HomeMy WebLinkAbout20091217notice_of_application_pac.pdfOffice of the Secretary
Service Date
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
December 17, 2009
IN THE MATTER OF THE APPLICATION
OF PACIFICORP DBA ROCKY MOUNTAIN
POWER FOR APPROV AL OF A POWER
PURCHASE AGREEMENT BETWEEN
ROCKY MOUNTAIN POWER AND BELL
MOUNTAIN HYDRO LLC
CASE NO. PAC-O9-
NOTICE OF APPLICATION
NOTICE OF
MODIFIED PROCEDURE
NOTICE OF
COMMENT/PROTEST DEADLINE
YOU ARE HEREBY NOTIFIED that on December 4, 2009, PacifiCorp dba Rocky
Mountain Power (PacifiCorp; Company) filed an Application with the Idaho Public Utilities
Commission (Commission) requesting approval of a 20-year Power Purchase Agreement
between PacifiCorp and Bell Mountain Hydro, LLC (Bell Mountain) dated November 17, 2009
(Agreement).
Bell Mountain intends to construct, own, operate and maintain a Pelton-wheel
hydroelectric generating facility (Facility) for the generation of electric power located
approximately 40 miles north of Howe, Idaho, in Butte and Lemhi Counties at a location more
particularly described as: SW 1/4 of the SW 1/4, Section 7, Township ION, Range 27E, Boise
Meridian. Bell Mountain warrants that the Facility will be a qualified small power production
facility (QF) under the applicable provisions of the Public Utility Regulatory Policies Act of
1978 (PURPA). Agreement,-r 3.
The facility is described as the following:
Two creeks, Bell Mountain Creek and Mahogany Creek, feed into a two-mile
canal, which Seller has recently lined, and 16 000 feet of new steel pipe.
Seller has also installed a new Pelton-wheel and a new 290 kW generator.
The water is used both for irrigation and power production. Water flow is
year-round and irrigation season is from April to October. Seller has a non-
consumptive water right to generate power. Seller has the ability to store
approximately 10 acre-feet of water in the canal (the "Pond"), which is
equivalent to about seven hours of generation at the Facility Capacity Rating.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
Seller has no right to directly or indirectly regulate the flow of water to the
Facility except the cycling, or storing, of approximately 10 acre-feet of water
in the canal immediately upstream of the Facility s generating structure.
Agreement, Exh. A.
The submitted Agreement, as reflected in the Application, is the result of negotiation
and compromise. PacifiCorp will pay Bell Mountain non-Ievelized conforming energy or non-
conforming energy purchase prices for net output adjusted for the month and on-peak/off-peak
hours in accordance with Commission Order Nos. 30423 (monthly and daily price multipliers),
30480 (SAR methodology - fuel cost component), and 30744 (Conforming Energy Annual
Rates). The parties recognizing the intermittent nature of the resource have also agreed to
include a mechanical availability guarantee (MAG) and as a surrogate adopt the Company
current $5.1 O/MWh wind integration cost adjustment. Agreement,-r 5.1. In addition, the
Agreement contains provisions for delay liquidated damages (,-r 2.3) to secure the established
scheduled commercial operation date of December 15 2009.
The nameplate rating of the Facility is 290 kW. Agreement, Exh. A. The estimated
annual net generation is 1 102 530 kWh. Agreement, Exh. D. Under normal and/or average
conditions, the Facility will not exceed 10 aMW in any calendar month. Should the Facility
exceed 10 aMW on a monthly basis, PacifiCorp may accept inadvertent energy at its sole
discretion, but will not purchase or pay for inadvertent energy. Agreement,-r 5.
The Scheduled Commerical Operation Date of the Facility is December 15 , 2009.
Agreement,-r 2.2.4. Agreement,-r 2.1 provides that the Agreement will not become effective until
the Commission has approved all of the Agreement's terms and conditions and declares that all
payments PacifiCorp makes to Bell Mountain are just and reasonable and legitimate expenses, all
of which the Commission will allow PacifiCorp to recover in rates in Idaho in the event other
jurisdictions deny recovery of their proportionate share of said expenses.
YOU ARE FURTHER NOTIFIED that the Commission has reviewed the filings of
record in Case No. PAC-09-09. The Commission has preliminarily found that the public
interest in this matter may not require a hearing to consider the issues presented and that issues
raised by the Company s filing may be processed under Modified Procedure , by written
submission rather than by hearing. Reference Commission Rules of Procedure, IDAP
31.01.01.201-204.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
YOU ARE FURTHER NOTIFIED that the deadline for filing written comments or
protests with respect to PacifiCorp s Application and the use of Modified Procedure in Case No.
P AC-09-09 is Friday, January 8, 2010.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the deadline, the Commission may consider the matter on its merits and may
enter its Order without a formal hearing. If comments or protests are filed within the deadline
the Commission will consider them and in its discretion may set the matter for hearing or may
decide the matter and issue its Order based on the written positions before it. Reference IDAP
31.01.01.204.
YOU ARE FURTHER NOTIFIED that written comments concerning Case No. PAC-
09-09 should be mailed to the Commission and the Company at the addresses reflected below.
Street Address for Express Mail:
Bruce Griswold, Director
Short- Term Origination
PacifiCorp
825 NE Multnomah, Suite 1800
Portland, OR 97232
E-mail: bruce.griswold~pacificorp.com
Commission Secretary
Idaho Public Utilities Commission
PO Box 83720
Boise, ID 83720-0074
472 W. Washington Street
Boise, ID 83702-5918
Ted Weston
Idaho Regulatory Affairs Manager
Daniel E. Solander, Senior Counsel
Rocky Mountain Power
201 S. Main Street, Suite 2300
Salt Lake City, UT 84111
E-mail: daniel.solander~pacificorp.com
ted. weston~pacificorp.com
All comments should contain the case caption and case number shown on the first page of this
document. Persons desiring to submit comments via e-mail may do so by accessing the
Commission s home page located at www.puc.idaho.gov. Click the "Comments and Questions
icon and complete the comment form using the case number as it appears on the front of this
document. These comments must also be sent to PacifiCorp at the e-mail addresses listed above.
YOU ARE FURTHER NOTIFIED that the Application in Case No. PAC-09-
may be viewed at www.puc.idaho.gov by clicking on "File Room" and "Electric Cases " or can
be viewed during regular business hours at the Idaho Public Utilities Commission, 472 W.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
Washington Street, Boise, Idaho and at the Idaho offices of PacifiCorp dba Rocky Mountain
Power.
DA TED at Boise, Idaho this /1 day of December 2009.
JI SIDENT
MARSHA H. SMITH, COMMISSIONER
ATTEST:
~tO
, D. Jewell
Commission Secretary
bls/O:PAC-O9-09 sw
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE