HomeMy WebLinkAbout20090923notice_of_petition.pdfOffice of the Secretary
Service Date
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
September 23 , 2009
IN THE MATTER OF THE PETITION OF
ACIFICORP DBA ROCKY MOUNTAIN
POWER FOR AN ORDER REVISING THE
WIND INTEGRATION RATE FOR WIND-
POWERED SMALL POWER GENERATION
QUALIFYING FACILITIES
) CASE NO. PAC-O9-
) NOTICE OF PETITION
) NOTICE OF
) MODIFIED PROCEDURE
) NOTICE OF
) COMMENT/PROTEST DEADLINE
YOU ARE HEREBY NOTIFIED that on September 2009, PacifiCorp dba Rocky
Mountain Power filed a Petition with the Idaho Public Utilities Commission (Commission) for
an Order increasing the published avoided cost wind integration rate from $5.10 to $9.90 per
MWh. Avoided cost rates are the purchase price paid to qualifying small power production
facilities (QFs) for purchases of QF capacity and energy. The proposed change will be
applicable to purchases by Rocky Mountain Power of electric power from wind-powered QFs
except in those circumstances where the QF developer agrees in the power purchase agreement
to deliver QF output to Rocky Mountain Power on a firm hourly schedule.
BACKGROUND
The Commission in Order No. 29839, Case No. IPC-05-, found that the supply
characteristics of wind generation and related integration costs could provide a basis for
adjustment of the published avoided cost rates, an adjustment that may be different for each
utility. In subsequent Order No. 30497 in Case No. PAC-07-, the Commission approved a
Settlement Stipulation which by its terms required Rocky Mountain Power to file notice with the
Commission of any changes to its wind integration costs as reflected in subsequent changes to its
Integrated Resource Plan (IRP). Settlement Stipulation, Section 1I1( a)( c)( d).
1 Reference Sections 201 and 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA) and the
implementing regulations of the Federal Energy Regulatory Commission (FERC).
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
PETITION
Rocky Mountain Power submits as Exhibit A to its Petition, an excerpt from
PacifiCorp s 2009 IRP Appendix F - "wind integration costs and capacity planning
contributions" in which PacifiCorp provides a description of the methodology used and the
results derived from PacifiCorp s analysis of the wind integration cost issue. The Company
2009 IRP wind integration cost analysis identifies its wind integration cost to be $9.96 per MWh.
The Company filed its 2009 IRP with the Commission on May 29, 2009 in Case No. P AC-09-
06. A Notice of the Company s IRP filing was issued on June 24, 2009; the deadline for filing
written comments was July 31 , 2009. Commission Staff was the only party to file comments.
On September 15 , 2009, the Commission issued an acceptance and acknowledgement of the
Company s 2009 IRP filing.
YOU ARE FURTHER NOTIFIED that the Commission has reviewed the filings of
record in Case No. PAC-09-07. The Commission has preliminarily found that the public
interest in this matter may not require a hearing to consider the issues presented and that the
issues raised by the Company s filing may be processed under Modified Procedure , by
written submission rather than by hearing. Reference Commission Rules of Procedure, IDAP A
31.01.01.201-204.
YOU ARE FURTHER NOTIFIED that the deadline for filing written comments or
protests with respect to Rocky Mountain Power s Application and the use of Modified
Procedure in Case No. PAC-09-07 is Friday, October 30, 2009. Persons desiring a hearing
must specifically request a hearing in their written protests or comments.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the deadline, the Commission may consider the matter on its merits and may
enter its Order without a formal hearing. If comments or protests are filed within the deadline
the Commission will consider them and in its discretion may set the matter for hearing or may
decide the matter and issue its Order based on the written positions before it. Reference IDAP
31.01.01.204.
YOU ARE FURTHER NOTIFIED that written comments concernIng Case No.
P AC-09-07 should be mailed to the Commission and the Company at the addresses reflected
below.
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
Commission Secretary
Idaho Public Utilities Commission
PO Box 83720
Boise, ID 83720-0074
Street Address for Express Mail:
Daniel E. Solander
Senior Counsel
Rocky Mountain Power
201 S. Main Street, Suite 2300
Salt Lake City, UT 84111
E-mail: daniel.solander(fYpacificorp.com
472 W. Washington Street
Boise, ID 83702-5918
Ted Weston, Manager
Idaho Regulatory Affairs
Rocky Mountain Power
201 S. Main Street, Suite 2300
Salt Lake City, UT 84111
E-mail: ted.weston((l),pacificorp.com
All comments should contain the case caption and case number shown on the first page of this
document.Persons desiring to submit comments via e-mail may do so by accessing the
Commission s home page located at www.puc.idaho.gov. Click the "Comments and Questions
icon and complete the comment form using the case number as it appears on the front of this
document. These comments must also be sent to PacifiCorp at the e-mail addresses listed above.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the time limit set, the Commission may consider this matter on its merits and
issue its Order without a formal hearing. If written comments are received within the time limit
set, the Commission will consider them, and in its discretion may set the same for formal
hearing.
YOU ARE FURTHER NOTIFIED that the Petition in Case No. PAC-09-07 may
be viewed at www.puc.idaho.gov by clicking on "File Room" and "Electric Cases " or can be
viewed during regular business hours at the Idaho Public Utilities Commission, 472 West
Washington Street, Boise, Idaho and at the Idaho offices of PacifiCorp dba Rocky Mountain
Power.
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
DATED at Boise, Idaho this ;;z;L day of September 2009.
J.
JIM . KEMPTON, P SIDENT
MARSHA H. SMITH, COMMISSIONER
~~~
MACK A. REDFO
ATTEST:
~~_
D. Jewell
Co mission Secretary
blsIO:PAC-09-07 sw
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE