Loading...
HomeMy WebLinkAbout20171012final_order_no_33906.pdfOffice of the Secretary Service Date October 12,2017 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION ) OF IDAHO POWER COMPANY FOR A )CASE NO.IPC-E-16-28 CERTIFICATE OF PUBLIC ) CONVENIENCE AN1)NECESSITY TO )ORDER NO.33906 CONSTRUCT SYSTEM IMPROVEMENTS ) FOR WOOD RIVER VALLEY ) CUSTOMERS ) ) In November 2016,Idaho Power Company filed an Ap1ication for a Certificate of Public Convenience and Necessity (CPCN)to construct a second transmission line and related facilities and secure adequate and reliable service in the Wood River Valley.The Commission issued a Notice of Application,and granted intervention petitions from Kiki Tidwell.Laura Midgley,the Sierra Club,the Idaho Conservation League,the City of Ketchum,CoxCom,and Rock Rolling Properties #1 and #2.Order Nos.33657.33675,33683.33711,33760.The Commission conducted a public hearing on July 26,2017,and a technical hearing on August 8,2017.At the conclusion of the technical hearing,Chair Anderson set a deadline of August 22,2017 for i ntervenor funding requests. Sierra Club timely petitioned for intervenor funding.On September 15,2017,the Commission issued Final Order No.33872 granting the Company’s Application and granting Sierra Club’s intervenor funding request.On September 20,2017,KikiTidwell filed a late petition for intervenor funding,1 to which no one objected.The Commission denies Ms. Tidwell’s petition as untimely. PETITIONS FOR INTERVENOR FUNDING Intervenor funding is available under Idaho Code §61-617A and Commission Rules 161 through 165.Section 61-617a(1)declares it is “the policy of [Idaho]to encourage participation at all stages of all proceedings before this commission so that all affected customers receive full and fair representation in those proceedings.”Idaho Code §61-617A(2).Commission Rule 164 provides,“Unless otherwise provided by order,an intervenor requesting intervenor funding must ‘Ms.Tidwell filed the petition on her own behalf.However,Ms.Tidwell’s attorney,Peter Richardson,confirmed that his office still represents Ms.Tidwell. ORDER NO,33906 apply no later than fourteen (14)days after the last evidentiarv hearing in a proceeding or the deadline for submitting briefs....’IDAPA 31.01.01.164. COMMISSION DECISION The Commission received Ms.Tidwell’s late petition for intervenor funding on September 20,2017.In her request,Ms.Tidwell states,“I was not aware of the possibility of Intervenor funding.”Petition at 1.The Commission notes that Ms.Tidwell attended the technical hearing conducted on August 8,2017.Ms.Tidwell was present when Chair Anderson stated,“Intervenor funding requests under Rule 164 are due 14 days from today.”Transcript at 686,lines 15-16.Ms.Tidwell’s petition was received almost a month after the deadline. Accordingly,we deny the petition as untimely. ORDER IT IS HEREBY ORDERED that Ms.Tidwell’s late petition for intervenor funding is denied as untimely. THIS IS A FINAL ORDER.Any person interested in this Order may petition for reconsideration within twenty-one (21)days of the service date of this Order with regard to any matter decided in this Order.Within seven (7)days after any person has petitioned for reconsideration,any other person may cross-petition for reconsideration.See Idaho Code §61- 626. ORI)ERNO.33906 DONE by Order of the Idaho Public Utilities Commission at Boise,Idaho this day of October 2017. PAUL KJELLANI3ER,PRESIDENT KRISTTNE RAPER,COMMISSIONER ERIC ANDERSON,COMMISSIONER ATTEST: Diane M.Hanian Commission Secretary I Legal LORDERS 1PCE1628 djh5 doe ORDER NO.33906