HomeMy WebLinkAbout20130328notice_of_application_order_no_32772.pdfOffice of the Secretary Servlce Date March 28, 201 3 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF ROCKY MOUNTAIN ) POWER'S APPLICATION TO CHANGE ) CASE NO. PAC-E-13-02 THE DEPRECIATION RATES APPLICABLE ) TO ITS ELECTRIC PROPERTY ) NOTICE OF APPLICATION 1 ) NOTICEOF ) INTERVENTION DEADLINE 1 ) ORDER NO. 32772 YOU ARE HEREBY NOTIFIED that on January 22, 2013, PacifiCorp dba Rocky Mountain Power ("RMP" or "Company") submitted an Application seeking a Commission Order, pursuant to Idaho Code Ej 61-525 and Rule 52 of the Idaho Public Utilities Commission ("Commission") Rules of Procedure, for approval of proposed changes to depreciation rates applicable to RMP's depreciable electric plant. The Company proposes January 1, 2014, as the effective date for the proposed changes. YOU ARE FURTHER NOTIFIED that the Company's last depreciation application, Case No. PAC-E-07- 14, was filed on August 3 1, 2007, with rates effective January 1,2008. YOU ARE FURTHER NOTIFIED that the Company has performed an updated depreciation study ("Depreciation Study") and requests authorization to implement the depreciation rates set forth in the Exhibit No. 3 attached to its Application. YOU ARE FURTHER NOTIFIED that the Depreciation Study identifies changes that have occurred since the Company's last depreciation study, measures the effect of the changes on the prudent recovery of presently surviving capital, and proposes revisions to the current depreciation rates. YOU ARE FURTHER NOTIFIED that the results of the Depreciation Study suggest an increase in annual depreciation expense of approximately $83.9 million ($160.8 million including the accelerated depreciation associated with early retirement of the Carbon plant) on a total Company basis, based on projected plant balances as of December 3 1, 2013. YOU ARE FURTHER NOTIFIED that RMP states that its proposed changes would result in an estimated increase to the Idaho jurisdictional depreciation expense of approximately NOTICE OF APPLICATION NOTICE OF INTERVENTION DEADLINE ORDER NO. 32772 1 $4.5 million ($8.9 million including the early retirement of the Carbon plant) beginning January 1, 2014. YOU ARE FURTHER NOTIFIED that in order to maintain consistent depreciation rates across its six jurisdictionslservice territories, the Company has filed for approval of its Depreciation Study in Oregon, Utah, Wyoming, and Washington. YOU ARE FURTIHER NOTIFIED that, in support of its Application, the Company attached the direct testimony of Henry E. Lay, Corporate Controller of PacifiCorp, John J. Spanos, Senior Vice President of Gannett Fleming, Inc., and K. Ian Andrews, Manager of Resource Development for PacifiCorp. YOU ARE FURTHER NOTIFIED that RMP requested that this matter be processed through Modified Procedure. NOTICE OF INTERVENTION DEADLINE YOU ARE FURTHER NOTIFIED that persons desiring to intervene in this matter must file a Petition to Intervene with the Commission pursuant to this Commission's Rules of Procedure 72 and 73. IDAPA 3 1 .01.0 1.072 and -.073. Persons intending to participate as parties in this case must file a Petition to Intervene within 14 days of the service date of this Order YOU ARE FURTHER NOTIFIED that the following persons are designated as RMP's representatives in this matter: Daniel Solander Ted Weston Rocky Mountain Power Rocky Mountain Power 201 S. Main. Suite 2300 201 S. Main, Suite 2300 Salt Lake City, UT 841 11 Salt Lake City, UT 841 1 1 E-mail: daniel.solander@pacificorp.com E-mail: ted.westonO,pacificorp.com YOU ARE FURTHER NOTIFIED that once the deadline for intervention has passed, the Commission Secretary shall prepare a Notice of Parties. Once the Notice of Parties is issued, Staff counsel will convene an informal prehearing conference or public workshop to discuss a possible settlement of the issues presented in this case. YOUARE FURTHER NOTIFIED that all hearings and prehearing conferences in this matter will be held in facilities meeting the accessibility requirements of the Americans with Disabilities Act (ADA). Persons needing the help of a sign language interpreter or other assistance in order to participate in or to understand testimony and argument at a public hearing may ask the Commission to provide a sign language interpreter or other assistance at the hearing. NOTICE OF APPLICATION NOTICE OF INTERVENTION DEADLINE ORDER NO. 32772 2 The request for assistance must be received at least five (5) working days before the hearing by contacting the Commission Secretary at: IDAHO PUBLIC UTILITIES COMMISSION PO BOX 83720 BOISE, IDAHO 83720-0074 Tel: (208) 334-0338 Fax: (208) 334-3762 E-Mail: secretary@puc.idaho.gov YOU ARE FURTHER NOTIFIED that Rule 276 provides that the Commission is not bound by any settlement which may be reached by the parties. IDAPA 31.01.01.276. If a settlement is reached, the Commission will "independently review any settlement proposed to it to determine whether the settlement is just, fair and reasonable, in the public interest or otherwise in accordance with law or regulatory policy." Id. The Commission may accept, reject or modify any settlement. Moreover, the proponents of settlement carry the burden of showing that the settlement is reasonable and in the public interest. Rule 275. When a settlement calls for Commission action, the Commission will prescribe an appropriate procedure to examine the proposed settlement. Rule 274. YOU ARE FURTHER NOTIFIED that all proceedings in this matter will be conducted in accordance with the Commission's Rules of Procedure, IDAPA 31.01.01.000 et sey. O R D E R IT IS HEREBY ORDERED that persons desiring to intervene in this matter shall file a Petition to Intervene within 14 days of the service date of this Order. IT IS FURTHER ORDERED that once the deadline for Petitions to Intervene has passed, the Commission Secretary shall prepare and issue a Notice of Parties. Staff counsel shall convene an informal prehearing conference or public workshop so that interested parties may discuss a possible settlement of the issues presented in this case. NOTICE OF APPL,ICATION NOTICE OF INTERVENTION DEADLINE ORDER NO. 32772 3 DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this ;g " day of March 20 13. MARSHA H. SMITH, COMMISSIONER ATTEST: Commission Secretary NOTICE OF APPLICATION NOTICE OF INTERVENTION DEADLINE ORDER NO. 32772 4