HomeMy WebLinkAbout20190503Decision Memo.pdfDECISION MEMORANDUM
TO:COMMISSIONER KJELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM:EDWARD JEWELL
DEPUTY ATTORNEY GENERAL
DATE: MAY 3,2019
SUBJECT: IN THE MATTER OF IDAHO POWER,S APPLICATION TO
EVALUATE SCHEDULE 84 - NET METERING; CASE NO. IPC-E-19-15
On April 5,2019,Idaho Power Company ("ldaho Power" or "Company") filed an
Application requesting the Commission temporarily suspend Schedule 84 for new applicants and
"initiate a collaborative process to explore modification to the compensation structure and excess
energy value applied under Schedule 84[.]" Application at 2.
On April 18,2019, the Commission issued a Notice of Application and Notice of
Procedural Comment Deadline, which established a two week procedural comment period.
Order No. 34315.
BACKGROUND
In IPC-E-I7-13, the Commission approved the Company's proposal to separate
residential and small general service customers with on-site generation into Schedules 6 and 8.
Order Nos. 34046,34147. This left commercial, industrial, and irrigation ("CI&I") customers
with on-site generation in Schedule 84.
Stemming from Commission orders in IPC-E-17-13 are two dockets currently
underway, IPC-E-18-15 and IPC-E-18-16. In Order No. 34315 the Commission sought
comments from interested parties regarding how the Company's Application should be
processed in relation to IPC-E-18-15 and IPC-E-18-16.
Specifically, the Commission requested comments on the following questions:
1DE,CISION MEMORANDUM
l) Whether and to what extent this Application impacts or is impacted by IPC-E-18-
15 and IPC-E-I8-16.
2) Whether and to what extent the issues raised in IPC-E-18-15, IPC-E-18-16, and
this docket can and should be examined holistically.
3) Whether this docket should be processed according to Idaho Power's proposal on
page 8 of the Application.
4) Whether the Commission should process this docket by modified procedure or by
hearings.
5) Whether the Commission should suspend Schedule 84 for new applicants while
IPC-E-I9-15 is being processed, and if the Commission does suspend Schedule
84 in the interim, whether the suspension should be from the date of filing-April
5,2019-or some other date.
6) Whether the Company's proposed effective date of January 1,2020 in IPC-E-19-
15 is feasible.
THE PROCEDURAL COMMENTS
Timely comments were submitted by City of Boise, Idaho Clean Energy Association,
Idaho Conservation League and Vote Solar, Idaho Irrigation Pumpers Association, Micron
Technology, Russell Schiermeier, Idaho Chapter Sierra Club, Commission Staff, and the
Company.
COMMISSION DECISION
What is the Commission's decision on how to process this case?
Edward J
Deputy General
I \Lega|\ELECTRIC\IPC-E-19-15UPCEl9l5_dec memo Z_ej
L
2DECISION MEMORANDUM