HomeMy WebLinkAbout20140304SCR Bridger Update.pdfS!ffi*.
An IDACORP Company
LISA D. NORDSTROM
Lead Counsel
I nordstrom @idahooower.com
March 3,2014
VIA HAND DELIVERY
Jean D. Jewell, Secretary
ldaho Public Utilities Commission
472 West Washington Street
Boise, ldaho 83702
LDN:kkt
Enclosurescc: Service List
RA Dept files
Legalfiles
Tim Tatum
Kelley Noe
Re: Case No. IPC-E-13-16
Selective Catalytic Reduction ('SCR") Controls on Jim Bridger Units 3 and 4
Dear Ms. Jewel!:
ln Order No. 32929, the Commission directed ldaho Power Company
("Company") to submit quarterly reports updating the Commission on any changes to
environmental policy or regulations until such time as the Bridger upgrades are installed
and placed in service. While the project is still in an early stage of construction, the
enclosed materials indicate that the Company still expects the SCRs on Units 3 and 4
will be placed in service by December 31 , 2015, and December 31, 2016, respectively.
Please note that the attachment to this report is commercially sensitive and if
disclosed freely could subject ldaho Power or its customers to risk of competitive
disadvantage or other business injury. Consequently, the attachment will be provided
separately to those parties that have signed the Protective Agreement in this matter.
The undersigned attomey, in accordance with RP 233, certifies that this monthly report
contains information that is a trade secret or privileged or confidential as described in
ldaho Code S 9-340, et seq., and $ 48-801, et seq., and as such is exempt from public
inspection, examination, or copying.
Very truly yours,
Xn.e%^rl*.
Lisa D. Nordstrd'm
1221 W. ldaho 5t. (83702)
PO. Box 70
Boise, lD 83707
ldaho Power Companv's
Quarterlv Report for the Jim Bridser SCR Upsrade at Units 3 and 4
March 3.2014
This quarterly report provides an update as to the current status of environmental policies or
regulations that are relevant to the construction of the Selective Catalytic Reduction ('SCR")
controls at Jim Bridger Units 3 and 4. This report also provides a construction progress update
for the SCR installation project through February 15, 2014, and a schedule of major construction
milestones. Finally, a summary of actual project costs and a forecast of total project costs
through December 31,2013, are provided as a confidential attachment to this report.
Environmental Requlations Update:
Federal lmplementation Plan ("FlP") for Reoional Haze in Wvomino
On January 30, 2014, the Environmental Protection Agency ('EPA') published in the Federal
Register the approval of the Wyoming State lmplementation Plan ("SlP") for the installation of
SCRs on Jim Bridger Units 3 and 4 in 2015 and 2016, respectively. The final ruling also
affirmed the 0.07 emission limit for nitrogen oxides, resulting in no project scope changes. This
ruling is consistent with the installation dates and emission limits that were used for modeling
the economics of the SCR installation versus other alternatives in the Company's Coal Unit
Environmental Analysis. This final rule will become effective March 3,2014.
Clean Air Act Section 111(d)
By June 2014, the EPA is expected to release its draft proposal for performance standards for
carbon dioxide emissions from existing fossil fuel-fired power plants (Clean Air Act Section
111(d)). The final rule is expected by June 2015 with a deadline of June 2016 for the State
lmplementation Plans. lt is currently estimated that approval or disapproval, from the Federal
EPA, of the SlPs will occur in 2018.
Coal Combustion Residuals
ln 2012, various environmental groups filed a lawsuit (Appalachian Voices, et al. v. Jackson,
Case No. 1:12-00523) against the EPA seeking to compel the EPA to undertake action to
address the coal ash disposal regulations that were initially proposed in 2010 under the
Resource Conservation and Recovery Act ("RCRA'). The United States District Court for the
District of Columbia ordered the EPA to propose a date by which it would finalize revised coal
ash disposal rules. On January 29,2014, the EPA entered into a Consent Decree committing to
take final action by December 19, 2014, regarding EPA's proposed revision of RCRA Subtitle D
regulations pertaining to coal combustion residuals.
The updates provided above for the Clean Air Act Section 111(d) and Coal Combustion
Residuals are intended to provide the Commission with the timeframe in which regulatory action
by the States or EPA might occur. At this point, there has not been a change in these
environmental regulations or the rules governing National Ambient Air Quality Standards,
cooling water intakes or effluent guidelines that would warrant an update to the Company's
assumptions used in its Coal Unit EnvironmentalAnalysis.
Gonstruction Progress Update:
The project to install the SCR controls on Jim Bridger Units 3 and 4 is moving forward as
planned and is on schedule to meet the required completion dates. The following section
provides a high level description of the project activities to date.
Upon receiving a Certificate of Public Convenience and Necessity from the ldaho Public Utilities
Commission, ldaho Power Company issued its formal notice to support the issuance of a full
notice to proceed ('FNTP') on December 2, 2013, to PacifiCorp, its operating partner. A
coordination meeting was convened on December 19,2013, with the Babcock & Wilcox and
Perry Group (BWP or EPC Contractor) and certain subcontractors to review each
subcontractor's contract and scopes of work, review design drawings, discuss coordination
issues and schedule requirements, and to align on safety goals. Following that meeting, the
EPC Contractor's staff and subcontractors began mobilization to setup temporary facilities and
establish the site office trailer complex for construction.
Since the issuance of the FNTP, major procurement packages that were included as part of the
EPC contract were released for structural steel, fabricated plate for the SCR and flues, certain
major equipment, onsite nursing services, and construction trailers. Also, the design for the
safety vent stack relocation has been ongoing.
The SCR retrofit will require a micropile foundation due to the limited amount of space around
each unit. The initial micropile tests were unsuccessful. New locations and design parameters
for test piles have been identified by the EPC Contractor and testing is still being conducted.
For optimal performance of the SCR, the temperature of the gas entering the SCR must be at
least 600 degrees Fahrenheit. ldaho Power, PacifiCorp, and the EPC Contractor (Project
Team) are currently evaluating whether a low temperature economizer exit gas temperature
("EEGT') control system is needed at this time to achieve optimal long{erm performance of the
unit. The Project Team is analyzing the limited amount of time the unit operates at reduced
loads resulting in an exit gas temperature below the 600 degree threshold as compared to the
cost of installing the low temperature EEGT control system.
On January 21, 2014, PacifiCorp and the EPC Contractor finalized the Unit 4 induced draft fan
sizing. PacifiCorp agreed to the requirements for stress and the number of starts, and adjusted
the performance guarantees to accommodate the higher than expected required pressure rise.
A change in work order will be issued with the modified technical specification. There is no cost
change to the contract for this change in work.
On January 29, 2014, the Project Team's recommendation to proceed with the installation of a
bare tube base economizer was issued to the Jim Bridger plant boiler engineer. The bare tube
economizer was selected over a finned tube economizer, based on the estimated reduced
forced outages due to channeling erosion from fly ash around the fins. The cost of the bare
tube economizer from the selected provider was evaluated as the lowest cost option and met
the performance criteria.
On January 31 , 2014, the EPC Contractor issued a letter outlining work that could be
accomplished during a short outage on Unit 3 in the spring of 2014. Jim Bridger plant
management is currently reviewing the proposed work in conjunction with the length of the
outage to determine if the timing for the work would be appropriate.
Schedule:
Generally, the project remains on schedule with the following major milestones:
. Physical Flow Model Demonstration - March 2014o SCR Area Foundation lnstallation Complete - June 4,2014o Unit 3 Fall Outage Start - September 5, 2015o Unit 3 Mechanical Completion - November 5, 2015o Unit 3 Compliance deadline - December 31,2015o Unit 4 Fall Outage Start - September 3, 2016o Unit 4 Mechanical Completion - November 3, 2016o Unit 4 Compliance deadline - December 31,2016
Gonclusion:
At this point, there have been no material changes in environmental policies or regulations that
would warrant an update to the Company's assumptions used in its Coal Unit Environmental
Analysis supporting installation of SCR on Jim Bridger Units 3 and 4. The installation of SCR
controls at Jim Bridger Units 3 and 4 remains on schedule and under budget. The SCR
investments continue to be the most cost-effective means of ensuring that Units 3 and 4 comply
with state and federal emissions regulations. Further, the Company continues to believe that
the Jim Bridger SCR investments represent the lowest cost and least risk option for serving
future customer demands.
3
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on this 3d day of March 2014 I served a true and
correct copy of the within QUARTERLY REPORT FOR THE JIM BRIDGER SCR
UPGMDE AT UNITS 3 AND 4, upon the following named parties by the method
indicated below, and addressed to the following:
Gommission Staff
Kristine A. Sasser
Deputy Attomey General
ldaho Public Utilities Commission
472 West Washington (83702)
P.O. Box 83720
Boise, ldaho 83720-007 4
lndustrial Customerc of ldaho Power
Peter J. Richardson
Gregory M. Adams
RICHARDSON ADAMS, PLLC
515 North 27th Street(83702)
P.O. Box 7218
Boise, ldaho 83707
Dr. Don Reading
6070 Hill Road
Boise, ldaho 83703
ldaho Conservation League
Benjamin J. Otto
ldaho Conservation League
710 North Sixth Street
Boise, ldaho 83702
Snake River Alliance
Dean J. Miller
McDEVITT & MILLER LLP
420 West Bannock Street (83702)
P.O. Box 2564
Boise, ldaho 83701
Hand Delivered
X U.S. Mail
_Overnight Mail
_FAXX Email kris.sasser@puc.idaho.qov
Hand Delivered
U.S. Mail
Overnight Mail
FAXX Email peter@ richa rd so nada ms. com
qreo@richardsonadams. com
Hand Delivered
X U.S. Mail
_Ovemight Mail
_FAXX Email dreadino@mindsprinq.com
_Hand DeliveredX U.S. Mail
Overnight Mail
FAXX Email botto@idahoconservation.orq
_Hand Delivered
X U.S. Mail
Overnight Mail
FAXX Emai! ioe@mcdevitt-miller.com
CERTIFICATE OF SERVICE
Ken Miller, Clean Eneryy Program Director
Snake RiverAlliance
P.O. Box 1731
Boise, ldaho 83701
_Hand Delivered
X U.S. Mail
_Ovemight Mail
_FAXX Email kmiller@snaleriveralliance.orq
CERTIFICATE OF SERVICE