HomeMy WebLinkAbout20140724Comments.pdfKRISTINE A. SASSER DEPUTY ATTORNEY GENERAL IDAHO PUBLIC UTILITIES COMMISSION PO BOX 83720 BOISE, IDAHO 83720-0074 (208) 334-03s7 BAR NO. 6618 Street Address for Express Mail: 472W, WASHINGTON BOISE, IDAHO 83702-5918 Attorney for the Commission Staff IN THE MATTER OF THE APPLICATION OF IDAHO POWER COMPANY F'OR APPROVAL OR REJECTION OF AN ENERGY SALES AGREEMENT WITH EIGHTMILE HYDRO CORPORATION FOR THE SALE AND PURCHASE OF ELECTRIC ENERGY FROM THE EIGHTMILE HYDRO PROJECT. REC il \,'[: n ?0ilr JUL 2t+ Pt{ 2: l0 tDAli i i' ji.Liil uT I Lt Ti IS {]Oi,i r,! l$S lCl.l BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC.E-I4.I2 COMMENTS OF THE COMMISSION STAFF COMES NOW the Staff of the Idaho Public Utilities Commission, by and through its Attorney of record, Kristine A. Sasser, Deputy Attorney General, and in response to the Notice of Application and Notice of Modified Procedure issued in Order No. 33063 on June 26,2014, in Case No. IPC-E-14-12, submits the following comments. BACKGROUND On May 27,2014, Idaho Power Company filed an Application requesting that the Commission accept or reject an Agreement between Idaho Power and Eightmile Hydro Corporation (Eightmile Hydro), for the sale and purchase of electric energy generated by the Eightmile Hydro Project. On May 5, 2014,Idaho Power and Eightmile Hydro entered into an Agreement pursuant to the terms and conditions of various Commission Orders applicable to PURPA agreements for non-seasonal hydro projects. Idaho Power states that Eightmile Hydro proposes to operate and maintain a 360 kilowatt (kW) non-seasonal hydro energy facility to be STAFF COMMENTS JULY 24,2014 located near Leadore, Idaho. The Company maintains that the project will be a qualified facility (QF) under the applicable provisions of the Public Utility Regulatory Policies Act (PURPA). Under the terms of the Agreement, Eightmile Hydro elected to contract with Idaho Power for a2l-year terrn using the non-levelized published avoided cost rates as currently established by the Commission in Order No. 32817 for energy deliveries of less than 10 average MW (aMW). Eightmile Hydro has selected August 30, 2014, as the project's Scheduled Operation Date. Various requirements have been placed upon the project in order for Idaho Power to accept energy deliveries from this facility. Idaho Power will monitor compliance with these requirements throughout the term of the Agreement. The Agreement provides that all applicable interconnection charges and monthly operational or maintenance charges under Schedule 72 \vill be assessed to Eightmile Hydro. A Schedule 72 Generator Interconnection Agreement (GIA) between Eightmile Hydro and Idaho Power was executed on December 4,2013. Article 21 of the Agreement provides that the PPA will not become effective until the Commission has approved all terms and conditions and declared that all payments Idaho Power makes to Eightmile Hydro for purchases of energy will be allowed as prudently incurred expenses for ratemaking purposes. STAFF ANALYSIS Idaho Power explains that the recent hydro agreements are the first hydro-based agreements submitted for approval "that contain revised terms and conditions subsequent to the Commission's final and reconsideration orders from Case No. GNR-E-11-03. As such, the form of the [Agreement] has several terms and conditions that vary from previously approved agreements in order to comply with the Commission's recent orders." Application at 4. In addition, Idaho Power and Eightmile Hydro also agreed to changes in some standard provisions that the parties propose for Commission approval. Discussed below are each of the significant differences between provisions in this Agreement and previous PURPA contracts for hydro projects. Revised Provisions for Entitlement to Firm Enerry Rates In Case No. IPC-E-04-08/10, Idaho Power proposed a performance band to firm up QF power and make it more predictable and reliable. The Company contended that by providing STAFF COMMENTS JULY 24,2014 economic incentives for QF developers to more accurately estimate the amount of firm energy it will deliver each month, the Company hoped to encourage developers to deliver firm rather than non-firm energy. Obtaining better estimates of the monthly amounts of firm energy to be provided, Idaho Power contended, will increase the Company's ability to predict when QF generation will be available and will improve the Company's ability to integrate QF resources into its resource planning and acquisition processes as firm resources. By including the firming provisions in the QF contracts, the Company stated that it is attempting to more closely align the firmness of the energy purchases under the QF contracts with firm energy purchases it makes every day in the wholesale market. To address Idaho Power's concerns, in Order No. 2963 the Commission adopted provisions for a901110 percent performance band in order for QFs to be entitled to hrm energy rates. Under the adopted provisions, monthly QF deliveries of energy in excess of 110 percent of scheduled "net energy" receive only 85 percent of the market price, or the contract rate, whichever is less. If the QF delivers less than 90 percent of the scheduled "net energy" amount, existing contracts provide for liquidated damages to compensate the utility and its customers for having to acquire energy to make up the shortfall. Under the 90/110 provisions, QFs must provide monthly generation estimates that, after the first year, can only be revised every three months. Moreover, QFs are not allowed to revise their generation estimates in the immediate three months of the forecast period. Table I below graphically illustrates how monthly generation estimates may be revised based on Order No. 29632. Table 1. Opportunities to Make an Estimate Revision According to Order No.29632 However, in this Energy Sales Agreement atl6.2.3,Idaho Power proposes to adopt a monthly, rather than quarterly timeframe for making revisions to generation estimates . Table 2 Month I 2 3 4 5 6 7 8 9 l0 lt l2 I 2 .,4 5 6 7 8 9 1"'opportunity at the end of month 3 allows revision for Julv. Aue. and Seo 2"d opportunity at the end of month 6 allows revision for Oct, Nov, and Dec 3no opportunity at the end of month 9 allows revision for Jan. Feb. and March STAFF COMMENTS JULY 24,2014 below, reproduced from the Agreement, illustrates the proposed schedule for revisions. In proposing the change, Idaho Power states that the Seller gains more clarity and flexibility in adjusting its estimated energy deliveries and Idaho Power maintains the stability in the estimates necessary for its planning and operation. Idaho Power admits that this change deviates from Order No.29632, but both the Company and the Seller propose Commission adoption of the change.l Table 2. New Method to Make Estimate Revisions Proposed by ldaho Power and Eightmile Hydro Notification Month Future Monthly Net Enerry Amounts Elisible to Be Revised November January and any future months December February and any future months January March and anv future months February Aoril and anv future months March Mav and any future months April June and anv future months Mav July and any future months June Ausust and anv future months Julv September and any future months Aueust October and any future months September November and any future months October December and anv future months In order to compare the two methods effectively, Staff created Table 3 to visually illustrate the new timeframes mentioned above. As can be seen, one major difference is the time lapse between the point when revision is made and the point when the estimates begin. Order No. 29632 requires a three-month gap, whereas the new method proposes a one-month gap. For example, the estimate for the month of April and later can be revised at the end of December under Order No. 29632; the estimate for the month of April and later can be revised at the end of February under the new method. I In its Application, Idaho Power stated that "with the proposed change, the Seller must still provide 12 months of estimated Net Energy Amounts, and still cannot revise the immediate three months of estimated Net Energy Amounts." However, in response to Staff production requests, Idaho Power admitted that this statement was incorrect and that the Agreement does, in fact, permit monthly revisions to estimated energy generation amounts. STAFF COMMENTS JULY 24,2014 Table 3. Opportunities to Make an Estimate Revision as Proposed by ldaho Power and Eightmile Hydro In the Application (See Page 5 and Page 6), Idaho Power admits that the new method allows revision to occur 'oon a monthly, rather than quarterly, basis" and that the change is 'ocontrary to" and "vades from" Order No. 29632. Because this new timeframe fails to comply with the Order, Staff recommends that the proposed Agreement be rejected by the Commission. Besides not complying with a prior Commission order, Staff opposes approval of a change to the 90/110 requirements in this case for the following additional reasons: l. There are already approximately 17 existing non-wind contracts that comply with Order No. 29632. These projects can only revise their generation estimates three months ahead of time. If the Commission approves a change in requirements for this Agreement, Staff would expect existing contracts to seek similar treatment or amendments. 2. The change of the timeframe is inconsistent with the reasoning of prior positions taken by Idaho Power and Staff in cases IPC-E-04-08 and IPC-E-04-10 in2004. Back then, Idaho Power proposed to allow QFs to revise their energy estimates three times during the first year of operation and every two years thereafter, because a two-year interval allows the Company to more easily integrate the QF resource into its biennial IRP planning process. Staff, on the other hand, recommended a six-month interval for the duration of the contract. The Commission adopted a three month interval stating, "The Commission finds it reasonable to provide more frequent opportunities to revise generation estimates than proposed by the Company. We find that the interest of the Company in planning for QF resources is better served if the generation forecast is a reliable estimate." (See Order No. 29632). Month I 2 J 4 5 6 7 8 9 l0 il t2 2 3 4 5 6 7 8 9 Notification made in Nov allows revision for Jan and any future months Notification made in Dec allows revision for Feb and any future months Notification made in Jan allows revision for March and any future months STAFF COMMENTS JULY 24,2014 3.Currently, as a standard to distinguish firm vs. non-firm, the 90/110 requirements are only utilized in non-wind projects, although wind projects with the 90/110 band do exist. For all practical purposes it applies mostly to hydro projects because there are so few other types of facilities (e.g., solar, biomass, cogeneration, landfill gas). Changing to monthly generation estimates would likely accommodate nearly all seasonal variations in hydro production, significantly diminishing the purpose of the 90/110 requirement. Staff believes there must continue to be some method to distinguish firm from non-firm energy for specific resources based on their operating characteristics. Integration charges have been adopted as a reasonable substitute to the 90/l l0 requirements for wind projects, and are now also being proposed for solar projects. Staff does not consider a monthly forecast revision schedule to be a reasonable substitute for a quarterly forecast revision schedule; instead, it is simply a much less rigorous requirement. Idaho Power's planning for generation from its own hydro facilities is still done on a quarterly or seasonal basis. Without a well-reasoned explanation of why monthly revisions are more beneficial for the project, the utility and the utility's ratepayers, it seems reasonable to apply the same planning standards to non-utility hydro facilities. Any change in the existing 90/110 forecasting requirements should apply to all three utilities. All interested persons and parties should have an opportunity to weigh in so the Commission can make a decision based on a fully developed record. In addition, any changes should apply not only to hydro, but also other resource types such as geothermal, cogeneration, biomass, and landfill gas. Therefore, a generic case under a separate docket may be a more appropriate procedure so that all utilities and interested parties could participate. Although the hydro facility in this contract might be too small to cause critical planning issues, several other contracts containing the same forecasting requirements were filed with the Commission concurrently with this matter. Because larger hydro facilities or other projects may have greater effects on the planning process if monthly forecasting is approved, Staff does not believe the Commission should consider this forecasting change on a case-by-case basis. 4. 5. 6. 7. STAFF COMMENTS JULY 24,2014 While not stated in its Application, the Company attempts to justiS the forecasting requirement by stating in production request responses that the three-month notification process has caused significant confusion with QFs and that, even though Idaho Power has worked with each project individually, the issue still persists. Idaho Power also states that by allowing the Seller to revise the net energy estimates on a more frequent basis, there is a greater chance that these estimates will be more reliable values that will be more useful in the Company's short-term planning process. Idaho Power further states that it does not believe that a change to a 30-day notification period will have a significant impact on the 12 months of estimated generation data or on its long-term planning process. Staff agrees that much of the justification provided by Idaho Power in response to Staff production requests has merit. Nonetheless, Staff believes that a change to the notification requirements associated with the 90/1 10 rules is more properly addressed in a separate proceeding that includes all of the potential stakeholders. Change to the Definition of Mid-Columbia Market Energy Cost The definition of "Mid-Columbia Market Energy Cost" has been changed to replace the reference to the Dow Jones index with reference to the Intercontinental Exchange (ICE) index and formula. This change is consistent with Order No. 33053 issued on June 10,2014 in Case No. IPC-E-13-252. Incorporation of Seasonal and Non-Seasonal Hydro Definitions and Rates The Agreement includes the addition of paragraphs 1.29, 1.38, L39,3.4 and 7.6 to incorporate definitions of "non-seasonal hydro facility" and "seasonal hydro facility" as well as o'seasonal hydro facility test periods"; to incorporate and maintain separate rates for seasonal and non-seasonal hydro projects; and to ensure that seasonal hydro projects perform within the requirements of generating 55 percent of their annual generation in the months of June, July and August. These additions are consistent with Order Nos. 32697 and32802 in Case No. GNR-E-I1- 03. 2 This change is relevant to the 90/l l0 performance requirement. STAFF COMMENTS JULY 24,2014 Under the terms of the Agreement, Eightmile Hydro elected to contract with Idaho Power for a 2O-year term using the non-levehzed published avoided cost rates as currently established by the Commission in Order No. 32817 for energy deliveries of less than l0 aMW. Staff has reviewed the rates contained in the Agreement and agrees that they are correct. Removal of Provisions for Delay Liquidated Damages Provisions providing for delay liquidated damages have been removed because of the Commission's adoption of the partial stipulation in Commission Order No. 32697. The stipulation required that delay damages be based on the difference between market rates at the time the QF fails to achieve its scheduled operation date and the avoided cost rates contained in the contract, rather than being based on a predetermined amount of liquidated damages specified at the time of contract signature. Similarly, termination damages are to be based on actual damages, rather than on a predetermined amount. The Agreement maintains provisions to provide for delay security, however, so that funds will be available to pay Idaho Power in the event delay or termination damages are actually incurred. Revised Provisions for Ownership of Renewable Enerry Credits The Agreement incorporates changes to Article VIII, "Environmental Attributes," to indicate that Eighmile Hydro owns all Environmental Attributes or Renewable Energy Credits/Certificates. This is consistent with Commission decisions in Case No. GNR-E-11-03 Order No. 32697 (December 18,2012), and Order No. 32802 (Order on Reconsideration; May 6, 2013). Those orders require that RECs for SAR based projects will be owned by the QF, and RECs produced by projects utilizing the IRP methodology will be equally apportioned between the utilities and the QF absent an alternative agreement by the parties. Other Minor Revisions The parties have revisednI2.4 relating to Scheduled Maintenance to give the Seller the option to claim maintenance will be scheduled at the same time each year with one notification, in order to eliminate the requirement of sending multiple notifications for maintenance that is scheduled for the same time every year. Several other minor revisions have been made to the Agreement in an attempt to add clarity. Staff believes all of the minor revisions are reasonable and appropriate. STAFF COMMENTS JULY 24,2014 RECOMMENDATIONS Staff recommends that the proposed Agreement be rejected because it fails to comply with the requirements of Order No. 29632. Staff does not believe that Idaho Power provided adequate justification to carve out an exception to a prior Commission order. However, Staff believes that a separate proceeding, in which all utilities and interested parties can actively participate, would provide a good opportunity to discuss the benefits and detriments of Idaho Power's proposed modifications to the existing generation estimate requirements. However, if the parties to the Agreement wish to revise its 90/110 requirements so as to be consistent with Order No.29632, Staff believes all other proposed changes from prior hydro contracts are acceptable. A. Sasser Attorney General Respectfully submitted this M'U day of July 2014. Deputy Technical Staff: Rick Sterling Yao Yin i:umisc:comments/ipce14. l2ksrps)ry comments STAFF COMMENTS JULY 24,2014 CERTIFICATE OF SERVICE I HEREBY CERTIFY THAT I HAVE THIS 24Th DAY OF JULY 2014, SERVED THE FOREGOING COMMENTS OF' THE COMMISSION STAFF, IN CASE NO. IPC.E-I4.I2,BY MAILING A COPY THEREOF, POSTAGE PREPAID, TO THE FOLLOWING: DONOVAN E. WALKER IDAHO POWER COMPANY P.O. BOX 70 BOISE,ID 83707 E-MAIL: dwalker@idahopower.com dockets@idahopower.com RANDY C. ALLPHIN TDAHO POWER COMPANY PO BOX 70 BOISE ID 83707-0070 E-MAIL : rallphin@idahopower.com CERTIFICATE OF SERVICE