LISA D. NORDSTROM
Lead Counsel
lnordstrom@idahopower.com
March 19, 2020
Diane Hanian, Secretary
Idaho Public Utilities Commission
11331 W. Chinden Boulevard
Building 8, Suite 201-A
Boise, Idaho 83714
Re: IPC-E-19-40 – Schedule 19, Large Power Service - Update to Substation
Allowance - Tariff Compliance Filing
Dear Ms. Hanian:
Pursuant to RP 133, Idaho Power Company hereby submits the enclosed compliance
filing in the above-captioned proceeding pursuant to Idaho Public Utilities Commission Order
No. 34576, which includes the tariff schedule listed below, reflecting the change in rates with
an effective date of March 15, 2020, per the order.
Sixth Revised Sheet No. 19-6 Cancelling Fifth Revised Sheet No. 19-6
If you have any questions regarding this tariff advice, please contact Regulatory
Analyst Grant Anderson at 388-6498 or ganderson@idahopower.com.
Sincerely,
Lisa D. Nordstrom
LDN:kkt
Enclosure
RECEIVED
2020 March 19, PM 2:55
IDAHO PUBLIC
UTILITIES COMMISSION
Idaho Power Company Sixth Revised Sheet No. 19-6
Cancels
I.P.U.C. No. 29, Tariff No. 101 Fifth Revised Sheet No. 19-6
IDAHO Issued by IDAHO POWER COMPANY
Issued per Order No. 34576 Timothy E. Tatum, Vice President, Regulatory Affairs
Effective – March 15, 2020 1221 West Idaho Street, Boise, Idaho
SCHEDULE 19
LARGE POWER SERVICE
(Continued)
SPECIAL ARRANGEMENTS FOR SUBSTATION ALLOWANCES AND/OR TRANSMISSION VESTED
INTEREST (Continued)
Definitions (Continued)
Transmission Vested Interest Portion is that part of the Company’s transmission system in
which a Transmission Vested Interest is held.
Substation Allowance
If a Schedule 19 Customer’s request for service requires the installation of new or upgraded
transformer capacity in Substation Facilities, the following considerations will be included in the
separate agreement between the Customer and the Company:
The Customer will initially pay for the cost of new or upgraded Substation Facilities
required because of the Customer’s request. The Customer will be eligible to receive a one-
time Substation Allowance based upon subsequent sustained usage of capacity by the
Customer.
a. Substation Allowance: The maximum possible allowance will be
determined by multiplying the Customer’s actual increase in load by $49,253 per MW,
but will not exceed the actual cost of the Substation Facilities.
b. Substation Allowance Refunds: The Substation Allowance will be
refunded to the Customer over a five-year period, with annual payments based on the
Customer’s Basic Load Capacity at the time of refund. The first refund will be paid one
year following the first month energy is delivered through the new Substation Facilities.
The refunds will occur based on the following adjustment, which will be
added to the Substation Allowance received in the previous year. If there is no
change in load from the previous year, the Substation Allowance for that year is
equal to the Substation Allowance from the previous year:
((Change in load from the previous year as measured in MW) x (Substation Allowance per MW))
Number of Substation Allowance Refunds remaining in five-year period
The Customer’s annual refunds will be made in accordance with the
Substation Allowance amount stated in the separate construction agreement
between the Customer and the Company.
Transmission Vested Interest
If a Schedule 19 Customer’s request for service requires the installation of new or upgraded
capacity in Transmission Facilities, and those Transmission Facilities are serving the Customer by a
radial feed, the following considerations will be included in the separate agreement between the
Customer and the Company:
IDAHO PUBLIC UTILITIES COMMISSION
Approved Effective
Mar. 23, 2020 Mar. 15, 2020
Per O.N. 34576