HomeMy WebLinkAbout20180216Vail Exhibit 52.pdfCase No.PAC-E-17-07
Exhibit No.52
Witness:Rick A.Vail
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
O ROCKY MOUNTAIN POWER
Exhibit Accompanying Second Supplemental Testimony of Rick A.Vail
Q706 Facility Study
February 2018
O
Rocky Mountain Power
V PAciFICORP ExhiCb e1o 8
TRANSMISSION
Large Generator Interconnection
Facilities Study Report
Final
Completed for
("InterconnectionCustomer")
Q0706
Proposed Point of Interconnection
PacifiCorp's proposed Aeolus substation at 230 kV
March 3,2017
O
Rocky Mountain Power
Exhibit No.52 Page 2 of 18VAPACIFICORP°¾aNeo ARE O
TRANSMISSION Rnal Facilities Study Report
TABLE OF CONTENTS
1.0 DESCRIPTION OF THE PROJECT ..............................................................................................I
2.0 STUDY SCOPE AND OBJECTIVES............................................................................................l
3.0 TYPE OF INTERCONNECTION SERVICE ...................................................................................1
4.0 STUDY ASSUMPTIONS...........................................................................................................I
5.0 PROPOSED POINT OF INTERCONNECTION ..............................................................................3
6.0 SCOPE OF WORK ...................................................................................................................4
6.1 Generating Facility Modifications ...................................................................................4
6.1.1 Interconnection Customer to be Responsible For.....................................................4
6.1.2 Transmission Provider to be Responsible For ..........................................................7
6.2 Tie Line Requirements and Point of Interconnection (Aeolus).......................................7
6.2.1 Interconnection Customer to be Responsible For.....................................................7
6.2.2 Transmission Provider to be Responsible For ..........................................................8
6.3 Point of Interconnection (Aeolus substation)...................................................................9
6.3.1 Interconnection Customer to be Responsible For.....................................................9
6.3.2 Transmission Provider to be Responsible For ..........................................................9
7.0 COST ESTIMATE (+/-20%).................................................................................................10
8.0 SCHEDULE...........................................................................................................................12O9.0 PARTICIPATIONBY AFFECTED SYSTEMS ............................................................................12
10.0 APPENDICES........................................................................................................................13
10.1 Appendix 1:Higher Priority Request.........................................................................14
10.2 Appendix 2:Property Requirements ..........................................................................15
O
March 3,2017
/Q706 Page i CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 3 of 18YPACIFICORP°":Neo AR Oa
TR AN SM I SS I ON Rnal Facilities StudyReport
1.0 DESCRIPTIONOF THE PROJECT
("Interconnection Customer")proposed interconnecting 250 MW of new generation to
PacifiCorp's ("Transmission Provider")proposed Aeolus substation at 230 kV located in Carbon
County,Wyoming.The project ("Project")will consist of 125 GE 2.0-116 turbines for a total
output of 250 MW.The requested commercial operation date is November 1,2018.
Interconnection Customer will NOT operate this generator as a Qualified Facility as defined by
the Public Utility Regulatory Policies Act of 1978 (PURPA).
The Transmission Provider has assigned the Project "Q0706."
2.0 STUDYSCOPE AND OBJECTIVES
The objective of the Facilities Study is to:
Complete a facilities analysis,which shall specify and estimate the cost of equipment,
engineering,procurement,and construction required to address issues as outlined in the
system impact study,and
Provide a scope of work and an estimated cost and schedule for completing the scope of
work.
3.0 TYPE OF INTERCONNECTIONSERVICE
The Interconnection Customer has selected Energy Resource (ER)Interconnection Service.
4.0 STUDY ASSUMPTIONS
All active higher priority transmission service and/or generator interconnection requests will
be considered in this study and are listed in Appendix 1.If any of these requests are withdrawn,
the Transmission Provider reserves the right to restudy this request,as the results and
conclusions contained within this study could significantly change.
For study purposes there are two separatequeues:
o Transmission Service Queue:To the extent practical,all network upgrades that
are required to accommodate active transmission service requests will be modeled
in this study.
o Generation Interconnection Queue:Interconnection Facilities associated with
higher queue interconnection requests will be modeled in this study.
The Interconnection Customer's request for energy or network resource interconnection
service in and of itself does not convey transmission service.Only a Network Customer may
make a request to designate a generating resource as a Network Resource.Because the queue
of higher priority transmission service requests may be different when a Network Customer
requests network resource designation for this Generating Facility,the availablecapacity or
transmission modifications,if any,necessary to provide network resource interconnection
O
March 3,2017
/Q706 Page 1 CONFIDENTIAL/FINAL
Rocky Mountain Power
V PACIFICORP ExhiCb o 52P e4o 8
TR AN SM I SS I ON Rnal Facilities Study Report
service may be significantly different.Therefore,the Interconnection Customer should regard
the results of this study as informationalrather than final.
This study assumes the Project will be integrated into Transmission Provider's system at the
proposed Aeolus 230 kV substation.
The Interconnection Customer will construct and own any facilities required between the Point
of Interconnection and the Project.
Generator tripping may be required for certain outages.
All facilities will meet or exceed the minimum Western Electricity Coordinating Council
("WECC"),North American Electric Reliability Corporation ("NERC"),and Transmission
Provider performance and design standards.
The most current transmission facility ratings were used for the analysis.
All existing and proposed Remedial Action Schemes (RAS)are assumed to be in service for
this study.
The Energy Gateway West (2024)and Energy Gateway South (2024)projects are assumed to
be in service;the Dave Johnston to Amasa (future)to Heward (future)to Aeolus (future)230
kV line is assumed to be rebuilt as part of the Gateway projects.Note that these dates are
inconsistent with the Q0706 Project's planned in-service date.A RAS that will drop up to 600
MW of generation for the followingoutages is assumed to be in-service:
O o Aeolus -Anticline 500 kV line
o Anticline -Populus 500 kV line
o Aeolus -Clover 500 kV line
o Clover 500/345 kV auto transformer
All system improvements associated with the prior queued projects are assumed to be in
service before Q0706.
Based on the Federal Energy Regulatory Commission's proposed revisions to the Pro Forma
Large Generator Interconnection Agreement (Docket No RMl6-1-000),the followingpower
factor requirement was assumed for the Project:
o "9.6.1 Power Factor Design Criteria.Interconnection Customer shall design the Large
Generating Facility to maintain a composite power delivery at continuous rated power
output at the POI at a power factor within the range of 0.95 leading to 0.95 lagging,unless
Transmission Provider has established different requirements that apply to all generators
in the Control Area on a comparable basis.Non-synchronous generators shall only be
required to maintain the above power factor when their output is above 10 percent of the
Generating Facility Capacity."
The 2.0 MW GE wind turbines for Q0706 were assumed to have a +/-0.9 power factor at
turbine terminals.
Transmission Provider reserves the right to restudy the Project if any of the above mentioned
assumptions are changed or if any of the required mitigations are not in service at the time of
interconnection.
This report is based on information available at the time of the study.It is the Interconnection
Customer's responsibility to check the Transmission Provider's web site regularly for
Transmission System updates at http://www.pacificorp.com/tran.html
March 3,2017
/Q706 Page 2 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 5 of 18VAPACIFICORP°":.Neo AR Oa
TR AN SM I SS I ON Rnal Facilities Study Report
5.0 PROPOSED POINT OF INTERCONNECTION
The Interconnection Customer's proposed Generating Facility is to be interconnected through a
new 230 kV bay at the proposed Aeolus substation.The Interconnection Customer will construct
a seven-to eight-mile 230 kV transmission line into the Aeolus substation from their 230 kV
collector substation.Based on the data provided by the Interconnection Customer,the Project
consists of two 230 -34.5 kV transformers with the rating of 84/112/140 MVA each.Each one of
the 230 -34.5 kV transformers is connected to two separate 34.5 collector systems.The first
collector system has sixty-two (62)2.0 MW GE turbines connected to it totaling 124 MW and the
second collector system has sixty-three (63)2.0 MW GE turbines connected to it totaling 126
MW.The total maximum output of the Project shall not exceed 250 MW.
Figure 1 below is a one-line diagram that illustrates the interconnection of the proposed Generating
Facility to the Transmission Provider's system.
e s Substation 84/112/140 MVA I
230 -34.5 kV I
230 kV z =9%-
I \
I 84/112/140 MVA -
I 230 -34 5 kV
230 kV
Change of
Ownership 34 5 kV
I
Proposed
Aeolus
Substation
525 -230 kV
Transformer
Figure 1 System One Line Diagram
O
March 3,2017
/Q706 Page 3 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 6 of 18VAPACIFICORP°3:sNeo AR E Oa
TRANSMISSION Rnal Facilities Study Report
6.0 SCOPE OF WORK
6.1 Generating Facility Modifications
The following outlines the design,procurement,construction,installation,and ownership of
equipment at the Interconnection Customer's Generation Facility.
6.1.1 INTERCONNECTIONCUSTOMERTO BE RESPONSIBLE FOR
Design,procure,install,and own all equipment required for the Large Generating
Facility.
Obtain all necessary permits,lands,rights of way and easements required for the
construction and continued maintenance of the facilities required for the Q0706 Project.
All easements and permits shall be recorded in the name of the Transmission Provider
and shall be on forms acceptable to the Transmission Provider.All easements and rights
of way will be obtained for durations acceptable to the Transmission Provider;this
includes all permits/easements for ingress and egress prior to the start of construction.
o Provide a separate fenced area along the perimeter of the Interconnection
Customer's Generating Facility in which the Transmission Provider can install a
control house for any protection and communication equipment.This area will
O share a fence and ground grid with the Generating Facility and have separateaccess.
AC station service for the control house will be supplied by the Interconnection
Customer.
Provide a CDEGS grounding analysis.
Design and install conduits,per Transmission Provider's standards,to the demarcation
point.
The collector substation batteries will be sized to carry the communication equipment
with DC to DC converters.
Demonstrate the reactive capability of the facility and the voltage control system prior
to commercial operation.Conditions of operations include:
o Operate in voltage control mode with the ability to deliver power output to the POI
within the range of +/-0.95 power factor.(Please see Standard Large Generator
Interconnection Agreement,article 9.6.1 and 9.6.2 in OATT.)Any additional
reactive compensation must be designed such that the discrete switching of the
reactive device,if required,does not cause step voltage changes greater than ±3%
at any load serving bus on the Transmission Provider's system.
o As required by NERC standard VAR-001-la,the Transmission Provider will
provide a voltage schedule for the POI.Generating Facilities should be operated so
as to maintain the voltage at the POI,or other designated point as deemed
appropriate by Transmission Provider,between 1.00 per unit to 1.04 per unit.The
Transmission Provider may also specify a voltage and/or reactive power bandwidth
as needed to coordinate with upstream voltage control devices such as on-load tap
March 3,2017
/Q706 Page 4 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 7 of 18YPACIFICORP°":=Neo AR E Oa
TR AN SM I SS I ON Rnal Facilities Study Report
changers.At the Transmission Provider's discretion,these values might be adjusted
depending on operating conditions.
o At low output levels,the Project needs to ensure that it maintains the power factor
within ±0.95 at the POI and minimize the reactive power flow towards the
transmission system to prevent high voltages.
o Generating Facilities capable of operating with a voltage droop are required to do
so.Voltage droop control enables proportionate reactive power sharing among
Generating Facilities.Studies will be required to coordinate voltage droop settings
if there are other facilities in the area.It will be the Interconnection Customer's
responsibility to ensure that a voltage coordination study is performed,in
coordination with Transmission Provider,and implemented with appropriate
coordination settings prior to unit testing.
o For areas with multiple Generating Facilities,additional studies may be required to
determine whether or not critical interactions,including but not limited to control
systems,exist.These studies,to be coordinated with Transmission Provider,will
be the responsibility of the Interconnection Customer.If the need for a master
controller is identified,the cost and all related installationrequirements will be the
O responsibility of the Interconnection Customer.
Design,procure,install,and own Phasor Measurement Units (PMUs).
Provide a standard model from the WECC Approved Dynamic Model Library prior to
interconnection,since the Transmission Provider cannot submit a user written model
to WECC for inclusion in base cases.The list of approved generator models is
continually updated and is available on the http://www.WECC.biz website.
All generators must meet the Federal Energy Regulatory Committee (FERC)and
WECC low voltage ride-through requirements as specified in the interconnection
agreement.
Prior to construction,arrange construction power with the Transmission Provider.The
Project is within the Transmission Provider's service territory and both station service
and temporary construction power metering shall conform to the Six State Electric
Service Requirements manual.
Prior to back feed,arrange distribution voltage retail meter service for electricity
consumed by the Project and arrange back up station service for power that will be
drawn from the transmission or distribution line when the Project is not generating.
Interconnection Customer must call the PCCC Solution Center 1-800-640-2212 to
arrange this service.Approval for back feed is contingent upon obtaining station
service.
Provide the followingdata points from the Q0706 collector substation:
o Analogs:
O ·Transformer #1 real power
March 3,2017
/Q706 Page 5 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 8 of 18VAPACIFICORP°":.Neo AR E O
TRANSMISSION Rnal Facilities StudyReport
·Transformer #l reactive power
·Real power flow through 34.5 kV line feeder breaker T1-1
·Reactive power flow through 34.5 kV line feeder breaker T1-1
·Real power flow through 34.5 kV line feeder breaker Tl-2
·Reactive power flow through 34.5 kV line feeder breaker T1-2
·Real power flow through 34.5 kV line feeder breaker Tl-3
·Reactive power flow through 34.5 kV line feeder breaker T1-3
·Real power flow through 34.5 kV line feeder breaker Tl-4
·Reactive power flow through 34.5 kV line feeder breaker Tl-4
·Real power flow through 34.5 kV line feeder breaker T1-5
·Reactive power flow through 34.5 kV line feeder breaker T1-5
·Transformer #2 real power
·Transformer #2 reactive power
·Real power flow through 34.5 kV line feeder breaker T2-1
·Reactive power flow through 34.5 kV line feeder breaker T2-1
·Real power flow through 34.5 kV line feeder breaker T2-2 ,
·Reactive power flow through 34.5 kV line feeder breaker T2-2
O ·Real power flow through 34.5 kV line feeder breaker T2-3
·Reactive power flow through 34.5 kV line feeder breaker T2-3
·Real power flow through 34.5 kV line feeder breaker T2-4
·Reactive power flow through 34.5 kV line feeder breaker T2-4
·Real power flow through 34.5 kV line feeder breaker T2-5
·Reactive power flow through 34.5 kV line feeder breaker T2-5
·A phase 230 kV transmission voltage
·B phase 230 kV transmission voltage
·C phase 230 kV transmission voltage
·Average Wind speed
·Average Plant Atmospheric Pressure (Bar)
·Average Plant Temperature (Celsius)
o Status
·230 kV breaker Tl
·34.5 kV collector circuit breaker Tl-l
·34.5 kV collector circuit breaker Tl-2
·34.5 kV collector circuit breaker Tl-3
·34.5 kV collector circuit breaker Tl-4
·34.5 kV collector circuit breaker Tl-5
·230 kV breaker T2
·34.5 kV collector circuit breaker T2-1
·34.5 kV collector circuit breaker T2-2
·34.5 kV collector circuit breaker T2-3
March 3,2017
/Q706 Page 6 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 9 of 18VAPACIFICORP°3:sNeo AR E O
TRANSMISSION Rnal Facilities StudyReport
·34.5 kV collector circuit breaker T2-4
·34.5 kV collector circuit breaker T2-5
6.1.2 TRANSMISSIONPROVIDERTO BE RESPONSIBLE FOR
Design,procure and install a small control building at a location provided and prepared
by the Interconnection Customer inside the Generating Facility fence line.
The list of major equipment identified for this portion of the Project is as follows:
o (1)small control building AC and DC panels and temperature controlled
o (1)125VDC,100Ah battery bank
o (1)130VDC,12A battery charger
o (1)GE D20 RTU
o (1)24"open frame rack (DNP 3.0 protocol with hard wired connections)
Revenue metering is required for each of the two Interconnection Customer power
transformers and will be located on the high side of each of the step-up transformers.
The primary metering transformers shall be combination CT/VT extended range high
accuracy metering with ratios to be determined during the design phase of the project.
The Transmission Provider will design and procure the collector revenue metering
O panels.The panels shall be located inside the collector control house.The collector
substation metering panel shall include two revenue quality meters,test switches,and
all SCADA metering data terminated at a metering interpositionblock.
An Ethernet or phone line is required for retail sales and generation accounting via the
MV-90 translation system.
6.2 Tie Line Requirements and Point of Interconnection (Aeolus)
The following outlines the design,procurement,construction,installation,and ownership of
equipment associated with the radial line connecting the Interconnection Customer's
Generating Facility to the Transmission Provider's Point of Interconnection substation.
6.2.1 INTERCONNECTIONCUSTOMERTO BE RESPONSIBLE FOR
Obtain all necessary permits,lands,rights of way and easements required for the
construction and continued maintenance of the facilities required for the Q0706 Project.
Design and install approximatelyseven miles of 230kV transmission line between the
Q0706 Generation Facility and the Aeolus substation.The Transmission Provider
requires that the bus is built to the Transmission Provider's 230kV standard.
Design and install ½"OPGW and attachment hardware per the Transmission
Provider's standards with nodes and channel banks at both ends.The OPGW cable will
be coiled on the above structure such that there is enough cable and conductor to reach
the POI substation tower with normal sags.Also,provide all hardware for stringing of
the last span of conductor and OPGW into the POI sub tower.
O
March 3,2017
/Q706 Page 7 CONFIDENTIAL/FINAL
Rocky Mountain Power
V PAciFICORP ExhibLN 52Pag 10o7f18
TR AN SM I SS I ON
Rnal Facilities Study Report
This fiber is to be installed by the Interconnection Customer and upon acceptance will
be owned and maintained by Transmission Provider.Channels will be crossed at
Aeolus substation to the back bone communication system.
Design and construct a single 230kV circuit breaker and associated equipment tie line
substation adjacent to Aeolus substation with a common fence between the two
facilities.
o The ground mats between the Aeolus and the tie line substation will be tied
together.Therefore,the Interconnection Customer must match the standards of the
Aeolus substation.
Conduitwill be required to be installed between the Interconnection Customer's tie line
substation and Aeolus substation.The Interconnection Customer will provide their
conduit drawings and install the necessaryconduit to demarcation point at the Point of
Interconnection.The Transmission Provider will install the connecting conduit in the
Aeolus substation.
Design (per the Transmission Provider's standards)and install a dead-end structure
with sufficient bus to allow for proper attachment to a 230kV disconnect switch inside
the Transmission Provider's substation.The switch will be the Point of Change of
O Ownership.
Provide the output from two sets of current transformers to be fed into the bus
differential relays with a maximum current transformer ratio matching the maximum
CT ratio of the breakers at Aeolus substation.The detection and clearing of faults on
the tie line between the tie line and the collector substations will be the responsibility
of the Interconnection Customer.Facilities must be installed to detect and isolate the
line if it is faulted in five cycles or less.
6.2.2 TRANSMISSIONPROVIDERTO BE RESPONSIBLE FOR
Review the Interconnection Customer's design of the proposed new transmission line,
OPGW and connection to the Aeolus substation structure for general conformance with
Transmission Provider's construction standards.
Provide a CDEGS grounding analysis of the Aeolus substation.
Provide the Transmission Provider's construction standards and review the
Interconnection Customer's design for the last bus support structure located outside the
POI substation fence line to ensure compatibility with the termination switch.
Connect the Interconnection Customer's last span of bus to the 230kV,disconnect
switch at the change of ownership location including the OPGW cable.The
Transmission Provider will maintain this last bus span at the Interconnection
Customer's expense.
o This short span of bus will be protected with a redundant bus differential relay
systems.The bus differential relays will be located in Aeolus substation.The
March 3,2017
/Q706 Page 8 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 11 of 18PACIFICORP°32.°i:E Oa
O TRANSMISSION
Final Facilities StudyReport
Interconnection Customer will need to provide the output from two sets of current
transformers to be fed into the bus differential relays with a maximum current
transformer ratio matching the maximum CT ratio of the breakers at Aeolus
substation.If a fault is detected,both the 230 kV breakers in Aeolus substation and
the 230 kV breaker in the Interconnection Customer's tie line substation will be
tripped.
o A relay at Aeolus substation will monitor the voltage magnitude and frequency.If
the magnitude or frequency of the voltage is outside of normal range of operation
a signal will be sent over the communication system to the collector substation.At
the collector substation this signal is to trip open all of the 34.5 kV feeder breakers
to disconnect the wind turbine generators.By tripping the 34.5 kV breakers instead
of the 230 kV breakers the station service to the Generating Facility is maintained
to facilitate the restoration of the generation.This relay will also have phase and
ground directionalovercurrent elements set to operate for faults in the line between
Shirley Basin substation and the Interconnection Customer's collector substation
and serve as a back-up to the main protection installed by the Interconnection
Customer.
6.3 Point of Interconnection (Aeolus substation)
The following outlines the design,procurement,construction,installation,and ownership of
equipment at the Point of Interconnection.
6.3.1 INTERCONNECTIONCUSTOMERTO BE RESPONSIBLE FOR
Obtain all necessarypermits,rights of way and easements required for the construction
at Aeolus substation.
6.3.2 TRANSMISSIONPROVIDERTO BE RESPONSIBLE FOR
Complete design and construction of one transformer bay at Aeolus to terminate the tie
line in.Three (3)feet of panel space will be required in the 230 kV control house.The
followingequipment will be installed:
o (1)-230 kV circuit breaker
o (3)-230kVCCVT
o (2)-230 kV group operated breaker disconnect switch
o (1)-230 kV group operated line disconnect switch,with ground blade,with motor
operator
o (3)-144 kV MCOV surge arrester
o (1)-RTAC
The interchange metering will be designed bidirectional and rated for the total net
generation of the Project including metering the retail load (per tariff)delivered to the
Interconnection Customer.The Transmission Provider will specify and order all
March 3,2017
/Q706 Page 9 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 12 of 18VAPACIFICORP°32:JA 1LOa
TR AN SM I SS I ON
Rnal Facilities StudyReport
interconnection revenue metering,including the instrument transformers,metering
panels,junction box and secondary metering wire.The primary metering transformers
shall be combination CT/VT extended range for high accuracy metering with ratios to
be determined during the design phase of the Project.
The metering design package will include two revenue quality meters,test switch,with
DNP real time digital data terminated at a metering interpositionblock.One meter will
be designated a primary SCADA meter and a second meter will be used designated as
backup with metering DNP data delivered to the alternate control center.The metering
data will include bidirectional KWH KVARH,revenue quantities including
instantaneous PF,MW,MVAR,MVA,including per phase voltage and amps data.
An Ethernet connection is required for retail sales and generation accounting via the
MV-90 translation system.
Listed below is the data that will be supplied by the Aeolus substation.
o Analogs:
·Net Generation real power
·Net Generator reactive power
·Interchange energy register
O From Tie Substation Adjacentto Aeolus
o Status:
·230 kV breaker
7.0 CosT ESTIMATE (+/-20%)
The followingestimate represents only scopes of work that will be performed by the Transmission
Provider.Costs for any work being performed by the Interconnection Customer are not included.
Interconnection -Direct Assignment Facilities
Q0706 collector substation -Add RTU $450,000
Q0706 collector substation -Add metering $434,000
Aeolus substation -Add metering $230,000
Aeolus substation -Add 230 kV line position $1,584,000
Tie line substation -Add relay settings and grounding $62,000
Total Cost $2,760,000
O
March 3,2017
/Q706 Page 10 CONFIDENTIAL/FINAL
Rocky Mountain Power
V PAciFICORP Exhib No 5e2PaAE3of18
TR AN SM I SS I ON Rnal Facilities Study Report
*Any distribution line modifications identified in this report will require a field visit analysis in
order to obtain a more thorough understanding of the specific requirements.The estimate
provided above for this work could change substantially based on the results of this analysis.
Until this field analysis is performed the Transmission Provider must develop the project
schedule using conservative assumptions.The Interconnection Customer may request that the
Transmission Provider perform this field analysis,at the Interconnection Customer's expense,
prior to the execution of an Interconnection Agreement in order to obtain more cost and schedule
certainty.
Note:Costs for any excavation,duct installationand easements shall be borne by the
Interconnection Customer and are not included in this estimate.This estimate is as accurate as
possibly given the level of detailed study that has been completed to date and approximates the
costs incurred by Transmission Provider to interconnect this Generator Facility to Transmission
Provider's electrical distribution or transmission system.The Interconnection Customer will be
responsible for all actual costs,regardless of the estimated costs communicated to or approved
by the Interconnection Customer.
O
O
March 3,2017
/Q706 Page 11 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 14 of 18VAPACIFICORP°32.°;AC Oa
TRANSMISSION
Rnal Facilities StudyReport
8.0 SCHEDULE
Execute Interconnection Agreement April 28,2017
Provision of Financial Security May 2,2023
Interconnection Customer Design Information Provided June 27,2023
*Transmission Provider Engineering &Procurement Commences August 7,2023
**Energy Imbalance Market Modeling Data Submittal August 7,2023
Transmission Provider Engineering Design Complete February 27,2024
InterconnectionCustomer Property/Permits/ROW Procured February 6,2024
Construction Begins May 1,2024
Interconnection Customer's Facilities Receive Backfeed Power January 31,2025
Initial Synchronization/Generation Testing February 28,2025
Commercial Operation March 28,2025
*As applicable and determined by the Transmission Provider,within 60 days of the
Interconnection Customer's authorization for the Transmission Provider to begin engineering,the
Interconnection Customer shall provide a detailed short circuit model of its generation system.
This model must be constructed using the ASPEN OneLine short circuit simulation program and
contain all individual electrical components of the Interconnection Customer's generation system.
**Any design modifications to the Interconnection Customer's Generating Facility after this date
requiring updates to the Transmission Provider's network model will result in a minimum of 3
months added to all future milestones including Commercial Operation.
Please note,the time required to perform the scope of work identified in this report appears to
result in a timeframe that does not support the Interconnection Customer's requested Commercial
Operation date of November 1,2018.
9.0 PARTICIPATIONBY AFFECTEDSYSTEMS
Transmission Provider has identified the following affected systems:None.
O
March 3,2017
/Q706 Page 12 CONFIDENTIAL/FINAL
Rocky Mountain Power
V PAciFICORP Exhib No 5e2Pa15o7f18
TR AN SM I SS I ON
Rnal Facilities Study Report
10.0APPENDICES
Appendix 1:Higher Priority Requests
Appendix 2:Property Requirements
O
O
March 3,2017
/Q706 Page 13 CONFIDENTIAL/FINAL
Rocky Mountain Power
V PACIFICORP ExhibLNo52Pag 16o7f18
O TRANSMISSION
Final Facilities StudyReport
10.1 Appendix 1:Higher Priority Request
All active higher priority transmission service and/or generator interconnection requests will be
considered in this study and are identified below.If any of these requests are withdrawn,the
Transmission Provider reserves the right to restudy this request,as the results and conclusions
contained within this study could significantly change.
Transmission/Generation Interconnection Queue Requestsconsidered:
Q0199 (200 MW)
Q0200 (100 MW)
Q0201 (100 MW)
Q0267 (88 MW)
Q0290 (252 MW)
Q0306/335 (80 MW)
Q0375 (230 MW)
Q0409 (320 MW)
Q0542 (240 MW)
O
O
March 3,2017
/Q706 Page 14 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 17 of 18VAPACIFICORP°32.°iAR E O
TRANSMISSION Rnal Facilities StudyReport
10.2 Appendix 2:PropertyRequirements
Property Requirements for Point of Interconnection Substation
Requirements for rights of way easements
Rights of way easements will be acquired by the Interconnection Customer in the Transmission
Provider's name for the construction,reconstruction,operation,maintenance,repair,replacement
and removal of Transmission Provider's Interconnection Facilities that will be owned and operated
by PacifiCorp.Interconnection Customer will acquire all necessary permits for the project and will
obtain rights of way easements for the project on Transmission Provider's easement form.
Real Property Requirements for Point of Interconnection Substation
Real property for a point of interconnection substation will be acquired by an Interconnection
Customer to accommodate the Interconnection Customer's project.The real property must be
acceptable to Transmission Provider.Interconnection Customer will acquire fee ownership for
interconnection substation unless Transmission Provider determines that other than fee ownership
is acceptable;however,the form and instrument of such rights will be at Transmission Provider's
sole discretion.Any land rights that Interconnection Customer is planningto retain as part of a fee
property conveyance will be identified in advance to Transmission Provider and are subject to the
Transmission Provider's approval.
The InterconnectionCustomer must obtain all permits required by all relevant jurisdictions for the
planned use including but not limited to conditional use permits,Certificates of Public
Convenience and Necessity,California Environmental Quality Act,as well as all construction
permits for the project.
Interconnection Customer will not be reimbursed through network upgrades for more than the
market value of the property.
As a minimum,real property must be environmentally,physically,and operationallyacceptable to
Transmission Provider.The real property shall be a permitted or permittable use in all zoning
districts.The Interconnection Customer shall provide Transmission Provider with a title report and
shall transfer property without any material defects of title or other encumbrances that are not
acceptable to Transmission Provider.Property lines shall be surveyed and show all encumbrances,
encroachments,and roads.
Examples of potentially unacceptable environmental,physical,or operational conditions could
include but are not limited to:
1.Environmental:known contamination of site;evidence of environmental
contamination by any dangerous,hazardous or toxic materials as defined by any
governmental agency;violation of building,health,safety,environmental,fire,
land use,zoning or other such regulation;violation of ordinances or statutes of
any governmental entities having jurisdiction over the property;underground or
March 3,2017
/Q706 Page 15 CONFIDENTIAL/FINAL
Rocky Mountain Power
Exhibit No.52 Page 18 of 18VAPACIFICORP°":=Neo ARE-Oa
TRANSMISSION Rnal Facilities StudyReport
above ground storage tanks in area;known remediation sites on property;ongoing
mitigation activities or monitoring activities;asbestos;lead-based paint,etc.A
phase I environmental study is required for land being acquired in fee by the
Transmission Provider unless waived by Transmission Provider.
2.Physical:inadequate site drainage;proximity to flood zone;erosion issues;
wetland overlays;threatened and endangered species;archeological or culturally
sensitive areas;inadequate sub-surface elements,etc.Transmission Provider may
require Interconnection Customer to procure various studies and surveys as
determined necessary by Transmission Provider.
Operational:inadequate access for Transmission Provider's equipment and vehicles;existing
structures on land that require removal prior to building of substation;ongoing maintenance for
landscaping or extensive landscape requirements;ongoing homeowner's or other requirements or
restrictions (e.g.,Covenants,Codes and Restrictions,deed restrictions,etc.)on property which
are not acceptable to the Transmission Provider.
O
March 3,2017
/Q706 Page 16 CONFIDENTIAL/FINAL