IN THE MATTER OF THE
APPLICATION OF IDAHO POWER
COMPANY TO UPDATE ITS WIND
INTEGRATION RATES AND
CHARGES.
Case No. IPC-E-13-22
AWEA AND RNP COMMENTS IN
SUPPORT OF MOTION TO DISMISS
li !l
Attorneyfor Renewoble Northwest Project and American Wind Energt Association
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
I. INTRODUCTION
Pursuant to Idaho Public Utilities Commission ("IPUC" or "Commission") Rules of
Procedure ("RP") 56 and 256, Renewable Northwest Project (*RNP") and American Wind
Energy Association ("AWEA") hereby file these Comments in support of the January 31,2014,
Motion to Dismiss the Application of Idatro Power Company ("Idaho Power" or the "Company")
to Update its Wind Integration Rates and Charges (the "Application") filed by Cold Springs
Windfarm, LLC, Desert Meadow Windfarm, LLC, Hammett Hill Windfarm, LLC, Mainline
Windfarm, LLC, Ryegrass Windfarm, LLC, Two Ponds Windfarm, LLC, Cassia Wind Farm
LLC, Hot Springs Windfarm, LLC, Bennett Creek Windfarm, LLC, Cassia Gulch Wind Park
LLC, Tuana Springs Energy, LLC, and High Mesa Energy, LLC (collectively, "Movants").
Specifically, RNP and AWEA (1) support Movants' Motion to Dismiss to the extent that it
argues for dismissal of Idaho Power's Application in its entirety , and (2) recommend that the
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS
Commission direct Staff to schedule a series of workshops for interested parties to confer with
Idaho Power on its wind integration rates, charges and methodologies prior to the Company
submitting any revised application that would affect the wind integration rates assessed against
any wind generator qualiffing facilities ("QFs") that may come online in the future.
II. BACKGROT]ND
Idaho Power's Application in this proceeding seeks to increase the wind integration rates
and charges imposed on both QFs with existing contractual legally enforceable obligations and
any future wind generator QFs. To accomplish this, Idaho Power's Application and
accompanying testimony sets forth three methods from which the Commission could choose to
implement wind integration charges. Movants are a group of wind-generator QFs, each of which
is a party to a Firm Energy Sales Agreement ("FESA") with Idaho Power that contains fixed
avoided cost rates for the duration of each FESA's 2}-year term. Although Movants' Motion to
Dismiss focuses on Method 3, all three of the methods are inconsistent with the Public Utility
Regulatory Policies Act of 1978 ("PURPA").
Movants advance several arguments in support of their Motion to Dismiss: (1) federal
law prohibits and preempts unilateral modification of QF contracts that contain fixed-price
avoided cost rates calculated at the time the QFs incurred a contractual legally enforceable
obligation; (2) Section 210(e) of PURPA and Section 292.602 of the Federal Energy Regulatory
Commission's ("FERC") regulations implementing PURPA preempt the entire field of ongoing
state regulation of wind QFs sized 30 MW and under; (3) Movants' FESAs do not allow Idatro
Power to unilaterally modiff the hxed avoided cost rates contained in those contracts, and
Movants have not consented to modiffing such rates via updates to the Company's wind
AWEA AND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS
integration charges; and (a) federal law preempts further administrative proceedings that would
subject Movants to the adjudicatory process of litigating the merits of Idaho Power's proposed
wind integration costs. Movants then recommend the following:
In order to ensure that Movants are not subjected to this preempted
burden, the Commission should dismiss Idaho Power's entire
Application and allow it to be re-filed without recommending
modification of existing contractual legally enforceable
obligations. Because Idaho Power's unlawful proposal is so
interwoven with the rest of its filing, dismissal of the entire
Application is warranted. However, in the alternative, the
Commission should dismiss and strike from the record the portions
of Idaho Power's Application and testimony that recommend that
the Commission alter the rates and terms in existing contractual
legally enforceable obligations.
III. COMMENTS
RNP and AWEA support Movants' recommendation that the Commission dismiss Idatro
Power's entire Application and allow it to be re-filed without proposing to modifu existing
contractual legally enforceable obligations. RNP and AWEA generally agree with the legal
rationale advanced by Movants in support of dismissing the Company's Application. In lieu of
reiterating those arguments, these Comments highlight some of the public policy bases that
support dismissal of Idaho Power's entire Application. These Comments also address why it is
not inthe public interest to dismiss and strike from the record only those portions of the
Application and testimony identified by Movants as applying to existing contractual legally
enforceable obligations. Instead, RNP and AWEA recommend that the Commission dismiss the
Application in its entirety and convene a series of workshops for interested parties to confer with
Idaho Power on its wind integration rates, charges and methodologies prior to the Company
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS
submitting a new application affecting the
have a legally enforceable obligation.
rates of wind QFs that currently do not
1. Dismissing the Company's Entire Application Is in the Public Interest.
Dismissing the Company's entire Application is in the public interest as it would send a
strong signal regarding the sanctity of contracts and the importance of fostering a business
climate that is conducive to new investments while also respecting existing investments.
Dismissing the Company's entire Application would serve the public interest by
reaffirming the importance of the sanctity of contracts, including Movants' FESAs. Movants'
Motion to Dismiss addresses the specific PURPA provisions and related FERC regulations that
require adherence to the terms of the contract or other legally enforceable obligation between a
QF and the purchasing utility; such terms include the avoided cost rate calculated at the time of
contracting. This principle of respecting the QFs' contracts has deeper roots than PURPA;
indeed, the sanctity of contracts is a cornerstone of American law that is reflected in numerous
legal opinions as well as the Idaho Constitution. Neither the Idaho Legislature nor state agencies
may infringe upon existing contracts. Allowing Idatro Power to advance an Application to
unilaterally amend the avoided cost rates reflected in existing QFs' contracts would constitute an
impermissible infringement upon such contracts.
Dismissing the Company's Application would also serve the public interest in that it
would emphasize the importance of cultivating a business climate that is conducive to
investment. For businesses to have the confidence to invest in Idaho, they must have some level
of certainty that their contracts will remain intact. Allowing Idaho Power to unilaterally amend
existing contracts does not offer business certainty to those that would invest in Idaho. Not only
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS
does Idaho Power's Application act as a deterrent to would-be investors, it also destabilizes those
who have already invested significant sums of money to develop projects in Idaho. As noted in
their Motion to Dismiss, Movants have already had to respond to several attempts by the
Company to diminish the value of their investments in the state, including the Company's recent
attempt to unilaterally amend PURPA contracts so that it would have a right to "economic
curtailment." Having to defend against these repeated attempts to encroach on existing contracts
is costly, time-consuming, and bad for business. Demonstrating the importance of adhering to
existing contracts would serve the public interest by supporting new and existing investments in
Idaho.
2. In Lieu of Partial Dismissal, the Commission Should Direct Idaho Power to
Collaborate with Interested Parties Before Re-filing its Application.
Dismissing only part of the Application and testimony would not accomplish the
objectives discussed in the previous section, and would suffer from some of the legal
deficiencies identified in Movants' Motion to Dismiss. Instead, RNP and AWEA encourage the
Commission to dismiss the entire Application and direct Staff to schedule a series of workshops
to address the issues raised in the Application and Wind Integration Study prior to Idaho Power
re-filing an application that would apply to new wind QFs.
As an alternative to dismissing the entire Application, Movants propose striking out
Method 3 from the Company's Application and testimony; however, Methods I and2 are also
inconsistent with PURPA. Method 3 poses the most apparent violation, as it would spread
increased integration costs equally across all PURPA generators-new and existing-thereby
raising the rates of existing QFs, in violation of their FESAs. The situation is more nuanced with
Methods I and2, but the flaws nonetheless exist. For example, Methods I and2 would change
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS 5
the avoided costs paid to future wind QFs based upon revenue shortfalls related to existing QFs'
contracts. Thus, even though Methods 1 and 2 purport to keep existing QFs whole, the
methodologies still link the integration costs that would be imposed on future QFs to the
"unrecovered" costs associated with existing QFs. However, in assessing integration costs on
new wind QFs, the Company's methodology should be limited to calculating the forward-going
incremental costs of integrating those new QFs-not the incremental costs associated with new
QFs plus the revenue shortfalls related to integrating any existing projects. Because Methods I
and2take the latter approach, removing existing QFs from the Application would not remedy
Idaho Power's conflating of ctrrent system costs with forward-going incremental costs. As a
result, dismissal of the Company's entire Application is waranted, as Idaho Power must
necessarily rethink its approach and file a new application that comports with PURPA.
Given the complexity and history, the issues raised in Idaho Power's Application would
be best addressed-at least in the first instance-through a series of workshops to be held prior
to the Company re-filing its application. This approach would have several benefits. First, it
would allow for brainstorming and collaboration toward a solution that is more palatable across a
wider range of stakeholders, as opposed to quarrelling over complex issues in an adversarial
setting. Second, it would allow interested parties to allocate time and resources on a more
voluntary basis, as opposed to the situation in this proceeding, in which parties whose contracts
are at risk of being unilaterally amended must participate to protect their interests. Third, it may
be a more efficient and cost-effective way to resolve the issues raised in this docket than going
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS
through a contested case.' Accordingly, RNP and AWEA request that the Commission provide
an opportunity, through a series of issue workshops, for Idatro Power and interested parties to
collaborate on the issues raised in the Company's Application.
TV. CONCLUSION
WHEREFORE, RNP and AWEA respectfully request that the Commission (l) grant
Movants' Motion to Dismiss Idaho Power's entire Application, and (2) direct Staffto schedule a
series of workshops to address the issues raised in the Application and Wind lntegration Study
prior to Idaho Power re-filing an application that would apply to only new wind QFs.
DATED this 7th day of February,zDl4
K&L Gates LLP
Teresa Hill
Attomey for RNP and AWEA
' RI.IP and AWEA requested a technical hearing in this case because we do not believe that the
issues can be adequately addressed with a Modified Procedure (as requested by the Company);
however, we believe that issue workshops outside of a contested case could be a more productive
way to discuss the issues that would otherwise be addressed in a formal proceeding through
discovery, parties' testimony, cross-examination, etc. In the event that the Commission does not
grant Movants' Motion to Dismiss, we continue to support the need for a technical hearing,
discovery, etc. in this proceeding.
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS 7
CERTIFICATE OF SERVICE
I hereby certify that on the Tthday of February,2014, a true and correct copy of the
foregoing RENEWABLE NORTHWEST PROJECT AND AMERICAN WIND ENERGY
ASSOCIATION COMMENTS IN SUPPORT OF MOTION TO DISMISS, Case No. IPC-E-I3-
22,was served by electronic mail and U.S. Mail, postage prepaid, to:
I
IDAHO POWER COMPANY:Donovan E. Walker
Idaho Power Company
l22l W. Idaho St. (83702)
P.O. Box 70
Boise,ID 83707-0070
Email : dwalker@.idahopower. com
dockets@idahopower. com
Michael J. Youngblood
Greg Said
Idaho Power Company
t22l w. Idaho St. (83702)
P.O. Box 70
Boise,ID 83707-0070
Email: myoungblood@idahopower.com
gsaid@idahopower.com
COMMISSION STAFf,':Kris Sasser
Deputy Attorney General
Idaho Public Utilities Commission
472 W. Washington (83702)
P.O. Box 83720
Boise, lD 83720-0074
Email: kris.sasser@puc.idaho. gov
IDAHO WINDS LLC:Dean J. Miller
McDevitt & Miller LLP
420W. Bannock Street
Boise,lD 83702
Email : i oe@mcdevitt-miller.com
Rick Koebbe, President
Idaho Winds, LLC
5420W. Wicher Road
Glenns Ferry,ID 83623
Email: rk@oowerworks.com
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS
SNAKE RIVER ALLIANCE:Ken Miller
Clean Energy Program Director
Snake River Alliance
Box 1731
Boise,ID 83701
Email: kmiller@snakeriveralliance.org
COLD SPRINGS WINDFARM, LLC;
DESERT MEADOW WINDFARM, LLC;
HAMMETT HILL WINDF'ARM, LLC;
MAINLINE WINDFARM, LLC;
RYEGRASS WINDFARM, LLC; ATID
TWO PONDS WINDFARM, LLC:
Peter J. Richardson
Richardson Adams, PLLC
515 N. 27th Street
Boise, lD 83702
Email : peter@richardsonadams.com
Benjamin G. Huang, Manager
c/o Mountain Air Projects
6000 N. Foxtail Way
Glenns Ferry, lD 83623
CASSIA WINDFARM LLC;
HOT SPRINGS WINDFARM LLC;
BEiYNETT CREEK WINDFARM LLC;
CASSIA GULCH WIND PARK, LLC;
TUANA SPRINGS ENERGY, LLC; AND
HIGH MESA ENERGY, LLC:
Gregory M. Adams
Richardson Adams, PLLC
515 N. 27th Street
Boise, lD 83702
Email: grreg@.richardsonadams.com
Paul Ackerman
Assistant General Counsel
Exelon Business Services Corporation
100 Constellation Way
Baltimore, MD 21202
ROCKLAND WIND FARM, LLC:Deborah E. Nelson
Preston N. Carter
Givens Purlsey LLP
601 W. Bannock Street (83702)
P.O. Box2720
Boise,lD 83701-2720
Email: den@ givenspursley.com
pre stoncarter@ givenspursley.com
9AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS
IDAHO WIND PARTNERS I, LLC:Deborah E. Nelson
Preston N. Carter
Givens Purlsey LLP
601 W. Bannock Steet (83702)
P.O.Box2720
Boise,lD 83701-2720
Email: den@ givenspursley.com
prestoncarter@ givenspursley.com
MEADOW CREEK PROJECT COMPAI\TY
LLC:
Deborah E. Nelson
Preston N. Carter
Givens Purlsey LLP
601 W. Bannock Street (83702)
P.O.Box2720
Boise, lD 83701-2720
Email: den@ givenspursley.com
prestoncarter@ givenspursley.com
DATED this 7th day of Februar5r, 2014.
- 14.fu
TERESA A. HILL
K&L GATES LLP
AWEAAND RNP COMMENTS IN SUPPORT OF MOTION TO DISMISS 10