Loading...
HomeMy WebLinkAbout20210722Intervention_Order_No_35115.pdfORDER NO. 35115 1 Office of the Secretary Service Date July 22, 2021 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION The Idaho Conservation League (“ICL”) petitioned to intervene in this case on July 12, 2021, pursuant to Rules of Procedure 71 through 75 of the Idaho Public Utilities Commission, IDAPA 31.01.01.071-.075. FINDINGS OF FACT We find that no party timely opposed this Petition to Intervene. We further find that based on the pleadings and other documents filed in this case, intervention by this party would serve the purposes of intervention as described by Rule 74 of the Rules of Procedure and should be granted. O R D E R IT IS THEREFORE ORDERED that the Petition to Intervene filed by ICL is hereby granted. IT IS FURTHER ORDERED that all parties in this proceeding serve all papers hereafter filed in this matter on all parties of record. This Intervenor is represented by the following for purposes of service: Idaho Conservation League: Benjamin J. Otto 710 N 6th Street Boise, ID 83702 botto@idahoconservation.org IT IS FURTHER ORDERED that parties continue to comply with Order No. 35058, issued June 3, 2021. All pleadings should be filed with the Commission electronically and shall be deemed timely filed when received by the Commission Secretary. See Rule 14.02. Service between parties should also be accomplished electronically. Voluminous discovery-related documents may be filed and served on CD-ROM or a USB flash drive. IN THE MATTER OF IDAHO POWER COMPANY’S APPLICATION TO INITIATE A MULTI-PHASE COLLABORATIVE PROCESS FOR THE STUDY OF COSTS, BENEFITS, AND COMPENSATION OF NET EXCESS ENERGY ASSOCIATED WITH CUSTOMER ON-SITE GENERATION ) ) ) ) ) ) ) CASE NO. IPC-E-21-21 ORDER NO. 35115 ORDER NO. 35115 2 DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 22nd day of July 2021. PAUL KJELLANDER, PRESIDENT KRISTINE RAPER, COMMISSIONER ERIC ANDERSON, COMMISSIONER ATTEST: Jan Noriyuki Commission Secretary I:\Legal\ELECTRIC\IPC-E-21-21 On-Site Generation\orders\IPCE2121_ICL_es.docx