HomeMy WebLinkAbout20190329Decision Memo.pdfDECISION MEMORANDUM
TO:COMMISSIONER KJELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM:EDWARD JEWELL
DEPUTY ATTORNEY GENERAL
DATE: MARCH 29,2019
SUBJECT:IN THE MATTER OF'THE APPLICATION OF ROCKY MOUNTAIN
POWER FOR AUTHORITY TO MODIFY SCHEDULE NO. 135 _ NET
METERING SERVICE; CASE NO. PAC-E-19-03.
On March 75, 2019, Rocky Mountain Power ("Rocky Mountain" or "Company")
filed an Application seeking approval of a modification to its Electric Service Schedule No. 135
- Net Metering Service ("Schedule No. 135"). The Company requests an effective date of May
t5,2019.
THE APPLICATION
The Company seeks a modification to Schedule No. 135 to allow customers to
transfer financial credits once per year between meters that are owned by the same customer and
located on the same or contiguous premises as the meter with excess financial credits, so long as
the meters are served by the same primary feeder and are on the same rate schedule.
STAFF RECOMMENDATION
Staff recommends the Commission issue a Notice of Suspension, Notice of
Application, and Notice of Modified Procedure suspending the proposed effective date and
setting a June 12,2019 comment deadline and a June 19,2019 reply comment deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Suspension, Notice of Application,
and Notice of Modified Procedure suspending the proposed effective date and setting a June 12,
2019 comment deadline and a June 19, 2019 reply comment deadline?
Edward J
DECISION MEMORANDUM
I :\Legal\ELECTRIC\PAc-E- I 9-03\PACE I 903-dec memo-ej
I
Deputy General
(