HomeMy WebLinkAbout20200306Decision Memo.pdfDECISION MEMORANDUM
TO:COMMISSIONER KIELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM:EDWARD JEWELL
DEPUTY ATTORNEY GENERAL
DATE: MARCH 6,2020
STJBJECT: IN THE MATTER OF IDAHO POWER,S APPLICATION TO
EVALUATE SCHEDULE 84 - NET METERING; CASE NO. IPC-E-19-15.
On April 5, 2019, the Company filed an Application requesting the Commission
initiate a collaborative process to study the continued reasonableness of terms in Schedule 84 for
commercial, industrial, and irrigation ("CI&I") net metering customers. The Company requested
Schedule 84 be suspended to new applicants as of April 5, 2019, while the case was processed.
The Commission determined the Company had not demonstrated that Schedule 84 should be
closed to new applicants during the pendency of the case, and therefore suspended the
Company's proposed effective date. Order No. 34315.
By statute, the maximum amount of time the Commission could initially suspend the
proposed effective date was for 5 months plus 30 days. Under the same statute, the Commission
can continue to suspend an effective date for an additional sixty days upon a showing of good
cause on the record, or indefinitely upon a signed writing from the Company. Idaho Code * 6l-
622(4). The Commission suspended the effective date for the maximum initial statutory amount,
which was until October 7,2019.
On September 10, 2019, the Company submitted a letter consenting to extend the
suspension of the proposed effective date until November 15,2019.
On November 15, 2019, based on good cause showing, the Commission issued a
Notice of Continued Suspension of Effective Date, which suspended the proposed effective date
for sixty days, until January 14,2020, in order for the parties to continue to pursue settlement.
Order No. 34488.
IDECISION MEMORANDUM
On January 14, 2020, the Commission issued another Notice of Continued
Suspension of Effective Date, which suspended the proposed effective date for an additional
sixty day, until March 16,2020. Order No. 34534. The Commission issued this additional
extension to allow the parties time to meet and confer regarding the impact Order No. 34509 in
Case No. IPC-E-18-15 would have on this docket. Id.
On February 5,2020, the Commission issued Order No. 34546 in Case No. IPC-E-
18-15, which in part, declined to make any determinations about the IPC-E-19-15 case in IPC-E-
18-15. Order No. 34546 at ll-12. In Staff s Answer to petitions for reconsideration in IPC-E-
18-15, Staff stated,
Staff recommends the Commission direct the Company to
withdraw its Application in IPC-E-19-15. That case was
conducted in a manner almost identical to IPC-E-18-15, which the
Commission found to not sufficiently include public participation
and required the completion of a credible and fair comprehensive
study. Staff believes it would be reasonable for the Commission to
direct parties in IPC-E-19-15 to prepare a comprehensive study
using the same procedures and the same criteria established by
Order No. 34509 for residential and small general service
customers.
The parties have had difficulty coordinating a time to meet to discuss next steps in
IPC-E-19-15 following the Commission's orders in IPC-E-18-15, and therefore Staff
recommends the Commission continue to suspend the effective date in order to allow parties to
discuss proposals for next steps. The Company has indicated to counsel that it concurs an
additional extension of time is appropriate given the circumstances.
STAFF RECOMMENDATION
Staff recommends the Commission suspend the effective date in this case for an
additional sixty days, until May 15,2020, unless the Company timely withdraws its Application.
COMMISSION DECISION
Does the Commission wish to suspend the effective date in this case for an additional
sixty days, until May 15,2020, unless the Company timely withdraws its Application?
Ed J
Deputy Attorney General
I:\L-egal\ELECTRICIPC-E- I 9- I 5UPCEI 9 l5_dec memo 7_ej
DECISION MEMORANDUM 2