HomeMy WebLinkAbout20231010Decision Memo.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON
COMMISSIONER HAMMOND
COMMISSIONER LODGE
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: ADAM TRIPLETT
DEPUTY ATTORNEY GENERAL
DATE: OCTOBER 10, 2023
SUBJECT: IN THE MATTER OF IDAHO POWER COMPANY’S APPLICATION FOR
MODIFICTIONS TO THE COMPANY’S COMMERICIAL &
INDUSTIRAL DEMAND RESPONSE PROGRAM, SCHEDULE 82; CASE
NO. IPC-E-23-24.
On October 2, 2023, Idaho Power Company (“Company”), applied for Commission
approval of proposed modifications to Schedule 82—Flex Peak Program (“Schedule 82”). The
Company proposes revising Schedule 82 to (1) modify certain payment structures; (2) add a waiver
provision covering participating customers whose Load Control Device fails; (3) revise the
definition of the “Day of” Load Adjustment; (4) establish an option to extend the four-hour
notification limit for certain customers; and (5) add definitions for certain terms along with other
minor updates related to the other proposed changes. The Company requests that the Application
be processed via Modified Procedure and an effective date of April 15, 2024.
STAFF RECOMMENDATION
Staff recommends that the Commission issue a Notice of Application and Notice of
Intervention Deadline establishing a 21-day intervention period.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Intervention
Deadline establishing a 21-day intervention period?
Adam Triplett
Deputy Attorney General