HomeMy WebLinkAbout20151104final_order_no_33417.pdfOffice of the Secretary
Service Date
November 4,2015
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER )
COMPANY’S ANNUAL UPDATE TO LOAD )CASE NO.IPC-E-15-25
AND GAS FORECASTS AND LONG-TERM )
CONTRACTS FOR ITS INCREMENTAL )
COST INTEGRATED RESOURCE PLAN )ORDER NO.33417
AVOIDED COST METHODOLOGY )
________________________________________________________________________________________
)
Pursuant to the Public Utility Regulatory Policies Act of 1978 (PURPA)and the
implementing regulations of the Federal Energy Regulatory Commission (FERC),the Idaho
Public Utilities Commission (Commission)has approved an incremental cost Integrated
Resource Plan (IRP)methodology to calculate avoided cost rates paid to certain PURPA
qualifying facilities (QFs).The avoided cost rate is the purchase price paid to QFs for purchases
of QF energy and capacity.
In Order Nos.32697 and 32802,the Commission determined that the load forecast
and natural gas forecast inputs to the IRP avoided cost methodology should be updated annually
on October 15 of each year.The Commission stated
We find that,in order to maintain the most accurate and up-to-date reflection
of a utility’s true avoided cost,utilities must update fuel price forecasts and
load forecasts annually —between IRP filings....In addition,it is appropriate
to consider long-term contract commitments because of the potential effect
that such commitments have on a utility’s load and resource balance We
further find it appropriate to consider PURPA contracts that have terminated
or expired in each utility’s load and resource balance.
Order No.32697 at 22.
On October 15,2015,per the Commission’s directive,Idaho Power Company
submitted its annual updates for fuel prices and load forecasts.The Company also submitted
information regarding new and expiring contracts.
COMPLIANCE FILING
Idaho Power’s most recent load forecast from September 2015 shows,on average,a
slight decrease in Idaho Power customer loads when compared to the October 2014 load forecast
provided for the 2014 update,and approved by the Commission in Order No.33182 (Case No.
IPC-E-1 4-25).
ORDERNO.33417 1
As of October 15,2015,Idaho Power will update the natural gas price forecast within
the Incremental Cost IRP (ICIRP)avoided cost model to reflect the most recent U.S.Energy
Information Administration (EIA)natural gas price forecast,published on April 14,2015.The
October 2015 gas forecast is the nominal ETA forecast for Henry Hub’.It indicates,on average,
a slight increase in the average annual natural gas forecast prices over the next 20 years,
compared to the ETA 2014 natural gas price forecast used in the ICIRP avoided cost model from
the previous update.
Idaho Power currently has three non-PURPA,long-term power purchase agreements:
Elkhorn Valley Wind (101 megawatts (MW)),Raft River Geothermal (13 MW),and Neal Hot
Springs Geothermal (22 MW).Idaho Power currently has 140 contracts with PURPA QF
projects with a total nameplate capacity of 1,232 MW.Included in the signed contracts are nine
new Oregon solar QF contracts totaling 69 MW.New contracts,terminated or expired contracts,
as well as new contract pricing,are all included in the ICIRP model on a continuous basis.
STAFF REVIEW
Staff reviewed the Company’s forecast and contract updates.Staff reported that the
load and gas price forecasts submitted by Idaho Power reflect the Company’s most current
estimates,and were prepared consistent with the methods used in the Company’s IRP.Staff
maintained that the load and gas price forecasts and the long-term contract changes submitted by
the Company comply with the requirements of Order Nos.32697 and 32802.Staff
recommended that the Commission accept the forecasts and contract changes without further
process.
DISCUSSION AND FINDINGS
The Commission has jurisdiction over Idaho Power and the issues raised in this
matter under Title 61 of the Idaho Code and PURPA.The Commission has authority under
PURPA and FERC regulations to set avoided costs,to order electric utilities to enter into fixed-
term obligations for the purchase of energy from QFs,and to implement FERC rules.Also,the
Commission is empowered to resolve complaints between QFs and utilities and to approve QF
contracts.
The Henry Hub is a natural gas delivery point near Erath,Louisiana,and the confluence of many interstate and
intrastate natural gas pipelines.See Hershey v.Energy Transfer Partners,L.P.,610 F.3d 239,242 (5th Cir.2010).
The price of natural gas at the Henry Hub is a commonly-used gas price index.
ORDERNO.33417
Pursuant to this authority,we have reviewed and considered the filings of record in
this case.We find that Idaho Power’s filing complies with the directives issued by this
Commission in Order Nos.32697 and 32802.Based on our review of the totality of the updates,
we accept the updated inputs to Idaho Power’s IRP avoided cost calculation for filing.
ORDER
IT IS HEREBY ORDERED that Idaho Power’s annual update to its load and gas
price forecast and long-term contract status for purposes of its incremental cost IRP methodology
are accepted,effective October 15,2015.
THIS IS A FINAL ORDER.Any person interested in this Order may petition for
reconsideration within twenty-one (21)days of the service date of this Order.Within seven (7)
days after any person has petitioned for reconsideration,any other person may cross-petition for
reconsideration.See Idaho Code §6 1-626.
DONE by Order of the Idaho Public Utilities Commission at Boise,Idaho this
day of November 2015.
MARSHA H.SMITH,COMMISSIONER
SlONER
ATTEST:
JEewe4’
mmission Secretary
0:IPC-E-15-25dh
ORDER NO.33417 3