HomeMy WebLinkAbout20180412press release.pdf Case No. PAC-E-17-03
Final Order: 34018
Contact: Matt Evans
(208) 334-0339 office
(208) 520-4763 cell
www.puc.idaho.gov
Commission accepts Rocky Mountain Power
long-range planning document
BOISE (April 12, 2018) – Regulators have accepted a long-range planning document
outlining how Rocky Mountain Power intends to meet the demand for electricity among its
customers over the next 20 years.
Rocky Mountain Power’s Integrated Resource Plan (IRP) represents a “cost-conscious plan
to transition to a cleaner energy future,” according to the company, which serves
approximately 75,000 customers in eastern Idaho.
The IRP anticipates significant reductions in coal generation along with investments in
renewable resources, transmission infrastructure and energy efficiency programs.
Regulated electric utilities are required to submit an IRP every other year. It serves as a
status report outlining the company’s ongoing plans for providing adequate and reliable
service to its customers at the lowest cost and least risk during the planning period.
The Commission’s acknowledgement of an IRP does not necessarily mean the projects
highlighted will be completed, but rather that the utility has met its long-range planning
requirements.
Rocky Mountain Power’s 2017 IRP was developed with input from a diverse group of
stakeholders, including customer advocacy groups, regulatory staff and other interested
parties.
It identifies “the company’s plans to provide reliable and reasonably priced service to its
customers.”
Those plans call for the retirement of more than 3,500 megawatts of coal-fired generation,
anticipating that it will be replaced primarily with renewables such as wind and solar.
Efficiency measures, two new natural gas facilities and wholesale power purchases are also
expected to help meet the demand for energy through 2036.
The IRP’s action plan, which outlines the company’s plans for the first 10 years of the
planning horizon, includes what the company refers to as its Energy Vision 2020 projects,
which calls for the addition of 1,100 MW of new wind resources and 905 MW of upgraded
or “repowered” wind resources, and construction of a transmission line in Wyoming.
The wind projects must be operational by the end of 2020 in order to receive the full
benefits of federal tax credits.
The electricity generated at the new wind facilities would be carried via a 140-mile, 500-
kilovolt transmission line in Wyoming that is expected to relieve congestion on Rocky
Mountain’s transmission system.
After 2020, the utility’s preferred portfolio calls for 859 MW of new wind generation,
including the addition of 774 MW in Idaho in 2036.
The IRP also anticipates 1,040 MW of new solar resources to come online between 2028
and 2036, with the majority installed in Utah beginning in 2031.
The first new natural gas-fired resource is expected to be added in 2029, a year later than
anticipated in Rocky Mountain’s 2015 IRP.
Demand-side management resources (DSM), which include energy efficiency and
conservation, are also expected to play a key role in helping the company meet customers’
demand for electricity.
The IRP indicates incremental energy-efficiency resources are expected to provide a 2,077
MW reduction, enough to meet 88 percent of the forecasted load growth through 2026.
Aside from energy efficiency, the company’s DSM resources include load control programs
capable of shifting energy use away from periods of peak demand for energy. This shift
helps the utility avoid or defer the need for new power plants.
Customers enrolled in load control programs allow the utility to remotely curtail their
energy use – shutting down irrigation pumps, for example - in exchange for incentives such
as reduced rates or a bill credit.
The 2017 IRP calls for load control to be capable of reducing the demand for energy, or
load, by 365 MW by the end of the planning period. The company’s previous IRP called for
load control programs to have a load-shedding capacity of less than 50 MW.
Rocky Mountain does not anticipate upgrades to coal plants in order to meet
environmental regulations, a decision that will “save customers hundreds of millions of
dollars,” according to the company. Instead, the IRP calls for the retirement of those coal-
fired units.
Commission staff asserted that more analysis should have been conducted in order to
better gage the economics of coal plant retirements, including earlier closure of some units,
to ensure that Rocky Mountain identified the least-cost generation resources. The company
agreed to conduct additional analysis of its coal units as it prepares its 2019 IRP.
The company expects to offset a portion of the lost coal generation throughout the planning
period with market purchases, although Rocky Mountain intends to construct two new
natural gas facilities – a 200-MW frame simple cycle combustion turbine in 2029, and a
436-MW combined combustion turbine in 2030.
Over the life of the IRP, the preferred portfolio includes 1,313 MW of new natural-gas
capacity. That is a reduction of 1,540 MW relative to the 2015 IRP.
In its analysis of the IRP, Commission staff said there is a high probability that the company
underestimated natural gas prices over the 20-year planning period, and criticized the
limited public input taken by the company regarding the preferred portfolio outlined in the
IRP due to the “late introduction” of the Energy Vision 2020 projects.
The company countered that it took public input on the projects at the “earliest possible
point” and recognized “the need to be open and transparent.” Rocky Mountain also said
concerns about gas prices are misplaced, claiming its assumptions were “reasonable and
align with current market fundamentals driven by projections of supply and demand.”
In its order acknowledging the IRP, the Commission said it expects the company “to
actively consider the concerns raised in this case as it plans, and to continue evaluating all
resource options and the best interests of its customers when developing the 2019 IRP.”
All documents related to this case, including the Commission’s order, are available on the
Commission’s web site, www.puc.idaho.gov. To review them, click on “Open Cases” under
the “Electric” heading and scroll down to the case number, PAC-E-17-03. Or go here.