HomeMy WebLinkAbout20160830final_order_no_33570_errata.pdfBEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER
COMPANY'S APPLICATION TO MODIFY
OPTIONAL SCHEDULE 62, GREEN
ENERGY PURCHASE PROGRAM RIDER
)
) CASE NO. IPC-E-16-13
)
) ERRATA TO
) ORDER NO. 33570
-------------------)
Office of the Secretary
Service Date
August 30, 2016
On August 29, 2016, the Commission issued Order No. 33570. The following
change should be made to that Order:
Page 3, first Ordering paragraph:
READS:
"IT IS HEREBY ORDERED that Idaho Power's Application to modify the
Green Energy Purchase Program Rider is granted. The Revised Schedule 62
filed with the Commission on June 22, 2016, is approved, effective upon
issuance of this Order."
SHOULD READ:
"IT IS HEREBY ORDERED that Idaho Power's Application to modify the
Green Energy Purchase Program Rider is granted. The Revised Schedule 62
filed with the Commission on June 22, 2016, is approved, effective 60 davs
after the service date of this Order, as requested in the Application."
DATED at Boise, Idaho this
O:IPC-E-l 6-l 3_djh_Errata
day of August 2016.
J n D. Jewell
=sion Secretary