HomeMy WebLinkAbout20120601order_no_32552_errata.pdfOffice of the Secretary
Service Date
June 1,2012
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION )
OF IDAHO POWER COMPANY FOR )CASE NO.IPC-E-12-17
AUTHORITY TO IMPLEMENT POWER )
COST ADJUSTMENT (PCA)RATES FOR )ERRATA TO
ELECTRIC SERVICE FROM JUNE 1,2012 )ORDER NO.32552
THROUGH MAY 31,2013
___
)
On May 31.2012.IPUC Order No.32552 was issued by this Commission.The
following change(s)should be made to that Order:
Page 2,Paragraph 2.lines 7-9:
READS:
“In last year’s rate case,the Commission determined that the Company
should recover 100%of its demand-side management (DSM)incentive and
conservation costs as part of the PCA.”
SHOULD READ:
‘in last year’s rate case,the Commission determined that the Company should
recover 100%of its demand response incentive costs as part of the PCA.”
Page 4.Paragraph 1,lines U2:
READS:
“4.Other Adjustments.This year’s PCA Application includes two other
adjustments to the projected power cost adjustment (in addition to the DSM
adjustment mentioned above).”
SHOULD READ:
“4.Other Adjustments.This year’s PCA Application includes two other
adjustments to the projected power cost adjustment (in addition to the demand
response adjustment mentioned above).”
DATED at Boise,Idaho this I day of June 2012.
/1 f):/..
fV
Jean D.Jewell
Càmmission Secretary
bls/O:IPC-E-1 2-1 7c1h2 Errata