June 2, 2016
VIA HAND DELIVERY
Jean D. Jewell, Secretary
ldaho Public Utilities Commission
472 West Washington Street
Boise, ldaho 83702
Re: Case No. IPC-E-13-16 - Selective Catalytic Reduction (SCR") Controls on Jim Bridger
Power Plant Units 3 and 4 - ldaho Power Company's 10th Quarterly Report
Dear Ms. Jewell:
In Order No. 32929, the ldaho Public Utilities Commission ("Commission') directed
ldaho Power Company ("Company") to submit quarterly reports updating the Commission
on any changes to environmental policy or regulations unti! such time as the Jim Bridger
Power Plant upgrades are installed and placed in service. The enclosed materials indicate
that the SCR on Unit 4 will be placed in service by December 31 ,2016.
Please note that the attachment to this report is commercially sensitive and if
disclosed freely could subject ldaho Power or its customers to risk of competitive
disadvantage or other business injury. Consequently, the attachment will be provided
separately to those parties that have signed the Protective Agreement in this matter. The
undersigned attorney, in accordance with RP 67, certifies that this monthly report contains
information that is a trade secret as described in lilaho Code S 74-101, et seq., and $ 48-
801, et seq., and as such is exempt from public inspection, examination, or copying.
Very truly yours,
oQf,Yl*r;*,*
Lisa D. Nordstrom
LDN:kkt
Enclosurecc: Service List
'1221 W. ldaho 5t. (83702)
PO. Box 70
Boise, lD 83707
rU*i-lC,r^;i-ti!ilJlSSlON
10th Quarterlv Reoort for the Jim Bridser Plant
Selective Catalvtic Reduction Uporade at Units 3 and 4
June 2. 2016
This quarterly report provides an update as to the current status of environmental policies or
regulations that are relevant to the construction of the Selective Catalytic Reduction ("SCR')
controls at the Jim Bridger Plant Units 3 and 4 ("Bridger Plant"), as wel! as a construction
progress update for the SCR installation project through May 1, 2016, and a schedule of major
construction milestones. Finally, a summary of actual project costs and a forecast of total
project costs as of March 31, 2016, is provided as a confidential attachment to this report.
Environmenta! Regula :
Clean Air Act Section 111(d) for Existino Power Plants
On October 23,2015, the final Clean Power Plan was published in the Federal Register and the
Environmenta! Protection Agency proposed a Federal lmplementation Plan.
On February 9, 2016, the U.S. Supreme Court issued orders staying the Clean Power Plan
pending resolution of challenges to the rule. The DC Circuit Court of Appeals set a litigation
schedule, with oral arguments scheduled for June 2,2016. On May 16, 2016, the DC Circuit
Court of Appeals ordered that the ora! arguments be rescheduled before the en banc court on
Tuesday, September 27,2016. Because an appeal of any decision made by the DC Circuit
Court is expected, the en banc review is likely to speed up the overall litigation process;
however, timing of the final outcome is difficult to predict.
Proiect Cost Update:
The tota! cost variance for the Unit 4 SCR remains relatively unchanged compared to last
quarter's report. Currently, the Unit 4 SCR is approximately $6.7 million under the original cost
estimate.
Gonstruction Proorc :
The SCR at Unit 3 was completed on-time and is currently operational; therefore, the
construction progress updates herein will be for Unit 4.
The following are updates on projects that were included as part of the Engineering,
Procurement and Construction contract (.EPC Contract") or individual projects identified as
separate expense categories in the budget.
As of May 1 , 2016,99.2 percent of the 3,031 tons of Unit 4 structural steels had been erected
and 84 percent of the Unit 4 SCR electrical work had been completed.
During a three-day spring outage, a large amount of electrical tie-in work was completed. A
substantial amount of cable pulls, electrical, and piping work has been accomplished this
quarter.
The large particle ash system downcomers has been installed. Insulation blankets are being
installed on the transfer conveyor. lnsulation work continues on the reactor and duct work.
PacifiCorp has received proposals/bids from contractors to perform the reinforcement work on
the air preheater, boiler, and extema! flue gas path. PacifiCorp is currently evaluating these
proposals for award.
PacifiCorp is working with its corporate environmental group to add aqueous ammonia, the
nitrogen oxides ("NOr') reduction reagent, to the list of permitted sources that can be disposed
of in the wastewater ponds at the plant.
Sc.hedule:
The project remains on schedule to comply with the required completion dates with the following
major milestones remaining :
o Unit 4 Fall Outage Start - September 3,2016. Unit 4 Mechanical Completion - November 3, 2016o Unit 4 Compliance Deadline - December 31 ,2016
ConcJusion:
The installation on the Unit 4 SCR controls at the Bridger Plant remains on schedule and under-
budget. Based on what is known today, the SCR investments continue to be the most cost-
effective means of ensuring that Units 3 and 4 comply with state and federa! emissions
regulations. Further, the Company continues to believe that the Bridger Plant SCR investments
represent the lowest cost and least risk option for serving future customer demands.
2
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on this 2d day of June 2016 t served a true and correct
copy of the within loth QUARTERLY REPORT FOR THE JIM BRIDGER SELECTIVE
CATALYTIC REDUCTION UPGMDE AT UNITS 3 AND 4, upon the following named
parties by the method indicated below, and addressed to the following:
Commission Staff
Don Howell
Deputy Attomey General
ldaho Public Utilities Commission
472 West Washington (83702)
P.O. Box 83720
Boise, ldaho 83720-007 4
lndustrial Customers of ldaho Power
Peter J. Richardson
Gregory M. Adams
RICHARDSON ADAMS, PLLC
515 North 27th Street (83702)
P.O. Box 7218
Boise, ldaho 83707
Dr. Don Reading
6070 Hill Road
Boise, ldaho 83703
ldaho Gonservation League
Benjamin J. Otto
ldaho Conservation League
710 North Sixth Street
Boise, ldaho 83702
Snake River Alliance
Dean J. Miller
McDEVITT & MILLER LLP
420 West Bannock Street (83702)
P.O. Box 2564
Boise, Idaho 83701
Ken Miller, Clean Energy Program Director
Snake River Alliance
P.O. Box 1731
Boise, ldaho 83701
X Hand Delivered
U.S. Mail
Ovemight Mail
FAXX Emai! don.howel!@puc.idaho.qov
Hand DeliveredX U.S. Mail
_Ovemight Mail
_FAXX Email peter@richardsonadams.com
qreq@richardsonadam s.com
_Hand Delivered
X U.S. Mail
_Ovemight Mail
_FAX
Email dreading@mindspring.com
_Hand DeliveredX U.S. Mai!
_Overnight Mail
-FAxX Email botto@idahoconservation.org
_Hand Delivered
X U.S. Mail
_Overnight Mail
_FAXX Email ioe@mcdevitt-miller.com
_Hand Delivered
X U.S. Mail
CERTIFICATE OF SERVICE
Ovemight Mail