HomeMy WebLinkAbout20030205Second Errata - Final Order No 29157.pdfOffice of the Secretary
Service Date
February 5, 2003
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF PACIFICORP DBA UTAH POWER &
LIGHT COMPANY FOR APPROVAL OF
INTERIM PROVISIONS FOR THE SUPPLY
OF ELECTRIC SERVICE TO MONSANTO
COMPANY
SECOND ERRATA TO
FINAL ORDER NO. 29157
CASE NO. PAC-OI-
On January 27, 2003, IPUC Order No. 29157 was issued by this Commission. The
following change should be made to that Order:
Page 11 , lines 4-
READS:
Using 1 000 hours the Irrigators calculate a rate of25.45 mills/kWh. Tr. p.
730, Exh. 101.
SHOULD READ:
Using 1 000 hours the Irrigators calculate a rate of up to 20.45 mills/kWh.
Tr. p. 746, 766, Exh. 301.
DATED at Boise, Idaho this 5 ,.,.day of February 2003.
~AJ.Je D. Jewell
Commission Secretary
bls/O:PACEOl16 29157errata2