Loading...
HomeMy WebLinkAbout20121114Attachments.pdfBEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 1 Article 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 FIRM ENERGY SALES AGREEMENT BETWEEN TITLE Definitions IDAHO POWER COMPANY AND NEW ENERGY TWO, LLC TABLE OF CONTENTS No Reliance on Idaho Power Warranties Conditions to Acceptance ofEnergy Term and Operation Date Purchase and Sale ofNet Energy Purchase Price and Method of Payment Environmental Attributes Facility and Interconnection Metering and Telemetry Records Operations Indemnification and Insurance Force Majeure Liability; Dedication Several Obligations Waiver Choice ofLaws and Venue Disputes and Default Governmental Authorization Commission Order Successors and Assigns Modification Taxes Notices Additional Terms and Conditions Severability Counterparts Entire Agreement Signatures Appendix A AppendixB AppendixC AppendixD FIRM ENERGY SALES AGREEMENT (10 aMW or Less) Project Name: Swager Farms Project Number: 31616130 THIS AGREEMENT, entered into on this 2. c.(tday of fhec..r 2010 between NEW ENERGY TWO, LLC, an Idaho limited liability company (Seller), and IDAHO POWER COMPANY, an Idaho corporation (Idaho Power), hereinafter sometimes referred to collectively as "Parties'' or individually as "Party." WITNESSETH: WHEREAS, SeHer will design, construct, own, maintain and operate an electric generation facility; and WHEREAS, Seller wishes to sell, and Idaho Power is willing to purchase, finn electric energy produced by the Seller's Facility. THEREFORE, In consideration of the mutual covenants and agreements hereinafter set forth, the Parties agree as follows: ARTICLE 1: DEFINITIONS As used in this Agreement and the appendices attached hereto, the following terms shall have the following meanings: 1.1 "Base Energy"-Monthly Net Energy less than 110% of the monthly Net Energy Amount as specified in paragraph 6.2 of this Agreement. 1.2 "Commission" -The Idaho Public Utilities Commission. 1.3 "Contract Year" -The period commencing each calendar year on the same calendar date as the Operation Date and ending 364 days thereafter. 1.4 "Delay Liquidated Damages"-Damages payable to Idaho Power as calculated in paragraph 5.3, 5.4, 5.5, 5.6 and 5.8. -1- 5/19/2010 1.5 "Delay Period"-All days past the Scheduled Operation Date until the Seller's Facility achieves the Operation Date. 1.6 "Delay Price"-The current month's Mid-Columbia Market Energy Cost minus the current month's All Hours Energy Price specified in paragraph 7.3 of this Agreement. If this calculation results in a value less than 0, the result of this calculation will be 0. 1. 7 "Designated Dispatch Facility" -Idaho Power's Systems Operations Group, or any subsequent group designated by Idaho Power. 1.8 "Facility"-That electric generation facility described in Appendix B of this Agreement. 1.9 "First Energy Date" -The day commencing at 00:01 hours, Mountain Time, following the day that Seller has satisfied the requirements of Article IV and the Seller begins delivering energy to Idaho Power's system at the Point of Delivery. 1.10 "Heavy Load Hours" -The daily hours beginning at 7:00 am, ending at 11 :00 pm Mountain Time, ( 16 hours) excluding all hours on all Sundays, New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving and Christmas. 1.11 "Inadvertent Energy" -Electric energy Seller does not intend to generate. Inadvertent energy is more particularly described in paragraph 7.5 ofthis Agreement. 1.12 "Interconnection Facilities"-All equipment specified in Schedule 72. 1.13 "Initial Capacity Determination" -The process by which Idaho Power confirms that under normal or average design conditions the Facility will generate at no more than 10 average MW per month and is therefore eligible to be paid the published rates in accordance with Commission Order No. 29632. 1.14 "Light Load Hours"-The daily hours beginning at 11:00 pm, ending at 7:00am Mountain Time (8 hours), plus all other hours on all Sundays, New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving and Christmas. 1.15 "Losses"-The loss of electrical energy expressed in kilowatt hours (kWh) occurring as a result of the transformation and transmission of energy between the point where the Facility's energy is metered and the point the Facility's energy is delivered to the Idaho Power electrical system. The loss calculation formula will be as specified in Appendix B of this Agreement. -2- 5/19/2010 1.16 "Market Energy Reference Price"-Eighty-five percent (85%) of the Mid-Columbia Market Energy Cost. 1.17 "Material Breach"-A Default (paragraph 19.2.1) subject to paragraph 19.2.2. 1.18 "Maximum Capacity Amount"-The maximum capacity (MW) ofthe Facility will be as specified in Appendix B of this Agreement. 1.19 "Metering Equipment" -All equipment specified in Schedule 72, this Agreement and any additional equipment specified in Appendix B required to measure, record and telemeter bi directional power flows between the Seller's electric generation plant and Idaho Power's system. 1.20 "Mid-Columbia Market Energy Cost" -The monthly weighted average of the daily on-peak and off­ peak Dow Jones Mid-Columbia Index (Dow Jones Mid-C Index) prices for non-firm energy. If the Dow Jones Mid-Columbia Index price is discontinued by the reporting agency, both Parties will mutually agree upon a replacement index, which is similar to the Dow Jones Mid-Columbia Index. The selected replacement index will be consistent with other similar agreements and a commonly used index by the electrical industry. 1.21 "Nameplate Capacity"-The full-load electrical quantities assigned by the designer to a generator and its prime mover or other piece of electrical equipment, such as transformers and circuit breakers, under standardized conditions, expressed in amperes, kilovolt-amperers, kilowatts, volts or other appropriate units. Usually indicated on a nameplate attached to the individual machine or device. 1.22 "Net Energy"-All of the electric energy produced by the Facility, less Station Use, less Losses, expressed in kilowatt hours (kWh). Subject to the terms of this Agreement, Seller commits to deliver all Net Energy to Idaho Power at the Point of Delivery for the full term of the Agreement. Net Energy does not include Inadvertent Energy. 1.23 "Operation Date"-The day commencing at 00:01 hours, Mountain Time, following the day that all requirements of paragraph 5.2 have been completed. 1.24 "Point of Delivery"-The location specified in Appendix B, where Idaho Power's and the Seller's electrical facilities are interconnected and the energy from this Facility is delivered to the Idaho Power electrical system. -3- 5/19/2010 1.25 "Prudent Electrical Practices" -Those practices, methods and equipment that are commonly and ordinarily used in electrical engineering and operations to operate electric equipment lawfully, safely, dependably, efficiently and economically. 1.26 "Scheduled Operation Date" -The date specified in Appendix B when Seller anticipates achieving the Operation Date. It is expected that the Scheduled Operation Date provided by the Seller shall be a reasonable estimate of the date that the Seller anticipates that the Seller's Facility shall achieve the Operation Date. 1.27 "Schedule 72"-Idaho Power's Tariff No 101, Schedule 72 or its successor schedules as approved by the Commission. The Seller shall be responsible to pay all costs of interconnection and integration of this Facility into the Idaho Power electrical system as specified within Schedule 72. 1.28 "Season"-The three periods identified in paragraph 6.2.1 ofthis Agreement. 1.29 "Special Facilities"-Additions or alterations of transmission and/or distribution lines and transformers as described in Schedule 72. 1.30 "Station Use"-Electric energy that is used to operate equipment that is auxiliary or otherwise related to the production of electricity by the Facility. 1.31 "Surplus Energy"-Is (1) Net Energy produced by the Seller's Facility and delivered to the Idaho Power electrical system during the month which exceeds 11 0% of the monthly Net Energy Amount for the corresponding month specified in paragraph 6.2. or (2) If the Net Energy produced by the Seller's Facility and delivered to the Idaho Power electrical system during the month is less than 90% of the monthly Net Energy Amount for the corresponding month specified in paragraph 6.2, then all Net Energy delivered by the Facility to the Idaho Power electrical system for that given month or (3) All Net Energy produced by the Seller's Facility and delivered by the Facility to the Idaho Power electrical system prior to the Operation Date. 1.32 "Total Cost of the Facility" -The total cost of structures, equipment and appurtenances. -4- 5119/2010 ARTICLE II: NO RELIANCE ON IDAHO POWER 2.1 Seller Independent Investigation -Seller warrants and represents to Idaho Power that in entering into this Agreement and the undertaking by Seller of the obligations set forth herein, Seller has investigated and determined that it is capable of performing hereunder and has not relied upon the advice, experience or expertise of Idaho Power in connection with the transactions contemplated by this Agreement. 2.2 Seller Independent Experts -All professionals or experts including, but not limited to, engineers, attorneys or accountants, that Seller may have consulted or relied on in undertaking the transactions contemplated by this Agreement have been solely those of Seller. ARTICLE III: WARRANTIES 3.1 No Warranty by Idaho Power-Any review, acceptance or failure to review Seller's design, specifications, equipment or facilities shall not be an endorsement or a confirmation by Idaho Power and Idaho Power makes no warranties, expressed or implied, regarding any aspect of Seller's design, specifications, equipment or facilities, including, but not limited to, safety, durability, reliability, strength, capacity, adequacy or economic feasibility. 3.2 Qualifying Facility Status-Seller warrants that the Facility is a "Qualifying Facility," as that term is used and defined in 18 CFR 292.201 et seq. After initial qualification, Seller will take such steps as may be required to maintain the Facility's Qualifying Facility status during the term of this Agreement and Seller's failure to maintain Qualifying Facility status will be a Material Breach of this Agreement. Idaho Power reserves the right to review the Facility's Qualifying Facility status and associated support and compliance documents at anytime during the term of this Agreement. ARTICLE IV: CONDITIONS TO ACCEPTANCE OF ENERGY 4.1 Prior to the First Energy Date and as a condition of Idaho Power's acceptance of deliveries of energy from the Seller under this Agreement, Seller shall: -5- 5/19/2010 4.1.1 Submit proof to Idaho Power that all licenses, permits or approvals necessary for Seller's operations have been obtained from applicable federal, state or local authorities, including, but not limited to, evidence of compliance with Subpart B, 18 CFR 292.201 et seq. as a certified Qualifying Facility. 4.1.2 Opinion of Counsel -Submit to Idaho Power an Opinion Letter signed by an attorney admitted to practice and in good standing in the State ofldaho providing an opinion that Seller's licenses, permits and approvals as set forth in paragraph 4.1.1 above are legally and validly issued, are held in the name of the Seller and, based on a reasonable independent review, counsel is of the opinion that Seller is in substantial compliance with said permits as of the date of the Opinion Letter. The Opinion Letter will be in a form acceptable to Idaho Power and will acknowledge that the attorney rendering the opinion understands that Idaho Power is relying on said opinion. Idaho Power's acceptance of the form will not be unreasonably withheld. The Opinion Letter will be governed by and shall be interpreted in accordance with the legal opinion accord of the American Bar Association Section ofBusiness Law (1991). 4.1.3 Initial Capacity Determination -Submit to Idaho Power such data as Idaho Power may reasonably require to perform the Initial Capacity Determination. Such data will include but not be limited to, Nameplate Capacity, equipment specifications, prime mover data, resource characteristics, normal and/or average operating design conditions and Station Use data. Upon receipt of this information, Idaho Power will review the provided data and if necessary, request additional data to complete the Initial Capacity Determination within a reasonable time. 4.1.3 .1 If the Maximum Capacity specified in Appendix B of this Agreement and the cumulative manufacture Nameplate Capacity rating of the individual generation units at this Facility is less than 10 MW. The Seller shall submit detailed, manufacturer, verifiable data of the Nameplate Capacity ratings of the actual individual generation units to be installed at this Facility. Upon verification by Idaho Power that the data provided establishes the combined Nameplate Capacity rating of the generation units to -6- 5119/2010 be installed at this Facility is less than 10 MW, it will be deemed that the Seller has satisfied the Initial Capacity Determination for this Facility. 4.1.4 Nameplate Capacity-Submit to Idaho Power manufacturer's and engineering documentation that establishes the Nameplate Capacity of each individual generation unit that is included within this entire Facility. Upon receipt of this data, Idaho Power shall review the provided data and determine if the Nameplate Capacity specified is reasonable based upon the manufacturer's specified generation ratings for the specific generation units. 4.1.5 Engineer's Certifications -Submit an executed Engineer's Certification of Design & Construction Adequacy and an Engineer's Certification of Operations and Maintenance (O&M) Policy as described in Commission Order No. 21690. These certificates will be in the form specified in Appendix C but may be modified to the extent necessary to recognize the different engineering disciplines providing the certificates. 4.1.6 Insurance -Submit written proof to Idaho Power of all insurance required in Article XIII. 4.1. 7 Interconnection-Provide written confirmation from Idaho Power's delivery business unit that Seller has satisfied all interconnection requirements. 4.1.8 Network Resource Designation-The Seller's Facility has been designated as a network resource capable of delivering firm energy up to the amount of the Maximum Capacity. 4.1.9 Written Acceptance-Request and obtain written confirmation from Idaho Power that all conditions to acceptance of energy have been fulfilled. Such written confirmation shall be provided within a commercially reasonable time following the Seller's request and will not be unreasonably withheld by Idaho Power. ARTICLE V: TERM AND OPERATION DATE 5.1 Term -Subject to the provisions of paragraph 5.2 below, this Agreement shall become effective on the date first written and shall continue in full force and effect for a period of 15 (not to exceed 20 years) Contract Years from the Operation Date. I ~ - 7- 5/19/2010 5.2 Operation Date-The Operation Date may occur only after the Facility has achieved all of the following: a) Achieved the First Energy Date. b) Commission approval of this Agreement in a form acceptable to Idaho Power has been received. c) Seller has demonstrated to Idaho Power's satisfaction that the Facility is complete and able to provide energy in a consistent, reliable and safe manner. d) Seller has requested an Operation Date from Idaho Power in a written format. e) Seller has received written confmnation from Idaho Power of the Operation Date. This confirmation will not be unreasonably withheld by Idaho Power. 5.3 Operation Date Delay -Seller shall cause the Facility to achieve the Operation Date on or before the Scheduled Operation Date. Delays in the interconnection and transmission network upgrade study, design and construction process that are not Force Majeure events accepted by both Parties, shall not prevent Delay Liquidated Damages from being due and owing as calculated in accordance with this Agreement. 5.3 .1 If the Operation Date occurs after the Scheduled Operation Date but on or prior to 90 days following the Scheduled Operation Date, Seller shall pay Idaho Power Delay Liquidated Damages calculated at the end of each calendar month after the Scheduled Operation Date as follows: Delay Liquidated Damages are equal to ((Current month's Initial Year Net Energy Amount as specified in paragraph 6.2.1 divided by the number of days in the current month) multiplied by the number of days in the Delay Period in the current month) multiplied by the current month's Delay Price. 5.3.2 If the Operation Date does not occur within ninety (90) days following the Scheduled Operation Date the Seller shall pay Idaho Power Delay Liquidated Damages, in addition to those provided in paragraph 5.3 .1, calculated as follows: Forty five dollars ($45) multiplied by the Maximum Capacity with the Maximum Capacity being measured in kW. 5.4 If Seller fails to achieve the Operation Date within ninety (90) days following the Scheduled Operation -8- 5/19/2010 Date, such failure will be a Material Breach and Idaho Power may terminate this Agreement at any time until the Seller cures the Material Breach. Additional Delay Liquidated Damages beyond those calculated in 5.3.1 and 5.3.2 will be calculated and payable using the Delay Liquidated Damage calculation described in 5.3 .1 above for all days exceeding 90 days past the Scheduled Operation Date until such time as the Seller cures this Material Breach or Idaho Power terminates this Agreement. 5.5 Seller shall pay Idaho Power any calculated Delay Damages or Delay Liquidated Damages within 7 days of when Idaho Power calculates and presents any Delay Damages or Delay Liquidated Damages billings to the Seller. Seller's failure to pay these damages within the specified time will be a Material Breach of this Agreement and Idaho Power shall draw funds from the Delay Security provided by the Seller in an amount equal to the calculated Delay Damages or Delay Liquidated Damages. 5.6 The Parties agree that the damages Idaho Power would incur due to delay in the Facility achieving the Operation Date on or before the Scheduled Operation Date would be difficult or impossible to predict with certainty, and that the Delay Liquidated Damages are an appropriate approximation of such damages. 5.7 Prior to the Seller executing this Agreement, the Seller shall have agreed to and executed a Letter of Understanding with Idaho Power that contains at minimum the following requirements: a) Seller has filed for interconnection and is in compliance with all payments and requirements of the interconnection process b) Seller has received and accepted an interconnection feasibility study for this Facility. c) Seller has provided all information required to enable Idaho Power to file an initial transmission capacity request. d) Results of the initial transmission capacity request are known and acceptable to the Seller. e) Seller acknowledges responsibility for all interconnection costs and any costs associated with acquiring adequate firm transmission capacity to enable the project to be classified as an Idaho Power firm network resource. -9- 5/19/2010 f) If the Facility is located outside of the Idaho Power service territory, in addition to the above requirements, the Seller must provide evidence that the Seller has acquired firm transmission capacity from all required transmitting entities to deliver the Facility's energy to an acceptable point of delivery on the Idaho Power electrical system. 5.8 Within thirty (30) days of the date of a final non-appealable order as specified in Article XXI approving this Agreement the Seller shall post liquid security ("Delay Security") in a form as described in Appendix D equal to or exceeding the amount calculated in paragraph 5. 8 .1. 5.8.1 Delay Security The greater of forty five ($45) multiplied by the Maximum Capacity with the Maximum Capacity being measured in kW or the sum of three month's estimated revenue. Where the estimated three months of revenue is the estimated revenue associated with the first three full months following the estimated Scheduled Operation Date, the estimated kWh of energy production as specified in paragraph 6.2.1 for those three months multiplied by the All Hours Energy Price specified in paragraph 7.3 for each ofthose three months. 5.8.1.1 In the event (a) Seller provides Idaho Power with certification that (1) a generation interconnection agreement specifying a schedule that will enable this Facility to achieve the Operation Date no later than the Scheduled Operation Date has been completed and the Seller has paid all required interconnection costs or (2) a generation interconnection agreement is substantially complete and all material costs of interconnection have been identified and agreed upon and the Seller is in compliance with all terms and conditions of the generation interconnection agreement, the Delay Security calculated in accordance with paragraph 5 .8.1 will be reduced by ten percent (1 0% ). 5.8.1.2 If the Seller has received a reduction in the calculated Delay Security as specified in paragraph 5.8.1.1 and subsequently (1) at Seller's request, the generation interconnection agreement specified in paragraph 5 .8.1.1 is revised and as a result the Facility will not achieve its Operation Date by the Scheduled Operation Date or (2) if the Seller does not maintain compliance with the generation interconnection agreement, -10- 5/19/2010 the full amount of the Delay Security as calculated in paragraph 5.8.1 will be subject to reinstatement and will be due and owing within 5 business days from the date Idaho Power requests reinstatement. Failure to timely reinstate the Delay Security will be a Material Breach of this Agreement. 5.8.2 Idaho Power shall release any remaining security posted hereunder after all calculated Delay Damages and/or Delay Liquidated Damages are paid in full to Idaho Power and the earlier of (1) 30 days after the Operation Date has been achieved or (2) 60 days after the Agreement has been terminated. ARTICLE VI: PURCHASE AND SALE OF NET ENERGY 6.1 Delivery and Acceptance of Net Energy -Except when either Party's performance 1s excused as provided herein, Idaho Power will purchase and Seller will sell all of the Net Energy to Idaho Power at the Point of Delivery. All Inadvertent Energy produced by the Facility will also be delivered by the Seller to Idaho Power at the Point of Delivery. At no time will the total amount of Net Energy and/ or Inadvertent Energy produced by the Facility and delivered by the Seller to the Point of Delivery exceed the Maximum Capacity Amount. 6.2 Net Energy Amounts -Seller intends to produce and deliver Net Energy in the following monthly amounts: -11- 5/19/2010 6.2.1 Initial Year Monthly Net Energy Amounts: Season 1 Season 2 Season 3 Month March April May July August November December June September October January February 648,000 648,000 648,000 648,000 648,000 648,000 648,000 648,000 648,000 648,000 648,000 648,000 6.2.2 Ongoing Monthly Net Energy Amounts -Seller shall initially provide Idaho Power with one year of monthly generation estimates (Initial Year Monthly Net Energy Amounts) and beginning at the end of month nine and every three months thereafter provide Idaho Power with an additional three months of forward generation estimates beyond those generation estimates previously provided. This information will be provided to Idaho Power by written notice in accordance with paragraph 25.1, no later than 5:00PM of the 51h day following the end of the previous month. If the Seller does not provide the Ongoing Monthly Net Energy Amounts in a timely manner, Idaho Power will use the most recent 3 months of the Initial Year Monthly Net Energy Amounts specified in paragraph 6.2.1 for the next 3 months of monthly Net Energy amounts. 6.2.3 Seller's Adjustment ofNet Energy Amount 6.2.3.1 No later than the Operation Date, by written notice given to Idaho Power in accordance with paragraph 25.1, the Seller may revise all of the previously provided Initial Year Monthly Net Energy Amounts. 6.2.3 .2 Beginning with the end of the 9th month after the Operation Date and at the end of every third month thereafter: ( 1) the Seller may not revise the immediate next three -12- 5/19/2010 months of previously provided Net Energy Amounts, (2) but by written notice given to Idaho Power in accordance with paragraph 25.1, no later than 5:00 PM of the 5111 day following the end of the previous month, the Seller may revise all other previously provided Net Energy Amounts. Failure to provide timely written notice of changed amounts will be deemed to be an election of no change. 6.2.4 Idaho Power Adjustment ofNet Energy Amount-Ifldaho Power is excused from accepting the Seller's Net Energy as specified in paragraph 12.2.1 or if the Seller declares a Suspension of Energy Deliveries as specified in paragraph 12.3.1 and the Seller's declared Suspension of Energy Deliveries is accepted by Idaho Power, the Net Energy Amount as specified in paragraph 6.2 for the specific month in which the reduction or suspension under paragraph 12.2.1 or 12.3.1 occurs will be reduced in accordance with the following: Where: NEA Current Month's Net Energy Amount (Paragraph 6.2) SGU a.) Ifldaho Power is excused from accepting the Seller's Net Energy as specified in paragraph 12.2.1 this value will be equal to the percentage of curtailment as specified by Idaho Power multiplied by the TGU as defined below. b.) If the Seller declares a Suspension of Energy Deliveries as specified in paragraph 12.3.1 this value will be the sum of the individual generation units size ratings as specified in Appendix B that are impacted by the circumstances causing the Seller to declare a Suspension of Energy Deliveries. TGU = Sum of all of the individual generator ratings of the generation units at this Facility as specified in Appendix B of this agreement. RSH TH = Actual hours the Facility's Net Energy deliveries were either reduced or suspended under paragraph 12.2.1 or 12.3.1 Actual total hours in the current month -13- 5119/2010 Resulting formula being: Adjusted Net Energy = NEA Amount _ ( ( X NEA ) X ( TGU TH This Adjusted Net Energy Amount will be used in applicable Surplus Energy calculations for only the specific month in which Idaho Power was excused from accepting the Seller's Net Energy or the Seller declared a Suspension ofEnergy. 6.3 Unless excused by an event of Force Majeure, Seller's failure to deliver Net Energy in any Contract Year in an amount equal to at least ten percent (10%) of the sum of the Initial Year Net Energy Amounts as specified in paragraph 6.2 shall constitute an event of default. ARTICLE VII: PURCHASE PRICE AND METHOD OF PAYMENT 7.1 Base Energy Heayy Load Purchase Price -For all Base Energy received during Heavy Load Hours, Idaho Power will pay the non-levelized energy price in accordance with Commission Order 30744, 30738 and adjusted in accordance with Commission Order 30415 for Heavy Load Hour Energy deliveries with seasonalization factors applied: Season 1 -(73.50 %) Season 2-(120.00 %) Season 3-(100.00 %) Year Mills/kWh Mills/kWh Mills/kWh 2010 57.98 94.67 78.89 2011 59.54 97.21 81.01 2012 61.22 99.95 83.29 2013 62.62 102.23 85.19 2014 64.05 104.57 87.14 2015 65.52 106.97 89.14 2016 67.10 109.55 91.29 2017 68.63 112.05 93.38 2018 70.29 114.77 95.64 2019 71.91 117.40 97.83 2020 73.56 120.10 100.08 2021 75.26 122.87 102.39 2022 76.99 125.70 104.75 2023 78.78 128.61 107.18 2024 80.60 131.59 109.66 2025 82.47 134.65 112.21 2026 84.75 138.37 115.31 2027 87.10 142.21 118.51 -14- 5/19/2010 2028 2029 2030 2031 89.53 92.03 94.60 96.69 146.17 150.25 154.45 157.85 121.81 125.21 128.71 131.55 7.2 Base Energy Light Load Purchase Price-For all Base Energy received during Light Load Hours, Idaho Power will pay the non-levelized energy price in accordance with Commission Order 3 07 44, 3 073 8 and adjusted in accordance with Commission Order 30415 for Light Load Hour Energy deliveries with seasonalization factors applied : Season 1 -(73.50 %) Season 2-(120.00 %) Season 3-(100.00 %) Year Mills/kWh Mills/kWh Mills/kWh 2010 52.63 85.93 71.61 2011 54.19 88.47 73.73 2012 55.87 91.21 76.01 2013 57.27 93.49 77.91 2014 58.70 95.83 79.86 2015 60.17 98.23 81.86 2016 61.75 100.81 84.01 2017 63.28 103.32 86.10 2018 64.94 106.03 88.36 2019 66.56 108.66 90.55 2020 68.21 111.36 92.80 2021 69.90 114.13 95.11 2022 71.64 116.97 97.47 2023 73.42 119.88 99.90 2024 75.25 122.86 102.38 2025 77.12 125.91 104.93 2026 79.40 129.64 108.03 2027 81.75 133.48 111.23 2028 84.18 137.43 114.53 2029 86.68 141.51 117.93 2030 89.25 145.71 121.43 2031 91.33 149.12 124.27 7.3 All Hours Energy Price-The price to be used in the calculation of the Surplus Energy Price and Delay Damage Price shall be the non-levelized energy price in accordance with Commission Order 30744 and 30738 with seasonalization factors applied: -15- 5/19/2010 Season 1 -(73.50 %) Season 2-(120.00 %) Season 3-(100.00 %) Year Mills/kWh Mills/kWh Mills/kWh 2010 55.60 90.78 75.65 2011 57.16 93.32 77.77 2012 58.84 96.06 80.05 2013 60.24 98.34 81.95 2014 61.67 100.68 83.90 2015 63.14 103.08 85.90 2016 64.72 105.66 88.05 2017 66.25 108.17 90.14 2018 67.91 110.88 92.40 2019 69.53 113.51 94.59 2020 71.18 116.21 96.84 2021 72.87 118.98 99.15 2022 74.61 121.82 101.51 2023 76.39 124.72 103.94 2024 78.22 127.71 106.42 2025 80.09 130.76 108.97 2026 82.37 134.49 112.07 2027 84.72 138.32 115.27 2028 87.15 142.28 118.57 2029 89.64 146.36 121.97 2030 92.22 150.56 125.47 2031 94.30 153.97 128.31 7.4 Surplus Energy Price-For all Surplus Energy, Idaho Power shall pay to the Seller the current month's Market Energy Reference Price or the All Hours Energy Price specified in paragraph 7.3, whichever is lower. 7.5 Inadvertent Energy- 7.5.1 Inadvertent Energy is electric energy produced by the Facility, expressed in kWh, which the Seller delivers to Idaho Power at the Point of Delivery that exceeds 10,000 kW multiplied by the hours in the specific month in which the energy was delivered. (For example January contains 744 hours. 744 hours times 10,000 kW = 7,440,000 kWh. Energy delivered in January in excess of7,440, 000 kWh in this example would be Inadvertent Energy.) 7.5.2 Although Seller intends to design and operate the Facility to generate no more than 10 average MW and therefore does not intend to generate Inadvertent Energy, Idaho Power -16- 5/19/2010 will accept Inadvertent Energy that does not exceed the Maximum Capacity Amount but will not purchase or pay for Inadvertent Energy. 7.6 Payment Due Date -Undisputed Energy payments, less any payments due to Idaho Power will be disbursed to the Seller within 30 days of the date which Idaho Power receives and accepts the documentation of the monthly Net Energy actually delivered to Idaho Power as specified in Appendix A. 7.7 Continuing Jurisdiction of the Commission .This Agreement is a special contract and, as such, the rates, terms and conditions contained in this Agreement will be construed in accordance with Idaho Power Company v. Idaho Public Utilities Commission and Afton Energy, Inc., 107 Idaho 781, 693 P.2d 427 (1984), Idaho Power Company v. Idaho Public Utilities Commission, 107 Idaho 1122, 695 P.2d 1 261 (1985), Afton Energy, Inc, v. Idaho Power Company, 111 Idaho 925, 729 P.2d 400 (1986), Section 210 of the Public Utilities Regulatory Policies Act of 1978 and 18 CFR §292.303-308 ARTICLE Vill: ENVIRONMENTAL ATTRIBUTES 8.1 Seller retains ownership under this Agreement of Green Tags and Renewable Energy Certificates (RECs ), or the equivalent environmental attributes, directly associated with the production of energy from the Seller's Facility sold to Idaho Power. ARTICLE IX: FACILITY AND INTERCONNECTION 9.1 Design of Facility-Seller will design, construct, install, own, operate and maintain the Facility and any Seller-owned Interconnection Facilities so as to allow safe and reliable generation and delivery of Net Energy and Inadvertent Energy to the Idaho Power Point of Delivery for the full term of the Agreement. ARTICLE X: METERING AND TELEMETRY 10.1 Metering-Idaho Power shall, for the account of Seller, provide, install, and maintain Metering Equipment to be located at a mutually agreed upon location to record and measure power flows to Idaho Power in accordance with this Agreement and Schedule 72. The Metering Equipment will be at the -17- 5/19/2010 location and the type required to measure, record and report the Facility's Net Energy, Station Use, Inadvertent Energy and maximum energy deliveries (kW) at the Point of Delivery in a manner to provide Idaho Power adequate energy measurement data to administer this Agreement and to integrate this Facility's energy production into the Idaho Power electrical system. 10.2 Telemetry-Idaho Power will install, operate and maintain at Seller's expense communications and telemetry equipment which will be capable of providing Idaho Power with continuous instantaneous telemetry of Seller's Net Energy and Inadvertent Energy produced and delivered to the Idaho Power Point of Delivery to Idaho Power's Designated Dispatch Facility. ARTICLE XI-RECORDS 11.1 Maintenance of Records-Seller shall maintain at the Facility or such other location mutually acceptable to the Parties adequate total generation, Net Energy, Station Use, Inadvertent Energy and maximum generation (kW) records in a form and content acceptable to Idaho Power. 11.2 Inspection -Either Party, after reasonable notice to the other Party, shall have the right, during normal business hours, to inspect and audit any or all generation, Net Energy, Station Use, Inadvertent Energy and maximum generation (kW) records pertaining to the Seller's Facility. ARTICLE XII: OPERATIONS 12 .1 Communications -Idaho Power and the Seller shall maintain appropriate operating communications through Idaho Power's Designated Dispatch Facility in accordance with Appendix A of this Agreement. 12 .2 Energy Acceptance - 12.2.1 Idaho Power shall be excused from accepting and paying for Net Energy or accepting Inadvertent Energy which would have otherwise been produced by the Facility and delivered by the Seller to the Point of Delivery, if it is prevented from doing so by an event of Force Majeure, or temporary disconnection of the Facility in accordance with Schedule 72. If, for reasons other than an event of Force Majeure, a temporary disconnection under Schedule 72 exceeds twenty (20) days, beginning with the twenty-first day of such interruption, curtailment -18- 5/19/2010 or reduction, Seller will be deemed to be delivering Net Energy at a rate equivalent to the pro rata daily average of the amounts specified for the applicable month in paragraph 6.2. Idaho Power will notifY Seller when the interruption, curtailment or reduction is terminated. 12.2.2 If, in the reasonable opinion ofldaho Power, Seller's operation of the Facility or Interconnection Facilities is unsafe or may otherwise adversely affect Idaho Power's equipment, personnel or service to its customers, Idaho Power may temporarily disconnect the Facility from Idaho Power's transmission/distribution system as specified within Schedule 72 or take such other reasonable steps as Idaho Power deems appropriate. 12.2.3 Under no circumstances will the Seller deliver Net Energy and/or Inadvertent Energy from the Facility to the Point of Delivery in an amount that exceeds the Maximum Capacity Amount. Seller's failure to limit deliveries to the Maximum Capacity Amount will be a Material Bre~ch of this Agreement. 12.2.4 If Idaho Power is unable to accept the energy from this Facility and is not excused from accepting the Facility's energy, Idaho Power's damages shall be limited to only the value of the estimated energy that Idaho Power was unable to accept. Idaho Power will have no responsibility to pay for any other costs, lost revenue or consequential damages the Facility may mcur. 12.3 Seller DeclaJ'ecl Suspension ofEnergy Deliveries 12.3.1 If the Seller's Facility experiences a forced outage due to equipment failure which is not caused by an event of Force Majeure or by neglect, disrepair or lack of adequate preventative maintenance of the Seller's Facility, Seller may, after giving notice as provided in paragraph 12.3.2 below, temporarily suspend all deliveries ofNet Energy to Idaho Power from the Facility or from individual generation unit(s) within the Facility impacted by the forced outage for a period of not less than 48 hours to correct the forced outage condition ("Declared Suspension of Energy Deliveries"). The Seller's Declared Suspension of Energy Deliveries will begin at the start of the next full hour following the Seller's telephone notification as specified in paragraph 12.3.2 and will continue for the time as specified (not less than 48 hours) in the written -19- 5/19/2010 notification provided by the Seller. In the month(s) in which the Declared Suspension of Energy occurred, the Net Energy Amount will be adjusted as specified in paragraph 6.2.4. 12.3.2 If the Seller desires to initiate a Declared Suspension of Energy Deliveries as provided in paragraph 12.3.1, the Seller will notify the Designated Dispatch Facility by telephone. The beginning hour of the Declared Suspension of Energy Deliveries will be at the earliest the next full hour after making telephone contact with Idaho Power. The Seller will, within 24 hours after the telephone contact, provide Idaho Power a written notice in accordance with XXIV that will contain the beginning hour and duration of the Declared Suspension of Energy Deliveries and a description of the conditions that caused the Seller to initiate a Declared Suspension of Energy Deliveries. Idaho Power will review the documentation provided by the Seller to determine Idaho Power's acceptance of the described forced outage as qualifying for a Declared Suspension of Energy Deliveries as specified in paragraph 12.3.1. Idaho Power's acceptance of the Seller's forced outage as an acceptable forced outage will be based upon the clear documentation provided by the Seller that the forced outage is not due do an event of Force Majeure or by neglect, disrepair or lack of adequate preventative maintenance of the Seller's Facility. 12.4 Scheduled Maintenance -On or before January 31 of each calendar year, Seller shall submit a written proposed maintenance schedule of significant Facility maintenance for that calendar year and Idaho Power and Seller shall mutually agree as to the acceptability of the proposed schedule. The Parties determination as to the acceptability of the Seller's timetable for scheduled maintenance will take into consideration Prudent Electrical Practices, Idaho Power system requirements and the Seller's preferred schedule. Neither Party shall unreasonably withhold acceptance of the proposed maintenance schedule. 12.5 Maintenance Coordination -The Seller and Idaho Power shall, to the extent practical, coordinate their respective line and Facility maintenance schedules such that they occur simultaneously. 12.6 Contact Prior to Curtailment -Idaho Power will make a reasonable attempt to contact the Seller prior to exercising its rights to interrupt interconnection or curtail deliveries from the Seller's Facility. Seller understands that in the case of emergency circumstances, real time operations of the electrical system, -20- 5/19/2010 and/or unplanned events Idaho Power may not be able to provide notice to the Seller prior to interruption, curtailment, or reduction of electrical energy deliveries to Idaho Power. ARTICLE XIII: INDEMNIFICATION AND INSURANCE 13.1 Indemnification -Each Party shall agree to hold harmless and to indemnify the other Party, its officers, agents, affiliates, subsidiaries, parent company and employees against all loss, damage, expense and liability to third persons for injury to or death of person or injury to property, proximately caused by the indemnifying Party's (a) construction, ownership, operation or maintenance of, or by failure of, any of such Party's works or facilities used in connection with this Agreement or (b) negligent or intentional acts, errors or omissions. The indemnifying Party shall, on the other Party's request, defend any suit asserting a claim covered by this indemnity. The indemnifying Party shall pay all documented costs, including reasonable attorney fees that may be incurred by the other Party in enforcing this indemnity. 13.2 Insurance-During the term of this Agreement, Seller shall secure and continuously carry the following insurance coverage: 13.2.1 Comprehensive General Liability Insurance for both bodily injury and property damage with limits equal to $1,000,000, each occurrence, combined single limit. The deductible for such insurance shall be consistent with current Insurance Industry Utility practices for similar property. 13.2.2 The above insurance coverage shall be placed with an insurance company with an A.M. Best Company rating of A-or better and shall include: (a) An endorsement naming Idaho Power as an additional insured and loss payee as applicable; and (b) A provision stating that such policy shall not be canceled or the limits of liability reduced without sixty (60) days' prior written notice to Idaho Power. 13.3 Seller to Provide Certificate of Insurance -As required in paragraph 4.1.5 herein and annually thereafter, Seller shall furnish Idaho Power a certificate of insurance, together with the endorsements required therein, evidencing the coverage as set forth above. -21- 5/19/2010 13.4 Seller to Notify Idaho Power of Loss of Coverage -If the insurance coverage required by paragraph 13.2 shall lapse for any reason, Seller will immediately notify Idaho Power in writing. The notice will advise Idaho Power of the specific reason for the lapse and the steps Seller is taking to reinstate the coverage. Failure to provide this notice and to expeditiously reinstate or replace the coverage will constitute a Material Breach of this Agreement. ARTICLE XIV: FORCE MAJEURE 14.1 As used in this Agreement, "Force Majeure" or "an event of Force Majeure" means any cause beyond the control of the Seller or of Idaho Power which, despite the exercise of due diligence, such Party is unable to prevent or overcome. Force Majeure includes, but is not limited to, acts of God, fire, flood, storms, wars, hostilities, civil strife, strikes and other labor disturbances, earthquakes, fires, lightning, epidemics, sabotage, or changes in law or regulation occurring after the effective date, which, by the exercise of reasonable foresight such party could not reasonably have been expected to avoid and by the exercise of due diligence, it shall be unable to overcome. If either Party is rendered wholly or in part unable to perform its obligations under this Agreement because of an event of Force Majeure, both Parties shall be excused from whatever performance is affected by the event of Force Majeure, provided that: (1) The non-performing Party shall, as soon as is reasonably possible after the occurrence of the Force Majeure, give the other Party written notice describing the particulars of the occurrence. (2) The suspension of performance shall be of no greater scope and of no longer duration than is required by the event of Force Majeure. (3) No obligations of either Party which arose before the occurrence causing the suspension of performance and which could and should have been fully performed before such occurrence shall be excused as a result of such occurrence. -22- 5/19/2010 ARTICLE XV: LIABILITY; DEDICATION 15.1 Limitation of Liability. Nothing in this Agreement shall be construed to create any duty to, any standard of care with reference to, or any liability to any person not a Party to this Agreement. Neither party shall be liable to the other for any indirect, special, consequential, nor punitive damages, except as expressly authorized by this Agreement. Consequential damages will include, but not be limited to, the value of renewable energy certificates and, ifthe Facility is fueled by gas produced by an anaerobic digester system, any diminution or loss of anaerobic activity due to the inability ofldaho Power to accept energy from the Facility. 15.2 Dedication. No undertaking by one Party to the other under any provision of this Agreement shall constitute the dedication of that Party's system or any portion thereof to the Party or the public or affect the status of Idaho Power as an independent public utility corporation or Seller as an independent individual or entity. ARTICLE XVI: SEVERAL OBLIGATIONS 16.1 Except where specifically stated in this Agreement to be otherwise, the duties, obligations and liabilities of the Parties are intended to be several and not joint or collective. Nothing contained in this Agreement shall ever be construed to create an association, trust, partnership or joint venture or impose a trust or partnership duty, obligation or liability on or with regard to either Party. Each Party shall be individually and severally liable for its own obligations under this Agreement. ARTICLE XVII: WAIVER 17.1 Any waiver at any time by either Party of its rights with respect to a default under this Agreement or with respect to any other matters arising in connection with this Agreement shall not be deemed a waiver with respect to any subsequent default or other matter. -23- 5/19/2010 ARTICLE XVlll: CHOICE OF LAWS Al\TD VENUE 18.1 This Agreement shall be construed and interpreted in accordance with the laws of the State of Idaho without reference to its choice of law provisions. 18.2 Venue for any litigation arising out of or related to this Agreement will lie in the District Court of the Fourth Judicial District ofldaho in and for the County of Ada. ARTICLE XIX: DISPUTES AND DEFAULT 19.1 Disputes -All disputes related to or arising under this Agreement, including, but not limited to, the interpretation of the terms and conditions of this Agreement, will be submitted to the Commission for resolution. 19.2 Notice ofDefault 19.2.1 Defaults. If either Party fails to perform any of the terms or conditions of this Agreement (an "event of default"), the nondefaulting Party shall cause notice in writing to be given to the defaulting Party, specifying the manner in which such default occurred. If the defaulting Party shall fail to cure such default within the sixty (60) days after service of such notice, or if the defaulting Party reasonably demonstrates to the other Party that the default can be cured within a commercially reasonable time but not within such sixty (60) day period and then fails to diligently pursue such cure, then, the nondefaulting Party may, at its option, terminate this Agreement and/or pursue its legal or equitable remedies. 19.2.2 Material Breaches -The notice and cure provisions in paragraph 19.2.1 do not apply to defaults identified in this Agreement as Material Breaches. Material Breaches must be cured as expeditiously as possible following occurrence of the breach. 19.3 Security for Performance -Prior to the Operation Date and thereafter for the full term of this Agreement, Seller will provide Idaho Power with the following: 19.3.1 Insurance -Evidence of compliance with the provisions of paragraph 13.2. If Seller fails to comply, such failure will be a Material Breach and may only be cured by Seller supplying evidence that the required insurance coverage has been replaced or reinstated; -24- 5/19/2010 19.3.2 19.3.3 Engineer's Certifications-Every three (3) years after the Operation Date, Seller will supply Idaho Power with a Certification of Ongoing Operations and Maintenance (O&M) from a Registered Professional Engineer licensed in the State of Idaho, which Certification of Ongoing 0 & M shall be in the form specified in Appendix C. Seller's failure to supply the required certificate will be an event of default. Such a default may only be cured by Seller providing the required certificate; and Licenses and Permits -During the full term of this Agreement, Seller shall maintain compliance with all permits and licenses described in paragraph 4.1.1 of this Agreement. In addition, Seller will supply Idaho Power with copies of any new or additional pennits or licenses. At least every fifth Contract Year, Seller will update the documentation described in Paragraph 4.1.1. If at any time Seller fails to maintain compliance with the permits and licenses described in paragraph 4.1.1 or to provide the documentation required by this paragraph, such failure will be an event of default and may only be cured by Seller submitting to Idaho Power evidence of compliance from the permitting agency. ARTICLE XX: GOVERNMENTAL A UTIIORrZATION 20.1 This Agreement is subject to the jurisdiction of those governmental agencies having control over either Party of this Agreement. ARTICLE XXI: COMMISSION ORDER 21.1 This Agreement shall become finally effective upon the Commission's approval of all terms and provisions hereof without change or condition and declaration that all payments to be made to Seller hereunder shall be allowed as prudently incurred expenses for ratemaking purposes. ARTICLE XXII: SUCCESSORS AND ASSIGNS 22.1 This Agreement and all of the terms and provisions hereof shall be binding upon and inure to the benefit of the respective successors and assigns of the Parties hereto, except that no assignment hereof by either -25- 5/19/2010 Party shall become effective without the written consent of both Parties being first obtained. Such consent shall not be unreasonably withheld. Notwithstanding the foregoing, any party which Idaho Power may consolidate, or into which it may merge, or to which it may convey or transfer substantially all of its electric utility assets, shall automatically, without further act, and without need of consent or approval by the Seller, succeed to all of Idaho Power's rights, obligations and interests under this Agreement. This article shall not prevent a financing entity with recorded or secured rights from exercising all rights and remedies available to it under law or contract. Idaho Power shall have the right to be notified by the financing entity that it is exercising such rights or remedies. ARTICLE XXIII: MODIFICATION 23 .1 No modification to this Agreement shall be valid unless it is in writing and signed by both Parties and subsequently approved by the Commission. ARTICLE XXIV: TAXES 24.1 Each Party shall pay before delinquency all taxes and other governmental charges which, if failed to be paid when due, could result in a lien upon the Facility or the Interconnection Facilities. ARTICLE XXV: NOTICES 25.1 All written notices under this Agreement shall be directed as follows and shall be considered delivered when faxed, e-mailed and confirmed with deposit in the U.S. Mail, first-class, postage prepaid, as follows: -26- 5/19/2010 To Seller: To Idaho Power: Original document to: Laura Knothe, PE New Energy Two, LLC 8720 Vic Lane Middleton ID 83644 Telephone: Cell: FAX: (208) 890-8783 (208) 585-9016 E-mail: laura@thenewenergycompany.com Original document to: Vice President, Power Supply Idaho Power Company POBox 70 Boise, Idaho 83707 Email: LGgrow@idahopower.com Copy of document to: Cogeneration and Small Power Production Idaho Power Company PO Box 70 Boise, Idaho 83 707 E-mail: rallphin@idahopower.com Either Party may change the contact person and/or address information listed above, by providing written notice from an authorized person representing the Party. ARTICLE XXVI: ADDITIONAL TERMS AND CONDITIONS 26.1 This Agreement includes the following appendices, which are attached hereto and included by reference: Appendix A AppendixB Appendix C AppendixD Generation Scheduling and Reporting Facility and Point of Delivery Engineer's Certifications Forms ofLiquid Security -27- 5/19/2010 ARTICLE XXVII: SEVERABILITY 27.1 The invalidity or unenforceability of any term or provision of this Agreement shaH not affect the validity or enforceability of any other tenns or provisions and this Agreement shall be construed in all other respects as if the invalid or unenforceable term or provision were omitted. ARTICLE XXVTII: COUNTERPARTS 28.1 This Agreement may be executed in two or more counterparts, each of which shall be deemed an miginal but all of which together shall constitute one and the same instrument. ARTICLE XXlX: ENTIRE AGREEMENT 29.1 This Agreement constitutes the entire Agreement of the Parties concerning the subject matter hereof and supersedes all prior or contemporaneous oral or written agreements between the Parties concerning the subject matter hereof. IN WITNESS WHEREOF, The Parties hereto have caused this Agreement to be executed in their respective names on the dates set forth below: Idaho Power Company New Energy Two, LLC By {firsn LL tkuJ By ~ Lisa A Grow Laura Knothc, PE Sr. Vice President, Power Supply Dated 5· 2'-l ·tO Dated 5 J 2--l[to "Idaho Power" "Seller" -28- 5/19/2010 APPENDIX A A -1 MONTHLY POWER PRODUCTION AND SWITCHING REPORT At the end of each month the following required documentation will be submitted to: Idaho Power Company Attn: Cogeneration and Small Power Production POBox 70 Boise, Idaho 83707 The meter readings required on this report will be the readings on the Idaho Power Meter Equipment measuring the Facility's total energy production and Station Usage delivered to Idaho Power and the maximum generated energy (kW) as recorded on the Metering Equipment and/or any other required energy measurements to adequately administer this Agreement. This document shall be the document to enable Idaho Power to begin the energy payment calculation and payment process. The meter readings on this report shall not be used to calculate the actual payment, but instead will be a check of the automated meter reading information that will be gathered as described in item A-2 below: -29- 5/19/2010 Idaho Power Company Cogeneration and Small Power Production MONTHLY POWER PRODUCTION AND SWITCHING REPORT Project Name Address City Meter Number: End of Month kWh Meter Reading: Beginning of Month kWh Meter: Difference: Times Meter Constant: kWh for the Month: Metered Demand: Breaker Opening Record * Breaker O~ening Reason Codes 1 Lack of Adequate Prime Mover 2 Forced Outage of Facility 3 Disturbance of IPCo System 4 Scheduled Maintenance 5 Testing of Protection Systems 6 Cause Unknown 7 Other (Explain) State * Facility Out~ut Month Reason Zip Station Usage Year Project Number: Phone Number: Station Usage Metered Maximum Generation kW Net Generation Breaker Closing Record I hereby certify that the above meter readings are true and correct as of Midnight on the last day of the above month and that the switching record is accurate and complete as required by the Firm Energy Sales Agreement to which I am a Party. Signature Date -30- 5/19/2010 A-2 AUTOMATED METER READING COLLECTION PROCESS Monthly, Idaho Power will use the provided Metering and Telemetry equipment and processes to collect the meter reading information from the Idaho Power provided Metering Equipment that measures the Net Energy and energy delivered to supply Station Use for the Facility recorded at 12:00 AM (Midnight) of the last day of the month .. The meter information collected will include but not be limited to energy production, Station Use, the maximum generated power (kW) and any other required energy measurements to adequately administer this Agreement. A-3 ROUTINE REPORTING Once the Facility has achieved its Operation Date and has operated in a reliable and consistent manner for a reasonable period of time, the Parties may mutually agree to modify this Routine Reporting requirement. Idaho Power Contact Information Daily Energy Production Reporting Call daily by 10 a.m., 1-800-356-4328 or 1-800-635-1093 and leave the following information: • Project Identification -Project Name and Project Number • Current Meter Reading • Estimated Generation for the current day • Estimated Generation for the next day Planned and Unplanned Project outages Call 1-800-345-1319 and leave the following information: • Project Identification-Project Name and Project Number • Approximate time outage occurred • Estimated day and time of project coming back online -31- 5/19/2010 Seller's Contact Information 24-Hour Project Operational Contact Name: Telephone Number: Cell Phone: Jay Kesting (208) 94 7-4519 (208) 559-4244 Project On-site Contact information Name: Telephone Number: Kurt Standley (208) 280-1166 -32- 5/19/2010 APPENDIXB FACILITY AND POINT OF DELIVERY Project Name: Swager Farms Project Number: 31616130 B-1 DESCRIPTION OF FACILITY (Must include the Nameplate Capacity rating and VAR capability (both leading and lagging) of all generation units to be included in the Facility.) The facility consists of an anaerobic digester, gen sets and waste handling equipment. The total nameplate capacity of the three generators is 2000 kW. Var Capability (Both leading and lagging)) Leading is .98 Lagging is .8 B-2 LOCATION OF FACILITY Near: Buhl, ID Sections: _11_ Township: __lQ_S_ Range: 15E Clover Quadrangle County: Twin Falls ID. Description oflnterconnection Location: Near 1707 E 3800 N, Buhl, ID 83316 Nearest Idaho Power Substation: Clover Substation B-3 SCHEDULED FIRST ENERGY AND OPERATION DATE Seller has selected September l, 2011 as the Scheduled First Energy Date. Seller has selected October 1. 2012 as the Scheduled Operation Date. In making these selections, Seller recognizes that adequate testing of the Facility and completion of all requirements in paragraph 5.2 of this Agreement must be completed prior to the project being granted an Operation Date. -33- 5/19/2010 B-4 MAXIMUM CAPACITY AMOUNT: This value will be _2_MW which is consistent with the value provided by the Seller to Idaho Power in accordance with Schedule 72. This value is the maximum energy (MW) that potentially could be delivered by the Seller's Facility to the Idaho Power electrical system at any moment in time. B-5 POINT OF DELIVERY "Point of Delivery" means, unless otherwise agreed by both Parties, the point of where the Sellers Facility's energy is delivered to the Idaho Power electrical system. Schedule 72 will determine the specific Point of Delivery for this Facility. The Point of Delivery identified by Schedule 72 will become an integral part of this Agreement. B-6 LOSSES If the Idaho Power Metering equipment is capable of measuring the exact energy deliveries by the Seller to the Idaho Power electrical system at the Point of Delivery, no Losses will be calculated for this Facility. If the Idaho Power Metering is unable to measure the exact energy deliveries by the Seller to the Idaho Power electrical system at the Point of Delivery, a Losses calculation will be established to measure the energy losses (kWh) between the Seller's Facility and the Idaho Power Point of Delivery. This loss calculation will be initially set at 2% of the kWh energy production recorded on the Facility generation metering equipment. At such time as Seller provides Idaho Power with the electrical equipment specifications (transformer loss specifications, conductor sizes, etc) of all of the electrical equipment between the Facility and the Idaho Power electrical system, Idaho Power will configure a revised loss calculation formula to be agreed to by both parties and used to calculate the kWh Losses for the remaining term of the Agreement. If at any time during the term of this Agreement, Idaho Power determines that the loss calculation does not correctly reflect the actual kWh losses attributed to the electrical equipment between the Facility and the Idaho Power electrical system, Idaho Power may adjust the calculation and retroactively adjust the previous months kWh loss calculations. -34- 5/19/2010 B-7 METERING AND TELEMETRY Schedule 72 will determine the specific metering and telemetry requirements for this Facility. At the minimum the Metering Equipment and Telemetry equipment must be able to provide and record hourly energy deliveries to the Point of Delivery and any other energy measurements required to administer this Agreement. These specifications will include but not be limited to equipment specifications, equipment location, Idaho Power provided equipment, Seller provided equipment, and all costs associated with the equipment, design and installation of the Idaho Power provided equipment. Seller I will arrange for and make available at Seller's cost communication circuit(s) compatible with Idaho Power's communications equipment and dedicated to Idaho Power's use terminating at the Idaho Power facilities capable of providing Idaho Power with continuous instantaneous information on the Facilities energy production. Idaho Power provided equipment will be owned and maintained by Idaho Power, with total cost of purchase, installation, operation, and rnaintenance, including administrative cost to be reimbursed to Idaho Power by the Seller. Payment of these costs will be in accordance with Schedule 72 and the total metering cost will be included in the calculation of the Monthly Operation and Maintenance Charges specified in Schedule 72. B-8 NETWORK RESOURCE DESIGNATION Idaho Power cannot accept or pay for generation from this Facility until a Network Resource Designation ("NRD") application has been accepted by Idaho Power's delivery business unit. Federal Energy Regulatory Commission ("FERC") Rules require Idaho Power to prepare and submit the NRD. Because much of the information Idaho Power needs to prepare the NRD is specific to the Seller's Facility, Idaho Power's ability to file the NRD in a timely manner is contingent upon timely receipt of the required information from the Seller. Prior to Idaho Power beginning the process to enable Idaho Power to submit a request for NRD status for this Facility, the Seller shall have completed all requirements as specified in Paragraph 5.7 of this Agreement. Seller's failure to provide complete and accurate information in a timely manner can significantly impact Idaho Power's ability and -35- 5/19/2010 cost to attain the NRD designation for the Seller's Facility and the Seller shall bear the costs of any of these delays that are a result of any action or inaction by the Seller. -36- 5119/2010 APPENDIXC ENGINEER'S CERTIFICATION OF OPERATIONS & MAINTENANCE POLICY on behalf of himself and The undersigned ----- hereinafter collectively referred to as "Engineer," hereby states and certifies to the Seller as follows: 1. That Engineer is a Licensed Professional Engineer in good standing in the State ofldaho. 2. That Engineer has reviewed the Energy Sales Agreement, hereinafter "Agreement," between Idaho Power as Buyer, and _______ as Seller, dated ___________ _ 3. That the cogeneration or small power production project which is the subject of the Agreement and this Statement is identified as IPCo Facility No. ________ and is hereinafter referred to as the "Project." 4. That the Project, which is commonly known as the ________ __;Project, is located m Section __ Township ____ Range ____ , Boise Meridian, _____ County, Idaho. 5. That Engineer recognizes that the Agreement provides for the Project to furnish electrical energy to Idaho Power for a ____ year period. 6. That Engineer has substantial experience in the design, construction and operation of electric power plants of the same type as this Project. 7. That Engineer has no economic relationship to the Design Engineer of this Project. 8. That Engineer has reviewed and/or supervised the review of the Policy for Operation and Maintenance ("O&M") for this Project and it is his professional opinion that, provided said Project has been designed and built to appropriate standards, adherence to said O&M Policy will result in the Project's producing at or near the design electrical output, efficiency and plant factor for a fifteen ( 15) year period. 9. That Engineer recognizes that Idaho Power, in accordance with paragraph 5.2 of the Agreement, is relying on Engineer's representations and opinions contained in this Statement. -37- 5/19/2010 I 0. That Engineer certifies that the above statements are complete, true and accurate to the best of his knowledge and therefore sets his hand and seal below. By ______________________ __ (P .E. Stamp) Dme ________________________ ___ -38- 5/19/2010 APPENDIXC ENGINEER'S CERTIFICATION OF ONGOING OPERATIONS AND MAINTENANCE The undersigned on behalf of himself and ____________ hereinafter collectively referred to as "Engineer," hereby states and certifies to the Seller as follows: 1. That Engineer is a Licensed Professional Engineer in good standing in the State of Idaho. 2. That Engineer has reviewed the Energy Sales Agreement, hereinafter "Agreement," between Idaho Power as Buyer, and _________ as Seller, dated------------ 3. That the cogeneration or small power production project which is the subject of the Agreement and this Statement is identified as IPCo Facility No. and hereinafter referred to as the "Project". 4. That the Project, which is commonly known as the _________ P.roject, is located m Section __ Township Range , Boise Meridian, County, Idaho. 5. That Engineer recognizes that the Agreement provides for the Project to furnish electrical energy to Idaho Power for a fifteen (15) year period. 6. That Engineer has substantial experience in the design, construction and operation of electric power plants of the same type as this Project. 7. That Engineer has no economic relationship to the Design Engineer of this Project. -39- 5/19/2010 8. That Engineer has made a physical inspection of said Project, its operations and maintenance records smce the last previous certified inspection. It is Engineer's professional opinion, based on the Project's appearance, that its ongoing O&M has been substantially in accordance with said O&M Policy; that it is in reasonably good operating condition; and that if adherence to said O&M Policy continues, the Project will continue producing at or near its design electrical output, efficiency and plant factor for the remaining __ _ years of the Agreement. 9. That Engineer recognizes that Idaho Power, in accordance with paragraph 5.2 of the Agreement, is relying on Engineer's representations and opinions contained in this Statement. 10. That Engineer certifies that the above statements are complete, true and accurate to the best of his knowledge and therefore sets his hand and seal below. By ____________ __ (P.E. Stamp) Date ---------------------------- -40- 5119/2010 APPENDIXC ENGINEER'S CERTIFICATION OF DESIGN & CONSTRUCTION ADEQUACY The undersigned on behalf of himself and ____________ hereinafter collectively referred to as "Engineer", hereby states and certifies to Idaho Power as follows: 1. 2. That Engineer is a Licensed Professional Engineer in good standing in the State ofldaho. That Engineer has reviewed the Firm Energy Sales Agreement, hereinafter "Agreement", between Idaho Power as Buyer, and _____________ as Seller, dated 3. That the cogeneration or small power production project, which is the subject of the Agreement and this Statement, is identified as IPCo Facility No ________ and is hereinafter referred to as the "Project". 4. That the Project, which is commonly known as the ________ _____cProject, is located m Section __ Township ____ Range ____ , Boise Meridian, _____ County, Idaho. 5. That Engineer recognizes that the Agreement provides for the Project to furnish electrical energy to Idaho Power for a fifteen (15) year period. 6. That Engineer has substantial experience in the design, construction and operation of electric power plants of the same type as this Project. 7. That Engineer has no economic relationship to the Design Engineer of this Project and has made the analysis of the plans and specifications independently. 8. That Engineer has reviewed the engineering design and construction of the Project, including the civil work, electrical work, generating equipment, prime mover conveyance system, Seller furnished Interconnection Facilities and other Project facilities and equipment. -41- 5/19/2010 9. That the Project has been constructed in accordance with said plans and specifications, all applicable codes and consistent with Prudent Electrical Practices as that term is described in the Agreement. 10. That the design and construction of the Project is such that with reasonable and prudent operation and maintenance practices by Seller, the Project is capable of performing in accordance with the terms of the Agreement and with Prudent Electrical Practices for a ____ year period. 11. That Engineer recognizes that Idaho Power, in accordance with paragraph 5.2 of the Agreement, in interconnecting the Project with its system, is relying on Engineer's representations and opinions contained in this Statement. 12. That Engineer certifies that the above statements are complete, true and accurate to the best of his knowledge and therefore sets his hand and seal below. By ________________________ _ (P .E. Stamp) Dme ____________________ __ -42- 5/19/2010 APPENDIXD FORMS OF LIQUID SECURITY The Seller shall provide Idaho Power with commercially reasonable security instruments such as Cash Escrow Security, Guarantee or Letter of Credit as those terms are defined below or other forms of liquid financial security that would provide readily available cash to Idaho Power to satisfy the Delay Security requirement within this Agreement. For the purpose of this Appendix D, the term "Credit Requirements" shall mean acceptable financial creditworthiness of the entity providing the security instrument in relation to the term of the obligation in the reasonable judgment of Idaho Power, provided that any guarantee and/or letter of credit issued by any other entity with a short-term or long-term investment grade credit rating by Standard & Poor's Corporation or Moody's Investor Services, Inc. shall be deemed to have acceptable financial creditworthiness. 1. Cash Escrow Security-Seller shall deposit funds in an escrow account established by the Seller in a banking institution acceptable to both Parties equal to the Delay Security. 2. Guarantee or Letter of Credit Security-Seller shall post and maintain in an amount equal to the Delay Security: (a) a guaranty from a party that satisfies the Credit Requirements, in a form acceptable to Idaho Power at its discretion, or (b) a Letter of Credit in a form acceptable to Idaho Power, in favor of Idaho Power. The Letter of Credit will be issued by a financial institution acceptable to both parties. -43- 5/19/2010 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY · ATTACHMENT 2 MECHANICAL Heating Ventilation Air Conditioning Plumbing Radiant Heating Refrigeration • design, sales & installation • preventative maintenance • service & repair ARCHITECTURAL METALS Flashing Metal Roofing Metal Siding • design, fabrication &. installation METAL FABRICATION Structural Stairs, Railings Stainless Steel Specialty Fabrication Custom Product Manufacturing • design, fabrication &. installation FOOD SERVICE Commercial Kitchens Institutional Kitchens Restaurant Kitchens • design, fabrication & installation FOOD PROCESSING EQUIPMENT Food Manufacturing Equip. Sorting & Sizing Washing & Conveying Packaging Custom Equipment • design, fabrication, sales & installation BIOGAS DIGESTERS • design, fabrication sales & installation 6920 Salashan Pkwy, A·1 02 P.O. Box 2708 Ferndale, WA 98248 Office: 360.366.9900 Fax: 360.366 5800 corporate@andgar.com http :1 /www andgar.com May 27,2009 Idaho Power Compani 1221 W. Idaho Street Boise, ID 83702 ATTN: Rowena Bishop RE: Swager Farms #268 Dear Rowena, Due to project uncertainties, we are no longer willing to proceed with the Facility Study for the Swager Farms project #268. We may want to pursue this project again in the future but feel that it is not in our best interest to do so at this time. Thank you for your work on this so far. We look forward to working with you more in the near future. Sincerely, Eric Powell ANDGAR CORPORATION BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 3 SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Pro\ider: IDAHO POWER COMPANY Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: Rowena Bishop 1221 W. Idaho Street, Boise lD 83702 208-388-2658 208-388-6647 rbishop@idahopower.com An Interconnection Request is considered complete when it provides all applicable and correct information required below. Preamble and Instructions An Interconnection Customers who request interconnection must submit this Interconnection Request by hand delivery, mail, e-mail, or fax to the Transmission Provider. Processing Fee or Deposit: If the Interconnection Request is submitted under the Fast Track Process, the non-refundable processing fee is $500. If the Interconnection Request is submitted under the Study Process, whether a new submission or an Interconnection Request that did not pass the Fast Track Process, the Interconnection Customer shall submit to the Transmission Provider a (lb-p®.\ttl"!a~: i;:.~<,;t;,e:.,:l $1;000 t\'iwards the cost of the feasibility study. ' Interconnection Customer Information Legal Name of the Interconnection Customer (or, if an individual, individual's name) N'";rn~: <An,clj{AY Lovporo.hoV\ :C¢,i~t:t.1'~;!:~c:n: ~...,'t-'t-1 _,_\-e."""---'0""--'\""A_,~_,V''-:-~+'""e....,V'\...,..,><--------------------­ Mamn~(Addtess; Po Bo x '}_Jog ~U~(A;,hc-.VJ Pt'-wy A-lu?. .Sta.ce: \/JA...:..· __ _ Z:ip: · .. if~24Q l~~telHty Lopation {ifdttferent from above): '?. l/l.. 1\1 i] Ob TdepJwne (Bvening): --------- Cont~tNrume: ____________________________________________________________ _ Title:-------------------------,--------------- Ad&ess: _________________________________________________________ __ Telephone (Day): ________________ Telephone (Evening): _______________ _ Fax: _____________________ E-Mail Address:------------ Apl1liUJ.ti6i.i :ls for: ' · X New Small Generating Facility ___ Capacity addition to Existing Small Generating Facility .. If capacity additiqn t6 existing facility, please describe:---------------- Net Metering? Yes_ No_ To Supply Power to the Interconnection Customer? Yes _No_ To Supply Power to Others? Yes .)S_No __ To Ltt-1\i-\)' For installations at locations with existing electric service to which the proposed Small Generating Facility will interconnect, provide: (Local Electric Service Provider*) (Existing Account Number*) [*To be provided by the Interconnection Customer if the local electric service provider is different from the Transmission Provider] ContactNrune: ________________________________________________________ ___ Title: _______________________________________________ __ Address: ______________________________________________________________ ___ Telephone (Day): -------------------Telephone (Evening):--------------- Fax:----------------------------E-Mail Address:----------- Re:<l t)ei;:i'ed }Joint ef iuterconiwl;t\(,n: See Ire£~(}..~ Dva.w ,·VI q ..,./ lnt<:<rco•mJe:bmt CDntrJlT:er'.;: Itequ.ested In-Service Date:: ___ Cf,__,_/_~_._/-'-2» __ 1 [:;..) _________________ _ 2 Small Generating Facility Information Data apply only to the Small Generating Facility, not the Interconnection Facilities. ,l?.nergy Sonn:t'; _· Solar _Wind _Hydro _Hydro Type (e.g. Run-of-River):. ____ _ Diesel _Natural Gas _Fuel Oil 4 Other (state type) ~B ..... to..,.,"'·o'-"5"----------- }';J.irt.ut· ?-riovc:i: _Fuel Cell >\ Recip Engine _Gas Turb Steam Turb _Microturbine _PV _Other __ Induction Inverter kW (Typical) Generator Nameplate kV AR: c.r~g Interconnection Customer or Customer-Site Load: _____ ___.__.kW (if none, so state) Typical Reactive Load (if known): ______ _ List components of the Small Generating Facility equipment package that are currently certified: Equipment Type Certifying Entity 1. -------- 2. --------------- 3. ---------- 4. ------------ 5. -------- Is the prime mover compatible with the certified protective relay package? __ Yes __ No Generator (or solar collector) Manufacturer, Model Name & Number: _.S._r+:....o......;.vn~f--='e;.;..o.f-"'~=-----?.__I:=.;_'l...:.......3=b.=D'-1;(::-'~=~=--~.:...J· '-"'=:i""'c._,__ha.~J)-+-­ Version Number:----------- l(,d ~ -'.ih~~\ O~rl~l:.'tJor j:~.,·~/etF&t~ol' tz~ted:l'(ll·l'~r :~~~cto-.·: tiFt:~hJ:tg\ -·--~---"Lagging: _....;.•-~-=-· -~-- Total Number of Generators in wind farm to be interconnected pursuant to this Interconnection Request: Elevation: __ Single phase _Three phase Inverter Manufacturer, Model Name & Number (if used):---------------- List of adjustable set points for the protective equipment or software: ----------- Note: A completed Power Systems Load Flow data sheet must be supplied with the Interconnection Request. 3 Small Generating Facility Characteristic Data (for inverter~based machines) Max design fau1t contribution current: ___ _ Instantaneous orRMS? Harmonics Characteristics:------------------------ Small Generating Facility Characteristic Data (for rotating machines) RPM Frequency: 12-oo (*)Neutral Grounding Resistor.(If Applicable): ____ _ Synchronous Generators: $€e, A-ffcu:.hed Direct Axis Synchronous Reactance, Xd: ___ P.U. Direct Axis Transient Reactance, X'd: P .U. Direct Axis Subtransient Reactance, X" d: --------'p .U. Negative Sequence Reactance, X2: ____ P.U. Zero Sequence Reactance, X0: P.U. KVABase: Field Volts:----------- Field Amperes: _____ _ Induction Generators: Motoring Power (kW): -=------,,---- lit or K (Heating Time Constant): _____ _ Rotor Resistance, Rr. ------ Stator Resistance, Rs: ------ Stator Reactance, Xs: ------ Rotor Reactance, Xr: _____ _ Magnetizing Reactance, Xm: _____ _ Short Circuit Reactance, Xd": _____ _ Exciting Current:------ Temperature Rise: _____ _ Frame Size: -----­ Design Letter: ___,..,.......,,------,-- Rs;ar,tivd'pw~)t ,ltequ:i.i:"?(j Ip v ~~:t (NO. LO!ld) .. _~ _____ _ Riail-t1'ie !>o\vcr Rcqhlied 111 V!ii·.s (.fW:ll.{,!<.d): ··-=::-:--c:-:::c::-:-=- Total Rotating Inertia, H: Per Unit on kV A Base Note: Please contact the Transmission Provider prior to submitting the Interconnection Request to determine if the specified information above is required. 4 Excitation and Governor System Data for Synchronous Generators Only Provide appropriate IEEE model block diagram of excitation system, governor system and powe~ system stabilizer (PSS) in accordance with the regional reliability council criteria. A PSS may be detennined to be required by applicable studies. A copy of the manufacturer's block diagram may not be substituted. Interconnection Facilities Information . tAt :\l:1 y S' (je_ Willa t:ransfon~ler be used between the generator and tbe point of common coupling·l ~ ii~~ XN o Will the transformer be provided by the Interconnection Custome::r'? • ~Ye$ XN 6 Transformer Data (If Appllcable. for Interconnection Customer-Owned Transformer): Is the transformer: __ single phase __ three phase? Size: kVA -------" TrB.DSformer Impedance: % on kVA Base If Three Phase: Transformer Primary: __ Volts __ Delta __ Wye __ Wye Grounded Transformer Secondary: __ Volts __ Delta __ Wye __ Wye Grounded Transformer Tertiary: __ Volts __ Delta __ Vfye __ Wye Grounded Transformer Fuse Data Of Applicable, for Interconnection Customer-Owned Fuse): (Attach copy of fuse manufacturer's Minimum Melt and Total Clearing Time-Current Curves) Manufacturer:--------Type: ______ Size: ____ Speed: _____ _ Interconnecting Circuit Breaker (ifaoplicable): Manufacturer: A B ¥:. Type: fC '2.- Load Rating (Amps): I bDo Interrupting Rating (Amps): '$S' ILA Trip Speed (Cycles): l D Y'I\S Interconnection Protective Relays (If APPlicable): If Microprocessor-Controlled: tsecJ:w; ~~ Wl ~'+lOA' C s.R.e cd-tM-~tl) List of Functions and Adjustable Setpoints for the protective equipment or software: Setpoint Function Minimum Maximum 1. 2. 3. 4. 5. 6. 5 IfDiscrete Components: (Enclose Copy of any Proposed Time-Overcurrent Coordination Curves) Manufacturer: _____ Type: ___ Style/Catalog No.: ____ Proposed Setting: ____ _ ·Manufacturer: Type: Style/Catalog No.: Proposed Setting: ____ _ Manufacturer: Type: Style/Catalog No.: Proposed Setting: ____ _ Manufacturer: Type: Style/Catalog No.: Proposed Setting: ____ _ Manufacturer: Type: Style/Catalog No.: Proposed Setting: ____ _ Current Transformer Data (If Applicable): (Enclose Copy of Manufacturer's Excitation and Ratio Correction Curves) Manufacturer: £L .. :~ S Type: A-· \'1oo Accuracy Class:_ Proposed Ratio Connection: \'200 : '>"' Manufacturer:-------------------­ Type:-------Accuracy Class: _ Proposed Ratio Connection: __ Potential Transformer Data af Applicable): Manufacturer:--------------------Type: _______ Accuracy Class:_ Proposed Ratio Connection: __ Manufacturer:----------------:----­ Type:-------Accuracy Class: _ Proposed Ratio Connection: __ 6 General Information ,En.do.se <.:P.PY of .site tle:c;trk<Jl tme-Jjut: i:li~gram .showing the configuration of all Small Generating .f'acility equipment, current and potential circuits, and protection and control schemes. This one-line diagram must be signed and stamped by a licensed Professional Engineer if the Small Generating Facility is larger than 50 kW. Is One-Line Diagram Enclosed\~: . ..:.c'Yts . ..::..:.:.:....No · · ·. F,oclos~: ,iop:y ~~f nny :iiie:d6t~i1opentation that indicates the precise physical location of the proposed Small Generating Facility ~.USGS topographic map or other diagram or documentation). Proposed location of protective interface equipment on property (include address if different from the Interconnection Customer's address)---------------------- Enclose copy of any site documentation that describes and details the operation of the protection and control schemes. Is Available Documentation Enclosed? _Yes __ No Enclose copies of schematic drawings for all protection and control circuits, relay current circuits, relay potential circuits, and alarm/monitoring circuits (if applicable). Are Schematic Dmwings Enclosed? _Yes __ No Applicant Signature I hereby certify that, to the best of my knowledge, all the information provided in this Interconnection Request is true and correct. For Interconnection Customer: Siq;_ff e.d.L. . -~~~=~-------Ditt6: 9h-k Printed l>i/e --::wif~as 7 ~-- -- 7.2/ 1 2 . 4 7 KV 3~ UTIU T Y DIST R I B U T I O N LIN E .3 0 "" - ' " " " ' 1 ' ST I C K [ F ' C R A T £ 1 1 AIR I R E A K S \ I { T C H ,~ - !'1 : 0 I(V A "' · ,., . ! ! ) ; T1 U/ I V T ~v iH 7 / ~ D i o V.t . ·~D IO J n t D 'r r ~ M1 t VfS [ L E : . l . l r J C A a . ! l l O O A M• l II' E R A T E D I Y U T I U T Y '< J F ' R E O U P ! £ 1 ) D c mS C O K O T l£ V 1 0 : ~ 3 I _,& ' ) .'C ( : j __ __ _ _ ·~ - - -- - - - 1-S 1 52 G1 1- C B 1 ll 8 e t f J P 1-S 2 ~ 'o - - - - - - - - J KT K ~ - 5 :~ ; ; ~ 3 fF ~ I I I 12 o o : s I ~ J~c K W m l M3 4 1 0 A _ 1-C T < I - 0 , • I AN A L O G ME T E R I N G ~ - -- -- - - - -- - - ~- -- -r -- (A V R • AU T O VO L T A G E RE G U L A T O R ) fO V E R N 0 3 - 2- C B 1 - - - - - - - - -- - - - -- - -- - - 1 2- S 1 -f - - I I -- - -- - - - - - - - -- - - -t ~ (A V R ~ AU T O VO L T A G E RE G U L A T O R ) fO V E R N O , - - - - -- - - - - - - - - -- -- - -· - -- -- - - -· -- - - - - - -- - - -- - - - - - - - - - - - - - - -- - PR E L I M I N A R Y RE L A Y Sm 1 N G S FO R G1 & C2 ~ -l r "" " - . rJU•fiK • F ' = l f ' _, . , __ _ I OD I I K l i • II - ~ I I U ! ' ! ' •.11 1 o b la . W - ~ __ .. _., . . ~ p ! : l ! t t l a i c -;. -= - , '" ' , . . . .. . , . , .. .,: o-.. • 1-- ' •.roe : l l ' l $- " ' " ' E l l " U ! U i " ~ [ICt i l l ; C [O i . - .. . . . . . - PR O P O S E D N~ EO U I P t . a N T 11) BE OW N [ D BY CU S J O W E R AN D SU P F U D BY OTH E R S PR O P O S E D NE W EO U I P l i E N T TO BE OW N l D f!f CU S T O I I E R AN D SL W I . S IJY GE N - l E C LlC PR O P O S m N£W EO U ! P ' I D I T TO BE OW N E D BY CU S T O W £ R AN D Slf i P l i E D BY t.W m N IM C H I N E R T ' W: ma a . : l. n l "!li l i r & lll VIlfM D ' i i 1~ 1 I 1- : . : c ; . : 1!1 ll ~ ~ ~ .- s \ G I K N -- _, , ~ ... . . . . . . . h. . . . . _ N I . o ~ M -M ·- Jll - j[ s PI736D-Technical Data Sheet ,----· -------~~-----------···---·---~ I . i i ----..1 PI736D SPECIFICATIONS & OPTIONS STAMFORD STANDARDS Newage Stamford industrial generators meet the requirements of BS EN 60034 and the relevant sections of other national and international standards such as BS5000, VDE 0530, NEMA MG1-32, IEC60034, CSA C22.2-100, AS1359. Other standards and certifications can be considered on request. DESCRIPTION The STAMFORD PE range of synchronous ac generators are brushless with a rotating field. They are separately excited by the STAMFORD Permanent Magnet Generator (PMG). This is a shaft mounted, high frequency, pilot exciter which provides a constant supply of clean power via the Automatic Voltage Regulator (AVR) to the main exciter. The main exciter output is fed to the main rotor, through a full wave bridge rectifier, protected by surge suppression. VOLTAGE REGULATORS The PE range of generators, complete with a PMG, are available with one of two AVRs. Each AVR has soft start voltage build up and built in protection against sustained over-excitation, which will de-excite the generator after a minimum of B seconds. Underspeed protection (UFRO), is also provided on both AVRs. The UFRO will reduce the generator output voltage proportional to the speed of the generator below a pre- satiable level. The MX341 AVR Is two phase sensed with a voltage regulation of :1: 1 %. (see the note on regulation). The MX321 AVR is 3 phase rms sensed with a voltage regulation of 0.5% rms (see the note on regulation). The UFRO circuit has adjustable slope and dwell, for controlled recovery from step loads. An over voltage protection circuit will shutdown the output device of the AVR, it can also trip an optional excitation circuit breaker if required. As an option, short circuit current limiting is available with the addition of current transformers. Both the MX341 and the MX321 need a generator mounted current transformer to provide quadrature droop characteristics for load sharing during parallel operation. Provision is also made for the connection of the STAMFORD power factor controller, for embedded applications, and a remote voltage trimmer. 2 WINDINGS & ELECTRICAL PERFORMANCE All generator stators are wound to 2/3 pitch. This eliminates triplen (3rd, 9th, 15th ... ) harmonics on the voltage waveform and is found to be the optimum design for trouble-free supply of non-linear loads. The 2/3 pitch design avoids excessive neutral currents sometimes seen with higher winding pitches. A fully connected damper winding reduces oscillations during paralleling. This winding, with the 2/3 pitch and carefully selected pole and tooth designs, ensures very low levels of voltage waveform distortion. TERMINALS & TERMINAL BOX Standard generators feature a main stator with 6 ends brought out to the terminals, which are mounted on the frame at the non-drive end of the generator. A sheet steel terminal box contains the AVR and provides ample space for the customers' wiring and gland arrangements. It has removable panels for easy access. SHAFT &KEYS All generator rotors are dynamically balanced to better than BS6861 :Part 1 Grade 2.5 for minimum vibration in operation. Two bearing generators are balanced with a half key. INSULATION/IMPREGNATION The Insulation system is class 'H', and meets the requirements of UL 1446. All wound components are impregnated with materials and processes designed specifically to provide the high build required for static windings and the high mechanical strength required for rotating components. QUALITY ASSURANCE Generators are manufactured using production procedures having a quality assurance level to BS EN ISO 9001. NOTE ON REGULATION The stated voltage regulation may not be maintained in the presence of certain radio transmitted signals. Any change in performance will fall within the limits of Criteria 'B' of EN 61000-6-2:2001. At no time will the steady-state voltage regulation exceed 2%. Note: Continuous development of our products entitles us to change specification details without notice, therefore they must not be regarded as binding. Front cover drawing is typical of the product range. CONTROL SYSTEM A.V.R. VOLTAGE REGULATION SUSTAINED SHORT CIRCUIT INSULATION SYSTEM PROTECTION RATED POWER FACTOR STATOR WINDING IJVINDING PITCH IJVINDING LEADS MAIN STATOR RESISTANCE MAIN ROTOR RESISTANCE EXCITER STATOR RESISTANCE EXCITER ROTOR RESISTANCE R.F.I. SUPPRESSION WAVEFORM DISTORTION MAXIMUM OVERSPEED BEARING DRIVE END BEARING NON-DRIVE END WEIGHT COMP. GENERATOR WEIGHT WOUND STATOR WEIGHT WOUND ROTOR WR2 1NERTIA SHIPPING WEIGHTS In a craie PACKING CRATE SIZE TELEPHONE INTERFERENCE COOLING AIR VOLTAGE STAR kVA BASE RATING FOR REACTANCE VALUES Xd DIR. AXIS SYNCHRONOUS X'd DIR. AXIS TRANSIENT X"d OIR. AXIS SUBTRANSIENT Xq QUAD. AXIS REACTANCE X"q QUAD. AXIS SUBTRANSIENT XL LEAKAGE REACTANCE Xz NEGATIVE SEQUENCE Xo ZERO SEQUENCE P1736D WINDING 312 STAMFORD SEPARATELY EXCITED BY P.M.G. MX341 I MX321 I :t1% ' :t 0.5 % jiNith 4% ENGINE GOVERNING Fl.EFER TO SHORT CIRCUIT DECREMENT CURVES (page 7) CLASS H IP23 O.B DOUBLE LAYER LAP -.. TWO THIRDS 6 0.0018 Ohms PER PHASE AT 22•c STAR CONNECTED 2.69 Ohms at 22•c 17 Ohms at zz•c ~ .. 0.1 Ohms PER PHASE AT 22•c as EN 61000~-2 & as EN 61000-6-4,VDE 0875G, VDE 0875N. refer to factory for others NO LOAD< 1.5% NON-DISTORTING BALANCED LINEAR LOAD< 5.0% 1500 ReviMin BALL. 6228 C3 ---~---·-BALL. 6319 C3 1 BEARING 2BEARING 3233 kg 3182 kg 1368 kg 1368 kg 1548 kg 1486 kg -53.5769 kgm2 52.578 kgm2 3350kg 3372kg 194 X 105 X 154(cm) 194 x 105 x 154(cm) 50 Hz 60Hz THF<2% TIF<50 1.79 m'lsec 3793 elm 2.3 m'lsac 4874 elm 3801220 I 4001231 4151240 l 4401254 418/240 440/254 4601266 480/277 920 920 920 ~ 920 1050 1150 1150 1150 2.11 1.90 1.77 I 1.57 2.49 2.44 2.23 2.05 0.16 0.14 0.13 I 0.12 0.18 0.18 0.16 0.15 I 0.11 ! 0.10 0.09 i I 0.08 0.13 0.13 0.12 0.11 1.35 1.22 1.13 I 1.01 1.59 1.56 1.43 1.31 0.34 I 0.31 0.29 I 0.26 0.40 0.39 0.36 0.33 0.04 0.04 0.03 I 0.03 0.05 0.05 0.04 0.04 0.20 ' 0.18 0.17 I 0,15 0.23 0.23 0.21 0.19 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 REACTANCES ARE SATURATED VALUES ARE PER UNIT AT RATING AND VOLTAGE INDICATED T'd TRANSIENT TIME CONST. 0.162s T"d SUB-TRANSTIME CONST. 0.015s T'do O.C. FIELD TIME CON ST. 2.17s Ta ARMATURE TIME CONST. 0.0163s SHORT CIRCUIT RATIO 1/Xd 3 [;] z 416 v % ga 97 96 95 94 0.20 440 v ga 97 % 96 95 94 0.20 460 v 98 97 % 96 94 0 20 480 v 99 97 % 96 95 9J 0.20 PI736D Winding 312 THREE PHASE EFFICIENCY CURVES /~ !--~ / v / 0 30 0.40 0 50 0 60 0 70 0 60 0.90 ~ I--"" ./ !-----" I ~ v / 0 30 0 40 0 50 0 60 0 70 0 30 0 90 ~ ----:..--- / v /' 0 30 0 40 0 50 0 GO 0 70 o ao 0 9•) ~ t::=--/ / 1-- / 0 30 0.40 0 50 o eo 0 70 0 90 5 1.00 1.00 1 00 1 00 STAMFORD -- P.F. 1.0 0.9 0.8 1 10 1050 KVA - P.F. 1.0 0.9 0.8 1 10 1150 KVA PF. -1.0 0.9 0.8 110 1150 KVA P.F. 1.0 0.9 0.8 1 10 50 -Hz 30 , I 25 n. iS ~20 ~ g 11 .... z ~15 z ~ .... 1/ .... z ~10 I n:: w 2 ... ?~- 5 , ~ I /If 0 " 0 200 400 60 r---Hz 30 25 n. iS W20 ~ I ~ g .... z l*15 z ~ .... .... z ~10 ' 0! w n. "' 5 I ~ .... lllh 'Ill ~I 0 0 200 400 PI736D Winding 312 Locked Rotor Motor Starting Curve 346V 380V 400V 415V - I I I { ~ - I I L., ~ L I I I ' 600 800 1000 1200 1400 1600 1600 2000 LOCKED ROTOR kVA 380V d16V 440V I I I tl v . II' 1/ I I ~ ~ I I I I I I I I I 600 800 1000 1200 1400 1600 1800 2000 LOCKED ROTOR kVA 6 STAMFORD 440V I 2200 2400 2600 4GOV 480V I I I 2200 2400 2600 PI736D STAMFORD Three-phase Short Circuit Decrement Curve. No-load Excitation at Rated Speed Based on star (wye) connection. 100000 ! SVJIME.'hi::AL • • •ASYUUElRJ:.Al ... .. . . . • ._ . . :$. . ~10000 1--.. I il ' ~ ' I I I"-I 1000 I I 0.001 0.01 11M~-,~ 1 10 Sustamed Short Ctrcutt = 3,000 Amps 100000 i ... . . i . .. . ffi10000 . i . - I 1000 I 0.001 0.01 :::;ustalneu _,n011 vlrCUil-<+,..:uu '"'m Note 1 The following multiplication factors should be used to adjust the values from curve between time 0.001 seconds and the minimum current point in respect of nominal operating voltage : 50Hz 60 Hz Voltage I-' actor Voltage Factor 380v X 1.00 416V X 1.00 4UUV X 1.00 440v X 1.06 415v X 1.09 46Uv X 1.10 440v X 1.16 480v X 1.15 The sustained current value is constant lrrespectjve of voltage level p SYMMETRCAI... • • •ASYMUETM:AL I • I r..... I .......... I - n•~ll .. , 1 10 s Note 2 The following multiplication factor should be used to convert the values calculated in accordance with NOTE 1 to those applicable to the various types of short circuit : 3-phase 2-phase L-L 1-phase L-N nstantaneous X 1.00 X 0.87 X 1.30 Minimum X 1.00 X 1.80 x3.20 :sustamea X 1.00 X 1.50 X2.50 Max. sustamea auration 10 sec. 5 sec. 2sec. All other times are unchanged Note 3 Curves are drawn for Star (Wye) connected machines. 7 PI736D STAMFORD Winding 312/ 0.8 Power Factor RATINGS Class-Temp Rise Cont. F - 1 05/4o•c Cont. H -125t4o•c Standby -150/40"C Standby -163/27·c 50Hz Star (V) 380 400 415 440 380 400 415 440 380 400 415 440 380 400 415 440 ...... ,_,,, ......................... ,.,_,,, ..... ········-·······················-············-.. · .,,.,,,u,.-o., ... ,,,,,.,,,_, .. ,,,,,, .. ,,.,,,,,,,,,,, ·····-····················· ............................ .......................................................... kVA 850 850 850 850 920 920 920 920 960 960 960 960 985 985 985 985 kW 680 680 680 680 736 736 736 736 768 768 768 768 788 788 788 786 Efficiency(%) 96.0 96.1 96.2 96.3 95.9 96.0 96.1 96.3 95.8 96.0 96.1 96.2 95.8 95.9 96.1 96.2 kWinput 708 708 707 706 767 767 766 764 802 BOO 799 798 823 822 820 819 60Hz Star (V) 416 440 460 480 416 440 460 480 416 440 460 480 416 440 460 480 ...................................................... .......................................................... .. ..................................................... '" .................................................... ........... " ........................................... kVA 970 1065 1065 1065 1050 1150 1150 1150 1095 1200 1200 1200 1125 1230 1230 1230 kW 776 852 852 852 840 920 920 920 876 960 960 960 900 984 984 984 Efficiency (%) 96.0 96.0 96.2 96.2 95.9 95.9 96.1 96.2 95.8 95.9 96.0 96.1 95.7 95.8 96.0 96.1 kWinput 808 888 886 886 876 959 957 956 914 1001 1000 999 940 1027 1025 1024 DIMENSIONS 1793 970 OVER COVERS 639 . _...,.-) .. . 1- ........, 1/ 6-HOLES 035 _/ COUPLING DISC 'AN' S.A.ENo 18 16,7 S.A.E No21 D S.A.ENo24 0 ©2006 928.5 - ~ ~~ D 10 lr--1 I ~:T-435cr 365 830 errs I 830 1-BRG AOAPTOR S.A.ENoO S.A.ENoOO 858,5 2.23 18"1 ~ 6 SPIGOT 476 GSPIGOT 296 &SPIGOT 2.SRQ ADM>TORS S.A.ENoO S.A.E No 00 STAMFORD Barnack Road • Stamford • Lincolnshire • PE9 2NB Tel: 00 44 (0)1780 484000 • Fax: oo 44 (0)1780 484100 --r : 1330 TD_PI736D.GB_10.06_03_GB lntertie/Generator Protection Relay M·3410A Integrated Protection System® M-341 OA Standard Panel I M-341 DA Horizontal Panel (Optional) M-3410A Vertical Panel (Optional) • Facilitates standardization for small/medium intertie and generator protection applications • Microprocessor-based relay provides 15 protective relay functions, including Sync-Check, 2 programmable outputs and 2 programmable inputs • Relay voltage inputs can be directly connected (no VT required) for voltages 480 V or less PROTECTION • Local and remote serial communications (MODBUS protocol) capability for monitoring and control functions M-341 OA lntertie/Generator Protection Relay Protective Functions • Sync-check with Phase Angle, l1 V and !iF with dead line/dead bus options (25) • Phase undervoltage (27) protection • Ground undervoltage (27G) protection • Dual-setpoint, single or three phase, directional power detection that can be selected as over/ under power protection (32) • Dual-zone, offset-mho loss-of-field for generator protection {40) • Sensitive negative sequence overcurrent protection and alarm {46) • Negative sequence overvoltage {47) • Inverse time neutral overcurrent (51 N) • Phase overcurrent with voltage restraint/control (51 V) protection • Phase overvoltage (59) protection • Ground overvoltage (59G) protection • Peak overvoltage (591) protection • VT fuse-loss detection and blocking (60FL) • Reconnect enable for intertie protection (79) • Four-step over/under frequency (81) protection Standard Features • 2 programmable outputs, 2 programmable inputs, and 1 self-test output • Oscillographic recording (COMTRADE file format) • Time-stamped sequence of events recording for 32 events • Metering of Voltage, Current, real and reactive Power, Power Factor, Frequency, and Positive Sequence Impedance • One RS-232 port (COM1) on front and one RS-232 or 485 port (COM2) on rear • M-381 OA IPScom~ For Windows™ Communications Software • M-3811A IPScom For Palm OS® Communications Software • MODBUS protocol • Supports both 50 and 60 Hz applications • Accepts 1 A or 5 A rated CT inputs • Relay voltage Inputs can be directly connected (no VT required) for voltages ~480 V ac • Continuous Self-Diagnostics Optional Features • M-3801 C IPSplo~ Oscillograph Analysis Software • Horizontal and Vertical panel mount versions available (see Figures 2 and 4) -2- M-341 OA lntertie/Generator Protection Relay Tests and Standards The M-341 OA Generator/lntertie Protection Relay complies with the following type tests and standards: Voltage Withstand Dielectric Withstand All terminals except power supply and status input contacts, 2500 V ac/3500 V de Power Supply and Status Input Contacts: IEC 60255-5 1 ,500 V de for power supply voltages (12, 24, 48 V inputs) 2500 V ac/3500 V de for power supply voltages (120 V ac/125 V de input) • NOTE: Digital data circuits (RS-232/485 communication ports) are excluded. Impulse Voltage Power Supply Input Voltages, 120 V ac/125 V de: IEC 60255-5 5,000 V pk, +1-polarity applied to each independent circuit to earth 5,000 V pk, +I· polarity applied between independent circuits 1 .2 j.IS by 50 j.IS, 500 ohms impedance, three surges at every 5 second Interval • NOTE: Digital data circuits (RS-232/485 communication ports) are excluded. Power Supply Input Voltages, 12, 24,48 V de: IEC 60255-5 3,000 V pk, +1-polarity applied to each independent circuit to earth 3,000 V pk, +I· polarity applied between independent circuits 1.2 j.IS by 50 j.IS, 500 ohms impedance, three surges at every 5 second interval • NOTE: Digital data circuits (RS-232/485 communication ports) are excluded. Insulation Resistance IEC 60255-5 > 40 Megaohms • NOTE: Digital data circuits (RS-232/485 communication ports) are excluded. Electrical Environment Electrostatic Discharge Test IEC 61000-4-2 Class 4 ( ± 8 kV) -point contact discharge and air discharge • NOTE: Digital data circuits (RS-232/485 communication ports) are excluded. Fast Transient Disturbance Test I EC 61000-4-4 ( ± 2 kV, 5 kHz) AC Power Supply Input ( ± 1 kV, 5 kHz) RS-232, RS-485 and ground Surge IEC 61000-4-5 (±2 kV, 1.2 J.1.S by 50 j.IS line to ground) AC Power Supply Input ( ± 1 kV, 1.2 J.1.S by 50 JlS line to line) AC Power Supply Input ( ± 1 kV, 1.2 j.IS by 50 JlS line to ground) RS-485 Port Surge Withstand Capability ANSI/IEEE 2,500 V pk-pk Oscillatory each independent circuit to earth C37.90.1 2,500 V pk-pk Oscillatory between each independent circuit 1989 5,000 V pk Fast Transient each independent circuit to earth 5,000 V pk Fast Transient between each Independent circuit • NOTE: Digital data circuits (RS-232/485 communication ports) are excluded. , 0 ElEHilill 1 0 lllillllll!l ~ [1!]00 liJ[]00 0 0 > • 0 lstruzioni di instatlazione ed esercizio Instructions for installation and service ITSCB601933/001 it-en 6-97 ABBSACE lstruzfoni di installazione, di esercizio e di manutenzione per interruttori automatici aperti di bassa tensione Installation, service and maintenance instructions for low voltage air circuit-breaker SACE Emax 12. Unita di protezione PR111/LI-LSI-LSIG 12. PR111/LI-LSI-LSIG protection unit 12.1 Generafita 12. 1 General L'unita SAGE PR 111/P realizza le seguenti funzioni di protezione: The SAGE PR111/P unit carries out /he following protecl/on functions: L -protezione da sovraccarico a tempo lungo inverse L -protection against overload with inverse long time-delay S -protezione da corte circulto a tempo breve S -protection against short-t/me short-circuit I -protezione da corte circuito istantaneo I protection against instantaneous short-circuit G -protezione da guasto a terra G -protection against earth fault linst -protezione a soglia Iissa da corto circuito linst -rapid protection against instantaneous short-circuit Le unita SACE PR111 disponibill all'utente sorJo: The SAGE PR111 units available to the user are: PR1111L+I+Iinst PR1111L+S+I+Ilnst PR1111L +S+f+G+IInst Fig. 47 Le protezioni possono essere realizzate In modo trifase o trifase con neutro a second a del tipo di interruttore impiegato (tripolare, tetra pol are o tripolare con neutro estemo). L'unita, e autoalimentata·e garantisce il corretto funzionamento delle funzioni di proteziona in presenza di una corrente maggiore o uguale al 18% del valore nominale del trasformatore amperometrico di fase (TA). L'assieme sgancietore di protezione e cosi composto: - 3 o 4 trasforrnatori di corrente (TA) -unita di proteziane SACE PR111 -un solenoide di epertura (SA) della sganciatore di massima corrente che aglsce direttamente sui comando dell'interruttore_ Mod. LM4379 I I Rev. I I I The protections can be made either in three-phase or three-ph<~se with neutral mode, depending on the type of circuit-breaker used (three-pole, four-pole or three-pole with external neutral}. The unit is self-powered and ensures correct operation of the protec­ tion functions when there is a current higher than or equal to 18% of the rated phase current transformer value (CT). The protection release assembly consists of the fol/owlng: -3 or 4 current transformers (GT} -SAGE PR111 protection unit -an opening solenoid (OS) of the overcurrenl release which acts directly on the circuit-breaker operating mec/Janism_ Apparecchio Apparatus SACE Emax Scala Scale N" Doc-601933/001 ~~'::?.: Doc. No-521100 12.8 Curve di intervento 12.8.1 Curve dllntervento protezione "L" JOO?;:) 200 .. I ' 4 50 2 20 o' 10 e 0 0 • D • ' 2 I .. ·' 0. , ,I .... P,O< 1 I r ~: ~ 12.8 Trip curves 12.8.1 Trip curves of protection "L" I ~ I "' "' ['-.. ' I'. .U ' ', "' 1'-..1 ~~ .... ' ""' A.O 0.1 .., IU Q._~ 0.5 0.& 6.70.80.91 1,2 1,5 $ 6 1 e: It 10 11 15 zg 25. ;~tl,.. 12.8.2 Curve dl lntervento protezlone "I" 12.8.2 Trip curves of protection "I" olo' 10 0 0 ' D 10 • . • I • -0.2 ., 1,0 .. ,,...._ 1,) 2 l. ~····10 11 " 20 " ... Mod. IM4379 I I Apparecchlo Rev. I I I Apparatus SACEEmax WDoc. 601933/001 Doc. No Tolleranza sulle soglle di intervento L ~ ± Sgancio tra 1,05 e 1,3 11 (secondo le Norme IEC 947 -2) I = ±20% Trip threshold tolerance L = Releasebetwean 1.05 and 1.311 (In conform­ ity with IEC 947-2 standards) =.t20% Tolleranza sui tempi di in- tervento l ~ :1: 10% (20% per 1~2 x In) I = ± 20% Trip time talerarn;es L = :1: 10% (20% par 1>2 x In) I =.t20% Legenda In~ Correntanominaladei trasformalorl di car- rente t =tempo dllntervento caption In = Raled currsnt of cur­ rent transformers I =triptime Scala Scale N' Pag S.ll Nc. 1131100 12.8.3 Curve di intervento protezione "S" t(s( lOO' 100 • . ,o 2 >0 ·~ 10 i'..: ...... • • ' " I -. r-... ' ~· D ~1 '~ 0,3 Q4 0,5 0,8 O.fDJUI.,I!1 I.:Z 1,'!1 • I(J ,.., 100 fj . ;o :!() 10 • ' 2 I I , ... ,_ ' 02 ., 0,.. C.S 0.6 0,?0,1Q.JJ1 1,7 , .. Mod. IM4379 I I Rev. I I I 12.8.3 Trip curves of protection "S" .. 4. 0 Ul4 ~ ' ' " ~ ' 1'.. ....... 1'-' ' ,, • . . • • 189~0 \~ •• :JO ~ 0 u c~ 0 ~ • 3 • 5 1J 1 I If~ 11: " lO ,. Apparecchlo Apparatus SACE Emax N' Doc 601933/001 Doc. No. Tolleranza sulla soglie di intervenlo s = t 10% Trip threshold tolerance s = :t 10% Tolleranza sui tempi dl in-lervento s = t 20% Tn'p Ume tolerances s = ~20% Legend a In= Corrente nominaledei trasformatori dl cor-rente t = tempo dl inlervento CapUon In= Rated current of cur­ rant lrensformers r = lripttm .. Scala Scale N'Pao-Sh.ND, 64(100 12.8.4 Curve di intervento protezione "G" •[" . s: I ,. ~~ (~ ~ ~ (~ ~ ) ••' -·--·--· -100 • ' ' 20 !O' ~ 6() -•• ,. 10 ··---·---' ' . ' 1 •.. OA 0,2 ~""" ....... I" ' ~ •.. 0..04 lOJ 0.111 0,.& G~ G.9 o,70.a0.91 1,1 1.5 Mod. jM4379 I I Rev. I I I I 12.8.4 Trip curves of protection "G" I J .. ' I I ... Tolleranza sulle soglie di intervenlo G = t20% Trip threshold tolerance \··'!:> = ± 20% . '··•.::·., > T ol/eranza sui lempl di in­lervenlo G = ± 20% Tnp lime tolerances G= ±20% Legend a ~ c-- In = Corrente nominole dei trasformatori di Cor­ rente I s 6 7 • Iii l~ 12 10 " ... Appruecchio Appar.,tus SACE Emax N" Doc 601933/001 Doc. No. = tempo di lntervento Caption In= Rated current of cur­ rent transformers t =trip time Scala Scale N'PIIIJ Sh. t-lo 65/100 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 4 Kyle Juergens Andgar Corporation 6920 Salashan Parkway A-102 Ferndale, W A 98248 Ph 360-366-9900 Re: Swager Fanns-Project# 268 Dear Kyle: An IDACORP Company September 17, 2008 Thank you for your Generator Interconnection application for the Swager Farms Project to be connected to the Idaho Power system at Twin Falls County, Idaho (see attached copy). Since we have received all of the required materials, this application is now considered complete. As you may be aware, we are required to post certain information to our OASIS (Open Access Same Time Infonnation) website. Please refer to the website petiodically to view a list of current projects at http://oatioasis.com/ipco/index.html under GENERATOR INTERCONNECTION INFORMATION folder, on the left side ofthe screen. At this time, Idaho Power Company will assign a planning engineer for this project, and we will contact you in the near future to schedule a Scoping Meeting. For your review, I am attaching a copy of the standard Interconnection Feasibility Study Agreement that needs to be executed by you soon after our Scoping Meeting. Please feel free to contact me with your questions about the Generator Interconnection Process anytime. I will forward this application to our T &D Planning Leader, Marc Patterson, who will be evaluating your request. Encl Application Sincerely, ~ /aulvn ~r . Rowena Bishop Operations Analyst Ph 208-388-2658 Standard Interconnection Feasibility Study Agreement Cc: Marc Patterson/IPC Small Gen Feasibility Study Agreement Swager Farms Project# 268 Feasibility Study Agreement THIS AGREEMENT is made and entered into this __ day of ______ 2008 by and between _____________ , a _____________ organized and existing under the laws of the State of ________________ _J ("Interconnection Customer,") and Idaho Power Company a Corporation existing under the laws of the State ofldaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by Interconnection Customer on 9/10/08, also known as Project# 268; and · WHEREAS, Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; and WHEREAS, Interconnection Customer has requested the Transmission Provider to perform a feasibility study to assess the feasibility of interconnecting the proposed Small Generating Facility with the Transmission Provider's Transmission System, and of any Affected Systems; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1. 0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause to be performed an interconnection feasibility study consistent the standard Small Generator Interconnection Procedures in accordance with the Open Access Transmission Tariff. 3.0 The scope of the feasibility study shall be subject to the assumptions set forth in Attachment A to this Agreement. 4.0 The feasibility study shall be based on the technical information provided by the Interconnection Customer in the Interconnection Request, as may be modified as the result of the scoping meeting. The Transmission Provider reserves the right to request additional technical information from the Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the feasibility study and as designated in accordance with the standard Small Generator Interconnection Procedures. If the Interconnection Customer modifies its Interconnection Request, the time to complete the feasibility study may be extended by agreement of the Parties. Small Gen Feasibility Study Agreement Swager Farms Project# 268 5.0 In performing the study, the Transmission Provider shall rely, to the extent reasonably practicable, on existing studies of recent vintage. The Interconnection Customer shall not be charged for such existing studies; however, the Interconnection Customer shall be responsible for charges associated with any new study or modifications to existing studies that are reasonably necessary to perform the feasibility study. 6.0 The feasibility study report shall provide the following analyses for the purpose of identifying any potential adverse system impacts that would result from the interconnection of the Small Generating Facility as proposed: 6.1 Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; 6.2 Initial identification of any thermal overload or voltage limit violations resulting from the interconnection; 6.3 Initial review of grounding requirements and electric system protection; and 6.4 Description and non-bonding estimated cost of facilities required to interconnect the propose9. Small Generating Facility and to address the identified short circuit and power flow issues. 7.0 The feasibility study shall model the impact of the Small Generating Facility regardless of purpose in order to avoid the further expense and interruption of operation for reexamination of feasibility and impacts if the Interconnection Customer later changes the purpose for which the Small Generating Facility is being installed. 8.0 The study shall include the feasibility of any interconnection at a proposed project site where there could be multiple potential Points of Interconnection, as requested by the Interconnection Customer and at the Interconnection Customer's cost. 9.0 In lieu of Feasibility Study deposit, Interconnection Customer agrees that study funds will be drawn from the application fee for the performance of the Interconnection Feasibility Study. Transmission Provider shall charge and Interconnection Customer shall pay the actual costs of the Interconnection Feasibility Study. Any difference between the deposit and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate. Page 2 of3 Small Gen Feasibility Study Agreement Swager Farms Project# 268 10.0 Once the feasibility study is completed, a feasibility study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the feasibility study must be completed and the feasibility study report transmitted within 30 business days of the Interconnection Customer's agreement to conduct a feasibility study. 11.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 12.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company-Delivery Signed ________________________ ___ Signed ______________________ __ Printed Printed ----------------------------------------------------- Title Title --------------------------------------------------------- Date Date ---------------------------------------------------------- Small Gen Feasibility Study Agreement Swager Farms Project # 268 Attachment A to Feasibility Study Agreement Assumptions Used in Conducting the Feasibility Study The feasibility study will be based upon the information set forth in the Interconnection Request and agreed upon in the seeping meeting held on _________ _ 1) Designation ofPoint oflnterconnection and configuration to be studied. 2) Designation of alternative Points of Interconnection and configuration. 1) and 2) are to be completed by the Interconnection Customer. Other assumptions (listed below) are to be provided by the Interconnection Customer and the Transmission Provider. Page 1 of 1 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 5 AND GAR"' LETTER OF TRANSMITTAL TO: Idaho Power Rowena BishoQ 1221 W. Idaho Street Boise, ID 83702 WE ARE SENDING YOU: [g) 0 Shop Drawings D 0 Submittals D 0 Specifications D 0 Contract D DATE: 9/18/2008 ATTN: -=-R....:o_:w:....:e:..:...n:..:.a:....:B=-•==· s-=h:..:.o..~:.2 ___________ _ RE: _S 7 m_a....,.II_G=-e.:....n_e:....:r_;_a_;_to_;_r_I_n...;..te_;_r....:c...::.o.:....n_n_ec_tt_· o.:....n=.=R.::..:e:..:cqLu....:e...::.s.:....t __ 'Pen.) <:c 1 #-26 "b Attached Copy of Letter Change Order Plans Details 0 Under separate cover via the following: [g) Mail 0 Fax 0 UPS OOvernight 00ther COPIES DATE DESCRIPTI ON 1 9/18/2008 Small Gener ator Interconnection Re uest THESE ARE TRANSMITTED AS CHECKED BELOW: 0 For approval 0 For your use D REMARKS: Rowena, D D D ' As requested For review 0 Approved as submitted 0 Returned for correction 0 Attatched an updated interconnection r equest. Please let us know if you have any questions. Thanks, Eric Powell Andgar Corporation COPY TO: File 6920 Salashan Pkwy, A-1 02-P .0. Box 2708 corporate@an SIGNED: Eric Powell -Ferndale WA 98248-Office: 360.366.9900-Fax: 360.366.5800 dgar.com-http://www.andgar.com SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: Rowena Bishop 1221 W. Idaho Street, Boise ID 83702 208-388-2658 208-388-6647 rbishop@idahopower.com An Interconnection Request is considered complete when it provides all applicable and correct information required below. Preamble and Instructions An Interconnection Customers who request interconnection must submit this Interconnection Request by band delivery, mail, e-mail, or fax to the Transmission Provider. Processing Fee or Deposit: If the Interconnection Request is submitted under the Fast Track Process, the non-refundable processing fee is $500. If the Intercoimection Request is submitted under the Study Process, whether a new submission or an Interconnection Request that did not pass the Fast Track Process~ the Interconnection Customer shall BUbmit to the Transmission Provide:: ade}i(i:,;.-ii lWttl) e,'J:~id :.$!.GOO il(,wards the cost of the feasibility study. Interconnection Customer Information Legal Name of the Interconnection Customer (or, if an individual, individual's name) Nan:te: A tV'{o-.v' " Ootit~c~P~~~:"': -....l:~='i*""!.:2"'-_:U-'-'·""'J..::..:0=-)('".=,.jr:<."'" .. "'"V\ .... s"'-------------------­ Mailins' A.ddrc~;s;~. -'.P._.· ...._C.L?.:.-· __,_B"'"'o""'x"---_·..._z.-'r'-=D'-'o,__ _ ____,6,_CfL.:~'-D~--=~=.:.•...:-.!et_~,_h.....:.d.,_,,'"'"'h~-PJ-..!:k..::..:w"""'-'y'f--'-A_-...!.IV-=-="l. $t.tlte: ~~ 'Z:ip: _q+-· .... ~_...?"-8.L...lol\ __ _ F<tcilityLQ>?.1ti:vll(if dhferentfromabove): ~]7 L tJ f]QQ E R .. A\--.1 1 I-0 ~"633L6 't~leph<.>~ie (01ty)! (3f;.r;i)~t£ -1'160 ...:;....:::·:re:Jt-.phane (!!v&tii..ug):' ________ _ F.'a.~: (3(.-o) ~::,cG ~--:r-eoo :a.-Mail Adcix~-~$:· IL\Jii:?.j@.c71.v'c..~.r~v-. (CivV\. v \) 1 ContactNwne: ____________________________________________________________ _ Title: ________ _:_ _______________________ _ Ad~ess: ________________________________________________________ __ Telephone (Day): ___________ Telephone (Evening):--------- Fax:-------------------E-Mail Ad~ess: ----------- Appl itatio1i'J.s :foi·; · ~New Small Generating Facility ____ Capacity addition to Existing Small Generating Facility If capacity addition I<'J existing facility, please describe:-------------- Net Metering? Yes _No_ To Supply Power to the Interconnection Customer? Yes _No _ To Supply Power to Others? Yes _.X_ No__ lo ~~~--~ 1;+-y For installations at locations with existing electric service to which the proposed Small Generating Facility will interConnect, provide: (Local Electric Service Provider*) (Existing Account Number*) (*To be provided by the Interconnection Customer if the local electric service provider is different from the Transmission Provider) Contact Name:-------------------------------------------------- Title:----------------------------------------- Adiliess: ___________________________________________ _ Telephone (Day):---------------Telephone (Evening):--------'----- Fax: ---------------------E-Mail Ad~ess: ------------- .R.~q}ie~~d. J?o.int oflo~er®mwcti()rl. __ S..;._e_e.._--'.4-€:-.r_: "'-__ \ ___ V.::..:_{",~!I..w.:.::..,;;:;;7:':v·7•f ____________ _ l·,t•nM)'i1•j'<>,.:f:nTj ('.,:,.,\)..t'L''"'''1~ 'f,''•'(.<UL'Sttd. ''l·l"·s•:.l.;jj';,,~ ]);~'l~· crl $" J Z,oto •« '~..,. ... .,,..A ~.-'..;o .... •.v. -'~~l ,_,.,, ~~:-... ·-'V 1 ,.,. l '""' Y "''""' u. -------!----------------------- 2 Small Generating Factlitv rnforDUltion Data apply only to the Smlill Generating Facility, not the Interconnection Facilities. Enetgy Sourt<~: ·-Solar _Wind _Hydro _Hydro Type (e.g. Run-of-River): ____ _ Diesel _Natural Gas _Fuel Oil J( Other (state type) ~E.__·,_., c-,:j'J-''."-'"+S ______ _ Jjri.n:ie.:Mi:)ye:t: _Fuel Cell X Recip Engine _Gas Turb _Steam Turb _Microtwbine _PV _Other T.Yr•e ~rd~u~~·a1or:_!(_Synchronous __ Induction Inverter Gt~nehttw: Narr.re_p.T~ite R<ltirig: 1 DO kW (Typical) Generator Nameplate kV AR: ~61Y Interconnection Customer or Customer-Site Load: _______ kW (if none, so state) Typical Reactive Load (if known);------- ktaxitrmm ~lrys1~~l E>..-po~t Capa~Hity ·kequestcd: _J.I..r::UXJ'-='""". :.....-_kW List components of the Small Generating Facility equipment package that are currently certified: Equipment Type CertifYing Entity 1. ------------- 2. ------------------ 3. --------------- 4. ----------------- 5. ------------- Is the prime mover compatible with the certified protective relay package? __ Yes Generator (or solar collector) Manufacturer, Model Name & Number: Version Number:-------------- lndi vkh.wl Oeru~rator J'qw.cr :FM:::to.r · ·r. •• ,;.,P.d. ·J>r;·,,.~.-.~a.~r·L.,t:. ':e;.,,:n"' 'lo:.l.t. .•. -· 1¥'1;.1~ :\ v .. I.; ~'""·"'t."J" ,......._ __ _ Lagging: ---'-' 1J-=--· Total Number of Generators in wind farm to be interconnected pursuant to this __ No Interconnection Request: Elevation: _Single phase _Three phase Inverter Manufacturer, Model Name & Number (if used):----------------------- List of adjustable set points for the protective equipment or software: ----------------- Note: A completed Power Systems L<>ad Flow data sheet must be supplied with the Interconnection Request. 3 Small Generating Facility Characteristic Data (for inverter-based machines) Max design fault contribution current: ___ _ Instantaneous orRMS? Harmonics Characteristics:----------------------- St;.ut,-up teq:Jir<i:men:is: __ . ·------------------------ Small Generating Facility Characteristic Data (for rotating machines) RPM Frequency: \·zoo (*)Neutral Grounding Resistor (If Applicable): ____ _ Synchronous Generators: ~·e a+-+tt1clred Direct Axis Synchronous Reactance, Xd: ·z.o~ P.U. Direct Axis Transient Reactance, X'd: 0 • 1 ~ P .U. Direct Axis SubtransientReactance, X" d: D, 1\ P.U. Negative Sequence Reactance, X1: 0. ;1 P.U. Zero Sequence Reactance, X0: o. o 2 P.U. KVA Base: -___,~'6~1-;:..S· _____ _ Field Volts: 4~0 . Field Amperes: ~It IE'., . ~~ f'F Induction Generators: Motoring Power (kW): -:----:---Ilt or K (Heating Time Constant):-----­ Rotor Resistance, Rr: ------ Stator Resistance, Rs: ------ Stator Reactance, Xs: ------ Rotor Reactance, Xr: ------ Magnetizing Reactance, Xm: -----­ Short Circuit Reactance, Xd": ------ Exciting Current: _____ _ Temperature Rise: _____ _ Frame Size: ------ Design Lotter; ._ :R,flfLClt'flil 'Pe>Vf~ld\eg;uh"io lu V ~tts (N 'J_.,f:u~cl): . ._ ____ _ Rr,acti'l"¢ l'ower Re(ttlliidlri Varfl {itt\tl t.oatD1 ------ Total Rotating Inertia, H: Per Unit on kVA Base Note: Please contact the Trans:mjssion Provider prior to submitting the Interconnection Request to detennine jfthe specified infonnation above is required. 4 Excitation and Governor System Data for Svncbronous Generators Only Provide appropriate IEEE model block diagram of excitation system, governor system and power system stabilizer (PSS) in accordance with the regional reliability council criteria. A PSS may be deteniuned to be required by applicable studies. A copy of the manufacturer's block diagram may not be substituted. Intereon.nectiun Facilities Information . . .. • . lt·t\ \~'t~ Si.JL- Will a tt1lJlsfonner be used between the generator and the point of common coupling? -~.:::_''(e~ 'LNo Will the transformer be provided by the Interconnection CustomE;r? ~~--Y~~ K ~'i:'!() TrllilSforrner Data (If Applicable. for Interconnection Cnstomer-OWDcd Transformer): Ls the transfonner: __ single phase __ three pbase? Size: _____ k.VA Transfonner Impedance; % on kV A Base If Three Phase: Transfonner Primary: __ Volts __ Delta __ Wye __ Wye Grounded Transformer Secondary; __ Volts __ Delta __ Wye __ Wye Grounded Transformer Tertiary: __ Volts __ Delta __ Vfye __ Wye Grounded Transformer Fuse Data (If Amlicable. for Interconnection Customet·Qwned Fuse): (Attach copy of fuse manufacturer's Minimum Melt and Total Clearing Time-Current Curves) Manufacturer: ________ Type: ______ Size: ___ Speed:------ 1nterconnecting Circuit Breaker (if applicable): Manufacturer: A'\?:?. B Type: _ C], Load Rating (Amps): 16CrO ,Interrupting Rating (Amps): 5~5 MTrip Speed (Cycles): __ l_rJ_~-~- Interconnection Protective Relays lliAppJicablel: If Microprocessor-Controlled: List of Functions and Adjustable Setpoints for the protective equipment or software: Setpoint Function Minimum Maximum 1. 2. 3. 4. 5. 6. 5 If Discrete Components: (Enclose Copy of any Proposed Time-Overcurrcnt Coordination Curves) Manufacturer: ____ Type: ___ Style/Catalog No.: ____ Proposed Setting:----- Manufautucer: Type: Style/Catalog No.: Proposed Setting:----- Manufacturer: Type: Style/Cam log No.: Proposed Setting: ----- Manufacturer: Type: Style!Cntalog No.: Proposed Setting:----- Manufacturer: type: Style/Catalog No.: Proposed Setting:----- Current Transformer Data af Applicable): (Encl.ose Copy of Manufacturer's Excitation and Ratio Correction Curves) Manufacturer: PC:;... f.:..S.:<:--------------- Type: A -l ~t.'O Accuracy Class: _ Proposed Ratio Connection: i '1-00 f-1$" Manufacturer:---------------------~­ Type:-------Accuracy Class:_ Proposed Ratio Connection: __ Potential Transformer Data af Applicable): Manufacturer:--------------------­ Type:-------Accuracy Class:_ Proposed Ratio Connection: __ Manufacturer:--------------------­ Type:-------Accuracy Class:_ Proposed Ratio Connection: __ 6 General Information Enc.lm;e .:.r.l:jl}' p iL~ el~ctrdt.:ill.-one~line: diegrnm , h9wing the configuration of all Small Generating Facility equipment, current and potential circuits, and protection and control schemes. This one-line diagram must be signed and stamped by a licensed Professional Engineer if the Small Generating Facility is larger tlum 50 kW. Is One-Line Diagram Enclosed~' .:..K_ Y e$ _:_No - ;'E\iiC.l,{)$t) copy (~:ta:l1'}~· *:iia t'k1cii~:tr.,~i'ltation that indicates the precise physical location of the proposed Small Generating Facility ~ USGS topographic map or other diagram or documentation). Proposed location of protective interface equipment on property (include address if different from the Interconnection Customer's address)---------------------- Enclose copy of any site documentation that describes and details the operation of the protection and control schemes. Is Available Documentatio:11 Enclosed? _Yes __ No Enclose copies of schematic drawings for all protection and control circuits, relay current circuits, relay potential circuits, and alarm/monitoring cin;uits (if applicable). Are Schematic Dr.1wings Enclosed? _Yes __ No Applicant Signature I hereby certify that, to the best of my knowledge, all the information provided in this Interconnection Request is true and co.rrect. For Interconnection Customer: Signed ~~::...:·~-~'?J"""9'F==---_....,_......;__;_,'t><J1e: Printed 7 24 . 9 KV 14 . 4 KV 0\ l t ( D I Y U U L m .,. , ; . ; ; : ~ ·i: m l o O 30 UT I LIT Y OIS T R I B U TlON LI N E _~ _ ~. ·- I "' IJ~ J, Ttll l l . PII O J t t f U t l ~1 s- ~ u.; . . . t_ ~ r , ; ~ ~ 1 r-r m ,l~ 1 I f I 1~ 0 1 ·.~ ~c ' f t 1 % m o ­ 'i ~l t l f ! I J f l l . I . N ~f £ ~ 1 1 1 DY I ( D h tu $ 1 1 1 « • "" ' " ' " ' ; . , ; . ; : , a .. O<N · > t < "' 1-S 1 r ~-· GU < C Q H 1i '!5\' > . ' C i t .. . ' ]1 I< O N I 1 E l i f -- '-··4~ 1 1 1 1 1 { . 11 t qp _ S E ~ c ..... 1-C 6 1 l: 2 0 0 A T J P }. .., l.. ·P · r~ .- I . - - - -· ~ ,. , s ; , t. r ·· f .~cx W I ! i< ~ - · . -· - 1. , • xr~ __ . r-·- • ~- ~ ~ .. _ , ; 12 0 0 > • . • ' •• • ! : :·:: : b ·-· --- ' ®E ' I i " @ l i ® ~ . i i f~ P 1- C T - H \l ~ ~· c • " ' T ~ .. 3., 0 A : : J · t i ,_ AN A L O G UE T E ... . . . ' r.. ''" • f ~ 1 •~ G -· ; I - I' ... . . . . . . . . . . . . . . . . II ·~ u ~ ~ ' I l: i ~i i . ~ U . L ~ D ~ 1 1 i ~. . - - - - - - .... .. 1 .. ·· ·· · '· ~- - Oc~ : .' ~~ ~ \ ; EN G I N E ~~ , . ; . .. . '.=~ } ~- - -- - - -·· -\1 .. ~: " ' / G1 ,. ~! ~ ~J .~~ .L-L_ . t . .. ~I ~ D £ ~ E' - .. . . .. -- --- -- ---- ---- · ... (A V R • AU T O VO L T A C £ RE G U L A T O R ) .. : I i [ I ~0 \ I E , ; , : . ~ ·-- · ' * 60 0 K\J & 75 0 KV A ON BID FU E L 2· 0 1 / ! . ~ ~ I Z Q I # , I IJ P ( ~ t O J f .. ll. . l l t ~~ ~ ~ ~ ~ . I I I I . E l ! . . . , CV I ' P J I I ! t J I LI I I P I ' O t t ~ I £ D J f l i E M - l t t L L C . o .. .. 0 .. ""S . , " " ' " " " " " 1 ... ,._ """ j 2·S 1 .. , _ I ' -~ -~ sl II ,,.. . J ~l : N ~ = - - CL O S r ,,.. . . . . . , 'f .. til • 2·C B 1 I? M ; , . ~( . ·· · · ' ·· -- -- - · ~~ . -~ · · .. t .. i •, rR I P ~ro c M i i<' M:J < r()A f -~ - - -~ ... . ·_J ~ ·- · '1 ... "t- -1" " .. . . 2-s l ! p- ~ ? : : ; - - , : •, 1 '! ·,1 12 0 0 <5 ~@@ @ @ ® 2- C T t - S tj. _ S1 l l -- - f StS .B . E C K I I ' I T H . •3 • r.OA • _ . I _ , =r __ .. -.. -- - 1 I I AV R ! .. . _ .. _ .. .._ (A V R • AU T O VO l T A G E R(G U l J , T O R ) .. .... . . . . . , ~-~ ~ '- n : . . : m ~ , \ .. NG I N E ~~ ~ .. -- - 1 ~~ " .1 - 2 -- 2 \~_-· ... ~~ G l L FMA N ~ 8 PI736B ~Technical Data Sheet PI 73GB SPECIFICATIONS & OPTIONS STAMFORD f.j.@§l grnsntiwfl STANDARDS Newage Stamford industrial generators meet the requirements of BS EN 60034 and the relevant sections of other national and International standards such as B$5000, VDE 0530, NEMA MG1-32, IEC60034, CSA C22.2-100, AS1359. Other standards and certifications can be considered on request. DESCRIPTION The STAMFORD PI range of synchronous ac generators are brushless with a rotating field .. They are separately excited by the STAMFORD Permanent Magnet Generator (PMG). This Is a shaft mounted, high frequency, pilot exciter which provides a constant supply of clean power via the Automatic Vollage Regulator (AVR) to the main exciter. The main exciter output is fed to the main rotor, through a full wave bridge rectifier, protected by surge suppression. VOLTAGE REGULATORS The PI range of generators, complete with a PMG, are available with one of two AVRs. Each AVR has soft start voltage build up and built in protection against sustained over-excitation, which will de-excite the generator after a minimum of 8 seconds. Underspeed protection (UFRO), is also provided on both AVRs. The UFRO will reduce the generator output voltage proportional to the speed of the generator below a pre- sellable level. The MX341 AVR is two phase sensed with a voltage regulation oft 1 %. (see the note on regulation). The MX321 AVR is 3 phase rms sensed with a voltage regulation of 0.5% nns (see the note on regulation}. The UFRO circuit has adjustable slope and dwell, for controlled recovery from step loads. An over voltage protection circuit will shutdown the output device of the AVR, it can also trip an optional excitation circuit breaker if required. As an option, short circuit current limiting Is available with the addition of current transformers. Both the MX341 and the MX321 need a generator mounted current transformer to provide quadrature droop characteristics for load sharing during parallel operation. Provision Is also made for the connection of the STAMFORD power factor controller, for embedded applications, and a remote voHage trimmer. WINDINGS & ELECTRICAL PERFORMANCE All generator sta.tors are wound to 2/3 pitch. This eliminates triplen (3rd, 9th, 15th ... ) harmonics on the voltage waveform and Is found to be the optimum design for trouble-free supply of non-linear loads. The 2/3 pitch design avoids excessive neutral currents sometimes seen with higher winding pitches. A fully connected damper winding reduces oscillations during paralleling. This winding, with the 2/3 pitch and carefully selected pole and tooth designs, ensures very low levels of voltage waveform distortion. TERMINALS & TERMINAL BOX Standard generators feature a main stator with 6 ends brought out to the terminals, which are mounted on the frame at the non-drive end of the generator. A sheet steel terminal box contains the AVR and provides ample space for the customers' wiring and gland arrangements. It has removable panels for easy access. SHAFT& KEYS All generator rotors are dynamically balanced to better than B$6861 :Part 1 Grade 2.5 for minimum vibration in operation. Two bearing generators are balanced with a half key. INSULA TIONnMPREGNATION The insulation system is class 'H', and meets the requirements of UL 1446. All wound components are impregnated with materials and processes designed specifically to provide the high build required for static windings and the high mechanical strength required for rotating components. QUALITY ASSURANCE Generators are manufactured using production procedures having a quality assurance level to BS EN ISO 9001. NOTE ON REGULATION The stated voltage regulation may not be maintained in the presence of certain radio transmitted signals. Any change in performance will fall within the limits of Criteria 'B' of EN 61 000-6-2:2001. At no time will the steady-state voltage regulation exceed 2%. Note: Continuous development of our products entiUes us to change speclflcaUon details without notice, therefore they must not be regarded as binding. Front cover drawing is lypical of the product range. 2 STAMfORD l,f.BQ§§ grmllrarfan J CONTROL SYSTEM A.V.R. VOLTAGE REGULATION SUSTAINED SHORT CIRCUIT INSULATION SYSTEM PROTECTION RATED POWER FACTOR STATOR WINDING WINDING PITCH WINDING LEADS MAIN STATOR RESISTANCE MAIN ROTOR RESISTANCE EXCITER STATOR RESISTANCE EXCITER ROTOR RESISTANCE R.F.I. SUPPRESSION WAVEFORM DISTORTION MAXIMUM OVERSPEED BEARING DRIVE END BEARING NON-DRIVE END WBGHT COMP. GENERATOR WEIGHT WOUND STATOR WEIGHT WOUND ROTOR WR'INERTIA SHIPPING WEIGHTS in a crate PACKING CRATE SIZE TELEPHONE INTERFERENCE COOUNGAIR VOLTAGE STAR kVA BASE RATING FOR REACTANCE VAW ES Xd DIR. AXIS SYNCHRONOUS X'd DlR. AXIS TRANSIENT X"d OIR. AXIS SUBTRANSIENT Xq QUAD. AXIS REACTANCE X"q QUAD. AXIS SUBTRANSIENT XL LEAKAGE REACTANCE X2 NEGATIVE SEQUENCE Xo ZERO SEQUENCE PI736B WINDING 312 SEPARATELY EXCITED BY P.M.G. MX341 I MX321 I ± 1% r :t 0.5% jWlth 4% ENGINE GOVERNING REFER TO SHORT CIRCUIT DECREMENT CURVES (page 7) CLASS H IP23 0.8 DOUBLE LAYER LAP TWO THIRDS 6 0.0027 Ohms PER PHASEAT22"C STAR CONNECTED 2.33 Ohms at22'C 17 Ohms at 22'C 0.1 Ohms PER PHASE AT 22'C BS EN 61000-6-2 8o BS EN 61000-B-4,VDE 0875G, VOE 0875N. refer to factory for others NO LOAD < 1.5% NON-DISTORTING BALANCED LINEAR LOAD < 5.0% 1500 Rev/Min BALL. 6228 C3 BALL. 6319 C3 1 BEARING 2 BEARING 2680 kg 2830 kg 1108 kg 1106 kg 1260 kg 1197 kg 42.2755 kgm2 41 .2746 kgm~ 2876kg 2900kg 194 x 105 x 154(cm) 194 x 105 x 154(cm) so Hz 60Hz THF<2% TIF<50 1. 79 m•isec 3793 crm 2.3 m'/sec 4874 cfm 380/220 400/231 415/240 440/254 416/240 4401254 460/266 480/277 700 700 700 700 815 875 675 675 2.14 1.93 1.79 1.60 2.58 2.48 2.26 2.08 0.16 0.14 0.13 0.12 0.19 0.18 0.16 0.15 0.11 0.10 0.09 008 0.14 0.13 0.12 0.11 1.37 1.24 1.15 1.02 1.65 1.56 1.45 1.33 0,35 0.32 0.29 0.26 0.42 0.40 0.37 0.34 0.04 0.04 0.03 0.03 0.05 0.05 0.04 0.04 0.20 0.18 0.17 0.15 0.24 0.23 0.21 0.19 0.03 0 02 0.02 0.02 0.02 0.02 0.02 0.02 REACTANCES ARE SATURATED VALUES ARE PER UNIT AT RATING AND VOLTAGE INDICATED T'd TRANSIENT 11ME CONST. 0.144s T"d SUB-TRANSTIME CON ST. 0.0135 T'do O.C. FIELD TIME CONST 1.93s Ta ARMATURE TIME CON ST. o.0163s SHORT CIRCUIT RATIO 1/Xct 3 !Sol ~ / / *" PI736B Winding 312 THREE PHASE EFFICIENCY CURVES v I--:~ ~ -1--. v v ~ --:1--- I'.F. r--1.0 ~ r-- U\) '030 ~40 UO O&G U-G !ll40 UO i€oil ;:'!0 STAMfORD l.).b'tgQ genet"atlon I TOO KVA 400 v 91 I /: ~ I I I =t==:i::j !-----/ ·v t..---~ -:.. / / % / ~ 1.1211 4).30 0 ~ Q.!o l)El) 0 71! O.el! U\9 I~ t to L-------------------------------------------~700K~A 415 v 97 I .. :.. PJ:. ~ 1-' J ./ --_...--~ -~ ~ v--!--" -- ..__._ /v I % o.s '!Iii -~~ -~ P• ~M 0~ ON ~U ~~ 1~ 1a 440 v ~~ ..,.;,-~ -~ ~ l-- / v /. 9!! - !--" 10il 4 700 KvA P.l<. 70 f.lt 0.9 O.B STAMFORD f.J.U@j gener11eion I 416 v tt /. / ·-_/ % % !I') PI736B Winding 312 THREE PHASE EFFICIENCY CURVES _.,... ~ ~ f-- v ,. I - _,_ 1.0 0.9 u· -- Ui:l UO ~AO Uo ~-€i) ln'G D ~ UO UO l '19 8 5KVA 440 v 97 -· - / !--~ r--..- ~ ~ -~ ! -r---r--% .u I v ' !a u~ <1~ e.-o M~ 4$9 or4 oHID uo si!Q t 10 460 V !H ../"' ~ ---~ ~ I.--t- / r -- 93-1)~ 0::10 0:40 OM H~ itl'o 480 v ~t % ~­-> /; ~ , .,..,..... 1--:::: ~ r---1-- / -v 5 ·~- i B7$ KVA - 'Ul 0.9 o.e 875 KVA P.F'. -1 ~~ 1601 ~ 50 r--Hz 30 25' !!> 0 ~ -.: ... 1/ ..# ~ ·!;; I ;;~s .... ~ .... ~ ~10 / !/ v / "' tl." ... 1 5 1/. jf, (I , 0 200 400 r--60 30 Hz I 2.5 ' I ! i. 0 ~0 oc ... g 1.1 .... ~5 lf "" r; ~ s ~1() w ... ;.,._ 11 e lf '/ rA :M~ I ,._ (;I , 0 200 .tOO PI 73GB Winding 312 Locked Rotor Motor Starting Curve 'l.~i 3!10V .oli):()\1 <liSV l/ ..... ...... ~ L' v ~ """ i.o'. ,r I' J ,. .. '" I~ v 1.' ~ 1/. "' ' ..... I lJ' r/ '/ 1/ I I -~ - I ., 600 800 1000 1201) 1400 1600 t.004UHfOTOfU~ :!2{/'1 ;!,;'.,. .I.Ajm' ~ ""' I 1/ ! ..,.. 1.1" ...... I ! t/ ~ !;.<' t..-I ' I I ! ' 6(1() BOO tOOO 1200 Ll:ICKEOAOT-CAkiq. 1400 1Mtl 1000 : 6 STAMfORD ~ I 1800 20..1l(i q;roy :.--1. I ' I I 2000 22Co!J STAMfORD PI736B f,J.h'l§i gen~atlonl Three-phase Short Circuit Decrement Curve. No-load Excitation at Rated Speed Based on star (wye) connection. 100000 -1-.. ---SYWAElRf('.AL --1---· --• • •A&"""'ETmC.U -... t . .. .. ~ -r oooo . . . . r--. - "'-· " ....... t-I 1000 0.001 0.01 0.1 'llME{&•nl 1 10 Sustained Short Circuit = 2,400 Amps 100000 - ---r· --.. r--sYMMETRtCAl -·---'-... --· ----., • • •ASVJ.t.IETRICI\l. t ... . . . . 1;;10000 . ~ . ~ -. .............. r-r--f-' 1000 0.001 0.01 0.1 TM(I«t] 1 10 Sustained Short Circuit = 3,400 Amps Note 1 The following multiplication factors should be used to adjust the values from curve between time 0.001 seconds and the minimum current point in respect of nominal operating voltage : 50Hz 60Hz Voltage Factor v oltage t-aclor 380v X 1.00 416_v X 1.00 400v X 1.()5 440V X 1.06 415v X 1.09 460v X 1.10 440v X 1.16 4BOv X 1.15 .. The suslalrled current value Is constant lrresp~ci!Ve of voltage level Note 2 The following multiplication factor should be used to convert the values calculated in accordance wilh NOTE 1 to those applicable to the various types of short circuit : 3-phase 2-phase L-L 1-phase L-N llnstantaneous X 1.00 x0.87 X 1.30 1\111nlmum X 1.00 X 1.80 x3.20 @!StBine_Q_ X 1.00 X 1.50 x2.50 I Max. susta~nea aurat1on 10 sec. 5 sec. 2sec. All otner times are uncnangea Note 3 Curves are drawn for Star (Wye) connected machines. 7 P1736B SJAifDBD Winding 312/ 0.8 Power Factor lli&ii~J RATINGS Class -Temp Rise Con!. F -1 05t4o•c Cont. H -125/4o·c Standby -1S0/4o•c Standby-163/27"C 50Hz Star (V) 380 400 415 440 380 400 415 440 380 400 -..vA 650 650 650 650 700 700 700 700 730 730 kW 520 520 520 520 . 560 560 560 560 584 584 Efficiency (%) 95.5 95.7 95.8 95.9 95.4 95.6 95.7 95.9 95.3 95.5 kWinput 545 543 543 542 587 586 585 584 613 612 60Hz StarM 416 440 460 480 416 440 460 480 416 440 kVA 750 815 815 815 815 875 875 875 845 910 kW 600 652 652 652 652 700 700 700 676 728 Efficiency(%) 95.5 95.5 95.7 95.8 95.3 95.4 95.6 95.8 95.3 95.4 kWinpul 628 683 681 681 684 734 732 731 709 763 DIMENSIONS &3g 77~-S -~ / . ~ tr --- .......... H ji..--..J ,,....., I/ ~ 1- -tiO~ESD35 _/ 435 c ... 365 &SPIGOT 47& &SPIGOT 6'30 C:l'r. 830 COUPLING DISC 'AN' S.A.EHo18 15,7 S.A.ENo21 0 S.A.ENo24 0 © 2004 Newage lnternalional Limiled. Reprinted wilh permission of N.l. only. Prtnted In England. 1·BRG ADAPTORS S.ii.ENoD S.A.E No DO 295 &SPIGOT 2-BRG ADAPTORS S.A.e NoO SA.ENoOO Bamack Road • Stamford • Lincolnshire • PE9 2NB Tel: 00 44 (0)1780 484000 • Fax: 00 44 (0)1780 484100 Website: www.newage-avkseg.com 415 440 380 400 415 440 730 730 750 750 750 750 584 584 600 600 600 600 95.7 95.8 95.3 95.5 95.6 95.8 610 610 630 628 628 626 460 480 416 440 460 480 910 910 870 940 940 940 728 728 696 752 752 752 95.6 95.7 95.2 95.3 95.5 95.7 762 761 731 789 787 786 970 OVER COVERS TD_PI736B.GB_06.04_01_GB lntertie/Generator Protection Relay M·3410A Integrated Protection System® M-3410A Standard Panel • ~=?> ~~· ED """'-\~--~· 0 0P'.;!"U<JI" •3• ~.1~"-""'· 0 a .. :o.r .... .,, .. M·3UO•\ ">-~:~.-.~,,., ... c C.':ll.Tr.:-.:.~ ~~~QTt&/O~~OR L:;;u·~..! 0 Q ltQVrT:!'.t'~~ .PHOttC'nON eo~ ~:.&;o~'l"' Q Cc.:c,~:~ ~!bii~iiO:t\i"i;,ttr;n·.j ""''"~"-T'I 0 (IH,...-.,;,•,t:. :;:::;;[)-·"-{;"-:.~::. ·::_ ,: I•'''' 0 OrL..>ouo • p,-, -~ ... 0 1:1....-JTIO OlOJ""-"'f M-3410A Horizontal Panel (Optional) CD (0! M-3410A Vertical Panel (OptlonaO • .,.,_.,,;-r.~r·"\10 @ • • Facilitates standardization for small/medium intertle and generator protection applications • Microprocessor-based relay provides 15 protective relay functions, Including Sync-Check, 2 programmable outputs and 2 programmable inputs • Relay voltage inputs can be directly connected (no VT required) for voltages 480 V or less PROTECTION • Local and remote serial communications {MOD BUS protocol) capability for monitoring and control functions M·3410A lntertie/Generator Protection Relay Protective Functions • Sync-check wtth Phase Angle, tJ. V and ilF with dead line/dead bus options (25) • Phase undervoltage (27) protection • Ground undervoltage (27G) protection • Dual-setpolnt, single or three phase, directional power detection that can be selected as over/ under power protection (32) • Dual-zone, oHset·mho loss-of-field for generator protection (40) • Sensitive negative sequ~nce overcurrent protection and alarm (46) • Negative sequence ovarvoltage (47) • Inverse time neutral overcurrent (51 N) • Phase overcurrent with voltage restralnVcontrol (51 V) protection • Phase overvoltage (59) protection • Ground overvoltage (59G) protection • Peak overvoltage (591) protection • VTfuse-loss detection and blocking (60FL) • Reconnect enable for intertie protection (79) • Four-step over/under frequency (81) protection Standard Features • 2 programmable outputs, 2 programmable inputs, and 1 self-test output • OsciUographlc recording (COMTRADE file format) • Time-stamped sequence of events recording for 32 events • Metering of Voltage, Current, real and reactive Power, Power Factor, Frequency, and Positive Sequence Impedance • One RS-232 port (COM1) on front and one RS-232 or485 port (COM2) on rear • M-381 OA I PScome For Windowsm Communications Software • M-3811 A IPScom For Palm os• Communications Software • MODBUS protocol • Supports both 50 and 60 Hz applications • Accepts 1 A or 5 A rated CT inputs • Relay voltage Inputs can be directly connected (no VT requfred) for voltages ~480 V ac • Continuous Self-Diagnostics Optional Features • M-3801C IPSploPOscillographAnalyslsSoftware • Horizontal and Vertical panel mount versions available (see Figures 2 and 4) -2- M-3410A lntertleiGeneratorProtectlon Relay Tests and Standards The M-341 OA Generator/Jntertie Protection Relay complies with the following type tests and standards: Voltage Withstand Dielectric Withstand All terminals except power supply and status Input contacts, 2500 V ac/3500 V de Power Supply and Status Input Contacts: IEC 60255-5 i ,500 V de for power supply voltages (12, 24, 48 V Inputs) 2500 V ac/3500 V de for power supply voltages ( 120 V ac/125 V de Input) • NOTE: Digital data circuits {RS-232/485 communication ports) are excluded. Impulse Voltage Power Supply Input Voltages, 120 Vac/125 V de: IEC 60255-5 5,000 V pk, +1-polarity applied to each Independent circuit to earth 5,000 V pk, +1-polarity applied between lndepandentcircults 1.2 )lS by 50 J.LS, 500 ohms Impedance, three surges at every 5 second interval • NOTE: Digital data circuits (RS-23~1485 communication ports) are excluded. Power Supply Input Voltages1 12, 24,48 V de: IEC 60255-5 3,000 v pk, +1-polarity applied to each Independent circuit to earth 3.000 V pi<, +1-polarity applied between independent circuits 1.2 fJS by 50 flS. 500 ohms Impedance, three surges at every 5 second Interval • NOTE: Digital data circuits (RS-2321485 communication ports) are excluded. Insulation Resistance IEC 60255-5 > 40 Megaohms • NOTE: Digital ~ata circuits (RS-232/485 communication ports) are excluded. Electrical Environment Electrostatic Discharge Test IEC 61000-4-2 Class 4 ( :t8 kV) -point contact discharge and all' discharge a NOTE: Digital data circuits (RS-232/485 communication ports) are excluded. Fast Transient Disturbance Test IEC 61000-4-4 (±2 kV, 5kHz) AC Power Supply Input ( ± 1 kV, 5 kHz) RS-232, RS-485 and ground Surge IEC 61000-4-5 (±2 kV, 1 .. 2 fJS by 50 fJS line to ground) AC Power Supply lnput ( ± 1 kV, 1 .2 J.1S by 50 fJS line to line) AC Power Supply Input (± 1 kV, 1.2 fJS by 50 JlS line to ground) RS-485 Port Surge Withstand Capability ANSIIIEEE 2,500 V pk-pk Oscillatory each independent circuit to earth C37 90.1 2,500 V pk-pk Oscillat<;>ry between each independent circuit 1989 5,000 V pk FastTransient each independent circuit to earth 5,000 V pk Fast Transient between each Independent circuit • NOTE: Digital data circuits (RS-232/485 communication ports} are excluded .. II :,....-"' -/ 880(!] :s ~·· I ~$ I ::. ·~ 0 [][D[l)!li] j o r-~, r ~ []ffi00 w illill00 f-----1 > • ffi(LD m f---El~BEIE EJElEI~!!l 888~!) [!} z 889 D 6JEI DC EIB u__ BEl .o i!]Ci] l! .!. 0 lstruzioni di installazione ed esercizio Instructions for installation and service ITSCB 601933/001 il-en 6-97 ABBSACE lstruzioni di installazione, di esercizio e di manutenzione per interruttori automatici aperti di bassa tensione Installation, service and maintenance instructions for low voltage air circuit-breaker SACE Emax Alii II jl I'll' 12. Unita di protezione PR111 /LI -LSI -LSIG 12.1 Generalita L'unita SACE PR 111/P reatizza Ia seguenll runzionl di protezione: l -prolezlone da so~~~accerico a tempo lungo lnverso S -proteziona da corto circullo a tempo breve I -protezione da curto clrculto lstantaneo G -protezlone da guasto a terra finst -pratezlone a soglia Iissa da corte circu~o Le unita SACE PR111 dlspo:llbl\1 all'utente sono: PR111/L+l+llnst 12. PR111/LI-LSI-LSIG protection unit 12.1 General The SA CE PR1111P tm/1 carries out tho following protection functions: L. prolfJction against overload with /nYat5·e long trme-detay S protection ogainsL short-tim" short-cirt:uit I -protection against Instantaneous short-circuit G -ptotecOon ligalnsl earth fault lfnst -mpfd protection agalnsl inslllntaneol.ls shorl-cfrcu/1 The SACE PR 111 units FWBilabla to the user are: PR111/L+S+I+llnst PR111/L+S+I+G+llnst Fig. 47 Le prolezioni possono essere realizzate in modo lrifase o trifase con neutm a secom!a del lipo dllnterruttore lmplegato (lrlpolara. tetrepotare o lripolare ao11 neutro e!llemo). ~unltA, e autoalltnentata·e garenfisce il corretto 1Wi21onainento c!elle runzlonl dl protaziono In p•esenza di una oommte maggiore·o uguale-af 1 8% del val<;>re nominate del trasformatore amperomelrico dl lose (T A). L'assleme sgancialcru c,li Jlfoleztone e c:osl composto: -3 o d trasfarmalori di cortontc (T A) -unitil dt prowzlone SACE PR1 11 -un solenoids dl apertura (SA) dello sganciatore (j\ mas sima corrente che aglsce direttamente sui comando de!l'interrunore _ Mod. IM4379 I I Rev. I I I Thlil proleallons C81J·bo marie either In lhre&-phass or tl'lre&-ph"ifSB wflh neutral modo, depending on the /yfHlof drcvlt-bteakerusod (thrGR-!JOI9, fuur-pole or three-pole IVith extamalneutml), Thli unit Is self-powen>d .:~nd ensur~ correcl opera/ion of /he prolec­ tiOn flm~lfons whrurlllete Is a cummt lrlgl•errflan oroquatro 18% of!/1e rattJd phase currant lr.tnsloJmer il:~tua (CT). Tho proleclion releasll asssmbly consists of lfte following: -3 or 4 CUm1nr /ronsforrooro /CT) -SACE PR111 protectt1111 un/1 -an opening solenoid (OS) of the overcumml release which ac/s direclly an the c;irr;uit-breaker aperaling mechanism. Apparocchio SACE Emax Sc<lla Apparatus Scala N'Doc 601933/001 N' ppa. Dor:.NO-$1r.l-JD. ~lJUJI 12.S Curve di lntervento 12.8.1 Curve dllntervenlo protezlone "L" ' 0 100 • ' .. - 10 ., . I 3Cittt.1 '·' l) 12.8.2 Curve dllntervento protozlone "I" ~I • : .. 1110 ' .0 !0 ID' tO ' ·- • ~1 ,, ·~ Mod. IM•I379 I Rov. f I 12.8 Trip curves 12.8.1 Trip curves of protection "L" ~ !'.. i'~ !'.. I'.: !'., -....._ I' " "'!'..'~ "' I" .. . • 12.8.2 Trip curves of protecllon nl" • -t.• D.t M 0 I 0,10.01 l,t '·' > ' . ' I I f: Iii tO ~~ " "' " '' I Appouocc,liO I Appar~lus SACEEmax N"OI)C. Doc. No 601933/001 T olletanza sulle sog~e di intervento L • ± Sganclo Ira 1,05 c 1.3 11 (secondo le Norme1EC!l47-2) I = ot20% Trip threshold tolerance L "' Relsssobotween 1.05 8nd1.3/1 (lrtcofff(]{Jif­ ity with IEC 94 7-2 standards) =±20% T olleranza sui lempl di In· lervenlo L .. ± 10% (20% per 1~2 x lnl I ~ ± ~0% Trip time loforancss l ~ :t 10% (20% psf/>2 X In) I =~20% Logenda In • Corrente nomN!edei trasformatorl di c.Jr­ reniB t = lempo dllnlerven\o Caption In • Ralod cumm! of cur­ !Mflrbn&fonnsrs r ~~rrlpfime ~~· Scale N'P>o Sit, Nil. 03/100 12.8.3 Curve di intervento protezione "S" IISJ JOO ~~ j >00 100 I . "' • 10 tO"' "'1-r--. I 2 " I ~-"' "' ' OA ·''-"' • I() !DO ~~ ~ 100 41 . 1!0 l 20 ' tO ' ' I O.i ... '·' ~ ..• Mod, IM4379 I I Rl•. I I I 12.8.3 Trip curves of protection "S" ~ ~ ~ -~ [4 i) " ""' 1'- "' '"' I' "' I X • l~ I) . . • ... /lppoteoel1ia Apf"'(ahls SACE Emax N"Doc. 601933/001 Doc. No. 1 oHeranza sUite sogio ~I ln18MI!llo s = t 10% /rip threshold inl6rance .>= .t 10~ Toller•nzs sui tempi dl in­ lervento s~ ~ 2o% Ttip limelol6~ces s 0 .t20l6 ltgonda In= Corrun1enomlnaledei uasformatori di cor· rente t = tempo dl lntervento Caption In • Rsctxl currsnt of cur· f9IJ1 lransfDrmRrs I • lr/ptrms S<;ala Scale ~;~ ..,"' 12.8.4 Curve di intervento protetione "G" 12.8.4 Trip curves of protection ''G" :{:tl ""''" ( (~ (~ I~ ; 700UII >GO I .0 "' ,,. 10 "' •< ~ " u,of----lf---l--+-i--H-H-H-t--if---1---t-l-+t-Hl-H--t-1--l--l I.N?~.Ic----oo'=2--!,a ,,---!M~O.~>'""o.a~•J.,,,-!D-::l0'=0-!-1 -'uL,---',-=,,__j,'---':-__j:-!-, --!-, -,,!--!-.-!,,...,.1:-!,>=-,-!:,i,-. --:.,~-._cf:--,-'1. MD<L IM4379 I I Appaoe@lo R~v. I I I App&tD:Us SACEEmax N'Ooc. Dor.Nu. 601933/001 Tolrerahza sutle ~glle dl interYenlo G= ± 20% Tolferanz:a sui tempt di in. tetvenlo Gz±20% Trip rtme tolsrances G=r20% Legonda In= Corren!e nomlnale <1<0 trssformatof1 di a>r· renlo ' = 1empo di lnt.ervento Caprlon In= Rated CUffent nf cur· t81Jt transformers t = tr/pNme SClllol Seal~ Jt'P~ sn.~ r;!!ll()l) CURRENT TRA.NSFORMERS }flindow Diameter 3.25" Models 3360 RW & SH. Fully encapsulated. Jndoor/outdoor applications. Standard 5·amp secondary. Others available. JE"B "07...,.3 ... ~ ....... t. 5.75~ 3360R\V-** " Flexible le-<~.ds are UL 3173 12.5 degree C. CSA approved, #16 A WG 24" long · ea Non-Standard length to be specified. co Terminals are brass No. 10~32 UNC o Mounting bra.okcts optional, orde,r No. rl:iO-MBK. o Approxim-llte weight J Ibs:. q Additional ratios avaHable. CATALOG NUMBER **-JOO ·~-400 **-500 ,..*=-~oo ••~7SO **-ROO •"'-l OO!J · <!.*-li&t> ~ **~1 5.00 ;jl*'-1600 **'-?rinn ll"*-c?'\{}(i **-1/)00 - *'*.1.'ifln ~·*.4000 - APPLICATION: Ft1T AmrueteJS, Watthour Meters, Wattmeters, Relays, · CONTINUOUS THERMAL RATING: 1.33 at JO C. amb._; 1.0 at 55 C. amb. INSULATION CLASS: 0.6 kV. BIL IOkV. fuH \Vave. 50-400Hz. C€ Jml Ill l : 1.2.501! ~"·oo . . .J) 3360SH-** . CURREN'T V.A. FOR ANSi METERING CLASS AT 60 H~ RATIO -t--)~ .. h A~!PERES ~ CLASS BOJ B0.2 .B0.5 B0.9 B1.8 300j 150 0.6 -06 L2 2.4 ~ -400:5 25 0 0.3 06 t.2 T ?. - 500·$ 35 0 03 01 06 T2 24. 6005 5.o]} OJ f)3 0.6 l 2 1.2 ?so:s 500 03 03 0.3 06 l? 800:5 6ffo OJ 0.3 OJ on 1 ., 1000·5 75.0 -:oJ 03 0 j 06 0.6 120tYS --'liJ) ~Q_3 0.3 03 01 06 tS00-5 900-tlJ OJ 0) fl 06 lflOO·:'i ·ru; 0 i Q" .J)3 OJ 0~ 06 ?ru\fi·"i ·· 1----·U Q"''~'-~-<-.~:... ~-. ,1' n,. . ni 01 , __ .. lDQO, .-D.J---0 ?'iOO·'i _j_Q.{L(L 0 l . 01 01 () 1 01 - 300!)·~ tJnn o 1 . __ Jl..L 1-· en 01. 1)1,• 1.~(i(l·" 1 1(1_0_ _j)~+-·0.3... F---fl "\. {ll 01 ~000:5 .. 1200 0.3 0.3 . 0.1 03 fH Made in the United States of Americ-a 29 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 6 Small Gen Feasibility Study Agreement Swager Fanns Project# 268 Feasibility Study Agreement THIS AGREEMENT is made and entered into this __ day of S:?y -\em0e( 2008 by and between 1-\-VIdgotf (onp<li'D\.-t-.'on , a Cocfl'>lfc'-h.\)V' organizedand existing under the laws of the State of __ ..I.(IA.v.L .... I{\...,(....._b-"'u'~~J-\-zl-'-=v'-'"=----------~ ("Interconnection Customer,") and Idaho Power Company a Corporation existing under the laws of the State ofldaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be refened to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by Interconnection Customer on 9/10/08, also known as Project# 268; and WHEREAS, Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; and WHEREAS, Interconnection Customer has requested the Transmission Provider to perfonn a feasibility study to assess the feasibility of interconnecting the proposed Small Generating Facility with the Transmission Provider's Transmission System, and of any Affected Systems; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause to be perfonned an interconnection feasibility study consistent the standard Small Generator Interconnection Procedures in accordance with the Open Access Transmission Tariff. 3.0 The scope ofthe feasibility study shall be subject to the assumptions set forth in Attachment A to this Agreement. 4.0 The feasibility study shall be based on the technical infonnation provided by the Interconnection Customer in the Interconnection Request, as may be modified as the result of the scoping meeting. The Transmission Provider reserves the right to request additional teclmical infonnation from the Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the feasibility study and as designated in accordance with the standard Small Generator Interconnection Procedures. If the Interconnection Customer modifies its Interconnection Request, the time to complete the feasibility study may be extended by agreement of the Parties. Page 1 of3 Small Gen Feasibility Study Agreement Swager Fanns Project# 268 5.0 In perfonning the study, the Transmission Provider shall rely, to the extent reasonably practicable, on existing studies of recent vintage. The Interconnection Customer shall not be charged for such existing studies; however, the Interconnection Customer shall be responsible for charges associated with any new study or modifications to existing studies that are reasonably necessary to perfonn the feasibility study. 6.0 The feasibility study report shall provide the following analyses for the purpose of identifying any potential adverse system impacts that would result from the interconnection of the Small Generating Facility as proposed: 6.1 Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; 6.2 Initial identification of any thennal overload or voltage limit violations resulting from the interconnection; 6.3 Initial review of grounding requirements and electric system protection; and 6.4 Description and non-bonding estimated cost of facilities required to interconnect the proposed Small Generating Facility and to address the identified short circuit and power flow issues. 7.0 ' The feasibility study shall model the impact of the Small Generating Facility regardless of purpose in order to avoid the further expense and inten-uption of operation for reexamination of feasibility and impacts if the Interconnection Customer later changes the purpose for which the Small Generating Facility is being installed. 8.0 The study shall include the feasibility of any interconnection at a proposed project site where there could be multiple potential Points of Interconnection, as requested by the Interconnection Customer and at the Interconnection Customer's cost. 9.0 In lieu of Feasibility Study deposit, Interconnection Customer agrees that study funds will be drawn from the application fee for the perfonnance of the Interconnection Feasibility Study. Transmission Provider shall charge and Interconnection Customer shall pay the actual costs of the Interconnection Feasibility Study. Any difference between the deposit and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate. Page 2 of3 ·. Small Gen Feasibility Study Agreement Swager Fanns Project # 268 10.0 Once the feasibility study is completed, a feasibility study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the feasibility study must be completed and the feasibility study report transmitted within 30 business days of the Interconnection Customer's agreement to conduct a feasibility study. 11.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 12.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 3 0 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Idaho Power Company-Delivery Signed----'---~-a-v._<::_. -~--·· __ -----.._ ____ _ Signed._-?~~. ~2:5;:;::• :;::2~===------- Printed Ma-rc (o.:t1-e r .SovJ Printed f vk -::::J.U"'C~ S Title .t;_, ata:rry i.eaelc." ~Ti D f'611tr~ Title tktM f1~1ol#nfYn-f /!);.,....-~ v I ? Date 7/zr/o ,}' Page 3 of3 Small Gen Feasibility Study Agreement Swager;_farms Project# 268 Attachment A to Feasibility Study Agreement Assumptions Used in Conducting the Feasibility Study The feasibility study will be based upon the inform ation set forth in the Interconnection Request and agreed upon in the scoping meeting held on 9 I.Z.'l/C!8 , : 1) Designation ofPoint of Interconnection and configuration to be studied. ~l(t(r ~ -~~'A.\(<'\~ ~i~.!.iry ·nb 7 e 5 [{troA.( ): B(.L/t/J ID ~ 350 r tl'!·.e ex/<MJid"t.. .OV\ Afil ,d --~il.loro • · ..... J .t/'a,.._ )2h.vcC<.,iskbufn ... ?eech/' Ct.<Jvt~rtJI.<.. 2) Designation of altemative Points of Interconnection and configuration. 1) and 2) are to be completed by the Interconnection Customer. Other assumptions (listed below) are to be provided by the Interconnection Customer and the Transmission Provider. /11&.--xlh"-'-<--~V--6ufpt;/-//4t.tled -4 /.ZMW, / J_ L J I by /dc.l.o fbt-oJ.V ( /i lev co"' -'l.c. c:f -frah. .. !d"/' /'YJ<;r -rv tTf2. jl /'vv'l GJ vu:J ~-A Lu y'<! -w ~ e CJ"·"'d t!..vt r: r (JI'·a.:fu /\. , Page 1 ofl \.C ,.-.1 ~ ~ 00 9 .... """"" ..= = ~ z Q Q 00 ~ ~ t- Q t-~ I l;l'.l e ~ ~ ~ ~ ~ ~ ~ ~ j I I '[ 1 I I BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 7 CP GENERATOR INTERCONNECTION FEASIBILITY STUDY For integration of the proposed SWAGER FARMS DAIRY DIGESTER PROJECT In TWIN FALLS COUNTY, IDAHO To the IDAHO POWER COMPANY ELECTRICAL SYSTEM For ANDGAR CORPORATION The INTERCONNECTION CUSTOMER FINAL REPORT NOVEMBER 13, 2008 LO Introduction Andgar Corporation has contracted with Idaho Power Company (IPCO) to perform a Generator Interconnection Feasibility Study for the integration of the proposed 1.2 MW digester project at Swager Farms (project #268). The proposed location of the project is in Idaho Power's southern Idaho service territory in Twin Falls County at 3800 North 1707 East. See Appendix B for general location map of project area. This report documents the basis for and the results ofthe Feasibility Study for the Swager Farms Project. It describes the proposed project, the study cases used; estimated costs for interconnection and determination of project interconnect feasibility. 2.0 Summary The proposed small generation project is a 1.2 MW biogas generation project consisting of two 600 kW Stamford PI736B synchronous generator units. The generation project will connect to the IPCO owned Clover 012 (COVR-0 12) 12.5 kV distribution feeder. The upgrades to this feeder needed to connect this project include a 350' line extension, transformer and capacitor bank installations, as well as a generation interconnection and protection package. The estimated cost to interconnect this generation project to Idaho Power's system is $316,250. This feasibility study indicates the existing 46 kV transmission system does currently have the capacity for the 1.2 MW output of the digester project. However, there are limitations in the Midpoint West transmission system to the north and west of this area. There is no available transmission capacity for this project in the Midpoint West system when considering other proposed generation projects ahead of this one in the queue. An existing study is attached as Appendix C which details the existing system limitations and describes the improvements necessary to increase the capacity of this system another 330 MW. However, this proposed capacity is already committed to other proposed generation projects currently ahead of this one in the queue. 3.0 Scope of Interconnection Feasibility Study The Interconnection Feasibility Study was done and prepared in accordance with Idaho Power Company Standard Generator Intercotlllection Procedures, to provide a preliminary evaluation of the feasibility of the interconnection of the proposed generating project to the Idaho Power system. As listed in Section 5.0 of the Interconnection Feasibility Study agreement, the Interconnection Feasibility Study report provides the following information: preliminary identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; preliminary identification of any thermal overload or voltage limit violations resulting from the interconnection; and preliminary description and non-binding estimated cost of facilities required to interconnect the Small Generating Facility to the Distribution System and to address the identified short circuit and power flow issues. 2 All other proposed Generation projects prior to this project in the Generator Interconnect queue were considered in this study. A current list of these projects can be found on the Idaho Power web site as follows: http://www.oatioasis.com/ipco/index.html. 4.0 Description of Proposed Generating Project The Swager Farms biogas project proposes to connect to the Idaho Power distribution system for an injection of 1.2 MW (maximum project output) using two 600 kW Stamford PI736B synchronous generator units. 5.0 Description of Transmission Facilities The 1.2 MW Andgar biogas generation project at Swager Farms Dairy in Twin Falls County, Idaho will connect IPCO's Clover 012 (COVR-012) 12.5 kV distribution line. The Clover substation is served by Idaho Power's Dale -Twin Falls 46 kV transmission system. There is adequate capacity on this 46 kV transmission system to serve this project. This feasibility study has identified limitations in the Midpoint West transmission system to the north and west of this area. There is no available transmission capacity for this project in the Midpoint West system when considering other proposed generation projects ahead of this one in the queue. An existing study is attached as Appendix C which details the existing system limitations and describes the improvements necessary to increase the capacity of this system another 330 MW. However, this proposed capacity is already committed to other proposed generation projects currently ahead of this one in the queue. 6.0 Description of Substation Facilities The substation serving the area around Swager Farms Dairy is IPCO's Clover (COVR) substation, which is located near the intersection of 3350 N. and 1950 E. in Twin Falls County. The existing substation transformer is a 46:12.5 kV, 4.69 MVA transformer. This study indicates there is adequate capacity at COVR substation for the 1.2 MW biogas project. 7.0 Description of Distribution Facilities The 1.2 MW Andgar biogas generation project at Swager Fanus Dairy in Twin Falls County, Idaho will connect to IPCO's COVR-012 12.5 kV distribution line. There is adequate capacity on this distribution line to serve this project. However, the project will have to run at a power factor between 80% and 88%, lagging. In other words, it will have to absorb between 650 kV AR and 900 kV AR, especially during periods of light loading. A capacitor bank will have to be added for compensation purposes due to the facilities lagging power factor. Since it will be running between 80% and 88% power factor, 650 kV AR to 900 kV AR will need to be generated. That V AR flow will come from a 900 leV AR capacitor bank located near the intersection of 3550 N. and 1700 E. This location eliminates high voltage 3 concerns which would have become an issue if the bank were placed closer to Swager Fanns Dairy. Other additions include a line extension and transfonner addition at the POI. The line extension will be 350' long and comprised of#4 ACSR conductor. The transformer will be a 1500 kVA 12.47 kV:480 V padmount transformer. Since the biogas generation project is served by a feeder that also serves other Idaho Power customers, and to minimize the risk of islanding the generator with local load, a generation interconnection and protection package will be required at the point of interconnection (POI). This package includes a 12.5 kV recloser, controls, CTs, PTs, and communications per Idaho Power's standard for generators connected to the distribution system. 8.0 Circuit Breaker Short Circuit Limits The maximum available fault current with the Andgar 1.2 MW project connected is about 6000 Amps at the POI. The 12.5 kV breakers at COVR substation are rated for 18 KAIC. This feasibility study ·indicates that there is adequate short circuit interrupting capability on these breakers for the addition of this generation project. 9.0 Site Load At the generating site, 75 kW of load has been studied for insertion prior to generation. There will be no required upgrades to add the 75 kW of load at Swager Fanns. 10.0 Cost Estimate The estimated costs to interconnect the 1.2 MW biogas generation project by Andgar at Swager Farms Dairy in Twin Falls County is $316,250. These upgrades are listed in the following · Table. Description Estimated Cost One 1500 kVA 12.47kV:480 V padmount transformer, 900 kV AR capacitor bank and 350' of new line at POI $91,250 Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs, and communications $225,000 Total Estimated Cost $316,250 Table 1: Cost Estimates 11.0 Description of Operating Requirements In addition to the upgrades listed in section 8.0 of this report, the proposed project must meet several operating requirements. The project must be controlled to operate at a lagging power 4 factor between 80% and 88% or meet the voltage schedule provided by Idaho Power. If this requirement can not be met, further voltage studies will be necessary. Voltage flicker at startup and during operation will be limited to less than 5% as measured at the point of interconnection. For this to occur, the generation facility can not exceed 50 Amps during start up at the 12.5 kV voltage level. This forces the generating facility to start their generators separately. The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems. The project must also limit the ground fault current at the point of interconnection to 20 Amps. See Appendix A for more details 12.0 Conclusion The requested interconnection of the 1.2 MW And gar Biogas project located at Swager Farms Dairy in Twin Falls County to Idaho Power's system was studied. The results of this study indicate that it is feasible to connect this project to the existing Idaho Power system. A transmission system impact study is required for this project to determine any additional transmission system upgrades required but not detailed in this feasibility study report. 5 APPENDIX A A-1.0 Method of Study The Feasibility Study plan inserts the Project up to the maximum requested injection into the selected Western Electric Coordinating Council (WECC) power flow case and then, using Power World Simulator Version 11, examines the impacts of the new resource on Idaho Power's transmission system (lines, transformers, etc.) within the study area under various operating/outage scenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability of the configurations considered. The WECC case is a recent case modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. For distribution feeder analysis, Idaho Power utilizes Advantica's SynerGEE Software. A-2.0 Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determine under which system configuration modifications may be required: The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating is acceptable. Idaho Power's Voltage Operating Guidelines were used to determine voltage requirements on the system. This states that voltages, under normal operating conditions, are to be maintained within plus or minus 5% (0.05 per unit) of norriinal. Therefore, voltages greater than or equal to 0.95 p.u. voltage and less than or equal to 1.05 p.u. voltage are acceptable. Voltage flicker during starting, stopping or operation of the generator is limited to 5% as measured at the point of interconnection, per Idaho Power's T &D Advisory Information Manual. Idaho Power's Reliability Criteria for System Planning was used to determine proper transmission system operation. All other applicable national and Idaho Power standards and prudent utility practices were used to determine the acceptability of the configurations considered. The stable operation ofthe system requires an adequate supply of volt-amperes reactive (VARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply ofV ARs will result in voltage decay or even collapse under the worst conditions. All customer generation must meet IEEE 519 and ANSI C84.1 Standards. Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by IPC upgrade projects that are either currently under construction or whose 6 budgets have been approved for construction in the near future. All other potential future ratings are outside the scope of this study. Future transmission changes may, however, affect current facility ratings used in the study. A-3.0 Grounding Requirements Idaho Power Company (IPC) requires interconnected transformers to limit their ground fault current to 20 amps at the point of interconnection. A-4.0 Electrical System Protection Guidance IPC requires electrical system protection per Requirements for Generation Interconnections found on the Idaho Power Web site, http://ww.w.idahopower.com/aboulus/business/generationlnterconnectl. A-5.0 WECC Coordinated Off~Nominal Frequency Load Shedding and Restoration Requirements IPC requires frequyncy operational limits to adhere to WECC Under-frequency and Over­ frequency Limits per the WECC Coordinated Off-Nominal Frequency Load Shedding and Restoration Requirements available upon request. 7 APPENDIXB Project #268 Swager Farms A Clover Substation * POl e Capacitor Bank APPENDIXC GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY REPORT for Up to 330 MW of New Generation On the 138 kV Transmission System In the Twin Falls Area to IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM FINAL REPORT June 29, 2007 -1- 1.0 Introduction Multiple new generation projects have contacted Idaho Power Company (IPC) to perform Generator Interconnection System Impact Studies for Network Resource Interconnection Service at 138 kV for the integration of new generation projects in the Twin Falls area. This report documents the basis for and the results of this System Impact Study. Previous studies were performed with these new generation projects being non-dispatchable. This System Impact Study will document the transmission system improvements required if the new generation projects are dispatchable. It describes the backbone transmission system improvements required for Network Resource Interconnection Service of the new generation proposed, the study cases used, outage scenarios assumed, redispatch requirements, and results of all work in the areas of concern. 2.0 Summary The performance of the backbone transmission system was evalu!lted to integrate up to 304 MW of new generation on the 138 kV transmission system in the Twin Falls area. Five phases of transmission system improvements are required to provide 304 MW of new generation Network Resource Interconnection Service. Phase #1: Phase #2: Phase #3: Install an 8 ohm 138 kV Series Reactor on the Upper Salmon-Mountain Home Junction 138 kV transmission line. Without this improvement, the outage of the Midpoint-Rattlesnake 230 kV transmission line results in an overload of the Upper Salmon-Mountain Home Junction 138 kV line with no new generation in the Twin Falls area. This improvement is necessitated by the transmission improvements associated with Generation Project 88, and as a result should be funded by Idaho Power Company-Delivery. This phase of improvements is estimated at approximately $290,000. Install a 4 ohm 138 kV Series Reactor on the Mountain Home Junction-Lucky Peak 138 kV transmission line. Without this improvement, the outage ofthe Rattlesnake-Boise Bench 230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Mountain Home Junction­ Lucky Peak 138 kV line with new generation levels greater than 42 MW in the Twin Falls area. This phase of improvements is estimated at approximately $290,000. Install a 12.35 ohm 138 kV Series Reactor on the Lower Malad-Mountain Home Junction 138lcV transmission line and increase the impedance of the existing Upper Salmon-Mountain Home Junction 138 kV Series Reactor to 26.2 ohms. Without this improvement, the outage of the Midpoint­ Rattlesnake 230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Lower Malad-Mountain Home Junction 138 kV line with new generation levels greater than 94 MW in the Twin Falls area. This phase of improvements is estimated at approximately $290,000. -2- Phase#4: Phase#S: Re-configure the Midpoint-Rattlesnake 230 kV series capacitor bank to allow 1/3 of the compensation to be bypassed via IPC's SCADA system and install a "automatic 1/3 bypass scheme" for overloads exceeding series capacitor's 30 minute emergency equipment rating of 135%. Without this improvement, the outage of the Midpoint-Boise Bench #3 230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Midpoint­ Rattlesnake 230 kV Series Capacitor Bank with new generation levels greater than 153 MW in the Twin Falls area. This phase of improvements is estimated at approximately $100,000. Fold the Midpoint-DRAM #1 230 kV transmission line into the King Substation and install a 230/138 kV 300 MVA transformer. Without this improvement, the outage of the Rattlesnake-Boise Bench 230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Mountain Home Junction-Lucky Peak 138 kV line with new generation levels greater than 156 MW in the Twin Falls area. This phase of improvements is estimated at $10,320,000. Once all five phases of improvements have been completed, the transmission system is capable of interconnecting approximately 330 MW of new generation in the Twin Falls area and serving them on a dispatchable basis. Section 8.0 of this report details the results of studies to quantify generation redispatch requirements following single contingencies on the transmission system. Reductions in the amount of generation which may be redispatched following contingencies, are possible by completing Phase #4 improvements earlier than required or funding optional modifications on the Midpoint-Boise Bench #3 series capacitor bank. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). The proposed cost allocation is subject to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. 3.0 Summary of Interconnection Requests Requests were made to Idaho Power Co. by multiple generation projects in the Twin Falls area to study the interconnection of the proposed generation projects to Idaho Power's transmission system at the 138 kV level for Network Resource Interconnection Service. 4.0 Scope of Interconnection System Impact Study The Interc01mection System Impact Study was done and prepared in accordance with the FERC Order 2003-A, Standard Large Generator Interconnection Procedures, to provide a preliminary evaluation of the System Impact of the interconnection of the proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities of the Idaho Power system to manage this new resource within the study area of the proposed interconnection. -3- 5.0 Description of Existing Transmission Facilities As shown in Figure 1 of Section 7.0, Midpoint Substation, north of Twin Falls, has three 230 kV lines that carry bulk power westward to the Boise area. Midpoint-DRAM #1 line utilizes single 715.5 MCM conductor and has a continuous rating of339 MVA. The Midpoint-Rattlesnake-Boise Bench #2line utilizes a 2 conductor bundle of715.5 MCM. This line has a continuous rating of 677 MV A. The Midpoint-Boise Bench #3 line has similar conductors and the same rating as the Rattlesnake-Boise Bench #2 line. In the Mountain Home area, an additional230 kV line is planned to carry bulk power westward. The Rattlesnake-Bennett Mountain-Danskin-Mora line utilizes single 1272 MCM conductors ( 4 78 MV A) from Rattlesnake-Bennett Mountain, single 1590 MCM conductors (550 MV A) from Bennett Mountain-Danskin and Danskin-Mora. The Bennett Mountain-Danskin-Mora transmission lines are required for the interconnection of Generation Project 88; scheduled to be in-service Spring of2008. In addition to the Midpoint to the Boise area 230 kV lines previously mentioned, there are two 138 kV circuits which can carry power from the Twin Falls area to the Mountain Home area. They are: • King-Lower Malad-Mountain Home Junction 138 kV Line • King-Upper Salmon-Mountain Home Junction 138 kV Line Generators located in the Twin Falls area which are intended to serve load growth in the Treasure Valley area, will be adding new incremental flows on top of existing committed east-to-west transactions across the Midpoint West transmission cutplane. This System Impact study will model approximately 1100 MW of transfers across the Midpoint West cutplane, prior to this proposed generator addition. For these studies, the flow level of the Midpoint west cutplane is defined as the sum of the flows on the following lines: • Midpoint-DRAM #1 230 kV line • Midpoint-Rattlesnake 230 kV Line • Midpoint-Boise Bench #3 230 kV Line • Lower Malad-Mountain Home Junction 138 kV Line • Upper Salmon-Mountain Home Junction 138 kV Line 6.0 Description of Configurations Studied Since the most limiting operating conditions are expected during heavy production on the upper and middle Snake and Boise River hydro plants, with heavy east-west transfers across the Idaho Power transmission system, the injection of the new generation at King 13 8 kV bus was inserted into a power flow case that would simulate committed (approximately 1100 MW) pre-contingency flows on the Midpoint West transmission path. 7.0 Post-transient Study Results This Interconnection System Impact Study Report is for Network Resource Interconnection Service at 138 kV, for numerous proposed generation additions in the Twin Falls area. System transfers across the Midpoint West cutplane are modeled at approximately 1100 MW prior to -4- the proposed transmission improvements or the proposed generators producing any power. Hydro generation production for the Boise & Snake plants, were modeled at heavy, but realistic levels. Output levels for the existing peakers at Dans kin and Bennett Mountain were varied over their operating ranges as appropriate. N-0 and N-1 outage performance for the existing system are recorded. For generation projects which will be dispatchable, generation levels at King 138 kV bus are increased until a transmission system component reaches its 30 minute emergency equipment ratings during N-1 outages. IPC's 30 minute emergency equipment ratings are 115% of continuous thermal ratings on transmission lines and transformers, and 135% on Midpoint series capacitors. The most effective and cost-efficient transmission system improvements are then added to the model and King generation is then increased until30 minute emergency equipment ratings are reached during N-1 outages. Following any N-1 outage, transmission line and transformer loadings which are less than or equal to the 30 minute emergency equipment ratings (115%), but greater than the equipment continuous ratings (100%), must be reduced to the continuous ratings by generation curtailments, redispatch, or some other operating procedure. For the Midpoint series capacitor bankS, following any N-1 outage, similar corrective actions are required for loadings which are less than or equal to the 30 minute emergency equipment ratings (135%), but greater than the equipment 8 hour rating (110%). Various options to correct overloads following N-1 outages will be explored. System following Generation Project 88 The following one line diagram depicts the transmission system with no outages, after the addition of Generation Project 88 and its associated improvements. Midpoint WGst = 1109 MW System following Generation Project 88-No Outages Figure 1 -5- System following Generation Project 88 with N-1 Outages The following one line diagram depicts the transmission system following the addition of Generation Project 88 and its associated improvements in 2008, with no new generation in the Twin Falls area, and the only N-1 outage between Midpoint and the Mountain Home area that results in loadings above continuous thermal ratings on the 138 kV transmission system. Midpoint West"' 1038 MW System following Generation Project 88 -Midpoint-Rattlesnake 230 kV Outage Figure 2 Phase #I Transmission Improvements The Midpoint Series Capacitor banks are capable of 110% of thermal rating for eight ho~rs. A prolonged outage of the Midpoint-Rattlesnake 230 kV line will require a reduction o{transfers across the Midpoint West cutplane to prepare for the next contingency. The overload of the Midpoint-Boise Bench #3 Series Capacitor is less than its 8 hour rating, and will be resolved with the reduction in transfers. As a result, only the overloads on the 138 kV lines between Upper Salmon and Mountain Home Junction are problematic. The most effective and cost­ efficient transmission improvement to alleviate these overloads is the installation of a series reactor on the Upper Salmon-Mountain Home Junction 138 kV line to better balance flows on the transmission network. A series reactor with an impedance of .042 p.u. (8 ohms) alleviates the overloads. Since this N-1 overload condition pre-exists the addition of any new generation in the Twin Falls area, Idaho Power Company will take responsibility to fund this series reactor installation. The following one line diagram depicts the system with Phase #1 improvements added, no new generation in the Twin Falls area, and the same N-1 as Figure 2. -6- Midpoint West= 1038 MW Phase #1 Transmission Improvements -Midpoint~Rattlesnake 230 leV Outage No New Generation Figure 3 Phase #2 Transmission Improvements The following one line diagram depicts Phase #1 transmission improvements and 42 MW of new generation in the Twin Falls area, and the only N-1 outage that results in loadings at or above 30 minute equipment ratings. Mldooint Wast= 1077 MW Phase #1 Transmission Improvements-Rattlesnake-Boise Bench #2 230 kV Outage 42 MW of New Generation Figure 4 -7- The most effective and costMefficient transmission improvement to alleviate this overload is the installation of a series reactor on the Mountain Home JunctionMLucky Peak 138 kV line to better balance flows on the transmission network. A series reactor with an impedance of .021 p.u. (4 ohms) was determined to be the optimal size considering future generation additions. This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #2 improvements added, 42 MW of new generation in the Twin Falls area, and the same N-1 as Figure 4. Please note that generation redispatch will be required following this contingency to reduce loadings to levels which can be acconunodated continuously. Midpoint We!!t = 1075 MW Phase #2 Transmission Improvements-Rattlesnake-Boise Bench #2 230 kV Ou~age 42 MW of New Generation Figure 5 Phase #3 Transmission Improvements The following one line diagram depicts Phase #2 transmission improvements and 94 MW of new generation in the Twin Falls area, and the only NM I outage that results in loadings at or above 30 minute equipment ratings. M8- Mldpp!nl West" 1106 MW Phase #2 Transmission Improvements -Midpoint-Rattlesnake 230 kV Outage 94 MW of New Generation Figure 6 To interconnect generation quantities greater than 94 MW will require additional transmission system improvements. The most effective and cost-efficient transmission improvements to alleviate these overloads are the installation of a new series reactor on the Lower Malad­ Mountain Home Junction 138 kV line and an increase in the impedance of the Upper Salmon­ Mountain Home Junction 138 kV line series reactor. These improvements, referred to as Phase #3, will better balance flows on the transmission network. A Lower Malad-Mountain Home Junction series reactor impedance of .065 p.u. (12.35 ohms) was determined to be the optimal size considering future generation additions. The impedance of the Upper Salmon-Mountain Home Junction series reactor should be increased to .138 p.u. (26.2 ohms). This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #3 improvements added, 94 MW of new generation in the Twin Falls area, and the same N-1 as Figure 6. -9- Midpoint West"' 1099 MW Phase #3 Transmission Improvements-MidpointMRattlesnake 230 kV Outage 94 MW of New Generation Figure7 Phase #4 Transmission Improvements The following one line diagram depicts Phase #3 transmission improvements and 153 MW of new generation in the Twin Falls area, and the only N-1 outage that results in loadings at or above 30 minute equipment ratings. Midpoint WM t : H72 MW Phase #3 Transmission Improvements -Midpoint~Boise Bench #3 230 kV Outage 153 MWofNew Generation Figure 8 -10- To interconnect generation quantities greater than 153 MW will require additional transmission system improvements. If new generation levels exceed 153 MW, and the Midpoint-Boise Bench #3 230 kV line opens, the series capacitor bank on the Midpoint-Rattlesnake 230 kV transmission line may exceed its 30 minute overload capability of 135%. Presently, both the 230 kV series capacitor banks at Midpoint are configured to operate either fully in-service or fully by-passed. The most effective and cost-efficient transmission improvement to alleviate this overload is there-configuration of the Midpoint-Rattlesnake 230 kV series capacitor bank to allow one third of the compensation to be bypassed. In addition, an automatic control scheme should be employed to bypass one third of the series capacitor bank when appropriate system conditions are detected. The re-configuration of the series capacitor bank and the addition of the automatic control scheme is referred to as Phase #4. The following one line diagram depicts the system with Phase #4 improvements added, 153 MW of new generation in the Twin Falls area, and the same N-1 as Figure 8. Midpoint West= 1145 MW Phase #4 Transmission Improvements-Midpoint-Boise Bench #3 230 kV Outage 153 MW of New Generation Figure 9 Phase #5 Transmission Improvements The following one line diagram depicts Phase #4 transmission improvements and 156 MW of new generation in the Twin Falls area, and the only N-1 outage that results in loadings at or above 30 minute equipment ratings. -11- Midoolnt Wast "' 1151 MW Phase #4 Transmission Improvements-Rattlesnake-Boise Bench #2 230 kV Outage 156 MW of New Generation ·Figure 10 To interconnect generation quantities greater than 156 MW will require additional transmission system improvements. If new generation levels exceed 156 MW, and the Rattlesnake-Boise Bench #2 230 kV line opens, the Mountain Home Junction-Lucky Peak 13 8 kV transmission line may exceed its 30 minute overload capability of 115%. The required system improvements are referred to as "Phase #5" and include folding the Midpoint-DRAM #1 230 kV transmission line into and back out of the King Substation and installing a 230/138 kV 300 MV A transformer. This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation intercoooections. The following one line diagram depicts the system with Phase #5 improvements added, 156 MW of new generation in the Twin Falls area, and the same N-1 as Figure 10. -12- Midpoint w.,sr = 1165 MW Phase #5 Transmission Improvements-Rattlesnake-Boise Bench #2 230 kV Outage 156 MW of New Generation Figure 11 Phase #5 transmission improvements are capable of accommodating approximately 330 MW of new generation in the Twin Falls area. The following one line diagram depicts the system with Phase #5 improvements added, 330 MW of new generation in the Twin Falls area, and the loss of the Midpoint-Rattlesnake 230 kV transmission line. At 330 MW of new generation in the Twin Falls area, two other outages also result in transmission system components loaded at their 30 minute emergency equipment ratings. Midpoint West ,. 1272 MW Phase #5 Transmission Improvements-Midpoint-Rattlesnake #2 230 kV Outage 330 MW of New Generation Figure 12 -13- 8.0 Generation Redispatch Requirements Generators which have chosen to be dispatchable are allowed to operate at levels which may create overloads at or below 30 minute emergency equipment ratings following N-1 contingencies. Following any N-1 outage, transmission line and transformer loadings which are less than or equal to the 30 minute emergency equipment ratings (115%), but greater than the equipment continuous ratings (100%), must be reduced to the continuous ratings by generation curtailments, redispatch, or some other operating procedure. For the Midpoint series capacitor banks, following any N-1 outage, similar corrective actions are required for loadings which are less than or equal to the 30 minute emergency equipment ratings (135%), but greater than the equipment 8 hour rating (110%). The following table summarizes generation curtailment requirements for the proposed generation projects modeled at King 138 kV Substation; for various timeframes, and for numerous transmission system single contingencies. The fourth column ofthe table provides information regarding potential benefits of requesting and funding an optional improvement. The improvement evaluated is the re-configuration of the Midpoint-Boise Bench #3 230 kV series capacitor bank to allow one third of the compensation to be bypassed. Unlike Phase #4, no automatic control scheme is contemplated. This Optional Improvement may reduce the magnitude of generation which must be redispatched during a Midpoint-Rattlesnake 230 kV Transmission Line outage. The Optional Improvement is estimated at approximately $50,000. The fifth column of the table provides information regarding potential benefits of completing a portion of Phase #4 improvements early. Phase #4 improvements can be separated into two components. The first component is the "re-configuration" of the Midpoint-Rattlesnake 230 kV series capacitor so it can be operated "fully in-service", "113 bypassed", "2/3 bypassed", or "fully bypassed". The second component was the "automatic control scheme". The Phase #4a improvement contained in the fifth column is for expediting only the "re-configuration" component. Expediting the phase #4a improvement may reduce the magnitude of generation which must be redispatched during a Midpoint-Boise Bench #3 230 kV Transmission Line outage. The Phase #4a improvement is estimated at approximately $50,000. -14- Maximum Maximum Maximum Allowable Allowable Allowable Maximum Generation Generation Generation Allowable After N-1 After N-1 Before Generation w/Optional w/Phase #4a Contingency N-1 After N-1 Improvement Improvement After Phase #1, but before Phase #2 Midpoint-Boise Bench #3 230 kV Line 42MW OMW OMW 42MW Midpoint-Rattlesnake 230 kV Line 42MW 7MW 7MW 7MW Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 42MW 9MW 9MW 9MW kVLine Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 42MW 42MW 42MW 42MW Line After Phase #2, but before Phase #3 Midpoint-Boise Bench #3 230 kV Line 94MW OMW OMW 94MW Midpoint-Rattlesnake 230 kV Line 94MW 9MW 9MW 9MW Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 94MW 32MW 32MW 32MW kV Line Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 94MW 80MW 80MW 80MW Line Mountain Home Junction-Lower Malad 138 94MW 49MW 49MW .49MW kVLine Lucky Peak-Micron 138 kV Line 94MW 45MW 45MW 45MW Danskin 230/138 kV Transformer 94MW 90MW 90MW 90MW' After Phase #3, but before Phase #4 Midpoint-Boise Bench #3 230 kV Line 153MW OMW OMW 153MW Midpoint-Rattlesnake 230 kV Line 153MW 17MW 53MW 17MW Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Dansldn 138 153MW 71MW 71MW 71MW kVLine Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 153MW 120MW 120MW 120MW Line Mountain Home Junction-Lower Malad 138 153MW 129MW 129MW 129MW kV Line Lucky Peak-Micron 138 kV Line 153 MW 84MW 84MW 84MW Danskin 230/138 kV Transformer 153MW 125MW 125MW 125MW Maximum Maximum Maximum Allowable Allowable Allowable Maximum Generation Generation Generation Allowable After NMI After N-1 Before Generation w/Optional w/Phase #4a Contingency NMl After N-1 Improvement Improvement After Phase #4, but before Phase #5 Midpoint-Boise Bench #3 230 kV Line 156MW 156MW 156MW N/A MidiJoint-Rattlesnake 230 kV Line 156MW 18MW 53MW N/A Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 156MW 71MW 71MW N/A kVLine Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 156MW 120MW 120MW N/A Line Mountain Home Junction-Lower Malad 138 156MW 129MW 129MW N/A kV Line Lucky Peak-Micron 138 kV Line 156MW 84MW 84MW N/A Danskin 230/138 kV Transformer 156MW 125MW 125MW N/A After Phase #5 Midpoint-Boise Bench #3 230 kV Line 330MW 140MW 140MW N/A Midpoint-Rattlesnake 230 kV Line 330MW 25MW 123MW N/A Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 330MW 254MW 254MW N/A kV Line Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 330MW 3lOMW 310MW N/A Line Mountain Home Junction-Lower Malad 138 330MW 280MW 280MW N/A kVLine Lucky Peak-Micron 138 kV Line 330MW 265MW 265MW N/A Danskin 230/138 kV Transformer 330MW 295MW 295MW N/A King 230/138 kV Transformer 330MW 245MW 245MW N/A -16- 9.0 Fault Study Results Since this System Impact Study lumps all the proposed generation additions at King 138 kV bus, this Draft Report makes no attempt to address fault study concerns. Each proposed generation project will have to be evaluated individually based on its specific location. 10.0 Transient Stability Study Results The Midpoint West Transmission System is not transient stability limited. Therefore, no transient stability studies were performed. 11.0 Conclusions The System Impact of interconnecting up to304 MW of new generation in the Twin Falls area to Idaho Power's 138 kV transmission system was studied. Five phases of transmission system improvements are required to provide Network Resource Interconnection Service to 304 MW of new generation, on a dispatchable basis. Phase #1 is the installation of an 8 ohm 138 kV Series Reactor on the Upper Salmon-Mountain Home Junction 138 kV transmission line. This improvement corrects an N-1 overload that exists before any new generation is added in the Twin Falls area. As a result, the estimated $290,000 cost of this improvement will be borne by Idaho Power Company. After approximately 42 MW of new generation is added, Phase # 1 improvements are no longer sufficient. Phase #2 improvements require the installation of a 4 ohm 138 kV Series Reactor on the Mountain Home Junction-Lucky Peak 138 kV transmission line. The estimated $290,000 cost of this improvement should be allocated to new generator interconnections. Following the addition of approximately 94 MW of new generation, Phase #3 transmission improvements are required. Phase #3 improvements require the installation a 12.35 ohm 138 kV Series Reactor on the Lower Malad-Mountain Home Junction 138 kV transmission line, and increasing the impedance of the existing Upper Salmon-Mountain Home Junction 138 kV Series Reactor to 26.2 ohms. The estimated $290,000 cost of Phase #3 improvements should be allocated to new generator interconnections. Following the addition of approximately 153 MW of new generation, Phase #4 transmission improvements are required. Phase #4 involves re-configuring the Midpoint-Rattlesnake 230 kV series capacitor bank to allow 1/3 of the compensation to be bypassed via IPC's SCAD A system and install a "automatic 1/3 bypass scheme" for overloads exceeding the series capacitor's 30 minute emergency equipment rating of135%. The estimated $100,000 cost of this improvement should be allocated to new generator interconnections. Following the addition of approximately 156 MW of new generation, Phase #5 transmission improvements are required. Phase #5 involves folding the Midpoint-DRAM #1 230 kV transmission line into and back out of the King Substation and installing a 230/13 8 kV 300 MVA transformer. The estimated $10,320,000 cost of this improvement should be allocated to new generator interconnections. Phase #5 transmission improvements are adequate to interconnect approximately 330 MW of new generation in the Twin Falls area, on a dispatchable basis, before additional improvements are required. APPENDIX A 1.0 Method of Study The study methodology inserts the proposed generators up to the maximum requested output of 304 MW into the selected WECC power flow case and then, using the PowerWorld Simulator powerflow program, examines the impacts of the new resource on Idaho Power's transmission system (lines, transformers, etc.) within the study area under various operating/outage scenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability of the alternatives considered. The WECC case is a recent case modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. 2.0 Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determine the acceptability of the alternatives: Loadings on transmission lines and transformers should not exceed 115% of the continuous rating, immediately following any N-1 outage. Loading on the Midpoint 230 kV series capacitors should not exceed 135% ofthe continuous rating, immediately following anyN-1 outage. These loadings levels of 115% on transmission lines and transformers and 135% on Midpoint series capacitors correspond to IPC's 30 minute emergency equipment ratings. Any loadings immediately following an N-1 outage, less than the 30 minute emergency rating is acceptable. Loadings which are less than the 30 minute emergency equipment ratings, but greater than the equipment continuous ratings, must be reduced to the continuous ratings by generation curtailments, re­ dispatch, or some other operating procedure. Any remedial action schemes (RAS) or other transmission switching, must be judged to be reasonable before the alternatives performance can be deemed acceptable. The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating for transmission lines and transformers is acceptable. Less than or equal to 110% of continuous rating for the Midpoint 230 kV series capacitors is acceptable. Transmission voltages, under normal operating conditions, are maintained within plus or minus 5% (0.05 per unit) of nominal. Therefore, voltages greater than or equal to 0.95 p.u. voltage and less than or equal to 1.05 p.u. voltage are acceptable. The stable operation of the transmission system requires an adequate supply of volt-amperes reactive (VARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply ofVARs will result in voltage decay or even collapse under the worst conditions. Idaho Power designs its system to integrate Network Resources at full capability during specified outage conditions. Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by IPC upgrade projects that are either currently under construction or whose budgets have been approved for -18- construction in the near future. All other potential future ratings are outside the scope of this study. Future transmission changes may, however, affect current facility ratings used in the study. -19- BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 8 November 1 7, 2008 Re: Project# 268, Swager Farms Dear Mr. Juergens:. ® An IDACORP Company Enclosed is a signed System Impact Study Agreement (SISA) for the above-referenced generator interconnection project. Please provide all technical data, if you have not already done so, when you deliver the executed Agreement. Please review the Point oflnterconnection, sign, and return all pages to Candace Gentry, 1221 West Idaho Street, Boise, ID 83702. In order to proceed, we must receive the executed System Impact Study Agreement, and a required $2,000 deposit from you by January 2, 2009, otherwise your application will be deemed withdrawn. The studies will begin on the date we receive your deposit, the signed System Impact Study Agreement, and all required technical data. If the technical data is not provided or if it is deficient, you will be notified and must cure the deficiency within ten (l 0) Business Days, provided, however, such deficiency does not include failure to deliver the executed SISA or deposit. Upon receipt of the executed System Impact Study Agreement, the System Impact Study will be completed within 30 calendar days. During the study period, we will keep you apprised Of our progress. If you have any questions in the meantime, please contact me. Marc Patterson C: R Bishop/IPC Enclosure: Two Signed SISAs (one for your records) P.O. Box 70 (83707) 1221 W.ldaho St. Boise, ID 83702 r, Small Generator System Impact Study Agreement Project# 268, Swager Farms System Impact Study Agreement THIS AGREEMENT is made and entered into this __ day of ______ 2008, by and between , a organized and existing under the laws of the State of , ("Interconnection Customer,") and Idaho Power Company a Corporation existing under the laws of the State of!daho, ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on September 10, 2008, and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a feasibility study and provided the results of said study to the Interconnection Customer (This recital to be omitted if the Parties have agreed to forego the feasibility study.); and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a system impact study(s) to assess the impact of interconnecting the Small Generating Facility with the Transmission Provider's Transmission System, and of any Affected Systems; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause to be performed a system impact study(s) consistent with the standard Small Generator Interconnection Procedures in accordance with the Open Access Transmission Tariff. 3.0 The scope of a system impact study shall be subject to the assumptions set forth in Attaclunent A to this Agreement. 4.0 A system impact study will be based upon the results of the feasibility study and the technical information provided by Interconnection Customer in the Interconnection Request. The Transmission Provider reserves the right to request additional technical information from the Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the system impact study. If the Small Generator System Impact Study Agreement Project# 268, Swager Fatms Interconnection Customer modifies its designated Point of Interconnection, Interconnection Request, or the technical information provided therein is modified, the time to complete the system impact study may be extended. 5.0 A system impact study shall consist of a short circuit analysis, a stability analysis, a power flow analysis, voltage drop and flicker studies, protection and set point coordination studies, and grounding reviews, as necessary. A system impact study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested interconnection service, including a preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection. A system impact study shall provide a list of facilities that are required as a result of the Interconnection Request and non-binding good faith estimates of cost responsibility and time to construct. 6.0 A distribution system impact study shall incorporate a distribution load flow study, an analysis of equipment interrupting ratings, protection coordination study, voltage drop and flicker studies, protection and set point coordination studies, grounding reviews, and the impact on electric system operation, as necessary. 7.0 Affected Systems may participate in the preparation of a system impact study, with a division of costs among such entities as they may agree. All Affected Systems shall be afforded an opportunity to review and comment upon a system impact study that covers potential adverse system impacts on their electric systems, and the Transmission Provider has 20 additional Business Days to complete a system impact study requiring review by Affected Systems. 8.0 If the Transmission Provider uses a queuing procedure for sorting or prioritizing projects and their associated cost responsibilities for any required Network Upgrades, the system impact study shall consider all generating facilities (and with respect to paragraph 8.3 below, any identified Upgrades associated with such higher queued interconnection) that, on the date the system impact study is commenced - 8.1 Are directly interconnected with the Transmission Provider's electric system; or 8.2 Are interconnected with Affected Systems and may have an impact on the proposed interconnection; and 8.3 Have a pending higher queued Interconnection Request to interconnect with the Transmission Provider's electric system. 9.0 A distribution system impact study, if required, shall be completed and the results transmitted to the Interconnection Customer within 30 Business Days after this Agreement is signed by the Parties. A transmission system impact study, if required, shall be completed and the results transmitted to the Interconnection Customer within 45 Small Generator System Impact Study Agreement Project# 268, Swager Fanus Business Days after this Agreement is signed by the Parties, or in accordance with the Transmission Provider's queuing procedures. 10.0 A $2,000 deposit will be required from the Interconnection Customer upon execution of this agreement by the Interconnection Customer. 11.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 12.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 3 0 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS THEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Idaho Power Company Signed: /J.f~~~*$~ ::=:::::::"7=;::::,...,...., Printed: Marc Patterson Title: Leader, T &D Planning Date: November 17, 2008 Interconnection Customer: -------------------------- Signed'--------------- Printed -------------------------- Title _____________ _ Date ____________________ _ Small Generator System Impact Study Agreement Project# 268, Swager Farms Attachment A Assumptions Used in Conducting the System Impact Study The system impact study shall be based upon the results of the feasibility study, subject to any modifications in accordance with the standard Sl1rlall Generator Interconnection Procedures, and the following assumptions: 1) Designation ofPoint of Interconnection and configuration to be studied. 2) Designation of alternative Points of Interconnection and configuration. 1) and 2) are to be completed by the Interconnection Customer. Other assumptions (listed below) are to be provided by the Interconnection Customer and the Transmission Provider. BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 9 Small Generator System Impact Study Agreement Project# 268, Swager Fanns System Impact Study Agreement THIS AGREEMENT is made and entered into this 11£\Vl day of <'S;tJ...IA..\J..ct(y 200~y and between A-roj?-1"" [ol'~or t'\h. OVI • , a c m eo,'-ct b" c v• organized and existing under the laws ofthe State of ll )l!shfV\'d-vV) , ("Interconnection Customer,") and Idaho Power Company a Corporation existing under the laws of the State ofldaho, ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be refe1red to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on September 10, 2008, and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a feasibility study and provided the results of said study to the Interconnection Customer (This recital to be omitted if the Parties have agreed to forego the feasibility study.); and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a system impact study(s) to assess the impact of interconnecting the Small Generating Facility with the Transmission Provider's Transmission System, and of any Affected Systems; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause to be performed a system impact study(s) consistent with the standard Small Generator Interconnection Procedures in accordance with the Open Access Transmission Tariff 3.0 The scope of a system impact study shall be subject to the assumptions set forth in Attachment A to this Agreement. 4.0 A system impact study will be based upon the results of the feasibility study and the technical inf01mation provided by Interconnection Customer in the Interconnection Request. The Transmission Provider reserves the right to request additional technical information from the Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the system impact study. If the Small Generator System Impact Study Agreement Project# 268, Swager Farms Interconnection Customer modifies its designated Point oflnterconnection, Interconnection Request, or the technical infonnation provided therein is modified, the time to complete the system impact study may be extended. 5.0 A system impact study shall consist of a short circuit analysis, a stability analysis, a power flow analysis, voltage drop and flicker studies, protection and set point coordination studies, and grounding reviews, as necessary. A system impact study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested interconnection service, including a preliminary indication of the cost and length oftime that would be necessary to correct any problems identified in those analyses and implement the interconnection. A system impact study shall provide a list of facilities that are required as a result of the Interconnection Request and non-binding good faith estimates of cost responsibility and time to construct. 6.0 A distribution system impact study shall incorporate a distribution load flow study, an analysis of equipment interrupting ratings, protection coordination study, voltage drop and flicker studies, protection and set point coordination studies, grounding reviews, and the impact on electric system operation, as necessary. 7.0 Affected Systems may participate in the preparation of a system impact study, with a division of costs among such entities as they may agree. All Affected Systems shall be afforded an opportunity to review and comment upon a system impact study that covers potential adverse system impacts on their electric systems, and the Transmission Provider has 20 additional Business Days to complete a system impact study requiring review by Affected Systems. 8.0 If the Transmission Provider uses a queuing procedure for sorting or prioritizing projects and their associated cost responsibilities for any required Network Upgrades, the system impact study shall consider all generating facilities (and with respect to paragraph 8.3 below, any identified Upgrades associated with such higher queued interconnection) that, on the date the system impact study is commenced- 8.1 Are directly interconnected with the Transmission Provider's electric system; or 8.2 Are interconnected with Affected Systems and may have an impact on the proposed interconnection; and 8.3 Have a pending higher queued Interconnection Request to interconnect with the Transmission Provider's electric system. 9.0 A distribution system impact study, if required, shall be completed and the results transmitted to the Interconnection Customer within 30 Business Days after this Agreement is signed by the Parties. A transmission system impact study, if required, shall be completed and the results transmitted to the Interconnection Customer within 45 Small Generator System Impact Study Agreement Project# 268, Swager Farms Business Days after this Agreement is signed by the Parties, or in accordance with the Transmission Provider's queuing procedures. 10.0 A $2,000 deposit will be required from the Interconnection Customer upon execution of this agreement by the Interconnection Customer. 11.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 12.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS THEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Idaho Power Company Signed: Printed: Marc Patterson Title: Leader, T &D Planning Date: November 17,2008 Interconnection Customer: ~ttr {orpur()l-h'vf\ Signed ~~~ Printed f?ri c \?nwe 1/ Title 1'rru a t ' ' Small Generator System Impact Study Agreement Project# 268, Swager Farms Attachment A Assumptions Used in Conducting the System Impact Study The system impact study shall be based upon the results of the feasibility study, subject to any modifications in accordance with the standard Small Generator Interconnection Procedures, and the following assumptions: 1) Designation ofPoint of Interconnection and configuration to be studied. ~ oV\ 1-\'e. ~rifh"vn IV\ t~ -Peu5ihi ll'+v gfVtdy. 2) Designation of alternative Points of Interconnection and configuration. 1) and 2) are to be completed by the Interconnection Customer. Other assumptions (listed below) are to be provided by the Interconnection Customer and the Transmission Provider. BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 10 February 2, 2009 Eric Powell Andgar Corporation 6920 Salashan Pkwy. A102 Ferndale, WA 98428 360.366.9900 Re: Swager Farms Generator Interconnection Project# 268 Dear Eric: An IDACORP Compan1 Enclosed is an Executed System Impact Study Agreement between you and Idaho Power Company for the above-referenced Generator Interconnection project. Please provide any technical data required for the study, if you have not already done so. We expect the System Impact Study to be completed by March 18, 2009. During the study period, we will keep you apprised of our progress. If you have any questions in the meantime, please contact me. Sincerely, Marc Patterson Engineering Leader, T &D Planning 208.388.2712 marcpatterson@idahopower. com Enclosure: Executed System Impact Study Agreement C: R Bishop/IPC P.O. Box 70 (83707) 1221 W. Idaho St. BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 11 April 10,2009 Eric Powell Andgar Corporation 6920 Salashan Pkwy. A 1 02 Fendale, W A 98428 306.366.9900 Subject: GINT#268 System hnpact Study Dear Mr. Powell: An IDACORP Company The Generator Interconnect Projecf (GINT) #268 was reviewed for system impacts. This review identified other projects as well as other transmission system requests (TSR's) ahead of this in the queue. The results of this review determined that the impact of this project were inconclusive without the associated TSR :from the energy provider. At this time, no additional transmission system upgrades have been identified that are associated with this project, other than those upgrades identified in the Feasibility Study Report. After a contract is reached between this project and the energy provider, any required TSR will be submitted by the energy provider and a more detailed study will occur. Sincerely, Marc Patterson Engineer Leader, T &D Planning 208.388.2712 marcpatterson@idahopower.com C: R Bishop/IPC 1221 W. Idaho St. (83702) P.O. Box 70 Boise, ID 83707 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 12 Eric Powell Andgar Corporation 6920 Salashan Pkwy. Al02 Ferndale, WA 98428 306.366.9900 Re: Project# 268-Swager Farms Project Dear Eric: An IDACORP Company "". April 24, 2009 Attached please find two copies of the Facility Study Agreement (FSA) that describes the design phase of the project, the responsibilities and obligations of both parties, and the work schedules required. To proceed with this application, Idaho Power must receive your executed FSA and the required deposit in order to remain in the Generator Interconnection queue. The deposit under this FSA is $15,000 based on the estimated engineering costs provided to you in the Feasibility Study Report. If you wish to proceed, please complete Attachment A, sign both copies and submit them along with the deposit to Idaho Power Company, attn: Rowena Bishop by June 8, 2009, otherwise your application will be deemed withdrawn. Please contact me if you have any questions. Encl: Two Facility Study Agreements Cc: Candace Gentry/IPC Rowena Bishop/IPC Ed Kosydar/IPC Sincerely, Marc Patterson Leader, T &D Engineering Ph 208.388.2712 1221 W. Idaho St. (83702) P.O. Box 70 Facilities Study Agreement THIS AGREEMENT is made and entered into this __ day of _____ __;2009, by and b~~ a organized and existing under the laws of the State of ("Interconnection Customer,") and Idaho Power Company, a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on September 10, 2008, and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a system impact study and provided the results of said study to the Interconnection Customer; and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the system impact study in accordance with Good Utility Practice to physically and electrically connect the Small Generating Facility with the Transmission Provider's Transmission System. NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause a facilities study consistent with the standard Small Generator Interconnection Procedures to be performed in accordance with the Open Access Transmission Tariff. 3.0 The scope of the facilities study shall be subject to data provided in Attachment A to this Agreement. 4.0 The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s). The facilities study shall also identify (1) the electrical switching configuration ofthe equipment, including, without limitation, transformer, switchgear, meters, and other station equipment, (2) the nature and estimated cost of the Transmission Provider's Facilities Study Agreement -1 -Swager Farms Project #268 Interconnection Facilities and Upgrades necessary to accomplish the interconnection, and (3) an estimate of the time required to complete the construction and installation of such facilities. 5.0 The Transmission Provider may propose to group facilities required for more than one Interconnection Customer in order to minimize facilities costs through economies of scale, but any Interconnection Customer may require the installation of facilities required for its own Small Generating Facility if it is willing to pay the costs of those facilities. 6.0 A deposit of $15,000 is due upon execution of this agreement by the Interconnection customer. 7.0 In cases where Upgrades are required, the facilities study must be completed within 45 Business Days of the receipt of this Agreement. In cases where no Upgrades are necessary and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 Business Days. 8.0 Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the facilities study must be completed and the facilities study report transmitted within 30 Business Days of the Interconnection Customer's agreement to conduct a facilities study. 9.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 10.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company -Delivery Signed: ___________ _ Signed: ___________ ___ Printed Name: Printed Name: ----------------------------- Title: Title: ------------------------------------------------------ Facilities Study Agreement -2-Swager Farms Project #268 Attachment A to Facilities Study Agreement Data to Be Provided by the Interconnection Customer With the Facilities Study Agreement 1. Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT /PT) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps 2. One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station. Number of generation connections: 3. Will an alternate source of auxiliary power be available during CT/PT maintenance? Yes No --- 4. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? Yes ___ No __ (Please indicate on the one-line diagram). 5. What type of control system or PLC will be located at the Small Generating Facility? 6. What protocol does the control system or PLC use? 7. Please provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines. 8. Physical dimensions of the proposed interconnection station: Facilities Study Agreement - 3 -Swager Farms Project #268 9. Bus length from generation to interconnection station: 10. Line length from interconnection station to Transmission Provider's Transmission System. 11. Tower number observed in the field. (Painted on tower leg)*: 12. Number of third party easements required for transmission lines*: *To be completed in coordination with Transmission Provider. 13. Is the Small Generating Facility located in Transmission Provider's service area? Yes ___ No ___ IfNo, please provide name oflocal provider: 14. Please provide the following proposed schedule dates: Begin Construction Generator Step-Up Transformers Receive Back Feed Power Generation Testing Commercial Operation Facilities Study Agreement -4- Date: ------------------------- Drue: ________________________ __ Date: ------------------------- Date: ------------------------- Swager Farms Project #268 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 13 June 8, 2009 Andgar Corporation Attn: Eric Powell 6920 Salashan Parkway A-102 Ferndale, W A 98248 Re: Project #268 System Impact Study Refund Dear Mr. Powell: An IDACORP Company Project #268 has completed the System Impact Study phase and the project has been withdrawn. As a result, we are returning the original $2,000.00 deposit plus interest of $24.93. Please find enclosed a check totaling $2,024.93. Date of Request Description of Requested Service 2/9/09 Project #268 Swager Farms System Impact Study If I can be of any further assistance, please call (208) 388-5736. 1221 W. Idaho St. {83702) P.O. Box 70 Boise, ID 83707 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 14 The New Energy Company, LLC October 12, 2009 Rowena Bishop Idaho Power Company 1221 W. State Street Boise ID 83702 Re: Small Generator Interconnection Applications for 2 Locations Dear Rowena: Please find enclosed Small Generator Interconnection Request Applica­ tion Forms for two locations: 1. Double B Dairy 1250 West 1100 South Murtaugh, ID 83344 2. Swager Farms 1707 E 3800 N Buhl, ID 83316 New Energy plans to complete anaerobic digesters at both facilities in 2010. Please find enclosed the $1000 deposit for each project for a to­ tal of $2000. Please call me at 208.890.8783 with questions or if more information is required. Thank you, Laura Knothe, PE The New Energy Company, LLC 8720 Vic Lane Middleton, ID 8366 Phone: 208.890.8783 Fax: 208.585.9016 E-mail: laura@thenewenergycompany.com SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact P.erson: Address: Telephone Number: Fax: E-Mail Address: Rowena Bishop 1221 W. Idaho Street, Boise ID 83702 208-388-2658 208-388-6647 rbishop@idahopower.com An Interconnection Request is considered complete when it provides all applicable and correct information required below. Preamble and lnstroctioos An Interconnection Customers who request interconnection must submit this Interconnection Request by hand delivery, mail, e-mail, or fax to the Transmission Provider. Processiog Fee or Deposit: If the Interconnection Request passes ALL screens of SOIP Section 2.2.1, the application may be submitted under the Fast Track Process, and the non-refundable processing fee is $500. Please contact Idaho Power if you have any questions. All Interconnection Requsts submitted under the Study Process, whether a new submission or an Interconnection Request that djd not pass the Fast T!!ck Process. shall submit to the Transmission Provider a deposit not to exceed $1 ,000 ·towards the cost of the feasibility study. Interconne4:tion Castomer loformatioo Legal Name of the Interconnection Customer (or, if an individual, individual's name) Name: __ O~w~n~e~uO~pe~r~a~to~r~co~m~p~a~n~y~d~e~v~e~loLp~m~e~n~t~in~p~r~o~g~re~s~s _____________________ _ ConmmPc~on:-~S~e~e~B~e~lo~w~----------------------------------------- Mailing Address:----------------------------_:._--------=------- C~tr: ____________________ _ State:. _____ _ Zip:------------ Facility Location (if different from above):-----------------------=-------- Telephone (Day): __________ Telephone (Evenmg): _______ _ Fax:----------------------E·Mail Address:--------------------- 1 I I I~ I Alternative Contact Information (if different :from the Interconnection Customer) Contact Name: · Laura Knothe PE Title: Project Manager Address: 8720 Vic Lane Middleto"n ID 83644 Telephone (Day); 208 890.8783 Telephone (Evening): 20B 890 8783 Fax: _ _,2..,0.,.8..,58=5.'"".9'""'0"'"'16><--_________ E-Mail Address: laura@thenewenergycompany.com Application is for: x New-small Generating Facility ___ Capacity ru.Mition to Existing Small Generating Fac~lity If capacity addition to existing facility, please describe: _.!.:N~A!-. ----------:-- Will the Small Generating Facility be· used for any of the following? To SuppJy Power to the Interconnection ·customer? Yes _No _k_ To Supply Power to Others? Yes __ No _x_ For installations at locations with existing electric service to which the proposed Small Generating Facility wil1 interconnect, provide: · Idaho Power Company 2169397508 (Local Ele<:tric Service Provider*) (Existing Account Number*) [*To be provided by the Interconnection Customer if the local electric service provider is different from the Transmission Provider] ConmctNIDne: ________________________________________________________ ___ Title:------------------------------------------- Adm~s: __________________________________________________________ __ Te1ephone (Day): ------,-------------Telephone (Evening):---------- Fax: ______________________ E-Mail Address:--------------- Requested Point oflnterconnection: 1707 E 3800 N Buhl ·ID 83316 : Interconneption Customer's Requested in-Service Date: ~J""u'-'-'lyt-2~0~1~0i.-_______________ _ 2 Small Generating Facility Information Data apply only to the Small Generating Facility, not the Interconnection Facilities. Energy Source:_ Solar _Wind _Hydro _Hydro Type (e.g. Run-of-River):. ____ _ _ Diesel _Natural Gas _Fuel Oil 1 Other (stafe type) ..JM:fie£lt.uha!ii!.!n.!le<..!G~ae;s!L.-._~-- Prime Mover: _Fuel Cell _ _x_Recip Engine · _Microturbine - _GasTurb _PV Type of Generator: _0_synchronous Induction Inverter _Steani Turb _Other Generator Nameplate Rating: 1200 kW (Typical). Generator Nameplate kV AR: __ _ Interconnection Customer or Customer-Site Load: -'-'N""o:..:.ne=--____ kW (if none, so state) Typical Reactive Load (if known): _N..:.:..A..:...._ ___ _ Maximum Physical Export Capability Requested: ___::12=0..:.0 ____ kW List components of the Small Generating Facility equipment package that are currently certified: Equipment Type Certifying Entity 1. --------- 2. --------------- 3. ----------4. ______________ __ 5. -------------- Is the prime mover compatible with the certified protective relay package? __ Yes No Generator (or solar collector) Manufacturer, Model Name & Number: (2) Caterpillar G3512 Gas Gensets@ 600kW Version Number:----------- Nameplate Output Power R~ng in kW: (Summer) _·..::12:::;0;,:,0....,.· .,......_,....--(Winter) ---'1:.:.20:.:0:....._ __ _ Nameplate Output Power Rating in.kVA; (Summer) 1500' · (Winre,r) _·...:.1.:::.50:::=:0~--- lndividuid Generator ·Power. F~ctor Rated Power Factor: Leading: --------'Lagging:· _:-=·o.a=-------- Total Number of Generators in wind farm to be interconnected pursuant to this NA Interconnection Request: Elevation: _Single phase _Three phase Inverter Manufacturer, Model Name & Number (if used): --~!1-lA.~------------ List of adjustable set points for the protective equipment or software:----------- .Mote; A completed Powul" Systems Luad Flow t.Jata sllu~::liiiWIL lJil IIUtJUiilltl with L11c lulcrconnection RegueRt 3 Small Generating Facility Characteristic Data (for inverter-based machines) Max design fault contribution current: --'N,_,A'--'----Instantaneous_ or RMS? __ Hannonics Characteristics: _ _.!.N~A~------------------- Start-up requirements: __ _:...:N::_A:__ ___________________ _ Small Generating Facility Characteristic Data (for rotating machines) RPM Frequency: 1200/60Hz (*)Neutral Grounding Resistor (If Applicable): ____ _ Synchronous Generators: Direct Axis Synchronous Reactance, Xd: ___ P. U. Direct Axis Transient Reactmce, X'd: P.U. Direct Axis Subtransient Reactance, X" d: -----------'P.U. Negative Sequence Reactance, X2: P.U. Zero Sequence Reactance, Xo: P.U. KVA Base:----------- Field Volts:------ Field Amperes: ------ Induction Generators: Motoring Power (kW}: ------ Ilt or K (Heating Time Constant):-----­ Rotor Resistance, Rr: ------ Stator Resistance, Rs: ------ Stator Reactance, Xs: _____ _ Rotor Reactance, Xr: ------ Magnetizing Reactance, Xm: _____ _ Short Circuit Reactance, Xd'': _____ _ Exciting Current-----­ Temperature Rise:-----­ FnuneS~e: -------- Design Letter:------- Reactive Power Required In Vars (No Load):------ Reactive Power Required In Vars (Full Load): _____ _ Total Rotating Inertia, H: Per Unilon k. VA Base Note: Please contact the Transmission Provider prior to submitting the Interconnection Request to determine if the specified information above is reqyired. 4 I I I I I Excitation and Governor System Data for Svncbronous Generators Only Provide appropriate IEEE model block diagram of excitation system. governor system and power system stabilizer (PSS) in accordance with the regional reliability council criteria. A PSS may be detennined to be required by applicable studies. A copy of the manufacturer's block diagram may not be substituted. Interconuectiou Facilities luformatioo Will a transformer be used betw~en the genemtor and the point of common coupling? 0 Yes _No Will the tmnsformer be provided by the Interconnection Customer? _0_ Yes __ No Transformer Data Of Applicable. for Interconnection Customer-Owned Transformer): Is the transformer: __ single phase __ three phase? Size: -----'kVA Transformer Impedance: ___ % on kVA Base If Three Phase: Transformer Primary: __ Volts __ Delta __ Wye __ Wye Grounded Transformer Secondary: __ Volts __ Delta __ Wye __ Wye Grounded Transformer Tertiary: __ Volts __ Delta __ Wye __ Wye Grounded Transformer Fuse Data (If Applicable, for Inten;onnection Customer-Owned Fuse): (Attach copy of fuse manufacturer's Minimum Melt and Total Clearing Time-Current Curves) Manufacturer: ________ Type: _______ Size: ----'Speed: _____ _ Interconnecting Circuit Breaker (if aoolicable): Manufacturer:------------Type: ___ _ Load Rating (Amps): Interrupting Rating (Amps): Trip Speed (Cycles): ___ _ futerconnection Protective Relays Of Applicable): If Microprocessor-Controlled: List of Functions and Adjustable Setpoints for the protective equipment or software: Setpoint Function Minimum Maximum 1. See attached SEL-547 Relay Settings Sheet 2. 3. 4. 5. 6. I I If Discrete Components: (Enclose Copy of any Proposed Time-Overcurrent Coordination Curves) Manufacturer: Type: Style/Catalog No.: Proposed Setting: Manufacturer: Type: StyleJCatalog No.: Proposed Setting: Manufacturer: Type: Style/Catalog No.: Proposed Setting: Manufactur~r: Type: Style/Catalog No.: Proposed Setting: Manufacturer: Type: Style/Catalog No.: Proposed Setting: Current Transformer Data (If Applicable): (Enclose Copy of Manufacturer's Excitation and Ratio Correction Curves) Manufacturer:--------------------- Type: -------Accuracy Class: _ Proposed Ratio Connection: __ Manufacturer:--------------------­ Type:--------Accuracy Class: _ Proposed Ratio Connection: __ Potential Transformer Data (If Applicable): Manufacturer:--------------------- Type: -------Accuracy Class:_ Proposed Ratio Connection: __ Manufacturer. _____________________ __ Type: --------Accuracy Class: _ Proposed Ratio Connection: __ 6 General Information Enclose copy of site electrical one-line diagram showing the configuration of all Small Generating Facility equipment, current and potential circuits, and protection and control schemes. 1bis one-line diagram must be signed and stamped by a licensed Professional Engineer if the Small Generating Facility is larger than 50 kW. Is One-Line Diagram Enclosed? 0_ Yes __ No · Enclose copy of any site documentation that indicates the precise physical location of the proposed Small Generating Facility ~ USGS topographic map or other diagram or documentation). Proposed location of protective interface equipment on property (include address if different from the Interconnection Customer's address) 1707 E 3800 N Byhl IP 83316 Enclose copy of any site documentation that describes and details the operation of the protection and control schemes. Is Available Documentation Enclosed? ..Y._Yes __ No Enclose copies of schematic drawings for all protection and control circuits, relay current circuits, relay potential circuits, and alarm/monitoring circuits (if applicable). Are Schematic Drawings Enclosed? _Yes __ No Applicant Signature I hereby certify that, to the best of my knowledge, all the information provided in this Interconnection Request is true and correct. For Interconnection Customer: Printed I tLLUYO.... 7 UNITED STATES DEPARTMENT OF TliE INTERIOR GEOLOOICAL SURVEY ec!Hl(IVIt INTEiri'Al.. 10 FE['f N~~I.OI:!XInlC"'l•f1C.Ioi.DAT\IIlllFUIIISI Prirrlloyh)&t'IA~, \.UIM.-<N.lf<Nd.""Td Dt .......... ---impi'O<Otd,.ufacsl. -~- s.-..urt'hip..,-, ' ....,_,.. --J~rOid •••••... \.) ln!tnh"' ~"' f J u s Ram () su~ Ro-..te Q.O\IER, IDAHO q iJ....a.TR IU "" .......,_ ~ ... ~...., / ' Ge n e r a t o r Co n t r o l Pa n e l 10 0 0 A c I 3P 48 0 / 2 7 7 .6 M W Ge n e r a t o r 10 0 0 A c I 3P . 48 0 1 2 7 7 .6 M W Ge n e r a t o r 20 0 0 A c l 3P ~ I I To Ut i l i t y ·· · ·-- - -- - - - - - - - - - ···-~ -- · ·- - -- -' - - - 2. 5 MV A Tr a n s f o r m e r Date ___ _ SEL·547 Relay EZ Settings Sheet I' of 4 Appendix C SEL-547 Relay EZ Settings Sheet EZ Settings <use SHOE and SET E commands) General Settings Relay Identifier (30 characters) RELID Terminal Identifier (30 characters) TERMID Current Traosfonner Ratio (l-1000) CRATIO "" Nominal Input Voltage, line-to-line (208-480 Vac) NOMV = Three-Phase Voltage Connection (WYE); fixed setting 3PCONN = Nominal System Frequency (50, 60 Hz) FREQ = Phase Rotation (ABC, ACB) ROfATE = Date Format (MDY, YMD) DATE = LED Flash Interval (OFF, 5, 10, 15, 30,60 sec.) LEDFL = Voltage Element Settings (device 27/59; 4 elements> Undel'voltage l Pickup (OFF, 50-100%); see Note 1 27UV1P = Undervoltage 1 Time Delay (0.00-16000 eye) 27UVID = Undervoltage 2 Pickup (OFF, 50-100%); see Note 1 27UV2P = Undervoltage 2 Time Delay (0.00-16000 eye) 27UVID ;;; Overvoltage 1 Pickup (OFF, 50-144%); see Note 1 S90V1P = Overvoltage 1 Time Delay (0.00-16000 eye) 590VID = Overvoltage 2 Pickup (OFF, 50-144%); see Note 1 590VZP ;;; Overvoltage 2 Time Delay (0.00-16000 eye) 590V2D = Frequency Element Settings (device 81; 4 elements) Undervoltage Block Pickup (50-100%); see Note 1 27BLKP = Over-and Underfreqnency 1 Picklrp (OFF, 40.1-69.9 H.:) 810l11P = Over-and Underfrequency I Time Delay Gi.00-1 0000 eye) 810U1D = Over-and Underfrequency 2 Pickup (OFF, 40.1-69.9 Hz) 810U2P = DatG Code 20080922 User's Guide SEL-547 Relay 2 of 41 SEL-547 Relay EZ Settings Sheet. Date. ___ _ -SEL-547 Relay Over-and Undetfrequency 2 Time Delay (5.00-16000 eye) Over-and Underfrequency 3 Pickup (OFF, 40.1-69.9 Hz) Over-and Underfrequency 3 Tune Delay (5.00-16000 cyc) Over-and Underfrequency 4 Pickup (OFF, 40.1-69.9 Hz) Over-and Underfrequency 4 Time Delay (5.00-16000cyc) 810U2D = ---------- 810U3P = ---------- 810U3D 810U4P 810U4D = ------------ Directional Power Element Settings (device 32; 1 element) Three--Phase Power Pickup (OFF, 40-900 Watts, secondary) Power Element, Forward or Reverse (F, R) Power Element Time Delay (0.00-16000 eye) 32P 32FR 320 = Synchronism Check Element Settings (device 25; 1 element) Difference Voltage Pickup (OFF, 1-50%); see Note 1 Maximum Slip Frequency (0.1-0.5 Hz) Maximum Angle (2-60 degrees) User's Guide 25DIFP = ------------------ 25SLP = ------------------ ZSANG Dale Code 20080922. BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 15 Laura Knothe, PE The New Energy Company 8720 Vic Lane Middleton, ID 83644 Re: Swager Farms-Project# 307 Dear Laura: October 19, 2009 ® An IDACORP Company Thank you for your Generator Interconnection application for the Rock Creek Dairy Project to be connected to the Idaho Power system at Twin Falls County, Idaho (see attached copy). Since we have received all of the required materials, this application is now considered complete. As you may be aware, we are required to post certain information to our OASIS (Open Access Same Time Information) website. Please refer to the website periodically to view a list of current projects at http://www.oatioasis.comfll>CO!index.html under GENERATOR INTERCONNECTION INFORMATION folder, on the left side ofthe screen. For your reference, enclosed is a copy of Idaho Power Company's Requirements for Generation Interconnection which may or may not apply to your project. More information about the Generation Interconnection process can be found on the Idaho Power website at: http://www .idahopower. com/ About U s/BusinessToB usiness/Generationlntercollllect/ default. cfin At this time, Idaho Power Company will assign a planning engineer for this project, and we will contact you in the near future to schedule a Scoping Meeting. For your review, I am attaching a copy of the standard Interconnection Feasibility Study Agreement that needs to be executed by you soon after our Scoping Meeting. Please feel free to contact me with your questions about the Generator Interconnection Process anytime. I will forward this application to our T &D Planning Leader, Marc Patterson, who will be evaluating your request. Encl Application Sincerely, R~~B~sf::{J Operations Analyst Ph 208-388-2658 Idal1o Power Company's Requiren1.ents for Generation Interconnection Standard Interconnection Feasibility Study Agreement Cc: Marc Patterson/IPC (via email) 1221 W. Idaho St. (83702) P.O. Box 70 Boise, ID 83707 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 16 Sma11 Gen Feasibility Study Agreement Swager Farms Project# 307 Feasibility Study Agreement THIS AGREEMENT is made and entered into this_2l_day of Dc-+-che v-2009 by and between ..0 l.LQ_ a_-----=-=L=L=C.-=-------- organized and existing under tate of -T do b (,'\, , ("Interconnection Customer,") and Idaho Power Company a Corporation existing under the laws of the State of Idaho {"Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a 11Party," or collectively as the "Parties." RECITALS WHEREAS, Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by Interconnection Customer on October 12, 2009, also known as Project# 307; and WHEREAS, Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; and WHEREAS, Interconnection Customer has requested the Transmission Provider to perform a feasibility study to assess the feasibility of interconnecting the proposed Small Generating Facility with-the Transmission Provider's Transmission System, and of any Affected Systems; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings.indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause to be performed an interconnection feasibility study consistent the standard Small Generator Interconnection Procedures in accordance with the Open Access Transmission Tariff. 3.0 The scope of the feasibility study shall be subject to the assumptions set torth in Attachment A to this Agreement. 4.0 The feasibility study shall be based on the technical information provided by the Interconnection Customer in the Interconnection Request, as may be modified as the result of the scoping meeting. The Transmission Provider reserves the right to request additional technical information from the lnterconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the feasibility study and as designated in accordance with the standard Small Generator Intercoru1ection Procedures. If the Interconnection Customer modifies its Interconnection Request, the time to complete the feasibility study may be extended by agreement of the Parties. Page 1 of3 Small Gen Feasibility Study Agreement Swager Farms Project# 307 5.0 In performing the study, the Transmission Provider shaH rely, to the extent reasonably practicable, on existing studies of recent vintage. The Interconnection Customer shall not be charged for such existing studies; however, the Interconnection Customer shall be responsible for charges associated with any new study or modifications to existing studies that are reasonably necessary to perform the feasibility study. 6.0 The feasibility study rep01i shall provide the following analyses for the purpose of identifying any potential adverse system impacts that would result from the interconnection of the Small Generating Facility as proposed: 6.1 Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; 6.2 Initial identification of any thermal overload or voltage limit violations resulting from the interconnection; I 6.3 Initial review of grounding requirements and electric system protection; and 6.4 Description and non-bonding estimated cost of facilities required to interconnect the proposed Small Generating Facility and to address the identified short circuit 'and power flow issues. 7.0 The feasibility study shall model the impact of the Small Generating Facility regardless of purpose in order to avoid the further expense and interruption of operation for reexamination of feasibility and impacts if the Interconnection Customer later changes the purpose for which the Small Generating Facility is being installed. 8.0 The study shall include the feasibility of any interconnection at a proposed project site where there could be multiple potential Points of Interconnection, as requested by the Interconnection Customer and at the Interconnection Customer's cost. 9.0 In lieu of Feasibility Study deposit, Interconnection Customer agrees that study funds will be drawn from the application fee for the performance of the Interconnection Feasibility Study. Transmission Provider shall yharge and Interconnection Customer shall pay the actual costs of the Interconnection Feasibility Study. Any difference between the deposit and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate. Page 2 of3 Small Gen Feasibility Study Agreement Swager Farms Project# 307 10.0 Once the feasibility study is completed, a feasibility study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the feasibility study must be completed and the feasibility study report transmitted within 30 business days of the Interconnection Customer's agreement to conduct a feasibility study. 11.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 12.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Idaho Power Company-Delivery Signed ~f1:.C./lg Printed &fa trc f?d-/e YSor...... Title eh~i 1/>eenhj f-R~eJe r Date I o/:z.:r /d1 Interconnection Customer: ""fbe f)e,"J t=De'=-g~ C(-¥Uf4-r::JJ LLC.. Signed~.< PE. Printed la..u,~rcx_ k. no-±be P (; Title HCUh~ ~ Pa.chuA Date lo 1-:l-., lo1 Page 3 of3 Small Gen Feasibility Study Agreement Swager Farms Project# 307 Attachment A to Feasibility Study Agreement Assumptions Used in Conducting the Feasibility Study The feasibility study will be based upon the information set forth in the Interconnection Request and agreed upon in the scoping meeting held on I c... I ::>...'7 I o 4 1) Designation of Point of Interconnection and configuration to be studied. 2) Designation of alternative Points of Interconnection and configuration. 1) and 2) are to be completed by the Interconnection Customer. Other assumptions (listed below) are to be provided by the Interconnection Customer and the Transmission Provider. Page 1 of 1 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 17 ) I GENERATOR INTERCONNECTION FEASIBILITY STUDY for integration of the proposed PROJECT #307 to the IDAHO POWER COMPANY ELECTRICAL SYSTEM for the INTERCONNECTION CUSTOMER FINAL REPORT JANUARY 13, 2010 CP 1.0 Introduction The Generation Interconnection Customer has contracted with Idaho Power Company (IPCo) to perform a Generator Interconnection Feasibility Study for the integration of a proposed 1.2 MW dairy digester Project (project #307). The location of the project is in Idaho Power1s Southern Idaho service territory in Twin Falls County, Idaho. This report documents the basis for and the results of this Feasibility Study for the Generation Interconnection Customer. It describes the proposed project, the study cases used, the impact of associated projects, and results of all work in the areas of concern. 2.0 Summary The proposed project is a 1.2 MW biogas generation project consisting of two 600 kW synchronous generators. The proposed Point of Interconnection (POI) for the generating facility with the IPCo system is in Twin Falls County, Idaho at the 12.5 kV distribution level. This feasibility study indicates the existing local transmission system does currently have the capacity for the 1.2 MW output of the digester project. The upgrades to this feeder needed to connect this project include a capacitor bank installation, as well as a generation interconnection and protection package. The estimated cost to interconnect this generation project to Idaho Power's system is $234,800. 3.0 Scope oflnterconnection Feasibility Study The Interconnection Feasibility Study was done and prepared in accordance with Idaho Power Company Standard Generator Interconnection Procedures, to provide a preliminary evaluation of the feasibility of the interconnection of the proposed generating project to the Idaho Power system. As listed in the Interconnection Feasibility Study agreement, the Interconnection Feasibility Study report provides the following information: preliminary identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; preliminary identification of any thermal overload or voltage limit violations resulting from the interconnection; and preliminary description and non-binding estimated cost of facilities required to interconnect the Small Generating Facility to the Distribution System and to address the identified short circuit and power flow issues. -2- II All other proposed Generation projects prior to this project in the Generator Interconnect queue were considered in this study. A current list of these projects can be folllld on the Idaho Power web site as follows: http://www.oatioasis.com/ipco/index.html. 4.0 Description of Proposed Generating Project Project #307 proposes to connect to the IPCo distribution system for an injection of 1.2 MW (maximum project output) using two 600 kW synchronous generator. 5.0 Description of Existing Substation Facilities The distribution substation that serves this area is located approximately three and a half miles south and east of the POI. The existing substation transformer is a 46: 12.5 kV transformer that has adequate capacity for this project. The associated feeder breaker at the substation is rated for use at 12.5 kV. This breaker's interrupting capabilities are not exceeded with the added generation. 6.0 Description of Existing Distribution Facilities The distribution feeder serving this area is grounded wye and operates at 12.5 kV. There is adequate capacity on this feeder to serve this project. However, the project will have to run at a power factor between 90% and 98% lagging when at full output. In other words, the generation facility will have to absorb between 240 kVAR and 580 kV AR when operating at full output (1200 kW) throughout the year. A capacitor bank will have to be added for compensation pwposes due to the facilities lagging power factor. Since it will be running at a max power factor of 90%, 600 k V AR will need to be produced. That V AR flow will come from a 600 kV AR capacitor bank located a couple spans to the west of COVR substation. This location eliminates high voltage concerns which would have become an issue if the bank were placed closer to the POI. Since the biogas generation project is served by a feeder that also serves other Idaho Power customers, and to minimize the risk of islanding the generator with local load, a generation interconnection and protection package will be required at the POL This package includes a 12.5 kV recloser, controls, CTs, PTs, and communications per Idaho Power's standard for generators connected to the distribution system. 7.0 Description of Existing Transmission Facilities ~3- The transmission line that serves this area is a 46 kV radial tap. With the addition of this generation project no capacity related problems occur on this tap. Therefore, no improvements need to be made on the immediate transmission system. However, high voltage becomes a problem during periods of light loading (fall and spring). To avoid this problem the generators will need to lag at a 90% power factor at these times. In the summer and winter the generators can lag up to a 98% power factor as indicated previously. 8.0 Description and Cost Estimate of Required Facility Upgrades The estimated costs to interconnect the 1.2 MW biogas generation project in Twin Falls County, Idaho is $234,800. These upgrades are listed in the following Table. Description Estimated Cost 600 kV AR capacitor bank $9,800 Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs, and communications) $225,000 Total Estimated Cost $234,800 Table 1: Cost Estimates These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads. (Tax Gross Up has not been included presuming construction of interconnection facilities will not qualify under IRS rules as a taxable event. Allowance for funds used during construction (AFUDC) has not been included in the cost estimates since it is assumed that IPC will be provided up-front funding by the Project). These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. 9.0 Description of Operating Requirements In addition to the upgrades listed in section 8.0 of this report, the proposed project must meet several operating requirements. The project must be controlled to operate at a lagging power factor of90% during the fall and spring months and between 90% and 98% during the summer and winter months or meet the voltage schedule provided by Idaho Power. Voltage flicker at startup and during operation will be limited to less than 5% as measured at the point of interconnection. For this to occur, the current cannot exceed 46 Amps during start up at the 12.5 kV voltage level. This forces the generating facility to start the generators separately. The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems. The project must also limit the ground fault current at the point of interconnection to 20 Amps. See Appendix A for more details -4- ) 10.0 Conclusions The requested interconnection of project #307 to IPCo's system was studied. The results of this study indicate that it is feasible to connect this project to the existing IPCo system with the upgrades outlined above. -5- APPENDIX A A-1.0 Method of Study The Feasibility Study plan insects the .Project up to the maximum requested injection into the selected Western Electric Coordinating Council (WECC) power flow case and then, using Power World Simulator Version 12, examines the impacts of the new resource on Idaho Power's transmission system (lines, transformers, etc.) within the study area under various operating/outage scenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability of the configurations considered. The WECC case is a recent case modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. For distribution feeder analysis, Idaho Power utilizes Advantica's SynerGEE Software. A-2.0 Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determirie under which system configuration modifications may be required: The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating is acceptable. · Idaho Power's Voltage Operating Guidelines were used to determine voltage requirements on the system. This states, in part, that distribution voltages, under normal operating conditions, are to be maintained within plus or minus 5% (0.05 per unit) of nominal everywhere on the feeder. Therefore, voltages greater than or equal to 0.95 pu voltage and less than or equal to 1.05 pu voltage are acceptable. Voltage flicker during starting or stopping the generator is limited to 5% as measured at the point of intercOimection, per Idaho Power's T &D Advisory Infonnation Manual. Idaho Power's Reliability Criteria for System Planning was used to determine proper transmission system operation. All customer generation must meet IEEE 519 and ANSI C84.1 Standards. AU other applicable national and Idaho Power standards and prudent utility practices were used to determine the acceptability of the configurations considered. The stable operation of the system requires an adequate supply of volt-amperes reactive (VARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply ofVARs will result in voltage decay or even collapse under the worst conditions. -6- II / Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by !PC upgrade projects that are either currently under construction or whose budgets have been approved for construction in the near future. All other potential future ratings are outside the scope of this study. Future transmission changes may, however, affect current facility ratings used in the study. A~3.0 Grounding Guidance Idaho Power Company (IPC) requires interconnected transformers to limit their ground fault current to 20 amps at the point of interconnection. A~4.0 Electrical System Protection Guidance IPC requires electrical system protection per Requirements for Generation Interconnections found on the Idaho Power Web site, http://www.idahopower.com/aboutus/business/generationlntercmmect/. A-5.0 WECC Coordinated Off-Nominal Frequency Load Shedding and Restoration Requirements IPC requires frequency operational limits to adhere to WECC Under-frequency and Over­ frequency Limits per the WECC Coord.inated Off-Nominal Frequency Load Shedding and Restoration Requirements available upon request. -7- BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 18 Laura Knothe The New Energy Company 8720 Vic Lane Middleton, ID 83644 An IDACORP Company January 13, 2010 RE: Swager Farms, Double B Dairy and Rock Creek Dairy-Project #s 307, 308, 309 Dear Ms. Knothe: Enclosed are the Final Feasibility Study Reports for the above-referenced projects. The feasibility analysis indicates that the system is capable of integrating your generator at the proposed location. However, the study does not provide any transmission rights which may be required for the sale of energy from this project. It is recommended that you contact Idaho Power's Power Supply Department to begin the study process for the delivery of energy from this project. Additional network upgrades may be required which could have a significant financial impact. If you have any comments to the draft report, please contact me as soon as possible. Since no System Impact Study is required, I have enclosed two (2) copies of the Facility Study Agreement (FSA) for the above-referenced projects. In order to proceed with these applications, Idaho Power must receive your agreement to proceed with a Facility Study by executing both copies of each FSA and submitting completed Attachments, along with the required deposit in order to remain in the Generator Interconnection queue. The deposit under the FSA is based on the estimated engineering costs provided to you in the Feasibility Study Reports. The required deposits are: #307 $11,740.00 #308 $11,250.00 #309 $17,760.00 If you wish to proceed, please sign both copies of each FSA and submit them along with the deposit(s) to Idaho Power Company, attn: Rowena Bishop by March 1, 2010, otherwise your application will be deemed withdrawn. Please contact me if you have any questions. Sincerely, Marc Patterson Engineering Leader, T &D Planning Ph. 208.388.2712 Encl: Final Feasibility Study Reports-#307, #308, #309 2 copies-Facility Study Agreement #307 2 copies -Facility Study Agreement #308 2 copies-Facility Study Agreement #309 C: Chris Punt/IPC Ed Kosydar/IPC 1221 W. Idaho St. (83702) P.O. Box 70 Boise, ID 83707 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 19 March 3, 2010 The New Energy Company LLC Attn: Laura Knothe 8720 Vic Lane Middleton ID 83644 E-mail Copy: laura@thenewenergycompany.com RE: Letter of Understanding -.. '"·· ... '• An IDACORP Company -.... _ .... ----•!-------~---~- -~-----~-~----~------·-- Randy C. Allphin Sr. Energy Contract Coordinator Tel: (208) 388-2614 rallphin@idahopower.com Swager Farms Dairy-Proposed Anaerobic Digester Project Ms. Knothe, Summarized below is a brief outline of the purchase power agreement, interconnection process and transmission capacity requirements for your proposed generation project. Purchase Power Agreement The project you have described appears to be eligible for a purchase power agreement under the guidelines for a Qualifying Facility as defined by the Public Utilities Regulatory Policies Act of 1978 (PURP A). At the time you are ready to proceed with a purchase power agreement for this project, Idaho Power will prepare a purchase power agreement that complies with the current rules and regulations that govern these PURP A agreements, any draft purchase power agreements previously provided to you for review must be updated to include current rules and regulations. Prior to Idaho Power executing a purchase power agreement it will be required that you have: 1.) Provided documentation that substantiates that the project has filed for interconnection and is in compliance with any payments and/or other requirements specified in the Interconnection process for this project and; Page I of4 P 0 Box 70 Boise, Idaho 83707 1221 W Idaho St. Boise, lduho 83702 2.) Received and accepted an intercmmection feasibility study for this project and; 3.) Returned a signed copy of this letter of understanding and all of the required information to enable Idaho Power to file an application requesting transmission capacity for this project. Completion of the enclosed Transmission Capacity Application Questionnaire will provide the majority of this information and; 4.) Confinnation that the results of the initial transmission capacity application are known and the project accepts these results and intends to continue with the development of the project including, if applicable, execution of a Network Resomce Integration Study Agreement in the fonn enclosed herein. Interconnection and Transmission Capacity Your project will be responsible for all costs of physically interconnecting the project to the Idaho Power electrical system and any costs associated with acquiring adequate firm transmission capacity on the Idaho Power transmission system to enable the project's energy to be delivered to Idaho Power customers. Interconnection Your project will be required to complete the interconnection process and execute a Generation Interconnection Agreement ("GIA''). Transmission Capacity To sell your project's energy to Idaho Power, your project must be designated as a Network Resource ("DNR"). In order for this project to achieve DNR status, Idaho Power is required to make a request (complete and file· an application) and be granted firm transmission capacity from the Idaho Power delivery business unit ("Delivery") to move your project's energy from the physical intercollllection point to Idaho Power customers. In accordance with various rules and regulations, the project must be granted DNR status no later than 60 days prior to the project delivering any energy to Idaho Power. Idaho Power will begin this finn transmission capacity application process only after the project has returned a signed copy of this letter of understanding and all of the information required for Idaho Power to file this application (see attached Transmission Capacity Application Questionnaire). After filing a complete finn transmission capacity application with Delivery, Idaho Power will receive notification back from Delivery within 30 days that: (a) adequate transmission capacity is available for this project without the need to construct upgrades; or (b) a transmission capacity system impact study is required to determine the available transmission capacity and/or required upgrades; or (c) a statement of the required transmission upgrades and the associated costs. Idaho Power will notify the project of this response to the transmission capacity application in a timely manner after the response is received from Delivery. Page2of4 P 0 Box 70 Boise, Idaho 83707 I 22 I W Idaho St. Boise, Idaho 83702 If the response from Delivery is as specified in item (a) (transmission capacity is available), the project will be required to execute a purchase power agreement with Idaho Power within 30 days in order to retain this transmission capacity reservation. If the response from Delivery is as specified in items (b) or (c) (studies required and/or upgrades required), the project will be required to execute a Network Resource Integration Study Agreement (sample copy attached for your information) and submit all required deposits or fees within 15 days after receiving notification of this requirement in order for Idaho Power to continue the transmission capacity request. This Network Resource Integration Study Agreement will specify that the project will be responsible for costs incurred by Idaho Power to perform any required studies. If, after the studies are concluded the project wishes to continue the pmsuit of transmission capacity, the project will also be responsible for ali transmission system upgrade costs identified within the studies. The fees and costs will be in the form of both initial deposits as well as actual costs. If at any time after executing the Network Resource Integration Study Agreement the project does not pay any required fees, or elects to stop the transmission study or upgrade process, the project shall be responsible for all costs incurred by Idaho Power in performing the studies or upgrades up to the point of termination of the Network Resource Integration Study Agreement. Upon successful completion of the above described transmission capacity upgrade process, a transmission capacity reservation will exist for this project. However, in order to finalize this transmission capacity reservation, a purchase power agreement with Idaho Power must be executed no later than 30 days after the transmission capacity upgrades are completed. If the purchase power agreement is not executed by this deadline, the transmission capacity reservation will be released and this process wiH have to be repeated if the project later requests transmission capacity. As noted earlier, this transmission capacity acquisition and associated Network Resource designation must be completed, at the minimum, 60 days prior to the project delivering any energy to Idaho Power. In addition, the project must provide routine updates to Idaho Power of the expected online date of the generation project to ensure Idaho Power is capable of accepting the energy from the project on the actual date the project comes online. Page 3 of4 P 0 Box 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702 Please return all required information to: Idaho Power Company Attn: Randy C. Allphin POBox 70 Boise, ID 83707 E-mail: rallphin@idahopower.com Sincerely, ({f.~· Randy C Allphin Idaho Power Company Understood and accepted this __ day of _______ __, 2010 Signature Print Name Title Page 4 of4 P 0 Box 70 Boise, Idaho 83707 1221 W Idaho St. Boise, idaho 83702 M IOACORP ComParlV Transmission Capacity Application Questionnaire This list is the known information requirements as of the date of the letter transmitting this request. If additional information is required, Idaho Power will promptly notify the project developer of the additional information requirements. A. Project Name B. Project Location C. Project Developer Name Address City I State I Zip Phone Number E-mail D. Idaho Power Delivery Business unit Interconnection "Que" reference number (if not known, please contact the Idaho Power Interconnection group) E. Evidence of the Project's good standing status in the Idaho Power Interconnection Process F. Copy of the Idaho Power Interconnection feasibility study and a statement from the project that the project has accepted the results of the interconnection feasibility study and is continuing the process of interconnecting and developing the generation project. G. Maximum Capacity (MW) _____ _ Page I of3 H. Beginning day and time of energy deliveries Day (mm/dd/yyyy) __________ _ Time ______________ _ I. Ending day and time of energy deliveries Day (mm/dd/yyyy) _________ _ Time _____________ _ J. VAR capability (both leading and lagging) of all generators _________ _ K. Identification of the control area(s) from which the energy will originate L. List any periods of restricted operations throughout the year M. Maintenance schedule N. Minimum loading level of each generation unit ------------------ 0. Normal operating level of each generation unit.----------------- P. Any must-run generation unit designations required for system reliability or contractual reason Puge 2 of3 Q. Approximate variable generation cost {$/MWh) Note-this will be estimated energy pricing from a potential purchase power agreement that this project may be eligible for. R. If the generation resource is to be located in the Idaho Power Balancing Authority Area and if only a portion of the resource output is to be designated as a Network Resource, then explain arrangements governing sale and delivery of additional output to third parties. S. If the project is not directly interconnected to the Idaho Power transmission system, provide the transmission provider(s) name, Point of Receipt, Point of Delivery and the transmission reservation number for all of the transmission providers required to deliver the project's energy to Idaho Power. TransmissionProvlder(s)Name ______ '--------------------- PointofRecelpt _____________________________ _ Point of Delivery ______________________________ _ Transmission Reservation Number(s) ------------------------- T. If the project is directly interconnected to the Idaho Power transmission system, provide the Point of Receipt, physical location and voltage. Point of Receipt, ______________________________ _ Physical Location ______________________________ _ Voltage _______ _ U. Is the project committed to execute a purchase power agreement with Idaho Power upon a favorable resolution of the identified interconnection and transmission costs? Yes 0 No 0 V. Is any portion of the maximum capacity identified for this project committed to any other party? Yes D No 0 Signature __________________ Date _______________ ___ Page 3 of3 NETWORK RESOURCE INTEGRATION STUDY AGREEMENT THIS Agreement is made and entered into this __ day of ____ 20_ between Idaho Power Company ("Idaho Power'' or "Company") through its Power Supply business unit ("Power Supply") and Delivery to install Company's Schedule 72 .,w~~· ~~!~~t. 1: \I J ~,1 -~·"·""'·"'·· classified as a DNR and for Idaho Power to 'l[fl\ii] ''I~ QF on a firm basis, a network resource must be performed by Idaho Power's delivery SIS will identify the need and associated costs for ng "upgrades" (as that term is defined in Idaho Power allow the QF to operate as a DNR and deliver firm energy to the Company's load centers. The Federal Energy Regulatory Commission's rules require that Power Supply make the request to Delivery to perform the SIS. Delivery will bill Power Supply for the costs incurred to perform the SIS. NETWORK RESOURCE INTEGRATION STUDY AGREEMENT -1 AGREEMENTS: 1. Developer hereby requests that Power Supply initiate the process for Delivery to conduct a SIS for determining the cost of the QF's becoming a DNR for the Company. Developer agrees to pay all charges associated with any analyses that Delivery determines are reasonably necessary to evaluate the impact of the QF on Developer of the 3. cuted by Developer, payment of the required to enable Power Supply to d ce the SIS. Subject to Developer's providing any requested supplemental payments in a timely the SIS with due diligence. Power Supply will respond to Developer's reasonable requests for information regarding an estimated completion date for the SIS and, if necessary, with an explanation of why additional time is required to complete the SIS. NETWORK RESOURCE INTEGRATION STUDY AGREEMENT-2 4. Following completion of the SIS, a copy of the completed SIS shall be provided to Developer. Power Supply and Developer shall then reconcile the payments made for the SIS and "true-up" any over or under payments made by Developer. The total charge to Developer for the SIS will not exceed the actual cost of the SIS as billed by Delivery to Power Supply. IN WITNESS WHEREOF, the Parties have ..r&~~sed this Agreement to be ~/ ~·~ executed effective on the first day written above. , -·''1 . NETWORK RESOURCE INTEGRATION STUDY AGREEMENT-3 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 20 March 3, 2010 The New Energy Company LLC Attn: Laura Knothe 8720 Vic Lane Middleton ID 83644 E-mail Copy: laura@thenewenergycompany.com RE: Letter of Understanding An IDACORP Company Randy C. Allphin Sr. Energy Contract Coordinator Tel: {208) 388-2614 rallphin@idahopower.com Swager Farms Dairy-Proposed Anaerobic Digester Project Ms.Knothe, Summarized below is a brief outline of the purchase power agreement, interconnection process and transmission capacity requirements for your proposed generation project. Purchase Power Agreement The project you have described appears to be eligible for a purchase power agreement under the guidelines for a Qualifying Facility as defmed by the Public Utilities Regulatory Policies Act of 1978 (PURPA). At the time you are ready to proceed with a purchase power agreement for this project, Idaho Power will prepare a purchase power agreement that complies with the current rules and regulations that govern these PURP A agreements, any draft purchase power agreements previously provided to you for review must be updated to include current rules and regulations. Prior to Idaho Power executing a purchase power agreement it will be required that you have: 1.) Provided documentation that substantiates that the project has filed for intercolUlection and is in compliance with any payments and/or other requirements specified in the Interconnection process for this project and; Page 1 of4 P 0 Box 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702 2.) Received and accepted an interconnection feasibility study for this project and; 3.) Returned a signed copy of this letter of understanding and all of the required information to enable Idaho Power to file an application requesting transmission capacity for this project. Completion of the enclosed Transmission Capacity Application Questionnaire will provide the majority of this information and; 4.) Confirmation that the results of the initial transmission capacity application are known and the project accepts these results and intends to continue with the development of the project including, if applicable, execution of a Network Resource Integration Study Agreement in the form enclosed herein. Interconnection and Transmission Capacity Your project will be responsible for all costs of physically interconnecting the project to the Idaho Power electrical system and any costs associated with acquiring adequate firm transmission capacity on the Idaho Power transmission system to enable the project's energy to be delivered to Idaho Power customers. Interconnection Your project will be required to complete the interconnection process and execute a Generation Interconnection Agreement ("GIA''). Transmission Capacity To sell your project's energy to Idaho Power, your project must be designated as a Network Resource ("DNR"). In order for this project to achieve DNR status, Idaho Power is required to make a request (complete and file an application) and be granted firm transmission capacity from the Idaho Power delivery business unit ("Delivery") to move your project's energy from the physical interconnection point to Idaho Power customers. In accordance with various rules and regulations, the project must be granted DNR status no later than 60 days prior to the project delivering any energy to Idaho Power. Idaho Power will begin this ftrm transmission capacity application process only after the project has returned a signed copy of this letter of understanding and all of the information required for Idaho Power to file this application (see attached Transmission Capacity Application Questionnaire). After filing a complete flllU transmission capacity application with Delivery, Idaho Power will receive notification back from Delivery within 30 days that: (a) adequate transmission capacity is available for this project without the need to construct upgrades; or (b) a transmission capacity system impact study is required to determine the available transmission capacity and/or required upgrades; or (c) a statement of the required transmission upgrades and the associated costs. Idaho Power will notify the project of this response to the transmission capacity application in a timely manner after the response is received from Delivery. Page 2 of4 P 0 Box 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702 If the response from Delivery is as specified in item (a) (transmission capacity is available), the project will be required to execute a purchase power agreement with Idaho Power within 30 days in order to retain this transmission capacity reservation. If the response from Delivery is as specified in items (b) or (c) (studies required and/or upgrades required), the project will be required to execute a Network Resource Integration Study Agreement (sample copy attached for your information) and submit all required deposits or fees within 15 days after receiving notification of this requirement in order for Idaho Power to continue the transmission capacity request. This Network Resource Integration Study Agreement will specify that the project will be responsible for costs incWTed by Idaho Power to perform any required studies. If, after the studies are concluded the project wishes to continue the pursuit of transmission capacity, the project will also be responsible for all transmission system upgrade costs identified within the studies. The fees and costs will be in the form of both initial deposits as well as actual costs. If at any time after executing the Network Resource Integration Study Agreement the project does not pay any required fees, or elects to stop the transmission study or upgrade process, the project shall be responsible for all costs incurred by Idaho Power in performing the studies or upgrades up to the point of termination of the Network Resource Integration Study Agreement. Upon successful completion of the above described transmission capacity upgrade process, a transmission capacity reservation will exist for this project. However, in order to fmalize this transmission capacity reservation, a purchase power agreement' with Idaho Power must be executed no later than 30 days after the transmission capacity upgrades are completed. If the purchase power agreement is not executed by this deadline, the transmission capacity reservation will be released and this process will have to be repeated if the project later requests transmission capacity. As noted earlier, this transmission capacity acquisition and associated Network Resource designation must be completed, at the minimum, 60 days prior to the project delivering any energy to Idaho Power. In addition, the project must provide routine updates to Idaho Power of the expected online date of the generation project to ensure Idaho Power is capable of accepting the energy from the project on the actual date the project comes online. Page3 of4 P 0 Box 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702 Please return all required infonnation to: Idaho Power Company Attn: Randy C. Allphin P0Box70 Boise, ID 83707 E-mail: rallphin@idahopower.com Sincerely, ({f.~· Randy C Allphin Idaho Power Company Understood and accepted this j_ day of__....::;A->t<-poL..;-.__.I ___ __,, 2010 Signature Print Name Title Page4 of4 P 0 Box 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702 An IIIACOAP torllpa'lV Transmission Capacity Application Questionnaire This fist Is the known information requirements as of the date of the letter transmitting this request. If add/tiona/Information is required, Idaho Power will promptly notify the project developer of the additional information requirements. A. Project Name 8 wa3er Dcu: reb , De 6-fBk r B. Project Location llol F B.. b.A.. C. Project Developer Name Address City I State I Zip Phone Number E-mail D. Idaho Power Delivery Business unit Interconnection ''Que" reference number (if not known, please contact the Idaho Power Interconnection group) E. Evidence of the Project's good standing status in the Idaho Power Interconnection Process ~;;~~~i ~~~$ CI0-~~1tfp~ F. Copy of the Idaho Power Interconnection feasibility study and a statement from the project that the project has accepted the results of the interconnection feasibility study and is continuing the process of interconnecting and developing the generation project. G. Maximum Capacity (MW) l, '2.. M.vJ Page I of3 H. I. J. Beginning day and time of energy deliveries Day (mrn/dd/yyyy) $\ \ I a 0 l \ Time 1$~ 00 Clt ffi Ending day and time of energy deliveries Day (mm/ddtyyyy) 12\ \ \ 4-0Glle Time 6 ~ 06 ~ ro VAR capability (both leading and lagging) of all generators 1 q ~ lf(J._J~S 1 • fS(o..~ K. Identification of the control area( s) from which the energy will originate ~=~-h;! :~;~.:f~o :-if!:.ha fg ~ L. List any periods of restricted operations throughout the year t' -0 0':0 C! ... CMI\ =-b r ; pc< r ...R cl, M. Maintenance schedule N. Minimum loading level of each generation unit ___ _.::f.o:!:::..:=0:::...0....L.{_~..oL._ _______ _ 0. Normal operating level of each generation unit. --.....l/_0.::...:=0:::...0+1-60~.-_______ _ Page2 of3 Q. Approximate variable generation cost ($/MWh) Note -this will be estimated energy pricing from a potential purchase power agreement that this project may be eligible for. {)at (lqpS,ol"rr-Pcl va.t ,a.bl..e jentLrrJ"'~· R. If the generation resource is to be located in the Idaho Power Balancing Authority Area and if only a portion of the resource output is to be designated as a Network Resource, then explain arrangements governing sale and delivery of additional output to third parties. S. If the project is not directly interconnected to the Idaho Power transmission system, provide the transmission provider(s) name, Point of Receipt, Point of Delivery and the transmission reservation number for all of the transmission providers required to deliver the project's energy to Idaho Power. Transmission Provider(s) Name _:Q-1--.J..!A'-'------------------------ PolntofRecelpt ____________________________ _ Point of Delivery ____________________________ _ Transmission Reservation Number(s) ------------------------ T. If the project is directly interconnected to the Idaho Power transmission system, provide the Point of Receipt, physical location and voltage. Point of Receipt D Physical Location n 0 1 £. 3 <oOO [\) Voltage \ d . 5 \:_ V U. Is the project committed to execute a purchase power agreement with Idaho Power upon a favorable resolution of the identified interconnection and transmission costs? Yes~ NoD V. Is any portion of the maximum capacity identified for this project committed to any other party? Yes D No r:::J/ Signature ~c-~~' --'-~=--===---Date ----'-'-/ -'-/l-+-{--=--s.-o---=--t _0 __ _ Page 3 of3 NETWORK RESOURCE INTEGRATION STUDY AGREEMENT THIS Agreement is made and entered into this __ day of ____ 20_ between Idaho Power Company ("Idaho Power'' or "Company") through its Power Supply business unit ("Power Supply") and to the Company's load centers. The Federal Energy Regulatory Commission's rules require that Power Supply make the request to Delivery to perform the SIS. Delivery will bill Power Supply for the costs incurred to perform the SIS. NETWORK RESOURCE INTEGRATION STUDY AGREEMENT -1 AGREEMENTS: 1. Developer hereby requests that Power Supply initiate the process for Delivery to conduct a SIS for determining the cost of the OF's becoming a DNR for the Company. Developer agrees to pay all charges associated with any analyses that Delivery determines are reasonably necessary to evaluate the impact of the QF on Developer's reasonable requests for information regarding an estimated completion date for the SIS and, if necessary, with an explanation of why additional time is required to complete the SIS. NETWORK RESOURCE INTEGRATION STUDY AGREEMENT-2 4. Following completion of the SIS, a copy of the completed SIS shall be provided to Developer. Power Supply and Developer shall then reconcile the payments made for the SIS and "true-up" any over or under payments made by Developer. The total charge to Developer for the SIS will not exceed the actual cost of the SIS as billed by Delivery to Power Supply. NETWORK RESOURCE INTEGRATION STUDY AGREEMENT-3 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 21 The New Energy Company, LLC April 2, 2010 Rowena Bishop Idaho Power Company 1221 W Idaho Street Boise ID 83702 Re: Facility Study Agreements for Projects 307 and 308 and Interconnec­ tion Application for additional capacity for Project 309 Dear Ms. Bishop: Please find enclosed the following applications and applicable deposits: Facility Study Agreement and deposit in the amount of $11,740 for Project 307, Swager Dairy Digester Facility Study Agreement and deposit in the amount of $11,250 for Project 308, Double B Dairy Digester Interconnection Application and deposit in the amount of $1000 for additional capacity of 1.6 MW (for a total of 4.0 MW) for Project 309, Rock Creek Dairy Digester. Please contact me at 208.890.8783 if additional information is required. Thank you, Laura Knothe, PE The New Energy Company, LLC 8720 Vic Lane Middleton, ID 8366 Phone: 208.890.8783 Fax: 208.585.90 16 E-mail: laura@thenewenergycompany.com . I Facilities Study Agreement TIDS AGREEMENT is made and entered into this 2nd day of April, 2010 by and between _The.New Energy Company, LLC_, a Limited Liability Company_ organized and existing under the laws of the State of . .. Idaho. ("Interconnection Customer,11) and Idaho Power Company, a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on. October 12, 2009, and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a system impact study and provided the results ofsaid study to the Interconnection Customer; and WHEREAS; the Interconnection Customer has requested the Transmission Provider to perform a facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conc~usions of the system impact study in accordance with Good Utility J>ractice to physically and electrically connect the Small Generating Facility with the Transmission Provider's Transmission System. NOW, THEREFORE., in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provid~r· shall cause a facilities study consistent with the standard Small Generator Interconnection Procedures to he performed in accordance with the Open Access Transmission Tariff. 3.0 The scope of the facilities study shall be subject to data provided in Attachment A to this Agreement. 4.0 The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s). The facilities study shall also identify (1) the electrical switching configuration of the equipment, including, without limitation, transformer, switchgear, meters> and other station equipment, (2) the nature and estimated cost of the Transmission Provider's I Interconnection Facilities and Upgrades necessary to accomplish the interconnection, and (3) an estimate of the time required to complete the construction and installation of such facilities .. 5.0 The Transmission Provider may propose to group facilities required for more than one Interconnection Customer in order to minimize facilities costs through economies of scale, but any Interconnection Customer may require the installation of facilities required for its own Small Generating Facility if it is willing to pay the costs ofthosefacilities. 6.0 A deposit of $11,740.00 is due upon execution of this agreement by the Interconnection customer. 7.0 fu cases where Upgrades are required, the facilities study must be completed within 45 Business Days of tlle receipt of this Agreement. In cases where no Upgrades are n~cessary, and the required facilities are litnited to Interconnection Facilitie$, the facilities study must be completed within 30 Business Days. 8.0 Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the facilities study must be completed and the facilities study report tran~J;D.itted within 30 Business Days of the futerconnection Customer's agreement to conduct a facilities study. 9.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the futerconnection Customer after the study is completed and delivered and will include a summary of professional time. 10.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Idaho Power Company -Delivery Signed&/ &.-,~ PrintedName: 6u!AI?JP ~~~'tt>lrg_ Title: PM .Su~E/Ltl!.S'Ito f, 4/t~/ra Interconnection Customer: Signed:~ PrintedName: ~ ~vw+h, P{;; Title: _f+Yi.:...l~~·b.:e c~i~~~-~~,__.==-- J Attachment A to Facilities Study Agreement Data to Be Provided by the Interconnection Customer With the Facilities Study Agreement 1. Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. On the one,. line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT /PT) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps 2. One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station.. Number of generation connections: 1 connection 3. Will an alternate source of auxiliary power be available during CT IPT maintenance? Yes No NA 4. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? Yes No _ x __ (Please indicate on the one-line diagram). 5. What type of control system or PLC will be located at the Small Generating Facility? Automation Direct 6. What protocol does the control system or PLC use? __ Modbus or other if required __________________ _ 7. Please provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines. 8. Physical dimensions of the proposed interconnection station: NE Comer of 3900 N 1700 E , I 9. Bus length from generation to interconnection station: __________ TBD ________________________________________________ ~~ 10. Line length from interconnection station to Transmission Provider's Transmission System. ________ TBD __________________________________________________ _ 11. Tower number observed in the field. (Painted on tower leg)*: TBD =-----~== ---=-=====--------======-------------------------------- 12. Number of third party ease:ments required for transmission lines*: ________ __;None anticipated:__ ___________________________ _ *To be completed in coordination with Transmission Provider. 13. Is the Small Generating Facility located in Transmission Provider's servic.e area? Yes --=.:x'--__ No _____ lfNo, please provide name oflocal provider: 14. Please provide the following proposed schedule dates: Begin Construction Generator Step-Up Transformers Receive Back Feed Power Generation Testing Commercial Operation Dme: __ ~1=0/~1/=2=0=10~------------ Date: 4/15/2011 Date: ----=5/~1=5/-=2_,_01~1,_ _____ _ Date: __ ...;:8:!....:/1=/2=0"-"1'""'"1 __________ _ Project #307 Swager Farms _. Clover Substation * POl e Capacitor Bank Addition --COVR12 --46kV Transmission Line --Roads BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 22 May 7, 2010 The New Energy Company LLC Attn: Laura Knothe 8720 Vic Lane Middleton, ID 83644 Original and Attachments: Scheduled for Pick up at Idaho Power on May 7, 2010 Cover letter E-mail copy: Laure Knothe Dean J. (Joe) Miller laura@thenewenergycompany.com joe.mcdevitt-miller.com Re: Swager Fanns Digester, Project #31616130 Ms. Knothe, ® An IDACORP Company As you are aware on March 16, 2010, the Idaho Public Utilities Commission (IPUC) issued Order 31025 which revised the Published Avoided Cost rates. These rates are the energy prices Idaho Power is required to include in PURP A purchase power agreements for projects less than 10 average MW. This Order was very specific in stating that any contracts executed after March 16, 2010, must have the new energy pricing. However, in regards to the Swager Farms Digester project, our records indicate that prior to March 16, 2010: a.) The interconnection feasibility study had been completed and the project was continuing to progress through the interconnection process. b.) Information from the project required to complete and file the transmission capacity application had been provided. Subsequently the transmission applications were filed and Idaho Power received confirmation that contingent upon execution of both a Generation Interconnection Agreement (GIA) and purchase power agreement, transmission capacity is available for this project. c.) A PURPA purchase power agreement was materially complete and except for routine final processing, an agreement would have been executed prior to March 16, 2010. P.O. Box 70 (83707) 1??1 W ltl:>hn ~t At this time Idaho Power is willing to execute the attached PURP A purchase power agreement that contains the energy prices that were in effect prior to JPUC order 31025 issued on March 16, 2010 contingent upon the project returning fully executed agreements to Idaho Power prior to 5 PM Mountain time, on May 24, 2010. Upon receipt from you of the three signed copies of the PURP A purchase power agreement enclosed with this letter by the above due date, I will arrange for and present the agreement to Idaho Power Company management for their signature. I will return to you one fully executed copy for your records, and Idaho Power will prepare and file a copy with the Idaho Public Utilities Commission (JPUC) requesting approval of the agreement. Idaho Power will keep the third copy for our records. If all three copies of the PURP A purchase power agreement are not executed and received by Idaho Power by the time and date specified above, this specific agreement (which includes the pre March 16, 2010 PURPA energy prices) will no longer be available for this project. Idaho Power will update any future proposed PURP A agreements for this project to be in accordance with all current and applicable rules, regulations and energy pricing. Please use one of the following addresses to return the executed agreements to Idaho Power: US Mail: Idaho Power Company Attn: Randy Allphin POBox70 Boise, ID 83 707 Overnight Mailing Address: Idaho Power Company Attn: Randy Allphin 1221 Widaho Boise, ID 83 702 This agreement as with all PURP A purchase power agreement will require Idaho Public Utilities Commission (JPUC) approval. Only after both parties have executed this agreement and the IPUC has approved the agreement, as specified within the agreement, shall the agreement be considered to be effective and a binding commitment shall exist between the parties. If you have any questions please do not hesitate to contact me. Sincerely, /?;f.~- Randy C. Allphin Senior Energy Contract Coordinator (208) 388-2614 E-mail: rallphin@idahopower .com BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 23 August 17, '1010 Laura Knothe The New Energy Company 8720 Vic Lane Middleton, ID 83644 Re: Swager Farms Dairy Digester Project Facility Study Report -Project #307 Dear Ms. Knothe: An IDACORP Company Idaho Power Company (IPC) has completed the Facility S,t dy c.ost estim te for your Generator Interconnection project. Attached please fmd a Draft Facility Study Report (PSR). I am available to discuss the FSR, and begin Construction ·arrangements for the project. In order to proceed with this project, please provide your comments to the Facility Study Report to me by September 17, 2010 and indicate whether you wlsh to proceed with final design and construction. The fmal report will be us~d to prepare a draft Generator Interconnection Agreement in preparation for Construction. Rowena Bishop will be working with you to fmalize the Interconnection Agreement. Before we can begin Construction or order rna erials you are tesponsible for contacting Idaho Power's credit departmen to cliseuss credit requirements for ·epnstruction funding. Please contact Kelley Noe (208-38.8-5736} at your earlie t convenience. Once we receive funding, or the credit Tequirement is et, we can proceed with c;on truction of the project. The actual construction and litbor eharges w.ill.be finalized approximately 90 days subsequent to project completion. We will reconcile any·ovet-or underpayment at that time. I look forward to hearing from you soon. Sincerely, Eric Hackett Project Leader Attachment: Swager Farms Dairy Digester Project Draft Facility Study Report with Drawings Cc: R Bishop/IPC KNoe/IPC A Sloan/IPC DRAFT Generator lnterconneQ'tion Facility Study J{ep0rt for lihe Swager Farms Dairy Digester Proj;eet -Project #307 An IDACORP Company DRAFT-FACILITY STUDY REPORT (FSR) Swager Farms Dairy Digester Project #307 August 17, 2010 1. General Facility Description The proposed project will consist of Idaho Power's standard overh~ad generation interconnection package including an overhead recloser, metering package, local service power transformer, disconnect switches, and a relay/control box. Additionally, one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transform · w,nl be installecJ, including the associated underground cabling and vaults. The project is locat;ed Twi n Falls County, Ida,ho and connects to the 12.5 kV system on Idaho Power Company's @lover (CL:YR-012) distributldn line. The total project output is 1.2 MW. Interconnection Customer: Laura Knothe The New Energy Company 8720 Vic Lane Middleton, ID 83644 A Standard Generator nte ·G<;)nn ction Agreement under r1::litho Power Company's Open Access Transmission Tariff (OATT) or phedule 72 be'ftWeen Interconnection Customer and Idaho Power Company -Delivery ~'FJ;ansrnis ion Owner) f6).; the Swager Farms Dairy Digester Project, specifically Generator nterco · eal}i~n Project #3,07, will be prepared for this project. Final drawings will1be pr9duced in•WJe · elin he~b below in MILESTONES. ~) 2. Interconnection Point ... The'"lniei·b~nnection Poinf.}'6r the ~Sw.ager Farms Dairy Digester Project will be the low-side bushings on·the' padmounted'transformer (SW1). The project's location is in TlOS Rl5E Section 21 of Twin Falls 'Gounty, Idaho. A drawing identifying the Point of Interconnection is attached. 3. Point of Change of Ownership The Point of Change of Ownership for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SW1). 4. Interconnection Details In general, interconnection equipment includes, but is not limited to, switching/disconnection, metering, system protection and control, and communications/telemetry. All interconnection equipment electrically located on the generator side of the Point of Change Ownership shall be owned and maintained by the Generator. All interconnection equipment electrically located on the utility side of the Point of Change Ownership shall be owned, operated, and maintained by Idaho Power. 1 4.1 Project Team An Idaho Power Company project team was assembled to investigate the proposed project, and develop cost estimates and a project schedule to construct Idaho Power facilities required for the interconnection. The project team consisted of the following employees: -··--·-"-Senior Engineer En ~in_e_er_--J~.r.s>J:.ect_io_n_ ........... -------1-M-~~e~ing Technical Advisor 1 Area Ap~atus Leader._ R~_ght ofWay .. ~e._n.t --···-.. -----I I Design Engineer Distr~~ution ~iti~()Sesigner ------1 r-::----;'s · D · · tatlons est ner 4.2 Customer's Interconnection Facilities switches, all feet of the 4.3 Other Facilities Provided by 4.3.1 4.3.3 Monitoring Information If the Interconnection Customer requires the ability to monitor information related to the Idaho Power recloser in the generation interconnection package they are required to supply their own communications circuit to the control box. 4.3.4 Easements The Interconnection Customer will secure underground and overhead easements with Swager Farms Dairy once a specific route is determined. Idaho Power will provide the documentation. 2 4.4 Idaho Power Company's Interconnection Facilities Idaho Power will install a standard generation interconnection package on the ex1stmg distribution feeder (CLVR-012) on private property southwest of the intersection of 3800 North and 1700 East in Twin Falls County, ID. See the attached work order maps (WO 27328106, sheet 1 of2) for details. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-311C line protection relay. The relay will be located in a pole mounted enclesure and will also contain a test switch (TS4), SLSS, modems, isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) oQ.~-,1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye :;padmounted transfor~er .. on top of a vault. Conduit and underground cables will be ~ installed from the intercohiiection package to )\. -, •• · !~· ' ~--~· padmounted transformer. Protective posts wi}l,.,be installed to protect the. ground mounted equipment from damage. '· · ·' · A 2" conduit will be installed alo.ngs~de the undergrotina'primary to facilitate information exchange to the customer about tlie recloser. (The Interconilectign Customer is responsible for providing and installing the appropriate cable.) . ' 4.5 Scope of Upgfaaes Idaho Power ~iil;.J.install anew capacitor B~nk on the existing distribution feeder (CLVR-012) just west of_Jh~:i,#~ting Clo~:er Substation; ~ee the attached work order maps (WO 27328106, sheet~2 ;~1:~) for d~tails. ~ ' l. The projec~·wpst be controlled to operate at a lagging power factor of 90% during the fall and spring months and between 90% and 98% during the summer and winter months or meet the voltage schedule provided by Idaho Power. Voltage flicker at startup and during operation will 'be limited to less than 5% as measured at the point of interconnection. For this to occur, the current cannot exceed 46 Amps during start up at the 12.5 kV voltage level. This forces the generating facility to start the generators separately. The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems. 3 5. Budget The following good faith estimates are provided in 2010 dollars: Estimated Cost & Ownership: and 1500 kVA Transformer Milestones: GRAND TOTAL 4 .. X- . H # _M ~ " ! _ E ~ \ ! ' I G PA C K A G E P- # # MF G R TY P E " l -- - - - - - 1 CO O P E R "V W V E 3 B X " BY IP C O -- - - + - - - - B Y OW N E R TH 12 , 5 0 0 - 4 8 0 / 2 7 7 2.5 M V A H2 HO · I ~ 1 H3 Z= l l X2 X~I · X O X3 60 0 - 1 5 t : RE Q O S E R r 2 ~' < > I , , , ~o o · ~ c 56 0 - 3 5 X- Jl. # 2 3 r" -I ! ,~ , , D "i ' o o ! , ' g ' ' " ! ~ •( " -"1 I ,. - - ~ ' " " ' - - - < i 15k V A -- ~ -t ~er - -- - r - - - - - 2 1 51 Sl ~I 8 1 §I ~ I ~ I s; : l ~ I 1 ;j " ' ·"' i '" ' -- - - 1--- , ~ I ~I L __ I )C A L SE RVI C E iE L 3 1 1C BO X I I 15 k V A 72 0 0 - 1 2 0 / 2 4 0 V 91 2 I I I I I I I I #± 60 0 k W CA T E R P I L L A R G~ 5 1 2 SY N C R O N O U S GE N E R A T O R PR O J E C T LO C A T I O N : #± I ' "" 4 "" J • 2 E 0 ~ ~ ~ c ~ ~ l ~ ~ I l: ' ~ El ~ ~ ~ ~ ~ ~ ~ I ~ ~ CO V R 01 2 12 . 5 k V BY IP C O - -- + - - -- B Y O~ E R Tl 1 ;u oo_.q o n ,, ,J . - . f k ,. ~ ' ! ' ! ! ' ~ - ~ , ~-.u <: . l l . r o- - - - - - - - 1 00 0 - 1 5 I I R£ W m l X- I I I l -- - < > ! ., , : ... ~~ ~ """ ' ., ~ , I l I .. . . . . H I ' : ~ xl I • w ,. , , ~~ ~ -0 - t '-- -- r - - - ~ b • I ' ' ( ! -t ! l ~ : J, ~~: . _ 1"' /' " ' ' •- - - - - - - ~ - - - j ( !ii 1 OS 1 ) OS 2 1 r '' I J, 1,._ , , '< ' ~ I !:> 1 1' ,. , _ , , "<O V e 1 t: l 11 2 aq ~ I lS I 52 G 1 => 2 C 2 Sl ~ I 10 L ~ I I -- I IP C O LO C A l S< R V I C E I '" " S£ L J 1 1 C eo x I I I I I I I -· CA T W I I . L . M lm ! J "" " " " " " c:D € J I I l l 0 o t .. -· CATC l P I J . . , U CJ & : Z "" " " " " " .., . . . . " " ' PR O J E C T LO C A T I O N · TIO S . RIS E , SE C T I < l ' 4 21 • !L . .J 8 0 0 NO R T H 17 00 EA ST. TW I N FA L L S CO U N T Y . ID A H O IN SE R V I C E BY t.t A Y 20 1 1 .. J • 2 " AL L O ~ D CA P A C I T Y RE V I S I O N t-2l - lf l lr, I I W ,.l e ' . . , . , . . " " jO.I o ~. /·.,. , . . , D IIr y ~- p : ~U'fo~ .. . rr f • E 0 BY CO N T R A C T : -- - - - KV A j 1 ~ , . ., , ... ,, ~ '- " ' " + ~ SIN G l E LIN E AP P R O V A L SJ . u t t r d ~ ; ~ e r -- Coo l . . l ( . . . , . . . . , __ _ S, . L , r t t E o g . -­ .l( l ~ r o l u , ( " " ' n . . , ~- - 6"C ~ ~ < O ' d l o o o ! t o -­ ~ & .. ie o d L"" ' " ' -- - a fi- o j : d l . c u d : r -- Plc . . . o ~ g .. . . R(I U I I N Q Y -~ - - 10 STE V E C~ L U N T w.o . 27 J i n 4 0 llE r E R ! : N d I!A A W D I O S K~ • i i 1 1 : i ~T R < l . S D E : I I A T I C S SW A G E R FA R M S DA I R Y DI G E S T E R ~ IN T E R C O N N E C T I O N &A SI N G L E LI N E ~ ~- ~~~ ~ = = ~ ~~~ ~ ~ ~ID A A ~O b ~ ~~~~ ~ ~~ ~ ~ ~ ~ ~ I ' 4 2 E I CO V R 01 2 I 12 . 5 k V BY IP C O BY 01 \ N E R D P- f l X- , f t f-~ E ~ ! _ N ~ ~ - ~ -, ~E a . ~ J 8 X " l UF f o o - 1 5 £" ; l UF ~ " T ' I f ' C " ~z K f S ... . . . . j ~f l > 1 20 0 / S [ t- - - _ _ _ , . . . . . - .- 0 I r~ l ' s . il J ! J ~'i l 'Y ' ~~ : . " ' 1 " " L--- - - r -- -1 e~; l '2 I ~ I x- • t -= i -~ x ~! ___ T __ _ = ~~ - ·, "" ) I <> " " ' !i os 1 ) I ~I I • ' ' ~- i i< l 52 G I I'l l i~ O : C . 1 2 0 / 2 < 0 V ~ II c ~I L __ I T. ·: ~~ ,! L __ j I I • ~ ~ ~ l f ~ B ~ ~ ~ i a ~ i ~ ~ IL , IPC O LO C A L SE R V I C E FO R SU J I IC BO X 4·· .3 I I I I I "" " " - tt . T ~ ~ l . J : . c:;E N E I A T C R T ,, "" " " CA 1 E J I P I I . l . I A ~ 1 l "" " " " " " ~. t . T a l PR P . E C T LO C A T I O N · T1 D S , RIS E , SE C T I O N 21 .l8 0 0 NO R T H 17 0 0 EA S T , TW I N FA L l S CO I J N T Y , ID A H O IN SE R V I C E BY MA Y 20 1 1 ,. 1 AL L O W E D CA P A C I T Y 8Y CO N T R A C T : -- - - - KV A j 1 RE V I S I O N f.• . J 1 · 1G lo < U I I I ' " W~I i o r o " ' to o q . , r a r . , t O U , ~j!, ~j l ' 1 ~~ ... . j I t D c SIN G L E LIN [ AP P R O V A L ~~! ' X U S ~ "- - ·-­ ~1 . ·.~ -- ­ ~t " o l ~ -·-­ "'"" ' ~ c ~ ... -­ l'o " ! ; Qt g i c r > o l l . . . r " - ­ illl f l o &f01 io l l e l l + * -- a l' f t r - t l ~ - - - -- - l;t i l ()p o l -- - "" " ' " -·-­ Ill !li s t . " t ( ( J l ! M i ~ ¥A »l ,. .,i O RE F E R E H < l : .OiiA I O ! H G S o ... . ,. .... R ,_ ,,. , ~ , _ , , E M: ":iC ! ' ! t \ I A ll= ! i CO ' I T I I O . . SO € \ ! A f! CS SW A G E R FA R M S DA r R Y DI G E S T E R ~ ~ IN T E R C O N N E C T I O N ~ ~ SI N G L E LI N E r- 1. ~ ~ ~ ~ ~ ~ 0 0 ~ 1 ~ , ; ~ ~ 0 ! DA T E ! 8- 2 1 - 1 0 ~ r- ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 1- - " " ' - " - = . ; ; - = :: . , . - - - l 'i " 01 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 24 ~WESTERN ., STATES Spokane,WA 509-535-17 44 Western States Equipment Company 500 East Overland Road Meridian, 10 a3642 208-888-2287loffice) 208-884-2308lfax) Reference: Swager Farms LETTER OF GUARANTEE Subject: · Financial guarantee for the payment of Liquidated Damages payable under the Firm Energy Sales Agreement for Swager Farms, Project Number 31616130. We, the undersigned, Western States Equipment Company, an Idaho corporation ("Guarantor") hereby declare that we irrevocably and unconditionally guarantee as primary guarantor on behalf of New Energy Three, LLC ("Customer") with its place of business at 8720 Vic Lane, Middleton 10, the full and prompt payment when due of the payment obligations of Customer to Idaho Power Company ("Idaho Power") in the amount of eighty-one thousand dollars ($81 ,000.00). This Guarantee is provided to cover Customer's payment obligations to Idaho Power under paragraph 5.3 and 5.4 of the Firm Energy Sales Agreement for the Swager Farms, Project Number 31616130 (hereafter referred to as "the Agreement"). Payment shall be made by Guarantor to Idaho Power hereunder when demand for such payment is made by Idaho Power upon the failure of Customer to meet its obligations under paragraph 5,8 of the Agreement regarding the failure to meet the scheduled operation date as defined in Appendix "B". Payment shall be unconditional and absolute and without objection or legal proceedings and, without limiting the generality of the foregoing, shall not be released, discharged or otherwise affected by any modification, amendment, waiver, extension of or supplement to the Agreement, any change in the corporate existence of the Customer or Guarantor, or any insolvency, bankruptcy, reorganization or other similar proceedings affecting the Customer or its assets, or the Guarantor .. This Guarantee is a guarantee of payment and not merely of collection and Guarantor agrees that its obligations hereunder are of a primary obligor and not merely of a surety. The Guarantor agrees that Idaho Power may resort to the Guarantor for payment of the obligation whether or not Idaho Power has resorted to any collateral security, or shall have proceeded against Customer or any other obligor principally or secondarily obligated with respect to the obligation. All payments hereunder by Guarantor shall be made without set-off or counterclaim in U.S. dollars in immediately available funds. This Guarantee shall remain in force until New Energy has, to the satisfaction of Idaho Power, under the terms of paragraph 5.2 of the Agreement, achieved the Operation Date or until Guarantor is released from this Guarantee pursuant to paragraph 5.8.2 of the Agreement. Meridian, ID 208-888-2287 Pasco,WA 509-547-9541 Twin Falls, ID 208-734-7330 Pendleton, OR 541-276-5812 Pocatello, ID 208-232-2640 LaGrande, OR 541-963-3101 Idaho Falls, ID 208·552-2287 Missoula, MT 406-721-4050 Lewiston, ID 208-746-3301 Kalispell, MT 406-752-3030 This Guarantee is governed by the law applicable to the Agreement. The courts having jurisdiction for matters relating to the Agreement shall have jurisdiction in respect of matters relating to this guarantee. This Guarantee may not be amended, supplemented or modified, nor any of the terms and conditions hereof waived, except by a written instrument executed by the Guarantor and Idaho Power. This Guarantee is effective as of the date executed below. Done at Meridian, ID on August 30, 2010 Tom Harris President Western States Equipment Company BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 25 September 16, 2010 Laura Knothe The New Energy Company 8720 Vic Lane Middleton, ID 83644 I MHO POWER® An IDACORP Company Re: Swager Farms Dairy Digester Project Final Facility Study Report -Project #307 Dear Ms. Knothe: Idaho Power Company (IPC) has completed the Facility Study cost estimate for your Generator Interconnection project. Attached please find the Final Facility Study Report (FSR). I am available to discuss the FSR, and begin Construction arrangements for the project. This report will be used to prepare a draft Generator Interconnection Agreement in preparation for Construction. Rowena Bishop will be working with you to fmalize the Interconnection Agreement. Before we can begin Construction or order materials, you are responsible for contacting Idaho Power's credit department to discuss credit requirements for construction funding. Please contact Kelley Noe (208-388-5736) at your earliest convenience. Once we receive funding, or the credit requirement is met, we can proceed with construction of the project. The actual construction and labor charges will be finalized approximately 90 days subsequent to project completion. We will reconcile any over-or underpayment at that time. I look forward to hearing from you soon. Sincerely, Eric Hackett Project Leader Attachment: Swager Farills Dairy Digester Project Final Facility Study Report with Drawings Cc: R Bishop/IPC KNoe/IPC A Sloan/IPC FINAL Generator Interconnection Facility Study Report for the Swager Farms Dairy Digester Project-Project #307 for The New Energy Group in Twin Falls County, Idaho September 16,2010 FINAL-FACILITY STUDY REPORT (FSR) Swager Farms Dairy Digester Project #307 September 16,2010 1. General Facility Description The proposed project will consist of Idaho Power's standard overhead generation interconnection package including an overhead recloser, metering package, local service power transformer, disconnect switches, and a relay/control box. Additionally, one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer will be installed, including the associated underground cabling and vaults. The project is located in Twin Falls County, Idaho and connects to the 12.5 kV system on Idaho Power Company's Clover (CLVR-012) distribution line. The total project output is 1.2 MW. Interconnection Customer: Laura Knothe The New Energy Company 8720 Vic Lane Middleton, ID 83644 A Standard Generator Interconnection Agreement under Idaho Power Company's Open Access Transmission Tariff (OATT) or Schedule 72 between Interconnection Customer and Idaho Power Company -Delivery (Transmission Owner) for the Swager Farms Dairy Digester Project, specifically Generator Interconnection Project #307, will be prepared for this project. Final drawings will be produced in the timeline shown below in MILESTONES. 2. Interconnection Point The Interconnection Point for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SW1). The project's location is in T10S R15E Section 21 of Twin Falls County, Idaho. A drawing identifying the Point oflnterconnection is attached. 3. Point of Change of Ownership The Point of Change of Ownership for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SW1 ). 4. Interconnection Details In general, interconnection equipment includes, but is not limited to, switching/disconnection, metering, system protection and control, and communications/telemetry. All interconnection equipment electrically located on the generator side of the Point of Change Ownership shall be owned and maintained by the Generator. All interconnection equipment electrically located on the utility side of the Point of Change Ownership shall be owned, operated, and maintained by Idaho Power. 1 4.1 Project Team An Idaho Power Company project team was assembled to investigate the proposed project, and develop cost estimates and a project schedule to construct Idaho Power facilities required for the interconnection. The project team consisted of the following employees: Project11anager Senior Engineer ! ! Principal Engineer Relay & Communications Leader Engineer -Protection 11etering Technical Advisor --... Area Apparatus Leader Right of Way Agent Design Engineer Distribution Line Designer Stations Designer 4.2 Customer's Interconnection Facilities The Interconnection Customer will install generators, low-side disconnect switches, all wiring and conduit between the generators and the padmounted transformer, appropriate grounding measures, and associated auxiliary equipment. Interconnection Customer will build underground facilities to the Point of Change of Ownership for the generator facility. The low-side disconnect switch should be visible, lockable, within ten (1 0) feet of the padmounted transformers, and accessible to Idaho Power personnel. 4.3 Other Facilities Provided by Interconnection Customer 4.3. 1 Telecommunications The Interconnection Customer will provide two communication circuits between the generation interconnection site and a location, or locations, specified by Idaho Power. One of the circuits will be a dedicated 4-wire leased analog circuit connected to the SEL 311 C relay and the other will be a POTS dial-up circuit to the revenue meter. The Interconnection Customer is responsible for supplying and coordinating the installation of the phone lines and paying the monthly service charges. The communication circuits will need to be installed and operational prior to generating into the Idaho Power system. 4.3.2 Ground Fault Equipment The customer will install ground fault limiting equipment that will limit the zero sequence fault current to 20 amps at the Interconnection Point. 4.3.3 Monitoring Information If the Interconnection Customer requires the ability to monitor information related to the Idaho Power recloser in the generation interconnection package they are required to supply their own communications circuit to the control box. 4.3.4 Easements The Interconnection Customer will secure underground and overhead easements with Swager Farms Dairy once a specific route is determined. Idaho Power will provide the documentation. 2 4.4 Idaho Power Company's Interconnection Facilities Idaho Power will install a standard generation interconnection package on the ex1stmg distribution feeder (CLVR-012) on private property southwest of the intersection of 3800 North and 1700 East in Twin falls County, ID. See the attached work order maps (WO 27328106, sheet 1 of2) for details. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-311 C line protection relay. The relay will be located in a pole mounted enclosure and will also contain a test switch (TS4), SLSS, modems, isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer on top of a vault. Conduit and underground cables will be installed from the interconnection package to padmounted transformer. Protective posts will be installed to protect the ground mounted equipment from damage. A 2" conduit will be installed alongside the underground primary to facilitate information exchange to the customer about the recloser. (The Interconnection Customer is responsible for providing and installing the appropriate cable.) 4.5 Scope of Upgrades Idaho Power will install a new capacitor bank on the existing distribution feeder (CLVR-012) just west of the existing Clover Substation. See the attached work order maps (WO 27328106, sheet 2 of2) for details. 4.7 Operational Limitations Interconnection Customer will be able to modify power plant facilities on the generator side of the Interconnection Point with no impact upon the operation of the transmission system whenever the generation facilities are electrically isolated from the transmission system. The project must be controlled to operate at a lagging power factor of 90% during the fall and spring months and between 90% and 98% during the summer and winter months or meet the voltage schedule provided by Idaho Power. Voltage flicker at startup and during operation will be limited to less than 5% as measured at the point of interconnection. For this to occur, the current cannot exceed 46 Amps during start up at the 12.5 kV voltage level. This forces the generating facility to start the generators separately. The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems. 3 5. Budget The following good faith estimates are provided in 2010 dollars: Estimated Cost & Ownership: ltfY-;·ln-Jtl;..,~~·~,f :..•:1'' ·:.-:.• ""I ,,;,; :;•~ }:~.f:.'l~~mi~JJeil~ "' ...... :~~-~f-.t~·.:u .. Z!..!,·.t~:-d!:t~i!ito"TIWw~·2!J·~!J;.t':?!,!. ~ 'i .. rsh s Generation Facilities: ~rovided by the customer (Including low-side d~.~~onnect switch) Customer N/A -· TOTAL N/A ~,Interconnection Facilities: i--· I !Overhead Generation Interconnection Package IPC $200,000 !underground Equipment and 1500 kVA Transformer PC $60,000 l TOTAL $260,000 !upgrades to Distribution: ~-· . lrPC --· !New Capacitor $30,000 TOTAL $30,000 GRAND TOTAL $290,000 Milestones: ., I , " ' • • :~,(,.H'i I "' ,,·:,, .J1bl4?i0~ ·. ' ... ~ .. , I o " -..... •' ' ·~ ,. 'I • 09/16/10 Final Facility Study Report Submitted to Customer 10/17110 Construction Funds Received by /PC 11/5/10 Order Materials 3/15/11 IPCO Construction Completion 4/1/11 IPCO Test and Commission Equipment Completion TBD Commercial Operation Construction Budget Timeline: Feb 2010 -April2011 $290,000 $290,000 ~------------------~---------------------------GRAND TOTAL 4 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 26 I • Laura Knothe The New Energy Company 8720 Vic Lane Middleton, ID 83644 October 25, 2010 Via email & ® An IOACORP Companv Certified Mail # 7006 0810 0006 5511 2990 Re: Swager Farms Project #307 & Double B Dairy Project #308 Dear Laura: Attached please find a copy of the final Facility Study Report (FSR) and a draft Generator Interconnection Agreement (GIA) for your Generator Interconnection projects. This GIA is part of Idaho Power Company's Rate Schedule 72 tariff approved by the Idaho Public Utilities Commission (IPUC). The IPUC has the authority to review and modify these schedules periodically. You may view the most current tariff at Idaho Power's website at: http://www.idahopower.com/aboutus/regulatoryinfo/tariffs.asp . If you would like to schedule a meeting or conference call to discuss the GIA please contact me as soon as possible. Under the Generator Interconnection process, the following items must be provided to me on or before execution of the GIA: Proof of Site Control for the project Insurance certification Financial arrangements/construction funding Although the preferred method of funding is full deposit upfront; payment arrangements may be requested. If you have not already done so, please contact Jill Sprenger (208-388-6424), Finance at your earliest convenience to discuss Idaho Power's credit requirements for construction funding. Once we receive funding, or the credit requirement is met, we can proceed with construction of the project. The actual construction and labor charges will be reconciled approximately 90 days subsequent to project completion. PLEASE NOTE -While the Generator Interconnection process (Feasibility, System Impact, and Facility studies) we are going through identifies any necessary Network Upgrades that may have to be made to move your Project energy to load, it does not secure the transmission rights to do so. The GIA only provides for the physical connection of the project output to the generator side of the point of interconnection with Idaho Power's grid. It does not cover the transmission service to transfer your project output across the connection point or to the ultimate load. An additional agreement providing for transmission of the energy is required to be secured to deliver your energy from the point of interconnection with your project to Idaho Power load. You or the energy purchaser must arrange for transmission, and provide the necessary documentation prior to commercial operation. This would include either a Transmission Service P.O. Box 70 (8370"7) 1221 \11/. Idaho St. Boise, ID 83702 Page 2 of2 Request (TSR) or a Network Designation from the energy purchaser. My records show that this has already been done. You may have noticed that we have drafted the GIA Attachments based on the Facility Study Report provided to you on September 16, 2010. Please review the Attachments to make sure they are comprehensive and accurate and advise me of any changes as soon as possible. The completed Attachments must be sent to me by close of business on November 29, 2010, so that we may prepare the GIA for execution. Failure to respond to this letter will be considered as an election not to pToceed with the project, and we will consider your Generator Interconnection request to have been withdrawn and terminated. If you have any further questions, please don't hesitate to contact me. Encl: Final Facility Study Reports-# 307 & #308 draft GIA for Swager Farms Project# 307 draft GIA for Double B Dairy Project# 308 Cc: (via email) Eric Hackett /IPC Rich Bauer/IPC Jill Sprenger/IPC Randy Allphin/IPC Sincerely, &1J~o~ Operations Analyst rbishop@idahopower.com ph 208.388.2658 Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29 Tariff No. 101 October 25, 2010 Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 1 of 1 TABLE OF CONTENTS RECITALS .............................................................................................................................................. 1 AGREEMENTS ...................................................................................................................................... 1 1. Capitalized Terms ................................................................................................................ 1 2. T arms and Conditions .......................................................................................................... 1 3. This Agreement is not an agreement to purchase Seller's power ......................................... 1 4. Attachments ......................................................................................................................... 1 5. Effective Date, Term, Termination and Disconnection .......................................................... 1 5.1 Term of Agreement ................................................................. , :"; ...................................... 2 5. 2 Termination .......................................................................... '· -:~.%= -~:· ..................................... 2 5. 3 Temporary Disconnection. .............................................. ,_. -:·.~f-:;~ ......................................... 2 6. Assignment. Liability, Indemnity, Force majeure. Consegh E;(jt(a/ Damages and Default. ...... 5 7. Insurance ................................................................. ,~4[{;"':( .. :X~~j;-..................................... 7 8. Miscellaneous ...................................................... · .... ~k'~ ............ :C:i-1?:-•................................. 7 9 N t. 1.26"-"'~'%;~ :-8 . o rces. . . . . .. . .. . . . .. . . . . . . . . . ... . . . . . . .. . . .. .. . . .. . .. . .. . . . . ... ... ·.-:r .......................... · · · . ·. ·. · · .. · · ·· · · · · ·· · · · · · · · · · ·· 1 o s· t ,} .• ~ .-·· ·t&~ 9 . rgna ures ................................................... -;.ft ~_,: .............................. ~~?;_£~~"~:············· .. ···:···· Attachment 1 ....... .... .. . .... ..... ....... ........ ..... .... ... ....... .... . '· r: ...................... Error! Bookm~rk not defmed . . ~,..,, ._. /_L Attachment 2 .......................................................... !-):!{!.:' .................... -., .. Error! BookMf;Jif\_not defined. Att h t 3 w.;z,r-. ·· £~ / ·?:· E I B k· . >tl~?. t d f' d ac men ............................................................... ---.'·;--........... , ~ ·f·.·.. rror oo mar"" no e 1ne • Attachment 4 ......................................... -....................... ~~-•... i d.1f'~.~ ... Errorl Bookmark not defined. :-o'"J"'; 7/"/. '<I 4)' Attachment 5 .................................................................... ~{ J: '(>:: ......... Error! Bookmark not defined. Attachment 6 ........................................ :4-1 :;;~ :/ _ .•...•.•••......... ~~;. .• _ ......... Error! Bookmark not defined. v1tJ;• ''~p~ %).{:~·' ?.4• >:W,f'?ffpa-, .; 'Z' ,. •i:.~« . ;~,#'~.-:-"'•¥ ,t/ -r~ · ~bK-'~ ./,;f.·h . . ;~-. --~ l"/,, . :,~?:'!-, . . -~.t~!f~h .,~~~~4~~y~~~/ -"i1'·-~·"'·· ~-~~r" "'~a-, .', , .. ~, ,,;;:;;;.;.~; ~~ ·''" y.:· ··'diP /:'(./~:·. . /" (•··· . . n'c;,;;•,;;. ::."!'.' -~. ~ ... ~d-:: t;y.~ ~~~-~ ,, ... .. ·z·,- 4 4;) ~~ -~>~~.(. . ·< .. ;.~:~, ,,,__, ~":/.:!".-:• .. ,P:;, _ _,_ -·~~~"-'J:-:t.;';<Y·Yjf;·}f. !:]!,·-,. ~[£~ ~ 1'~1--./Y:f'·· · ~-.'(f~(_fix~~~~ -~v ., ":t;; --z;~:e-? --~· '"·:.-w>@, · ~"'--~;;(~)'-... -~'11/~~~y f. .. ~;~~~ . ,'1'$'' ·-;:ff7t~ -.:·'::!!.,-. ~1-¥-.. ·~·~h}t·· ,.,,_~·f·. '(}'/~-. ·~· , .. /. ·;r.p;/ Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 1 of 9 This Generator Interconnection Agreement ("Agreement") under Idaho Power Company's Schedule 72 is effective as of the day of , 2010 between ____________ , ("Seller'' or "The Project") and Idaho Power Company -Delivery ("Company", or "Transmission Owner''). RECITALS A. Seller will own or operate a Generation Facility that Power's Commission-approved Schedule 72 and any successor B. The Generation Facility covered by this Attachment 1. AGREEMENTS 1. Capitalized Terms Capitalized terms used herein shall have the ~~n.,a.".r. of this Agreement. 2. Terms and Conditions This Agreement and Schedule 72 Seller's Generation Facility will ,..,#..,_,.,..,.., transmission/distribution system. Terms this Agreement. If there is any conflict Schedule 72 shall prevail. 3. for service under Idaho and conditions under which the parallel with, the Company's the same defined meaning in u~~[_,n~•~rnBnl and Schedule 72, may require will be covered under separate to affect any other agreement between the and Costs of the Generation Facility, Interconnection Diagram Depicting the Generation Facility, Interconnection ,,,,.;)="'•n and Upgrades. For Interconnecting the Generation Facility. A -Additional Operating Requirements for the Company's Transmission System Needed to Support the Seller's Generation Facility. Attachment 5-Reactive Power. Attachment 6 -Description of Upgrades required to integrate the Generation Facility and Best Estimate of Upgrade Costs. 5. Effective Date, Term. Termination and Disconnection. Idaho Power Company Generator Interconnection Agreement# 307 · I.P.U.C. No. 29. Tariff No. 101 Page 2 qf 9 5.1 Term of Agreement. Unless terminated earlier in accordance with the provisions of this Agreement, this Agreement shall become effective on the date specified above and remain effective as long as Seller's Generation Facility is eligible for service under Schedule 72. 5. 2 Termination. 5.2.1 Seller may voluntarily terminate this Agreement upon expiration or termination of an agreement to sell power to the Company. 5.2.2 After a Default, either Party may Section 6. 5. 5.2.3 Upon termination or expiration of Facility will be disconnected from the termination or expiration of this Agreement shall not relieve and obligations, owed or continuing at the time of the ranrrur•<=>nn• Section shall survive termination or expiration of this Agreement. Agreement pursuant to the Seller's Generation ution system. The of its liabilities provisions of this 5.3 Temporary Disconnection. Temporary disconnection shall only for so long as reasonably necessary under "Good Utility Practice." Good Utility Practice means any of the practices, methods and acts in or approved by a significant portion of the electric industry during the relevant time any of the practices, methods and acts which, in the exercise of reasonable judgment facts known at the time the decision was made, could have been expected to result at a reasonable cost consistent with good business practices, reliability, Good Utility Practice is not intended to be limited to the optimum practice, of all others, but rather to be acceptable practices, methods, in the region. Good Utility Practice includes compliance with Payment of lost revenue resulting from temporary disconnection governed by the power purchase agreement. 5.3.1 Condition" means a condition or situation: (1) that in the judgment of making the claim is imminently likely to life or property; or (2) that, in the case of the Company, is imminently likely (as in a non-discriminatory manner) to cause a material adverse effect on the or damage to the Company's transmission/distribution system, the "'"'""'""'''""'" Facilities or the equipment of the Company's customers; or case of the Seller, is imminently likely (as determined in a non­ to cause a material adverse effect on the reliability and security Generation Facility or the Seller's Interconnection Facilities. Under either the Company or the Seller may immediately suspend and temporarily disconnect the Generation Facility. The notify the Seller promptly when it becomes aware of an Emergency may reasonably be expected to affect the Seller's operation of the Facility. The Seller shall notify the Company promptly when it becomes aware of an Emergency Condition that may reasonably be expected to affect the Company's equipment or service to the Company's customers. To the extent information is known, the notification shall describe the Emergency Condition, the extent of the damage or deficiency, the expected effect on the operation of both Parties' facilities and operations, its anticipated duration, and the necessary corrective action. 5.3.2 Routine Maintenance, Construction. and Repair. The Company may interrupt interconnection service or curtail the output of the Seller's Generation Facility Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 3 of 9 and temporarily disconnect the Generation Facility from the Company's transmission/distribution system when necessary for routine maintenance, construction, and repairs on the Company's transmission/distribution system. The Company will make a reasonable attempt to contact the Seller prior to exercising its rights to interrupt interconnection or curtail deliveries from the Seller's Facility. Seller understands that in the case of emergency circumstances, real time operations of the electrical system, and/or unplanned events, the Company may not be able to provide notice to the Seller prior to interruption, curtailment or reduction of electrical energy deliveries to the Company. The Company shall use reasonable efforts to coordinate such reduction or temporary disconnection with the Seller. 5.3.3 Scheduled Maintenance. On or before January 31 of each calendar year, Seller shall submit a written proposed maintenance schedule of significant Facility maintenance for that calendar year and the Company and Seller shall mutually agree as to the acceptability of the proposed The Parties determination as to the acceptability of the Seller's timetable maintenance will take into consideration Good Utility Practices, system requirements and the Seller's preferred schedule. Neither Party withhold acceptance of the proposed maintenance schedule. 5.3.4. extent practical, coordinate their Generation Facility maintenance schedules shall provide and maintain adequate nrr•ro.~r"''"" to the Generation Facility and Seller-furnished some of Seller's protective relays will provide facilities. In Idaho Power will test such actual cost testing. During any forced outage, the Company may suspend effect immediate repairs on the Company's The Company shall use reasonable efforts to provide is not given, the Company shall, upon request, after the fact explaining the circumstances of 5.3.6 The Company shall notify the Seller as soon Good Utility Practice, operation of the Seller's Generation Facility may cause or deterioration of service to other customers served from the same electric system, or if operating the Generation Facility could cause damage to the Company's transmission/distribution system or other affected systems. Supporting documentation used to reach the decision to disconnect shall be provided to the Seller upon request. If, after notice, the Seller fails to remedy the adverse operating effect within a reasonable time, the Company may disconnect the Generation Facility. The Company shall provide the Seller with reasonable notice of such disconnection, unless the provisions of Article 5. 3. 1 apply. 5. 3. 7 Modification of the Generation Facilitv. The Seller must receive written authorization from the Company before making any change to the Generation Facility that may have a material impact on the safety or reliability of the Company's transmission/distribution system. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Seller makes such modification without the Company's prior written authorization, the latter shall have the right to temporarily disconnect the Generation Facility. Idaho Power Company Generator Interconnection Agreement # 30:r' · I.P.U.C. No. 29. Tariff No. 101 Page 4of9 ' 5.3.8 Reconnection. The Parties shall cooperate with each other to restore the Generation Facility, Interconnection Facilities, and the Company's transmission/distribution system to their normal operating state as soon as reasonably practicable following a temporary disconnection. 5.3.9 Voltage Levels. Seller, in accordance with Good Utility Practices, shall minimize voltage fluctuations and maintain voltage levels acceptable to Idaho Power. Idaho Power may, in accordance with Good Utility Practices, upon one hundred eighty (180) days' notice to the Seller, change its nominal level by more than ten percent (10%) at the Point of Delivery, in which shall modify, at Idaho Power's expense, Seller's equipment as accommodate the modified nominal operating voltage level. 5.4 Land Rights. 5.4. 1 Seller to Provide Access. Seller hereby grants term of this Agreement all necessary rights-of-way and 0 "'''"""'.an maintain, replace, and remove Idaho Power's Metering L..l.f'''J'"'' Equipment, Disconnection Equipment, Protection Equipment and other Facilities necessary or useful to this Agreement, including adequate and continuing access rights on property of Seller. warrants that it has procured sufficient easements and rights-of-way from third as to provide Idaho Power with the access described above. All documents easements or rights-of-way shall be subject to Idaho Power's approval 5.4.2 agree that it is necessary to avoid the adverse that would occur as a result of duplicate electric Jines being in close . Therefore, subject to Idaho Power's compliance with 4, Seller agrees that should Seller seek and receive from any local, state or body the right to erect, construct and maintain Seller-furnished Facilities upon, along and over any and all public roads, streets and highways, the use by Seller of such public right-of-way subordinate to any future use by Idaho Power of such public right-of-way for and/or maintenance of electric distribution and transmission facilities and claim use of such public right-of-way for such purposes at any time. by Paragraph 5.4.4, Idaho Power shall not be required to for exercising its rights under this Paragraph 5.4. 2. Subject to Idaho Power's compliance with Power may use and attach its distribution and/or transmission Interconnection Facilities, may reconstruct Seller's Interconnection Idaho Power's usage or Idaho Power may construct its own transmission facilities along, over and above any public right-of-way Seller pursuant to Paragraph 5.4.2, attaching Seller's Interconnection Facilities to such newly constructed facilities. Except as required by Paragraph 5.4.4, Idaho Power shall not be required to compensate Seller for exercising its rights under this Paragraph 5.4.3. 5.4.4 Conditions of Use. It is the intention of the Parties that the Seller be left in substantially the same condition, both financially and electrically, as Seller existed prior to Idaho Power's exercising its rights under this Paragraph 5.4. Therefore, the Parties agree that the exercise by Idaho Power of any of the rights enumerated in Paragraphs Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 5 of 9 5.4.2 and 5.4.3 shall: (1) comply with all applicable laws, codes and Good Utility Practices, (2) equitably share the costs of installing, owning and operating jointly used facilities and rights-of-way. If the Parties are unable to agree on the method of apportioning these costs, the dispute will be submitted to the Commission for resolution and the decision of the Commission will be binding on the Parties, and (3) shall provide Seller with an interconnection to Idaho Power's system of equal capacity and durability as existed prior to Idaho Power exercising its rights under this Paragraph 5.4. 6. Assignment. Uabilitv. lndemnitv. Force majeure. Consequential Damages and Default. 6. 1 Assignment. This Agreement may be assigned (21) calendar days prior written notice and opportunity to Party upon twenty-one y the other Party; provided that: 6. 1. 1 Either Party may assign this Party to any affiliate of the assigning Party the legal authority and operational ability the consent of the other rlilrea!ter credit rating and with the assigning Party under this Agreement. 6.1.2 The Seller shall Agreement, without the consent of the Company, 1Ql~.()/181Cer-al -'~ts"~,(Jril'" purposes to in providing financing for the Generation Facility, Seller will promptly notify the Company of any such '"'-'l'l'-'"'p this article is void and ineffective. obJif!JaltielrJm~nc)r shall a Party's obligations be c::r.,., ... ""''-'"'"' is responsible for meeting ::f}~~~~~ the Seller. Where required, conditioned or delayed. liability to the other Party for any loss, cost, .C!,.,,.,~n'"" attorney's fees, relating to or arising from shall be limited to the amount of direct ·an;,,.,ar Party be liable to the other Party for any except as authorized by this Agreement. protects each Party from liability incurred to third parties as provisions of this Agreement. Liability under this provision is limitations on liability found in Article 6. 2. Parties shall at all times indemnify, defend, and hold the other Party any and all damages, losses, claims, including claims and actions to or death of any person or damage to property, demand, suits, · costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's action or failure to meet its obligations under this Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party. 6. 3. 3 If an indemnified person is entitled to indemnification under this article as a result of a claim by a third party, and the indemnifying Party fails, after notice and reasonable opportunity to proceed under this article, to assume the defense of such claim, such indemnified person may at the expense of the indemnifying Party contest, Idaho Power Company Generator Interconnection Agreement # 307 · I.P.U.C. No. 29, Tariff No. 101 Page 6 of 9 settle or consent to the entry of any judgment with respect to, or pay in full, such claim. Failure to defend is a Material Breach. 6. 3. 4 If an indemnifying party is obligated to indemnify and hold any indemnified person harmless under this article, the amount owing to the indemnified person shall be the amount of such indemnified person's actual loss, net of any insurance or other recovery. 6.3.5 Promptly after receipt by an indemnified person of any claim or notice of the commencement of any action or administrative or leg~· if!: 'f_oceeding or investigation as to which the indemnity provided for in this article mq,fA~ -Jfiy, the indemnified person shall notify the indemnifying party of such fact. Any fffj,ltf.¥f or delay in such notification shall be a Material Breach and shall not affect a P9fi~ff4/:j}f~mnification obligation unless such failure or delay is materially prejudicial to th,eft,·. · mritfiJ.n,g party . . ·~t.~ "~~f 6.4 Force Majeure. As used in this JM!I/4iment, "Forc;-~~9_ure" or "an event of Force Majeure" means any cause beyond the pi!J1t/ol of the Seller or ({f{t]JJg Company which, despite the exercise of due diligence, such..,P.'~J!_y is unable to prevent 61ft§Mercome. Force Majeure includes, but is not limited to, act~(£ God, fire, f/gQd, storms, wii~Jl/lstilities, civil strife, stri~es and other lab~r disturba~ces, eartlfil~;~kes, fi)~~~Jghtning, ~pidemuillsabota¥e, or changes m law or regulatton occumng after rK'4'f;:9[!~!:?.{!¢H Date, whtch, by the exerctse of reasonable foresight such party C?Jt..ld not reasonlfiJ!~~!Jl··~ been expected to avoid and by the exercise of due diligence,_ it sha(11/ff.tf1221e to ov~rcclf«(!z'! either Party is rendered wholly or in part unable to perform tts obltga l§lfs~cjgJ; thts AgreefiJ~J!f because of an event of Force Majeure, both Parties shall be exc1 ,.,w lfilifr#...< . ..tJJever peffefiJI.ance is affected by the event of Force Majeure, provided that: ' -~·~-·-;~}·~-/¥~. ~ /.~~f.:,_ ~/ (1) ~--~fJ!!)-~performt~EJIJ .. ~shall, '{f! ~ff0n as is reasonably possible after the occuwJf{~~f thj-;_~1ce Majet{fitf'give the othef Party written notice describing the partie~!.~~ ffli the occui{f4,pe. ~-. ·¥~ -~)J ~-:s, ':7,:?!> ·.z..,-• .r.;;&-(g.J\ __ The ~t(pjliJ~!PJ?,p_f peff9!PJ,ance shall be .of no greater scope and of no long.er du at[ptl.,~~ ~f{(Jfr.fi.tfJ!l?:;tbfl. &~nt of Force MaJeure . . ;4?~'f:/, ,_., ·.·.-@~ff.P -;!~f!Jr·,:'*--7~·i-fi.£W, KJt{Jg/igations of either Party which arose before the occurrence causing •. ;/j)fY the susp~!f_%9n of$£tJttrmance and which could and should have been fully performed ~~f-7( before sudh;,fJ,C_G,urrer(6-~~sfra11 be excused as a result of such occurrence. ~~/: {?~ ·~h v-y,~ :.. 7;@._ •·;;/}' ~id%~~. ~t ~y v,~¥:,... ~{,i; ~ //~ '?%:-~ ·•;rqt~><·· ~ ~;>!(//.'. ~:t ;?'q '·?A_-.-.., %:-if· ·-~ifjf ~-J#jf ~~-·-.~ --~~ ~!f/ . i:#'i({~;t~. ~;}#·" ·-.,~- Idaho Power Company Generator Interconnection Agreement# 307 I.P.U .. C. No. 29. Tariff No. 101 Page 7 of 9 6. 5 Default and Material Breaches. 6. 5. 1 Defaults. If either Party fails to perform any of the terms or conditions of this Agreement (a "Default" or an "Event of Default'J, the nondefaulting Party shall cause notice in writing to be given to the defaulting Party, specifying the manner in which such default occurred. If the defaulting Party shall fail to cure such Default within the sixty (60) days after service of such notice, or if the defaulting Party reasonably demonstrates to the other Party that the Default can be cured within a commercially reasonable time but not within such sixty (60) day period and then fails to diligently pursue such cure, then, the nondefaulting Party may, at its option, terminate and/or pursue its legal or equitable remedies. 6. 5. 2 Material Breaches. The notice and J;i!l~~if:}J'{.istoJ in Paragraph 6. 6. 1 do not apply to Defaults identified in this Agreernrellv ... '',;;;"'"'""',..,.,.;...,, Breaches. Material Breaches must be cured as expeditiously occurrence of the breach. 7. Insurance. During the term of this Agreement, insurance coverage: 7. 1 Comprehensive damage with limits equal to $1, for such insurance shall be property. 7.2 following for both bodily injury and property single limit. The deductible Utility practices for similar an insurance company with policy shall not be canceled or the limits of written notice to Idaho Power. ~.!.,L_~=~~::...!::.!...-=-==::......!::.:........:::=..:..:::.:..:=-If the insurance coverage shall/apse for any reason, Seller will immediately notify Idaho Power ::~nt.n~P Idaho Power of the specific reason for the lapse and the steps :.u.n:ncn.v the coverage. Failure to provide this notice and to expeditiously coverage will constitute grounds for a temporary disconnection under be a Material Breach. 8. Miscellaneous. 8. 1 Governing Law. The validity, interpretation and enforcement of this Agreement and each of its provisions shall be governed by the laws of the state of Idaho without regard to its conflicts of law principles. 8.2 Salvage. No later than sixty (60) days after the termination or expiration of this Agreement, Idaho Power will prepare and forward to Seller an estimate of the remaining value Idaho Power Company Generator Interconnection Agreement# 30-7 · I.P.U.C. No. 29. Tariff No. 101 Page 8 of 9 of those Idaho Power furnished Interconnection Facilities as required under Schedule 72 and/or described in this Agreement, less the cost of removal and transfer to Idaho Power's nearest warehouse, if the Interconnection Facilities will be removed. If Seller elects not to obtain ownership of the Interconnection Facilities but instead wishes that Idaho Power reimburse the Seller for said Facilities the Seller may invoice Idaho Power for the net salvage value as estimated by Idaho Power and Idaho Power shall pay such amount to Seller within thirty (30) days after receipt of the invoice. Seller shall have the right to offset the invoice amount against any present or future payments due Idaho Power. 9. Notices. ~3';> (~·-?j/ 4~f? 9.1 General. Unless otherwise provided in thi~~$J;}feement, any written notice, demand, or request required or authorized in connection vtlt;~jl~~_greement ("Notice") shall be deemed properly given if delivered in person, delivered#.!Jrecog6J¥:.$l/9 national currier service, or sent by first class mail, postage prepaid, to the pe~~~-n 'specified i5'eJ~W-~ P£. , /'ff.---' ----/~'Z/ •k ' •. ~ ... » ·.-.r-. '•/. J.· ; • . ~.X:1~~i . '. ~~~~~., : ~t.::-.JY . {~_pz If to the Seller: Seller: 1/1~}/ .{/,-. -~&t~-~ ~~·· ~~ . .Zj{l ~~)..;. Attention: ,.:{:iJ}f' "-~ Address: ·· '<{{y, ,.)P~7• City: __________ §tate: -:~. ·.~.~;.r-~-:,. ___ _ Phone: F~" ~/'<· ....... "~;~~~)j '?~·-If to the Company: v, ... ,_ . .,..:~(1 ••. ,. ·<ff:0~---. ~ ., .f'·· ~~·.. '• "A Idaho Power Company-Delivery '7~i-· ·---~-?~~--· Attention: Operations M~ -~er ' M~~i"tY.·., ·{;;' 1221 W. Idaho Stre~~$i.~. Vf~-~7 ·7,· Boise: Idaho 8~&>"'" "7 --~~-~F Phone: 208-3~1(; S9 Fax: 20:~;., 88-5504 '';- .,.-,}'_ ' ~JI' ;.-:; 0p)t··. -~f';f ._ . 9.2 Bil_n"! and ~!(~Em~ ;~~!lings (99: payments shall be sent to the addresses set out below: %'~?.-:..r A.' -~~R.('-. ~~ •/.;(~'{M0-,.~_· >t-~PZ~&~ .. ·,.,.w., r · 1.:-h~,~ ... q: 4'-'Zh': r~~.... :y ~h~;-:~·~~=-·t>._~{'~~rr:·~>-~.P:~~& ~~rition: -~~~-~~"- .:f.ffJP-'dress· .,1#.&~ ·-~p.., ~*~{-/,U1 • ~~ w~,( P'.ft·v: ~&~ 0fW,.,§tate: Zip: ~¥,4'~ '"/r• ~ 7 -------' ------PffQn~r <~%]" dJx· --~'~?:.--~74 . --------··i:t~ ~~~ Idaho P~~~[ Compan;f~~ eli very Attention:~~orat~d'~ ier PO Box 447~fh-~./ Salt Lake City ~~, -8411 0-044 7 Phone: 208-388-5697 email: asloan@idahopower.com 9.3 Designated Operating Representative. The Parties may also designate operating representatives to conduct the communications which may be necessary or convenient for the administration of this Agreement. This person will also serve as the point of contact with respect to operations and maintenance of the Party's facilities. Idaho. Power Company Generator Interconnection Agreement# 307 I.P.U . .C. No. 29, Tariff No. 101 Page 9 of9 Seller's Operating Representative: Seller:------------------------ Attention: -----------------------------Address: _________________________ __ City: ___________ State: ____ .Zip: ____ _ Phone: Fax: ---------- Company's Operating Representative: Idaho Power Company -Delivery Attention: Regional Outage Coordinator-Regional Dispatch 1221 W. Idaho Street Boise, Idaho 83702 Phone: 208-388-2633, 388-5125, or 388-5175 during (after hours Southern Region 208-388-5190). 9.5 10. Signatures. IN WITNESS WHEREOF, the P<:>rtic~ respective duly authorized representati For the Seller Name: Date: _____ __;:;; For the Name: Title: ~~~~~j~JB[:)E3ra1:io Idaho Power Company Generator Interconnection Agreement # 307 · I.P.U.C. No. 29. Tariff No. 101 Page 1 of 3 Attachment 1 Description and Costs of the Generation Facilitv. Interconnection Facilities and Metering Equipment In this attachment the Generation Facility and Interconnection Facilities, including Special Facilities and upgrades, are itemized and identified as being owned by the Seller or the Company. As provided in Schedule 72, Pavment For Interconnection Facilities, the Company will provide a best estimate itemized cost of its Interconnection Facilities, including Special Facilities, upgrades and Metering Equipment. 6 General Facility Description .. ~.IJII The proposed project will connect to Idaho Power's 12.5kV system o -~ ~aho Power Company's Clover (CLVR-012) distribution line. The total project output is 1.2 MW. ~,~~~1~:("" /##~ ~~ Interconnection P9Jp! .. t'r ·-~-· .. The Interconnection Point for the Swager Farms Dairy Di~~t ('Project will be' t~jqw-side bushings on the padmounted transformer (SW1). The project's lo~ ~~~-··ts in T10S R15E Sfi~_2p,21 of Twin Falls County, Idaho. A dra~ing .identifying the_ Point of.ln~~{~-~ection is included as Attao~m,~nt 2. The Point of Change of Ownership Will be the low-stde bushmggJpj._,Jhe padmOL!P!~d transformer (SW~:). ~:f.»·. P;#?' . _,. 'Y ~--~ .. y,~ J~"1,-W2J" " ,, /~y. :z 0':..o:7*·. Seller's lnterconnectrog~~~jpes The Seller will install generators, low-sp~ disconnect s~~,b:J.''~ all wiring and conduit between the generators and the padmounted tran~t6J~! . appropriat~to!Jnding measures, and associated auxiliary equipment. The Seller will build ff'~~~fg~jl}J,Q. facilities ~h~. Point of Change of Ownership for the generator facility. The low-side discon~~ swff~.tJ,~ !d be vt~1~~-lockable, within ten (10) feet of the padmounted transformers, and accessibl~; Idaho ,!?', '"~r-Hxrsori'n~!~· .v·~; ~ .## ;,fW?f~X.~7.; ' . /4,0-l>t%;: -~ /.Xl ~-/./}.),;&~ .. , The Seller ~ill provide p}:199B-.z-se.~J9r to IPcr~~. · erator tr1f~ \Connect package as described in Telecommumcattons beJe~·' ,.J(0." ·:.?f%1? .. ~.';)· ;_/ :~~ -~ All interconnection ~:~.fpment eles_t-#lly locate~:?n the generator side of the Point of Change Ownership shall be owne~;~pd m~JW~Aest~X)J:!.~ Sell~f~ ·-~:.'-'· .... ~:r-.w-,: .. ~,.u'.:¥~,. ,, ~r- . ..;f#/i/l}!/.t.·. '7~.dther FacilitiErfi'~~ided by Seller Teleco9J!IJ.(fnica·tifins~ .;,-·... ·~>, The /lp~efeonnection Cl.t.~t~mer 'Wf;provide two communication circuits between the generation inter'Ctt9p~ction site and al'if§~~ion, 'oWJ.~~~tions, specified by Idaho Power. One of the circuits will be a dedicate9-~twire leased anatgJ;jdicircuit ·c.gJ1·nected to the SEL 311C relay and the other will be a POTS dial-up cif~~i~Jo the revenue ·~'m~ter. The Interconnection Customer is responsible for supplying and coordinating"'Jti~--installation 9}1fhe phone lines and paying the monthly service charges. The communication ~re,uits will n~~d;fo be installed and operational prior to generating into the Idaho Power Y.~ X~ /i'" ··z system. · .. -,;~;_,~ ,y~P· · //'/ ·">"/ ·z{:t~_fj~·r.;;· Ground Fault Equiprrie~ The Seller will install ground fault limiting equipment that will limit the zero sequence fault current to 20 amps at the Interconnection Point. Monitoring Information If the Interconnection Customer requires the ability to monitor information related to the Idaho Power recloser in the generation interconnection package they are required to supply their own communications circuit to the control box. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 2 of 3 Easements The Seller will secure underground and overhead easements with Swager Farms Dairy once a specific route is determined. Idaho Power will provide the documentation. Idaho Power Company's Interconnection Facilities Idaho Power will install a standard generation interconnection package on the existing distribution feeder (CLVR-012) on private property southwest of the intersection of 3800 North and 1700 East in Twin Falls County, I D. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering recloser, relays, fuses and riser necessary for the package. The interconnection will be ed by a SEL-311 C line protection relay. The relay will be located in a pole mounted e and will also contain a test switch (TS4), SLSS, modems, isolation interface, power supply, , control switch and surge protector. Idaho Power will install (and subsequently own and Grounded Wye I Grounded Wye padmounted ~nc:rnr·m-=•rmw cables will be installed from the interconnection "'""'~.,.,,.,.. will be installed to protect the ground mounted equ•o!in'ftsl!i"t A 2" conduit will be installed alongside the undergrou customer about the recloser. (The I ection vu•::nu• the appropriate cable). All interconnection equipment electrically 1\;,lyj::I,Lo::.•u 1:11~~ shall be owned, operated, and maintained "" and underground Jr,.,.to:>r•t•"""' posts J~);'~ ... litate information exchange to the ponsible for providing and installing the Point of Change Ownership accordance with Section 9, unless payment arrangements are IJ.C\(A'/'or Delivery Finance. will be based upon actual expenditures. Billing and Payment during Construction Transmission Provider will prepare monthly invoices for services performed in accordance with this Agreement and deliver the invoices to Seller. Seller will transmit payment to Transmission Provider no later than 30 days after receiving the invoice. In the event any monthly payment is missed, Idaho Power Company may revoke the unsecured nature of the construction funding and will require security for the remaining funds. In the event of payment default construction will cease until remediation is made by the Seller. Idaho Power Company Generator Interconnection Agreement# 30V ,. I.P.U.C. No. 29. Tariff No. 101 Page 3 of 3 Invoices are to be addressed to Seller as follows: In the event of a billing dispute, Seller must pay invoices when due subject to refund (without interest). lnvoice·s must be accompanied by appropriate supporting documentation and proof ·of expenditures as applicable. Idaho .Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 2 One-line Diagram Depicting the Small Generation Facility, Interconnection Facilities, Metering Equipment and Upgrades Idaho Power Company I.P.U.C. No. 29. Tariff No. 101 Milestones: Agreed to by: For the Seller: For the Transmission Provider Idaho Power Company, Delivery Generator Interconnection Agreement # 307 ' Page 1 of 1 Attachment 3 Idaho Power Company Generator Interconnection Agreement# 307 I.P.U ~C. No. 29, Tariff No. 101 Page 1 of 2 Attachment 4 Additional Operating Requirements for the Company's Transmission System and Affected Systems Needed to Support the Seller's Needs The Company shall also provide requirements that must be met by the Seller prior to initiating parallel operation with the Company's Transmission System. Operating Requirements The project is required to comply with the applicable Voltage and Cu IEEE Standard 519-1992 IEEE Recommended Practices and Electrical Power Systems or any subsequent standards as they Seller will be able to modify power plant facilities on the Qelner·at¢1Jt$rde no impact upon the operation of the transmission electrically isolated from the transmission system and a t.:>rt"Wrr.,., Company's Grid Operator. Voltage flicker at startup and during operation Interconnection Point. For this to occur, the current ca.t110.Qt kV voltage level. This forces the generating facility to Low Voltage Ride Through stortion Limits found in for Harmonic Control in "''"'"''.'"'""from time to time. nterconnection Point with or<:a1ftnn facilities are by Idaho Power "<M'~~<::ac:• red at the ... t..,w.'t'i .... at the 12.5 The Project shall remain interconnected ground fault down to a voltage of zero at arro:n,.o ONa~tnre~e phase or single phase to t;)n••uo·,,..,;q (C,,,.,torn as close to the Seller's facilities as Idaho Powe .• r~~~~~n~y1's C minimum times stated belq • Three phase • Single phase Ground Fault a... .... u.a."'' The Seller will system. fault being cleared for the mmercial Operation date only when all requirements have r Company's Power Sales Agreement. A transmission has been submitted to Idaho Power Company's Grid Idaho Power Company Generator Interconnection Agreement # 307 · I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 5 Reactive Power Requirements Idaho Power will determine the reactive power required to be supplied by the Company to the Seller, based upon information provided by the Seller. The Company will specify the equipment required on the Company's system to meet the Facility's reactive power requirements. These specifications will include but not be limited to equipment specifications, equipment location, Company­ provi:Jed eq~ipment, Seller provided .equipme~t, and all costs ~ssocia~~!fi.th ~he equipment: design and mstallat1on of the Company-provided eqwpment. The eqwpment s e~f1cat1ons and reqwrements will become an integral part of this Agreement. The Company-own.,J?PJ'{(uipment will be maintained by the Company, with total cost of purchase, installation, opefJiff&#tl't~ d maintenance, including administrative cost to be reimbursed to the Company by the sfi{J.~'P/ PaPf((fM~j of these costs will be in accordance with Schedule 72 and the total reactive power g~~t i$it be incllfO~f:l~· ·n the calculation of the Monthly Operation and Maintenance Charges specified in .jJ}ffdule 72. 0t;:j~1'.,. ::~rp· -~~·~ The project must be controlled to operate at unity pq~wl~Jfii~tor. ·;'¥(< .. }~~.w ' ~-·XX;. ~~~-~'l,/; <~ ·~;t, --~,, /4:-J::/, .·. -~-r ·~~~t-~." (~Pf' :• ··~X:f•"·' ~1?-.~-. '':1$~. --9[:,;» ;-~;.. "/i#: .' • ·~1 ~ • ·;Jt,j·/. ~~ .. ;~; . . -~-<6~o --ky." "~-"-:$-z;:.. -~ii(ri:<, .Z:~-'-h~j; ~-., "~ "''~~~#.;h.,... ·.;?,;:-$, ·~ ~~~~ 4-~~:>f-.•,. •N ',.:1-1J.~p,. ~ -~~ m.<~ ~ t#~ / ./,~f.,-?~~1%-?'~//.'-. ·.:·~ :twr ~ • e; 11?4~,-· ~"'--~ 4• .*'/ Jr. r ':?f.Jf-;._ ''/.1-!2• .x~~ '7::/ ':1'/4':-:·· "!i:.r~ ·~·(.~;· ., :;,;> ~~," ",,:.,,;·= ,i·~g ,.. , r~. ·v.0 ~-< ;;,r,wt~ d!i· .-:/··· '-'g/~ ;:~-*·· .·:#,)f_p,.· x~~!1J-#2.~.;" ~.? •Y')?• · ~,Wy-. vp*~ /.' ~~~~~.;. ·~~.; ' ~-;£%%;'; . ~~fi(.f',&' , ~ .·, ·I' "A ' · ·, ~·.;{:-·~-~" .;:~·%-'-'h' .... -:·.! .• i.! ~·_.., /, . '.1(.-~- / .. ·.~ .-~{;. .. ~ .. ; .. ,7 •• ,"'.~-. ~:..?:-;;.-;.. ,,., ;y.--;: •r ''',(,·::·?~ ~ . ;:.· :;,:._·,_y._ ... :·~~-'*~z---"-~~' V.'-.?:::;.~ -r~'Y~:~ ~~-·~7tf.·. ··~!.f«-?. ''W-% ~i..~~'~ ~-{/ :;z_,y· .. '"?_).:''>, wr~~ ~~ ~~ ".t;;1 ~: ·~[:;)~;. '/.;.>:<. //' 'l::~:~:-, .,~ .. y -'; ·.:;I;·. ;rg_:.;, ./i -12 J/).!A:' ~ ... ~:~ /.( ~.f:,Y¢" ., ;?,/;.-~?if ·:;?~:f/' lda)lQ.Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 6 Company's Description of Special Facilities and Upgrades Required to Integrate the Generation Facility and Best Estimate of Costs As provided in Schedule 72 this Attachment describes Upgrades, Special Facilities, including Network Upgrades, and provides an itemized best estimate of the cost of the required facilities. Upgrades Distribution Upgrades Idaho Power will install a new capacitor bank on the existing d the existing Clover Substation. BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 27 Bishop, Rowena Hackett, Eric "=rom: ;ent: To: Monday, January 03, 2011 9:53AM Laura Knothe Cc: Bishop, Rowena Subject: RE: Gl 307 & 308 -Swager Farms and Double B Dairy Great to hear from you Laura. As you can see if the FSR for both, it is approximately 6 months from the time we receive construction funding to the time we can have the project in-service on our end. We are still in good shape for meeting a late summer or early fall date. However, as you mentioned, the sooner funding is received and I can order materials and get the designers going on final design the better. I would anticipate material orders being placed within a couple weeks of payment and design to start a month or so after that based on current workload and resource availability. I think payment in the next 4-6 weeks would be best so we can schedule construction resources as well for this summer. Thanks again. Eric Hackett, P.E. Project Leader Idaho Power Company PO Box 70, 83707 1221 West Idaho St. Boise, ID 83 702 Office Phone: (208) 388-5712 Cell Phone: (208) 283-2720 rom: Laura Knothe [mailto:laura@thenewenergycompany.coml Sent: Monday, January 03, 2011 9:43 AM To: Hackett, Eric Cc: Bishop, Rowena Subject: GI 307 & 308 -Swager Farms and Double B Dairy Good morning Eric and Happy New Year! I just wanted to check in with you regarding the above referenced projects. We have an investor on board and will proceed with the GIA in the next week or so. We have several meetings this week, so I should know more by the end of the week. How is your work load at this point? We are looking at construction this spring/summer and an operation date in September or October. I'm sure we need to get this proceeding right away. Please advise! Thank you. Laura Knothe, PE, LEED AP The New Energy Company www.thenewenergycompany.com 208.890.8783 1 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 28 SMALL GENERA TOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: Rowena Bishop 1221 W. Idaho Street, Boise ID 83702 208-388-2658 208-388-6647 rbishop@idahopower.com An Interconnection Request is considered complete when it provides all applicable and correct information required below. Preamble and Instructions An Interconnection Customers who request interconnection must submit this Interconnection Request by hand delivery, mail, e-mail, or fax to the Transmission Provider. Processing Fee or Deposit: If the Interconnection Request passes ALL screens of SGIP Section 2.2.1, the application may be submitted under the Fast Track Process, and the non-refundable processing fee is $500. Please contact Idaho Power if you have any questions. All Interconnection Requsts submitted under the Study Process, whether a new submission or an Interconnection Request that did not pass the Fast Track Process, shall submit to the Transmission Provider a deposit not to exceed $1,000 towards the cost of the feasibility study. Interconnection Customer Information Legal Name of the Interconnection Customer (or, if an individual, individual's name) Name: New Energy Two, LLC Contact Person: Laura Knothe PE Mailing Address: ;,:..87-'-'2=0"------'-V-"'ic"'--"=L"""an""e"'---------------------------- City: Middleton State: ..,ID"'-------Zip: 83644 Facility Location (if different from above):----------------------- Telephone (Day): _ _;2=0"'"'8.=8-'<--90,_,."'"'87-'-'8!..:!.3'--------Telephone {Evening): ---=20"-"'8=.5=8"'-'5 . .:<_;90"-'IC.><6 __ _ Fax: ---'=2""0""'8'"".5'""'8""5"'"".9'""0'""1~6 _______ E-Mail Address: laura@thenewenergycompany.com SWAGER FARMS PROJECT Al ternative Contact lnfonnation (if different from the lnterconnection Customer) NA ContactNrune: ____________________________________________________________ __ Title: --------------------------------------------------------------------- Addr~s: ______________________________________________________________ __ Telephone (Day): ______________ Telephone (Evening): ---------------- Fax: E-Mail Address: ------------------------------------------------------- Application is for: ___ New Small Generating Facility --'-x"--Capacity addition to Existing Small Generating Facility If capacity addition to existing facility, please describe: Project has completed Facility Study and Draft GIA, but no pbysical work has been completed-Project Number 307. This application is for an additional800kW to bring the total request to 2000kW. The values below indicate the total project capacity and not the additional capacity for this specific request. Will the Small Generating Facility be used for any of the following? To Supply Power to the Interconnection Customer? Yes _No _x_ To Supply Power to Others? Yes __ No _x __ _ For installations at locations with existing electric service to which the proposed Small Generating Facility will interconnect, provide: (Local Electric Service Provider*) (Existing Account Number*) [*To be provided by the Interconnection Customer if the local electric service provider is different from the Transmission Provider] Contact Name: -------------------------------------------------------------- Title: ------------------------------------------------------------------ Address: ------------------------------------------------------------------ Telephone (Day): ________________ Telephone (Evening): ---------- Fax: -----------------------------------E-Mail Address: --------------------- Requested Point of Interconnection: See previous studies -Project Number 307 Interconnection Customer's Requested In-Service Date: :::8-'<Jep~t~em~b""'"et""""· 2:.:0""1""1'---------------------- SWAGER FARMS PROJECT Small Generating Facility Information Data apply only to the Small Generating Facility, not the Interconnection Facilities. Energy Source:_ Solar _Wind _Hydro _Hydro Type (e.g. Run-of-River): _____ _ _ Diesel _Natural Gas _Fuel Oil _x_ Other (state type) methane gas Prime Mover: _Fuel Cell _!l._Recip Engine _Gas Turb _Microturbine _PV Type of Generator: _x_Synchronous __ Induction Inverter _Steam Turb _Other Generator Nameplate Rating: up to2000 kW (Typical) Generator Nameplate kV AR: ___!ill to 1500 Interconnection Customer or Customer-Site Load: ___ n=o=n=e _____ --'kW (if none, so state) Typical Reactive Load (if known): _______ _ Maximum Physical Export Capability Requested: 2000 kW (total for both applications; 800kW Additional for this application) List components of the Small Generating Facility equipment package that are currently certified: Equipment Type Certifying Entity l. ----------------- 2. ----------------- 3. ----------------- 4. --------------- 5. ------------------ Is the prime mover compatible with the certified protective relay package? Yes No Generator (or solar collector) Manufacturer, Model Name & Number: MWM TCG 2016 V16 C-800kW Version Number: ________ ,, _______________________ _ Nameplate Output Power Rating in kW: (Summer) ---=2=-00=0=--------, (Winter) ----=2=0=00"------ Nameplate Output Power Rating in kVA: (Summer) __ _.::2.::..50=0'------(Winter) --"""2~50 __ 0=----- Individual Generator Power Factor Rated Power Factor: Leading: _______ Lagging: _,.""'"8 _____ _ Total Number of Generators in wind farm to be interconnected pursuant to this Interconnection Request: Elevation: __ Single phase _Three phase Inverter Manufacturer, Model Name & Number (if used):---------------- List of adjustable set points for the protective equipment or software:------------- Note: A completed Power Systems Load Flow data sheet must be supplied with the Interconnection Request. SWAGER FARMS PROJECT Small Generating Facility Characteristic Data (for inverter-based machines) Max design fault contribution current: Instantaneous orRMS? Harmonics Characteristics: ------------------------- Start-up requirements:--------------------------- Small Generating Facility Characteristic Data (for rotating machines) RPM Frequency: _____ _ (*)Neutral Grounding Resistor (If Applicable): ____ _ Synchronous Generators: Direct Axis Synchronous Reactance, Xd: ___ P.U. Direct Axis Transient Reactance, X'd: P.U. Direct Axis Subtransient Reactance, X" d: --------'P.U. Negative Sequence Reactance, X2: _, ____ P.U. Zero Sequence Reactance, X0: P.U. KVA Base:----------- Field Volts: ------Field Amperes: _____ _ Induction Generators: NA Motoring Power (kW): _____ _ i2 2t or K (Heating Time Constant): _____ _ Rotor Resistance, Rr: _____ _ Stator Resistance, Rs: _____ _ Stator Reactance, Xs: _____ _ Rotor Reactance, Xr: _____ _ Magnetizing Reactance, Xm: _____ _ Short Circuit Reactance, Xd": _____ _ Exciting Current: _____ _ Temperature Rise: _____ _ Frame Size: Design Letter: _____ _ Reactive Power Required In Vars (No Load): _____ _ Reactive Power Required In Vars (Full Load): _____ _ Total Rotating Inertia, H: Per Unit on kV A Base Note: Please contact the Transn1ission Provider plior to submitting the Interconnection Request to determine if the specified information above is required. SWAGER FARMS PROJECT ExcitatiQn and Governor System Data for Synchronous Generators Only Provide appropriate IEEE model block diagram of excitation system, governor system and power system stabilizer (PSS) in accordance with the regional reliability council criteria. A PSS may be determined to be required by applicable studies. A copy of the manufacturer's block diagram may not be substituted. Interconnection Facilities Information Will a transformer be used between the generator and the point of common coupling? _x_Yes _No Will the transformer be provided by the Interconnection Customer? __ Yes _x_No Transfonner Data (If Appllcable, for lnterconneorion Customer-Owned Transfonner): Is the trans former: __ single phase __ three phase? Size: kVA -----' Transformer Impedance: %on kV A Base If Three Phase: Transformer Primary: __ Volts __ Delta ___ Wye __ Wye Grounded Transformer Secondary: __ Volts __ Delta __ Wye __ Wye Grounded Transfonner Tertiary: __ Volts __ Delta __ Wye __ Wye Grounded Transformer Fuse Data (If Applicable, for Interconnection Customer-Owned Furu:, (Attach copy offuse manufacturer's Minimum Melt and Total Clearing Time-Current Curves) Manufacturer; --------Type: _______ Size: ____ Speed: _____ _ Interconnecting Circuit Breaker (if applicable): Manufacturer: ---,-------:------:-----:--::--:-Type:-=----- Load Rating (Amps): Interrupting Rating (Amps): Trip Speed (Cycles): ___ _ Interconnection Protective Relays Qf Applicable): If Microprocessor-Controlled: List of Functions and Adjustable Setpoints for the protective equipment or software: Setpoint Function Minimum Maximum l. 2. 3. 4. 5. 6. SWAGER FARMS PROJECT If Discrete Components: (Enclose Copy of any Proposed Time~Overcurrent Coordination Curves) Manufacturer: Type: Style/Catalog No.: Proposed Setting: Manufacturer: Type: Style/Catalog No.: Proposed Setting: Manufacturer: Type: Style/Catalog No.: Proposed Setting: Manufacturer: Type: Style/Catalog No.: Proposed Setting: Manufacturer: Type: Style/Catalog No.: Proposed Setting: Current Transfonner Data (If Applicable): (Enclose Copy of Manufacturer's Excitation and Ratio Correction Curves) Manufacturer: ---------------------------------------Type: ------------Accuracy Class: __ Proposed Ratio Connection: __ Manufacturer:-------------------------------- Type: ---------Accuracy Class: __ Proposed Ratio Connection: __ Potential Transfonner Data (If Applicable): Manufacturer: ------------------------------ Type: _______ Accuracy Class: __ Proposed Ratio Connection: __ Manufacturer: --------------------------Type: _______ Accuracy Class: __ Proposed Ratio Connection: __ SWAGER FARMS PROJECT General Information Enclose copy of site electrical one-line diagram showing the configuration of all Small Generating Facility equipment, current and potential circuits, and protection and control schemes. This one-line diagram must be signed and stamped by a licensed Professional Engineer if the Small Generating Facility is larger than 50 kW. Is One-Line Diagram Enclosed? _X_ Yes __ No Enclose copy of any site documentation that indicates the precise physical location of the proposed Small Generating Facility~. USGS topographic map or other diagram or documentation). See earlier applications. Proposed location of protective interface equipment on property (include address if different from the Interconnection Customer's address) 1707 E 3800 N Buhl ID 83316 Enclose copy of any site documentation that describes and details the operation of the protection and control schemes. Is Available Documentation Enclosed? _Yes __ No Enclose copies of schematic drawings for all protection and control circuits, relay current circuits, relay potential circuits, and alann/monitoring circuits (if applicable). Are Schematic Drawings Enclosed? _Yes __ No Applicant Signature I hereby certify that, to the best of my knowledge, all the information provided in this Interconnection Request is true and correct. For Interconnection Customer: ~~.;::d. J/ .· --c.::'.:.tf.b:..,....:~r->"' ....... _.~-···· 'ON --\ ~ Signed i _______________ Date: 1112/11 Printed Laura Knothe SWAGER FARMS PROJECT DATE: 01/11111 J08 ... -a. SCALE NTS 'f' ..-TRANSFORMER PAD 400KW 800KW 800KW GENERATOR GENERATOR GENERATOR + + ~ ~ ~ I A. ~ 2500KVA 1 BY I I r "Y -.,, f..I,.XFMR I UTILITY L--_____ __] ~-----I -----I -----~-----~ : ) : ) : ) : ) 3000A : I l I 1 I 1 I 1 JP I I : _l3000A BUS, 480V, 3Ql,_l3W : : L_____ -----_____ __L _____ _j *PARALLELING GEAR •PARALLELING GEAR SKE-1 SKETCH NO. REF.SHTS:· SWAGGER ONE-LINE DIAGRAM s J.::IC ~.E~~If r-.J..E .ER[ J'Y.Q W 440 E:a'sl CorporalS Dr .• Ste. 103 Meridian ID 83642 ph 208-288-2181 lax 208-288-2182 pro)ott 00000 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 29 January 2 0, 20 11 via email and An IDACORP Company Certified Mail# 70060810000655113157 Law-a Knothe 8720 Vic Lane Middleton, ID 83694 Re: Expansion Projects# 364 (Swager Fanns) and# 365 (Double B) Dear Laura: Thank you for your Generator Interconnection applications for the expansion ·projects shown above (see attached copy). Since we have.xeceived all of the req\iit:c:l'd materials, these applications are now consi4ered com,plete" As you may be aware, we are required to post certain information to our OASIS (Open Access Same Time Information) website. Please refer to the website periodically to view a list ·of currt!!lt pr.ojeGtS at http://www.oatioasis.corniiPCO/:index.html under GENERATOR INTERCONNECTION INFORMA TIONJolder, on the left side of the screen. Sinqe y<>u will be selli11g the project output to Idaho Power Company..:Power Supply (as .a Network Resource-NR, or as a-PURPA), transmission studies for moving this energy to -~he ioad or a poi11t of deHvezy Inside of our systettJ.: will be included in the. Generator Interconnection studies. If you haven't already done so, please contact Randy Allphin for your Power Sales contrac~ un.der a parallel process. He can he reached at 208;.388~2614. At this time, Id'aho Power Company wifl as~ign a plan,ning ,engineer (ot; this project, and we will .contilQt you it:t the • near :futur:e to schedule a-Scoping Meetiilg~ If your project passes screening for the FAST TRACK process, which means your project output •can he acconunodated into our system withoutfacilityupgrades or further·studies,.we will immediately notify you of next steps to proceed. For yow review; I am attaching a copy of die stan,dard fntercoimection Feasibility Study Agreement that :Qeeds to be executed by you soon after our Scoping Meeting; Please feel free to c.ontact me with yo.ur questions· about the Generator Interconnection Process anytime, I will forward this application to our T&D Planning Leader, Marc Patterson, who will he evaluating your request Sincerely, R."'. Rowena Bishop Ph 208-388-2658 Encl Application Idaho Power Company's Facility Connection Requirements Standard Interconnection Feasibility Study Agreement Cc (via email): Marc Patterson/IPC Randy Allphin/IPC BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 30 Small Generator Feasibility Study Agree~~pt 5ata.§M &1ms Project # 36'1 Feasibility Study Agreement THIS AGREEMENT is made and entered into this Z. day of f::'ebr ucr--; 2011, by and between he.. J\)e._.tJ Ene r ' /1"-c t"t.fi..C L-L a Lz_C. --------------------------organized and existing und r the laws o State of --=-'-~d=a.:!:...L.:::..""-=--------------' ("Interconnection Customer,") and Idaho Power Company a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by Interconnection Customer on January 14, 2011; also known as Project# 31P'i; and WHEREAS, Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; and WHEREAS, Interconnection Customer has requested the Transmission Provider to perform a feasibility study to assess the feasibility of interconnecting the proposed Small Generating Facility with the Transmission Provider's Transmission System, and of any Affected Systems; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause to be performed an interconnection feasibility study consistent the standard Small Generator Interconnection Procedures in accordance with the Open Access Transmission Tariff. 3.0 The scope of the feasibility study shall be subject to the assumptions set forth m Attachment A to this Agreement. 4.0 The feasibility study shall be based on the technical information provided by the Interconnection Customer in the Interconnection Request, as may be modified as the result of the scoping meeting. The Transmission Provider reserves the right to request additional technical information from the Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the feasibility study and as designated in accordance with the standard Small Generator Small Generator Feasibility Study Agreement .5 w c!PjtYf Fa.,r~s Project# S--&'1' ' Interconnection Procedures. If the Interconnection Customer modifies its Interconnection Request, the time to complete the feasibility study may be extended by agreement of the Parties. · 5.0 In performing the study, the Transmission Provider shall rely, to the extent reasonably practicable, on existing studies of recent vintage. The Interconnection Customer shall not be charged for such existing studies; however, the Interconnection Customer shall be responsible for charges associated with any new study or modifications to existing studies that are reasonably necessary to perform the feasibility study. 6.0 The feasibility study report shall provide the following analyses for the purpose of identifying any potential adverse system impacts that would result from the interconnection of the Small Generating Facility as proposed: 6.1 Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; 6.2 Initial identification of any thermal overload or voltage limit violations resulting from the interconnection; 6.3 Initial review of grounding requirements and electric system protection; and 6.4 Description and non-bonding estimated cost of facilities required to interconnect the proposed Small Generating Facility and to address the identified short circuit and power flow issues. 7.0 The feasibility study shall model the impact of the Small Generating Facility regardless of purpose in order to avoid the further expense and interruption of operation for reexamination of feasibility and impacts if the Interconnection Customer later changes the purpose for which the Small Generating Facility is being installed. 8.0 The study shall include the feasibility of any interconnection at a proposed project site where there could be multiple potential Points of Interconnection, as requested by the Interconnection Customer and at the Interconnection Customer's cost. 9.0 In lieu of Feasibility Study deposit, Interconnection Customer agrees that study funds will be drawn from the application fee for the perfonnance of the Interconnection Feasibility Study. Transmission Provider shall charge and Interconnection Customer shall pay the actual costs of the Interconnection Feasibility Study. Any difference between the deposit and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate. Small Generator Feasibility Study Agreement S '-"'tJt]u r-a.rrv~ s Project# 3?1 10.0 Once the feasibility study is completed, a feasibility study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the feasibility study must be completed and the feasibility study report transmitted within 30 business days of the Interconnection Customer's agreement to conduct a feasibility study. 11.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 12.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company-Delivery lh-L :D.u.0 fn.~~ Cb ) LL<!. Signed:4~- Printed: Marc Patterson Printed: la..u._ v-a_ ~ V'\ofu Title: Engineering Leader, T &D Planning Title: 4CL.WL~ ,IYu? 1'-lwkv-~ ~ ~ J':l. I 70 t I LL! Date: -z ( 2 I '2o I ( Date: Small Generator Feasibility Study Agreement S w~"je.-f nrm .s Project# '3-(p'/ Attachment A to Feasibility Study Agreement Assumptions Used in Conducting the Feasibility Study The feasibility study will be based upon the information set forth in the Interconnection Request and agreed upon in the scoping meeting held on Fe k:> ·z., zo t I 1) Designation ofPoint of Interconnection and configuration to be studied. C.l oveK /2 1'2,51:V 2) Designation of alternative Points of Interconnection and configuration. 1) and 2) are to be completed by the Interconnection Customer. Other assumptions (listed below) are to be provided by the Interconnection Customer and the Transmission Provider. Page 1 of 1 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 31 BH GENERATOR INTERCONNECTION FEASIBILITY STUDY For integration of the proposed SWAGER FARMS DIGESTER EXPANSION PROJECT In TWIN FALLS COUNTY, IDAHO To the IDAHO POWER COMPANY ELECTRICAL SYSTEM For NEW ENERGY TWO, LLC The INTERCONNECTION CUSTOMER DRAFT REPORT MARCH 16, 2011 Generator Interconnection Feasibility Study General Interconnection Information Station or Date of Total Trans Line Queue Request Location (MW) for POl 12.5 kV through Clover Twin Falls (COVR) #364 January 2011 County 2.0 substation Short Circuit Analysis Results System Changes Required: DYes 0No Power Flow Analysis Results System Changes Required: ~Yes 0No Projected In-Service Date September 2011 Type of facility (combined cycle, base load, CT, fuel type) Biogas System upgrades are required to the Idaho Power substation and to the existing distribution system to interconnect the 2 MW dairy digester generation project at Swager Farms. These upgrades are shown in the Table 1 below: Description Estimated Cost 4 total miles of distribution line upgrades $529,000 Substation upgrades to Clover Substation including new 7 MV A 46:12.5 kV transformer, associated bus reconfiguration and SCADA upgrades. $959,000 Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs, and communications $225,000 Total Estimated Cost $1,713,000 Table 1: Estimated interconnection costs for 2 MW project at Swager Farms Idaho Power recently updated its operating requirements for generators interconnecting to the distribution system. Because of these new requirements, there are upgrades required to the existing IPC distribution system to interconnect the 1.2 MW generator project at Swager Farms. These estimates are shown in Table 2 below. Description Estimated Cost Distribution line upgrades (2.5 miles total) $350,000 Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs, and communications $225,000 Total Estimated Cost $575 000 Table 2: Estimated interconnection costs for 1.2 MW project at Swager Farms -1 - / . . I Good Faith Cost Estimate Interconnection cost estimate for 2 MW generator project: $1,713,000. Interconnection cost estimate for 1.2 MW generator project: $575,000. System Impact Study Required? DYes ~ No This Feasibility Study only addresses the work required to interconnect the Swager Farms digester projects to the Idaho Power system. There are no transmission rights secured for the project until a transmission system request is submitted by the corresponding transmission customer. The required transmission facilities, if any, to support energy transfers will then be determined based on first come first serve basis (queue order). Operating Requirements: Project #364 will be controlled to operate at unity power factor with an operating bandwidth of± 300 kVAR. -2- BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 32 BH GENERATOR INTERCONNECTION FEASIBILITY STUDY For integration of the proposed SWAGER FARMS DIGESTER EXPANSION PROJECT In TWIN FALLS COUNTY, IDAHO To the IDAHO POWER COMPANY ELECTRICAL SYSTEM For NEW ENERGY TWO, LLC The INTERCONNECTION CUSTOMER FINAL REPORT APRIL 26,2011 Generator Interconnection Feasibility Study General Interconnection Information Station or Date of Total Trans Line Queue Request Location (MW) for POl 12.5 kV through Clover Twin Falls (COVR) #364 January 2011 County 2.0 substation Short Circuit Analysis Results System Changes Required: DYes ~No Power Flow Analysis Results System Changes Required: ~Yes 0No Projected In-Service Date September 2011 Type of facility (combined cycle, base load, CT, fuel type) Biogas System upgrades are required to the Idaho Power substation and to the existing distribution system to interconnect the 2 MW dairy digester generation project at Swager Farms. These upgrades are shown in the Table I below: Description Estimated Cost 4 total miles of distribution line upgrades $529,000 Substation upgrades to Clover Substation including new 7 MV A 46:12.5 kV transformer, associated bus reconfiguration and SCADA upgrades. $959,000 Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs, and communications $225,000 Total Estimated Cost $1,713,000 Table 1: Estimated interconnection costs for 2 MW project at Swager Farms Idaho Power recently updated its operating requirements for generators interconnecting to the distribution system. Because of these new requirements, there are upgrades required to the existing IPC distribution system to interconnect the 1.2 MW generator project at Swager Farms. These estimates are shown in Table 2 below. Description Estimated Cost Distribution line upgrades (2.5 miles total) $350~_000 Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs, and communications $225,000 Total Estimated Cost $575,000 Table 2: Estimated interconnection costs for 1.2 MW project at Swager Farms -I - I (· Good Faith Cost Estimate Interconnection cost estimate for 2 MW generator project: $1,713,000. Interconnection cost estimate for 1.2 MW generator project: $575,000. System Impact Study Required? DYes ~ No This Feasibility Study only addresses the work required to interconnect the Swager Farms digester projects to the Idaho Power system. There are no transmission rights secured for the project until a transmission system request is submitted by the corresponding transmission customer. The required transmission facilities, if any, to support energy transfers will then be determined based on first come first serve basis (queue order). Operating Requirements: Project #364 will be controlled to operate at unity power factor with an operating bandwidth of± 300 kVAR. -2 - , BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 33 April 27, 2011 Certified Mail #70092820000284567176 Laura Knothe 8720 Vic Lane Middleton, ID 83694 RE: Swager Farms expansion (GI 364) and Double B expansion (GI 365) Dear Laura: Enclosed is the Final Feasibility Study Report for each of the above-referenced projects. The feasibility analysis indicates that modification/addition of some facilities will not be required to integrate the network resource capacity addition of your project into the Idaho Power system. Since no System Impact Study is required, I have enclosed two (2) copies of the Facility Study Agreement (FSA) for each project. In order to proceed, Idaho Power must receive your agreement to proceed with the project(s) by executing both copies of the FSA and submitting completed Attachments, along with the deposit in order to remain in the Generator Interconnection queue. The deposit under each FSA is based on the estimated engineering costs. For GI 364-Swager Farms, the deposit is $30,000; For GI 365-Double B Dairy, the deposit is $18,800.00. In order for your application to remain in the Generator Interconnection study queue, Idaho Power must receive all ofthese items by June 9, 2011; otherwise the application will be deemed withdrawn: 1. the executed Facility Study Agreement, 2. the completed Attachment A, and 3. the corresponding deposit. Please submit to: Idaho Power Company, Attention: Rowena Bishop, 1221 West Idaho Street, Boise, ID 83702. Please contact me if you have questions. Sincerely, Marc Patterson Engineering Leader, T &D Planning Ph. 208.388.2712 Enclosures: Final Feasibility Study Report (2) GI 364 & 365 Facility Study Agreements (s) GI 364 & 365 C: Rowena Bishop/IPC Jl21 W, klaM St. (B310l) P.O. 8o:..70 l!olse, 10 8't1117 Facilities Study Agreement THIS AGREEMENT is made and entered into this __ day of 2011 by and between , a organized and existing under the laws of the State of , ("Interconnection Customer,") and Idaho Power Company, a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on 1/14/11; and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a system impact study and provided the results of said study to the Interconnection Customer; and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the system impact study in accordance with Good Utility Practice to physically and electrically connect the Small Generating Facility with the Transmission Provider's Transmission System. NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause a facilities study consistent with the standard Small Generator Interconnection Procedures to be performed in accordance with the Open Access Transmission Tariff. 3.0 The scope of the facilities study shall be subject to data provided in Attachment A to this Agreement. 4.0 The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s). The facilities study shall also identify (1) the electrical switching configuration of the equipment, including, without limitation, transformer, switchgear, meters, and other st~tion equipment, (2) the nature and estimated cost of the Transmission Provider's Small Generator Facilities Study Agreement - 1 -Swager Farms Expansion Project #364 Interconnection Facilities and Upgrades necessary to accomplish the interconnection, and (3) an estimate of the time required to complete the construction and installation of such facilities. 5.0 The Transmission Provider may propose to group facilities required for more than one Interconnection Customer in order to minimize facilities costs through economies of scale, but any Interconnection Customer may require the installation of facilities required for its own Small Generating Facility if it is willing to pay the costs of those facilities. 6.0 A deposit of $30,00.00 is due upon execution of this agreement by the Interconnection customer. 7.0 In cases where Upgrades are required, the facilities study must be completed within 45 Business Days of the receipt of this Agreement. In cases where no Upgrades are necessary, and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 Business Days. 8.0 Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the facilities study must be completed and the facilities study report transmitted within 30 Business Days of the Interconnection Customer's agreement to conduct a facilities study. 9.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 10.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company -Delivery Signed: Signed: ___________ _ Printed Name: Printed Name: --------------------- Title: Title: --------------------------- Date: Date: --------------------------- Small Generator Facilities Stlildy Agreement -2-Swager Farms Expansion Project #364 Attachment A to Facilities Study Agreement Data to Be Provided by the Interconnection Customer With the Facilities Study Agreement 1. Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT/PT) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps 2. One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station. Number of generation connections: 3. Will an alternate source of auxiliary power be available during CT /PT maintenance? Yes No --- 4. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? Yes No __ (Please indicate on the one-line diagram). 5. What type of control system or PLC will be located at the Small Generating Facility? 6. What protocol does the control system or PLC use? 7. Please provide a 7 .5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines. 8. Physical dimensions of the proposed interconnection station: Small Generator Facil~ties Study Agreement -3-Swager Farms Expansion Project #364 9. Bus length from generation to interconnection station: 10. Line length from interconnection station to Transmission Provider's Transmission System. 11. Tower number observed in the field. (Painted on tower leg)*: 12. Number of third party easements required for transmission lines*: *To be completed in coordination with Transmission Provider. 13. Is the Small Generating Facility located in Transmission Provider's service area? Yes ___ No ___ IfNo, please provide name of local provider: 14. Please provide the following proposed schedule dates: Begin Construction Date: ____________ _ Generator Step-Up Transformers Date: ____________ _ Receive Back Feed Power Generation Testing , Date: ____________ _ Commercial Operation Date: ____________ _ Small Generator Fadlities Study Agreement -4-Swager Farms Expansion Project #364 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 34 Laura Knothe 8720 Vic Lane Middleton, ID 83694 Junel 0, 2011 VIA email & An IDACORP Company Certified mail# 70090820000123019190 Subject: Swager Fa11llS expansion Project #364-FINAL NOTICE Dear Laura: By letter dated Apri1.27, 2011 Idaho Power provided you with a Facility Study Agreement for interconnection of the proposed Swager Fanns expansion to be interconnected in Twin Falls County, ldaho. Interconnection Customer was to exe-cute and return to me the Facility Study Agreement with the required $30,000.00 deposit by June 9, 2011. That time period has now expired. Your application for Generation Interconnection has now be_en de.emed withdrawn. Fai)ure to submit the deficient items to me l:>y June 24, 2011 will cause your deneratot tnterconnection req11est to be tenninated. If you have any further questions, please don't hesitate to contact me. cc (via email): Orlando Ciniglio/IPC Marc Patterson/IPC Eric Hackett/IPC Aubrae Sloan/fPC Sincerely, Rw)!A1 Rowena Bishop Operations Analyst Ph 208.388.2658 rbishop@idahopower.com P.O. Box 70 (83707) 1221 W. Idaho St. Boise, ID 83702 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 35 MP GENERATOR INTERCONNECTION FEASIBILITY STUDY For integration of the proposed SWAGER FARMS DIGESTER PROJECT In TWIN FALLS COUNTY, IDAHO To the IDAHO POWER COMPANY ELECTRICAL SYSTEM For NEW ENERGY TWO, LLC The INTERCONNECTION CUSTOMER REVISED REPORT August 26, 2011 Generator Interconnection Feasibility Study General Interconnection Information Station or Date of Total Trans Line Queue Request Location (MW) for POl 12.5 kV through Clover Twin Falls (COVR) #307 January 2011 County 1.2 substation Short Circuit Analysis Results System Changes Required: DYes [giNo Power Flow Analysis Results System Changes Required: [g]Yes DNo Projected In-Service Date September 2011 Type of facility (combined cycle, base load, CT, fuel type) Biogas Idaho Power recently updated its operating requirements for generators interconnecting to the distribution system. Because of these new requirements, there are upgrades required to the existing IPC distribution system to interconnect the 1.2 MW generator project at Swager Farms that were not identified in the original January 2010 report. The cost estimates for those upgrades are shown in Table 1 below. Description Estimated Cost Distribution line upgrades (2.5 miles total) $350,000 Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs, and communications $225,000 Total Estimated Cost $575,000 Table 1: Estimated interconnection costs for 1.2 MW project at Swager Farms Good Faith Cost Estimate Interconnection cost estimate for 1.2 MW generator project: $575,000. System Impact Study Required? DYes [gJ No This Feasibility Study only addresses the work required to interconnect the Swager Farms digester projects to the Idaho Power system. There are no transmission rights secured for the project until a transmission system request is submitted by the corresponding transmission customer. The required transmission facilities, if any, to support energy transfers will then be determined based on first come first serve basis (queue order). Operating Requirements: As part of the updated operating requirements, project #364 will be controlled to operate at unity power factor with an operating bandwidth of± 300 kVAR. -1- BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 36 September 9, 2011 Certified Mail# 70090820000123019695 LawaKnothe The New Energy Company 8720 Vic Lane Middleton, ID 83644 RE: Swager Farms Project# 307 Dear Laura: An IDACORP Company Sin<:e we issued your previous Feasibility Smdy Rtmort, some .ldMo Power -op~rating requirements ·changed that affect this project. The· additional modifications were previou~ly presented to you as part of our April 26, 2011 Feasibility Report for GINT#346~ Enclosed is a Revised Feasibility Study Report for lhe above-referenced proje_ct. The feasibility analysis indicates that nio.dification/addition of some facilities will be requited to integrate the network tesowc_e capacity addition <>f your project into the fqaho Power system. Enclosed are two Facility -Study Agreements (FSAs) for the above-referenced generator interconnection. In order to proceed with your project, and fot your ap:glication to r.emain in. the Generator Inter:¢qhtlectit.ni study queue, Idaho_ Power must rec.eive 2 signed cppies of the FSA by October 21, 201 L otherwise your GI application will be deemed ·withdrawn. The d~posit urtdel' this FSA is .$30,000 based .on estimated engineering costs. The submittal should be sent to: Idaho Power Company, Attention: Rowena Bishop, 1221 West Idaho Street,_ Boise, lD 83702. Pleas~ contaqt m~ if you ha:V¢ questions. Sincerely, Marc Patterson Engineering Leader, T&D Planning Ph. 208.388.2712 Enclosures: two Facility Study Agreements C: Rowena Bishop/IPC Ed Kosydar/IPC 1221 W, Idaho St, (83702) P.O. Box. 70 Boise, ID 83707 ·. Facilities Study Agreement THIS AGREEMENT is made and entered into this __ day of 2011 by and between , a organized and existing under the laws of the State of , ("Interconnection Customer,") and Idaho Power Company, a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on 10/12/09; and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a Revised Feasibility Study and provided the results of said study to the Interconnection Customer; and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the system impact study in accordance with Good Utility Practice to physically and electrically connect the Small Generating Facility with the Transmission Provider's Transmission System. NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause a facilities study consistent with the standard Small Generator Interconnection Procedures to be performed in accordance with the Open Access Transmission Tariff. 3.0 4.0 The scope of the facilities study shall be subject to data provided in Attachment A to this Agreement. The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions ofthe system impact study(s). The facilities study shall also identify (1) the electrical switching configuration ofthe equipment, including, without limitation, transformer, switchgear, meters, and other station equipment, (2) the nature and estimated cost of the Transmission Provider's Small Generator Facilities Study Agreement - 1 -Swager Farms Project #307 Interconnection Facilities and Upgrades necessary to accomplish the interconnection, and (3) an estimate of the time required to complete the construction and installation of such facilities. 5.0 The Transmission Provider may propose to group facilities required for more than one Interconnection Customer in order to minimize facilities costs through economies of scale, but any Interconnection Customer may require the installation of facilities required for its own Small Generating Facility if it is willing to pay the costs of those facilities. 6.0 A deposit of $30,000 is due upon execution of this agreement by the Interconnection customer. 7.0 In cases where Upgrades are required, the facilities study must be completed within 45 Business Days of the receipt of this Agreement. In cases where no Upgrades are necessary, and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 Business Days. 8.0 Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the facilities study must be completed and the facilities study report transmitted within 30 Business Days of the Interconnection Customer's agreement to conduct a facilities study. 9.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 10.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company -Delivery Signed: Signed: ____________ _ Printed Name: Printed Name: ----------------- Title: Title: ------------------------ Date: Date: ---------------------- Small Generator Facilities Study Agreement - 2 -Swager Farms Project #307 Attachment A to Facilities Study Agreement Data to Be Provided by the Interconnection Customer With the Facilities Study Agreement 1. Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT/PT) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps 2. One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station. Number of generation connections: 3. Will an alternate source of auxiliary power be available during CT/PT maintenance? Yes No --- 4. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? Yes No __ (Please indicate on the one-line diagram). 5. What type of control system or PLC will be located at the Small Generating Facility? 6. What protocol does the control system or PLC use? 7. Please provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines. 8. Physical dimensions of the proposed interconnection station: Small Generator Facilities Study Agreement - 3 -Swager Farms Project #307 9. Bus length from generation to interconnection station: 10. Line length from interconnection station to Transmission Provider's Transmission System. 11. Tower number observed in the field. (Painted on tower leg)*: 12. Number of third party easements required for transmission lines*: *To be completed in coordination with Transmission Provider. 13. Is the Small Generating Facility located in Transmission Provider's service area? Yes ___ No ___ IfNo, please provide name of local provider: 14. Please provide the following proposed schedule dates: Begin Construction Date: ____________ _ Generator Step-Up Transformers Date: ------------- Receive Back Feed Power Generation Testing Date: ____________ _ Commercial Operation Date: ____________ _ Small Generator Facilities Study Agreement -4-Swager Farms Project #307 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 37 CERTIFICATION OF AUTHORITY FOR AGENTS I, LAURA KNOTHE, the duly authorized and appointed MANAGER of The New Energy Company, LLC ("Company''), HEREBY REPRESENT, WARRANT, AND CERTIFY to Idaho Power Company that the following are authorized and empowered, for and on behalf of the Company, to execute instruments, agreements, certificates, and other documents (collectively "Documents") and to take actions on behalf of the Company, and that Idaho Power Company and its directors, officers, employees, and agents are entitled to consider and deal with such persons as agents of the Company for all purposes, until such time as an authorized officer of the Company shall have delivered to Idaho Power Company .a notice in writing stating that such person is and shall not longer be an agent on behalf of the Company. Any Documents executed by such persons shall be deemed duly authorized by the Company for all purposes. Name of Company: The New Energy Company, LLC 8720 Vic Lane Middleton, ID 83644 Name ofProject(s): Swager Fanns (New Energy Two, LLC) and Double B Dairy (New Energy Three, LLC) Leslie White Manager Laura Knothe Manager IN WITNESS WHEREOF, I have hereunto signed my name this _1_8_ day of October 2011. Print Name: Laura Knothe Title: Manager I, Kara G()dfrey, HEREBY CERTIFY, that Laura Knothe is the duiy elected and acting Manager of the Company and that the signature appearing above is his/her signature. '""'•-...1"-:-rr,_ l.-( IN WITNESS WHEREOF, I have hereunto signed my name this ,jl.) day of vc:;roi@l-.. 20 .n_. I 1/ v ' .~1 Print Name: nM< A 6 ()p~\21. Title: \ P\~'.0&-ewt BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 38 Facilities Study Agreement THIS AGREEMENT is made and entered into this 21 day of October, 2011 by and between New Energy Two, LLC, a Limited Liability Company organized and existing under the laws of the State of Idaho, ("Interconnection Customer,") and Idaho Power Company, a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on 10112/09; and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a Revised Feasibility Study and provided the results of said study to the Interconnection Customer; and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the system impact study in accordance with Good Utility Practice to physically and electrically connect the Small Generating Facility with the T:r·ansmission Provider's Transmission System. NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause a facilities study consistent with the standard Small Generator Interconnection Procedures to be performed in accordance with the Open Access Transmission Tariff. 3.0 The scope of the facilities study shall be subject to data provided in Attachment A to this Agreement. 4.0 The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s). The facilities study shall also identify (1) the electrical switching configuration of the equipment, including, without limitation, transformer, switchgear, meters, and other station equipment, (2) the nature and estimated cost of the Transmission Provider's Small Generator Facilities Study Agreement - 1 -Swager Farms Project #307 Interconnection Facilities and Upgrades necessary to accomplish the interconnection, and (3) an estimate of the time required to complete the construction and installation of such facilities. 5.0 The Transmission Provider may propose to group facilities required for more than one Interconnection Customer in order to minimize facilities costs through economies of scale, but any Interconnection Customer may require the installation of facilities required for its own Small Generating Facility if it is willing to pay the costs of those facilities. 6.0 A deposit of $18,260 is due upon execution of this agreement by the Interconnection customer. 7.0 In cases where Upgrades are required, the facilities study must be completed within 45 Business Days of the receipt of this Agreement. In cases where no Upgrades are necessary, and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 Business Days. 8~0 Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the facilities study must be completed and the facilities study report transmitted within 30 Business Days of the Interconnection Customer's agreement to conduct a facilities study. 9.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 10.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the iflvoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company -Delivery Signed:_~~ ~ Printed Name: Leslie White ----- Title: _Project Manager _____ _ Date: 10/21/2011 -------- Small Generator Facilities Study Agreement - 2 -Swager Farms Project #307 Attachment A to Facilities Study Agreement Data to Be Provided by the Interconnection Customer With the Facilities Study Agreement 1. Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. Submitted previously. On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT/PT) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps 2. One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station. Number of generation connections: 1 connection. 3, Will an alternate source of auxiliary power be available during CT/PT maintenance? Yes. No :NA. 4. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? Yes ---. No A (Please indicate on the one-line diagram). 5. What type of control system or PLC will be located at the Small Generating Facility? __ Automation Direct'-----------------------" 6. What protocol does the control system or PLC use? _Mobus or other if required·---------~----------. 7. Please provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines. Submitted previously. 8. Physical dimensions of the proposed interconnection station: NE Comer of 3900N 1700E Small Generator Facilities Study Agreement - 3 -Swager Farms Project #307 9. Bus length from generation to interconnection station: _______ TBD ______________________________ =-~--~~----~----------- 10. Line length from interconnection station to Transmission Provider's Transmission System. =-~~TBD ____ ~~--~-=~~----~--~~--------~--------------- 11. Tower number observed in the field. (Painted on tower leg)*:. TBD --------------------------------------------------------------~-- 12. Number of third party easements required for transmission lines*: .i-------N one Anticipated:;_·· --------------------------..,....="-----~~~---~~----"""- *To be completed in coordination with Transmission Provider. 13. Is the Small Generating Facility located in Transmission Provider's service area? Yes ---:o.X~ __ No _____ If No, please provide name oflocal provider: 14. Please provide the following proposed schedule dates: Begin Construction Generator Step-Up Transformers Receive Back Feed Power Generation Testing Commercial Operation Date: 12/15/2011 __ '----"-"--"---- Date: _6/15/2012 ____ =----- Date:. 7/15/2012:...,.._ _____ _ Date: 10/1/2012 --------------- Small Generator Facilities Study Agreement -4-Swager Farms Project #307 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 39 Rowena Bishop Idaho Power 1221 W. Idaho Street Boise, Idaho 83702 rbishop@idahopower.com Re: Proof of Site Control Swager Dairy Dear Ms. Bishop: The undersigned, Swager Farms, LLLP, is the Owner of Swager Dairy, as evidenced by copies of the vesting deed and tax records attached. This is to acknowledge that New Energy Company Two, LLC, is negotiating with Owner as regards the right to lease and occupy a site upon the subject property for purposes of development of an anaerobic digester project. Please consider this as Proof of Site Control as required to by Idaho Power to be submitted during the interconnection process ongoing between Idaho Power and New' Energy Company Two, LLC. Swager Farms, LLLP, an Idaho limited liability partnership Date: October _d__, 2011 t i 45048.0004.25~554.1 TWIN f'ALLs COU:VTY lfamflltl FRE"OER I CKSEN. WI Lll AMS 9:24:27 Am 12-22-2008 2008-026678 I. HCe': I III: IIi •• II= IJf«< QUITCLAIM DEED f.llll: aiEl FOR VALUE RECEIVED, THE GERBEN AND MARIANSW AGERFAMILY TRUST, under rrust agreement dated June 2l, 1991, Gerben Swager and Marian Swager, Trustees. hereby remises, releases. and forever quitclaims unto SWAGER FARMS.. LLLP, an Idaho limited liability partnership. 1707 East 3800 North, Buhl Idaho 83316-I 646. bereinafiercal1cd the "Grantee". all iiS righL title and interest in the following dc:sc.ribcd rea.l property. to-on;t: S~e EXHIBIT A atrach~d herdo. Together with all water rights appurtenant thereto. TO HAVE AND TO HOLD the premises. with their appurtenances unto said Grantee. and the: Grantee's heirs and assigns forever. DATED this I tit 1-l day of ~ • 2008. "GRANTOR" THE GERBEN AND MARlAN SWAGER FAMJL Y TRUST. General Partner STATE OF IDAHO ss: County of \J'~) -1ft,_:_ .j., ~ MARIAN SWAG2Trustee 011 this~ day of Du~ , 2008, before me. the undersigned. a Notary Public in and for said County and State, personally appe&Rd GERBEN SWAGER and MARIAN SWAGER. husband and wife. Trustees oftheGerben and Marian Swager Family Trust ult/a did 6124/91. General Partner. known to me to l'te such Trustees and thr: persons whose namc:s arr: subscribed to the within and fo~going instrument. and who acknowledged to me that they executed the same on behalf of the Trust as Geneml Partner of the Partnership. upc;m NQ. 1 T ......... JO~ ..... lS~~,. rt• • 'l'tltla..U.c-s-, ...... s--.. :Ill: NB 114 Mil 114wiiXICal't .. w-10-....,... ....._11: N 112 NW 114 8VaiBC'I' 'J"'c Twill ..... mp_, E*ldllc .... o6 way "'CZ! W). T ........ l0 ............ 15 .... ..._N ''len Twtal'lln.~.lkWio ...._21: W 112 Mil U.. NW 114 88 114 suaDICT'tO: ...... hDI M'a' "" a.Mt~ .,~ fwin Fa1ls County Property Information Access Twin Falls County Property Information Access Parcel ID Number RP10S1SE212400A 1 Owner Information !sWAGER FARMS, LLLP b707E3800N ISl.;'HL ID 83316 I Catca;ory 1-IRRGIDAG 10-RURAL HOMESITE I 0 • RURAL HOMESITE 18 -OTHER LAND 19-WASTE J l -RURAL RES BLDG 32 -RURAL IMP ON AG [7 ·IMP TO MAN HSG f48-MANUFHS W/SID Propel't)' loformatioo !377l 1700 E !Tax Code: 620000 Zip: 0 isEC21 T lOR 15 INt/2 NW Catcs!ory Information L9.742 1.000 1.000 ~4.226 14'.032 1:1.000 0.000 10.000 lo.OOO Tu Information Unit AC AC AC ~c lAC Page 1 of .i !Value t21064 11480 11480 127539 08868 017670 17360 43433 Year Built 2000 Effective Year: 2000 Other rural land Tax Year: 2006 ifax Year: 2007 tTax Year: 2008 Tax Year: 2009 Tax Year: 2010 Bill#: 28366 !Bill#: 29453 [BiU#: 30410 Bill#: 31365 Bill#: 32195 !Market: 2296090jMarlret: 2986733!f..wket: 29867331Market 23772041Market: 2377204 IImpr.Type: DWELL ic.B.: 0.00 lc.B.: 0.00 lc.B.: 0.00 lc.B.: 0.00 ~.B.: 0.00 !condition: AV IH.O.: o IJI.o.: o IFto.: o IJI.o.: 1.35331 lt-I.O.: 132014 I# Levels: 001 Special: 36.86 ~pecial: 36.86 !special: 36.86 ~pecial: 36.86 !special: 36.86 !Number Living Rooms: 1 ltax: 26246.90 ~ax: 29649.36 !Tax: 3023L88 ~ax: 23222.?:0 lr'Bx: 23987.08 !Number Bedrooms: 3 !Number Full Baths: 3 Half: 0 Fint Half: !First Half: !Fint Half: IFint Half: IFint Half: tN"umber Family Rooms: 0 Cost: 0.00 Cost 0.00 !cost: 0.00 !cost 0.00 least: 0.00 !Number Dining Rooms: 0 oterest: 0.00 Interest: 0.00 lrnterest: 0.00 ~Interest: 0.00 Interest: 0.00 !Number Kitchens: I !Penalty; 0.00 'Penalty: 0.00 !Penalty: 0.00 jPenaity: 0.00 !Penalty: 0.00 ptber Rooms: 1 !Paid: 13123.45 Paid: 14824.68 Paid: 15115.94 ~aid: 11611.35 !Paid: 11993.54 ~~ Sinks:1 Wtr Heaters: I ConceDed: 0.00 Cancelled: 0.00 ~celled: 0.00 !cancelled: 0.00 lcaucened: 0.00 Number Fireplaces: I n-otal Sq Feet: 2504 lsewnd Half: ISecood Half: lseeood Half: !second Half: !second Half: rrotat Living Sq Feet: 2504 !cost: 0.00 ~ost 0.00 !cost: 0.00 !cost: 0.00 lcost: 0.00 IPri:m..Heat: Forced hot air-gas !Interest 0.00 nterest 0.00 llutet"est: 0.00 lfntercst: 0.00 !Interest: 0.00 !central Air: Y Penalty: 0.00 iPenalty: 0.00 !Penalty: 0.00 Penalty: 0.00 Wc:nalty: 0.00 RoofType:Hip !Paid: 13123.45 Paid: 14824.68 IPaid: 15115.94 Paid: 11611.35 1Paid: 11993.54 Roof Covering: Comp sh heavy lcanceUed: 0.00 Pmcelled.: 0.00 lcanceiJed: 0.00 !cancelled: 0.00 !{:anrelled.: 0.00 Int. Walls: Drywall !Foundation: Formed cone http://216.83.79.6:9951/resultdetail.php?parcel=RP10Sl5E212400A 10113/201 I T\.\-in Falls County Property Information Access Special Taxing Districts: AMER.FALLS Page 2 of 4- i)eed Refereuce Numben: 08-()26679 08-026678 02-009992 99-007758 TB88093489 Last Change Date: 12-22-2008 Relafed Parcel Numbers: (none) Parcel Commeuts: ASSOC PARCEL -RPIOS15E210600; ASSOC PARCEL-RP10Sl5E213600; ASSOC PARCEL-RPl OS15E214800; ASSOC PARCEL-RPIOSI5E216010; ASSOC PARCEL-RPIOSISE210010; Owuership History: 2009 -2010 SWAGER FARMS, LLLP 2002 -2008 SWAGER, GERBEN 1999-2001 TRANSMUTATION PROPERTIES, INC I 994 -1998 HAFLIGER, HENRY C JR Scanned Worksheets: 1961 RURAL LAND APPRAISAL for: DROWN, LYNN R 1961 OUT BUILDING for: DROWN, LYNN R 1962 SUMMARY SHEET for: OPPLIGER, FRED 1970 SUMMARY SHEET for: SLIGAR, RODNEY L 1971 RURAL LAND APPRAISAL for: DROWN, LYNN R 1971 OUT BUILDING for: DROWN, LYNN R 1976 SUMMARY SHEET for: DROWN, LYNN R 1980 OUT BUILDING for: DROWN, LYNN R 1982 SUMMARY SHEET for: DROWN, LYNN R 1984 RURAL LAND APPRAISAL for: DROWN, LYNN R 1984 OUT BUILDING for: DROWN, LYNN R 1985 SUMMARY SHEET for: DROWN, LYNN R 1988 SUMMARY SHEET for: HAFLIGER, HENRY C JR 1989 OUT BUILDING for: DROWN, LYNN R 1989 MH APPRAISAL SHEET for: H&H DAIRY 1993 APPRAISAL HOUSE #1 for: HAFLIGER, HENRY C JR 1993 APPRAISAL HOUSE #2 for: HAFLIGER, HENRY C JR 1993 OUT BUILDING for: HAFUGER, HENRY C JR 1996 MH APPRAISAL SHEET for: H&H DAIRY Additional Property Sheets: Propettf Sheet: 2 Property Sheet: 3 Property Sheet: 4 Property Sheet: S Property Sheet: 6 Property Sheet: 7 .Property Sheet: 8 Property Shc;et 9 Property Sheet-10 Property Sheet: 11 Property Sheet: 12 Property Sheet: 13 Property Sheet: 14 Property Sheet: 15 bttp://216.83.79.6:9951/resultdetail.php?parcel=RP10SI5E212400A 10/13/2011 Tv.in Falls County Property Infonnation Access ?:-operty Sheet 16 Property Sheet: l 7 ?rooenv Sheec 18 £rooertv: Sheet: 19 Property Sheet: 20 Property Sheet; 21 Property Sheet 22 Property Sheet 23 Property Sheet 24 Property Sheet: 25 Pmoertv Sheet: 26 Prooerty Sheet 27 Property Sheet: 28 Property Sheet: 29 Property Sheet; 30 r rooerty Sheet: 31 Property Sheet 32 Property Sheet: 33 Property Sheet: 34 Property Sheet: 35 frooerty Sheet: 36 Property Sheet: 37 Property Sheet 38 Property Sheet; 39 Property Sheet: 40 Property Sheet: 41 Property Sheet: 42 Property Sheet: 43 Property Sheet: 44 Page 3 of4 Calculate taxes due-Interest as of date: I_ _ .. (do not use hyphens, enter as mmdd.yyyy) ~}~~j Tax Payment History Year_l!'ype_ ~ate !Hall IBatchiT_ranli rr~ IPenalJll In teres Total ~mArk :Payor User lfUP ~006 12-13-1 lso-35 13123.45 r.oo 0.00 13123.45 ~K4619-SWAGER BETHL IPa~ !£oo6 M FARMS I ~006 05-I7-~ 50-6 13123.45 0.00 0.00 13123.4~ CK 5027--SWAGER, IBETHL I IPaym_ent 2007 ~ Q_ERBEN 2007 i2-17-I 80-89 14824.6~ ~.00 ~.00 14824.6~ fcK 5632-SWAGER, !KAnnE Payment 2007 1M IGERBEN I 2007 12-17-2 ~0. 89 L4824.6B ~-00 0.00 t4S24.6a ~KS632-fSWAGER, K.ATiflE Payment li007 1M P~RBEN 12008 12-29-50-19 Ull5.94 p.oo 0.00 15115.94 CK6718-SWAGER JERIE !Payment ~008 I M FARMS rzoos 12-29-~ 50-19 15115.94 p.oo 0.00 15115.94 CK6718--SWAGER JERIE !Payment ~008 M FARMS ~009 12-17-CK 10008 !SWAGER ~AROL I 20-9 11611.35 0.00 0.00 11611.3~ if' ARMS, Payment 2009 I M !LLLP 12~17-2 ~0 ~9 11611.35 0.00 ~.00 I 161 L3'i ~K 10008 ~WAGER ~OL i 2009 FARMS, http:/1216.83. 79 .6:9951/resultdetail.php?parcel=RPl OS 15E212400A 10/13/2011 ·i'>l.m Falls County Property Information Access Page4of4 :Pavment 12009 ~ ILLLP I l !SWAGER i ~010 12-21-I 160-44 11993.54 ~.00 ~.00 ~K 11278- aymenr 2010 I 1993.54 -M IF ARMS, fpEEKABOC ! IL..LLP !zo10 06-17-~ SWAGER I ~0-51 11993.54 0.00 ~.00 I 1993.54 CK#ll882 ! ;Payment 2011 FARMS, DEBBIE i M ILLLP I use the browser BACK button to return to search results. Begin New Parcel Search ~2006 Developed by Steohenscn Computer Consulting. Inc. http:/1216.83. 79.6:995 1/resultdetail.php?parcel=RP 1 OS 15E212400A 10/13/2011 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 40 October 21, 2011 ldilho P.ower Company A:ttn: Rowena Bishop 1221 W~ ldaho St. Boise, ID &3702 RE; Swager FSA-GI 307 Dear Rowen~ We are pleasecl. tQ offer the e-!lo.los~d signed FaciHties Study. Agreement-for project #307 as well as the -deposit of $18·,260. Additionally, we have reviewed correspondence. that has taken place since the draft Generation Intercomiection Agreement issued by Idaho Eower on October 25 20 I 0 and we require your assistance in clarifying a few items pertaining to the studies and ·the ·associated r.ewsions to the estimated iriter.connectiO'n costs for this project. The priinaiy clarification We tequlre is the definition of the .new operating requirements which have caused a. significant change .iri fue, ei)tjmated intercoi~J1ection cost for this proJect compared with the costs provided in the aforementioned Pra~ Gei:t.er;ltio.n lri,terconnection A:greeJiletit s.till in our posseSsion. Please provide uummaTy, speci.fic to project-#.307, ofthetelevantdiffererices between the:rtew op~ratingrequlrements which are now in effect.antl those that were in effect when o:ur :gen¢ri):tiort intetcowec,:tion_ req\lest was accepted and .fimil studies wewsubm1tted by ldaho Power . . Plea,se. als.Q review the tim:eline shoWii, In 'T~:t.ble 1 and ·provide .feedbaek con<:eming this table so ·that we can better tinderstand tl!e evcm_ts that have ttahspire<l, siiice th¢ i$suan,ce of-the D.raft.GIA for project #307 .. 1'il~le :t:. Ti~eline ;1/~/11 Laura Knothe contacts Eric, .Hackett We provided art :updated of our progress on the Draft G•A:and jnqutreg abour e"pected interconnection t'rn,f'Hi'•n SChedUle, Exergy Development Group, 802 W. Bannock, 12lh Floor, Boise, ID phone: 208.336.9793 fax: 208.336.9431 A secondneed for clarificationhas to do with the"Operating.Requirements'section of the Al,lgust 26 Feasibility Study for project #307 which reads; ''As part of the updated operating requirements, project #364 will be controlled to operate at unity power factor with an operating bandwidth of± 300 kVAR~' Specifically, we would like to know if there hM Qeeil some coirfusiort between the two different 'interconnection queue numbers being discussed early in. 2011, namely #307 and #364. TheJeasibility study is for project #307~ but some of the text is clearly referring to project #3M. Plea5e do not hesitate to contact us with any questions regarding this letter or the enclosed. documents. Leslie White Project Manager, New Energy Two Ph. 208.890A660 Enclosures: Executed Facility Study Agreements (2) Deposit Check# 1571 Swager Site ControiDocumentation Exergy Development Group, 802 W. Bannock, 12lh Floor, Boise, lD phone: 208.336.9793 fax: 208.336.9431 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 41 Clark, Danielle From: Sent: To: Cc: Subject: Leslie- Patterson, Marc Thursday, December 08, 2011 4:35 PM 'Leslie White' Bishop, Rowena; Hackett, Eric; Schultz, Trevor FW: FSA for Project #307 Swager Farms Idaho Power will not provide our detailed system information and customer load information to you. As indicated early, when we completed the revised Feasibility Study we identified upgrades required to interconnect this project. In addition, we reviewed the system changes suggested by Exergy at our November 3rd meeting, but those options had already been considered in our study process. Therefore the upgrades identified in the Feasibility Study will be required in order to connect this project. In addition, because the project Facility Study will be completed next week, I suggest waiting for that study to be issued before setting another meeting to discuss this project. Marc Patterson From: Leslie White [mailto:lwhite@exerqydevelopment.com] Sent: Wednesday, December 07, 2011 9:54AM To: Patterson, Marc ; Subject: RE: FSA for Project #307 Swager Farms Hello Marc, Have you had time to consider this email and perhaps provide us with some direction with these concerns? Is there any chance we can arrange to talk about this on Friday or Monday? Warm regards, Leslie Leslie White 802 W Bannock, 12th Floor Boise, ID 83702 Office: 208.336.9793 1 Mobile: 208.890.4660 Y.YJ.Vw ..,E~.&f£1Y_t;l?..veiQQ.tn~nt. <;:_Q_n.J This electronic or printed document contains information which (a) may be LEGALLY PRIVILEGED, PROPRIETARY IN NATURE, OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is imended only for the use of the Addressee(s) named above If the reader of this message is not the intended recipient. or the employee or agent responsible to deiiver it to the intended recipient, you are hereby notified that any dissemination. distribution or copying of this ccmmunication is strict!y prohibited If you have received tl1is communication in el'rOJ, please immediately notify us by teiephone, and return ihe origina! message to us at the above emaii add1ess. Thank yoLI From: Leslie White Sent: Thursday, December 01, 2011 3:28 PM To: 'Patterson, Marc' Cc: 'Bishop, Rowena'; 'Hackett, Eric'; Josh Gunderson Subject: FSA for Project #307 Swager Farms 1 Marc, I spoke to Eric today and he has directed us back to you with regards to our questions surrounding #307. We continue to struggle with depth of the upgrades required on the distribution line, but this is probably attributable to our lack of familiarity with the line. In reviewing the two drawings presented under work order# 27328106, the single line (210- 62790) and the google earth map depicting the distribution line path and location of the POI and Substation, we are wondering if you can fill in a few blanks and help us with defining the equipment and conductors on that line and perhaps the line loads? We recognize that your team is confident io the need to upgrade 2 miles of distribution line as a result of their analysis, but I trust you can agree that the feasibility study does not provide the necessary details to support that conclusion. We are in a position to want see the problem and the solution as you see it but we are unable to do so and thus you have been peppered with questions as we seek to understand the situation better. Perhaps you are willing to share the details of your system modeling and analysis, but if not, we would still find it useful to see the inputs to that model-namely drawings that depict what infrastructure exists in the area shown on the google earth map provided previously. By allowing us to see the problem as you see it, we can invest our time toward answering our own questions rather than infringing on your time to answer them. If by some chance we come up with an alternative solution that works, all the better and then Exergy will have to purchase further studies to investigate in detail. If we cannot find a such a solution, then at least your team and our team will be seeing the same problem in the same way and we can move forward. Warm regards, Leslie Leslie White 802 W Bannock, 12th Floor Boise, ID 83702 Office: 208.336.9793 1 Mobile: 208.890.4660 '!!'/YYt.,~K~Y.<:i~Y-~.\.QQffi~Dl.G9~T1 This electronic or p1inted doclllnent contains information which (a) may be LEGALLY PRIVILEGED, PROPRIETARY IN NATURE. OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE. and (b) is intended only for the use of the Addressee(s) named above. It the reader of this message is not the mtended recipient, or the employee or agent responsible to deliver it to the intended recipient, you are hereby nO!ified that any dissemination. distribution or copying of this communication is strictly prohibited If you have received this communication in error, please imrnediately notify us by telephone, and return the original message to us at the above email address Thank you 2 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 42 December 15, 20fi Leslie White New Energy Two, LLC 802 W. Bannock 121h Floor Boise, ID 83702 An IDACORP Company Re: Swager Farms Dairy Digester Project Revised Draft Facility Study Rep0rt -Project #307 Dear Ms. White: Idaho Power Company (IPC) has completed the Draft Facility,Study cost estimate for your Generator Interconnection project based on the revised Feasibility Study Report dated August 26,, 2011. Attached please fmd the Draft Facility Study Report (FSR). I am available to discuss the FS~ and begin Construction arrangements for the project. In order to proceed with this project, please provide your comme!1,ts to the Facility Study Report to me by January 15, 2012 and indicate whether you wish to proceed with final design and construction. The final report will be used to prepare a draft -.nerator Interconnection Agreement in preparation for Construction. Rowena Bishop will be working with you=to fmalize the ln'ferconnection Agreement. Before we can begin Constru.ct~o . or order materials .. you are responsible for contacting Idaho Power's credit department to discuss credit r . uirements for construction funding. Please contact Aubrae Sloan (208-388-5697) at your e liest conv ·ence. Once we receive funding, or the credit requirement is met, we can proceed with construction oftl1eproject. The actual cons..troction and labor charges-will b finalized approximately 90 days subsequent to project completion. We will reeone,i]e any aver-or underpayment at that time. I look forward to hearing from yqo soon. Sincerely Eric Hackett Project Leader Attachment: Swager Farms Dairy Digester Project Draft Facility Study Report with Drawings Cc: R Bishop/IPC A Sloan/IPC RBauer/IPC D Walker/IPC DRAFT Generator Interconnection Facility Study Report for the Swager Farms Dairy Digester Project-Project #307 for New Energy Two, LLC in Twin Falls County, Idaho December 15, 2011 An IDACORP Company DRAFT-FACILITY STUDY REPORT (FSR) Swager Farms Dairy Digester Project #307 December 15, 2011 1. General Facility Description The proposed project will consist of Idaho Power's standard overhead generation interconnection package including an overhead recloser, metering package, local service power transformer, disconnect switches, and a relay/control box. Additionally, one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer will be installed, including the associated underground cabling and vaults. The project is located in Twin Falls County, Idaho and connects to the 12.5 kV system on Idaho Power Company's Clover (COVR-012) distribution line. The total project output is 1.2 MW. Interconnection Customer: Leslie White New Energy Two, LLC 802 W. Bannock 121h Floor Boise, ID 83 702 A Standard Generator Interconnection Agreement under Idaho Power Company's Open Access Transmission Tariff (OATT) or Schedule 72 between Interconnection Customer and Idaho Power Company -Delivery (Transmission Owner) for the Swager Farms Dairy Digester Project, specifically Generator Interconnection Project #307, will be prepared for this project. 1.1 Interconnection Point The Interconnection Point for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SW1). The project's location is in T10S R15E Section 21 of Twin Falls County, Idaho. A drawing identifying the Interconnection Point is attached. 1.2 Point of Change of Ownership The Point of Change of Ownership for the Swager Farms Dairy Digester Project will be the low­ side bushings on the padmounted transformer (SW1). 1.3 Customer's Interconnection Facilities The Interconnection Customer will install generators, low-side disconnect switches, all wiring and conduit between the generators and the padmounted transformer, appropriate grounding measures, and associated auxiliary equipment. Interconnection Customer will build underground facilities to the Point of Change of Ownership for the generator facility. 1 The low-side disconnect switch shall be as specified or as determined by mutual agreement and be readily accessible, operable, and lockable by Idaho Power personnel at all times. 1.4 Other Facilities Provided by Interconnection Customer 1.4.1 Telecommunications In addition to communication circuits that may be needed by the Interconnection Customer, the Interconnection Customer shall provide the, following communication circuits for Idaho Power's use: 1. One POTS (Plain Old Telephone Service) dial-up circuit for querying the revenue meter at the generation interconnection site. 2. One leased DDS (Digital Data Service) circuit for SCADA between the generation interconnection site and the Twin Falls Service Building (273 Blue Lakes Blvd. S., Twin Falls, ID 83301). This circuit must operate at 19.2 kbps data rate or higher. Please note that Frame Relay service is not acceptable. The Interconnection Customer is required to coordinate with a communications provider to provide the communications circuits and pay the associated one time setup and periodic charges. The communication circuits will need to be installed and operational prior to generating into the Idaho Power system. Note that installation by communications provider may take several months and should be ordered in advance to avoid delaying the project. If the communication circuit types listed above are not available at the site by a communications provider, the Interconnection Customer shall confer with Idaho Power. If high voltage protection is required by the communications provider for the incoming communications provider cable, the high voltage protection assembly shall be engineered and supplied by the Interconnect Customer. Options are available for indoor or outdoor mounting. The high voltage protection assembly shall be located in a manner that provides Idaho Power 24-hour access to the assembly for trouble­ shooting of Idaho Power owned equipment. 1.4.2 Ground Fault Equipment The customer will install ground fault limiting equipment that will limit the zero sequence fault current to 20 amps at the Interconnection Point. 1.4.3 Easements The Interconnection Customer will provide to Idaho Power a surveyed (Metes & Bounds) legal description along with exhibit map for Idaho Power's proposed facilities. After the legal description has been delivered to IPCO for review, IPCO will supply to the Interconnection Customer a completed IPCO easement for signature by the land owner of record. Once the signatures have been secured, the Interconnection Customer will return the signed easement to IPCO for recording. 1.4.4 Generator Output Limit Control The Interconnection Customer will install equipment to receive signals from Idaho Power Grid Operations for Generation Output Limit Control ("GOLC") -see Section 3 Operating Requirements. 2 1.4.5 Local Service The Interconnection Customer is responsible to arrange for local service to their site, as necessary. 1.4. 6 Monitoring Information If the Interconnection Customer requires the ability to monitor information related to the Idaho Power recloser in the generation interconnection package they are required to supply their own communications circuit to the control box. 1.5 Idaho Power Company's Interconnection Facilities Idaho Power will install a standard generation interconnection package on the existing distribution feeder (COVR-012) on private property southeast of the intersection of E. 3800 N. and N. 1700 E. in Twin Falls County, ID. See the attached work order maps (WO 27328106, sheet 1 of2) for details. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-311 C line protection relay. The relay will be located in a pole mounted enclosure and will also contain a test switch (TS4), SLSS, modems, isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer on top of a vault. Conduit and underground cables will be installed from the interconnection package to padmounted transformer. Protective posts will be installed to protect the ground mounted equipment from damage. A 2" conduit will be installed alongside the underground primary to facilitate information exchange to the customer about the recloser if desired. (The Interconnection Customer is responsible for providing and installing the appropriate cable.) 1.6 Facility Estimated Cost: The following good faith estimates are provided in 2011 dollars: nterconnectwn Facliltles: ;~ Overhead Gen~E~on InterconnectiC?E Package _-SU .. !J .. _~OT.'ALIIPIPCC ..... ,,,,,,,,,,, __ -------$200,000 '(J"~~~~ound Equipmen,! and 1500 kVA Trans_0_ryp.er _ $70,000 _,_,,_. ___ ,___ --~$2-'?,.Q_,OO~ ~~.!:: Section. 6 for the Pr.f!Jl!ct Grand Total ' 3 2. Milestones lfR'¥-··,~·1{~":.-~· .. ,.;.:t,..~;-~~·li'!.i:-; ... 13~rnr~;;=':~"'•-·'r':4.."1! 1.f•!t•~·r.;·;~,~~~~~0~::-: ... ,·,:;(~P~.""~r!"Ill'lf})!t11 t;~ :~ .. to~ ·~. ·,,-~/!·'~!·_•,. · -~~~""-~~)i.-.' .. •~;Jriz;_.·,,Jl_~·l't.,, t:~ !t.-.,;.=:-l.,~· :~/'.-.).•.~ .. '.~ .... ~~=:'_.i~~·,~-'./ _>...::t!~iJ.f:1I\L"it-,.-}/r.:'-Jr -~-j ..... 1 ~t! -~-.._ .. ~1 TBD Construction Funds Received by IPCO 6 Months after Construction IPCO Construction Complete Funds Received by IPCO 1 month after IPCO Construction VPCO Commissioning Complete Complete TBD by seller Commercial Operation Date These milestone dates assume that material can be procured and labor resources are available. Additionally, any permitting issues outside the immediate control of Idaho Power could also influence the Commercial Operation Date. 3. Operating Requirements The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and requirements for harmonic Control in Electrical Power Systems or any subsequent standards as they may be updated from time to time. Voltage flicker at startup and during operation must be limited to less than 5% as measured at the Interconnection Point. The Project will be subject to reductions directed by Idaho Power Grid Operations during transmission system contingencies and other reliability events. When these conditions occur, the Project will be subject to Generator Output Limit Control ("GOLC") and will have equipment capable of receiving an analog setpoint via DNP 3.0 from Idaho Power for GOLC. Generator Output Limit Control will be a setpoint from Idaho Power to the Project indicating maximum output allowed. The Project must be capable of riding through faults on adjacent section of the power system without tripping due to low voltage. It has been determined, through study, that the Project must be capable of remaining interconnected for any single phase voltage as low as 0.7 PU for 30 cycles, and for all three phase voltages as low as 0.8 PU for 30 cycles. Interconnection Customer will be able to modify power plant facilities on the Interconnection Customer side of the Interconnection Point with no impact upon the operation of the transmission or distribution system whenever the generation facilities are electrically isolated from the system and a terminal clearance is issued by Idaho Power Company's Grid Operator. 4. Reactive Power The Project must be controlled to operate as a VAr neutral system with a ± 300 kVAr operating band. 4 5. Upgrades 5.1 Distribution Upgrades Idaho Power will upgrade the existing distribution feeder (COVR-012) along E. 3550 N. from the Clover Substation (approximately N. 1950 E.) west toN. 1700 E. The new conductor will be 336.4 All Aluminum (336AAC) and will require new support structures to accommodate the larger wire. Additionally, an existing fixed type capacitor bank on the feeder will be upgraded. In order to avoid high voltage on the feeder during minimum load situations, the capacitor must have automatic controls in order to switch on and off as necessary. 6. Estimated Costs The following good faith estimates are provided in 2011 dollars: Estimated Cost: -•• ·,. 'i l!t.o;;~!~fw' ~:·· ·. ··:.~···r:··~-~ ··iffi·,., ·-·1~;.· i:f:5 _____ ,._ __ ,.,111 ...... •, • . ·:. -.1 · ·: :.,-:!:~~ .,·· '!-'J. (!Ailwltl ln '· .. " , ..•. ,. @!l:."U 3Silwc·.th [17.terconnection Facilities (from section 1.6): -- Overhead Generation Interconnection Package IPC $200,000 ,_OHUH ·-~· Underground Equipment and 1500 kVA Transformer IPC $70,000 .. , TOTAL $270,000 -· ... Upgrades to Distribution: Reconductor Approximately 2.5 Miles to 336 AAC IPC $325,000 ~ade C69 Capacitor IPC $30,000 . TOTAL $355,000 GRAND TOTAL I $625,000 Note Regarding Transmission Service: This Facility Study is a Network Resource Interconnection Facility Study. This study identifies the facilities necessary to integrate the Generating Facility into Idaho Power's network to serve load within Idaho Power's balancing area. Network Resource Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery. 5 I ' E D CO V R 01 2 12 . 5 k V "' "" .. BY IP C O 2· BY O~ E R I I I I I ~= = . - - - - - = c ~ I I ~u 1 X- . f t t ,.-l o l f ! . ~ ! . . ~ CC X P E R "V ' I I V U a X " I 1 ~- 1 5 [ : ~ ~ I t- - - - - - - - + -- 2 - - o • : :» , ? 12 K A j r , ~~; ~- - ~ x ~ ~ - - - - - ~ - - -- - - - - ~ t ~ ~ ~ I ~ I L i ~ i i '!! I i L. J 5 1 gi * ~~ : . 1 2 0 / Z I O Y ! IO k V A 7 ~~ 05 1 1. 05 2 ~ .:l f2 i !~ I 2 0 / 2 4 0 V i< l ~I ~I >2 G I 52 G 2 < ~I I 21 il! ~ j I I 11 .L _ _ I IP C O LO C A L SE R V I C E FO R SE l . J l 1 C BO X I I I I I I .. CA T = ~ l ~ GEN E A A I C A ..,. CI > T = : r . . ~ 2 ~ i;E N E A A T Q A ~ PR O J E C T LO C A T! O N · 11 0 5 , R1 5 E . SE C T I C I \ I '21 38 0 0 NO R T H 17 0 0 EA S T , TW I N FA L L S CO U N T Y , lD A H O IN SE R V I C E BY MA Y 20 1 1 , . AL L O W E D CA P A C I T Y BY CO N T R A C T ; -- - KV A ~ 1 RE V I S I O O 1-;o -I G -· ~~· ­ ~~ Oifi ) ~· "" ' l'.c:l fl nJ < N 1!- l • c SIN D . £ UN E AP P R O V A L ~=~~ : _ : _ _ _ _ ~I'll Pl<l l . C ... -- - - - ­ l. o " ' " ' - " " " " ' - - ~_ , . . . . . __ _ ::, . , ~L - a -- . -- ­ .... -- ­ 'CnW ~ I T ­ ·- - ~ " " _ u p l _l IIE F . ' E i l t H C E Cil i . ' M . H t ' S s, . ., . , .. . s~ . , , . , ~ · - l ) ;; . ( ; ~ n t : s co . l l R a . . S0 € 1 1 . - . T i a f= SW A G E R FA R M S DA I R Y DIG E S T E R ~ f= IN T E R C O N N E C T I O N ~A 1- - SI N G L E LIN E ;:; JD A K > PO W E R co . P N I Y BO I S E . IIW I D ~ SC A L E : Nc r £ DA T ( : 6-2 1 - 1 0 ~ ~A P P R O V E D I 21 0 - 6 2 7 9 0 I· A;¥ . ~ R l 1 Stl T , 1 I 01 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 43 ) January 25, 2012 Leslie White New Energy Two, LLC 802 W. Bannock lth Floor Boise, ID 83702 Re: Swager Farms Dairy Digester Project Revised Facility Study Report-Project #307 Dear Ms. White: An IDACORP Company Attached please fmd the Facility Study Report (FSR) based on the revised Feasibility Study Report dated August 26, 2011. This report is considered fmal as no comments were received by IPCO from the draft FSR sent December 15, 2011. Rowena Bishop will be using this FSR and working with you to finalize the Interconnection Agreement. Before we can begin Construction or order materials, you are responsible for contacting Idaho Power's credit department to discuss credit requirements for construction fimding. Please contact Aubrae Sloan (208-388-5697) at your earliest convenience. Once we receive funding, or the credit requirement is met, we can proceed with construction of the project. The actual construction and labor charges will be finalized approximately 90 days subsequent to project completion. We will reconcile any over-or underpayment at that time. Sincerely, Eric Hackett Project Leader Attachment: Swager Farms Dairy Digester Project Facility Study Report with Drawings Cc: R Bishop/IPC A Sloan/IPC RBauer/IPC D Walker/IPC Generator Interconnection Facility Study Report for the Swager Farms Dairy Digester Project-Project #307 for New Energy Two, LLC in Twin Falls County, Idaho January 25, 2012 An IDACORP Company FACILITY STUDY REPORT (FSR) Swager Farms Dairy Digester Project #307 January 25, 2012 1. General Facility Description The proposed project will consist of Idaho Power's standard overhead generation interconnection package including an overhead recloser, metering package, local service power transformer, disconnect switches, and a relay/control box. Additionally, one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer will be installed, including the associated underground cabling and vaults. The project is located in Twin Falls County, Idaho and connects to the 12.5 kV system on Idaho Power Company's Clover (COVR-012) distribution line. The total project output is 1.2 MW. Interconnection Customer: Leslie White New Energy Two, LLC 802 W. Bannock 1ih Floor Boise, ID 83702 A Standard Generator Interconnection Agreement under Idaho Power Company's Open Access Transmission Tariff (OATT) or Schedule 72 between Interconnection Customer and Idaho Power Company -Delivery (Transmission Owner) for the Swager Farms Dairy Digester Project, specifically Generator Interconnection Project #307, will be prepared for this project. 1.1 Interconnection Point The Interconnection Point for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SWl). The project's location is in T10S R15E Section 21 of Twin Falls County, Idaho. A drawing identifying the Interconnection Point is attached. 1.2 Point of Change of Ownership The Point of Change of Ownership for the Swager Farms Dairy Digester Project will be the low­ side bushings on the padmounted transformer (SWl ). 1.3 Customer's Interconnection Facilities The Interconnection Customer will install generators, low-side disconnect switches, all wiring and conduit between the generators and the padmounted transformer, appropriate grounding measures, and associated auxiliary equipment. Interconnection Customer will build underground facilities to the Point of Change of Ownership for the generator facility. 1 The low-side disconnect switch shall be as specified or as determined by mutual agreement and be readily accessible, operable, and lockable by Idaho Power personnel at all times. 1.4 Other Facilities Provided by Interconnection Customer 1.4.1 Telecommunications In addition to communication circuits that may be needed by the Interconnection Customer, the Interconnection Customer shall provide the following communication circuits for Idaho Power's use: 1. One POTS (Plain Old Telephone Service) dial-up circuit for querying the revenue meter at the generation interconnection site. 2. One leased DDS (Digital Data Service) circuit for SCADA between the generation interconnection site and the Twin Falls Service Building (273 Blue Lakes Blvd. S., Twin Falls, ID 83301). This circuit must operate at 19.2 kbps data rate or higher. Please note that Frame Relay service is not acceptable. The Interconnection Customer is required to coordinate with a communications provider to provide the communications circuits and pay the associated one time setup and periodic charges. The communication circuits will need to be installed and operational prior to generating into the Idaho Power system. Note that installation by communications provider may take several months and should be ordered in advance to avoid delaying the project. If the communication circuit types listed above are not available at the site by a communications provider, the Interconnection Customer shall confer with Idaho Power. If high voltage protection is required by the communications provider for the incoming communications provider cable, the high voltage protection assembly shall be engineered and supplied by the Interconnect Customer. Options are available for indoor or outdoor mounting. The high voltage protection assembly shall be located in a manner that provides Idaho Power 24-hour access to the assembly for trouble­ shooting of Idaho Power owned equipment. 1.4.2 Ground Fault Equipment The customer will install ground fault limiting equipment that will limit the zero sequence fault current to 20 amps at the Interconnection Point. 1.4.3 Easements The Interconnection Customer will provide to Idaho Power a surveyed (Metes & Bounds) legal description along with exhibit map for Idaho Power's proposed facilities. After the legal description has been delivered to IPCO for review, IPCO will supply to the Interconnection Customer a completed IPCO easement for signature by the land owner of record. Once the signatures have been secured, the Interconnection Customer will return the signed easement to IPCO for recording. 1.4.4 Generator Output Limit Control The Interconnection Customer will install equipment to receive signals from Idaho Power Grid Operations for Generation Output Limit Control ("GOLC") -see Section 3 Operating Requirements. 2 1.4.5 Local Service The Interconnection Customer is responsible to arrange for local service to their site, as necessary. 1.4. 6 Monitoring Information If the Interconnection Customer requires the ability to monitor information related to the Idaho Power recloser in the generation interconnection package they are required to supply their own communications circuit to the control box. 1.5 Idaho Power Company's Interconnection Facilities Idaho Power will install a standard generation interconnection package on the existing distribution feeder (COVR-012) on private property southeast of the intersection of E. 3800 N. and N. 1700 E. in Twin Falls County, ID. See the attached work order maps (WO 27328106, sheet 1 of2) for details. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-311 C line protection relay. The relay will be located in a pole mounted enclosure and will also contain a test switch (TS4), SLSS, modems, isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer on top of a vault. Conduit and underground cables will be installed from the interconnection package to padmounted transformer. Protective posts will be installed to protect the ground mounted equipment from damage. A 2" conduit will be installed alongside the underground primary to facilitate information exchange to the customer about the recloser if desired. (The Interconnection Customer is responsible for providing and installing the appropriate cable.) 1.6 Facility Estimated Cost: The following good faith estimates are provided in 2011 dollars: Interconnection Facilities: ,_,.,,. .... ~ ...... , ________ _ Overhe~~. Generation Interconnectio~ Packa-""g_e --------1-IP_C _______ , _____ g OO,OQ_O Underground E uipment and 1500 kV ~ J ransformer .. _ ···-IPC $70,000 SUBTOTAL $270,000] ---- .ee Section 6for the Project (]_rand Tot_a_l _______ _.___ _______ .. __ ._ 3 2. Milestones Commissioning Complete TBD by seller Commercial Operation Date These milestone dates assume that material can be procured and labor resources are available. Additionally, any permitting issues outside the immediate control of Idaho Power could also influence the Commercial eration Date. 3. Operating Requirements The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and requirements for harmonic Control in Electrical Power Systems or any subsequent standards as they may be updated from time to time. Voltage flicker at startup and during operation must be limited to less than 5% as measured at the Interconnection Point. The Project will be subject to reductions directed by Idaho Power Grid Operations during transmission system contingencies and other reliability events. When these conditions occur, the Project will be subject to Generator Output Limit Control ("GOLC") and will have equipment capable of receiving an analog setpoint via DNP 3.0 from Idaho Power for GOLC. Generator Output Limit Control will be a setpoint from Idaho Power to the Project indicating maximum output allowed. The Project must be capable of riding through faults on adjacent section of the power system without tripping due to low voltage. It has been determined, through study, that the Project must be capable of remaining interconnected for any single phase voltage as low as 0.7 PU for 30 cycles, and for all three phase voltages as low as 0.8 PU for 30 cycles. Interconnection Customer will be able to modify power plant facilities on the Interconnection Customer side of the Interconnection Point with no impact upon the operation of the transmission or distribution system whenever the generation facilities are electrically isolated from the system and a terminal clearance is issued by Idaho Power Company's Grid Operator. 4. Reactive Power The Project must be controlled to operate as a V Ar neutral system with a ± 300 kVAr operating band. 4 5. Upgrades 5.1 Distribution Upgrades Idaho Power will upgrade the existing distribution feeder (COVR-012) along E. 3550 N. from the Clover Substation (approximately N. 1950 E.) west toN. 1700 E. The new conductor will be 336.4 All Aluminum (336AAC) and will require new support structures to accommodate the larger wire. Additionally, an existing fixed type capacitor bank on the feeder will be upgraded. In order to avoid high voltage on the feeder during minimum load situations, the capacitor must have automatic controls in order to switch on and off as necessary. 6. Estimated Costs The following good faith estimates are provided in 2011 dollars: Estimated Cost: I . ~hieihnt.t0·,~ . .. I.; • ·. ~€}; oC.'•t7illi:i I • ·,.~·l~i·i:·.@i.a~@ffi~~"~ 0 I o'• '0'' ~ ' ...... •, . n erconnec ton actttes rom sec ton . : ~--· ll t t F, lt (fi t 1 6) Overhead Generation Interconnection Package ..... ,_ .. ~c -$200,000 r-.,___ . .,_ ·- Underground Equipment and 1500 kVA Transfo!iller IPC $70,000 ........... , .. _ TOTAL $2702000 l , ... ,_ .... __ ,.,, '-•·-·--· Up_g_rades to Distribution: Reconductor Approximately 2.5 Miles to 336 AAC IPC $325,000 Upgrade C69 Capacitor IPC $30,000 TOTAL! $355,00~ .,,,._, __ . GRAND TOTAL $625,000 Note Regarding Transmission Service: This Facility Study is a Network Resource Interconnection Facility Study. This study identifies the facilities necessary to integrate the Generating Facility into Idaho Power's network to serve load within Idaho Power's balancing area. Network Resource Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery. 5 I ' E D ~ ~ ~ c ~ ~ . i I ~ I ? 5 B ; ! I i ~ ! ~ ~ CO V R 01 2 12 . 5 k V o/ - - - - - - - - - -- ~- - - - - - -- -- - - 3 z I BY IP C O I I BY OW N E R I I I ' r ' .. ; - l i e __ . ,,, , _ ' , _ , , -- - - , I ' :- ~ - I ' ! i ,., 1 - i : i ' ~ ' ' 1 il J . ' r n ""' L~ -l- 1 j i~~--- - - - , r - - - - - - - - - '1 I f .. . . - i ' "' ) ll I 1' ·- - • il I ., ~ L "" ' I " =• I I I ,. -· ,. ~.F. : ! ' - - -- - - G ! l " ' " - - - -- J !I ~ I I I CA l U P I I . l A I I ~~1 !iO C l W C:A T 9 ! P U A J I G l : i 1 2 "" " " " " " ' "" " " " ' " " "" " ' " " ~. l l . f . T O I I PR O J E C T LO C A T I O N · T1 0 S . RI S E . SE C T I O N 21 • .. J8 0 0 NO R T H 17 0 0 EA S T , TW I N FA L L S CO U N T Y , ID A H O AL L O W E D CA P A C I TY BY CO N T R A C T : __ _ KV A ~ 1 REV l S·!ON t- Jl -'!G i :. . ... 1. . - ~ l ... . ict " ~~ · Fc r m 1 Dai r y :J i ; o t . . , , tt O U 1Jim O "" ~· f. - ~L r , r k ! ' : ' E D ~ ~r . , ... . T_ . _ l.n " " " U." ' "'- - .... . t, . · u t __ _ ;.; , . u n [ t , . . ., . ., __ ... . ;., . . , .. ,, .. "'. -­ .. . ,. ~.~ 1 " 114 1 > 1 -- - - a ~: : . ~ ;U ~ - 1 t. ... l:\ ' ; - - - f~ \ i l : : : O [ f -- - lu ~~ N'o! . 2'» 1 17 1t,1 1 !! U t R U < C E - OI I A W D< G~ ~ Q- 6 2 1 6 1-1,2 J-- - - 1 ~6 l 1 t l -( 1 -l ) ~ 60:: s;; : : J t ) I A ~ CCilT R O C S0£ 1 U o T I C S f: : SW A G E R FA R M S DA I R Y DIG E S T E R ~ - IN T E R C O N N E C T I O N ~ I ~ = SI N G L E LI N E 6 L IN SE R V I C E BY t.C A Y 20 1 1 1- - ll A I O PO ' I I ! l l CO I F A H ~ BO I St . ID A M O k ~ SC A L E : ~E OA . T t : 6- 2 1 - 1 0 ~ ~ "" " 'P O I ! O ' o m I 21 D- 6 2 7 9 0 ~ I . I 2 ,: "- •. ?" 1 1 fs• r . 1 I 01 ; " -- - -- -- -- - - ; - -- -- -- -- -- - ' 3 ~ 5 ~ .· BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 44 Clark, Danielle from: ent: ro: Leslie White [lwhite@exergydevelopment.com] Tuesday, February 28, 2012 12:47 PM Bishop, Rowena Cc: Hackett, Eric Subject: RE: Swager Farms-Gl 307 Hello Rowena, I cannot as of yet confirm inservice dates but I appreciate knowing that construction is dependent upon receipt of funds from Exergy. James will be meeting with our technology provider within the next two weeks. I should be able to extract the pertinent data to provide you with inservice dates at that point. Thanks, Leslie Leslie White 802 W Bannock, 12th Floor Boise, 10 83702 Office: 208.336.9793 1 Mobile: 208.890.4660 www.exergydevelopment.com This electronic or printed document contains infonnation which (a) may be LEGALLY PRIVILEGED, PROPRIETARY IN NATURE, OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) named above. If the reader of this message is not the intended recipient, or the employee or agent responsible to deliver it to the intended recipient. you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. If you l1ave received this communication in error, please immediately notify us by telephone, and return the original message to us at the above email address. Thank you. From: Bishop, Rowena [mailto:RBishop@idahopower.com] Sent: Friday, February 24, 2012 2:51 PM To: Leslie White Cc: Hackett, Eric Subject: RE: Swager Farms-GI 307 Leslie, Please give me a call next week so we can finalize the milestones and determine your inservice date. Note that construction may not begin until Idaho Power receives funding. Thank you. Rowena Bishop Oyerations .Jtna{yst Interchange Oyerations -cliq 4 'Ext. 388-2658 From: Bishop, Rowena Sent: Wednesday, February 15, 2012 11:54 AM To: 'Leslie White' ;C.c: Hackett, Eric Subject: RE: Swager Farms-timelines Hi Leslie, 1 Just checking on you? Please let us know what your intended in service date is as soon as possible. thx! Rowena Bishop Oyerations .:A.na[yst Intercfiange Oyerations -cfiq 4 'Ext. 388-2658 From: Bishop, Rowena Sent: Monday, February 06, 2012 3:08PM To: 'Leslie White' Cc: Hackett, Eric Subject: Swager Farms-timelines Hi Leslie, I am ready to offer a Draft GIA for Swager Farms. Please review this milestone table and let us know when you want to be in service so that we can proceed. Thank you. Critical milestones and responsibility as agreed to by the Parties: --:·,:~~!:I •,, __ ·: ', ,·,,;· \ 0 '1 .. \~ ®:.."&1. . . : '. . . ; . . . 6mos(per FSR) 1 mo Provided by Customer Rowena 'Ext. 2658 i~(t~cjol't:ifjQ : ' ·1 '.'."'·".-" '' '.~•·i~-;.•, · . •.· .•. ·. ''/' ,_ ""'',· --~:~~.:',f'i ·,~I.;·. .-·. '• -,.._ :,.. _.., t,_,:..,, ~ , ,.. • \', • 0 • • ' ' J • ' ~ , I, 1, , , • • p, \o •; ~-, • ,-' • •• ' j~··", . 't'ii''l"'"'';~_t~;;:··."····· ··,:<·._,,, ... 1 ... :. '/ ·-•• \:•:,,· '.--~·,·~·;·. J"l.'. _l~:;·: oF'•'•' \, t-,2 '...... .., ... ~!_•~ ',l o I ,~'' 'r• ·"='· ,'?'.:·1!4, ~· I r•.,, '-o Seller E&P funding received by IPCO $XXX Seller Remaining Balance received by IPCO $XXX Seller Customer GOLC ready to connect & customer telecomm requirements are complete ~PCO IPCO Construction Complete IJPCO IPCO Commissioning Complete PCO Project Leader issues Construction Complete Letter Seller Customer testing begins '$eller Customer's requested In-Service Date This transmission may contain information that is privileged, confidential and/or exempt from disclosure under applicable law. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution, or u'se of the information contained herein (including any reliance thereon) is STRICTLY PROHIBITED, If you received this transmission in error, please immediately contact the sender and destroy the material in its entirety, whether in electronic or hard copy fonnat. Thank you. 2 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 45 Leslie White Exergy Development Group of Idaho 802 W Bannock, Suite 1200 Boise, ID 83702 Re: Swager Farms Project-GI# 307 Dear Leslie: March 22, 2012 IDAHO POWER® An IDA CORP Company Via emaiVCertified 70102780000090951588 Attached please find a copy of the final Facility Study Report (FSR) dated January 25, 2012 and a draft Generator Interconnection Agreement (GIA) for your Generator Interconnection project. The GIA is part of Idaho Power Company's Rate Schedule 72 tariff approved by the Idaho Public Utilities Commission (IPUC). The IPUC has the authority to review and modify these schedules periodically. You may view the most current tariff at Idaho Power's website: httpi'l/Www.idahop.awer~comlabeutus/regufatotvihf6/tMiffs.aS'fi The GIA Attaclunents are based on the Facility Study Report. Please review the GIA Attaclunents to make sure they are comprehensive and accurate and advise me of any changes as soon as possible. Although the preferred method of funding is full payment upfront; payment arrangements may be requested. If you have not already done so, please contact Aubrae Sloan (208-388-5697), Operations ,Finance_at your earliest c_onyenience to discuss Idaho Power's credit requirements for construction funding. Orice we receive funding, or the credit requirement is met, we can proceed with construction of the project. The actual construction and labor charges will be reconciled approximately 90 days subsequent to project completion. Under the Generator Interconnection process, the following items must be provided to me on or before execution of the GIA: 1. Your requested in service date to complete Attaclunent 3 of the GIA. 2.Insurance certification pursuant to Section 7 of the GIA (certificate, 1 endorsement for Additional insured, and 1 for the cancellation notice) 3.Financial arrangements approved by Idaho Power credit department, or full payment for construction Failure to submit all of the requested items above by April 23, 2012 will cause your Generator Iriterconnection request to have been deemed withdrawn and terminated. Please contact me at your earliest convenience with any questions. Encl: Final Facility Study Report draft GIA for Swager Farms Project# 307 Cc: (via email) Eric Hackett, Project Leader/IPC Rich Bauer/IPC Aubrae Sloan/IPC Sincerely, ~L,~ Josh Harris Operations Analyst JHarris@idahopower.com P.O. Box 70 (83707) 1221 W. Idaho 5t. Boise. ID 83702 Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29 Tariff No. 101 March 22, 2012 GENERATOR INTERCONNECTION AGREEMENT Schedule 72 SWAGER FARMS DAIRY DIGESTER PROJECT 1.2MW Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 TABLE OF CONTENTS RECITALS .............................................................................................................................................. 1 AGREEMENTS ...................................................................................................................................... 1 1. Capitalized Terms ................................................................................................................ 1 2. Terms and Conditions .......................................................................................................... 1 3. This Agreement is not an agreement to purchase Seller's power ......................................... 1 4. Attachments ......................................................................................................................... 1 5. Effective Date. Term. Termination and Disconnection .......................................................... 1 5. 1 Term of Agreement. ............................................................................................................. 2 5.2 Termination .......................................................................... , ............................................... 2 5.3 Temporary Disconnection ................................................................................................... 2 6. Assignment. LiabilitY. Indemnity, Force majeure. Consequential Damages and Default ....... 5 7. Insurance ............................................................................................................................. 7 8. Miscellaneous ............................................................................... , ...................................... 7 9. Notices ................................................................................................................................. 8 10. Signatures ............................................................................................................................ 9 Attachment 1 ........................................................................................... Error! Bookmark not defined. Attachment 2 ........................................................................................... Error! Bookmark not defined. Attachment 3 ......................................................................................... ,.Error! Bookmark not defined. Attachment 4 ........................................................................................... Error! Bookmark not defined. Attachment 5 ........................................................................................... Error! Bookmark not defined. Attachment 6 ......................................................................... : ................ Error! Bookmark not defined. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 9 This Generator Interconnection Agreement ("Agreement") under Idaho Power Company's Schedule 72 is effective as of the day of , 2012 between -------------' ("Seller" or "The Project") and Idaho Power Company -Delivery ("Company", or "Transmission Owner"). RECITALS A. Seller will own or operate a Generation Facility that qualifies for service under Idaho Power's Commission-approved Schedule 72 and any successor schedule. B. The Generation Facility covered by this Agreement is more particularly described in Attachment 1. AGREEMENTS 1. Capitalized Terms Capitalized terms used herein shall have the same meanings as defined in Schedule 72 or in the body of this Agreement. 2. Terms and Conditions This Agreement and Schedule 72 provide the rates, charges, terms and conditions under which the Seller's Generation Facility will interconnect with, and operate in parallel with, the Company's transmission/distribution system. Terms defined in Schedule 72 will have the same defined meaning in this Agreement. If there is any conflict between the terms of this Agreement and Schedule 72, Schedule 72 shall prevail. 3. This Agreement is not an agreement to purchase Seller's power. Purchase of Seller's power and other services that Seller may require will be covered under separate agreements. Nothing in this Agreement is intended to affect any other agreement between the Company and Seller. 4. Attachments Attached to this Agreement and included by reference are the following: Attachment 1 -Description and Costs of the Generation Facility, Interconnection Facilities, and Metering Equipment. Attachment 2 ~ One-line Diagram Depicting the Generation Facility, Interconnection Facilities, Metering Equipment and Upgrades. Attachment 3-Milestones For Interconnecting the Generation Facility. Attachment 4 -Additional Operating Requirements for the Company's Transmission System Needed to Support the Seller's Generation Facility. Attachment 5-Reactive Power. Attachment 6 -Description of Upgrades required to integrate the Generation Facility and Best Estimate of Upgrade Costs. 5. Effective Date. Term. Termination and Disconnection. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 2 of 9 5.1 Term of Agreement. Unless terminated earlier in accordance with the provisions of this Agreement, this Agreement shall become effective on the date specified above and remain effective as long as Seller's Generation Facility is eligible for service under Schedule 72. 5.2 Termination. 5. 2. 1 Seller may voluntarily terminate this Agreement upon expiration or termination of an agreement to sell power to the Company. 5.2.2 After a Default, either Party may terminate this Agreement pursuant to Section 6.5. 5. 2. 3 Upon termination or expiration of this Agreement, the Seller's Generation Facility will be disconnected from the Company's transmission/distribution system. The termination or expiration of this Agreement shall not relieve either Party of its liabilities and obligations, owed or continuing at the time of the termination. The provisions of this Section shall survive termination or expiration of this Agreement. 5.3 Temporary Disconnection. Temporary disconnection shall continue only for so long as reasonably necessary under "Good Utility Pr-actice." Good Utility Practice means any of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, pr any of the practices, methods and acts which, in the exercise of reasonable judgment In light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region. Good Utility Practice includes compliance with WECC or NERC requirements. Payment of lost revenue resulting from temporary disconnection shall be governed by the power purchase agreement. 5. 3. 1 Emergency Conditions. "Emergency Condition" means a condition or situation: (1) that ;n the judgrrii:mt of the Party making the claim is imminently likely to endanger life or property; or (2) that, in the case of the Company, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to the Company's transmission/distribution system, the Company's Interconnection Facilities or the equipment of the Company's customers; or (3) that, in the case of the Seller, is imminently likely (as determined in a non­ discriminatory manner) to cause a material adverse effect on the reliability and security of, or damage to, the Generation Facility or the Seller's Interconnection Facilities. Under Emergency Conditions, either the Company or the Seller may immediately suspend interconnection service and temporarily disconnect the Generation Facility. The Company shalf notify the Seller promptly when it becomes aware of an Emergency Condition that may reasonably be expected to affect the Seller's operation of the Generation Facility. The Seller shall notify the Company promptly when it becomes aware of an Emergency Condition that may reasonably be expected to affect the Company's equipment or service to the Company's customers. To the extent information is known, the notification shall describe the Emergency Condition, the extent of the damage or deficiency, the expected effect on the operation of both Parties' facilities and operations, its anticipated duration, and the necessary corrective action. 5.3.2 Routine Maintenance, Construction, and Repair. The Company may interrupt interconnection service or curtail the output of the Seller's Generation Facility Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 3 of 9 and temporarily disconnect the Generation Facility from the Company's transmission/distribution system when necessary for routine maintenance, construction, and repairs on the Company's transmission/distribution system. The Company will make a reasonable attempt to contact the Seller prior to exercising its rights to interrupt interconnection or curtail deliveries from the Seller's Facility. Seller understands that in the case of emergency circumstances, real time operations of the electrical system, and/or unplanned events, the Company may not be able to provide notice to the Seller prior to interruption, curtailment or reduction of electrical energy deliveries to the Company. The Company shall use reasonable efforts to coordinate such reduction or temporary disconnection with the Seller. 5.3.3 Scheduled Maintenance. On or before January 31 of each calendar year, Seller shall submit a written proposed maintenance schedule of significant Facility maintenance for that calendar year and the Company and Seller shall mutually agree as to the acceptability of the proposed schedule. The Parties determination as to the acceptability of the Seller's timetable for scheduled maintenance will take into consideration Good Utility Practices, Idaho Power system requirements and the Seller's preferred schedule. Neither Party shall unreasonably withhold acceptance of the proposed maintenance schedule. 5. 3. 4. Maintenance Coordination. The Seller and the Company shall, to the extent practical, coordinate their respective transmission/distribution system and Generation Facility maintenance schedules such that they occur simultaneously. Seller shall provide and maintain adequate protective equipment sufficient to prevent damage to the Generation Facility and Seller-furnished Interconnection Facilities. In some cases, some of Seller's protective relays will provide back-up protection for Idaho Power's facilities. In that event, Idaho Power will test such relays annually and Seller will pay the actual cost of such annual testing. 5.3.5 Forced Outages. During any forced outage, the Company may suspend interconnection service to effect immediate repairs on the Company's transmission/distribution system. The Company shall use reasonable efforts to provide the Seller with prior notice. If prior notice is not given, the Company shall, upon request, provide the Seller written documentation after the fact explaining the circumstances of the disconnection. 5. 3. 6 Adverse Operating Effects. The Company shall notify the Seller as soon as practicable if, based on Good Utility Practice, operation of the Seller's Generation Facility may cause disruption or deterioration of service to other customers served from the same electric system, or if operating the Generation Facility could cause damage to the Company's transmission/distribution system or other affected systems. Supporting documentation used to reach the decision to disconnect shall be provided to the Seller upon request. If, after notice, the Seller fails to remedy the adverse operating effect within a reasonable time, the Company may disconnect the Generation Facility. The Company shall provide the Seller with reasonable notice of such disconnection, unless the provisions of Article 5. 3. 1 apply. 5. 3. 7 Modification of the Generation Facility. The Seller must receive written authorization from the Company before making any change to the Generation Facility that may have a material impact on the safety or reliability of the Company's transmission/distribution system. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Seller makes such modification without the Company's prior written authorization, the latter shall have the right to temporarily disconnect the Generation Facility. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 4 of 9 5. 3. 8 Reconnection. The Parties shall cooperate with each other to restore the Generation Facility, Interconnection Facilities, and the Company's transmission/distribution system to their normal operating state as soon as reasonably practicable following a temporary disconnection. 5.3.9 Voltage Levels. Seller, in accordance with Good Utility Practices, shall minimize voltage fluctuations and maintain voltage levels acceptable to Idaho Power. Idaho Power may, in accordance with Good Utility Practices, upon one hundred eighty (180) days' notice to the Seller, change its nominal operatiRg voltage level by more than ten percent (10%) at the Point of Delivery, in which ca~e Seller shall modify, at Idaho Power's expense, Seller's equipment as necessary to accommodate the modified nominal operating voltage level. 5. 4 Land Rights. 5. 4,1 Seller to Provide Access. Seller hereby grants to Idaho Power for the term of this Agreement all necessary Fights-of-way and easements. to install, operate, maintain, replace, and remove Idaho Power's Metering Equipment, Interconnection Equipment, Disconnection Equipment, Protection EtjtJipment and other Special Facilities necessary or useful to this Agreement, including adequate and continuing access rights on property of Seller. Seller warrants that it has procured sufficient easements and rights-of-way from third p(;!rlies SQ as to provide Idaho Power with the access described above. All documents graating such easements or rights-of-way shall be subject to Idaho Power's approval and in r:.ecordable form. 5.4.2 Use of Public Rights-of-Way. The Parties agree that it is necessary to avoid the adv.erse. environmental and operating impacts that would occur as a result of duplicate electric lines being constructed in close proximity. Therefore, subject to Idaho Power'_s compliance with Paragraph 5. 4.4, Seller agrees that should Seller seek and receive from any local, state or federal governmental body the right to erect, construct and maintain Seller-ft:Jmished Interconnection Facilities upon, along and over any and all public roads, streets and highways, then the use by Seller of such public right-of-way shall be subordinate to any fu1ure use by Idaho Power of such public right-of-way for construction and/or maintenance of electric distribution and transmission facilities and Idaho Power may -claim use of such public right-of-way for such purposes at any time. Except as required by Paragraph 5. 4. 4, Idaho Power shall not be required to compensate Seller for exercising its rights under this Paragraph 5. 4. 2. 5.4.3 Joint Use of Facilities. Subject to Idaho Power's compliance with Paragraph 15.4.4, Idaho Power may use and attach its distribution and/or transmission facilities to Seller's Interconnection Facilities, may reconstruct Seller's Interconnection Facilities to accommodate Idaho Power's usage or Idaho Power may construct its own distribution or transmission facilities along, over and above any public right-of-way acquired from Seller pursuant to Paragraph 5.4. 2, attaching Seller's Interconnection Facilities to such newly constructed facilities. Except as required by Paragraph 5. 4.4, Idaho Power shall not be required to compensate Seller for exercising its rights under this Paragraph 5.4.3. 5. 4. 4 Conditions of Use. It is the intention of the Parties that the Seller be left in substantially the same condition, both financially and electrically, as Seller existed prior to Idaho Power's exercising its rights under this Paragraph 5.4. Therefore, the Parties agree that the exercise by Idaho Power of any of the rights enumerated in Paragraphs Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 5 of 9 5.4.2 and 5.4.3 shall: (1) comply with all applicable laws, codes and Good Utility Practices, (2) equitably share the costs of installing, owning and operating jointly used facilities and rights-of-way. If the Parties are unable to agree on the method of apportioning these costs, the dispute will be submitted to the Commission for resolution and the decision of the Commission will be binding on the Parties, and (3) shall provide Seller with an interconnection to Idaho Power's system of equal capacity and durability as existed prior to Idaho Power exercising its rights under this Paragraph 5.4. 6. Assignment. Liability, Indemnity, Force maieure. Consequential Damages and Default. 6. 1 Assignment. This Agreement may be assigned by either Party upon twenty-one (21) calendar days prior written notice and opportunity to object by the other Party; provided that: 6. 1. 1 Either Party may assign this Agreement without the consent of the other Party to any affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement. 6.1.2 The Seller shall have the right to contingently assign this Agreement, without the consent of the Company, for collateral 'Security purposes to aid in providing financing for the Generation Facility, provided that the Seller will promptly notify the Company of any such contingent assignment. 6. 1. 3 Any attempted assignment that violates this article is void and ineffective. Assignment shall not relieve a Party of its obligations, nor shall a Party's obligations be enlarged, in whole or in part, by reason thereof An assignee is responsible for meeting the same financial, credit, and insurance obligations as the Seller. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed. 6. 2 Limitation of Liability. Each Party's liability to the other Party for any loss, cost, claim, injury, liability, or expense, including reasonable attorney's fees, relating to or arising from any act or omission in its performance of this Agreement, shall be limited to the amount of direct damage actually incurred. In no event shall either Party be liable to the other Party for any indirect, special, consequential, or punitive damages, except as authorized by this Agreement. 6.3 Indemnity. 6. 3. 1 This provision protects each Party from liability incurred to third parties as a result of carrying out the provisions of this Agreement. Liability under this provision is exempt from the genera/limitations on liability found in Article 6. 2. 6. 3. 2 The Parties shall at all times indemnify, defend, and hold the other Party harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's action or failure to meet its obligations under this Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party. 6. 3. 3 If an indemnified person is entitled to indemnification under this article as a result of a claim by a third party, and the indemnifying Party fails, after notice and reasonable opportunity to proceed under this article, to assume the defense of such claim, such indemnified person may at the expense of the indemnifying Party contest, Idaho Power Company Generator Interconnection Agreement # 307 I.P.U.C. No. 29, Tariff No. 101 Page 6 of 9 settle or consent to the entry of any judgment with respect to, or pay in full, such claim. Failure to defend is a Material Breach. 6. 3. 4 If an indemnifying party is obligated to indemnify and hold any indemnified person harmless under this article, the amount owing to the indemnified person shall be the amount of such indemnified person's actual loss, net of any insurance or other recovery. 6.3.5 Promptly after receipt by an indemnified person of any claim or notice of the commencement of any action or administrative or legal proceeding or investigation as to which the indemnity provided for in this article may apply, the indemnified person shall notify the indemnifying party of such fact. Any failure of or delay in such notification shall be a Material Breach and shall not affect a Party's indemnification obligation unless such failure or delay is materially prejudicial to the indemnifying party. 6.4 Force Majeure. As used in this Agreement, "Force Majeure" or "an event of Force Majeure" means any cause beyond the control of the Seller or of the Company which, despite the exercise of due diligence, such Party is unable to prevent or overcome. Force Majeure includes, but is not limited to, acts of God, fire, floqd, storms, wars, hostilities, civil strife, strikes and other labor disturbances, earthquakes, fires, lightning, epidemics, sabotage, or changes in law or regulation occurring after the Operation Date, which, by the exercise of reasonable foresight such party could not reasonably have been expected to avoid and by the exercise of due diligence, it shall be unable to overcome. If either Party is rendered wholly or in part unable to perform its obligations under this Agreement because of an event of Force Majeure, both Parties shall be excused from whatever performance is affected by the event of Force Majeure, provided that: (1) The non-performing Party shall, as soon as is reasonably possible after the occurrence of the Force Majeure, give the other Party written notice describing the particulars of the occurrence. (2) The suspension of performance shall be of no greater scope and of no longer duration than is required by the event of Force Majeure. (3) No obligations of either Party which arose before the occurrence causing the suspension of performance and which could and should have been fully performed before such occurrence shall be excused as a result of such occurrence. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 7 of 9 6. 5 Default and Material Breaches. 6. 5. 1 Defaults. If either Party fails to perform any of the terms or conditions of this Agreement (a "Default" or an "Event of Default'?, the nondefaulting Party shall cause notice in writing to be given to the defaulting Party, specifying the manner in which such default occurred. If the defaulting Party shall fail to cure such Default within the sixty (60) days after service of such notice, or if the defaulting Party reasonably demonstrates to the other Party that the Default can be cured within a commercially reasonable time but not within such sixty (60) day period and then fails to diligently pursue such cure, then, the nondefau/ting Party may, at its option, terminate this Agreement and/or pursue its legal or equitable remedies. 6. 5. 2 Material Breaches. The notice and cure provisions in Paragraph 6. 6. 1 do not apply to Defaults identified in this Agreement as Material Breaches. Material Breaches must be cured as expeditiously as possible following occurrence of the breach. 7. Insurance. During the term of this Agreement, Seller shall secure and continuously carry the following insurance coverage: 7. 1 Comprehensive General Liability Insurance for both bodily injury and property damage with limits equal to $1,000,000, each occurrence, combined single limit. The deductible for such insurance shall be consistent with current Insurance Industry Utility practices for similar property. 7. 2 The above insurance coverage shall be placed with an insurance company with an A.M. Best Company rating of A-or better and shall include: (a) An endorsement naming Idaho Power as an additional insured and loss payee as applicable; and (b) A provision stating that such policy shall not be canceled or the limits of liability reduced without sixty (60) days' prior written notice to Idaho Power. 7. 3 Seller to Provide Certificate of Insurance. As required in Paragraph 7 herein and annually thereafter, Seller shall furnish the Company a certificate of insurance, together with the endorsements required therein, evidencing the coverage as set forth above. 7. 4 Seller to Notify Idaho Power of Loss of Coverage -If the insurance coverage required by Paragraph 7. 1 shall/apse for any reason, Seller will immediately notify Idaho Power in writing. The notice will advise Idaho Power of the specific reason for the lapse and the steps Seller is taking to reinstate the coverage. Failure to provide this notice and to expeditiously reinstate or replace the coverage will constitute grounds for a temporary disconnection under Section 5. 3 and will be a Material Breach. 8. Miscellaneous. 8. 1 Governing Law. The validity, interpretation and enforcement of this Agreement and each of its provisions shall be governed by the Jaws of the state of Idaho without regard to its conflicts of law principles. 8.2 Salvage. No later than sixty (60) days after the termination or expiration of this Agreement, Idaho Power will prepare and forward to Seller an estimate of the remaining value Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 8 of 9 of those Idaho Power furnished Interconnection Facilities as required under Schedule 72 and/or described in this Agreement, less the cost of removal and transfer to Idaho Power's nearest warehouse, if the Interconnection Facilities will be removed. If Seller elects not to obtain ownership of the Interconnection Facilities but instead wishes that Idaho Power reimburse the Seller for said Facilities the Seller may invoice Idaho Power for the net salvage value as estimated by Idaho Power and Idaho Power shall pay such amount to Seller within thirty (30) days after receipt of the invoice. Seller shall have the right to offset the invoice amount against any present or future payments due Idaho Power. 9. Notices. 9.1 General. Unless otherwise provided in this Agreement, any written notice, demand, or request required or authorized in connection with this Agreement ("Notice") shall be deemed properly given if delivered in person, delivered by recognized national currier service, or sent by first class mail, postage prepaid, to the person specified below: If to the Seller: If to the Company: Idaho Power Company -Delivery Attention: Operations Manager 1221 W. Idaho Street Boise: Idaho 83702 Phone: 208-388-5669 Fax: 208-388-5504 9.2 Billing and Payment. Billings and payments shall be sent to the addresses set out below: Seller: ------------------------------------------------- Attention: ----------------------------------------------------- Address: ________ ~---------------------=---------------------City: _________________ ~State: ___ _cZip: ---------- Phone: Fax: Idaho Power Company-Delivery Attention: Corporate Cashier PO Box 447 Salt Lake City Utah 84110-044 7 --------------- Phone: 208-388-5697 email : asloan@idahopower.com 9.3 Designated Operating Representative. The Parties may also designate operating representatives to conduct the communications which may be necessary or convenient for the administration of this Agreement. This person will also serve as the point of contact with respect to operations and maintenance of the Party's facilities. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Seller's Operating Representative: Seller:-----------------------­Attention: Page 9 of 9 --------------------------Address: ____________________________ _ City: __________ State: ____ Zip: ____ _ Phone: Fax: -------- Company's Operating Representative: Idaho Power Company -Delivery Attention: Outage Coordinator-System/Regional Dispatch 1221 W. Idaho Street Boise, Idaho 83702 Phone: 208-388-2633, 388-5125, or 388-5175 during regtllar ltlusiness hours (after hours-Regional Dispatch Southern Region 208-388-5190 9.5 Changes to the Notice Information. Either Party may change this information by giving five (5) Business Days written notice pri0r to the effective date of the Ghange. 10. Signatures. IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their respective duly authorized representatives. For the Seller Name: Date: For the Company Name: Title: MC~nager, Grid Operations -Idaho Power Company, Delivery Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 1 of 3 Attachment 1 Description and Costs of the Generation Facilitv. Interconnection Facilities and Metering Equipment Type of Interconnection Service: Full Output: Nominal Delivery Voltage: Interconnection Details Studied as an Idaho Power Network Resource under PURPA 1.2 MW 12.5 kV General Facility Description The proposed project will consist of Idaho Power's standard overhead generation interconnection package including an overhead recloser, metering package, local service power transformer, disconnect switches, and a relay/control box. Additionally, one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer will be installed, including the associated underground cabling and vaults. The project is located in Twim Falls County, Idaho and connects to the 12.5 kV system on Idaho Power Company's Clover (COVR-012) distribution line. The total project output is 1.2 MW. Interconnection Point The Interconnection Point for the Swager Farms Dairy !Digester Project will be the low-side bushings on the padmounted transformer (SW1). The project's location is in T10S R15E Section 21 of Twin Falls County, Idaho. A drawing identifying the Point of Interconnection is included as Attachment 2. The Point of Change of Ownership will be the low-side bushings on the padmounted transformer (SW1). Seller's Interconnection Facilities The Seller will install generators, low-side disconnect switches, all wiring and conduit between the generators and the padmounted transformer, appropriate groundi171g measures, and associated auxiliary equipment. Seller will bui,ld underground facilities to the Point of Change of Ownership for the generator facility. The low-side disconnect switch snail be as specified or as determined by mutual agreement and be readily accessible, operable, and lockable by Idaho Power personnel at all times. The Seller will install equipment to receive signals from Idaho Power Company Grid Operations for Generator Output Limit Control ("GOLC") -see Attachment 4 Operating Requirements. The Seller will provide phone service to IPCo's generator interconnect package as described in Telecommunications below. The Seller will provide a DNP 3.0 serial data connection to the local Idaho Power Company SCADA RTU when any communication with Seller-owned and maintained equipment is required for GOLC, voltage control or other plant monitoring or control. Preliminary points lists and functional description were provided to the Seller in the Facility Study Report. All interconnection equipment electrically located on the generator side of the Point of Change Ownership shall be owned and maintained by the Seller. Other Facilities Provided by Seller Telecommunications In addition to communication circuits that may be needed by the Seller, the Seller shall provide the following communication circuits for Idaho Power's use: 1. One POTS (Plain Old Telephone Service) dial-up circuit for revenue metering at the generation interconnection site. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U .C. No. 29, Tariff No. 101 Page 2 of 3 2. One DDS (Digital Data Service) circuit guaranteed minimum data rate of 19,200 bits per second for SCADA between the generation interconnection site and Idaho Power Company's Twin Falls Service Building (273 Blue Lakes Blvd. S., Twin Falls, Idaho). The Seller is required to coordinate with the local communications provider to provide the communications circuits and pay the associated monthly charges. The communication circuits will need to be installed and operational prior to generating into Idaho Power system. Note that installation by the local communications provider may take several months and should be ordered in advance to avoid delaying the project. If the communication circuit types listed above are not available at the site by the local communications provider, the Seller shall confer with Idaho Power. If high voltage protection is required by the local communications provider for the incoming cable, the high voltage protection assembly shall be engineered and supplied by the Seller. Options are available for indoor or outdoor mounting. The high voltage protection assembly shall be located in a manner that provides Idaho Power 24-hour access to the assembly for communications trouble-shooting of Idaho Power owned equipment. Ground Fault Equipment The customer will install ground fault limiting equipmenHhat will limit the zero sequence fault current to 20 amps at the Interconnection Point. Easements The Seller will provide to IPCO a surveyed (Metes & Bounds} legal description along with exhibit map for IPCO's facilities. After the legal description has been delivered to IPCO for review, IPCO will supply to the Seller a completed IPCO easement for signature by the land owner of record. Once the signatures have been secured, the Seller will retum the signed easement to IPCO for recording. IPCO construction will not proceed until the appropriate easements are secured. Generator Output Limit Control The Seller will install equipment to receive signals from Idaho Power Grid Operations for Generation Output Limit Control ("GOLC") -see Attachment 4 Operating Requirements. Local Service The Seller is responsible to arrange for local service to their site, as necessary. Idaho Power Company's Interconnection Facilities Idaho Power will install a standard generation interconnection package on the existing distribution feeder (COVR-012) on private prop.erty southeast of the intersection of E. 3800 N. and N. 1700 E. in Twin Falls County, I D. See single line drawing as Attachment 2. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-311 C line protection relay. The relay will be located in a pole mounted enclosure and will also contain a test switch (TS4), SLSS, modems, isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) one 1500 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer on top of a vault. Conduit and underground cables will be installed from the interconnection package to padmounted transformer. Protective posts will be installed to protect the ground mounted equipment from damage. A 2" conduit will be installed alongside the underground primary to facilitate information exchange to the customer about the recloser if desired. (The Interconnection Customer is responsible for providing and installing the appropriate cable.) Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 3 of 3 All interconnection equipment electrically located on the utility side of the Interconnection Point shall be owned, operated, and maintained by Idaho Power. Estimated Cost & Ownership The following good faith estimates are provided in 2011 dollars !overhead Generation Interconnection Packa e lPCO lld"l1~~!g!<:)ll:!1:<:1. §g~J.}P!!lent and 1500 kV A Trans~ormer j1P9_0 __ , SUBTOTAL] L__-=· (See ATTACHMENT 6 ~-,. Pro}ect Grand TotaQj $270,000 .. $200,000 $70,000 Full payment is required up front in accordance with Schedule 72, unless payment arrangements are made in advance with Idaho Power Operations Finance (see Attachment 3). Billing for construction activities will be based upon actual expenditures. Idaho Power Company Generator Interconnection Agreement # 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 2 One-line Diagram Depicting the Small Generation Facility, Interconnection Facilities, Metering Equipment and Upgrades Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 3 Milestones 1. Idaho Power Company agrees only to the Construction timelines under its direct control provided in the Facility Study Report for this Project. 2. These milestones will begin, and the construction schedule referenced below, will only be valid upon receipt of funding in full from the Seller or their authorized third party no later than the date set forth below for such payment. Additionally, failure by Seller to make the required payments as set forth in this Agreement by the date(s) specified below will be a material breach of this Agreement, which may result in any or all of the following: (i) loss of milestone dates and construction schedules set forth below: (ii) immediate termination of this Agreement by Idaho Power; (iii) removal from the generator interconnection queue. Critical milestones and responsibility as agreed to by the Parties·: Customer GOLC ready to connect & customer -rt=t•t=t,...nrnlrnl 1 ______________ , __ 1 ________ ~_n .. !~'~r·~""' ~areco~efete Construction Complete ------------;--------+------~ -------------------------~ Commissioning Complete 1----------------~------~------~ rovided Agreed to by: For the Seller: For the Transmission Provider Idaho Power Company Project Leader issues Const~uction Complete Letter requested In-Service Date --------------------~ Date ____________ _ Date ____________ _ Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No_ 101 Page 1 of 1 Attachment 4 Additional Operating Requirements for the Company's Transmission System and Affected Svstems Needed to Support the Seller's Needs The Company shall also provide requirements that must be met by the Seller prior to initiating parallel operation with the Company's Transmission System. Operating Requirements The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems or any subsequent standards as they may be updated from time to time. Seller will be able to modify power plant facilities on the generator side of the Interconnection Point with no impact upon the operation of the transmission system whenever the generation facilities are electrically isolated from the transmission system and a terminal clearance is issued by Idaho Power Company's Grid Operator. Generator Output Limit Control ("Re-dispatch" or uGOLC'? The Project will be subject to reductions directed by Idaho Power Company Grid Operations during transmission system contingencies and other reliability events. When these conditions occur, the Project will be subject to Generator Output Limit Control ("GOLC") and have equipment capable of receiving signals from Idaho Power for GOLC. Generator Output Limit Control will be a setpoint from Idaho Power to the Project indicating maximum output allowed during transmission contingencies as specified in the Facility Study Report. Low Voltage Ride Through The Project must be capable of riding through faults on adjacent section of the power system without tripping due to low voltage. It has been determined, through study, that the Project must be capable of remaining interconnected for any single phase voltage as low as 0.7 PU for 30 cycles, and for all three phase voltages as low as 0.8 PU for 30 cycles. Ground Fault Equipment The Seller will install transformer configurations that provide a ground source to the transmission system. Idaho Power Company Generator Interconnection Agreement # 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 5 Reactive Power Requirements The project must be controlled to operate as a VAr neutral system with a+/-300 kVAr operating band. Voltage flicker at startup and during operation will be limited to less than 5% as measured at the Interconnection Point. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 6 Comparw's Description of Special Facilities and Upgrades Required to Integrate the Generation Facilitv and Best Estimate of Costs As provided in Schedule 72 this Attachment describes Upgrades, Special Facilities, including Network Upgrades, and provides an itemized best estimate of the cost of the required facilities. Upgrades Distribution Upgrades Idaho Power will upgrade the existing distribution feeder (COVR-012) along E. 3550 N. from the Clover Substation (approximately N. 1950 E.) west to N. 1700 E. The new c0nd~ctor will be 336.4 All Aluminum (336AAC) and will require new support structures to accommodate ·the larger wire. Additionally, an existing fixed type capacitor bank on the feeder will be upgraded. In order to avoid high voltage on the feeder during minimum load situations, the capc:~citor must have automatic controls in order to switch on and off as necessary. f!pgrar._ies_: ___ _ approximate 2.5 mi~es to 336 AAC ____ ____, C69 Capa~it_o_r __ -----...:., PROJECT GRAND $ BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 46 • Josh Harris Operations Analyst Idaho Power Company 1221 W. Idaho St Boise, 10 83702 Re: Swager Farms Project-Gl #307 Dear Josh, DEVELOPMENT GRO rgy Regarding the Swager Farms GIA our electrical engineers are not able to link the project's obligation to run at unity to Idaho Powers request to update your distribution capabilities referenced in correspondence from Trevor Schultz, dated April 16th. In light of the fact that the requirements and pricing established in the October 25, 2010 draft GIA, were substantially altered we believe it is necessary for Idaho Power to revisit the upgrade requirements specific to the verified capacity of 800 kW. We appreciate the information and the issues Trevor has identified, however, the study cases presented and the type of equipment utilized invoke the following questions: 1. The use of a synchronous generator may increase the voltage stability of the line. 2. Do the regulators enable the steady state voltage without reconductoring? I believe Cases 3 and 4 indicate the regulators fix the·problem. 3. We notice Case 4 is modeled without the capacitors, but if there is the requirement to run at Unity Power Factor, the capacitors may not be intended for flicker control, so why are they in the package? The four cases presented seem to be incongruous with the present requirements, and as James Carkulis pointed out in email correspondence today we intend to commence construction in the 2nd quarter on this project, thus we need to obtain clarity on this issue before signing the GIA. Regards, 4 LL W£& Leslie White President, Exergy New Energy, Biogas Division ~xergy Development Group 802 W Bannock, 1lh ~loor Boise, ID 83702 P 208.336.9793 ~ 208.336.9431 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 47 Small Generator Feasibility Study Agreement Swager Farms Project #307 Feasibility Study Agreement THIS AGREEMENT is made and entered into this _J_day of 1'1aif 2012, by and between £ 't ~ r'J r.; iJe vt../op rn~ ,_/ 6~ J-r d e..."-o , a ----=L=--=L.=C-.=--,-----------­ organized and existing 1under theiaws of the State of Lda..A o , ("Interconnection Customer,") and Idaho Power Company a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission 'Provider each may be. referred to as a "Party," or collectively as the ''Parties." RECITALS WHEREAS, Interconnection Customer is proposing to develop a Small Generating Facility o:r; generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by Interconnection Customer on October 12, 2009; also known as Project #307, and WHEREAS, Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; and WHEREAS, Interconnection Customer has requested the Transmission Provider to perform a feasibility study to assess the feasibility of interconnecting the proposed Small Generating Facility with the Transmission .Provider's Transmission System, and of any Affected Systems; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause to be performed an interconnection feasibility study consistent the standard Small Generator Interconnection Procedures in accordance with the Open Access Transmission Tariff. 3.0 The scope of the feasibility study shall be subject to the assumptions set forth in Attachment A to this Agreement. 4.0 The feasibility study shall be based on the technical information provided by the Interconnection Customer in the Interconne.ction Request, as may be modified as the result of the scoping meeting. The Transmission Provider reserves the right to request additional technical information from the Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the feasibility study and as designated in accordance with the standard Small Generator Interconnection Procedures. If the Interconnection Customer modifies its Interconnection Small Generator Feasibility Study Agreement Swager Farms Project #307 Request, the time to complete the feasibility study may be extended by agreement of the Parties. 5.0 In performing· the study, the Transmission Provider shall·rely, to the extent reasonably practicable, on existing studies of recent vi~1.tage: The Interconnection Customer shall not be charged for such existing studies; however; the Interconnection Customer shall be . responsible for charges associated with any new study or modifications to existing studies that are reasonably necessary to perform the feasibility study. 6.0 The feasibility study report shall provide the following analyses for the purpose of identifying any potential adverse systeni impacts that would result from the interconnection of the Small Generating Facility as proposed: 6.1 Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; 6.2 Initial identification of any thennal overload or voltage limit violations resulting from the interconnection; 6.3 Initial review of grounding requirements and electric system protection; and 6.4 Description and lion-bonding estimated cost of facilities required to interconnect the proposed Small Generating Facility and to address the identified short circuit and power flow issues. 7.0 The feasibility study shall model the impact of the Small Generating Facility regardless of purpose in order to avoid the further expense and interruption of operation for reexamination of feasibility and impacts if the Interconnection Customer later changes the purpose for which the Small Generating Facility is being installed. 8.0 The study shall include the feasibility of any interconnection at a proposed project site where there could be multiple potential Points of Interconnection, as requested by the Interconnection Customer and at the Interconnection Customer's cost. 9.0 In lieu of Feasibility Study deposit, Interconnection Customer agrees that study funds will be drawn from the application fee for the perfonnance of the Interconnection Feasibility Study. Transmission Provider shall charge and Interconnection Customer shall pay the actual costs ofthe Interconnection Feasibility Study. Any difference between the deposit and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate. 10.0 Once the feasibility study is completed, a feasibility study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the Small Generator Feasibility Study Agreement Swager Farms Project #307 feasibility study must be completed and the feasibility study report transmitted within 30 business days of the Interconnection Customer's agreement to conduct a feasibility study. 11.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 12.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees; the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company-Delivery Si~OO: ~-fi:t Printe~~ Signed: __________ _ Printed: ------------------------ Title: ----'--JIIl-----'-"'CU\::..:....:.=..:t<:...,j~c...;e_r _____ _ Title: -------------------------- Date: s/9 I zot z. Date: --------------------------------------------------- Small Generator Feasibility Study Agreement Swager Farms Project #307 Attachment A to Feasibility Study Agreement Assumptions Used in Conducting the Feasibility Study The feasibility study will be based upon the infonnation set forth in the Interconnection Request and agreed upon in the scoping meeting held on October 27, 2009: The Feasibility Study will be completed no later than ~0 Business days after Idaho Power receives the fully executed Interconnection Feasibility Study Agreement, unless any requested study data in NOT received. Interconnection Customer will provide the requested study data as soon as possible on or before the return of the executed Interconnection Feasibility Study Agreem~nt. 1) Designation of Point of Interconnection and configuration to be studied. 2) Designation of alternative Points of Interconnection and cbnfj.gtJ.ration. . . , 1) and 2) are to be completed by the Interconnection Customer. Other assumptions (listed below) are to be provided by the Interconnection Customer and the Transmission Provider. Page 1 of 1 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 48 TS GENERATOR INTERCONNECTION FEASIBILITY STUDY For integration of the proposed SWAGER FARMS DIGESTER PROJECT In TWIN FALLS COUNTY, IDAHO To the IDAHO POWER COMPANY ELECTRICAL SYSTEM For EXERGY The INTERCONNECTION CUSTOMER RE-STUDY REPORT June 1, 2012 Generator Interconnection Feasibility Study General Interconnection Information Station or Date of Total Trans Line Queue Request Location (MW) for POl Original Study: 12.5 kV January 2010 through Clover Re-Study: Twin Falls (COVR) #307 May 2012 County 0.8 substation Short Circuit Analysis Results System Changes Required: DYes [giNo Power Flow Analysis Results System Changes Required: (g!Yes DNo The cost estimates for those upgrades are shown in Table 1 below. Projected In-Service Date 2012 Type of facility (combined cycle, base load, CT, fuel type) Biofue1 Description Estimated Cost Generation Interconnection Protection Package (Includes 12.47 kV recloser, controls, CTs, PTs) $225,000 Total Estimated Cost $225,000 Table 1: Estimated interconnection costs for 0.8 MW project at Swager Farms Good Faith Cost Estimate Interconnection cost estimate for 0.8 MW generator project: $225,000. System Impact Study Required? DYes [gl No This Feasibility Study only addresses the work required to interconnect the Swager Farms digester projects to the Idaho Power system. There are no transmission rights secured for the project until a transmission system request is submitted by the corresponding transmission customer. The required transmission facilities, if any, to support energy transfers will then be determined based on first come first serve basis (queue order). Operating Requirements: Project #307 will be controlled to operate at unity power factor with an operating bandwidth of± 200 kVAR. -1 - BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 49 June 4, 2012 Certified Mail# 70113500000156449143 Leslie White Exergy 802 W Bannock, 121h Floor Boise, ID 83 702 RE: Project# 307-Swager Farms Dear Leslie: An IOACORP Comp~ny Enclosed is the Final Feasibility Study Report for the above-referenced project. The feasibility analysis indicates that modification/addition of some facilities will be required to integrate the network resource capacity addition of your project into the Idaho Power system. Please note, the Feasibility Study alone does not provide any transmission rights nor determines the necessary network upgrades to move the project energy to the load or a point of delivery in our system. Since no SYSTEM IMPACT STUDY is needed, enclosed is a Facility Study Agreement (FSA) for the next phase of the project. In order to proceed, and for your application to remain in the Generator Interconnection study queue, Idaho Power must receive the 2 copies of the signed FSA, the completed Attachments, and the deposit by July 9, 2012, otherwise your application will be deemed withdrawn. The deposit under this FSA is $11,250.00, based on the estimated engineering costs. The submittal should be sent to: Idaho Power Company, Attention: Josh Harris, 1221 West Idaho Street, Boise, ID 83702. Please contact me if you have questions. Sincerely, Daniel Arjona Engineering Leader, T &D Planning 208.3 88.2895 darjona@idahopower .com • Enclosures: Final Feasibility Study Report and FSA for signature (quantity 2) CC (via email): Josh Harris/IPC Orlando Ciniglio/IPC 1221 W. Idaho St. (83702) P.O. Box 70 Boise, ID 83707 Facilities Study Agreement THIS AGREEMENT is made and entered into this __ day of 2012 by and between , a organized and existing under the laws of the State of ("Interconnection Customer,") and Idaho Power Company, a Corporation existing under the laws of the State of Idaho ("Transmission Provider"). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties." RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on October 12, 2009, and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Transmission System; WHEREAS, the Transmission Provider has completed a system impact study and provided the results of said study to the Interconnection Customer; and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the system impact study in accordance with Good Utility Practice to physically and electrically connect the Small Generating Facility with the Transmission Provider's Transmission System. ~OW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause a facilities study consistent with the standard Small Generator Interconnection Procedures to be performed in accordance with the Open Access Transmission Tariff. 3.0 The scope of the facilities study shall be subject to data provided in Attachment A to this Agreement. 4.0 The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions ofthe system impact study(s). The facilities study shall also identify (1) the electrical switching configuration ofthe equipment, including, without limitation, transformer, switchgear, meters, and other station equipment, (2) the nature and estimated cost of the Transmission Provider's Small Generator Facilities Study Agreement - 1 -Swager Farms Project #307 Intercmmection Facilities and Upgrades necessary to accomplish the interconnection, and (3) an estimate of the time required to complete the construction and installation of such facilities. 5.0 The Transmission Provider may propose to group facilities required for more than one Interconnection Customer in order to minimize facilities costs through economies of scale, but any Interconnection Customer may require the installation of facilities required for its own Small Generating Facility if it is willing to pay the costs ofthose facilities. 6.0 A deposit of $11,250.00 is due upon execution of this agreement by the Interconnection customer. 7.0 In cases where Upgrades are required, the facilities study must be completed within 45 Business Days of the receipt of this Agreement. In cases where no Upgrades are necessary, and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 Business Days. 8.0 Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the Interconnection Customer. BatTing unusual circumstances, the facilities study must be completed and the facilities study report transmitted within 30 Business Days of the Interconnection Customer's agreement to conduct a facilities study. 9.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 1 0. 0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Interconnection Customer: Idaho Power Company -Delivery Signed: Signed: ____________ _ Printed Name: Printed Name: ------------- Title: Title: --------------- Date: Date: --------------- Small Generator Facilities Study Agreement -2 -Swager Farms Project #307 Attachment A to Facilities Study Agreement Data to Be Provided by the Interconnection Customer With the Facilities Study Agreement 1. Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT/PT) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps 2. One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station. Number of generation connections: 3. Will an alternate source of auxiliary power be available during CT/PT maintenance? Yes No --- 4. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? Yes No (Please indicate on the one-line diagram). 5. What type of control system or PLC will be located at the Small Generating Facility? 6. What protocol does the control system or PLC use? 7. Please provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines. 8. Physical dimensions ofthe proposed interconnection station: Small Generator Facilities Study Agreement - 3 -Swager Farms Project #307 9. Bus length from generation to interconnection station: 10. Line length from interconnection station to Transmission Provider's Transmission System. 11. Tower number observed in the field. (Painted on tower leg)*: 12. Number of third party easements required for transmission lines*: *To be completed in coordination with Transmission Provider. 13. Is the Small Generating Facility located in Transmission Provider's service area? Yes ___ No ___ IfNo, please provide name oflocal provider: 14. Please provide the following proposed schedule dates: Begin Construction Date: ____________ _ Generator Step-Up Transformers Date: ____________ _ Receive Back Feed Power Generation Testing Date: ____________ _ Commercial Operation Date: ____________ _ Small Generator Facilities Study Agreement - 4 -Swager Farms Project #307 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 50 July 9, 2012 Josh Harris Idaho Power Company 1221 W. Idaho St Boise, ID 83707 RE: FSA Project #307 Dear Josh, y Enclosed is the FSA and the attachment. With regards to our conversation this morning, the Swager account with Idaho Power has a credit balance of $24,093 which will be used to cover the deposit for this FSA and in part to cover the deposit for the FSA associated with project #390, Eagle View Dairy. :JLuJtL Leslie White The Biogas Division of Exergy New Energy Exergy Development Group of Idaho 208-336-9793 lwhite@exergydevelopment.com Enclosures: Completed FSA for project #307 kxergy Development Group 802 W Bannock, l21h r=loor Boise, ID 83702 P 208.336.9793 r= 208.336.9431 Facilities Study Agreement TIDS AGREEMENT is made and entered into this _6th_day of_June 2012 by and between Idaho Development Group of Idaho, a _LLC organized and existing under the laws of the State of _Idaho , (''Interconnection Customer,11) and Idaho Power Company, a Corporation existing under the laws of the State of Idaho ("Transmission Provider11). Interconnection Customer and Transmission Provider each may be referred to as a 11Party, 11 or collectively as the 11Parties.11 RECITALS WHEREAS, the Interconnection Customer is proposing to develop a Small Generating Facility or generating capacity addition to an existing Small Generating Facility consistent with the Interconnection Request completed by the Interconnection Customer on October 12, 2009, and WHEREAS, the Interconnection Customer desires to interconnect the Small Generating Facility with the Transmission Provider's Tmnsmission System; WHEREAS, the Transmission Provider has completed a system impact study and provided the results of said study to the Interconnection Customer; and WHEREAS, the Interconnection Customer has requested the Transmission Provider to perform a facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the system impact study in accordance with Good Utility Practice to physically and electrically connect the Small Generating Facility with the Transmission Provider's Transmission System. NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows: 1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated or the meanings specified in the standard Small Generator Interconnection Procedures. 2.0 The Interconnection Customer elects and the Transmission Provider shall cause a facilities study consistent with the standard Small Generator Interconnection Procedures to be performed in accordance with the Open Access Transmission Tariff. 3.0 The scope of the facilities study shall be subject to data provided in Attachment A to this Agreement. 4.0 The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s). The facilities study shall also identify (1) the electrical switching configuration of the equipment, including, without limitation, transformer, switchgear, meters, and other station equipment, (2) the nature and estimated cost of the Transmission Provider's Small Generator Facilities Study Agreement - 1 -Swager Farms Project #307 Interconnection Facilities and Upgrades necessary to accomplish the interconnection, and (3) an estimate ofthe·time required to complete the construction and installation of such facilities. 5.0 The Transmission Provider may propose to group facilities required for more than one Interconnection Customer in order to minimize facilities costs through economies of scale, but any Interconnection Customer may require the installation of facilities required for its own Small Generating Facility if it is willing to pay the costs of those facilities. 6.0 A deposit of $11,250.00 is due upon execution of this agreement by the Interconnection customer. 7.0 In cases where Upgrades are required, the facilities study must be completed within 45 Business Days of the receipt of this Agreement. In cases where no Upgrades are necessary, and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 Business Days. 8.0 Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the Interconnection Customer. Barring unusual circumstances, the facilities study must be completed and the facilities study report transmitted within 30 Business Days of the Interconnection Customer's agreement to conduct a facilities study. 9.0 Any study fees shall be based on the Transmission Provider's actual costs and will be invoiced to the Interconnection Customer after the study is completed and delivered and will include a summary of professional time. 10.0 The Interconnection Customer must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the Transmission Provider shall refund such excess within 30 calendar days of the invoice without interest. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. Transmission Provider: Idaho Power Comp77: Signed: 212.L~ Printed Name: £i,JU!VU2 Kos. Y/;24-1(._ Title: P JJ1 dey a..r .t.n&~ Date: 7 /z...~/;L Small Generator Facilities Study Agreement Interconnection Customer: Sign~~ Pri~:;~---- Title: CEO --------------------- Date: _June 6, 2012 ______ _ - 2 -Swager Farms Project #307 Attachment A to Facilities Study Agreement Data to Be Provided by the Interconnection Customer With the Facilities Study Agreement 1. Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT/PT) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps 2. One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station. Number of generation connections: One Connection c__ __ _ 3. Will an alternate source of auxiliary power be available during CT/PT maintenance? Yes No N/A 4. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? Yes No _X __ (Please indicate on the one-line diagram). 5. What type of control system or PLC will be located at the Small Generating Facility? Automation Direct -------------------------------- 6. \Yhat protocol does the control system or PLC use? _Modbus or other if required 7. Please provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines. 8. Physical dimensions of the proposed interconnection station: Near 1707 E3800N,Buhl.ID 8331 6 Small Generator Facilities Study Agreement -3-Swager Farms Project #307 9. Bus length from generation to interconnection station: ___ To be determined, less than 300' anticipated ________________ _ I 0. Line length from interconnection station to Transmission Provider's Transmission System. _______ TBD ________________________________ ___ 11. Tower number observed in the field. (Painted on tower leg)*: ____ Same as original study 12. Number of third party easements required for transmission lines*: ___ _:None anticipated *To be completed in coordination with Transmission Provider. 13. Is the Small Generating Facility located in Transmission Provider's service area? Yes ---=-X=--_ No _____ lfNo, please provide name oflocal provider: 14. Please provide the following proposed schedule dates: Begin Construction Date: _August 15, 2012 _____ _ Generator Step-Up Transformers Date: _December 30, 2012 _____ _ Receive Back Feed Power Generation Testing Date: _January 30, 2013 ______ _ Commercial Operation Date: _February 15, 2013 ____ _ Small Generator Facilities Study Agreement - 4 -Swager Farms Project #307 -------·--·--~ M -~r,;.:»ti.rt ~ lr;..~-- --- -~· ._ ... BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 51 September 10,2012 Leslie White Exergy New Energy 802 W. Bannock 12th Floor Boise, ID 83 702 An ID:ACOI!P Company Re: Swager Farms Dairy Digester Project (0.8 MW Output) Facility Study Report-Project #307 Dear Ms. White: Idaho Power Company (IPC) has completed the Facility Study cost estimate for your Generator Interconnection project based on the revised Feasibility Study Report dated June 1, 2012. Attached please find the Facility Study Report (FSR). Please note the FSR has different requirements than past reports because the total output of the project is less than 1 megavoltampere (MV A), particularly there is no requirement for you to provide telecommunications to the Idaho Power facilities. In order to proceed with this project, please provide your comments to the Facility Study Report to me by October 12, 2012 and indicate whether you wish to proceed with final design and construction. The final report will be used to prepare a Generator Interconnection Agreement in preparation for Construction. Josh Harris will be working with you to finalize the Interconnection Agreement. Before we can begin Construction or order materials, you are responsible for contacting Idaho Power's credit department to discuss credit requirements for construction funding. Please contact Aubrae Sloan (208-388-5697) at your earliest convenience. Once we receive funding, or the credit requirement is met, we can proceed with construction of the project. The actual construction and labor charges will be finalized approximately 90 days subsequent to project completion. We will reconcile any over-or underpayment at that time. I look forward to hearing from you soon. Sincerely, Eric Hackett Project Leader Attachment: Swager Farms Dairy Digester Project Facility Study Report with Drawings Cc: J Harris/IPC A Sloan/IPC D Walker/IPC Generator Interconnection Facility Study Report for the Swager Farms Dairy Digester Project-Project #307 for Exergy New Energy m Twin Falls County, Idaho September 10,2012 An IDACOI!P company FACILITY STUDY REPORT (FSR) Swager Farms Dairy Digester Project #307 September 10,2012 1. General Facility Description The proposed project will consist of a short three-phase distribution line extension and Idaho Power's overhead generation interconnection package (for projects less than 1 MV A) including an overhead recloser, metering package, local service power transformer, disconnect switches, and a relay/control box. Additionally, one 1000 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer will be installed, including the associated underground cabling and vaults. The project is located in Twin Falls County, Idaho and connects to the 12.5 kV system on Idaho Power Company's Clover (COVR-012) distribution line. The total project output is 0.8 MW. Interconnection Customer: Leslie White Exergy New Energy 802 W. Bannock 12th Floor Boise, ID 83702 A Standard Generator Interconnection Agreement under Idaho Power Company's Open Access Transmission Tariff (OATT) or Schedule 72 between Interconnection Customer and Idaho Power Company -Delivery (Transmission Owner) for the Swager Farms Dairy Digester Project, specifically Generator Interconnection Project #307, will be prepared for this project. 1.1 Interconnection Point The Interconnection Point for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SW1). The project's location is in T10S R15E Section 21 of Twin Falls County, Idaho. A drawing identifying the Interconnection Point is attached. 1.2 Point of Change of Ownership The Point of Change of Ownership for the Swager Farms Dairy Digester Project will be the low­ side bushings on the padmounted transformer (SWl). 1.3 Customer's Interconnection Facilities The Interconnection Customer will install generators, low-side disconnect switches, all wiring and conduit between the generators and the padmounted transformer, appropriate grounding measures, and associated auxiliary equipment. Interconnection Customer will build underground facilities to the Point of Change of Ownership for the generator facility. The low-side disconnect switch shall be as specified or as determined by mutual agreement and be readily accessible, operable, and lockable by Idaho Power personnel at all times. 1.4 Other Facilities Provided by Interconnection Customer 1.4.1 Ground Fault Equipment The customer will install ground fault limiting equipment that will limit the zero sequence fault current to 20 amps at the Interconnection Point. 1.4.2 Easements The Interconnection Customer will provide to Idaho Power a surveyed (Metes & Bounds) legal description along with exhibit map for Idaho Power's proposed facilities. After the legal description has been delivered to IPCO for review, IPCO will supply to the Interconnection Customer a completed IPCO easement for signature by the land owner of record. Once the signatures have been secured, the Interconnection Customer will return the signed easement to IPCO for recording. 1.4.3 Local Service The Interconnection Customer is responsible to arrange for local service to their site, as necessary. 1.4.4 Monitoring Information If the Interconnection Customer requires the ability to monitor information related to the Idaho Power recloser in the generation interconnection package they are required to supply their own cabling/wiring to the control box. 1.5 Idaho Power Company's Interconnection Facilities Idaho Power will install a generation interconnection package on the existing distribution feeder (COVR-012) on private property southeast of the intersection of E. 3800 N. and N. 1700 E. in Twin Falls County, ID. See the attached work order maps (WO 27328106, sheet 1 of2) for details. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-547 line protection relay. The relay will be located in a pole mounted enclosure and will also contain a test switch (TS4), isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) one 1000 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer on top of a vault. Conduit and underground cables will be installed from the interconnection package to padmounted transformer. Protective posts will be installed to protect the ground mounted equipment from damage. A 2" conduit will be installed alongside the underground primary to facilitate information exchange to the customer about the recloser if desired. (The Interconnection Customer is responsible for providing and installing the appropriate cable.) 2 1.6 Facility Estimated Cost: The following good faith estimates are provided in 2011 dollars: 2. Milestones 12/10/12 Construction Funds Received by IPCO 6/10/13 IPCO Construction Complete 7110/13 IPCO Commissioning Complete TBD by seller Commercial Operation Date These milestone dates assume that material can be procured and labor resources are available. Additionally, any permitting issues outside the immediate control of Idaho Power could also influence the Commercial Date. 3. Operating Requirements The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and requirements for harmonic Control in Electrical Power Systems or any subsequent standards as they may be updated from time to time. Voltage flicker at startup and during operation must be limited to less than 5% as measured at the Interconnection Point. The Project must be capable of riding through faults on adjacent section of the power system without tripping due to low voltage. It has been determined, through study, that the Project must be capable of remaining interconnected for any single phase voltage as low as 0.7 PU for 30 cycles, and for all three phase voltages as low as 0.8 PU for 30 cycles. Interconnection Customer will be able to modify power plant facilities on the Interconnection Customer side ofthe Interconnection Point with no impact upon the operation of the transmission or distribution system whenever the generation facilities are electrically isolated from the system and a terminal clearance is issued by Idaho Power Company's Grid Operator. 3 4. Reactive Power The Project must be controlled to operate as a VAr neutral system with a ± 200 kVAr operating band. 5. Upgrades 5.1 Distribution Upgrades Idaho Power will extend the existing distribution feeder (COVR-012) approximately 360 feet to the east Gust north of the ponds) on private property to facilitate and locate the Interconnection Facilities. 6. Estimated Costs The following good faith estimates are provided in 2011 dollars: Estimated Cost: ·~ :· .1IrBnl'2m;:rr'' ·. I .. I -• r •• I . ·( c!l:~!TtltrilinJ · . (~;;.1@:1]!~:lti' . !Interconnection Facilities (from section 1.6): -'"" -_,,._. -.. ,. __ Overhead Generation Interconnection Package & Line Extension IPC $145,000 Underground Equipment and 1000 kVA Transformer IPC $75,000 t=--SUBTOTAL $220,000 GRAND TOTAL $220,000, l Note Regarding Transmission Service: This Facility Study is a Network Resource Interconnection Facility Study. This study identifies the facilities necessary to integrate the Generating Facility into Idaho Power's network to serve load within Idaho Power's balancing area. Network Resource Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery. 4 i ~ I ~ ~ ~ i I ~. I 9 ~ 6 • ~ ~ • % l ~ • ~ ~ ~ ~ i ~ I D CO V R 01 2 12 . 5 k V 4· 3 2· .. BY IP C O -- - + - - -- B Y OW N E R Til I ~u I CO C F E R "V W V ( . 5 8 X " lo i E T E R . l ~ ! ~ ~ - ~ 1 RE C L O S ( J I ... ~- « r :·· - - - ~J S I 1 60 0 - ! 5 : - ' 0 I ~ I L- - - - - - , - :z. - ' o ! [ l ~ > t; l DS 1 1 J , i ~' I l ~ I l. I ! ( T ~I i -1 : J, 1Sk V A !< 1 52 0 1 t '" ' " l- - - -- -r- - · I'( ' :1", . , " ' " " ~ : ~ J., 72 G 0 - 1 2 D / Z 4 0 V I I I< I j " I I c B L _ , ; I I ~< I L ,.. . . , J : ~I -- -; ; ( ] I ) - - - - I SOll kW .. Iii I "''" ' > . W "" ' " _L I : ·: : . ' : : ' '0 IPC O LO C A L SE R V I C E 1 FO R SE L 5 4 7 BO X • • PR O J E C T LO C A T I O N : 11 0 5 , R1 5 E , SE C T I O N 21 JB O O NO R l l l 17 0 0 EA S T , TW I N FA U S CO U N T Y . ID A H O IN SE R V I C E BY 12 - 3 1 - 2 0 1 2 j 1 I= J '" " " ' " " s, .. ,; ~ , RE V J S J O N >-< - n 110ll f l l l "'1 •• ~. . . . . - .. ~~ . , t e : . ; " o i i y ~l •c'.IC ., . r: I T " • E D SIN G l E LIN E AP P R O V A L tt ~ E r l ) h w ~ .. . , , . , . _ __ _ ... . . . . . . . . . __ _ -- -­ :.: . . . , . . . . , ~ 1:- l o d ~ t . W ! t a - -- '-'- .. . . . . ... . . . . . . -- - :,~! TI ? J ! ! i ' " " .. c: : : : : = IIA -c ~ ; ; : t " i G CC I I I J-C \ I ( : > C l , l , l Jb SW A G E R FA R M S DA I R Y DIG E S T E R ! IN T E R C O N N E C T I O N ~ SI N G L E UN E Proposed Location for Distribution Upgrades and Interconnection Facilities Green = Distribution Upgrades Yellow= Interconnection Facilities (Interconnection Package) Red= Interconnection Facilities (Underground Cables and Vaults) Purple= Interconnection Facilities (Padmounted Transformer) BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 52 Leslie White Exergy 802 W. Bannock 12th Floor Boise, ID 83702 An IOACORP company September 14, 2012 Via email & Certified Mail #70 113500000156448948 Re: Swager Farms Dairy Digester Project-GI# 307 Dear Leslie: Attached please find a copy of the final Facility Study Report (FSR) dated September 10, 2012, and a Generator Interconnection Agreement (GIA) for the Swager Farms Dairy Digester Project. Pursuant to our standard GIA process, you would normally be receiving a Draft GIA at this point in time with 30 days to review and comment, after which time you would be offered a Final GIA which you would then have 30 days to execute and fund. The construction sequencing for this project, based upon Idaho Power's current resources and scheduling would have Idaho Power construction completion sometime during approximately May -June 2013, assuming you execute and fund the GIA by November. However, because Idaho Power is aware of your need to bring this project online and operational before the end of the year, and based upon the unique facts and circumstances of this project, Idaho Power was able to rearrange some project scheduling and sequencing in an attempt to offer to you an opportunity to have the interconnection work completed by the end of this year. In order for your project to come online by December 31, 2012, we are providing you with a Final Facility Study Report and a Final GIA. Idaho Power must have the executed GIA and funding no later than October 1, 2012, in order to complete construction by this date. Of course, if you wish to take time to review Draft versions of both the Facility Study and the GIA prior to being offered a Final GIA, please let me know and I will provide you with those documents. This will however push out the date by which we will have construction complete. I have provided you with a Final GIA with this letter, which if acceptable upon your review, is ready for execution and funding. This is being offered to you as a way to expedite the process so that Idaho Power may have the executed GIA and funding by October 1, 20 12, in order for your project to come online by December 31, 2012. Although the preferred method of funding is full payment upfront; payment arrangements may be requested. If you have not already done so, please contact Aubrae Sloan (208-388-5697), Operations Finance, if you wish to discuss Idaho Power's credit requirements for construction funding. Once we receive funding, or the credit requirement is met, we will proceed with construction of the project. The actual construction and labor charges will be reconciled approximately 90 days subsequent to project completion. Under the Generator Interconnection process, the following items must be provided to me on or before execution of the GIA: 1. Proof of Site Control for the project 2. Insurance certification pursuant to Section 7 of the GIA (certificate, 1 endorsement for Additional insured, and 1 for the cancellation notice) 3. Financial arrangements approved by Idaho Power credit department, or full payment for construction P.O. 801< 70 (83707) 1221 W. Idaho St. Boise, 10 8370i Failure to submit all of the requested items above by October 1, 2012 will cause your Generator Interconnection request to forgo the expedited process and construction completion will not be possible by December 31 2012, and wilJ be schedule for approximately May/June 2013. We will then provide you with a draft version of the Facility Study and work tlu·ough the Generator Interconnection Process as per the normal schedule. Please contact me at your earliest convenience with any questions. End: Final Facility Study Report Sincerely, Josh Harris Operations Analyst jharris@idahopower.com GIA for Swager Farms Dairy Digester Project #307 Cc: (via email) Eric Hackett/IPC Tess Park/IPC Aubrae Sloan/IPC Donovan Walker/IPC Randy Allphin/IPC Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29 Tariff No. 101 September 14, 2012 GENERATOR INTERCONNECTION AGREEMENT Schedule 72 Swager Farms Dairy Digester Project O.BMW Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 TABLE OF CONTENTS RECITALS ............................................................................................................................................. 1 AGREEMENTS ..................................................................................................................................... 1 1. Capitalized Terms ................................................................................................................ 1 2. Terms and Conditions .......................................................................................................... 1 3. This Agreement is not an agreement to purchase Seller's power ......................................... 1 4. Attachments ......................................................................................................................... 1 5. Effective Date. Term. Termination and Disconnection .......................................................... 2 6. Assignment. Liability, Indemnity, Force majeure, Consequential Damages and Default. ...... 5 7. Insurance ............................................................................................................................. 7 B. Miscellaneous ....................................................................................................................... 7 9. Notices ................................................................................................................................. 8 10. Signatures ............................................................................................................................ 9 Attachment 1 ......................................................................................................................................... 1 Attachment 2 ......................................................................................................................................... 1 Attachment 3 ......................................................................................................................................... 1 Attachment 4 ......................................................................................................................................... 1 Attachment 5 ......................................................................................................................................... 1 Attachment 6 ......................................................................................................................................... 1 Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 1 of 9 This Generator Interconnection Agreement ("Agreement") under Idaho Power Company's Schedule 72 is effective as of the __ day of , 2012 between ------------,-,-- ("Seller", "Customer'' or "The Project") and Idaho Power Company ("Company","Transmission Owner", "Idaho Power", "I PC" or "IPCO"). RECITALS A. Seller will own or operate a Generation Facility that qualifies for service under Idaho Power's Commission-approved Schedule 72 and any successor schedule. B. The Generation Facility covered by this Agreement is more particularly described in Attachment 1. AGREEMENTS 1. Capitalized Terms Capitalized terms used herein shall have the same meanings as defined in Schedule 72 or in the body of this Agreement. 2. Terms and Conditions This Agreement and Schedule 72 provide the rates, charges, terms and conditions under which the Seller's Generation Facility will interconnect with, and operate in parallel with, the Company's transmission/distribution system. Terms defined in Schedule 72 will have the same defined meaning in this Agreement. If there is any conflict between the terms of this Agreement and Schedule 72, Schedule 72 shall prevail. 3. This Agreement is not an agreement to purchase Seller's power. Purchase of Seller's power and other services that Seller may require will be covered under separate agreements. Nothing in this Agreement is intended to affect any other agreement between the Company and Seller. 4. Attachments Attached to this Agreement and included by reference are the following: Attachment 1 -Description and Costs of the Generation Facility, Interconnection Facilities, and Metering Equipment. Attachment 2 -One-line Diagram Depicting the Generation Facility, Interconnection Facilities, Metering Equipment and Upgrades. Attachment 3-Milestones For Interconnecting the Generation Facility. Attachment 4 -Additional Operating Requirements for the Company's Transmission System Needed to Support the Seller's Generation Facility. Attachment 5 -Reactive Power. Attachment 6 -Description of Upgrades required to integrate the Generation Facility and Best Estimate of Upgrade Costs. Attachment 7-Generator Interconnection Control Requirements Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 2 of 9 5. Effective Date, Term, Termination and Disconnection. 5. 1 Term of Agreement. Unless terminated earlier in accordance with the provisions of this Agreement, this Agreement shall become effective on the date specified above and remain effective as long as Seller's Generation Facility is eligible for service under Schedule 72. 5.2 Termination. 5.2. 1 Seller may voluntarily terminate this Agreement upon expiration or termination of an agreement to sell power to the Company. 5.2.2 After a Default, either Party may terminate this Agreement pursuant to Section 6. 5. 5. 2. 3 Upon termination or expiration of this Agreement, the Seller's Generation Facility will be disconnected from the Company's transmission/distribution system. The termination or expiration of this Agreement shall not relieve either Party of its liabilities and obligations, owed or continuing at the time of the termination. The provisions of this Section shall survive termination or expiration of this Agreement. 5.3 Temporarv Disconnection. Temporary disconnection shall continue only for so long as reasonably necessary under "Good Utility Practice." Good Utility Practice means any of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region. Good Utility Practice includes compliance with WECC or NERC requirements. Payment of lost revenue resulting from temporary disconnection shall be governed by the power purchase agreement. 5. 3. 1 Emergency Conditions. "Emergency Condition" means a condition or situation: (1) that in the judgment of the Party making the claim is imminently likely to endanger life or property; or (2) that, in the case of the Company, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to the Company's transmission/distribution system, the Company's Interconnection Facilities or the equipment of the Company's customers; or (3) that, in the case of the Seller, is imminently likely (as determined in a non­ discriminatory manner) to cause a material adverse effect on the reliability and security of, or damage to, the Generation Facility or the Seller's Interconnection Facilities. Under Emergency Conditions, either the Company or the Seller may immediately suspend interconnection service and temporarily disconnect the Generation Facility. The Company shall notify the Seller promptly when it becomes aware of an Emergency Condition that may reasonably be expected to affect the Seller's operation of the Generation Facility. The Seller shall notify the Company promptly when it becomes aware of an Emergency Condition that may reasonably be expected to affect the Company's equipment or service to the Company's customers. To the extent information is known, the notification shall describe the Emergency Condition, the extent of the damage or deficiency, the expected effect on the operation of both Parties' facilities and operations, its anticipated duration, and the necessary corrective action. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 3 of 9 5.3.2 Routine Maintenance. Construction, and Repair. The Company may interrupt interconnection service or curtail the output of the Seller's Generation Facility and temporarily disconnect the Generation Facility from the Company's transmission/distribution system when necessary for routine maintenance, construction, and repairs on the Company's transmission/distribution system. The Company will make a reasonable attempt to contact the Seller prior to exercising its rights to interrupt interconnection or curtail deliveries from the Seller's Facility. Seller understands that in the case of emergency circumstances, real time operations of the electrical system, and/or unplanned events, the Company may not be able to provide notice to the Seller prior to interruption, curtailment or reduction of electrical energy deliveries to the Company. The Company shall use reasonable efforts to coordinate such reduction or temporary disconnection with the Seller. 5.3.3 Scheduled Maintenance. On or before January 31 of each calendar year, Seller shall submit a written proposed maintenance schedule of significant Facility maintenance for that calendar year and the Company and Seller shall mutually agree as to the acceptability of the proposed schedule. The Parties determination as to the acceptability of the Seller's timetable for scheduled maintenance will take into consideration Good Utility Practices, Idaho Power system requirements and the Seller's preferred schedule. Neither Party shall unreasonably withhold acceptance of the proposed maintenance schedule. 5.3.4. Maintenance Coordination. The Seller and the Company shall, to the extent practical, coordinate their respective transmission/distribution system and Generation Facility maintenance schedules such that they occur simultaneously. Seller shall provide and maintain adequate protective equipment sufficient to prevent damage to the Generation Facility and Seller-furnished Interconnection Facilities. In some cases, some of Seller's protective relays will provide back-up protection for Idaho Power's facilities. In that event, Idaho Power will test such relays annually and Seller will pay the actual cost of such annual testing. 5.3.5 Forced Outages. During any forced outage, the Company may suspend interconnection service to effect immediate repairs on the Company's transmission/distribution system. The Company shall use reasonable efforts to provide the Seller with prior notice. If prior notice is not given, the Company shall, upon request, provide the Seller written documentation after the fact explaining the circumstances of the disconnection. 5.3.6 Adverse Operating Effects. The Company shall notify the Seller as soon as practicable if, based on Good Utility Practice, operation of the Seller's Generation Facility may cause disruption or deterioration of service to other customers served from the same electric system, or if operating the Generation Facility could cause damage to the Company's transmission/distribution system or other affected systems. Supporting documentation used to reach the decision to disconnect shall be provided to the Seller upon request. If, after notice, the Seller fails to remedy the adverse operating effect within a reasonable time, the Company may disconnect the Generation Facility. The Company shall provide the Seller with reasonable notice of such disconnection, unless the provisions of Article 5.3.1 apply. 5.3. 7 Modification of the Generation Facilitv. The Seller must receive written authorization from the Company before making any change to the Generation Facility that may have a material impact on the safety or reliability of the Company's transmission/distribution system. Such authorization shall not be unreasonably withheld. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29 , Tariff No. 101 Page 4 of 9 Modifications shall be done in accordance with Good Utility Practice. If the Seller makes such modification without the Company's prior written authorization, the latter shall have the right to temporarily disconnect the Generation Facility. 5.3. 8 Reconnection. The Parties shall cooperate with each other to restore the Generation Facility, Interconnection Facilities, and the Company's transmission/distribution system to their normal operating state as soon as reasonably practicable following a temporary disconnection. 5.3.9 Voltage Levels. Seller, in accordance with Good Utility Practices, shall minimize voltage fluctuations and maintain voltage levels acceptable to Idaho Power. Idaho Power may, in accordance with Good Utility Practices, upon one hundred eighty (180) days' notice to the Seller, change its nominal operating voltage level by more than ten percent (10%) at the Point of Delivery, in which case Seller shall modify, at Idaho Power's expense, Seller's equipment as necessary to accommodate the modified nominal operating voltage level. 5. 4 Land Rights. 5.4. 1 Seller to Provide Access. Seller hereby grants to Idaho Power for the term of this Agreement all necessary rights-of-way and easements to install, operate, maintain, replace, and remove Idaho Power's Metering Equipment, Interconnection Equipment, Disconnection Equipment, Protection Equipment and other Special Facilities necessary or useful to this Agreement, including adequate and continuing access rights on property of Seller. Seller warrants that it has procured sufficient easements and rights-of-way from third parties so as to provide Idaho Power with the access described above. All documents granting such easements or rights-of-way shall be subject to Idaho Power's approval and in recordable form. 5.4.2 Use of Public Rights-of-Wav. The Parties agree that it is necessary to avoid the adverse environmental and operating impacts that would occur as a result of duplicate electric lines being constructed in close proximity. Therefore, subject to Idaho Power's compliance with Paragraph 5.4.4, Seller agrees that should Seller seek and receive from any local, state or federal governmental body the right to erect, construct and maintain Seller-furnished Interconnection Facilities upon, along and over any and all public roads, streets and highways, then the use by Seller of such public right-of-way shall be subordinate to any future use by Idaho Power of such public right-of-way for construction and/or maintenance of electric distribution and transmission facilities and Idaho Power may claim use of such public right-of-way for such purposes at any time. Except as required by Paragraph 5.4.4, Idaho Power shall not be required to compensate Seller for exercising its rights under this Paragraph 5.4.2. 5.4.3 Joint Use of Facilities. Subject to Idaho Power's compliance with Paragraph 15.4.4, Idaho Power may use and attach its distribution and/or transmission facilities to Seller's Interconnection Facilities, may reconstruct Seller's Interconnection Facilities to accommodate Idaho Power's usage or Idaho Power may construct its own distribution or transmission facilities along, over and above any public right-of-way acquired from Seller pursuant to Paragraph 5.4.2, attaching Seller's Interconnection Facilities to such newly constructed facilities. Except as required by Paragraph 5.4.4, Idaho Power shall not be required to compensate Seller for exercising its rights under this Paragraph 5.4.3. 5.4. 4 Conditions of Use. It is the intention of the Parties that the Seller be left in substantially the same condition, both financially and electrically, as Seller existed prior Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 5 of 9 to Idaho Power's exercising its rights under this Paragraph 5.4. Therefore, the Parties agree that the exercise by Idaho Power of any of the rights enumerated in Paragraphs 5.4.2 and 5.4.3 shall: (1) comply with all applicable laws, codes and Good Utility Practices, (2) equitably share the costs of installing, owning and operating jointly used facilities and rights-of-way. If the Parties are unable to agree on the method of apportioning these costs, the dispute will be submitted to the Commission for resolution and the decision of the Commission will be binding on the Parties, and (3) shall provide Seller with an interconnection to Idaho Power's system of equal capacity and durability as existed prior to Idaho Power exercising its rights under this Paragraph 5.4. 6. Assignment. Liability, Indemnity, Force majeure, Consequential Damages and Default. 6. 1 Assignment. This Agreement may be assigned by either Party upon twenty-one (21) calendar days prior written notice and opportunity to object by the other Party; provided that: 6.1.1 Either Party may assign this Agreement without the consent of the other Party to any affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement. 6.1.2 The Seller shall have the right to contingently assign this Agreement, without the consent of the Company, for collateral security purposes to aid in providing financing for the Generation Facility, provided that the Seller will promptly notify the Company of any such contingent assignment. 6.1.3 Any attempted assignment that violates this article is void and ineffective. Assignment shall not relieve a Party of its obligations, nor shall a Party's obligations be enlarged, in whole or in part, by reason thereof. An assignee is responsible for meeting the same financial, credit, and insurance obligations as the Seller. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed. 6.2 Limitation of Liabilitv. Each Party's liability to the other Party for any loss, cost, claim, injury, liability, or expense, including reasonable attorney's fees, relating to or arising from any act or omission in its performance of this Agreement, shall be limited to the amount of direct damage actually incurred. In no event shall either Party be liable to the other Party for any indirect, special, consequential, or punitive damages, except as authorized by this Agreement. 6.3 Indemnity. 6.3.1 This provision protects each Party from liability incurred to third parties as a result of carrying out the provisions of this Agreement. Liability under this provision is exempt from the genera/limitations on liability found in Article 6.2. 6.3.2 The Parties shall at all times indemnify, defend, and hold the other Party harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's action or failure to meet its obligations under this Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party. 6.3.3 If an indemnified person is entitled to indemnification under this article as a result of a claim by a third party, and the indemnifying Party fails, after notice and Idaho Power Company Generator Interconnection Agreement# 307 I .P.U.C. No. 29, Tariff No. 101 Page 6 of 9 reasonable opportunity to proceed under this article, to assume the defense of such claim, such indemnified person may at the expense of the indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim. Failure to defend is a Material Breach. 6.3.4 If an indemnifying party is obligated to indemnify and hold any indemnified person harmless under this article, the amount owing to the indemnified person shall be the amount of such indemnified person's actual loss, net of any insurance or other recovery. 6.3.5 Promptly after receipt by an indemnified person of any claim or notice of the commencement of any action or administrative or legal proceeding or investigation as to which the indemnity provided for in this article may apply, the indemnified person shall notify the indemnifying party of such fact. Any failure of or delay in such notification shall be a Material Breach and shall not affect a Party's indemnification obligation unless such failure or delay is materially prejudicial to the indemnifying party. 6.4 Force Majeure. As used in this Agreement, "Force Majeure" or "an event of Force Majeure" means any cause beyond the control of the Seller or of the Company which, despite the exercise of due diligence, such Party is unable to prevent or overcome. Force Majeure includes, but is not limited to, acts of God, fire, flood, storms, wars, hostilities, civil strife, strikes and other labor disturbances, earthquakes, fires, lightning, epidemics, sabotage, or changes in law or regulation occurring after the Operation Date, which, by the exercise of reasonable foresight such party could not reasonably have been expected to avoid and by the exercise of due diligence, it shall be unable to overcome. If either Party is rendered wholly or in part unable to perform its obligations under this Agreement because of an event of Force Majeure, both Parties shall be excused from whatever performance is affected by the event of Force Majeure, provided that: (1) The non-performing Party shall, as soon as is reasonably possible after the occurrence of the Force Majeure, give the other Party written notice describing the particulars of the occurrence. (2) The suspension of performance shall be of no greater scope and of no longer duration than is required by the event of Force Majeure. (3) No obligations of either Party which arose before the occurrence causing the suspension of performance and which could and should have been fully performed before such occurrence shall be excused as a result of such occurrence. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 7 of 9 6. 5 Default and Material Breaches. 6. 5. 1 Defaults. If either Party fails to perform any of the terms or conditions of this Agreement (a "Default" or an "Event of Default'), the nondefaulting Party shall cause notice in writing to be given to the defaulting Party, specifying the manner in which such default occurred. If the defaulting Party shall fail to cure such Default within the sixty (60) days after service of such notice, or if the defaulting Party reasonably demonstrates to the other Party that the Default can be cured within a commercially reasonable time but not within such sixty (60) day period and then fails to diligently pursue such cure, then, the nondefaulting Party may, at its option, terminate this Agreement and/or pursue its legal or equitable remedies. 6.5.2 Material Breaches. The notice and cure provisions in Paragraph 6.5.1 do not apply to Defaults identified in this Agreement as Material Breaches. Material Breaches must be cured as expeditiously as possible following occurrence of the breach. 7. Insurance. During the term of this Agreement, Seller shall secure and continuously carry the following insurance coverage: 7. 1 Comprehensive General Liability Insurance for both bodily injury and property damage with limits equal to $1,000,000, each occurrence, combined single limit. The deductible for such insurance shall be consistent with current Insurance Industry Utility practices for similar property. 7.2 The above insurance coverage shall be placed with an insurance company with an A.M. Best Company rating of A-or better and shall include: (a) An endorsement naming Idaho Power as an additional insured and loss payee as applicable; and (b) A provision stating that such policy shall not be canceled or the limits of liability reduced without sixty (60) days' prior written notice to Idaho Power. 7.3 Seller to Provide Certificate of Insurance. As required in Paragraph 7 herein and annually thereafter, Seller shall furnish the Company a certificate of insurance, together with the endorsements required therein, evidencing the coverage as set forth above. 7. 4 Seller to Notify Idaho Power of Loss of Coverage -If the insurance coverage required by Paragraph 7. 1 shall/apse for any reason, Seller will immediately notify Idaho Power in writing. The notice will advise Idaho Power of the specific reason for the lapse and the steps Seller is taking to reinstate the coverage. Failure to provide this notice and to expeditiously reinstate or replace the coverage will constitute grounds for a temporary disconnection under Section 5.3 and will be a Material Breach. 8. Miscellaneous. 8. 1 Governing Law. The validity, interpretation and enforcement of this Agreement and each of its provisions shall be governed by the laws of the state of Idaho without regard to its conflicts of law principles. 8.2 Salvage. No later than sixty (60) days after the termination or expiration of this Agreement, Idaho Power will prepare and forward to Seller an estimate of the remaining value Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 8 of 9 of those Idaho Power furnished Interconnection Facilities as required under Schedule 72 and/or described in this Agreement, less the cost of removal and transfer to Idaho Power's nearest warehouse, if the Interconnection Facilities will be removed. If Seller elects not to obtain ownership of the Interconnection Facilities but instead wishes that Idaho Power reimburse the Seller for said Facilities the Seller may invoice Idaho Power for the net salvage value as estimated by Idaho Power and Idaho Power shall pay such amount to Seller within thirty (30) days after receipt of the invoice. Seller shall have the right to offset the invoice amount against any present or future payments due Idaho Power. 9. Notices. 9.1 General. Unless otherwise provided in this Agreement, any written notice, demand, or request required or authorized in connection with this Agreement ("Notice") shall be deemed properly given if delivered in person, delivered by recognized national currier service, or sent by first class mail, postage prepaid, to the person specified below: If to the Seller: Seller:------------------------ Attention:-------------------------- Address: _________ ~~-----~-----------City: _________ -=-State: ____ .Zip: ____ _ Phone: Fax: ----------- If to the Company: Idaho Power Company -Delivery Attention: Load Serving Operations Director 1221 W. Idaho Street Boise: Idaho 83702 Phone: 208-388-2630 Fax: 208-388-5504 9.2 out below: Billing and Payment. Billings and payments shall be sent to the addresses set Seller:----------------------- Attention:----------------------------Address: _________________________ __ City: ___________ ----=~State : ____ .Zip: ------ Phone: Fax: Idaho Power Company -Delivery Attention: Corporate Cashier PO Box447 Salt Lake City Utah 8411 0-044 7 --------- Phone: 208-388-5697 email: asloan@idahopower.com 9.3 Designated Operating Representative. The Parties may also designate operating representatives to conduct the communications which may be necessary or convenient for the administration of this Agreement. This person will also serve as the point of contact with respect to operations and maintenance of the Party's facilities. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 9 of 9 Seller's Operating Representative: Seller:-----------------------­ Attention:-------------------------- Address: _______________ ~---------- City: ___________ State: ____ ,Zip: ____ _ Phone: Fax: -------- Company's Operating Representative: Idaho Power Company -Delivery Attention: Outage Coordinator-System/Regional Dispatch 1221 W. Idaho Street Boise, Idaho 83702 Phone: 208-388-2633, 388-5125, or 388-5175 during regular business hours (after hours-System Dispatch Southern Region 208-388-5190) 9.5 Changes to the Notice Information. Either Party may change this information by giving five (5) Business Days written notice prior to the effective date of the change. 10. Signatures. IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their respective duly authorized representatives. For the Seller Name: -------------------------- Title: ____________________ _ Date: __________ _ For the Company Name: ------------------------- Title: Director, Load Serving Operations-Idaho Power Company, Delivery Date: Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 2 Attachment 1 Description and Costs of the Generation Facility, Interconnection Facilities and Metering Equipment Interconnection Details Type of Interconnection Service: Studied as an Idaho Power Network Resource under PURPA Full Output: 0.8 MW Nominal Delivery Voltage: 12.5 kV General Facility Description The proposed project will consist of a short three-phase distribution line extension and Idaho Power's overhead generation interconnection package including an overhead recloser, metering package, local service power transformer, disconnect switches, and a relay/control box. Additionally, one 1000 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer will be installed, including the associated underground cabling and vaults. The project is located in Twin Falls County, Idaho and connects to the 12.5 kV system on Idaho Power Company's Clover (COVR-012) distribution line. The total project output is 0.8 MW. Interconnection Point The Interconnection Point for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SW1). The project's location is in T10S R15E Section 21 of Twin Falls County, Idaho. A drawing identifying the Point of Interconnection is included as Attachment 2. The Point of Change of Ownership is electrically the same as the Interconnection Point. Point of Change of Ownership The Point of Change of Ownership for the Swager Farms Dairy Digester Project will be the low-side bushings on the pad mounted transformer (SW1 ). Seller's Interconnection Facilities The Swager Farms Project will install generators, low-side disconnect switches, all wiring and conduit between the generators and the padmounted transformer, appropriate grounding measures, and associated auxiliary equipment. Seller will build underground facilities to the Point of Change of Ownership for the generator facility. The low-side disconnect switch shall be as specified or as determined by mutual agreement and be readily accessible, operable, and lockable by Idaho Power personnel at all times. All interconnection equipment electrically located on the generator side of the Point of Change Ownership shall be owned and maintained by the Seller. Other Facilities Provided by Seller Ground Fault Equipment The Seller will install ground fault limiting equipment that will limit the zero sequence fault current to 20 amps at the Interconnection Point. Monitoring Information If the Seller requires the ability to monitor information related to the Idaho Power recloser in the generation interconnection package they are required to supply their own cabling/wiring to the control box. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 2 of 2 Easements The Seller will provide to Idaho Power a surveyed (Metes & Bounds) legal description along with exhibit map for Idaho Power's proposed facilities. After the legal description has been delivered to I PCO for review, IPCO will supply to the Seller a completed IPCO easement for signature by the land owner of record. Once the signatures have been secured, the Seller will return the signed easement to IPCO for recording. Local Service The Seller is responsible to arrange for local service to their site, as necessary. Idaho Power Company's Interconnection Facilities Idaho Power will install a generation interconnection package on the existing distribution feeder (COVR-012) on private property southeast of the intersection of E. 3800 N. and N. 1700 E. in Twin Falls County, ID. The new interconnection package will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-547 line protection relay. The relay will be located in a pole mounted enclosure and will also contain a test switch (TS4), isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) one 1000 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer on top of a vault. Conduit and underground cables will be installed from the interconnection package to padmounted transformer. Protective posts will be installed to protect the ground mounted equipment from damage. A 2" conduit will be installed alongside the underground primary to facilitate information exchange to the Seller about the recloser if desired. (The Seller is responsible for providing and installing the appropriate cable.) See single line drawing as Attachment 2. All interconnection equipment electrically located on the utility side of the Interconnection Point shall be owned, operated, and maintained by Idaho Power. Estimated Cost & Ownership The following good faith estimates are provided in 2012 dollars: llnterconn~c~!,~,!?._Fa_c:_!Hties: --·-.. ~ hPc -·--j !overhead Generation Interconnection Packa.9e & Line Extension $145,0001 !underground Equiprr1ent and 1000 kVA Transformer hPc -'I $75,000i ! SUBTOTAL --.I i $220,000i -·---- lrsee ATTACHMENT 6for Project Grand Total) ! j Full payment is required up front in accordance with Schedule 72, unless payment arrangements are made in advance with Idaho Power Operations Finance (see Attachment 3). Billing for construction activities will be based upon actual expenditures. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 1 of 1 Attachment 2 One-line Diagram Depicting the Small Generation Facility, interconnection Facilities, Metering Equipment and Upgrades Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 1 of 1 Attachment 3 Milestones Idaho Power Company agrees only to the Construction timelines under its direct control provided in the Facility Study Report for this Project. These milestones will begin, and the construction schedule referenced below, will only be valid upon receipt of funding in full from the Seller or their authorized third party no later than the date set forth below for such payment. Additionally, failure by Seller to make the required payments as set forth in this Agreement by the date(s) specified below will be a material breach of this Agreement, which may result in any or all of the following: (i) loss of milestone dates and construction schedules set forth below: (ii) immediate termination of this Agreement by Idaho Power; (iii) removal from the generator interconnection queue. Critical milestones and responsibility as agreed to by the Parties: :D.'tl\'' ' ' 10/1/2012 10/1/2012 12/10/2012 12/31/2012 12/31/2012 12/31/2012 12/31/2012 12/31/2012 Agreed to by: For the Seller: For the Transmission Provider Idaho Power Company w,:q;r11"\1tlr.!'l· . :filiW· l~llf'm•:lfl'O · Seller IPCO receives the remaining balance of Construction estimate $220, 000 OR Credit arrangements are approved by_IPCO IPCO Long Lead Time Material Ordered (approximately 8-10 week lead time) IPCO IPCO Construction Complete IPCO IPCO Commissioning Complete IPCO Project Leader issues Construction Complete Letter IPCO Director of Load Serving Operations authorizes project to be energized, upon verification that Seller has previously met Schedule 72, Sec 7 Insurance requirements Seller Seller testing begins Seller Seller's requested In-Service Date Date. _____ _ Date _____ _ Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 4 Additional Operating Requirements for the Company's Transmission System and Affected Svstems Needed to Support the Seller's Needs The Company shall also provide requirements that must be met by the Seller prior to initiating parallel operation with the Company's Transmission System. Operating Requirements The project is required to comply with the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992 IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems or any subsequent standards as they may be updated from time to time. Seller will be able to modify power plant facilities on the generator side of the Interconnection Point with no impact upon the operation of the transmission system whenever the generation facilities are electrically isolated from the system and a terminal clearance is issued by Idaho Power Company's Grid Operator. Voltage flicker at startup and during operation will be limited to less than 5% as measured at the Interconnection Point. It is preferable to bring each generating unit online separately to minimize voltage flicker on the distribution system. Low Voltage Ride Through The Project must be capable of riding through faults on adjacent section of the power system without tripping due to low voltage. It has been determined, through study, that the Project must be capable of remaining interconnect for any single phase voltage as low as 0. 7 PU for 30 cycles, and for all three phase voltages as low as 0.8 PU for 30 cycles. "As-Built" Generation Interconnection Data Modifications of the interconnection equipment or material changes for the Seller's generator facility that results in changes to modeling data (steady state data and dynamics data) previously submitted by the Seller for the System Impact Study requires prior approval from Idaho Power Company in order to validate that the System Impact Study results remain valid for the modified equipment or material changes to the facility. Validation of these results may require additional SIS re-study work. Should Seller make any changes to facility that were not considered in any studies or outlined in this agreement, Idaho Power reserves the right to delay interconnection until any applicable re-study work has been completed and approval has been granted. The Seller is encouraged to notify Idaho Power Company of such changes as soon as possible in order to minimize potential delays in energization of the Project. Equipment settings determined during final commissioning of the generator facility that are represented in the Transmission Provider's network models shall be provided by the Seller within 30 days following the date of commercial operations. Such settings include but are not limited to interconnection transformer energized tap position, load tap changer control settings, control setpoints (pickup level and time delay) of automatic switching schemes for static reactive power equipment, and final control characteristics of dynamic reactive power equipment. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29, Tariff No. 101 Page 1 of 1 Attachment 5 Reactive Power Requirements The project must be controlled to operate at unity power factor+/-200 kVAr. Voltage flicker at startup and during operation will be limited to less than 5% as measured at the Interconnection Point. Idaho Power Company Generator Interconnection Agreement# 307 I.P.U.C. No. 29. Tariff No. 101 Page 1 of 1 Attachment 6 Companv's Description of Special Facilities and Upgrades Required to Integrate the Generation Facilitv and Best Estimate of Costs As provided in Schedule 72 this Attachment describes Upgrades, Special Facilities, including Network Upgrades, and provides an itemized best estimate of the cost of the required facilities. Substation Upgrades $0 Distribution Upgrades $0 Transmission Upgrades $0 Upgrades The following good faith estimates are provided in 2012 dollars: ·--·--·'--------- BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 53 Clark, Danielle From: Harris, Joshua Sent: To: Monday, October 08, 2012 2:21 PM Clark, Danielle Subject: FW: Swager Farms (GI 307) Interconnection Agreement Thanks, Josh Harris OPERATIONS ANALYST Idaho Power I Generator Interconnection 208-388-5751 Email jharris@idahopower.com From: Walker, Donovan Sent: Thursday, September 20, 2012 4:39 PM To: 'lwhite@exergydevelopment.com' Cc: Harris, Joshua; Blackburn, Rex; Allphin, Randy; Anderson, John; Park, Tessia Subject: RE: 'Swager Farms (GI 307) Interconnection Agreement Ms. White, There has been no discussion, and absolutely no agreement from Idaho Power to extend the Scheduled Operation Date from the PPA for this project, as you have referred to in conversation with Idaho Power's Josh Harris, and as you refer to below. The Scheduled Operation Date for the project remains October 1, 2012. This date will obviously not be met, and consequently under the terms of the PPA a 90 cure period will commence. Idaho Power, through Josh Harris' communication and forwarding of a GIA to you last week, extended an option for the project to proceed with the required interconnection work, and a commitment from Idaho Power that it would have its required work completed by year end, 2012, IF the project executes the final GIA AND pays the required funding NO LATER THAN OCTOBER 1, 2012. Mr. Harris' letter of September 14, 2012, states clearly that in order to take advantage of this expedited process and construction, you must authorize Idaho Power to move forward by executing the GIA and paying the required funding no later than October 1, 2012. If this date is missed, then it will not be possible to complete the required interconnection work before the end of the year 2012. We look forward to your response. Donovan E. Walker LEAD COUNSEL Idaho Power I Legal 208-388-5317 -------------------- From: Harris, Joshua Sent: Wednesday, September 19, 2012 9:55 AM 1 To: Darrington, Michael; Allphin, Randy; Walker, Donovan Subject: FW: Swager Farms (GI 307) Interconnection Agreement FYI. Thanks, Josh Harris OPERATIONS ANALYST Idaho Power I Generator Interconnection 208-388-5751 Email jharris@idahopower.com From: Leslie White [mailto:lwhite@exerqydevelopment.com] Sent: Tuesday, September 18, 2012 9:54AM To: Harris, Joshua Subject: RE: Swager Farms (GI 307) Interconnection Agreement Hello Josh, Thank you for sending this offer. My understanding from talking to James this morning is that Roy Eiguren met with IP yesterday on our behalf and that that discussion has been tabled for a few days. I'll need to see the outcome of that conversation to give you some direction on this offer. Regards, Leslie Leslie White 802 W Bannock, 12th Floor Boise, ID 83702 Office: 208.336.9793 1 Mobile: 208.890.4660 ~YY!Y:!..GXQT.gy(tQYQI9J!t!)f).TJL991I.\ This electronic or printed document contains information which (a) may be LEGALLY PRIVILEGED, PROPRIETARY IN NATURE, OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only For the use of tl1e Addressee(s) named above. If the reader of this message is not the intended recipient, or the employee or agent responsible to deliver it to the intended recipient, you are he1 eby notified that any dissemination. distribution or copying of this communication is strictly prohibited, If you have received this communication in error. please immediately notify us by telephone, and return the original message to us at the above email address Thank you From: Harris, Joshua [mailto:JHarris@idahopower.com] Sent: Friday, September 14, 2012 10:17 AM To: Leslie White Cc: Hackett, Eric; Park, Tessia; Sloan, Aubrae; Walker, Donovan; Allphin, Randy; Darrington, Michael Subject: Swager Farms (GI 307) Interconnection Agreement Leslie, The attached is being sent to you in the mail today. Please let me know if you have any questions. Thanks, Josh Harris OPERATIONS ANALYST Idaho Power I Generator Interconnection 2 1221 W. Idaho Street I Boise, Idaho I 83702 Work 208-388-5751 Fax 208-433-3571 Email jharris@idahopower.com This transmis~ion may contain information that is privileged, confidential and/or exempt from disclosure under applicable law. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution, or use of the information contained herein (including any reliance thereon) is STRICTLY PROHIBITED. If you received this transmission in error, please immediately contact the sender and destroy the material in its entirety, whether in electronic or hard copy format. Thank you. 3 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 54 Clark, Danielle From: Walker, Donovan Sent: To: Monday, October 08, 2012 11 :31 AM Clark, Danielle Subject: FW: digester meeting on Friday From: James Carkulis [mailto:jcarkulis@exergydevelopment.com] Sent: Thursday, September 27, 2012 1:46PM To: Walker, Donovan; Leslie White; Laura Knothe; Harris, Joshua Cc: Blackburn, Rex; Allphin, Randy; Darrington, Michael; reiguren@idaho-politics.com; rriley@hawleytroxell.com Subject: Re: digester meeting on Friday Thanks. From: Walker, Donovan [mailto:DWalker@Idahopower.com] Sent: Thursday, September 27, 2012 01:43 PM To: James Carkulis; Leslie White; Laura Knothe; Harris, Joshua <JHarris@idahopower.com> Cc: Blackburn, Rex <RBiackburn@idahopower.com>; Allphin, Randy <RAIIphin@idahopower.com>; Darrington, Michael <MDarrington@idahopower.com>; 'reiguren@idaho-politics.com' <reiguren@idaho-politics.com>; 'rriley@ hawleytroxell.com' < rriley@hawleytroxell.com > Subject: Re: digester meeting on Friday I have us scheduled for 9:30a.m. tomorrow. See you then. Donovan. From: James Carkulis [mailto:jcarkulis@exergydevelopment.com] Sent: Thursday, September 27, 2012 01:03 PM To: Walker, Donovan; Leslie White <lwhite@exergydevelopment.com>; Laura Knothe < lknothe@exergydevelopment.com >; Harris, Joshua Cc: Blackburn, Rex; Allphin, Randy; Darrington, Michael; reiguren@idaho-politics.com <reiguren@idaho-politics.com>; rriley@hawleytroxell.com < rriley@hawleytroxell.com > Subject: Re: digester meeting on Friday We shall meet tomorrow. From: Walker, Donovan [mailto:DWalker@Idahopower.com] Sent: Thursday, September 27, 2012 11:43 AM To: James Carkulis; Leslie White; Laura Knothe; Harris, Joshua <JHarris@idahopower.com> Cc: Blackburn, Rex <RBiackburn@idahopower.com>; Allphin, Randy <RAIIphin@idahopower.com>; Darrington, Michael <MDarrington@idahopower.com>; 'reiguren@idaho-politics.com' <reiguren@idaho-politics.com>; 'rriley@ hawleytroxell.com' < rriley@ hawleytroxell.com > Subject: RE: digester meeting on Friday James, Idaho Power takes significant issue with your "first I heard" statement below. Your statement and inferences that there was some kind of agreement to move the dates in the PPA for the digesters, as part of the agreement reached with regard to the wind projects is absolutely not correct. Mr. Eiguren and Mr. Riley were both present as your attorneys at a meeting on August 14, 2012, with myself and Mr. Williams, on behalf of Idaho Power, to finalize the paperwork on the 1 settlement agreement for the wind projects. Mr. Riley attempted to present terms in those agreements related to the digesters. When I questioned him about it and informed him that there had been no agreement and no discussion related to the digesters, Mr. Eiguren stepped in and told Mr. Riley that the digesters were not part of the discussions that he and Rex Blackburn had previously had regarding termination of the wind PPAs, were not part of the agreement and settlement reached related to the wind projects, and were separate matters that had not been discussed, much les~ agreed to by the parties. In addition, Mr. Blackburn and myself again informed Mr. Eiguren on September 24, 2012, that there had been no discussion and no agreement to change the PPA dates for the digesters, and further that Idaho Power was not willing to agree to changes in those dates. Simply put, your agents-Messrs. Eiguren and Riley-will confirm that there was no agreement reached to modify the digester PPA agreements, and that Idaho Power expressly rejected any proposal to do so. If the purpose of your requested meeting tomorrow is to discuss modification of the terms of the digester PPAs, the meeting is not necessary. I previously advised Exergy, in writing, on September 20, 2012, that Idaho Power is not in agreement to amending these agreements. Additionally, as stated below, Idaho Power has offered Exergy an expedited schedule that would allow us to complete the required interconnection facilities prior to the end of this year-contingent upon Exergy authorizing Idaho Power to proceed with such work no later than Monday October 1, by paying the required deposit and executing the GIA. With the above in mind, please advise as to whether there is a need for us to meet tomorrow. -Donovan ------------------------ From: James Carkulis [mailto:jcarkulis@exergydevelopment.com] Sent: Thursday, September 27, 2012 9:35AM To: Walker, Donovan; Leslie White; Laura Knothe; Harris, Joshua Cc: Blackburn, Rex; Allphin, Randy; Darrington, Michael Subject: Re: digester meeting on Friday Meeting tomorrow at 9:30 shall be fine. I should be back from North Carolina by then. However, first I heard about something different than what was agreed to as the Term Sheet presented for settlement was an email to Leslie last Friday. Thanks James From: Walker, Donovan [mailto:DWalker@Idahopower.com] Sent: Thursday, September 27, 2012 08:48AM To: James Carkulis; Leslie White; Laura Knothe; Harris, Joshua <JHarris@idahopower.com> Cc: Blackburn, Rex <RBiackburn@idahopower.com>; Allphin, Randy <RAIIphin@idahopower.com>; Darrington, Michael <MDarrinqton@idahopower.com> Subject: RE: digester meeting on Friday James, Idaho Power can meet with you on Friday. Could we make it at either 9:00 or 9:30a.m.? Also, as previously indicated, Idaho Power has been clear that it will not agree to change the dates in the PPA. Idaho Power has offered an expedited schedule for the construction of the required interconnection facilities, and will commit to completing that work by the end of the year IF you authorize Idaho Power to proceed no later than Monday, October 1, by paying the required deposit and executing the GIA. 2 Please let me know if you can make it at 9:00 or 9:30a.m. tomorrow. Thanks, -Donovan From: James Carkulis [mailto:jcarkulis@exergydevelopment.com] Sent: Thursday, September 27, 2012 5:38AM To: Walker, Donovan; Leslie White; Laura Knothe; Harris, Joshua Subject: digester meeting on Friday Donovan: I would like to request a digester meeting on Friday around 10 AM please to sort this out. Thanks. James James T Carkulis 802 W Bannock, 12th Floor Boise, ID 83702 Office: 208.336.9793 I Mobile: 406.459.3013 jca rkulis@exergydeve lopment. com www .exer gydeveloprnent.com This electronic or printed document contains information which (a) may be LEGALLY PRIVILEGED, PROPRIETARY IN NATURE, OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) named above. If the reader of this message is not the intended recipient, or the employee or agent responsible to deliver it to the intended recipient. you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. If you have received this communication in error, please immediately notify us by telephone. and return !he original message to us at the above ernaii address. Thank you. This transmission may contain information that is privileged, confidential and/or exempt from disclosure under applicable law. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution, or use of the information contained herein (including any reliance thereon) is STRICTLY PROHIBITED. If you received this transmission in error, please immediately contact the sender and destroy the material in its entirety, whether in electronic or hard copy format. Thank you. 3 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 55 Clark, Danielle From: Sent: To: Subject: Walker, Donovan Monday, October 08, 2012 11 :29 AM Clark, Danielle FW: New Energy 2 and New Energy 3 From: James Carkulis [mailto:jcarkulis@exergydevelopment.com] Sent: Friday, September 28, 2012 11:40 AM To: Walker, Donovan; Harris, Joshua; Leslie White; Laura Knothe Subject: New Energy 2 and New Energy 3 Donovan: Thank you for the time today. Not sure I will stand for more insults though. I would venture to say Rex's reputation also precedes him. So we shall not be taking the expedited interconnection process for Swager. Let's proceed under normal circumstances. As to the PPAs, I think it best that we file our force majeure positions on those based on the generic PURPA docket going on. Hopefully, we can resolve both of these outside ofthe courtroom. Thanks. James )... .x~rgy • James T Carkulis 802 W Bannock, 12th Floor Boise, 10 83702 Office: 208.336.9793 I Mobile: 406.459.3013 , jcarkulis@exergydevelopment.com \Nifvw.exergydevelopment.com This electronic or printed document contains information wl1ich (a) may be LEGALLY PRIVILEGED, PROPRIETARY IN NATURE. OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) narned above If tile reader of this message is not the intended recipient, or lhe employee or agent responsible to deliver it to the intended recipient. you are hereby notified that any dissemination, distribution or copyrng of this communication is strictly prohibited If you have received this communication in error, please immediately notify us by telephone, and return the originai message to us at ttle above email address Thank you 1 - BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 56 From SeJier: NOTICE OF F0RCE MAJEURE UNDER A .{>-)...._ , ~,~S~:,~ g y FIRM ENERGY SALES AGREEMENTS DATED MAY 24, 2010 RE: SWAGER FARMS PROJECT (#31616130) DOUBLE B DAIRY PROJECT (#31616120) New Energy Two, LLC New Energy Three, LLC c/o Exergy Development Group of Idaho, LLC 802 W. Bannock Ste. 1200 Boise, II> 83702 Attn: James Carkulis Email:. jcarkulis@exergydevelopment.com To Idaho Power: Vice President, Power Supply Idaho Power Company With copy to: PO Box 70 Boise, Idaho 83707 Email: I grow@ idahopower.com Cogeneration and Small Power Production Idaho Power Company POBox 70 Boise, Idaho 83707 Email: rallphin@ idahopower.com Date: September 28, 2012 VIA EMAIL, HAND DELIVERY AND REGULAR MAIL In accordance with Article XIV (Force Majeure) of the Firm Energy Sale Agreements referenced above (hereinafter, collectively, the "FESA"), Seller hereby gives Idaho Power written notice of the occulTence of a Force Majeure event, in the following particulars: 1. There are currently ongoing proceedings upon the IPUC docket, the issues in which include pricing, size, duration and curtailment. (See, e.g., IPC-E-11-15.) 2. The pending proceedings concern, among other things, the unilateral amendment by Idaho Power of FESA provisions regarding (i) ownership of Green Tags and Renewable Energy Certificate(s) (RECs), or equivalent environmental attributes, and (ii) Suspension of Energy Deliveries (Curtailment). Exergy Development Group 802 W Bannock, 1 2•h Floor Bo1se, ID 83 702 P 208.3 36 9793 F 2 08.3 36.94 31 ;._ t t )..... l/)/ .. ··~ 3. The overall effect of the pending proceedings is that until such proceedings are finally resolved, the entire circumstance of continued viability of all renewable energy projects in Idaho is undecided and beyond the control of Seller. Indeed, the ultimate decisions made may render Seller wholly or in part unable to perform its obligations under the FESA. 4. A consequence of the pending proceedings, perhaps unintended, but certainly beyond the control of Seller, is that renewable energy project lenders are unwilling to lend in Idaho pending the outcome of these proceedings. There is, therefore, no financing available, making it impossible for Seller to pelform its obligation under the FESA. Accordingly, by this written notice to Idaho Power, Idaho Power is advised that a Force Majeure event has occurred, thereby creating a suspension of performance for the duration of the event, as further described in Article XIV of the FESA. Further, pursuant to Section 19.1 (Disputes) of Article XIX of the FESA, if Idaho Power disputes this matter, Seller reserves the right to submlt the same to the Idaho Public Utilities Commission and/or pursue any resolution to which it may be entitled before the appropriate Idaho district court, FERC and/or any other applicable tribunal or governing body. Further, Seller asserts that it is protected from any default under the FESA pending resolution of the asserted Force Majeure issues, including, without limitation, any dispute or litigation as to whether said Force Majeure Event does protect Seller from any such default. SELLER: New Energy Two, LLC ::w ~~ Leslie White Member cc: Donovan E. Walker. Esq. James CarkuJis Laura Knothe Brian L. Ballard, Esq. Exergy Development Group 802 W Bannock, 12th Floor Boise, ID 83702 P 208.336.9793 F 208.336.9431 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 57 ·. October 1, 2012 New Energy Two, LLC c/o Exergy Development Group of Idaho, LLC Attention: Laura Knothe 802 W. Bannock, 12th Floor Boise, ID 83 702 Sent Via: Email, Certified Mail Swager Farms Project Operation Date-Project #31616130 Dear Ms. Knothe: IDAHO POWER® An IDACORP Company The Finn Energy Sales Agreement (FESA) between Idaho Power Company and your Swager Farms anaerobic digester project dated May 24, 2010 established a Scheduled Operation Date of October 1, 2012. As required in Article 5.3.1 ofthe FESA, "if the Operation Date occurs after the Scheduled Operation Date but on or prior to 90 days following the Scheduled Operation Date, the seller shall pay Idaho Power Delay Liquidated Damages calculated at the end of each calendar month after the Scheduled Operation Date". Article 5.3.2 states, "If the Operation Date does not occur within 90 days following the Scheduled Operation Date, the Seller shall pay Idaho Power Delay Liquidated Damages, in addition to those provided in paragraph 5.3.1, calculated as follows: Forty five dollars ($45) multiplied by the Maximum Capacity with the Maximum Capacity being measured in kW". The FESA also stipulates in Article 5.4 that if New Energy Two fails to achieve the Operation Date within 90 days following the Scheduled Operation Date, such failure will be a Material Breach and Idaho Power may terminate the FESA at any time until the Seller cures the Material Breach. Idaho Power received your September 28, 2012, letter claiming a force majeure event has occurred. Idaho Power does not agree with your claim-that pending matters at the Idaho PUC, or your lack of ability to finance a project/projects are valid events of force majeure pursuant to the FESA. As of October 1, 2012, Idaho Power has not received a request for an Operation Date or any information that would allow Idaho Power to grant an Operation Date for the Swager 1 of2 Farms project from New Energy Two, LLC. Therefore, Idaho Power wiH begin calCulating Delay Liquidated Damages as specified in the FESA. If you have any question~ pleas·e do not h:esi tate to contact me. Sincerely, Michael Darrington Energy Contracts Idaho Power (208)3 88-5946 mdarrington@idahopower.com c;q: Dooov<:ttl: Wall<~r (TPC) Randy AlLphin (fPC} Josh Banis (JPC) ··· James Carktili$ (~,cergy) Leslie White (New Ertergy Two) 2 of2 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 58 October 2, 2012 Leslie White Exergy New Energy 802 W. Bannock 1th Floor Boise, ID 83702 IDAHO POWER® An IDACORP company Re: Swager Farms Dairy Digester Project (0.8 MW Output) Draft Facility Study-Report-Project #307 Dear Ms. White: ' . Given Exergy's recent election not to proceed with an expe,dited Generator Int~rconnection Agreement (GIA) as offered by Josh Harris on September 14, 2012, I have attached the Draft Fa~ility Study Report (FSR) for the subject project. In order to proceed with this project, please provide your comments to the FSR to me by November 1, _....,' 2012 and indicate whether you wish to pro~eed with final design ;1p.d construction. The final report will be used to prepare a draft GIA in preparatioif for Construction. Josh:Harris will be working with you to finalize the Interconnection Agreement. ' -;c, ' · ' -' Before we can begin Construction or order materials, you are responsible for contacting Idaho Power's credit department to discuss GP~_w_t requirements for construction futl.ding. Please contact Aubrae Sloan (208-388-5697) at your earliest con~enience. Once we receive funding, or the credit requirement is met, we can proceed with conStruction of!he•project. 1 i . The actual construction and hibor charges will be finalized approximately 90 days subsequent to project completion. We will-r;econcile ·~y bv~r~ br l.inderpayment at that time. I look forward to hearing from you soon.' Sincerely, Eric Hackett Project Leader Attachment: Swager Farms Dairy Digester Project Draft Facility Study Report with Drawings Cc: J Harris/IPC A Sloan/IPC D W alker/IPC An IDACORP Company DRAFT I Generator Interconnection Facility Study Report for the Swager Farms Dairy Digester Project-Project #307 ' · l oa:- Exergy New Energ¥ ill T,win Falls County, Idaho October 2, 2012 1. DRAFT-FACILITY STUDY REPORT (FSR) Swager Farms Dairy Digester Project #307 October 2, 2012 General Facility Description The proposed project will consist of a short three-phase distr~bution ·line extension and Idaho Power's overhead generation interconnection package (for projects less than 1 MVA) including an overhead recloser, metering package, local service power transfornier-, disconnect switches, and a relay/control box. Additionally, one 1000 kVA 277/480to 12.47 kV:Grounded Wye I Grounded Wye padmounted transformer will be installed, including the 'associated··~derground cabling and vaults. The project is located in Twin Falls County;,Jdaho a~d connects to. the 12.5 kV system on Idaho Power Company's Clover (COVR-012) distribution line:. The total projeCt output is 0.8 MW. Interconnection Customer: Leslie White Exergy New Energy 802 W. Bannock 121h Floor Boise, ID 83 702 A Standard Generator JnterconnecJion Agreem.enl under Idaho Power Company's Open Access Transmission Tariff.(OATT) or $chedule 72 between Interconnection Customer and Idaho Power Company -Delivery (Transmission Owner) for the Swager Farms Dairy Digester Project, specifically Generator Interconnection Project #30}, will be prepared for this project. 1.1 Interconnection Point The interconnection Point for the Swager Farms Dairy Digester Project will be the low-side bushings on the padmounted transformer (SWl). The project's location is in TlOS RISE Section 21 of Twin Falls County, Idaho. A drawing identifying the Interconnection Point is attached. 1.2 Point of Change of Ownership The Point of Change of Ownership for the Swager Farms Dairy Digester Project will be the low­ side bushings on the padmounted transformer (SWl). 1.3 Customer's Interconnection Facilities The Interconnection Customer will install generators, low-side disconnect switches, all wiring and conduit between the generators and the padmounted transformer, appropriate grounding measures, and associated auxiliary equipment. Interconnection Customer will build underground facilities to the Point of Change of Ownership for the generator facility. 1 The low-side disconnect switch shall be as specified or as determined by mutual agreement and be readily accessible, operable, and lockable by Idaho Power personnel at all times. 1.4 Other Facilities Provided by Interconnection Customer 1.4.1 Ground Fault Equipment The customer will install ground fault limiting equipment that will limit the zero sequence fault current to 20 amps at the Interconnection Point. 1.4.2 Easements . The Interconnection Customer will provide to Idaho' Pciwer a surveyed (Metes & Bounds) legal description along with exhibit map. for Idaho Power's proposed facilities. After the legal description ha been Clelivei-ect to IPCO for review, IPCO will supply to the lnterconnection Cu tomet. a com leted IPCO easement for signature by. the land owne~ of record. ~m.ce tlie signatures ~?lve been sec~red, the lnterconnectwn Customer will return s1gned easement to tC@ for recordmg. 1.4.3 Local Service The Interconnection Customer is responsible to arr~nge for local service to their site, as necessary. 1.4.4 Monitoring Information ·.·. . . . . . . If the Interconnection Custcnt~erTe · uires the abilitY'J~~~monitor information related to the Idaho Power recloser in the generation intercon,nection package they are required to supply their ?wn cabling/wir:in,g to•'the contto! hox. 1.5 Idaho Power Company's Interconnection Facilities Idaho Power will install a generation intercoimection package on the existing distribution feeder (COVR-012) on private property .southeast of the intersection of E. 3800 N. and N. 17QO .E~ in.Twin Falls County, ID. See'the attached work order maps (WO 27328106, sheet 1·of 1) for details.' •··:• ., I ... The new interconnection packag~ will include four distribution poles to mount a local service transformer, solid blade disconnects, primary metering package, recloser, relays, fuses and riser necessary for the package. The interconnection will be controlled by a SEL-547 line protection relay. The relay will be located in a pole mounted enclosure and will also contain a test switch (TS4), isolation interface, power supply, DC converter, control switch and surge protector. Idaho Power will install (and subsequently own and maintain) one 1000 kVA 277/480 to 12.47 kV Grounded Wye I Grounded Wye padmounted transformer on top of a vault. Conduit and underground cables will be installed from the interconnection package to padmounted transformer. Protective posts will be installed to protect the ground mounted equipment from damage. A 2" conduit will be installed alongside the underground primary to facilitate information exchange to the customer about the recloser if desired. (The Interconnection Customer is responsible for providing and installing the appropriate cable.) 2 1.6 Facility Estimated Cost: The following good faith estimates are provided in 2011 dollars: ~Overhead Q.ene!.~tion Interconnection Package & Line Extensio~ _ rP_g__ $145,000i ---t--------'-----·-·-1 $75,0_Q_Qj $220,0.!!Qj !Underground Equipment and 1000 kVA Transformer IPC ,.-~·----_, ___ , SUBTOTAL1 !$..'!.1!.&!..~.~~0...11. §for" the Project Grand Total ~--"--···-·---:----·· .. ···-·-.. ·"'" --"~ IPCO Commissioning Complete TBD by seller Cornmercia/ Operation Date These milestone dates assume that material ·can be ~pro.cured (\:IJd labor resources are available. Additionally, any permitti ng )~ues outside ttle, inimediate control of Idaho Power could also influence the Commercial 0penitio r • ate. ' .,_,, ---··· -.,.------.-,---· 3. Operating-Requiremeots " - The project 1is' ~·~qn ired to~comply witl.1 the applicable Voltage and Current Distortion Limits found in IEEE Standard 519-1992' )EEE Recommended Practices and requirements for harmonic Control in ElectriCdl.f_o,wer Systems qt 'any subsequent standards as they may be updated from time to time. Voltage fli&k~r at startup auq during'operatio.n must be limited to less than 5% as measured at the Interconnecti6ri::-.roint. ' •.!· The Project must b~c~'p?-bl{ofriding through faults on adjacent section of the power system without tripping due to low vOft~ge. It has been determined, through study, that the Project must be capable of remaining interconnected for any single phase voltage as low as 0.7 PU for 30 cycles, and for all three phase voltages as low as 0.8 PU for 30 cycles. Interconnection Customer will be able to modify power plant facilities on the Interconnection Customer side of the Interconnection Point with no impact upon the operation of the transmission or distribution system whenever the generation facilities are electrically isolated from the system and a terminal clearance is issued by Idaho Power Company's Grid Operator. 3 4. Reactive Power The Project must be controlled to operate as a VAr neutral system with a ± 200 kVAr operating band. 5. Upgrades 5.1 Distribution Upgrades Idaho Power will extend the existing distribution feeder (COVR-012) approximately 360 feet to the east (just north of the ponds) on private property to facilitate ·and locate the Interconnection Facilities. . 6. Estimated Costs The following good faith estimates are provided in"10 12 dollars: ------ "::-::1 $145,000! $75,000 $220,000 GRAND TOTAL $220,000J -~ ~--------------~~~~~~~~ ____ ] Note Regarding Transmissi'or;J :~~rvice: ... ··-. ·; .. ·, ·- This FacilitY ·s:tudy is a Network Reso~~~ Interconnection Facility Study. This study identifies the facilities necessary .to integrate the: Generating Facility into Idaho Power's network to serve load within Idaho Power's balaricing area. Network Resource Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery. 4 I ~- - - - -- -- - - - + -- - - - - - - -- - - 3 • I I 2 CO V R 01 2 12 .5k V BY IP C O BY O. , _ , E R P- H Mf ~ --~ r - : ~[ ~ ~ ! ~ ~ _ } _ ~ ] an : ~ = J & X · I 6D0 - 15 I 56 0 - . } 5 t- - - -- -- - . - - - 2: -- o ' : : ~~ ~ ! 12 K A 1 I 1 3 t r-x . - o r - - T - l t w•• • l ~ : I : ! ! ,, . v . L- ~ - - - ~ r - - _j t ";' " os , "( ' 72 0 0 - 1 2 0 / Z < O V J., \I> V A .., I t2 1 ~ ~( 1 0 - 1 2 0 / H O V l 52 G 1 c B ~I I I "1 ~ ~I gl L '" ' " J I I -- - , . ® - - - - i !PC O LO C A L SE R V J C E FO R SE l 5 4 7 BO X L , 80 0 k W CA 1 U I P k U R CJI S U ... . , . . . . _ . CO l H 4 1 C R PR O J E C T LO C A T I O N : TIO S , RIS E , SE C T I O N 21 36 0 0 NO R T H 17 0 0 EA S T , TW I N FA U.S CO U N T Y , ID A H O IN SE R V I C E BY 12 - 3 1 - 2 0 1 2 j 1 s •-u m - 1 7 s ·- · .. ~· RE VI SJ D N .. . . Q iu l • -. . , m - l!o o o I'll .. . . _ ~ , .. . . . Ow , ,~ l J ' ; i J ' !I ... DJ • D c SIN G l E LIN E N~ ' R O V A L ,. _ . . , . , . . __ :M I I I I u , ; - . _ _ _ :.j l : l l . . l ' n l f j . t - - -­ l:' ! ' . . . , t . , : ... _ _ !-' "' ~ ' - ­ "" " .. . . . . . l .. . . . . -- - - a ~i - ' l ta M " __ , ... . . __ . __ , r'f f i ! EN C E - Q -RA ' .. . . -- ­ .. . . . . - -- .. __ _ _ _ W'l. ~'J l . U I . l l W:. $ M I I A T T C : S Cl) l r ( T R O I , $ C H ( W A 1 J C S SWA G E R FA R M S DA I R Y DI G E S T E R ~ IN T E R C O N N E C T I O N SIN G L E LI N E mA H O POO E I ! tlW A I I Y Proposed Location for Distribution Upgrades and Interconnection Facilities Green = Distribution Upgrades Yellow = Interconnection Facilities (Interconnection Package) Red= Interconnection Facilities (Underground Cables and Vaults) Purple = Interconnection Facilities (Padmounted Transformer) BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-12-25 IDAHO POWER COMPANY ATTACHMENT 59 Walker, Donovan To: Cc: Subject: From: Harris, Joshua Harris, Joshua; Park, Tessia Hackett, Eric; Georgeson, Keith; Darrington, Michael; Anderson, Kathleen RE: Draft FSR for Swager Farms Gl#307 -------------- Sent: Thursday, November 01, 2012 10:27 AM To: Walker, Donovan; Park, Tessia Cc: Hackett, Eric; Georgeson, Keith; Darrington, Michael; Anderson, Kathleen Subject: FW: Draft FSR for Swager Farms GI#307 From: Leslie White [mailto:lwhite@exerqydevelopment.com] Sent: Thursday, November 01, 2012 9:58AM To: Hackett, Eric; Harris, Joshua Cc: James Carkulis; Laura Knothe Subject: RE: Draft FSR for Swager Farms GI#307 Good morning Josh and Eric, With regards to the draft FSR for Gl #307 and the draft GIA for Gl #390, Exergy provided IPCo with a notice of Force Majeure on September 281h. As mentioned in the notice a consequence of the pending I PUC proceedings is that renewable energy project lenders are unwilling to lend in Idaho. Therefore with regards to the current status of Gl#307 and Gl#390 we will remain ready to proceed with both pending documents upon resolution of the matter at the I PUC, but until that time I do not see the value in submitting comments to the FSR or GIA. I appreciate your continued work on these projects and look forward to finding a path forward. Please give me a call if you have any questions. Leslie leslie White 802 W Bannock, 12th Floor Boise, ID 83702 Office: 208.336.9793 1 Mobile: 208.890.4660 ~~~·~~\j_.§.YU r~}VCl f~i/8 [ 0 p rn_~~lJ..LS~OI11 This electronic or printed document contains information which (a) may be LEGALLY PRIVILEGED, PROPRIETARY IN NATURE. OR OTHERWISE PROTECTED BY LAW FF~OM DISCLOSURE and (b) is intended only for the use of the Addressee(s) named above. If the reader of this message is not the intend8d recipient. 01 the employee or agent responsible to deliver it to the intended rec;pient, you are hereby notified that any dissemination. distribution or copymg of this communicat•on is strictly prordbited If you have rec<'li•1ed this communicc;tion •n error, please immediately notify us by telephone, and return the original message to us at the abovfl amail address. H!ank you. From: Hackett, Eric [mailto:EHackett@idahopower.com] Sent: Wednesday, October 03, 2012 9:24AM To: Leslie White Cc: Harris, Joshua; Walker, Donovan; Sloan, Aubrae Subject: Draft FSR for Swager Farms GI#307 Leslie, Please see attached . 1 Eric Hackett, P.E., PMP ENGINEERING LEADER, COST & CONTROLS Idaho Power I Delivery Projects 1221 W. Idaho St. I Boise, ID I 83702 Work 208-388-5712 Mobile 208-283-2720 Email ehackett@idahopower.com This transmission may contain information that is privileged, confidential and/or exempt from disclosure under applicable law. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution, or use of the information contained herein (including any reliance thereon) is STRJCTL Y PROHffiiTED. If you received this transmission in error, please immediately contact the sender and destroy the material in its entirety, whether in electronic or hard copy format. Thank you. 2