HomeMy WebLinkAbout20180615Decision Memo.pdfDECISION MEMORANDUM TO COMMISSIONER KJELLANDER COMMISSIONER RAPER COMMISSIONER ANDERSON COMMISSION SECRETARY COMMISSION STAFF LEGAL FROM:YAO YIN SEAN COSTELLO, DAG DATE: JUNE 14,2018 SUBJECT:CASE NO. GNR.E.I8.O2 ANNUAL REVISION AND UPDATED CALCULATION OF THE ADJUSTABLE PORTION OF THE AVOIDED COST RATE FOR EXISTING PURPA CONTRACTS FOR AVISTA CORPORATION DBA AVISTA UTILITIES, FOR IDAHO POWER COMPANY, AND FOR PACIFICORP DBA ROCKY MOUNTAIN POWER CASE NO. PAC.E.18-05 ANNUAL REVISION OT QF VARIABLE ENERGY PRICES PURSUANT TO TERMS OF THE T992 AMENDMENTS TO POWER PURCHASE AGREEMENTS BETWEEN IDAHO QFS AND PACIFICORP The Idaho Public Utilities Commission in Order No. 28708, Case No. GNR-E-99-1, established a methodology for the annual adjustable rate portion of avoided costs for those QF contracts using variable costs associated with Colstrip, a coal-fired generating facility in southeast Montana. For those QF contracts with Colstrip-related fuel costs and variable O&M, future Colstrip variable cost adjustments are to be calculated by using FERC Form I Colstrip Unit Coal Costs per megawatt hour (MWh) and adding $2.00/MWh (the average variable O&M cost of Colstrip plus 20plMWh for generation taxes plus a five percent (5%) adjustment for line loss). As computed by Commission Staff, the Colstrip related adjustable rate will change from 17.61 milllkWh to 16.54 mill/kWh (see Attachment l). The same calculated rate revision under the avoided cost methodology is used by Avista, PacifiCorp dba Rocky Mountain Power, and Idaho Power Company. This change in the variable rate affects existing contracts under the previous SAR methodology. DECISION MEMORANDUM I The adjustable portion of the avoided cost rates under the Sumas-based methodology is based on annual average gas prices indexed at Sumas, Washington. As reported by Avista, the indexed gas prices have increased by $0.59/MMBtu. The approved gas price of $2.85/MMBtu plus the $0.59/MMBtu results in a gas price of $3.44lMMBtu for the 2018-2019 year (see Attachment 2). This equates to a SAR fuel cost of 24.42 mill/kWh as used in the model. The Commission Staff calculated changes to the annual adjustable rate portion of avoided costs for those QF contracts, using variable costs associated with Colstrip and Sumas, and provided the respective utilities with the updates for review by letter dated May 30,2018. Avista, Idaho Power, and PacifiCorp responded by letter that Staff s calculations are correct. In accordance with Order No. 29316, the adjustable portion of the avoided cost rate for PacifiCorp contracts with 1992 amendments has also been recomputed. Beginning on July 1, 2003, the adjustable portion for these contracts was ordered to be equal to the average cost of fuel for the Carbon, Hale, Naughton, Huntington, and Hunter generating plants, including a variable O&M component of $1.51 but exclusive of generation taxes and a line loss adjustment. The variable energy rate applicable to deliveries commencing July 1,2018 extending through June 30,2019 has been computed to be$23.67lMWh, an increase from $23.294{Wh last year. Staff confirmed that PacifiCorp's calculations are correct (see Attachment 3). COMMISSION DECISION Under avoided cost methodology the adjustable portion of avoided cost rates for existing contracts is calculated annually for an effective date of July l. Avista, Idaho Power, and PacifiCorp agree with Staffs proposed calculations. Also adjusted annually is the adjustable portion of avoided cost rates for existing PacifiCorp contracts with year 1992 amendments. For those contracts, PacifiCorp has correctly computed the new variable energy rate. Does the Commission agree with the proposed changes in the variable rates? Sean Costello Deputy Attorney General CNRE | 802_PACE I 805-Dec Memo__yy-sc 2DECISION MEMORANDUM COLSTRIP ADJUSTABLE RATE CALCULATION Updated For Period 7 11 118-6130/19 Colstrip Fuel Cost from Avista FERC Form 1 lor CY 2017 line 12 Net Generation (kwh) line 20 Fuel Fuel cost per kwh FuelCost per MWh Variable O&M, Gen. Tax, 57o line loss per MWh Total Colstrip Adjustable Rate ReferenceGNR-E-99-l O.N.28708 4117l2OO1 1 ,423,319,000 $20,697,118 $0.014541 $14.5414 $2.oooo $16.5414 Colstrip_'18-19 Attachment I Average Gas Prices at Sumas, Washington from Inside FERC publication ($/MMBtu) Calculating the 2017-2018 Avoided Cost Adjustable Rate Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec 2016 s2.57 $2.1 0 $ l.4l $r.42 $ 1.34 s1.46 $2.28 s2.34 $2.63 $2.64 $2.62 s3.27 2017 $4.8s $3. l7 $2.20 $2.34 s2.42 $2.70 s2.29 $2.48 $2.s6 $2.3s s2.65 $3.1s Average $2.173 $2.763 Ac@ $2.850 - ($2. 173 - $2.7 63) : $3.440 Note: $6.94lMMBtu : 2007-08 Approved Rate $7. I 8/MMBtu : 2008-09 Approved Rate $9.00/MMBtu : 2009- 10 Approved Rate $4.62lMMBtu : 2010-1 1 Approved Rate S4.99lMMBtu : 201 1-12 Approved Rate $4.60/MMBtu : 2012-13 Approved Rate $3.45lMMBtu : 201 3- 14 Approved Rate S4.35/MMBtu : 2014-15 Approved Rate $5. lO/MMBtu : 201 5- 16 Approved Rate 53.092/MMBtu = 2016-17 Approved Rate $2.850/MMBtu : 2017 -18 Approved Rate Attachment 2 PacifiCorp Total Variable Energy Rate for 2018 , 2019 Carbon Naughton $ 105,045,552 Huntington $ 138,300,998 Hunter s 145,938,639 Totals $ 389,28s,189Fuel Cost ($) $ 2017 FERC FORM I - Page 402 Linc 20 Generation (MVVH) 2017 FERC FORM 1 - Pagt 402 Linc 12 Average Fuel Cost ($/MVWI Variable O&M Total Variable Energy Rate for 201812019 For deliveries commencing July 1, 2018 extending through June 30, 2019 12 PacifiCorp/QFs contracts with approved 1992 amendment language 4,740,158 5,399,777 7 ,429,297 17,569,232 22.16 't.51 23.67 S S $ /MV1/l-l /M\ /t-l /MV1/t-l Attachment 3