HomeMy WebLinkAbout20240313Notice_of_Petition_Order_No_36115.pdf
NOTICE OF PETITION
NOTICE OF INTERVENTION DEADLINE
ORDER NO. 36115 1
Office of the Secretary
Service Date
March 13, 2024
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER
COMPANY’S PETITION TO MODIFY A
COMPLIANCE REQUIREMENT RELATED
TO UPDATING SCHEDULE 87
)
)
)
)
)
)
)
)
CASE NO. IPC-E-24-08
NOTICE OF PETITION
NOTICE OF
INTERVENTION DEADLINE
ORDER NO. 36115
On February 27, 2023, Idaho Power Company (“Company”) filed a petition (“Petition”)
with the Idaho Public Utilities Commission (“Commission”) requesting to modify a compliance
requirement in Commission Order No. 36048, issued in Case No. IPC-E-23-14, regarding updating
the Company’s Schedule 87, Intermittent Generation Integration Charges (“Schedule 87”).
NOTICE OF PETITION
YOU ARE HEREBY NOTIFIED that the Company represents that its Petition is to modify
a specific compliance requirement from Commission Order No. 36048, regarding updating
Schedule 87 rates and integration costs from the 2020 Variable Energy Resource Integration Study
(“2020 VER Study”). Petition at 2. Specifically, the Company seeks permission to update
integration charges based on the new integration study it was ordered to complete, and to bypass
the update based on the 2020 VER Study. Id.
YOU ARE FURTHER NOTIFIED that the Petition has been filed with the Commission
and is available for public inspection during regular business hours at the Commission’s office.
These documents are also available on the Commission’s website at www.puc.idaho.gov. Click on
the “ELECTRIC” icon, select “Open Cases,” and click on the case number as shown on the front
of this document.
YOU ARE FURTHER NOTIFIED that all proceedings in this case will be held pursuant
to the Commission’s jurisdiction under Title 61 of the Idaho Code, and that all proceedings in this
matter will be conducted pursuant to the Commission’s Rules of Procedure, IDAPA 31.01.01.000
et seq.
NOTICE OF PETITION
NOTICE OF INTERVENTION DEADLINE
ORDER NO. 36115 2
NOTICE OF INTERVENTION DEADLINE
YOU ARE FURTHER NOTIFIED that persons desiring to intervene in this matter to
obtain parties’ rights of participation must file a Petition to Intervene with the Commission
pursuant to this Commission’s Rules of Procedure 71-73, IDAPA 31.01.01.072-073. Persons who
wish to intervene as a party must file a Petition to Intervene no later than twenty-one (21)
days after the date of service of this Order. Persons desiring to present their views without
parties’ rights of participation do not have to intervene and may present their comments without
prior notification to the Commission or the parties.
YOU ARE FURTHER NOTIFIED that the Commission Secretary shall issue a Notice of
Parties after the deadline for intervention has passed. The Notice of Parties shall assign exhibit
numbers to each party in this proceeding.
YOU ARE FURTHER NOTIFIED that once the Notice of Parties is issued, Commission
Staff (“Staff”) will informally confer with the parties to discuss a schedule to process this case and
other issues as may be raised by the parties.
YOU ARE FURTHER NOTIFIED that the following persons are designated as the
Company’s representatives in this matter:
Donovan E. Walker
Idaho Power Company
1221 West Idaho Street (83702)
P.O. Box 70
Boise, Idaho 83707
dwalker@idahopower.com
dockets@idahopower.com
Alison Williams
Idaho Power Company
1221 West Idaho Street (83702)
P.O. Box 70
Boise, Idaho 83707
awilliams@idahopower.com
ORDER
IT IS HEREBY ORDERED that persons desiring to intervene in this case for the purpose
of obtaining parties’ rights of participation must file a Petition to Intervene with the Commission,
under Rules 71-73, IDAPA 31.01.01.071-073, no later than twenty-one (21) days after the service
date of this Order.
IT IS FURTHER ORDERED that, after the Secretary issues a Notice of Parties, Staff will
informally confer with the parties to discuss the appropriate scheduling of this case.
NOTICE OF PETITION
NOTICE OF INTERVENTION DEADLINE
ORDER NO. 36115 3
IT IS FURTHER ORDERED that parties comply with Order No. 35375, issued April 21,
2022. Generally, all pleadings should be filed with the Commission electronically and will be
deemed timely filed when received by the Commission Secretary. See Rule 14.02. Service between
parties should continue to be accomplished electronically when possible. However, voluminous
discovery-related documents may be filed and served on CD-ROM or a USB flash drive.
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 13th day of
March 2024.
__________________________________________
ERIC ANDERSON, PRESIDENT
__________________________________________
JOHN R. HAMMOND JR., COMMISSIONER
__________________________________________
EDWARD LODGE, COMMISSIONER
ATTEST:
____________________________________
Monica Barrios-Sanchez
Commission Secretary
I:\Legal\ELECTRIC\IPC-E-24-08_Sch 87\orders\IPCE2408_Ntc_Pit_Int_cb.docx