HomeMy WebLinkAbout20150602final_order_no_33309.pdfOffice ofthe Secretary
Service Date
June 2,2015
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER )
COMPANY’S APPLICATION TO APPROVE )CASE NO.IPC-E-15-07
OR REJECT ITS ENERGY SALES )
AGREEMENT WITH THE IDAHO )ORDER NO.33309
DEPARTMENT OF WATER RESOURCES )
On March 31,2015,Idaho Power Company flied an Application asking the
Commission to approve or reject its Energy Sales Agreement (Agreement or ESA)with the
Idaho Department of Water Resources (IDWR).Under the proposed Agreement,IDWR would
sell,and Idaho Power would purchase,electric power generated by the Pristine Springs #1 hydro
project (Facility)near Jerome,Idaho.On April 14,2015,the Commission issued a Notice of
Application and Notice of Modified Procedure,setting a 21-day comment period.Commission
Staff was the only party to file written comments and the Company did not file a reply.As
outlined below,we approve the Agreement.
BACKGROUND
The Facility is currently selling power to Idaho Power pursuant to the terms and
conditions of various Commission orders and the Public Utility Regulatory Policies Act
(PURPA).That Act requires electric utilities to purchase electric power from “qualifying
facilities”(QFs)at rates approved by the applicable state regulatory agency —in Idaho,this
Commission.16 U.S.C.§824a-3;Idaho Power v.Idaho PUC,155 Idaho 780,789,316 P.3d
1278,1287 (2013).The purchase or “avoided cost”rate shall not exceed the “incremental cost”
to the utility,defined as the cost of energy which,“but for the purchase from [the QF],such
utility would generate or purchase from another source.”16 U.S.C.§824a-3(d);18 C.F.R.§
292.10 1(6)(defining “avoided cost”).
The Facility is a QF under PURPA and has a nameplate rating of 125 kilowatts (kW).
Application at 4.This Commission approved the Facility’s existing 10-year Agreement with
Idaho Power in April 2005.Order No.29766.That Agreement expired April 30,2015.
Application at 2.
THE APPLICATION
Idaho Power asks the Commission to approve or reject its new Agreement with
IDWR.The new ESA is for five years.Application at 2.Idaho Power states that the parties
ORDER NO.33309 1
entered into the Agreement “pursuant to the terms and conditions of various Commission orders
applicable to this replacement PURPA QF ESA for non-seasonal hydro projects.”Id.at 3 (see
Order Nos.32697.32737.32802.and 32804.cited in Application).Specifically,the ESA
provides for “non-levelized,non-seasonal hydro published avoided cost rates,”and energy
deliveries of less than 1 0 average megawatts (aMW).Id.at 4.Idaho Power also asserts the ESA
“contains revised terms and conditions”that were recently approved by the Commission in Case
Nos.IPC-E-14-06.IPC-E-14-07,and IPC-E-14-12.Id.at 5.These terms include references to
the Intercontinental Exchange (ICE)index and formula,delay liquidated damages and delay
security,and IDWR’s ownership of renewable energy credits (RECs),among other provisions.
Id.
According to Idaho Power,the new Agreement satisfies FERC requirements
regarding execution of a Generation Interconnection Agreement,designation as a network
resource,and administration of Idaho Power’s Open Access Transmission Tariff (OATT).Id.at
6.The Facility’s Scheduled First Energy Date is May 1,2015.Id.at 4.The Agreement will
become effective only upon the Commission’s approval and finding that all payments made by
Idaho Power to IDWR for purchases of energy are “allowed as prudently incurred expenses for
ratemaking purposes.”Id.at 6-7.Idaho Power requested that,if its Application is approved,
such approval be effective May 1,2015,to avoid a lapse between the existing and replacement
ESAs.Id.at 7.
STAFF COMMENTS
Staff reviewed the ESA and determined the proposed rates are correct.Staff
Comments at 3.Staff noted that,because the project received capacity payments in its prior
agreement,the rates in the replacement contract include capacity payments for the full term of
the proposed ESA,consistent with Order Nos.32697,32737,and 32871.Id.Staff further
confirmed that all other terms and conditions in the Agreement are consistent with prior
Commission Orders.Id.Accordingly,Staff recommended the Commission approve all of the
Agreement’s terms and conditions and declare that all payments made by Idaho Power to IDWR
for purchase of energy be allowed as prudently incurred expenses for ratemaking purposes.Id.
FINDINGS AND CONCLUSIONS
The Idaho Public Utilities Commission has jurisdiction over Idaho Power,an electric
utility,and the issues raised in this matter under the authority and power granted it under Title 61
ORDER NO.33309 2
of the Idaho Code and PURPA.The Commission has authority under PURPA and Federal
Energy Regulatory Commission (FERC)regulations to set avoided costs,to order electric
utilities to enter into fixed-term obligations for the purchase of energy from QFs,and to
implement FERC rules.
The Commission has reviewed the record in this case,including the Application,the
replacement Agreement,and the comments and recommendations of Commission Staff.We find
that IDWR’s Facility is qualified to receive the non-levelized published avoided cost rates
contained in the Agreement.We further find that the proposed Agreement contains acceptable
contract provisions consistent with PURPA,FERC regulations,and this Commission’s prior
Orders.We find it reasonable to allow payments made under the Agreement as prudently
incurred expenses for ratemaking purposes.Finally,because the ESA utilizes published avoided
cost rates,we find it reasonable to allow for a May 1,2015 effective date.However,we
admonish the parties to submit agreements for approval early enough to allow the Commission
adequate time for review without the necessity of approving an effective date that has already
passed.
ORDER
IT IS HEREBY ORDERED that the March 26,2015 Energy Sales Agreement
between Idaho Power Company and the Idaho Department of Water Resources for a five-year
term is approved without change or condition.We further declare that all payments made by
Idaho Power to IDWR for purchases of energy will be allowed as prudently incurred expenses
for ratemaking purposes.
THIS IS A FINAL ORDER.Any person interested in this Order may petition for
reconsideration within twenty-one (21)days of the service date of this Order.Within seven (7)
days after any person has petitioned for reconsideration,any other person may cross-petition for
reconsideration.See Idaho Code §6 1-626.
ORDER NO.33309 3
DONE by Order of the Idaho Public Utilities Commission at Boise,Idaho this
day of June 2015.
)4
PAUL KJELLANIR,PRESIDENT
N\
MACK A.REDFORD,COMMISSIONER
1LL-
KR NE RAPER,COMMISSIONER
ATTEST:
Jin D.Jewel(J
fmmission Secretary
O:IPC-E-I 5-O7dh2
ORDER NO.33309 4