HomeMy WebLinkAbout20210924Decision Memo.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER KJELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: RILEY NEWTON
DEPUTY ATTORNEY GENERAL
DATE: SEPTEMBER 24, 2021
SUBJECT: IN THE MATTER OF IDAHO POWER COMPANY’S APPLICATION FOR
APPROVAL OR REJECTION OF THE THIRD AMENDMENT TO ITS
ENERGY SALES AGREEMENT WITH MC6 HYDRO LLC; CASE NO.
IPC-E-21-30.
On August 26, 2021, Idaho Power Company (“Company”) filed an Application with
the Commission requesting approval of the Second Amendment to its Energy Sales Agreement
(“ESA”) with MC6 Hydro, LLC (“Seller”) who sells energy generated by the MC6 hydro facility
(“Facility”). The Facility is a qualifying facility under the Public Utility Regulatory Policies Act
of 1978.
THE APPLICATION
The Company states, “as a result to the COVID-19 pandemic, the Facility was unable
to obtain its generator unit from Wuhan, China causing a Force Majeure event, which changed the
Operation Date to April 5, 2021, and the project received and installed a generator with a
Nameplate Capacity of 2.3 megawatts (“MW”)”—a capacity 0.2 MW larger than the 2.1 MW
generator capacity listed in the ESA. Application at 2.
Accordingly, the amendment provides for a change to Appendix B, Article B-1 of the
ESA so that the designated nameplate rating of the generator is “2.3 MW” rather than “2.1 MW.”
Id. at 3. The amendment also seeks to change Section 6.2.3, “Seller's Adjustment of Estimated Net
Energy Amounts After the Operation Date.” Id. Specifically, the amendment would change the
Net Energy Adjustment time period in Section 6.2.3 so that the Seller can “make adjustments by
the 25th day of the preceding month in which a change is requested.” Id. at 2. The Company
requests its Application be processed by Modified Procedure. Id. at 4.
DECISION MEMORANDUM 2
STAFF RECOMMENDATION
Staff recommends the Commission issue a Notice of Application and Notice of
Modified Procedure establishing a public comment deadline of October 28, 2021, and a Company
reply deadline of November 4, 2021.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Modified
Procedure establishing a public comment deadline of October 28, 2021, and a Company reply
deadline of November 4, 2021?
Riley Newton
Deputy Attorney General
I:\Legal\ELECTRIC\IPC-E-21-30 MC6\memos\IPCE2130_dec_rn.docx