HomeMy WebLinkAbout20220311Decision Memo.pdfDECISION MEMORANDUM
TO:COMMISSIONER ANDERSON
COMMISSIONER CHATBURN
COMMISSIONER HAMMOND
COMMISSION SECRETARY
LEGAL
WORKING FILE
FROM:RICHARD KELLER
RILEY NEWTON
DATE:MARCH 11,2022
RE:IN THE MATTER OF IDAHO POWER COMPANY'S APPLICATION
FOR APPROVAL TO MODIFY ITS DEMAND RESPONSE PROGRAMS;
CASE NO.IPC-E-21-32.
BACKGROUND
On March 4,2022,the Commission issued Order No.35336 approving the modifications
to Idaho Power Company's ("Company")Demand Response ("DR")programs.On March 10,
2022,the Commission subsequently issued an Errata to Order No.35336 removing the prior
defined effective date.The Commission Order now on Page 10,paragraph 1,READS:
IT IS HEREBY ORDERED that the Company's proposed modifications to its DR
programs-theresidential Air Conditioner Cool Credit Program,the Commercial
and Industrial Flex Peak Program,and the IrrigationPeak Rewards Program-are
reasonable and approved.
On March 9,2022,Idaho Power Company submitted a compliance filing for
Schedules 23,81,and 82 reflecting the approvedchanges to the Demand Response
programs.
Eighth Revised Sheet No.23-1 Cancelling Seventh Revised Sheet No.23-1
Eighth Revised Sheet No.23-2 Cancelling Seventh Revised Sheet No.23-2
Eighth Revised Sheet No.23-3 Cancelling Seventh Revised Sheet No.23-3
Eighth Revised Sheet No.23-4 Cancelling Seventh Revised Sheet No.23-4
Eighth Revised Sheet No.23-5 Cancelling Seventh Revised Sheet No.23-5
Eighth Revised Sheet No.23-6 Cancelling Seventh Revised Sheet No.23-6
Eighth Revised Sheet No.23-7 Cancelling Seventh Revised Sheet No.23-7
Seventh Revised Sheet No.23-8 Cancelling Sixth Revised Sheet No.23-8
Third Revised Sheet No.81-1 Cancelling Second Revised Sheet No.81-l
Third Revised Sheet No.81-3 Cancelling Second Revised Sheet No.81-3
Second Revised Sheet No.82-1 Cancelling First Revised Sheet No.82-1
DECISION MEMORANDUM -1 -MARCH 11,2022
First Revised Sheet No.82-2 Cancelling Original Sheet No.82-2
First Revised Sheet No.82-3 Cancelling Original Sheet No.82-3
Second Revised Sheet No.82-4 Cancelling First Revised Sheet No.82-4
Second Revised Sheet No.82-5 Cancelling First Revised Sheet No.82-5
Staffhas reviewed the Company's revised sheets for Schedules 23,81,and 82 confirming
they comply with the proposed modifications approved by the Commission.
STAFF RECOMMENDATION
Staffrecommends the Commission approve the schedule sheet revisions submitted by the
Company on March 9,2022,as filed,showing they are consistent with Order No.35336.
COMMISSION DECISION
Does the Commission wish to approve the revisions to Schedules 23,81,and 82?
Richard Keller
Udmemos/IPC-E-21-32 Decision Memo
DECISION MEMORANDUM -2 -MARCH I1,2022