HomeMy WebLinkAbout20210623Intervention_Order_No_35084.pdfORDER NO. 35084 1
Office of the Secretary
Service Date
June 23, 2021
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
The Industrial Customers of Idaho Power (“ICIP”) petitioned to intervene in this case
on June 10, 2021, and Idaho Hydroelectric Power Producers Trust, d/b/a IdaHydro (“IdaHydro”)
petitioned to intervene in this case on June 14, 2021. Both petitions were made pursuant to Rules
of Procedure 71 through 75 of the Idaho Public Utilities Commission, IDAPA 31.01.01.071-.075.
FINDINGS OF FACT
We find that no party timely opposed these Petitions to Intervene.
We further find that based on the pleadings and other documents filed in this case,
intervention by these parties would serve the purposes of intervention as described by Rule 74 of
the Rules of Procedure and should be granted.
O R D E R
IT IS THEREFORE ORDERED that the Petition to Intervene filed by ICIP is hereby
granted.
IT IS THEREFORE ORDERED that the Petition to Intervene filed by IdaHydro is
hereby granted.
IT IS FURTHER ORDERED that all parties in this proceeding serve all papers
hereafter filed in this matter on all parties of record. This Intervenors are represented by the
following for purposes of service:
Industrial Customers of Idaho Power:
Peter J. Richardson
Richardson Adams PLLC
515 N. 27th Street
P.O. Box 7218
Boise, ID 83702
peter@richardsonadams.com
Dr. Don Reading
6070 Hill Road
Boise, ID 83703
dreading@mindspring.com
IdaHydro:
C. Tom Arkoosh
Arkoosh Law Offices
913 River Street, Suite 450
Boise, ID 83702
tom.arkoosh@arkoosh.com
erin.cecil@arkoosh.com
IN THE MATTER OF IDAHO POWER
COMPANY’S APPLICATION FOR
APPROVAL OF THE CAPACITY
DEFICIENCY TO BE UTILIZED FOR
AVOIDED COST CALCULATIONS
)
)
)
)
)
CASE NO. IPC-E-21-09
ORDER NO. 35084
ORDER NO. 35084 2
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 23rd day
of June 2021.
PAUL KJELLANDER, PRESIDENT
KRISTINE RAPER, COMMISSIONER
ERIC ANDERSON, COMMISSIONER
ATTEST:
Jan Noriyuki
Commission Secretary
I:\Legal\ELECTRIC\IPC-E-21-09\Orders\IPCE2109_Idahydro_ICIP_mh.docx