HomeMy WebLinkAbout20160823final_order_no_33575.pdfOffice of the Secretary Service Date August 23, 2016 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF IDAHO POWER ) COMPANY'S APPLICATION TO APPROVE ) CASE NO. IPC-E-16-17 THE SECOND AMENDMENT TO ITS FIRM ) ENERGY SALES AGREEMENT WITH ) RIVERSIDE HYDRO I, LLC FOR MORA ) ORDER NO. 33575 _D_R_O_P_H_Y_D_R_O __________ ) On August 12, 2016, Idaho Power Company filed an Application asking the Commission to approve the Second Amendment to its Firm Energy Sales Agreement (FESA) with Riverside Hydro I, LLC. The FESA is a contract under the Public Utility Regulatory Policies Act (PURPA) for generation from the Mora Drop hydro facility, a PURPA qualifying facility (QF). This Amendment changes the Net Energy Amount notification process, similar to the process that the Commission has approved for Idaho Power involving more than 20 other energy sales agreements. Idaho Power asked that the Commission approve its Application upon Staffs review and without further process. Application at 4. BACKGROUND The Commission approved Idaho Power's Agreement with Riverside in 2006. Order No. 30088. In 2014, the Commission approved the Company's First Amendment, which changed the definition of the Mid-Columbia Market Energy Cost in the Agreement consistent with a Commission-approved stipulation. Order Nos. 33184, 33053. Idaho Power and Riverside agreed to the Second Amendment on June 22, 2016. PROPOSED AMENDMENT In the Second Amendment, Idaho Power and Riverside propose a change in the Net Energy Amount notification process to allow Riverside "to adjust the 'Initial Year Monthly Net Energy Amounts' on a monthly, rather than quarterly, basis." Application at 3. Under the Amendment, Riverside "can submit future revisions on a monthly basis, with a minimum of 30 days' notice prior to the beginning of the next month, rather than once every three months." Id Idaho Power indicates that, with this change, Riverside "gains more clarity and flexibility in adjusting its estimated energy deliveries and Idaho Power maintains the stability in the estimates necessary for its planning and operation." Id. at 4. ORDER NO. 33575 Idaho Power notes that, since August 2014, the Commission has approved more than 20 FESAs/ESAs between Idaho Power and QFs that allow the QFs to change the Initial Year Monthly Net Energy Amounts on a monthly basis. Id at 2. Also, the Commission has approved FESA/ESA amendments similar to that here. Id., citing Order Nos. 33358, 33359. In Order No. 33102, the Commission stated, "we find that monthly, as opposed to quarterly, reporting of energy generation estimates is a reasonably negotiated term between the parties and not inconsistent with the Commission's [earlier] guidance and findings." Order No. 33102 at 6; Application at 3. STAFF RECOMMENDATION Given the limited scope of the Amendment, Staff recommended that the request be approved without further process. DISCUSSION AND FINDINGS Consistent with our prior Orders referenced herein, we find it reasonable to amend Idaho Power's FESA with Riverside by shortening the Net Energy Amount notification process to allow monthly rather than quarterly updates. We find that no further process is needed and thus approve the Amendment as proposed. ORDER IT IS HEREBY ORDERED that Idaho Power's Application to approve the Second Amendment to its Firm Energy Sales Agreement with Riverside Hydro I, LLC is approved without change or condition. THIS IS A FINAL ORDER. Any person interested in this Order may petition for reconsideration within twenty-one (21) days of the service date of this Order. Within seven (7) days after any person has petitioned for reconsideration, any other person may cross-petition for reconsideration. See Idaho Code § 61-626. ORDER NO. 33575 2 DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this ;2 3 d day of August 2016. PAULKJ , PRESIDENT PER, COMISSiONER ATTEST: Diane Holt Assistant Commission Secretary O:IPC-E-16-17 _djh ORDER NO. 33575 3