HomeMy WebLinkAbout20220201Decision Memo.pdfRE
DECISION MEMORANDUM
TO:COMMISSIONER ANDERSON
COMMISSIONER CHATBURN
COMMISSIONER HAMMOND
COMMISSTON SECRETARY
LEGAL
WORKING FILE
FROM:YAO YIN
DAYN HARDIE
DATE: JANUARY 28,2022 I(cC- E 2-7-o r
IN THE MATTER OF IDAHO POWER'S ANNUAL COMPLIANCE
FILING TO UPDATE THE SUBSTATION ALLOWANCE UNDER
SCHEDULE 19, LARGE POWER SERVICE, TARTFF ADVTCE NO. 2l-03.
BACKGROUND
On December 28, 2021, Idaho Power Company ("Company") filed TariffAdvice No. 2l-
03 proposing an update to the Substation Allowance outlined in Schedule 19, Large Power Service,
as required by ldaho Public Utilities Commission OrderNos, 32893 and 32914. The Company
requested the update to the allowance become effective February 1,2022.
STAFF ANALYSH
Staff reviewed the Company's proposed changes to the allowance amount and overhead
rates in the Tariff Advice filed by the Company. The proposed Substation Allowance amount
increased from $49,016 to $57,640-an increase of 17.6 percent. Given the size of the increase,
Staffbelieves a more in-depth analysis should be conducted to ensure the components included in
the allowance amount reflect current accurate costs. The Company agreed to Staffs proposal for
additional time to analyze TariffAdvice No.2l-03.
Staff recommends the Commission treat the Company's Tariff Advice as an application
and issue a Notice of Application and Notice of Modilied Procedure. Staff recommends
establishing 2l-day comment deadline and a 7-day Company reply period. Staff also recommends
that the Commission suspend the Company's proposed February 1,2022 effective date until March
15,2022 pursuant to ldaho Code $ 6l-622(4) to allow proper time for public comment and the
Company's reply. The Company agreed with the additional time proposed by Staff.
-l -DECISION MEMORANDUM JANUARY 28,2022
COMMIS$ON DECISION
Does the Commission wish to:
l. Trest the Company's TaritrAdvice as an application and issue a Notice of Application?
2. Issue a Notlcc of Modified Procodure establishing 2lday comment deadline and a Tday
Company reply period?
3. Suspend the Company's p,roposed February l,}Azzcffective date until Marsh 15,2022?
/S/Yao Yin
Yao Yin
Idalro Public Utilities Commission Staff
t &nqurl&ho FonrrTulltAdvice Dcckbn MsmScfcillc 19
DECISION MEMORANDUM -r-JAl.luARY 28,2022