HomeMy WebLinkAbout20210820Decision Memo.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER KJELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: DAYN HARDIE
DEPUTY ATTORNEY GENERAL
DATE: AUGUST 20, 2021
SUBJECT: IN THE MATTER OF IDAHO POWER COMPANY’S APPLICATION FOR
APPROVAL OF ITS LOAD CURTAILMENT AND INTERRUPTION
PLAN; CASE NO. IPC-E-21-13.
On May 11, 2021, Idaho Power Company (“Company”) applied for approval of its 2021
Load Curtailment and Interruption Plan and for authority to update its Electric Service Rule J—
Continuity, Curtailment, and Interruption of Electric Service. The Company requests its
Application be processed by Modified Procedure.
On July 13, 2021, the Commission issued a Notice of Application and established a
deadline for intervention. Order No. 35101. The Idaho Irrigation Pumpers Association, Inc.
intervened. Following the intervention deadline, Staff informally conferred with the parties
regarding procedure and a schedule for this case.
STAFF RECOMMENDATION
Staff recommends the Commission issue a Notice of Modified Procedure and establish a
September 22, 2021 public comment deadline and an October 6, 2021 Company reply deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Modified Procedure and establish a
September 22, 2021 public comment deadline and an October 6, 2021 Company reply deadline?
__________________________
Dayn Hardie
Deputy Attorney General
I:\Legal\ELECTRIC\IPC-E-21-13\memos\IPCE2113_dec2_dh.docx