Aeolus West Transmission Path
Transfer Capability Assessment
Preliminary Study Report
Revision 1.0
October 2017
O Prepared by
PacifiCorp -Transmission Planning
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 2 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
Table of Contents
ExecutiveSummary...............................................................................1
1 Introduction ......................................................................4
1.1 Purpose.....................................................................................4
1.2 Plan of Service .................................................................................4
1.3 Planned OperatingDate ...................................................................4
1.4 Scope............................................................................5
2 Study Criteria......................................................................................5
2.1 ThermalLoading..................................................................................5
2.2 Steady State Voltage Range ............................................................6
2.3 Post-Transient Voltage Deviation.........................................................6
2.4 TransientStability Analysis Criteria...................................................................6
2.5 TransientVoltage Response..........................................................7
3 Base Case Development....................................................................8
3.1 Base Case Selection ...............................................................................8
3.2 Generating Facility Additions...............................................................10
3.3 Base Case Modification and Tuning......................................................11
4 Path Studies .........................................................................11
4.1 Aeolus West vs.TOT 4B ...........................................................11
4.2 Base Case Development.......................................................................14
4.3 TransientStability Analysis .............................................................14
5 Sensitivity Analysis .......................................................................................17
6 Study Conclusions .....................................................................................18
O
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 3 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
Executive Summary
This assessment was conducted to document the Transfer Capability of the Aeolus Westi
transmission path once the Gateway West -Subsegment D.22 (Bridger/Anticline -Aeolus)
transmission facilities (D.2 Project)are added to the Wyoming transmission system.
The Aeolus West transmission path (see Figure 1)is a new path that will be formed by
adding the D.2 Project in parallel with the TOT 4A3 (Path 37)transmission path facilities.
The anticipated in-servicedate for the D.2 Project is November2020.The D.2 Project will
include the following major transmission facilities:
Aeolus -Anticline 500 kV new line,Figure 1:Aeolus West Transmission Path
Shirley Basin -Freezeout 230 kV line ,
loop-in to Aeolus,
Aeolus 500/230 kV substation,^lu t
Anticline 500/345 kV substation,
Bridger -Anticline 345 kV new line,
Latham dynamic voltage control
device,
Shirley Basin -Aeolus 230 kV #2
line (16-mile),
Aeolus -Freezeout 230 kV line '"
rebuild,and
Freezeout -Standpipe 230 kV line reconstruction
The WECC 2021-22 HW power flow base case was utilized for the Aeolus West transfer
capability studies.In support of the EV2020 initiative,which calls for the addition of new
and repowered wind resources in Wyoming,the base case was modified to achieve the
1 The Aeolus West path will include the following major transmission elements:Aeolus*--Anticline 500 kV,Platte*-Latham 230 kV,Mustang*-Bridger 230 kV and Riverton*-Wyopo 230 kV transmission lines.(*meter location)
2 Gateway West -Subsegment D.2 is a key component of the Energy Vision 2020 (EV2020)initiative that was
announced by PacifiCorp on April 4,2017.Other components of the EV2020 initiative include repowering
PacifiCorp's existing wind fleet in southeast Wyoming and adding approximately 1,100 MW of new wind
generation east of Bridger/Anticline.
O 3 The existing TOT 4A (Path 37)path is comprised ofthe Riverton*-Wyopo 230 kV,Platte -Standpipe*230
kV and Spence*-Mustang 230 kV transmission lines.(*meter location)
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 4 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
transfer levels evaluated by adding 1169 MW (up 1270 MW as a sensitivity)of anticipated
generationresource currently in the PacifiCorp (PAC)-Large Generation Interconnection
(LGI)queue,which were used as a proxy for new resources.For different Aeolus West
transferlevels (heavyand light)resources in eastern Wyoming were redispatched relative to
the Jim Bridger Generation Plant.
Contingencies that were considered in this analysis include:
N-1 of D.2 Project facilities
N-1,N-2 Bridger contingencies
All Wyoming transmission system contingencies performedas part of the TPL-00l-4
annual assessment.
For the preliminary Transfer Capability assessment,simultaneous interaction between the
Aeolus West path and the TOT 4B path was evaluated;however,the interactionwith other
O transmission paths (Yellowtail South,Jim Bridger West,TOT lA and TOT 3)was monitored
throughoutthe study.
As part of the analysis,sensitivity studies were also performedto evaluate:(1)performance
of different dynamic voltage control architecture (SVC vs STATCOM)at Latham,and (2)
variations in the assumed magnitude and location of new wind generation,up to 1270 MW.
Conclusions
Technical studies demonstrated that with the addition of the planned D.2 Project facilities to
the Wyoming transmission system,system performancewill meet all NERC and WECC
performancecriteria.
Preliminary power flow studies demonstrate that by utilizing existing and planned southeast
Wyoming resources4,the Aeolus West transmission path can transferup to 1696 MW under
simultaneous transfer conditions with the TOT 4B transmission path,effectively'increasing
the east to west transfer levels across Wyoming by 817.5 MW.Power flow findings also
indicated:
4 Southeast Wyoming Resources:Existing Wind:1124 MW,Dave Johnston (net)717 MW,Repower Wind:
zero MW to 137.5 MW,New Wind:1152 -1169 MW at various locations
*Effective transfers were determined by subtracting the existing TOT 4A path maximum'*transfer level (960OMW)from the Aeolus West transfer level (1696 MW)and adding the Platte area loads (82.5 MW)that are up-
stream of the Aeolus West metering point.
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 5 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
Dynamic voltage control is necessary at the Latham 230 kV substation to mitigate
low voltageconditions resulting from loss of Bridger/Anticline -Aeolus transmission
facilities.
Under certain operatingconditions,three different Remedial Action Schemes (RAS)
will need to be implemented to trip generation following outage of specific
transmission facilities.
The location (and output level)of new and repowered wind resources can influence
the transfercapability level across the Aeolus West transmission path.
While a wide range of disturbances were evaluated,dynamic stability studies identified that
the slowest post fault voltage recovery will occur for a fault at Anticline or Jim Bridger 345
kV bus followed by loss of the Bridger/Anticline -Aeolus transmission segment and the
planned operation of a generation tripping (RAS)scheme.The stability analysis
demonstrated that all planned system events met the stability performancecriteria.
O
O
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 6 of 24
Case No.PAC-E-17-07
Witness:Rick A.VailO
1 Introduction
1.1 Purpose
The purpose of this study is to identify the new Aeolus West path limitation,the interaction
between the Aeolus West and the TOT 4B transmission paths by creating a nomogram,
system limitation(s)and various Remedial Action Scheme (RAS),such that the
interconnected transmission BES in Wyoming can support additionalgeneration with the D.2
Project and can be operated reliably during normal and contingency operations throughout
the planninghorizon.
This report outlines the power flow and dynamic stability study findings from the Aeolus
West transfer capability assessment and identifies performanceof the BES in Wyoming with
the addition of the D.2 Project and 1169 MW of new wind generation.
1.2 Plan of Service
The D.2 Project consists of the following system improvements:
1.A new 500 kV Anticline substation
2.A new 230/500 kV,1600 MVA transformerat Aeolus
3.A new 137.8-mile 3x1272 ACSR (Bittern),500 kV line between Aeolus and
Anticline substations
4.A new 500/345 kV,1600 MVA transformerat Anticline
5.A new 5.1-mile 3x1272 ACSR (Bittern),345 kV line between Anticline and Jim
Bridger substations
6.A new 50 MVAr reactor at Aeolus 230 kV bus
7.A new 200 MVAr shunt capacitor bank at Aeolus 500 kV bus
8.A new 200 MVAr shunt capacitor bank at Anticline 500 kV bus
9.Rebuild of the Aeolus -Freezeout and Freezeout -Standpipe 230 kV lines to 2x1272
ACSR (Bittern)conductor
10.A new 2xl557 ACSR/TW Aeolus -Shirley Basin 230 kV #2 line
11.A new dynamic reactivedeviceat Latham 230 kV substation.
1.3 Planned Operating Date
The plan of service for the facilities to be operationalis by November2020.
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 7 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
1.4 Scope
The Aeolus West transfer capability assessment assumes the addition of new wind generation
facilities plus the repoweredwind generation modeling data as noted in Table 1.While the
new technology and model information of the repoweredunits was used in the steady-state
and transient stability analysis,no incremental MW output was considered;i.e.,each
repowered facility was limited to its current Large Generator Interconnection (LGI)
agreement capacity.The study was performed using a 2021-22 heavy winter WECC
approvedcase which was modified to include the D.2 Projects and wind generation facilities.
The system model assumed summer line ratings to assess the thermal limitation of the
Wyoming system.Load served from Platte is normally represented as an open point between
Platte -Whiskey Peak 115 kV.The system configurationwith Platte l15 kV normally open
is presently the most limiting scenario for the existing TOT 4A/4B nomogram.
Table 1:GeneratingResource Scenario
O East Wyoming Jim Bridger Gen East Wyoming Repowered Wind New SE
Thermal Gen level (MW)Existing Wind (MW)Wyoming.Wind
(MW)(MW)(MW)
Dave Johnston -1400 -2100 1124 0.0 1169
Online (Foote Creek,Rock Repowering wind See Table 4
Wyodak -Online River,High Plains,turbine
Seven Mile Hill,representation was
Dunlap,Root added to the
Creek,Top of the system model but
World,Glenrock,the output was
Three Buttes,limited to existing
Chevron)LGI levels
2 Study Criteria
2.1 Thermal Loading
For system normal conditions described by the PO6 event,thermal loading on BES
transmission lines and transformers is requiredto be within continuous ratings.
O 6 Facility outage events that are identified with "P"designations are referenced to the TPL-001-4 NERC
standard.
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 8 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
For contingencyconditions described by Pl-P7 category planningevents,thermal loading on
transmission lines and transformers should remain within 30-minuteemergency ratings.
The thermal ratings of PacifiCorp's BES transmission lines and transformers are based on
PacifiCorp's Weak Link Transmission Database and Weak Link TransformerDatabase as of
March 31,2017.
2.2 Steady State Voltage Range
The steady state voltageranges at all PacifiCorp BES buses shall be within acceptable limits
as established in PacifiCorp's EngineeringHandbooksection 1B.3 "Planning Standards for
TransmissionVoltage"'as shown below.
Table 2:Voltage Criteria
Contingency Conditions (P1-OperatingSystem Normal Conditions (PO)
Configuration Vmin (pu)Vmax (pu)Vmin (pu)Vmax (pu)
Looped 0.95 1.06"0.90 1.10
Radial 0.90 1.06"0.85 1.10
Steady state voltage ranges at all applicable BES buses on adjacent systems were screened
based on the limits established by WECC regional criterion as follows:
95%to 105%of nominal for PO event (system normal),
90%to l10%of nominal for Pl-P7 events (contingency).
2.3 Post-Transient Voltage Deviation
Post-contingency steady state voltage deviation at each applicable BES load serving bus
(having no intermediate connection)shall not exceed 8%for Pl events.
2.4 Transient StabilityAnalysis Criteria
All voltages,frequencies and relative rotor angles are required to be stable and damped.
Cascading or uncontrolled separation shall not occur and transient voltage response shall be
within established limits.
I PacifiCorp EngineeringHandbook "Planning Standards for Transmission Voltage."April 8,2013.
O "In some situations,voltages may go as high as 1.08 pu at non-load buses,contingent upon equipment rating
review.
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 9 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
2.5 Transient Voltage Response
Transient stability voltage response criteria are based on WECC Regional Performance
Criteria WRl.3 throughWRl.5 as follows:
Transientstability voltage response at the applicable BES buses serving load (having
no intermediate connection)shall recover to at least 80%of pre-contingencyvoltage
within 20 seconds of the initiating event for all Pl-P7 category events,for each
applicablebus servingload.
For voltage swings following fault clearingand voltage recoveryabove 80%,voltage
dips at each applicable BES bus servingload (having no intermediate buses)shall not
dip below 70%of pre-contingencyvoltage for more than 30 cycles or remain below
80%of pre-contingencyvoltage for more than two seconds for all Pl-P7 category
events.
For contingencies without a fault (P2-1 category event),voltage dips at each
applicable BES bus servingload (having no intermediate buses)shall not dip below
70%of pre-contingencyvoltage for more than 30 cycles or remain below 80%of pre-
contingency voltagefor more than two seconds.
The following criteria were used to investigate the potential for cascading and uncontrolled
islanding.
Load interruption due to successive line tripping for thermal violations shall be
confmedto the immediate impacted areas and shall not propagate to other areas.The
highest available emergency rating is used to determine the tripping threshold for
lines or transformers when evaluatinga scenario that may lead to cascading.
Voltage deficiencies caused by either the initiating event or successive line tripping
shall be confinedto the immediate impacted areas,and shall not propagate to other
areas.
Positive damping in stability analysis is demonstrated by showing that the amplitude of
power angle or voltagemagnitude oscillations after a minimum of 10 seconds is less than the
initial post-contingency amplitude.Oscillations that do not show positive damping within a
30-second time frame shall be deemed unacceptable.
Stability studies shall be performedfor planning events to determine whetherthe BES meets
the performancerequirements.
O
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 10 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
Single contingencies (Pl category events):No generating unit shall pull out of
synchronism (excludes generators being disconnected from the system by fault
clearingaction or by a special protection system).
Multiple contingencies (P2-P7 category events):When a generator pulls out of
synchronism in the simulations,the resulting apparent impedance swings shall not
result in the tripping of any transmission system elements other than the generating
unit and its directly connected facilities.
Power oscillations are evaluated by exhibiting acceptable damping.The absence of
positive dampingwithin a 30-second time frameis considered un-damped.
3 Base Case Development
3.1 Base Case Selection
The base case development process involves selecting an approved WECC base case,
updatingthe models to represent existing and planned facilities (D.2 Project transmission and
wind generationfacilities)and then tuning the cases to maximum transfer conditions on the
WECC transmission path(s)being studied.For this study purpose,the published WECC
base case that is close to the projects'in-servicedate of November2020,which has average
load conditions based on 2021 load projection and availability of a stability case,was
selected.The WECC approvedbase case 2021-22 HW (created on August 19,2016)was
selected,which meets these criteria.This study focused on simultaneous transmission path
interaction in the Wyoming area between the Aeolus West and the TOT 4B transmission
paths;however,other transmission paths such as Yellowtail South (non-WECC path),Jim
Bridger West,TOT l A and TOT 3 (See Appendix A for path definitions)were monitored
throughoutthe study.
The various critical components for this study purpose from selected 2021-22HW base case
are listed below:
Table 3:Wyoming Load,Generation and Platte Normal Open Configurationin Base Case
North Wyoming PAC Load (including Wyodak load of 42 391 MWMW)
North Wyoming -Western Area Power Administration 211 MW(WAPA)Load
Eastern Wyoming PAC Load (including DJ load of 56 MW)474 MW
Eastern Wyoming PAC loads on WAPA system 95 MW
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 11 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
Central Wyoming Load (including JB load of 130 MW)434 MW
Yellowtail South Flow 192 MW
Yellowtail Generation 140/260 MW (Online/Max)
WAPA's Existing Small Generation in North Wyoming 26/50 MW(Online/Max)
WAPA's Existing Small Generation'°in Eastern Wyoming 484/584 MW(Online/Max)
Wyodak Generation (PacifiCorp/Black Hills)350/380 MW (Online/Max)
Dry Fork Generation (Basin Electric)420/440 MW (Online/Max)
Gross Laramie River Generation I (WAPA's swing machine)605 MW(Max)
Gross Laramie River Generation II 590/605 MW(Online/Max)
Gross Dave Johnston (DJ)Generation 700/774 MW(Online/Max)
Total Existing PAC East Wyoming Wind"Generation 885.7/1124 MW (Online/Max)
Rapid City DC W Tie 130 W2E (200 MW-bidirectional)
Stegall DC Tie 100 E2W (110 MW-bidirectional)
Sydney DC Tie 196 E2W (200 MW-bidirectional)
TOT 4A 627 MW
TOT 4B 469 MW
Jim Bridger (JB)Generation 2200 MW
Jim Bridger West Flow 2027 MW
TOT 3 1259.1 MW
TOT lA 195 MW
Platte -Mustang 115 kV Normal Open point Platte -Normal Open
WAPA'ssmall generation in north Wyoming includes;Boysen,BBill,Heart MT,Shoshone,Spring Mtn
10 WAPA's small generation in eastern Wyoming includes;Alcova.Fremont,Glendo,Guernsy,Kortes,
Seminoe,CLR_l,SS_Genl AND CPGSTN
"PAC eastern Wyoming wind generation includes;Root Creek.Three Buttes,Top of World,Glenrock,Rolling
Hills,Dunlap.Seven Mile Hill,Foote Creek and High Plains wind generation
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 12 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
3.2 GeneratingFacility Additions
Because the specific size and location of new and repowered Wyoming wind generation
associated with the EV2020 initiative will not be known until 1Q18,this study evaluated
anticipated Wyoming wind generation options12 for the preliminary Aeolus West analysis,
based on requests in the PacifiCorp Large Generation Interconnection(LGI)queue as a
proxy for new resources.The following generating facility assumptions were made and
added into the base case.
Table 4:AssumedGenerationProjects
Proposed New Wind Facilities Project size Point of Interconnection
Aeolus/Freezeout/Shirley Basin Area 320 MW Freezeout 230 kV
250 MW Aeolus 230 kV
250 MW Shirley Basin 230 kV
250 MW Shirley Basin 230 kV
Foote Creek Area 99 MW Foote Creek -High Plains 230 kV line
230 kV
Repowered Wind Facilities
High Plains/McFadden Ridge I Gen 0.0 MW High Plains 230 kV
Repowering (+29.75 MW)
Seven Mile Hill Gen Repowering 0.0 MW Freezeout 230 kV
(+27.65 MW)
Dunlap Gen Repowering (+26 MW)0.0 MW Shirley Basin 230 kV
Glenrock Gen Repowering I (+27.65)0.0 MW Windstar 230 kV
Glenrock Gen Repowering II (+27.65 0.0 MW Windstar 230 kV
MW)
TOTAL 1169 MW
See Appendix B for detail on repoweredand new wind farm modelling assumptions.
12 An additional resource option is outline in Sensitivity Study -Section 5.B.
O 3 The repowered generation was modeled,but the repowered MW output was not increased in the base case,
i.e.increase machine size was modeled,but output was limited to existing LGI agreement
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 13 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
3.3 Base Case Modification and Tuning
The 2021-22HW base case was modified to reflect the most recent Foote Creek,High Plains,
Top of the World and Three Buttes wind generation modeling as per recent MOD-032 data
submitted by each generator owner (GO).Transmission line impedances between Dave
Johnston and Standpipe were verified and updated and the transmission line ratings in the
2021-22 heavy winter case were modified to summer ratings,which represent the most
conservative thermal limitations.The Platte -Standpipe 230 kV dynamic line rating of
608/666/680MVA was assumed during the analysis.
The new wind resources listed in Table 4 were added to the base case and the existing
repoweredwind farm generator models and collector system data were updated.The Aeolus
West path was stressed by maximizing the output on all of the existing and new wind
generationfacilities.Output for the repoweredwind generation facilities was limited to the
existing LGI agreement generation levels.The additional generation in southeast Wyoming
was re-dispatched with Jim Bridger,central and southern Utah generation.The Jim Bridger
generationoutput was maintained such that Jim Bridger West path flows were held at 2400
MW.
As per the availabledata obtained from variouswind generation facilities at the time of this
study analysis,the base cases were reviewedand adjusted to ensure voltages in the collector
system of wind generation facilities were below 1.05 p.u.and that there was no reactive
power loop flow between the main generator step-up transformers GSU's for wind
generationfacility.This process involved tuning transformerand generator parameters such
that generators were producing appropriatereactivepower output.Additionally,within the
230 kV transmission system it was verified that the shunt reactive devices were accurately
represented,voltage profiles were normal,reactive power flows were within normal
operating ranges and transmission system voltage was maintained to match acceptable
PacifiCorp Transmission Voltage Schedules.
4 Path Studies
4.1 Aeolus West vs.TOT 4B
Based on the assumptions outlined above the study demonstrated that the Aeolus West
maximum transfer capability limit is 1696 MW,while meeting all NERC and WECC
performancecriteria.While this transfer level is 735 MW above the present TOT 4A (960
0
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 14 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
MW14)path limit for similar conditions,east to west transfers have effectively increased by
817.5 MW due to shifting the Platte area load (82.5 MW)east of the Aeolus West cut plane.
The Aeolus West path was stressed using by 3010 MW of total generation resources,which
includes thermal (Dave Johnston,717 MW -net),existing wind (l 124 MW),and new wind
(1169 MW)resources.It was assumed that the following eastern Wyoming thermal
generation was available for redispatch to maintain transfers on the Aeolus West and the
TOT 4B transmission paths:
Wyodak (268 MW)
DaveJohnston (717 MW,net)
The maximum flow limitation of 1696 MW was achieved by utilizing all new and existing
wind resources and reducing DaveJohnston generation by 149 MW.
Table 5:Aeolus West and TOT4B Corner Point Cases (See Figure 2)
Case TOT TOT 4B Platte -Limiting Element Outage
4A (MW)Latham
(MW)(MVA)
1 1696 103 546 Platte-Latham 230 kV line"Anticline -Aeolus 500
kV line outage with
RAS
2 1681 299 548 Platte-Latham 230 kV line"Anticline -Aeolus 500
kV line outage with
RAS
3 1651 499 547 Platte-Latham 230 kV lines Anticline -Aeolus 500
kV line outage with
RAS
4 1608 700 547 Platte-Latham 230 kV line"Anticline -Aeolus 500
kV line outage with
RAS
5 1575 857 -Yellowtail -Sheridan 230 kV N-0
line
547 Platte-Latham 230 kV line"Anticline -Aeolus 500
kV line outage with
RAS
14 Maximum nomogram point with normal open point at Platte and the dynamic line rating on Platte -
Standpipe 230 kV line is utilized
O "Platte -Latham 230 kV line flow may exceed the 557 MVA summer emergency rating depending on load at
Platte.Percentage loading is based on current rather than MVA.
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 15 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
See Appendix C for powerflow diagrams.
In the study,three different remedial action schemes (RAS)were considered for N-l outages:
i.Aeolus RAS to trip up to 640 MW of wind generation depending on pre-outage flow
conditions for any of the new transmission element outages between Aeolus -Jim
Bridger.
ii.Freezeout RAS to trip up to 140 MW of generation in the Freezeout area for the
Aeolus -Freezeout 230 kV line outage depending on the pre-outage flow conditions.
iii.Shirley Basin RAS to trip up to 60 MW of generation in the Shirley Basin area for the
Aeolus-Shirley Basin 230 kV line outage depending on pre-outage flow conditions.
Figure 2:Aeolus West Vs TOT4B Nomogram
WyomingSystem Operating Curve
O 2022 Heavy WinterLoads
Normal Open Point:Plattell5 kV
900
soo
700
600
500o
LL 400
200
I-100
0
0 200 400 600 800 1000 1200 1400 1600 1800
Aeolus West Flow (MW)
Figure 2 depicts that the Aeolus West and TOT 4B path interaction is minimized with the
addition of the D.2 Project,as indicated by the steeper curve (implying little or no path
interaction)as compared to present TOT 4A/TOT 4B interaction.However,anytime the
O
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 16 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
emergency dynamic line rating on Platte -Standpipe is lower than 651 MVA16 the
nomogram in Figure 2 will be shifted to the left.Therefore,a new system operating limit
(SOL)value will be identified to represent the real time rating restriction to the path.
Additionally,the load at Platte substation can cause a shift in the nomogram;higher load at
Platte can shift the curve towards the right and lower load at Platte can shift the curve
towards the left,making it more conservative.This is due to the Platte -Latham 230 kV line
beingthe limiting element,as mentioned in Table 5.
4.2 Base Case Development
The 2021-22 HW WECC case was modified to simultaneously stress the Aeolus West and
the TOT 4B path flows.The Aeolus West path was stressed using approximately2861 MW
of eastern Wyoming resource from a total of 30 10 MW (existing and future)wind and net
coal resource.These resources were re-dispatched with Jim Bridger and Utah Valley
resources such that the Jim Bridger West flows were maintained at 2400 MW.No additional
O resources were imported from WAPA into PAC to stress the Aeolus West path.Since the
future resources in eastern Wyoming are in excess of future availabletransmission capacity,
Dave Johnston plant output was reduced in eastern Wyoming.The Shiprock,San Juan and
Gladstone phase shifters were locked to regulate flow across the TOT 3 path between
Coloradoand Wyoming.
The TOT 4B path flows were adjusted between a minimum of 100 MW and a maximum of
857 MW.The Montana resources,up to 388 MW,were re-dispatched with WAPA (Dry
Fork)to reduce TOT 4B flow or re-dispatched with PAC resources to increase the TOT 4B
flow using Crossover,Rimrock and Steam Plant phase shifters in Montana.
4.3 Transient StabilityAnalysis
The stability analysis was performedusing GE provided model (GEO50 l)for repoweredand
new wind generation.The generic model for the Root Creek wind model was updated to
GE0501 (GE 1.85 units).Top of the World and Three Buttes were updated to GE 1.5 wind
turbine model provided by GE for PTI V33.The generic WECC models were used for the
Latham dynamic reactivedevice.
The transient stability study was performed for one (worst case)nomogram point of the
Aeolus West vs.the TOT 4B nomogram curve.The nomogram point with the heaviest
O N The highest loading on the Platte -Standpipe 230 kV line as per power flow analysis based on study
assumption.
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 17 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
Aeolus West flow was considered for stability study analysis.Table 6 provides the
nomogrampoint description.
Table 6:Nomogrampointfor Dynamic Stability
Case TOT TOT 4B Platte -Limiting Element Outage
4A (MW)Latham
(MW)(MVA)
1 1696 103 546 Platte-Latham 230 kV line Anticline -Aeolus
500 kV line outage
with RAS
See Appendix D for dynamic stability plots
Transientstability was performedon selective critical outages based on anticipated post fault
impact on the wind generation performance,especially for the portion of the system with a
O calculated short circuit ratio of approximately 1.5.Below is the list of critical transmission
outages.
1.Point of Rocks -Latham 230 kV line outage for three phase fault at Latham 230 kV
bus (5 cycles)
2.Standpipe -Platte 230 kV line outage for three phase fault at Standpipe 230 kV bus
(5 cycles)
3.Platte -Latham 230 kV line outage for three phase fault at Platte 230 kV bus (5
cycles)
4.Dave Johnston -Casper 230 kV line outage for three phase fault at Dave Johnston
230 V bus (5 cycles)
5.Amasa -Difficulty 230 kV line outage for three phase fault at Amasa 230 kV bus
(5 cycles)
6.Dave Johnston -Amasa 230 kV line outage for three phase fault at Dave Johnston
230 kV bus (5 cycles)
7.Shirley Basin -Aeolus 230 kV line outage for three phase fault at Shirley Basin
230 kV bus (5 cycles)
8.Freezeout -Standpipe 230 kV line outage for three phase fault at Freezeout 230 kV
bus (5 cycles)
O
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 18 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
9.Aeolus -Freezeout 230 kV line outage for three phase fault at Aeolus 230 kV bus
(5 cycles)
10.Aeolus -Anticline 500 kV line outage for three phase fault at Aeolus 230 kV bus (4
cycle fault and 10 cycles for RAS operation)
11.Aeolus -Anticline 500 kV line outage for three phase fault at Anticline 345 kV bus
(4 cycle fault and 10 cycles for RAS operation)
12.Riverton -Wyopo 230 kV line outage for three phase fault at Riverton 230 kV bus
(5 cycles)
Observation 1:During the stability analysis it was identified that the Latham SVC model
tripped on high voltage for Platte -Standpipe 230 kV line outage.Following the fault,the
Latham SVC is radial from Point of Rocks substation,causing high voltage at Latham 230
kV bus and tripping the SVC model.This issue can be resolved with changing the SVC
operating parameter such that the SVC blocks VAR supply for voltage below a certain
voltage level.
Observation 2:Additionally the slowest voltage recovery following the fault clearing
occurs for a fault at either the Anticline or the Jim Bridger 345 kV bus followed by the
loss of the new Aeolus -Anticline/Jim Bridger segment and operation of the Aeolus
RAS to drop generation,causing the largest angular separationbetween Jim Bridger and
Dave Johnston.For local fault conditions,the GE wind turbine models ramp down
momentarily,whereas the models do not ramp for remote faults.
Due to the fault being on the remote end (at Anticline or Jim Bridger)of the new Aeolus
-Bridger line segment,which is isolated from the wind farms,the voltage depression
seen by the wind generating units (modelled as current source)are not as low,the power
output is much higher during the fault and power output recovery is much faster after the
fault as comparedto the fault close to Aeolus.The remote fault results in more stress on
the system during the fault and post fault,which leads to slower voltage recovery.The
synchronous machines (modelled as voltage source)at Dave Johnston and Jim Bridger
(one unit offline in the stress base case)try to recover the system voltage,which leads to
higher angular separation between the two buses.Thus,the loss of the Aeolus -
Anticline/Jim Bridger segment with a remote fault is the most severe.
This issue can be mitigated by effectively sizing dynamic reactive device at Latham to
boost the system voltage.This disturbancedid not result in system instability or system
separation.
REDACTED
Rocky Mountain Power
Exhibit No.30 Page 19 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
Additionally,the stability analysis demonstratedthat all planning events met stability
performance criteria.
5 SensitivityAnalysis
A.A sensitivity study was performed to replace the SVC dynamic device model at
Latham with a generic STATCOM model.The dynamic simulations were
performed for a stressed base case and the STATCOM model displayed behavior
similar to the SVC model.High post fault voltage conditions require model data
adjustments to prevent SVC and STATCOM model blocking and tripping.
B.A sensitivity analysis was performed to evaluatethe system impacts of increasing
the magnitude and changing the location of generation resources identified in the
Assumed Generation Projects in Table 4.As part of this analysis,assumed wind
generation was increased from 1169 MW to 1270 MW,by increasing the
repowered generation by 137.5 MW and adding 240 MW of new generation in
the Bighorn area of northern Wyoming,and reducing the new wind generation at
Shirley Basin from 500 MW to 250 MW.(Other generation adjustments were
made for loads and resource balancing.)Due to reduced generation in southeast
Wyoming,Aeolus West transfer capability limit increased to 1790 MW.The
limiting element was the Platte -Latham 230 kV line emergency thermal rating
following outage of the Bridger/Anticline -Aeolus facilities and initiation of
associated generatingtripping.
The study also identified two different RAS schemes to trip generation for N-1
outage:
i.Aeolus RAS to trip up to 640 MW of wind generation dependingon pre
outage flow conditions for any of the new transmission element outage
between Aeolus -Anticline/Jim Bridger segment.
ii.Freezeout RAS to trip up to 190 MW of generation in Freezeout area for
Aeolus -Freezeout 230 kV line outage depending on pre outage flow
conditions.
Therewere no additional system improvementrequirements identified.
O
REDACTED
Rocky Mountain Power
ExhibitNo.30 Page 20 of 24
Case No.PAC-E-17-07
Witness:Rick A.Vail
O
6 Study Conclusions
Technical studies demonstrated that with the addition of the planned D.2 Project
facilities to the Wyoming transmission system,system performancewill meet all NERC
and WECC performancecriteria.
Preliminary power flow studies demonstrate that by utilizing existing and planned
southeast Wyoming resourceS4,the Aeolus West transmission path can transfer up to
1696 MW under simultaneous transfer conditions with the TOT 4B transmission path,
effectively'increasing the east to west transfer levels across Wyoming by 817.5 MW.
Power flow findings also indicated:
Dynamic voltage control is necessary at the Latham 230 kV substation to
mitigate low voltage conditions resultingfrom loss of Bridger/Anticline -Aeolus
transmission facilities.
Under certain operating conditions,three different Remedial Action Schemes
(RAS)will need to be implemented to trip generation following outage of
specific transmission facilities.
The location (and output level)of new and repowered wind resources can
influencethe transfercapability level across the Aeolus West transmission path.
While a wide range of disturbances were evaluated,dynamic stability studies identified
that the slowest post fault voltage recovery will occur for a fault at Anticline or Jim
Bridger 345 kV bus followed by loss of the Bridger/Anticline -Aeolus transmission
segment and the planned operationof a generation tripping (RAS)scheme.The stability
analysis demonstrated that all planned system events met the stability performance
criteria.