HomeMy WebLinkAbout20190117notice_of_modified_procedure_order_no_34230.pdfOffice of the Secretary
Service Date
January 17,2019
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION )CASE NO.PAC-E-18-12
OF ROCKY MOUNTAIN POWER TO )DECREASE ELECTRIC SERVICE )NOTICE OF
SCHEDULE 191 -CUSTOMER EFFICIENCY )MODIFIED PROCEDURE
SERVICES RATE )
)ORDER NO.34230
On November 9,2018,Rocky Mountain Power ("Company")filed an Application
seeking authorization to decrease the collection rate applied to customer bills for energy
efficiency measures.The Company states that as of September 30,2018,the balance in its
account for energy efficiencymeasures is over-collected by $2.1 million.
On November 29,2018,the Commission issued a Notice of Application and Notice
of Intervention Deadline setting an intervention deadline of December 19,2018,and suspending
the Company's proposed effective date of January 1,2019.Order No.34198.No parties
intervened.On January 7,2019,the Commission Secretary issued a Notice of Parties.Staff
informally conferred with the Company regarding procedure and scheduling.Now,the
Commission issues this Notice of Modified Procedure setting comment and reply deadlines.
NOTICE OF MODIFIED PROCEDURE
YOU ARE HEREBY NOTIFIED that the Commission has determined that the public
interest may not require a formal hearing in this matter and will proceed under Modified
Procedure pursuant to Rules 201 through 204 of the Idaho Public Utilities Commission's Rules
of Procedure,IDAPA 31.01.01.201 through .204.The Commission notes that Modified
Procedure and written comments have proven to be an effective means for obtaining public input
and participation.
YOU ARE FURTHER NOTIFIED that any person desiring to state a position on this
Application may file a written comment in support or opposition with the Commission no later
than February 7,2019.The comment must contain a statement of reasons supporting the
comment.Persons desiring a hearing must specifically request a hearing in their written
comments.Written comments concerning this Application shall be mailed to the Commission
and Rocky Mountain Power at the addresses reflected below:
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34230 1
For the Commission:For the Company:
Commission Secretary Ted Weston
Idaho Public Utilities Commission Michael Snow
PO Box 83720 1407 W.North Temple,Suite 330
Boise,ID 83720-0074 Salt Lake City,Utah 84116
E-Mail:
Street Address for Express Mail:
472 W.Washington Street Daniel E.Solander
Boise,ID 83702-5918 1407 W.North Temple,Suite 320
Salt Lake City,Utah 84116
These comments should contain the case caption and case number shown on the first page of this
document.Persons desiring to submit comments via e-mail may do so by accessing the
Commission's home page located at .Click the "Case Comment or Question
Form"under the "Consumers"tab,and complete the comment form using the case number as it
appears on the front of this document.These comments must also be sent to Rocky Mountain
Power at the e-mail addresses listed above.
YOU ARE FURTHER NOTIFIED that the Company shall file reply comments,if
necessary,no later than February 14,2019.
YOU ARE FURTHER NOTIFIED that the Application and supporting workpapers
and exhibits have been filed with the Commission and are available for public inspection during
regular business hours at the Commission offices.The Application and testimonies are also
available on the Commission's web site at .Click on the "File Room"tab at
the top of the page,scroll down to the type of "Open Electric Cases,"and then click on the case
number as shown on the front of this document.
YOU ARE FURTHER NOTIFIED that all proceedings in this case will be held
pursuant to the Commission's jurisdiction under Title 61 of the Idaho Code and specifically
Idaho Code §§61-307,61-503,and 61-622.The Commission may enter any final Order
consistent with its authorityunder Title 61.
YOU ARE FURTHER NOTIFIED that all proceedings in this matter will be
conducted pursuant to the Commission's Rules of Procedure,IDAPA 31.01.01.000 et seq.
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34230 2
ORDER
IT IS HEREBY ORDERED that this case be processed under Modified Procedure.
Parties and any interested persons wishing to file comments or protests in this matter must do so
by no later than February 7,2019.
IT IS FURTHER ORDERED that any reply comments be filed by no later than
February 14,2019.
DONE by Order of the Idaho Public Utilities Commission at Boise,Idaho this /
day of January 2019.
PAUL K -LLAN ,PRESIDENT
KRISTINE RAPER,CO SIONER
ERIC ANDERSON,COMMISSIONER
Diane M.Hanian
Commission Secretary
I:\Legal\ELECTRIC\PAC-E-18-12\PACE1812_ntemod proc_ej
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34230 3