HomeMy WebLinkAbout20240102Tariff Advice No. IPC-TAE-23-03.pdf
CONNIE ASCHENBRENNER
Rate Design Senior Manager
caschenbrenner@idahopower.com
VIA ENCRYPTED ELECTRONIC MAIL
December 29, 2023
Commission Secretary
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg 8,
Suite 201-A (83714)
PO Box 83720
Boise, Idaho 83720-0074
Re: Tariff Advice No. 23-03
Annual Compliance Filing to Update the Substation Allowance Amount under
Schedule 19, Large Power Service
Dear Commission Secretary,
Idaho Power Company (“Idaho Power” or “Company”) hereby submits its proposed
update to the Substation Allowance amount outlined in Schedule 19, Large Power Service
(“Schedule 19”). This is the annual compliance filing to update the Substation Allowance
amount contained within Schedule 19, as required by Idaho Public Utilities Commission
(“Commission”) Order Nos. 32893 and 32914. The following tariff sheet identifies the
proposed modification:
Tenth Revised Sheet No. 19-6 Cancelling Ninth Revised Sheet No. 19-6
The cost estimation methodology the Company used in this tariff advice is the
same methodology approved by the Commission in Case No. IPC-E-13-09 and
subsequent annual filings.
The proposed Substation Allowance amount reflects updated material costs, labor
rates, and the stations overhead rate, which in total results in the proposed per megawatt
Substation Allowance amount decreasing from $79,444 to $71,006, or by approximately
11 percent. The primary driver attributed to the decreased Substation Allowance amount
being proposed is the approximate 42 percent decrease in the cost of the 4-unit
metalclad switchgear, which more than offset the approximate 33 percent cost increase
RECEIVED
2023 December 29, PM 2:00
IDAHO PUBLIC
UTILITIES COMMISSION
Tariff Advice No. IPC-TAE-23-03
Commission Secretary
December 29, 2023
Page 2 of 3
of the 138kV/13.09kV, 44.8 MVA transformer. Another factor contributing to the decrease
in the Substation Allowance was a reduction in the stations overhead rate from 6.57
percent to 4.7 percent.
The workpapers used to calculate the per megawatt Substation Allowance amount
and the stations overhead rate are provided as confidential attachments to this tariff
advice. Please note that information in the workpapers is commercially sensitive and, if
disclosed freely, could subject Idaho Power or its customers to risk of competitive
disadvantage or other business injury.
The Company respectfully requests that the proposed updates are approved and
become effective by February 1, 2024.
If you have any questions regarding this tariff advice, please contact Regulatory
Analyst Ashley Herrera at 208-388-2656 or aherrera@idahopower.com.
Sincerely,
Connie Aschenbrenner
CA:sg
Enclosures
CERTIFICATE OF ATTORNEY
ASSERTION THAT MATERIALS REQUESTED AND PROVIDED DURING THE
COURSE OF AN IDAHO PUBLIC UTILITIES COMMISSION PROCEEDING
ARE PROTECTED FROM PUBLIC INSPECTION
Tariff Advice No. 23-03
The undersigned attorney, in accordance with RP 67, believes that the attachments
to Idaho Power Company’s Tariff Advice No. 23-03 filing contain information that Idaho
Power Company claims is a trade secret as described in Idaho Code § 74-101, et seq.,
and § 48-801, et seq., or otherwise protected from public disclosure, and as such is
exempt from public inspection, examination, or copying.
DATED this 29th day of December 2023.
Lisa D. Nordstrom
Counsel for Idaho Power Company
Idaho Power Company Tenth Revised Sheet No. 19-6
Cancels
I.P.U.C. No. 29, Tariff No. 101 Ninth Revised Sheet No. 19-6
IDAHO Issued by IDAHO POWER COMPANY
Issued – December 29, 2023 Timothy E. Tatum, Vice President, Regulatory Affairs
Effective – February 1, 2024 1221 West Idaho Street, Boise, Idaho
Advice No. 23-03
SCHEDULE 19
LARGE POWER SERVICE
(Continued)
SPECIAL ARRANGEMENTS FOR SUBSTATION ALLOWANCES AND/OR TRANSMISSION VESTED
INTEREST (Continued)
Definitions (Continued)
Transmission Vested Interest Portion is that part of the Company’s transmission system in which
a Transmission Vested Interest is held.
Substation Allowance
If a Schedule 19 Customer’s request for service requires the installation of new or upgraded
transformer capacity in Substation Facilities, the following considerations will be included in the separate
agreement between the Customer and the Company:
The Customer will initially pay for the cost of new or upgraded Substation Facilities
required because of the Customer’s request. The Customer will be eligible to receive a one-time
Substation Allowance based upon subsequent sustained usage of capacity by the Customer.
a. Substation Allowance: The maximum possible allowance will be
determined by multiplying the Customer’s actual increase in load by $71,006 per MW, but
will not exceed the actual cost of the Substation Facilities.
b. Substation Allowance Refunds: The Substation Allowance will be refunded
to the Customer over a five-year period, with annual payments based on the Customer’s
Basic Load Capacity at the time of refund. The first refund will be paid one year following
the first month energy is delivered through the new Substation Facilities.
The refunds will occur based on the following adjustment, which will be
added to the Substation Allowance received in the previous year. If there is no
change in load from the previous year, the Substation Allowance for that year is
equal to the Substation Allowance from the previous year:
((Change in load from the previous year as measured in MW) x (Substation Allowance per MW))
Number of Substation Allowance Refunds remaining in five-year period
The Customer’s annual refunds will be made in accordance with the
Substation Allowance amount stated in the separate construction agreement
between the Customer and the Company.
Transmission Vested Interest
If a Schedule 19 Customer’s request for service requires the installation of new or upgraded
capacity in Transmission Facilities, and those Transmission Facilities are serving the Customer by a
radial feed, the following considerations will be included in the separate agreement between the
Customer and the Company:
Idaho Power Company Ninth Tenth Revised Sheet No. 19-6
Cancels
I.P.U.C. No. 29, Tariff No. 101 Eighth Ninth Revised Sheet No. 19-6
IDAHO Issued by IDAHO POWER COMPANY
Issued – December 289, 20223 Timothy E. Tatum, Vice President, Regulatory Affairs
Effective – February 1, 20234 1221 West Idaho Street, Boise, Idaho
Advice No. 22-0523-03
SCHEDULE 19
LARGE POWER SERVICE
(Continued)
SPECIAL ARRANGEMENTS FOR SUBSTATION ALLOWANCES AND/OR TRANSMISSION VESTED
INTEREST (Continued)
Definitions (Continued)
Transmission Vested Interest Portion is that part of the Company’s transmission system in which
a Transmission Vested Interest is held.
Substation Allowance
If a Schedule 19 Customer’s request for service requires the installation of new or upgraded
transformer capacity in Substation Facilities, the following considerations will be included in the separate
agreement between the Customer and the Company:
The Customer will initially pay for the cost of new or upgraded Substation Facilities
required because of the Customer’s request. The Customer will be eligible to receive a one-time
Substation Allowance based upon subsequent sustained usage of capacity by the Customer.
a. Substation Allowance: The maximum possible allowance will be
determined by multiplying the Customer’s actual increase in load by $79,44471,006 per
MW, but will not exceed the actual cost of the Substation Facilities.
b. Substation Allowance Refunds: The Substation Allowance will be refunded
to the Customer over a five-year period, with annual payments based on the Customer’s
Basic Load Capacity at the time of refund. The first refund will be paid one year following
the first month energy is delivered through the new Substation Facilities.
The refunds will occur based on the following adjustment, which will be
added to the Substation Allowance received in the previous year. If there is no
change in load from the previous year, the Substation Allowance for that year is
equal to the Substation Allowance from the previous year:
((Change in load from the previous year as measured in MW) x (Substation Allowance per MW))
Number of Substation Allowance Refunds remaining in five-year period
The Customer’s annual refunds will be made in accordance with the
Substation Allowance amount stated in the separate construction agreement
between the Customer and the Company.
Transmission Vested Interest
If a Schedule 19 Customer’s request for service requires the installation of new or upgraded
capacity in Transmission Facilities, and those Transmission Facilities are serving the Customer by a
radial feed, the following considerations will be included in the separate agreement between the
Customer and the Company: