HomeMy WebLinkAbout20180813_cwh7jo.pdfDECISION MEMORANDUM
TO:COMMISSIONER KJELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
LEGAL
WORKING FILE
FROM:CHRIS HECHT
DATE:AUGUST 9,2019
SUBJECT:COMPLIANCE TARIFF FILING -IN THE MATTER OF THE
APPLICATION OF ROCKY MOUNTAIN POWER FOR AUTHORITY
TO MODIFY SCHEDULE NO.135 -NET METERING SERVICE;
CASE NO.PAC-E-19-03
On March 15,2019,Rocky Mountain Power filed an application requesting a
modification to its Electric Service Schedule No.135 -Net Metering,to allow customer to
transfer excess financial credits once per year between meters that are owned by the same
customer and located on the same or contiguous premises as the meter with excess financial
credits,as long as the meters are served by the same primary feeder and are on the same rate
schedule.
On July 3,2019,the Commission approvedthe proposed schedule with one modification:
For the purposes of Schedule 135,parcels shall be considered
contiguous if they share a common boundary or corner,and
includes parcels that would otherwise be considered contiguous but
are divided by a public right of way.
See Order No.34370.
On August 8,2019,the Company filed the revised sections of Service Schedule 135
(Sheet 135.2,Sheet 135.3 and Sheet 135.4).
DECISION MEMORANDUM l AUGUST 9,2019
STAFF RECOMMENDATION
Staff has reviewed the revised pages of Service Schedule 135 -Net Metering,and has
confirmed that the revisions comply with Order No.34370.Staff recommends approval of the
revisions submitted on August 8,2019.
COMMISSION DECISION
Does the Commission wish to approve the revisions to Service Schedule 135 -Net
Metering with the effective date of the Order,July 3,2019?
Chris Hecht
Udmemos/pac-e-19-03 Compliance Filing
DECISION MEMORANDUM 2 AUGUST 9,2019