Loading...
HomeMy WebLinkAbout20180824Cross Petition for Reconsideration.pdfROCKY MOUNTAIN HP,H,E,^n.,, NEC EIVED ?$18 i,UG 2lr ?H 2:21 1407 West North Temple, Suite 330 Salt Lake City, Utah 841 '16 August 24,2018 VA HAND DELIVERY Diane Hanian Commission Secretary Idaho Public Utilities Commission 472W. Washington Boise,ID 83702 Re cAsE NO. PAC-E-17-07 IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR CERTIFICATES OF PUBLIC CONVENIENCE AIYD NECESSITY AI\TD BINDING RATEMAKING TREATMENT FOR NEW WII\D AND TRANSMISSION FACILITIES Attention: Ms. Hanian Please find enclosed for filing an original and seven (7) copies of Rocky Mountain Power's Answer to Cross Petitions for clarification or, in the alternative, reconsideration of final Order No. 34104, dated July 20,2018. Informal inquiries may be directed to Ted Weston, Idaho Regulatory Manager at (801) 220-2963 Very truly yours, ! t,^Ll\Jr..ttQ ""^-DJSteward Vice President, Yvonne R. Hogle (#8930) 1407 West North Temple, Suite 320 Salt Lake City, Utah 841 l6 Telephone : (80 l) 220-47 3 4 Facsimile: (801) 220-3299 Email : Lvonne.ho gle@pac i fi corp.corn Katherine McDowell Adam Lowney (#10456) McDowell Rackner Gibson PC 419 SW I lth Avenue, Suite 400 Portland, Oregon 97205 Telephone : (503) 595-3924 Facsimile: (503) 595-3928 Email: katherine@mrg-law.com adam@mrg-law.com Attorneys for Rocky Mountain Power BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR CERTIFICATES OF PUBLIC CONVEMENCE AND NECESSITY AND BINDING RATEMAKING TREATMENT FOR WIND AND TMNSMISSION FACILITIES CASE NO. PAC.E-I7-07 ROCKY MOI]NTAIN POWER'S REPLY ANI) ANSWER TO CROSS. PETITIONS FOR RECONSIDERATION ) ) ) ) ) ) ) ) ) I. INTRODUCTION On August 10,2018, Rocky Mountain Power ("Company"), filed a petition for clarification or, in the altemative, reconsideration of final Order No. 34104, issued on July 20, 2018, in Case No. PAC-E-I7-07 ("Order") by the Public Utilities Commission of Idaho ("Commission"). On August 17, 2018, Monsanto Corporation ("Monsanto"), the PacifiCorp Idaho Industrial Customers ("PI[C"), and the Idaho Irrigation Pumpers Association, Inc. ("IIPA") filed answers and cross-petitions for reconsideration under Rule 331 of the Commission's Rule of Procedure (IDAPA 31.01.01.331). Three days REPLY AND ANSWER TO CROSS.PETITIONS FOR RECONSIDERATION Page I later, on August 20,2018, Commission Staff filed its answer. In accordance with Idaho Code 5 6l-626, and Commission Rules of Procedure 325 and 331-333 (IDAPA 31.01.01 .325 and 31.01.01.331-333), the Company submits this answer and reply to the cross-petitions for reconsideration. The Commission's rules are silent about the right to file an answer and reply in this context, so the Company requests leave to make this filing. The Company's reply and answer provides the Commission with a more complete record on which to grant clarification or reconsideration and outlines the Company's arguments if reconsideration is granted. First, the Company's request for reconsideration is not prohibited by the stipulation by and between the Company and Staff, dated May 8,2018 ("Stipulation"), as Staff alleges in its answer, because the Stipulation specifically provides that each party reserved all rights to argue for or against the imposition of a cost cap. Second, while the other parties disagree with the Company's interpretation of the Order, they appear generally supportive of the Company's request that the Commission clariff the Order. Third, a reasonable reading of the Order, together with the testimony, supports the Company's interpretation that the Commission did not intend to impose a hard cap that would bind future Commissions and categorically preclude recovery of prudent costs incurred in the public interest. Fourth, PIIC requests reconsideration of the imposition of an overall cost cap, rather than individual cost caps for the discrete projects. PIIC provides no evidence or other justification for this position. The Company's economic analysis addressed the overall project costs and any cost cap should therefore apply to overall project costs. REPLY AND ANSWER TO CROSS-PETITIONS FOR RECONSIDERATION Page2 Finally, the Commission should reject the conditional cross-petitions for reconsideration from Monsanto, IIPA, and PIIC, asking the Commission to deny the certificate of public convenience and necessity ("CPCN") for the Company's proposed wind and transmission projects ("Combined Projects") unless a hard cap is imposed. The extensive record demonstrates that the Combined Projects are the least-cost, least-risk resources to meet the Company's resource needs. There is no basis for the Commission to reconsider its conclusion that the "evidence shows that the future need for new generation facilities is most efficiently, effectively and reasonably met with the proposed projects (as modified herein) because the economic benefit captured through the [production tax credits] is in the public interest." Order at 8. II. ARGUMENT A. The Commission should clariff that the cost cap does not preclude recovery of prudently incurred costs that advance the public interest. 1. The Company's petition for clarification and/or reconsideration was consistent with the Stipulation. Staff argues that the Company's petition is prohibited by paragraph 26 of the Stipulation. Staff s Answer to Rocky Mountain Power's Petition for Clarification or, in the Alternative, Reconsideration ("Staff Answer") at 5. That paragraph provides if the Commission "imposes any additional material conditions on approval of this Stipulation," the Company can seek reconsideration only after providing formal notice within 15 days of its intent to withdraw from the Stipulation. Staff claims that the cost cap was imposed as a condition of approving the Stipulation, invoking the l5-day notice requirement. Staff Answer at 6. Staffs position ignores one of the central provisions of the Stipulation, in which the "Stipulating Parties reserve all rights to argue in this case for or against an overall REPLY AND ANSWER TO CROSS-PETITIONS FORRECONSIDERATION Page 3 capital cost cap for construction of the Stipulated Projects." Stipulation, fl 16. This provision excluded the cost cap from the Stipulation-including paragraph 26-and ensured that the Company "reserve[d] all rights" to dispute the imposition of such a cap. The specific reservation of rights on the cost cap issue applies here, not the general, boilerplate language on which Staff relies. Put another way, the Company's petition addresses an issue specifically carved out of the Stipulation and cannot, therefore, violate the terms of that Stipulation. 2. The parties' answers demonstrate the need for clarification of the overall cost cap imposed by the Commission. Staff argues that when parties described an "overall cost cap," they "generally referred to it as a 'hard cap."' Staff Answer at 3. Staff supports this argument with citations to the record that largely confirm the opposite conclusion. That is, when parties described Staff s proposed cost cap, they described it as a "hard" cap. For example, Staff cites Cindy Crane's cross-examination testimony as evidence that parties used the term "overall project cost cap" to mean a hard cap. Tr. 790. But in that testimony, when Ms. Crane was asked about an "overall project cost cap," she requested clarification on whether the question addressed the soft or hard cap at issue in the case. This example demonstrates that the term "cost cap" was generally used to describe both Staffs proposed hard cap and the Company's proposed soft cap. The Commission specifically described Staffs position as a hard cap in the Order, and then imposed an overall project cost cap without describing it as a hard cap. This, combined with the Commission's rejection of binding ratemaking treatment (which is what a hard cap is), creates the reasonable inference that the Commission intended to impose a cap that does not categorically preclude recovery of prudently incurred costs REPLY AND ANSWER TO CROSS-PETITIONS FOR RECONSIDERATION Page 4 regardless of the circumstances. Staff and PIIC claim that the Stipulation itself indicates that the "overall capital cost cap" means Staff s proposed hard cap because that is how the agreement describes the outstanding dispute between the Company and Staff. Staff Answer at 4; PIIC's Cross-Petition for Clarification and Reconsideration at 2 ("PIIC Cross-Petition"). But the testimony supporting the Stipulation provides greater clarity regarding how that term was intended. Staff s pre-filed testimony states that the "only issue not resolved between the Company and Commission Staff in the Stipulation relates to an overall cost cap." Tr. 1920. Staffls testimony then states that "Staff believes an overall Hard Cap is necessary to reduce the risk that these economic projects do not provide benefits to customers," while the Company "has proposed a soft cap." Tr. 1920; see also Tr. 1923 (Staff testimony at hearing describing that the Stipulation "caps" the costs at the benefits for the resource tracking mechanism ("RTM"), but Staff also recommends "hard cap"). Staff also claims that the Commission's denial of binding ratemaking treatment applied only to the RTM, implying that the Commission did grant binding ratemaking treatment when it imposed the cost cap. Staff Answer at 4,7 (suggesting the cost cap is authorized by Idaho Code $ 6l-541). But without an express statement in the Order binding future Commissions, it is unreasonable to interpret the cost cap as a hard cap authorized by Idaho Code $ 6l-541. Staff also claims that there is precedent for a hard cap set at the Company's estimates because the Company agreed to a hard cap in Wyoming. Staff Answer at7.ln fact, the Wyoming settlement includes a hard cap that is I I percent above the current estimate and is part of a larger overall settlement that included additional issues. Tr.l42- REPLY AND ANSWER TO CROSS.PETITIONS FOR RECONSIDERATION Page 5 144. And, as noted in the Company's Petition, the Utah Commission rejected proposals for a hard cap that "would preclude PacifiCorp from recovering an increase in [capital] costs even where incurring the increase was prudent[.]"I Staff did not identifu any precedent from this Commission or elsewhere for a hard cap at the current cost estimate. B. The Commission should deny the cross-petitions for reconsideration. If the Commission grants the Company's request for reconsideration, it may also address the parties' cross-petitions for reconsideration. Idaho Code $ 6l-626. If the Commission denies the Company's request, however, it must also deny all of the cross petitions. 1d The Company requests that the Commission grant its request for reconsideration but deny the cross-petitions. 1. If a cost cap is imposed, it should be an overall cap applied to the Combined Projects. PIIC requests that the Commission reconsider the imposition of an overall cost cap, and instead impose individual caps on each of the components of the Combined Projects (i.e., one cap for the wind projects, one for the network upgrades, and one for the transmission line). PIIC simply refers to its pre-filed testimony to support this request and provides no other justification in its cross-petition. PIIC Cross-Petition at 9. But PIIC's pre-filed testimony provides no rationale for the recommendation. See Tr. l57l (describing but not justiffing project-specific cap recommendation). Thus, PIIC has provided no substantive explanation for its proposal to impose project-specific cost caps. For the same reasons that an overall cost cap is unreasonable, specific individual cost caps are also unreasonable. Moreover, the Company's economic analysis was based on I Application of RoclE Mountain Power for Approval of a SigniJicant Energt Resource Decision and Voluntary Request for Approval of Resource Decision, UPSC Docket No. l7-035-40, Order at 34 (Jtne 22, 201 8). REPLY AND ANSWER TO CROSS.PETITIONS FOR RECONSIDERATION Page 6 overall project costs, not the individual components. Therefore, to the extent that the cost cap is intended to better ensure the realization of customer benefits, there is no basis for imposing project-specifi c cost caps. 2. The Commission should not reconsider its approval of the CPCN. a. The Combined Projects meet a resource need. Monsanto, PIIC, and IIPA request that the Commission reconsider granting the CPCN because they claim there is no present need for the Combined Projects. Monsanto's Response to Rocky Mountain Power's Petition and Cross-Petition for Reconsideration at 6 ("Monsanto Cross-Petition"); see also PIIC Cross-Petition at 8. On the contrary, the record demonstrates that the Company has an immediate and sustained need for system capacity (Tr. 253, 263, 335-337) and the Combined Projects were identified as integral components of the least-cost, least-risk resource portfolio in the 2017 lntegrated Resource Plan ("IIU"';, which analyzed all methods of meeting customers' near and long-term resource needs, including energy efficiency, demand-side management, front-office transactions ("FOTs"), new supply-side resources, and changes in use of or upgrades to existing resources. Tr. 156-170,249-273; see In the Matter of Idaho Power Co. 's Applicotion for a Certificate of Public Convenience and Necessity for the Langley Gulch Power Plant, Case No. IPC-E-09-03, Order No. 30892 at 2l (Sept. l, 2009) ("Idaho Power's [IRP] is a planning document that constitutes the baseline against which the utility s performance and acquisition of supply-side and demand-side resources are ordinarily measured."). Moreover, the Commission found that the Combined Projects will meet a future resource need, which Monsanto appears to concede. Order at7-8; Monsanto Cross- Petition at 6 ("There being no present necessity for new capacity . . .") (emphasis added). REPLY AND ANSWER TO CROSS-PETITIONS FORRECONSIDERATION Page 7 So even if there is no present need for the Combined Projects (which the Company disputes), the Commission's finding that the Combined Projects meet a future need is sufficient to support a CPCN. ,See Idaho Code $ 6l-526 (requires that the "present or future public convenience and necessity will require" the new resource). b. The Combined Projects are least-cost,least-risk. Monsanto, PIIC, and IIPA also argue that the Combined Projects are not least- cost, least-risk resources and will not produce customer benefits. See Monsanto Cross- Petition at 7; PIJC Cross-Petition at 7-8; IIPA's Answer in Oppositions to RMP's Petition and Joinder in Monsanto's Cross Petition at 2. The Company's extensive and conservative economic analysis demonstrates the Commission correctly concluded that the Combined Projects will "most efficiently, effectively and reasonably" meet the need for new generation resources. Order at 8. The Company's modeling shows the Combined Projects are expected to provide substantial benefits to customers and reduce market risk. Tr. 152-153, 195-196, 401, 407, 586-87, 597, 668-669. The Commission relied on that modeling and reasonably concluded that "displacing FOTs with the Combined Projects[] is fair, just and reasonable because the costs passed on to the utility's customers will likely be demonstrably less." Order at 8. The Company also demonstrated that it is in the public interest to pursue the Combined Projects now and defer consideration of competing solar options. Tr.438-440, 527-528,555, 559-561. The Commission analyzed the evidence and concluded that the Company's "sensitivity analysis is convincing and demonstrates that solar resources cannot displace the Combined Projects." Order at 10. Moreover, the "record supports the Company's modeling assumptions, including projected benefits of pursuing both wind REPLY AND ANSWER TO CROSS-PETITIONS FOR RECONSIDERATION Page 8 and solar at a future date." Order at 10. The Commission also found that the Company will "need the transmission projects in the future." Order at 8. By constructing the line now, when its costs are offset by PTC-eligible wind resources, customers will receive a net benefit. Tr. 571-572;942- 944,966-971. 3. The Company has not increased its overall project cost estimate. PIIC argues that if "RMP now believes that its project costs are going to be higher than it anticipated, there is reason to conduct additional analysis and process to determine whether it continues to make economic sense for ratepayers to invest in the combined projects." PIIC Cross-Petition at 8. The flaw in this argument, however, is that the Company has not, in fact, changed its overall project cost estimate. Contrary to PIIC's implication, the Company has simply requested the opportunity to demonstrate in the future that costs incurred above its current estimate-if any-are prudent and in the public interest. III. CONCLUSION For the reasons stated in the Company's Petition for Clarification or, in the Alternative, Reconsideration, the Company respectfully requests that the Commission clarifr or grant reconsideration of Order No. 34104 to make clear that the overall cost cap does not categorically preclude the future recovery of prudent costs incurred in the public interest. In addition, for the reasons set fomh above, if the Commission grants the Company's petition for reconsideration, it should deny Monsanto's, PIIC's, and IIPA's cross-petitions for reconsideration. The Company's economic analyses demonstrates that the Combined Projects are in the'public interest, have beneficial near- and long-term customer impacts, and are lower risk than a do-nothing resource strategy across a broad REPLY AND ANSWER TO CROSS.PETITIONS FOR RECONSIDERATION Page 9 range of potential future market and system conditions. Dated this 24t of August, 2018. Respectfully submitted, West North Temple, Suite 320 Lake City, Utah 841l6 (801) 220-4734 Facsim ile : (80 1) 220-3299 Email: yvonne.hogle@pacifi corp.com Afforney for Rocky Mountain Power REPLY AND ANSWER TO CROSS-PETITIONS FOR RECONSIDERATION Page l0 CERTIF'ICATE OF SERVICE I hereby certiff that on this 24ft day of August, 2018, I caused to be served, via E-mail a true and correct copy of Rocky Mountain Power's REPLY AND ANSWER TO CROSS- PETITIONS FOR RECONSIDERATION in PAC-E-17-07 to the following: Service List IDAHO IRRIGATION PUMPERS ASSOCIATION, INC. Eric L. Olsen ECHO HAWK & OLSEN, PLLC 505 Pershing Ave., Ste. 100 P.O. Box 6l l9 Pocatello, Idaho 83205 E-mail : elo@echohawk.com Anthony Yankel 12700Lake Avenue, Unit 2505 Lakewood, Ohio 44107 E-mail: tony(@yankel.net MONSANTO COMPANY Randall C. Budge Racine, Olson, Nye & Budge, Chartered P.O. Box 1391;201E. Center Pocatello, Idaho 83204-1391 E-mail : rcb@racinelaw.net Brubaker & Associates 16690 Swingley Ridge Rd., #140 Chesterfield, MO 63017 E-mail: bcol I ins@consultbai.com kiverson@consultbai.corn PIIC Ronald L. Williams Williams Bradbury, P.C. P.O. Box 388 Boise ID, 83701 E-mail : ron@wil I iamsbradburv.conr Jim Duke Idahoan Foods E-mail: i duke@i dahoan.com Kyle Williams BYU Idaho E-mail : williamsk@byui.edu Val Steiner Nu-West Industries, Inc. E-mail : val.steiner@asrium.com Bradley Mullins 1750 SW Harbor Way, Suite 450 Portland, OR 97201 E-mail : brmul I ins@mwanalytics.com COMISSION STAFF Brandon Karpen Deputy Attomey General Idaho Public Utilities Commission 472 W . Washington (83702) PO Box 83720 Boise, lD 83720-0074 E-mail : brandon.karpen@puc. i daho. gov Page I of2 PACIFICORP, DBA ROCKY MOUNTAIN POWER Ted Weston PacifiCorp, dba Rocky Mountain Power 1407 West North Temple Suite 330 Salt Lake City, uT 84116 E-mail : ted.weston@paci fi corp.com Yvonne Hogle PacifiCorp, dba Rocky Mountain Power 1407 West North Temple Suite 320 Salt Lake City, UT 84116 E-mail: vvonne.hos I e@pacifi corp.com Data Request Response Center PacifiCorp 825 NE Multnomah, Suite 2000 Portland, OR97232 E-mail: datarequest@pacifi corp.com Dated this24n day of August,2018. Operations Page2 of2