HomeMy WebLinkAbout20220802Amended_Certificate_No_537.pdfAMENDED CERTIFICATE NO. 537 1
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER
COMPANY’S PETITION FOR APPROVAL
OF A CUSTOMER SURCHARGE AND
MODIFIED LINE ROUTE
CONFIGURATION FOR CONSTRUCTION
OF A NEW 138 kV TRANSMISSION LINE
IN THE WOOD RIVER VALLEY
)
)
)
)
)
)
)
)
CASE NO. IPC-E-21-25
AMENDED CERTIFICATE NO. 537
IT IS HEREBY CERTIFIED that public convenience and necessity requires Idaho
Power Company to modify its Transmission Line Route approved by the 2017 CPCN issued in
Order No. 33872 to include the Owl Rock Road Route. More specifically, the modifications will
extend the transmission line burial further south a distance of 1.4 miles, from Elkhorn Road to near
Owl Rock Road and bury the distribution lines along the entirety of the Owl Rock Road Route as
described in the Company’s Petition in this case; to exercise all rights and privileges which have
been granted to said Idaho Power Company, its successors and assigns by any franchise or permit
conferred or hereafter conferred upon said Idaho Power Company, its successors and assigns by
any city or village or by any county or by the State of Idaho or by any political subdivision thereof.
This certificate is predicated upon and issued pursuant to the findings and order of this
Commission, the same being Order No. 35452 in the above entitled matter made and entered on
the 28th day of June, 2022.
DATED at Boise, Idaho, this 2nd day of August, 2022.
ERIC ANDERSON, PRESIDENT
JOHN CHATBURN, COMMISSIONER
//ABSTAINED//
JOHN R. HAMMOND JR., COMMISSIONER
ATTEST:
Jan Noriyuki
Commission Secretary
I:\Legal\ELECTRIC\IPC-E-21-25 Wood River Valley\IPCE2125_Cert 537_Amended_rn.doc