HomeMy WebLinkAboutFinal Approved Schedule No 94.pdf~~~~o~OUNTAIN
I.P.U.C. No.1 Original Sheet No. 94.1
ROCKY MOUNTAIN POWER
ELECTRIC SERVICE SCHEDULE NO. 94
STATE OF IDAHO
Energy Cost Adjustment
AVAILABILITY: At any point on the Company's interconnected system.
APPLICATION: This Schedule shall be applicable to all retail tariff Customers taking service
under the Company's electric service schedules.
ENERGY COST ADJUSTMENT: The Energy Cost Adjustment is calculated to collect the
accumulated difference between total Company Base Net Power Cost and total Company Actual Net Power
Cost calculated on a cents per kWh basis.
MONTHLY BILL: In addition to the Monthly Charges contained in the Customer's applicable
schedule, all monthly bils shall have applied the following cents per kilowatt-hour rate by delivery voltage.
Secondary
Schedule 1 0.100Ø per kWh
Schedule 6 0.100Ø per kWh
Schedule 6A 0.100Ø per kWh
Schedule 7 0.100Ø per kWh
Schedule 7A O.lOOØ per kWh
Schedule 9
Schedule 10 0.100Ø per kWh
Schedule 11 0.100Ø per kWh
Schedule 12 O.lOOØ per kWh
Schedule 19 0.100Ø per kWh
Schedule 23 0.100Ø per kWh
Schedule 23A 0.100Ø per kWh
Schedule 24 0.100Ø per kWh
Schedule 35 0.100Ø per kWh
Schedule 35A 0.100Ø per kWh
Schedule 36 0.100Ø per kWh
Delivery Voltage
Primary Transmission
0.093Ø per kWh
0.093Ø per kWh
0.091Ø per kWh
0.093Ø per kWh
0.093Ø per kWh
0.093Ø per kWh
0.093Ø per kWh
0.093Ø per kWh
Submitted Under Case No. PAC-E-I0-0l
ISSUED: March 17,2010 EFFECTIVE: April 1,2010
IDAHO PUBLIC UTILITIES COMMISSION
Approved Effective
March 31, 2010 April 1, 2010
Per O.N. 31033
Jean D. Jewell Secretary