comply with Order No.
34781, issued September 17, 2020. All pleadings should be filed with the Commission
electronically and shall be deemed timely filed when received by the Commission Secretary. See
Rule 14.02. Service between parties should also be accomplished electronically. Voluminous
discovery-related documents may be filed and served on CD-ROM or a USB flash drive.
IN THE MATTER OF ROCKY MOUNTAIN
POWER’S APPLICATION FOR APPROVAL
OR REJECTION OF AN ENERGY SALES
AGREEMENT WITH AMY FAMILY
HOLDINGS, LLC
)
)
)
)
)
CASE NO. PAC-E-20-18
ORDER NO. 34971
ORDER NO. 34971 2
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 25th
day of March 2021.
PAUL KJELLANDER, PRESIDENT
KRISTINE RAPER, COMMISSIONER
ERIC ANDERSON, COMMISSIONER
ATTEST:
Jan Noriyuki
Commission Secretary
I:\Legal\ELECTRIC\PAC-E-20-18\Orders\PACE2018_stay_dh.docx