HomeMy WebLinkAbout20140124notice_of_modified_procedure_order_no_32969.pdfOffice of the Secretary Service Date January 24,2014 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF IDAHO POWER )CASE NO.IPC-E-13-21 COMPANY’S APPLICATION FOR ) APPROVAL OF ITS CAPACITY )NOTICE OF DEFICIENCY PERIOD TO BE UTILIZED )MODIFIED PROCEDURE IN THE COMPANY’S SAR ) METHODOLOGY.)NOTICE OF SCHEDULING ) _______________________________ )ORDER NO.32969 In Order No.32697,the Commission directed that a case be initiated outside of each utility’s Integrated Resource Plan (IRP)filing for the establishment of the capacity deficiency period to be utilized in the utility’s SAR methodology.Idaho Power filed its 2013 JRP with the Commission on June 28,2013.On November 4.2013,Idaho Power filed this Application for approval of the capacity deficiency period to be utilized in the SAR avoided cost methodology. Idaho Power reports that its first deficit occurs in July 2021. On November 26,2013,the Commission issued a Notice of Application and set a deadline for intervention.Order No.32933.J.R.Simplot Company petitioned for,and was granted,intervention.Order No.32937.A Notice of Parties was issued on January 21,2014. NOTICE OF MODIFIED PROCEDURE YOU ARE HEREBY NOTIFIED that the parties have proposed that the case be processed by Modified Procedure.Further,the Commission has determined that the public interest may not require a formal hearing.Therefore,the matter will proceed under Modified Procedure pursuant to Rules 201 through 204 of the Idaho Public Utilities Commission’s Rules of Procedure,IDAPA 31.01.01.201-204.The Commission notes that Modified Procedure and written comments have proven to be an effective means for obtaining public input and participation. YOU ARE FURTHER NOTIFIED that the Application and workpapers have been filed with the Commission and are available for public inspection during regular business hours at the Commission offices.The Application is also available on the Commission’s web site at www.puc.idaho.gov.Click on the “File Room”tab at the top of the page,scroll down to “Open Electric Cases,”and then click on the case number as shown on the front of this document. NOTICE OF MODIFIED PROCEDURE NOTICE OF SCHEDULTNG ORDER NO.32969 1 YOU ARE FURTHER NOTIFIED that all proceedings in this case will be held pursuant to the Commission’s jurisdiction under Title 61 of the Idaho Code and that the Commission may enter any final order consistent with its authority under Title 61. YOU ARE FURTHER NOTIFIED that all proceedings in this matter will be conducted pursuant to the Commission’s Rules of Procedure,IDAPA 3 1.01.01.000,etseq. NOTICE OF SCHEDULING YOU ARE FURTHER NOTIFIED that,based on discussion and agreement between the parties,Staff proposed and the Commission adopts the following procedural schedule: February 28,2014 Comment deadline March 14,2014 Reply comment deadline The parties agree that best efforts will be made to answer discovery within 14 days,but no later than 21 days from the date of the discovery request. YOU ARE FURTHER NOTIFIED that all testimony and exhibits in Case No.IPC E-13-21 must comport with the requirements of Rule 231 and 267 of the Commission’s Rules of Procedure.IDAPA 31.01.01.231 and 267. YOU ARE FURTHER NOTIFIED that any person desiring to state a position on this Application may file a written comment in support or in opposition with the Commission no later than Friday,February 28,2014.The comment must contain a statement of reasons supporting the comment.Persons desiring a hearing must specifically request a hearing in their written comments.Written comments concerning this Application may be mailed to the Commission and Idaho Power at the addresses reflected below: Commission Secretary Donovan Walker Idaho Public Utilities Commission Idaho Power Company P0 Box 83720 P0 Box 70 Boise,ID 83720-0074 Boise,ID 83 707-0070 E-mail:dwalker@idahopower.com Street Address for Express Mail: Randy Allphin 472 W.Washington Street Tess Park Boise,ID 83702-59 18 Idaho Power Company P0 Box 70 Boise,ID 83 707-0070 E-mail:rallphin@idahopower.com tpark2(idahopower.com NOTICE OF MODIFIED PROCEDURE NOTICE OF SCHEDULING ORDER NO.32969 These comments should contain the case caption and case number shown on the first page of this document.Persons desiring to submit comments via e-mail may do so by accessing the Commission’s home page located at www.puc.idaho.gov.Click the ‘Case Comment or Question Form”under the “Consumers”tab,and complete the comment form using the case number as it appears on the front of this document.These comments must also be sent to Idaho Power at the e-mail addresses listed above. YOU ARE FURTHER NOTIFIED that if no written comments or protests are received within the deadline,the Commission may consider the matter on its merits and may enter its Order without a formal hearing.If comments or protests are filed within the deadline, the Commission will consider them and in its discretion may set the matter for hearing or may decide the matter and issue its Order based on the written positions before it.IDAPA 31.01.01.204. ORDER IT IS HEREBY ORDERED that this case be processed by Modified Procedure. IT IS FURTHER ORDERED that the parties adhere to the procedural schedule as set out in the body of this Order. NOTICE OF MODIFiED PROCEDURE NOTICE OF SCHEDULING ORDER NO.32969 3 DONE by Order of the Idaho Public Utilities Commission at Boise,Idaho this day of January 2014. 1 /1 J;fl/f PAUL KJELIADER,PRESIDENT N \\)(!\_ltO4J MACK A.REDFORD,COMMISSIONER 7,L;L i6i MARSHA H.SMITH,COMMISSIONER ATTEST: /1 A ‘1 1 / Jn D.JeweU mmission Secretary O:IPC-E-1 3-21ks2 NOTICE OF MODIFIED PROCEDURE NOTICE OF SCHEDULING ORDER NO.32969 4