Loading...
HomeMy WebLinkAbout20161021Harvey Direct.pdfr e _!\/ED r L ... J -i 2Cd oCCT 21 P 3: 12 1 r-' · 1 • • .... ; 1 It-' !-) i' I l ....... l, V N · ,-· '\-· , '"'n· ·, T3SI O I i . ; .. ~. .,,,,. -'\ ' I BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF IDAHO POWER COMPANY'S APPLICATION FOR AUTHORITY TO INCREASE ITS RATES FOR ELECTRIC SERVICE TO RECOVER COSTS ASSOCIATED WITH THE NORTH VALMY POWER PLANT. CASE NO. IPC-E-16-24 IDAHO POWER COMPANY DIRECT TESTIMONY OF TOM HARVEY 1 Q. Please state your name, business address, and 2 present position with Idaho Power Company ("Idaho Power" or 3 "Company") . 4 5 A. My name is Torn Harvey and my business address is 1221 West Idaho Street, Boise, Idaho 83702. I am 6 employed by Idaho Power as the Resource Planning and 7 Operations Director in the Power Supply Department. 8 9 10 Q. A. Please describe your educational background. I have a Bachelor of Business Administration in business management from Boise State University. I also 11 attended the University of Idaho's Utility Executive Course 12 in 2011. 13 Q. Please describe your work experience with 14 Idaho Power. 15 16 17 A. I was hired by Idaho Power in July 1980 to work in the Plant Accounting Department. I continued working in the accounting area through 1985. From 1985 18 through 2009, I was the Fuels Management Coordinator and 19 then was promoted to the Joint Projects Manager. In April 20 2015, I was promoted to my current position, Resource 21 Planning and Operations Director. My current 22 responsibilities include supervision over Idaho Power's 23 jointly owned coal assets, integrated resource planning, 24 cloud seeding program, river engineering, strearnflow 25 gaging, and operations hydrology. HARVEY, DI 1 Idaho Power Company 1 Q. What is the purpose of your testimony in this 2 case? 3 A. The purpose of my testimony is to discuss the 4 prudence of investments made at the North Valmy power plant 5 ("Valmy") that have added to the associated plant balances 6 since the Company's last depreciation rate update became 7 effective on June 1, 2012, and to inform the Idaho Public 8 Utilities Commission of necessary future investments at the 9 plant to ensure Valmy continues to be available for 10 reliable load service through the end of 2025 . My 11 testimony also presents Valmy's current position in the 12 Company's generation portfolio and the results of an 13 analysis performed by Idaho Power that supports the 14 proposed depreciable life at Valmy reflecting an end-of- 15 life date as of December 31, 2025. 16 17 Q. A. Please describe the Valmy plant. Valmy is a coal-fired power plant that 18 consists of two units and is located near Winnemucca, 19 Nevada. Unit 1 went in service in 1981 and Unit 2 followed 20 in 1985. Idaho Power owns 50 percent, or 284 megawatts1 21 ("MW") (generator nameplate rating), of Valmy. NV Energy 22 also has 50 percent ownership and is the operator of the 23 Valmy facility. Idaho Power and NV Energy work jointly to 24 make decisions regarding any environmental investment, 1 For planning purpo ses, Idaho Power uses the ne t dependable ca p a b ility of 262 MW. HARVEY, DI 2 Idaho Power Company ----------------------------------------------- 1 plant retirement, or conversion . The plant is connected 2 via a single 345 kilovolt transmission line to the Idaho 3 Power control area at the Midpoint substation. Idaho Power 4 has the northbound capacity and NV Energy has the 5 southbound capacity of this line. 6 Coal for the plant is shipped via railroad from 7 various mines in Utah , Wyoming, and Colorado. The power 8 plant uses a variety of emissions control technologies, 9 including state-of-the-art fabric filters that remove more 10 than 99 percent of particulate emissions. Additionally , a 11 Dry Sorbent Injection ("DSiu) system has been installed on 12 Unit 1 to reduce acid gas emissions and flue-gas scrubber 13 technology is utilized on Unit 2 for the reduction of 14 sulfur dioxide emissions. 15 16 I . VALMY OPERATIONS AND INVESTMENTS SINCE 2011 Q. Company witness Matthew Larkin states in his 17 direct testimony that the current depreciable life at the 18 Valmy plant reflects a 2031 end-of-life for Unit 1 and a 19 2035 end-of -life for Unit 2. What resource planning 20 analyses did the Company prepare based on the 2031 and 2035 21 end-of-life assumptions for Valmy approved in the last 22 depreciation study? 23 A. A 2031 end-of-life for Unit 1 and a 2035 end - 24 of-life for Unit 2 was used in the Idaho Power prepared 25 Coal Unit Environmental Investment Analysis for the Jim HARVEY , DI 3 Idaho Power Company 1 Bridger and North Valmy Coal-Fired Power Plants ("2013 Coal 2 Study") . This analysis guided Idaho Power's Valmy-related 3 decisions until the preferred p o r t folio selected as part of 4 the 2 015 Integrated Resource Plan ("IRP") concluded that a 5 2025 end-of-life assumption for Valmy would provide a more 6 favorable economic outcome as compared to the previous 7 operating life assumptions. 8 The analysis performed for the 2013 Coal Study 9 examined future investments required for environmental 10 compliance at existing coal units and compared those 11 inv estments to the costs of two alternatives: ( 1) 12 replacing such units with combined cycle combustion turbine 13 units or (2 ) converting the existing coal units to natural 14 gas. The 2013 Coal Study was inc luded as an exhibit to my 15 testimony in Case No. IPC-E-13-16.2 16 Q. What was the result of the analysis for Valmy 17 in the 2013 Coal Study? 18 A. At the time the study was prepared, it was 19 determined that continued operati o n of Unit 1 until 2031 2 0 and Unit 2 through 2035 was economi c , with the only notable 21 env ironmental investment required at Valmy being to install 22 OSI for compliance with the Mercury and Air Toxic Standards 23 ("MATS") regulation on Unit 1. Valmy is not subject to the 2 Idaho Power 's Application for a Certificate of Public Convenience and Necessity for the Investment in Selective Catalytic Reduction Controls on Jim Bridger Units 3 and 4 . HARVEY, DI 4 Idaho Power Company 1 Regional Haze Best Available Retrofit Technology ("RH 2 BART") regulations; therefore, no additional controls were 3 required for compliance with the RH BART regulations. 4 Idaho Power concluded that installation of the OSI system 5 was a low-cost approach to retain a diversified portfolio 6 of generation assets for customers and that continued 7 operation of Unit 1 would provide fuel diversity, helping 8 to mitigate risk associated with natural gas prices. Thus, 9 the Company continued to include Valmy in its generation 10 portfolio for the 2013 IRP and future resource planning. 11 Q. Please describe the operations of Valmy as 12 identified in the preferred portfolio analyzed in the 2013 13 IRP. 14 A. Although Idaho Power analyzed ceasing 15 operations at Valmy in 2021 and 2025 as part of the 2013 16 IRP, the preferred resource portfolio included continued 17 operations of the Valmy coal facility in full compliance 18 with environmental regulations through the 2013 IRP 1 9 planning period (2013-2032). Consistent with the 20 assumptions appl ied in the 2013 Coal Study, continued coal 21 operations were expected to require advanced financial 22 commitment in 2012 for the installation of OSI emission 23 control systems, approximately three years prior to their 24 installation and operation . 25 HARVEY, DI 5 Idaho Power Company 1 Q. Did Idaho Power commit financially and 2 subsequently install the DSI emission control systems 3 required at Valmy? 4 A. Yes. In 2012, Idaho Power committed 5 financially to the OSI investments required on Unit 1 to 6 meet the MATS regulation. Installation of the required 7 emission control systems was complete in the spring of 8 2015. 9 Q. With the DSI emission control system 10 investments completed on Unit 1, are both units at Valmy in 11 compliance with all known environmental regulations? 12 A. Yes. However, subsequent to the 2013 Coal 13 Study, it was determined that because of the existing 14 condition of the scrubber on Unit 2 , the scrubber would 15 need to be upgraded to meet the acid gas portion of the 16 MATS regulation. The scrubber upgrade on Unit 2 was 17 completed in 2015. With existing investments, Valmy is in 18 compliance with all current environmental regulations. 19 Q. Are there any future environmental regulations 20 that could affect Valmy? 21 A. At this time there are three environmental 22 regulations that have the potential to affect Valmy in the 23 future: the National Ambient Air Quality Standards 24 ("NAAQS"), Regional Haze, and the Federal Environmental 25 Protection Agency's Clean Air Act Section lll(d) HARVEY, DI 6 Idaho Power Company 1 ("11 1 (d) "). All impact areas for NAAQS are in attainment 2 and the state of Nevada is well below the Reasonable 3 Progress glide slope under the Regional Haze regulation so 4 no additional controls are anticipated at this time . 5 Finally , although there is still uncertainty around the 6 effect of final regulation related to lll(d), it is 7 anticipated that Valmy will be able to meet all targets set 8 by the final rule . 9 Q. Idaho Power 's last general rate case used a 10 2011 test year as a basis for plant values , which included 11 $148 million in Valmy-related plant . However, Mr . Larkin 12 indicated t h at current Valmy plant balances as of July 31 , 13 2016 , are approximately $217 million . Please explain what 14 is driving the approximately $70 million increase in the 1 5 Valmy balances from the 2011 test year to July 31 , 2016. 16 A. There have been a number of investments 17 required at Valmy over the last four and a half years to 18 ensure the plant remains operational in a safe , efficient , 19 and reliable manner , including investments required to 20 ensure environmental compliance as well as a number of 21 investments for routine maintenance and repair . 22 Q. Have you prepared an exhibit detailing the 23 investments made since the last general rate case? 24 A. Yes . Exhibit No . 4 details the investments 25 made at Valmy since the last general rate case , including HARVEY , DI 7 I daho Power Company 1 the investment by year and a classification as to whether 2 the investment was for environmental compliance, the safe 3 and economic operation of the plant, or for reliability 4 purposes. Exhibit No. 4 also includes a description and 5 justification for each of the investments. 6 Q. Does Idaho Power perform a review of the 7 planned capital projects prior to any investments being 8 made at Valmy? 9 A. Yes. For all planned capital projects, Idaho 10 Power receives from the plant operator, NV Energy, a 11 description of the project, the factors driving the need 12 for the project, and a recommendation for the work to be 13 performed. 14 Q. Were all of the projects comprising the 15 approximately $70 million in investment that occurred 16 between the 2011 test year and July 31, 2016, necessary for 17 either environmental compliance, the safe and economic 18 operation of the plant, or for reliability purposes? 19 20 A. Q. Yes. Please describe the investments made for 21 environmental compliance since 2011. 22 A. The investments made for environmental 23 compliance include OSI installation and coal pipe 24 replacement on Unit 1, the scrubber upgrade on Unit 2, the 25 coal crusher belt feeder project, dust collector upgrade, HARVEY, DI 8 Idaho Power Company 1 caustic tank building replacement , evaporation pond liner 2 replacement , bed demineralizer replacement , and the coal 3 combustion residual compliance project. 4 Q. What investments were made for the safe , 5 reliable , and economic operation of the plant? 6 A . To maintain the safe and reliable operation of 7 the plant, the cooling towers on both units were replaced , 8 the circulating water lines were recoated , the 9 mechanical/electrical shop was redesigned for increased 10 productivity, and the cathodic protection system was 11 upgraded. In addition, Unit 1 required the replacement of 12 the reheat tube and secondary tube sections of the boiler 13 and the sootblower system . Similarly , it was essential 14 that Unit 2 undergo a rebuild of the bottom ash hydrobin, a 15 burner and primary air duct replacement, a generator phase 16 end turn design betterment project , steam valve hardening , 17 and a primary superheat lower loop replacement . The 18 capital investments made at Val my since the last rate case 19 were prudent and essential for continued operation of the 20 plant. 21 22 23 Q. II. VALMY'S POSITION IN IDAHO POWER'S GENERATION PORTFOLIO Please describe the preferred portfolio 24 identified in the Company's 2015 IRP as it relates to Valmy 25 operations . HARVEY, DI 9 Idaho Power Company 1 A. Idaho Power analyzed a variety of retirement 2 dates for Valmy as part of the Company's 2015 IRP. Results 3 consistently indicated favorable economics associated with 4 two significant resource actions: the Boardman to 5 Hemingway ("B2H") transmission line and the early 6 retirement of Valmy. The preferred portfolio selected for 7 the 2015-2034 planning horizon contained both actions in 8 the year 2025, with completion of the B2H transmission line 9 preceding the end-of-year coal plant retirement. 10 Q. What were the factors driving the 2025 Valmy 11 end-of-life in the 2015 IRP preferred portfolio? 12 A. The preferred portfolio selected as part of 13 the 2015 IRP process contained no other resource additions 14 through the end of the 2020s. In addition to the absence 15 of resource needs, the resource sufficiency through the 16 early 2020s shielded the preferred portfolio from risk 17 exposure associated with the following near-term 18 uncertainties identified: planned but yet-to-be-built 19 Public Utility Regulatory Policies Act of 1978 (PURPA) 20 solar facilities, lll(d)'s proposed regulations, the 21 completion date of B2H, and the alignment of Valmy's early 22 retirement date with NV Energy. 23 Q. What was the action plan for Valmy's 2025 end- 24 of-life date as identified in Idaho Power's 2015 IRP? 25 HARVEY, DI 10 Idaho Power Company 1 A. The 2015-2018 action plan recognized in the 2 2015 IRP included ongoing permitting, planning studies, and 3 regulatory filings associated with the B2H transmission 4 line during all four years, and indicated, in 2016, Idaho 5 Power would work with NV Energy to synchronize depreciation 6 dates and determine if a date could be established to cease 7 coal-fired operations. This filing will synchronize 8 depreciation rates between the two companies. 9 Q. How have changes in market energy prices in 10 recent years impacted the value of Idaho Power's surplus 11 energy or "off-system" sales? 12 A. In 2011, the average price Idaho Power 13 recei ved for off-system sales was $22.71 per MW compared to 14 2015 when the average price Idaho Power received for off- 15 system sales was only $11.82 per MW. Moreover, year-to- 16 date 2016, Idaho Power's average price for off-system sales 17 is only $8.76 per MW. 18 Q. How does the decrease in the average price for 19 off-system sales impact Valmy operations? 20 A. The significant decrease in market prices has 21 resulted in a decrease in the number of hours Valmy 22 operates economically, as the dispatch cost is now 23 typi c ally higher than the market price. The following 24 chart details the decrease in Idaho Power's capacity factor 25 at Valmy over the last eight years as a result of the HARVEY, DI 11 Idaho Power Company 1 decrea s e in market prices . NV Energy is experiencing a 2 similar trend in its share of Valmy generation . 3 4 5 Year Idaho Power's Dispa tched Capacit y Factor 2008 7 6% 2009 7 2% 2010 6 4% 2011 2 9% 2012 2 7% 20 1 3 4 9% 2014 4 1 % 2015 1 5% Rather than a resource used to generate off-system 6 sales , Idaho Power has been relying on Valmy to meet the 7 Company 's peak energy needs , preserving the balanced 8 portfolio needed to reliably serve Idaho Power customers 9 during all types of system conditions. For example , when 10 extreme cold weather or extreme hot temperatures occur in 11 the West raising market prices , Valmy is available to 12 provide reliab l e energy and capacity to serve I daho Power 's 13 customers . Absent Valmy's generation , the Company woul d be 14 required to rely on market purchases on non-firm 15 transmission , which may not be available to serve the load . 16 Q. If Valmy is currently being used to he l p Idaho 17 Power reliably serve load , why is the Company proposing a 18 2025 end-of-life? 19 A . As shown in the preferred portfolio of Idaho 20 Power 's 2015 IRP , the economics of Valmy's operation are HARVEY , DI 1 2 Idaho Power Company 1 impacted in the long term, as new resources such as B2H or 2 other operating facilities are available to maintain the 3 balanced portfolio required to serve load reliably. 4 Q. Absent B2H, is it feasible to discontinue 5 operations prior to 2025? 6 A. No. As previously stated, Idaho Power relies 7 on Valmy to meet peak energy needs and to preserve the 8 balanced portfolio needed to reliably serve customers 9 during all types of system conditions. When extreme cold 10 weather or extreme hot temperatures occur in the West, 11 Valmy is providing reliable energy and capacity to serve 12 customers . The Company's peak-hour load and resource 13 balance analysis included on page 96 of the Company 's 2015 14 IRP demonstrates that Idaho Power would have peak-hour 15 capacity deficits beginning in 2020 if Valmy were retired 16 in 2019. A copy of the 2015 peak-hour analysis is provided 17 as Exhibit No. 5. As can be seen in Table 7.5 of Exhibit 18 No. 5 under the line labeled "Valmy Retire Units 1 and 2 19 Year-End 2019," peak-hour deficits without Valmy generation 20 capacity grow from 24 MW in 2020 to 236 MW by 2024. 21 Q. Please provide an example of how Valmy is 22 currently being used to balance Idaho Power 's portfolio and 23 reliably serve customers. 24 A. In the summers of 2015 and 2016, Idaho Power's 25 loads exceeded 2900 MW, resulting in market purchases HARVEY, DI 13 Idaho Power Company 1 between 300 to 500 MW to cover load while Valmy was 2 economically displaced by the market purchases and 3 operating at minimum levels. As the temperatures and load 4 continued to rise , wind generation decreased and Idaho 5 Power was unable to import additional market purchases to 6 cover the load due to transmission constraints . During 7 these hot afternoon time periods, Valmy was dispatched at 8 or near capacity. Another example occurred in the fall and 9 winter of 2014 and 2015. Valmy was dispatched during the 10 Langley Gulch power plant maintenance outages as Fall 11 Chinook spawning flows restricted hydro generation and 12 there was not sufficient transmission capacity to reliably 13 serve load with market purchases. Idaho Power will 14 continue to rely on Valmy during similar circumstances in 15 the future as load increases in the Company's service 16 territory and until the addition of new resources that are 17 available during peak hours or can provide additional 18 transmission capacity. 19 20 Q. III . CESSATION OF VALMY OPERATIONS Have Idaho Power and NV Energy agreed to a 21 date to cease coal-fired operations at Valmy? 22 A. No. However, Idaho Power and NV Energy 23 continue discussions working towards a mutually agreed upon 24 25 closure date . Synchronized depreciation dates for HARVEY , DI 14 Idaho Power Company 1 ratemaking purposes will help in establishing a date to 2 cease coal-fired operations. 3 Q. In his testimony, Company witness Mr. Larkin 4 discusses the use of a 2025 depreciable end-of-life date by 5 NV Energy for both units at the Valmy plant. Would it be 6 feasible for Idaho Power to continue to utilize Valmy 7 beyond 2025 if NV Energy was no longer an ownership 8 partner? 9 A. No. If NV Energy establishes a closure date 10 of 2025, Idaho Power's continued utilization of Valmy 11 beyond 2025 would require negotiation with NV Energy to 12 modify or terminate the existing Agreement for the 13 Ownership of the North Valmy Power Plant Project 14 ("Ownership Agreement"). In addition, the Agreement for 15 the Operation of the North Valmy Power Plant Project 16 ("Operation Agreement") would require nullification as it 17 identifies NV Energy as the operator of Valmy. Absent the 18 acquisition of a new operating partner or Idaho Power 19 acquiring or developing the skills and experience to 20 operate a coal-fired plant, it would be impractical for 21 Idaho Power to continue operating the plant after 2025 22 without NV Energy. 23 Q. Has Idaho Power performed any additional 24 analyses associated with the Valmy end-of-life date since 25 the 2015 IRP was completed? HARVEY, DI 15 Idaho Power Company 1 A. Yes. In 2016, Idaho Power assessed the 2 continued use of the 2025 end-of-life assumption for Valmy 3 using an updated evaluation of the present value revenue 4 requirement of operating period alternatives. 5 Q. How did the Company analyze the potential 6 revenue requirement impact of modifying the Valmy end-of- 7 life date? 8 A. To determine the potential revenue requirement 9 impact, Idaho Power analyzed the present value revenue 10 requirement of two operating period alternatives: (1) the 11 2025 end-of-life for both units and (2) the existing 2031 12 and 2034 3 staggered end-of-life assumptions. The operating 13 period alternatives used under the revenue requirement 14 scenarios consisted of the following two components: ( 1) 15 net present value ("NPV") revenue requirement associated 16 with the existing investment, additional run rate capital, 17 fixed operation and maintenance ("O&M") expenses, and 18 forecasted taxes and insurance and (2) the total variable 19 portfolio costs using the AURORA model from the 2015 IRP, 20 updated with the most recent load forecast, natural gas 21 forecast, and Valmy coal price forecast, utilizing the 3 Although the actual current depreciable life of Valmy Unit 2 is through the end of 2035 , the 2015 IRP planning period did not extend beyond 2034 ; therefore, this IRP-based analysis reflects a 2034 retirement . Extending the analysis to 2035 would likely result in an increase in the cost difference . HARVEY, DI 16 Idaho Power Company 1 resource assumptions from the preferred portfolio. The 2 results of this analysis are presented as Exhibit No. 6. 3 Q. Please describe the results of the revenue 4 requirement impact of the two operating period alternatives 5 presented in Exhibit No. 6. 6 A. Idaho Power's analysis results presented in 7 Exhibit No. 6 indicate that the NPV of the revenue 8 requirement associated with a 2025 end-of-life is $103 9 million less than the revenue requirement of a 2031/2034 10 retirement date. 11 Q. Did Idaho Power conduct updated present value 12 revenue requirement analyses that assessed the economics of 13 ceasing operations sooner than 20 2 5? 14 A. No. While Idaho Power's forecast indicates 15 Valmy is expected to be a necessary, but relatively 16 infrequent, contributor to system reliability, resulting in 17 a low capacity factor between now and 2025, the current 18 Ownership Agreement and Operation Agreement between Idaho 19 Power and NV Energy do not provide for provisions to cease 20 coal-fired operations at the plant if the plant owners do 21 not align on end-of-life dates. In addition, as described 22 in Mr. Larkin's testimony, the rate impact associated with 23 an accelerated depreciation schedule ending in 2019 would 24 be materially higher. In an attempt to mitigate this 25 customer rate impact, the Company has concluded that a 2025 HARVEY, DI 17 Idaho Power Company - 1 end-of-life date strikes a reasonable balance between 2 reliability, economics , and customer rate impacts. 3 Q. Please describe the routine capital 4 expenditures Idaho Power anticipates will be necessary to 5 safely and reliably operate Valmy through the plant 's end- 6 of -life date of 2025 . 7 A. The incremental investments expected through 8 Valmy's end-of-life are for upgrades and replacements of 9 plant infrastructure required to keep the plant 10 operational, safe, and reliable. Both units are on a 11 three-year outage cycle that requires each unit to be taken 12 down once every three years for unit inspection and 13 selected refurbishment . In 2018 and 2019, the units are 14 scheduled for their next outages so incremental investments 15 are expected to be higher these years . These outages, 16 which should be the last large ones performed, will help 17 ensure the units are operational and can continue to 18 provide reliable service through 2025 . 19 Q. Will Idaho Power perform the same review of 20 future incremental investments prior to any work being done 21 as the review performed for investments made since the 22 Company's last general rate case? 23 A. Yes . The Company will receive a description 24 of the factors driving the need for the project and a 25 recommendation for the work to be performed from the plant HARVEY, DI 18 Idaho Power Company 1 operator , NV Energy . The estimated cost of each project 2 will then be compared to the expected life of the asset as 3 well as the Valmy end-of-life date to determine prudency of 4 the planned investment . In addition , Idaho Power and NV 5 Energy will work together to identify ways to reduce O&M as 6 both partners prepare for future low production from the 7 plant through its end-of-life . 8 9 Q. A. Please summarize your testimony . Significant changes to the ongoing economics 10 of Valmy operations have occurred between 2010 and 2014 . 11 Market prices have decreased considerably, resulting in a 12 decrease in the number of hours Valmy operates economically 13 as the dispatch cost is now typically higher than the 14 market price. Idaho Power relies on Valmy to meet peak 15 energy needs and to preserve the balanced portfolio needed 16 to reliably serve customers during all types of system 17 conditions . However , Idaho Power's 2016 assessment of 18 Valmy indicated that a 2025 shutdown date is preferable 19 with respect to reliability and revenue requirement 20 impacts . Consistent with the action plan recognized in the 21 2015 IRP , Idaho Power will continue working with NV Energy 22 to synchronize the depreciation date of Valmy and determine 23 if a mutually agreeable date can be established to cease 24 coal -fired operations . It is not the expectation of Idaho 25 Power that any date agreed upon by the Company and its HARVEY , DI 19 Idaho Power Company 1 operating partner would extend Valmy operations beyond 2 2025. 3 Q. Based on the analysis presented in your 4 testimony, do you believe December 31, 2025, reflects the 5 most reasonable end-of-life assumption for the Valmy plant 6 based on what is known today? 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 A. Q. A. Yes, I do. Does this complete your testimony? Yes, it does. HARVEY, DI 20 Idaho Power Company 1 ATTESTATION OF TESTIMONY 2 3 STATE OF IDAHO 4 ss. 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 2 0 21 22 County of Ada I, Tom Harvey, having been duly sworn to testify truthfully, and based upon my personal knowledge, state the following: I am employed by Idaho Power Company as the Resource Planning and Operations Director in the Power Supply Department and am competent to be a witness in this proceeding. I declare under penalty of perjury of the laws of the state of Idaho that the foregoing pre-filed testimony and exhibits are true and correct to the best of my information and belief. DATED this 21 st day of October 2016. - Tom Harvey 23 SUBSCRIBED AND SWORN to before me this 21 st day of 24 October 2016. 25 26 27 28 29 Notary Public Residing at: Boise, Idaho My commission expires: 02/04/2021 HARVEY, DI 21 Idaho Power Company BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-16-24 IDAHO POWER COMPANY HARVEY, DI TESTIMONY EXHIBIT NO. 4 () Q) (/) CD z :-t 9 "C I =ti m Q>D>()x tC<':!. coco mo­~ ',< I ;::::;: 0 -:_ c» Z --c "'o 01 ()~ ~ Project Unit 2 Cooling Tower Replacement Unit 1 DSI Installation Unit 2 Scrubber Upgrade Unit 2 Scrubber Alomizer Upgrade 2011 2012 $80,324 $104,931 $0 $1,661,173 $0 $21,178 $0 $18,148 VALMY INVESTMENTS SINCE LAST GENERAL RATE CASE (CASE NO. IPC-E-11-08) 2013 2014 2015 2016 Total Purpose Project Description/Justification The Unit 2 cooling tower was operational in 1985 and was designed for a 20 -25 year life. Safety Metric: The existing cooling lower structure was nearing the end of its service life and the wood in the tower was deteriorating. Wood supports for access Safety I ways, piping, and lhe hot deck were rotted and became unsafe. Reliability Metric: The $113,989 $4,504,556 $2,450,464 $93,878 $7,348,142 cooling tower was operating at 67% of its perfonnance due to degradation of the tower Reliability affecting lhe condensers perfonnance to cool the exhaust from the turbine, causing a derate in back pressure. O&M Metric: The rotting of the wood structure resulted in an increase of maintenance costs to replace affected areas. Both units must meet the Mercury and Air Toxics Standard (MATS) 4-16-2015. This project / scope covers the Hydrochloric Acid (HCI) mitigation to comply with MATS Rule $624,036 $3,992,239 $495,356 $42,554 $6,815,359 Environmental for the unit to run beyond 4-16-2015. Technology selected was Dry Sorbent Injection (DSI) -Hydrated Lime is injected in the backend of the boiler lo remove HCI. HCI limit is .0020 lb/ MMBtu. This project was required for the unit to meet the MATS standard. The Valmy Unit 2 Dry Flue Gas Desulphurization (DFGD) system began service in 1985. It was based on technology developed and designed by Rockwell International. The system was not capable of optimum operation. This was due to problems with the original design, obsolete and worn-out equipment, the complexity of the system design and a lack of plant staffing to proper1y operate and maintain the system in its current condition. These problems fell into four main categories: safety issues, environmental problems, process issues related to the design complexity and a high cost of operation when compared to more recently designed and built DFGD systems. After started, this project was modified to increase the S02 removal from the original design of 70% to roughly 85% to ensure compliance with the Mercury and Air Toxics Standard (MATS). This project included: 1) the replacement of the Lime Slurry and Recycled Ash Slurry three way valve with Pinch valves, 2) the replacement of the valves below the inlet slrainers with new 1-1/2" pinch valves, 3) fabrication and installation of access safety platfonns missed by engineering but are required for operations and maintenance, 4) $1,014,212 $2,257,179 $3,062,885 $248,467 $6,603,920 Environmental upgrading the gland seals on the recycled ash and Lime Slurry Pumps, 5) relocating the two Lime Slurry Pumps for operations and maintenance, 6) replacing the day bin vibrator, 7) resolving the slurry pluggage issues at the atomizers by extending the hard piping to the atomizers and replacing the atomizer hoses, 8) replacement of lime and recycle ash slurry loop pressure transducers and isolation rings, 9) cleaning, inspection and modification of the atomizer slurry feed systems, 10) cleaning and inspection of atomizers and slurry distribution wheels, 11) vessel flue gas exit temperature thennocouple modifications, 12) replacement of all Orbinox valves to Clarkson valves, 13) installing new flushing water strainer, 14) installing pressure gauge isolation seals, 15) tuning of slaking water inlet temperature sparger and controls, 16) refining Flushing Sequences Logic, 17) installing new level indicators at the recycled ash day bins, and 18) removing and replace drains at the atomizer deck. The V2 Scrubber was placed inlo service in 1985, using three (3) separale vessels. Each vessel contains three (3) spray machines for a total of nine (9) spray machines. The machines are used for the removal of S02 from the flue gas in order to comply with the Title 5 mandate. Each spray machine consists of a 300HP water cooled motor turning at 3600 rpm, coupled lo a 10,000 rpm gearbox with a flex shaft and an atomizer wheel. The equipment condition deteriorated and became unreliable and inefficient. Costs to mainlain lhe equipment significantly increased. (12) Atomizer Machines were $1,355,170 $1,226,229 $3,505,849 ($102,237) $6,003,158 Environmental purchased from Alstom Power. (9) are in continuous use and (3) were purchased as spares. Along with the purchase of the Atomizers, all (9) turning vanes and Atomizer Housings and associated controls were replaced. After started, this project was modified lo increase the S02 removal from the original design of 70% to roughly 85% to ensure compliance with the Mercury and Air Toxics Standard (MATS). This project was a complement to the previous project to ensure compliance with the Mercury and Air Toxics Standard (MATS) () II) g: z :-l~ "U I =tj m Ill Ill () X IC<':!. CD CD ITT CT N'< I ;=.: o-_ en z ...... -u No c.n()""'""' Project Valmy Coal Crusher Bell Feeder Project Unit 2 Sootblower Syslem Replacemenl Unil 1 Cooling Tower Replacement Unit 1 Reheal Tube Replacemenl North Valmy Dust Collector Upgrade Unil 2 Botlom Ash Hydrobln Rebuild 2011 2012 $0 $378,222 $0 $144,858 $2,974,603 $219,234 $3,165,809 $25,449 $723,834 $922,915 $0 $0 2013 2014 2015 $3,709,529 $46,342 $0 $3,527,234 $79,877 $0 $1,437 $13,197 $0 $0 $0 $0 $987,841 $354,106 $135,968 $0 $83,458 $3,024,866 2016 Total Purpose Project Description/Justification The crusher tower arrangement and equipment created unnecessary dust generation which could have caused violations of lhe Nevada Department of Environmenlal Proteclion dusl elimination requirements. The vibratory feeders were not equipped with effective seals to the feeder skirtboard, which caused particulale spillage and dust emissions. The ring-granulator-style crushers generate significant dusl when crushing, and also acl as a fan to push dust out or lhe skirtboard and headbox openings when operating empty. Also, the system throughput was compromised due to sizing of the $0 $4,134,093 Environmental I exisling feeders/crushers; the 400 rating requires bolh feeders /crushers be operated lo Economic match downstream belt capacily of 800 TPH. Upgrading lhe feeders and crushers to a higher rate provides additional operaling flexibility. Existing crusher discharge chute work was not well configured and prone to pluggage. In order lo significantly improve reliabllily, the new arrangement eliminaled the single flop gate bottleneck present in lhe currenl transfer arrangement. These upgrades were also required per Nevada Department of Environmental Protections request for dusl elimination. The currenl condition of the Unit 2 soolblower system was rated from poor to very poor. The issues ranged from current overloading to excessive amounts of condensate to $0 $3,751,969 Reliabilily excessive slagging (wall slagging). These conditions were contributing to increasing tube erosion and decreased efficiency due to slagging issues. To ensure reliable operalions of lhe boiler, lhis project was needed for reliability. The unit 1 cooling tower was operational in 1981 and was designed for a 20 -25 year life. Safely Melric: The exisling cooling tower structure was nearing lhe end of its service life and the wood in the tower was deleriorated. Wood supports for access Safely/ ways, piping, and lhe hot deck were rotled and became unsafe. Reliability Metric: The $0 $3,208,471 cooling lower outlet water temperature never mel lhe design parameter thus affecting Reliabilily the condensers performance to cool the exhausl from the turbine, causing high back pressure. O&M Metric: The rolling of the wood structure was resulting in an increase of maintenance costs to replace affected areas. Unit 1 experienced an increase of forced outages to repair failed tubes; 2010 Unil 1 inspection oulage required over 100 pad welds lo patch thin lube wall areas, but lhe Reliabilily / reheal seclion needed replacemenl during the 2011 outage. Per the NVE Generation $0 $3,191,257 Economic Engineering inspection -recommendation was to replace all reheat sections otherwise failures will continue to occur with escalaling frequency up to potentially an average of one per monlh. The currenl Valmy coal dusl collection syslems were original inslallalion, circa late 1970's/ea~y 1980's, designed to meet combustible dust control standards of lhat time. OSHA in 2008 upgraded the standards for combustible dusl control and issued Instruction CPL 03-00-008 (3/11/2008) that contained policies and procedures for inspecting work places that create or handle combustible dusls. This program focused ($1,662) $3,123,002 Environmental on specific industries that have frequent combuslible dusl incidents and the National Emphasis Program is to inspect those facilities thal generale or handle combuslible dusls which pose a deflagration or other fire hazard when suspended in the air. Along wilh OSHA's directive and the potential to bum different sources of coal, the old dusl collection systems needed to be upgraded to meel those requirements. The Valmy Unit 2 botlom ash dewatering and recycle system was deteriorated and become unreliable and was at risk of total failure. An inspection by the OEM, Allen Sherman Hoff was completed in 2010 and repealed in 2012 with bolh inspections identifying a number of serious issues. ~ lhe plant did not complete the highesl priorily repairs, lhe system would have become very unreliable and resulted in significant load ($275,518) $2,832,806 Reliabilily / reductions and emergency repair costs. Additional work idenlified after the project Economic started is: concrete foundation repairs, replacing corroded underground electrical conduits, thickness inspections and repairs to the lower cone sections of two dewatering bins, additional Non Destructive Examination (NDE) testing, power outage and weather delays and repairs lo 6 inch and 8 inch knife gate valves. () Dl CJ) (1) z :-I~ -uI=tim ruDl()x <0<'2: ro ro mo­w'.:< ~;:.: 0 -O> Z --uNO (11 () .I>,. .I>,. Project Unit 2 Burner Replacement Unit 1 Sootblower System Replacement Unit 1 Secondary Supemeat Replacement Unit 2 Primary Air Duct Replacement North Valmy Caustic Tank Building Replacement Evaporation Pond Liner Replacement Mixed Bed Demineralizer Replacement Unit 1 Circulating Water Line Recoat 2011 2012 $0 $693 $0 $118,438 $2,114,142 ($29,440) $0 $0 $0 $257,820 $774,302 $1,262,317 $0 $30,834 $0 $0 2013 2014 2015 $2,330 $74,157 $2,339,126 $838,112 $1,198,044 ($23,995) $0 $0 $0 $0 $22,843 $2,212,396 $1,210,585 $368,344 $0 ($315,770) $0 $0 $841,661 $796,332 ($35,487) $0 $48,357 $1 ,199 2016 Total Purpose Project Description/Justification The Valmy Unit 2 burners were in poor condition and had a history of high failure rate. Advanced Control Technology burners were installed in 2007. The burner components were failing due to excessive wear and overheating. The failures induded, the burner inner barrel, diffusers, igniters, and scanners. In addition to the need of replacement for $9,732 $2,426,039 Reliability / reliability purposes, there was an average of 21,717 lost MWHs per year from 2007- Economic 2011 due to burner and igniter issues. This project replaced the burner components with high wear resistant materials, installed heavy duty igniter tubes, scanners, and new igniters. Cooling air was supplied to the scanners. Unit 1 experienced premature boiler tube erosion from the sootblowing activities. The cause for the erosion was from excessive moisture in the sootblowing medium. The redesigned system allowed for the extra sootblowing without damage to the boiler $0 $2,130,599 Reliability tubes. Without a property functioning sootblower system, the potential for an increase in ash contributes to more accumulation on the tubes reducing the thermal exchange, which would require more frequent deaning. This project involved the replacement of the secondary supertleat assemblies in the Unit 1 Boiler. Since 1998 eighteen (18) documented derates and forced outages have $0 $2,084,702 Reliability occurred requiring repairs to tube leaks. The Unit 1 boiler inspection conducted in 2008 indicated significant loss in the wall thickness of the tubing and the potential for a substantial increase in tube leaks. The North Valmy Unit 2 Primary Air Duct System is part of a system that apportions hot and cold air flow to the pulverizers for drying and transporting pulverized coal to the burners in a measured and controlled way. The duct worl<, dampers and expansion joints have been altered by pulverizer explosions and emergency repairs to return the ($289,625) $1,945,614 Reliability unit to service. This has resulted in misdistribution and control of primary air and has led to combustion control problems from burner coking to ductwork puffs. Restoration of the system restored its pertormance and increased reliability of the unit from forced outages. This project replaced the building that housed the caustic tanks. In early 2012 the containment basin in the Caustic Tank Building began leaking. The leaking caustic soda caused the ground to heave under the building resulting in significant damage to the Reliability / structure and the associated systems, including the electrical and piping to the caustic $0 $1,836,748 Safety I tank. The earth was excavated at the heave to alleviate the uplift pressure on the Environmental building. The excavated material was tested with the test results showing an elevated ph of 12.5 indicative of a caustic soda leak. The existing pond liner was 30 years old and was exhibiting several areas of delamination that are indicative of material failure. The condition of the existing liner $0 $1,720,848 Environmental suggests it has reached the end of its useful life and therefore required a new liner system to be installed with upgraded materials. This included a double walled liner with leak detection to ensure environmental compliance. This project replaced the mixed bed demineralizer and sulfuric acid and caustic soda tanks. The mixed bed demineralizers were 30+ years old. The su~uric acid tank and Safety I the caustic soda tanks were reaching the end of their designed corrosion life which $0 $1,633,341 Environmental involved serious leaks from the tanks. Sulfuric acid and caustic soda were becoming a higher priced commodity. The entire system needed to be replaced. The circulating water pipe lining was failing and in need of being relined during an extended outage. A failure of the lining could result in pipe corrosion and leaks and could require several days to excavate the line and complete repairs. System leaks Reliability I required an outage for repair. The cathodic protection system for the plant was replaced $1,486,158 $1,535,714 Economic in 2013. The poor pertormance of the system before the replacement most likely resulted in pipe exterior damage. Several other underground pipes have had an increased failure rate in recent years. A total failure of the pipe would result in a six (6) month forced outage. () Dl g: z :-i ~ -uI=t;m ~ !!l () ~ (1) < ' -· ~ r;n g .j>,. -...... 0 -O> Z -"'O ' 0 o,()N · .j>,. .j>,. Project Unit 2 Circulating Water Line Recoat Mechanical/Electrical Shop Rebuild Unit 2 Generation Phase End Tum Design Betterment Cathodic Protection System North Valmy Coal Combustion Residual Compliance Unit 2 Steam Valve Hardening Unit 1 Coal Pipe Replacement 2011 2012 $0 $0 $0 $102,137 $0 $1,420,942 $36,294 $500,521 $0 $0 $0 $0 $0 $0 2013 2014 2015 $0 $28,074 $1,476,360 $1,586,592 ($172,626) ($50) ($133,291) $0 $0 $634,186 ($11,703) $0 $0 $0 $1 ,289,835 $0 $0 $1,116,028 $0 $0 $189,674 2016 Total Purpose Project Description/Justification The circulaling water pipe lining was failing and in need of being relined during an extended outage. A failure of the lining could result in pipe corrosion and leaks and could require several days to excavate the line and complete repairs. System leaks Reliability / required an outage for repair. The cathodic protection system for the plant was replaced $18,739 $1,523,174 Economic in 2013. The poor performance of the system before the replacement most likely resulted in pipe exterior damage. Several other underground pipes have had an increased failure rate in recent years. A total failure of the pipe would result in a six (6) month forced outage. The old maintenance shop complex was comprised of several disconnected areas which decreased productivity, restricted the ability to provide optimal plant support, and inhibited the ability to conduct effective staff training. The old welding shop consisted of a small area between the units enclosed by insulation attached to chain link fencing. $0 $1 ,516,053 Economic The combined electrical~nstrumentation shop was contained in a small room adjacent to the business center. The lunchrooms were separate, with the largest used to conduct safety meetings/training with standing room only. Productive ongoing training could not be conducted with the entire staff because of inadequate meeting space. After an investigative analysis of the generator stator end turns, it was determined that the current phase end-turn connections were too rigid when last rebuilt by REGENCO. The phase end-turn connections must account for different component expansion rates $0 $1,287,652 Reliability / and also avoid the potential issues with natural frequency near the electromagnetic Economic exciting frequency forces of 120 hertz. All the generator stator end turns needed to be resoldered to prevent failure. The original cathodic protection system was installed during a period from 1981 to 1984. The old cathodic protection system was installed as an upgrade in 1991. The plant observed an increase in the rate of underground pipe corrosion, which suggested the existing cathodic protection system failed or was at the end of its useful life. An evaluation was performed for all five systems and the determination was that the Reliability/ majority of the depressed sacrificial anodes have been depleted and new anodes $0 $1,159,298 Economic needed to be installed in order to protect the underground piping, fire lines, and tank bottoms. It was also determined that there were several new wells put into service without any cathodic protection. These new well casings needed protection, and required a complete system for each well. Also, the evaluation proposed that the majority of the anodes in the condenser water boxes were depleted and need to be replaced. The Coal Combustion Residual (CCR) rule was published in the Code of Federal Regulations on April 17, 2015. Valmy had 180 days to comply with the CCR regulations. Valmy has taken a proactive approach to addressing the impacts of potential "ash piles" noted onsite. To continue to be proactive and avoid inadvertently creating CCR ($166,324) $1,123,511 Environmental impoundment, North Valmy needed to place asphalt and concrete at the bottom ash handling areas of Unit 1 and Unit 2. If this area was not paved, under the CCR rule, these areas would have been considered an "open dump" and a violation of the regulation, and may ultimately have lead to the creation of additional CCR impoundments at Valmy. Due to high temperatures, the current materials that made up the steam turbine valve internals were subject to formation of an oxide layer that could eliminate the clearance Reliability / between the moving and stationary parts. This could have caused the valves to bind $6,720 $1,122,748 Economic and bend, causing a forced outage. The valves were also originally designed for base load operation. This project helped increase the availability of the valves during high cycling. The plant was experiencing considerable erosion on its coal piping that leads from the pulverizers to the burners. This erosion resulted in coal leaks that were a housekeeping, dust control (OSHA dust control initiative) and ultimately a fire, health $921,442 $1,111,116 Safety / and explosion hazard. Identifying and replacing individual sections of piping has been Environmental performed in the past, which was a short term solution to the problem. A total replacement of the piping system including wear resistant pipe and a revised support and hanger system was required. () Q) ~ z :-1 !=> "'CJ I-m wD>"'CJx co < <;") 2: ro ro m c-c.n "< I ;::::;: o -_a,Z -"'CJ' 0 01 ()~ ~ Project 2011 2012 2013 2014 2015 2016 Total Purpose Project Description/Justification From the North Valmy Unit 2, 2009 boiler inspection for the primary superheat section of the boiler, 36 areas were identified with tubes 50% or less of Minimum Wall Thickness (MWT) and 68 areas were tubes were 60% or less than MWT. In comparing 2010 inspection report with 2009, sootblower lanes of the primary superheat had lost an additional 10% of their wall thickness. The inspection reports indicated the potential for Unit 2 Primary Superheat Reliability / an increase of forced outages. Many of the thinned tubes were replaced in 2010. Follow $0 $0 $0 $0 $1,057,855 $6,384 $1,064,239 up inspection in 2012 identified a few additional tubes to be replaced. A capital project in Lower Loop Replacement Economic 2013 installed tube shields over the tubes in the sootblower paths. The lower loops were still exposed to flue gas erosion. The inspection in 2014 indicated the tubes in the flue gas path continued to deteriorate. The 2015 planned outage created the opportunity to replace the high wear area tubes with new resistant material. Pulverizers are utilized to grind coal to fine dust before being transported to burner fronts. This process wears out roll wheel assemblies, table grinding segments, and the interior of the pulverizer equipment. Mill overhauls at Valmy have historically been on an 18 to 24 month cycle. The coal imported to Valmy is high in silica and quartz which causes excessive wear on pulverizer grinding sections. If the pulverizer condition Unit 1 Pulverizer '8' Major $623,089 ($42,115) $1,047,583 $438,835 $0 $0 $1,033,696 Reliability / deteriorates the units efficiency is decreased thus increasing the fuel usage and power Rebuild Economic costs. This project removed and replaced all major components induding roll wheels, grinding table segments, yoke, classifier and vanes, reject chute, loading cylinders and cables, labyrinth air seals, pyrite plows, burner shut off valves and seats, rebuill pulverizer motor, coal feeder belt drive and conveyor reducer and motor, eroded downspouts and chute, rebuilt lube oil system pumps. Note: The information presented in this exhibit reflects the total capital spend by specific project, for projects over $1 million, including amounts closed to FERG Account 101 -Electric Plant in Service, FERG Account 107 -Construction Work in Progress and any FERG Account 108 -Accumulated Provision for Depreciation removals but excluding AFUDC. BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION · CASE NO. IPC-E-16-24 IDAHO POWER COMPANY HARVEY, DI TESTIMONY EXHIBIT NO. 5 () Ql CJ) CD z :-19 "'C:r:=u~ Q>Dl()::::r IC<'fr CD CD r;n ;:.: ...... ',:< ...... z o -'t>o -"UN · ...... () ,I:>. 01 7. Planning Period Forecasts Idaho Power Company Tables 7.5 and 7.6 provide the peak-hour capacity deficits for July and December for the coal futures considered. Darker shading in the tables corresponds to larger deficits. Surplus positions are not specified in the tables. Because no deficits exist prior to 2020, the tables include data only for 2020 to 2034. Table 7.5 July monthly eeak-hour capacity deficits (MW) by coal future with existing and committed supply-and demand-side resources (90 h -percentile water and 951h -percentile load) Energy Deficits (aMW) 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Status Quo Maintain Coal Capacity Valmy Retire Units 1 and 2 Year-End 2019 Valmy Retire Units 1 and 2 Year-End 2025 Valmy Retire Unit 1 Year-End 2019 and Unit 2 Year-End 2025 Valmy Retire Unit 1 Year-End 2021 and Unit 2 Year-End 2025 Bridger Retire Unit 1 Year-End 2023 and Unit 2 Year-End 2028 Bridger Retire Unit 1 Year-End 2023 and Unit 2 Year-End 2032 Bridger Retire Unit 1 Year-End 2023 and Unit 2 Year-End 2032, Valmy Retire Units 1 and 2 Year-End 2025 (24) . ·---, Table 7.6 December monthly peak-hour capacity deficits (MW) by coal future with existing and committed supply-and demand­ side resources (901h -percentile water and 951h -percentile load) Energy Deficits (aMW) 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 Status Quo Maintain Coal Capacity Valmy Retire Units 1 and 2 Year-End 2019 - - -- - -(12) (32) (59) (58) (99) Valmy Retire Units 1 and 2 Year-End 2025 - -- - - -(12) (32) (59) (58) (99) Valmy Retire Unit 1 Year-End 2019 and Unit 2 Year-End 2025 -- --- -(1 2) (32) (59) (58) Valmy Retire Unit 1 Year-End 2021 and Unit 2 Year-End 2025 - - -- --(12) (32) (59) (58) Bridger Retire Unit 1 Year-End 2023 and Unit 2 Year-End 2028 Bridger Retire Unit 1 Year-End 2023 and Unit 2 Year-End 2032 Bridger Retire Unit 1 Year-End 2023 and Unit 2 Year-End 2032, Valmy Retire Units 1 and 2 Year-End 2025 Page 96 2015 IRP 2034 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-16-24 IDAHO POWER COMPANY HARVEY, DI TESTIMONY EXHIBIT NO. 6 North Valmy Generating Station Revenue Requirement of Valmy Operating Period Alternatives To determine the potential customer rate impact of modifying the depreciable end-of-life assumption at Valmy to 2025, Idaho Power analyzed the revenue requirement of two operating period alternatives: (1) the 2025 end-of-life for both units, and (2) the existing 2031 and 2035 staggered retirement assumption. The revenue requirement alternatives consist of two components: 1. The net present value ("NPV") revenue requirement associated with the existing investment, additional run rate capital, fixed operation and maintenance ("O&M") expenses, and forecasted taxes and insurance; and 2. The total variable portfolio costs using the AURORA model from the 2015 IRP, updated with the most recent load forecast, natural gas forecast, and Valmy coal price forecast, utilizing the resource assumptions from Portfolio P6(b). When combining components 1 and 2 above, the Company's analysis indicates that the least-cost result is the end-of-life for both Valmy units at the end of 2025 as compared to 2031/2035, by a differential of approximately $103 million. Figure 1 below provides a summary of the results, while the detailed NPV cash flow analysis is provided as Appendix A to this document. Scenario 2025 Retirement 2031/2034 Retirement Difference Figure 1: NPV Revenue Requirement Analysis Summary 2025 vs. 2031/2034 End-of-Life1 ($OOO's) Component 1: Component 2: Fixed Cost NPV AURORANPV $397,342 $4,167,493 $522,715 $4,145,163 ($125,283) $22,330 Combined NPV $4,564,835 $4,667,878 ($103,043) Based on this analysis, from an NPV perspective the net reduction in revenue requirement resulting from a 2025 end-of­ life assumption at Valmy as compared to 2031/2034 is approximately $103 million. When evaluating the 2025 and 2031/2034 scenarios, an end-of-life assumption of 2025 would result in NPV revenue requirement savings as compared to the existing operating assumption. 1 Although the actual current depreciable life of Valmy Unit 2 is through the end of 2035, the 2015 IRP planning period did not extend beyond 2034; therefore, this I RP-based analysis reflects a 2034 retirement. Extending the analysis to 2035 would likely result in an increase in the cost difference. 1 Exhibit No. 6 Case No. IPC-E-16-24 T. Harvey, IPC Page 1 of 2 Appendix A Idaho Power Company Valmy Revenue Requirement Comparison 2025 or 2031-2034 Retirement Forecasted Fixed Costs and Total Power Supply Costs Discount Rate 6.74% Fixed Costs 2016 50,578 2017 48,627 2018 49,774 2019 50,410 2020 53,234 2021 52,812 2022 50,506 2023 51,054 2024 50,911 2025 51,204 2026 51,461 2027 51,478 2028 51,240 2029 51,060 2030 49,736 2031 48,160 2032 38,638 2033 37,136 2034 36,366 Total $ 924,384 NPV $522,715.36 Total NPV NPV difference for the period 2016-2034 $(000) 6.74% 6.74% Aurora Fixed Costs $ 293,380 58,943 $ 332,194 56,520 $ 347,073 57,236 $ 349,001 57,504 $ 330,816 60,062 $ 336,715 58,004 $ 343,726 53,712 $ 357,713 52,135 $ 398,496 50,129 $ 414,280 49,440 $ 426,509 $ 443,502 $ 477,128 $ 493,717 $ 511,211 $ 515,699 $ 530,706 $ 535,206 $ 563,041 $ 8,000,111 $ 553,684 $4,145,162.64 $397,341.99 $4,667,878.00 ($103,043) 2 6.74% Aurora $ 293,380 $ 332,194 $ 347,073 $ 349,001 $ 330,816 $ 336,715 $ 343,726 $ 357,713 $ 398,496 $ 414,280 $ 434,241 $ 450,235 $ 484,014 $ 500,986 $ 518,893 $ 523,324 $ 535,860 $ 538,971 $ 567,098 $ 8,057,016 $4,167,492.87 $4,564,834.86 Exhibit No. 6 Case No. IPC-E-16-24 T. Harvey, IPC Page 2 of 2