HomeMy WebLinkAbout20120305Grow Direct.pdft:[ — BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION OF IDAHO POWER COMPANY FOR AUTHORITY TO INCREASE ITS RATES )CASE NO.IPC-E-12-14 AND CHARGES FOR ELECTRIC SERVICE DUE TO THE INCLUSION OF THE LANGLEY GULCH POWER PLANT INVESTMENT IN RATE BASE. IDAHO POWER COMPANY DIRECT TESTIMONY OF LISA A.GROW 1 Q.Please state your name and business address. 2 A.My name is Lisa A.Grow and my business 3 address is 1221 West Idaho Street,Boise,Idaho 83702. 4 Q.By whom are you employed and in what capacity? 5 A.I am employed by Idaho Power Company (“Idaho 6 Power”or “Company”)as the Senior Vice President of Power 7 Supply. 8 Q.Please describe your educational background 9 and work experience with Idaho Power. 10 A.I graduated from the University of Idaho in 11 1987 with a Bachelor of Science degree in Electrical 12 Engineering.I received an Executive Masters of Business 13 Administration from Boise State University in 2008.I 14 began my career at Idaho Power after graduating from the 15 University of Idaho in 1987,and have held several 16 engineering positions before moving into management in 17 2005.In 2005,I was named Vice President of Delivery 18 Engineering and Operations.In 2009,I was appointed to my 19 current position as Senior Vice President of Power Supply. 20 My current responsibilities include overseeing the 21 operation and maintenance of Idaho Power’s generation 22 fleet,power plant engineering and construction, 23 environmental affairs,water management,power supply 24 planning,and wholesale electricity and gas operations. 25 GROW,DI Idaho Power Company 1 Q.Please outline the major topics you will 2 address in your testimony in this proceeding. 3 A.I will briefly discuss the historical process 4 involved with the identification of the need for a baseload 5 generating resource,the ultimate selection for the power 6 plant now known as Langley Gulch,the Idaho Public 7 Utilities Commission’s (“Commission”)authorization and 8 binding commitment to provide rate base treatment for the 9 Company’s investment in Langley Gulch pursuant to Idaho 10 Code §61-541,and the expected completion and in—service 11 date for the Langley Gulch power plant. 12 Q.Please describe the Langley Gulch power plant. 13 A.The Langley Gulch power plant is a natural 14 gas-fired combined cycle combustion turbine (“CCCT”) 15 generating plant with a nameplate capacity of approximately 16 300 megawatts (“MW”).The project is constructed on a 17 parcel of land on the south side of Interstate 84 in 18 Payette County approximately five miles south of the town 19 of New Plymouth,Idaho.The project is a baseload 20 generating resource of the size and type identified in the 21 preferred resource portfolio in the Company’s Integrated 22 Resource Plans that have been accepted by the Commission. 23 Q.When was the Langley Gulch power plant first 24 identified as a needed resource? 25 GROW,DI 2 Idaho Power Company 1 A.What is now known as Langley Gulch power plant 2 was first identified as a needed resource in the 3 Commission-accepted 2004 Integrated Resource Plan (“IRP”) 4 In the 2004 IRP,the Company identified a need for a 5 generic 500 MW baseload pulverized coal—fired resource in 6 2011.Two years later in its Commission-accepted 2006 IRP, 7 the Company reassessed when it would need to add a coal— 8 fired resource and adjusted its long-term resource plan to 9 include a 250 MW pulverized coal—fired resource in 2013 and 10 a 250 MW advanced coal—fired resource in 2017.In June of 11 2008,Idaho Power filed an update to its 2006 IRP in which 12 it notified the Commission that due to uncertainties 13 associated with permitting new coal-fired generation,the 14 Company had decided not to proceed with the previously 15 planned coal-fired resource.These concerns coupled with 16 the possibility of new large loads locating in Idaho 17 Power’s service territory and the anticipated shift of flow 18 augmentation releases of water from the federal dams on the 19 Snake River above Brownlee Dam from July and August to May 20 and June prompted the Company to (1)revise the 250 MW 21 coal-fired resource to a natural gas—fired baseload 22 resource,(2)increase the size of the baseload resource to 23 approximately 300 MW,and (3)accelerate the on-line date 24 of the baseload resource to 2012. 25 GROW,DI 3 Idaho Power Company 1 While the identification for the need of a baseload 2 resource was first identified in the 2004 IRP,the result 3 of the changes in the 2006 IRP and the 2008 IRP Update ±5 4 what is now known as the Langley Gulch power plant. 5 Q.Based upon the need for a new baseload 6 resource as identified in the Company’s previous IRP5,did 7 the Company begin a request for proposals (“RPP”)process? 8 A.Yes.On April 1,2008,Idaho Power issued an 9 RET to solicit competitive proposals for up to 10 approximately 600 MW of dispatchable energy.The quantity 11 sought was revised on June 25,2008,to 300 MW.The 12 identified product was a d±spatchable,first-call,non- 13 recallable,physically delivered firm or unit contingent 14 energy dedicated solely to Idaho Power’s use.As stated in 15 the RET,this product requirement could be met through a 16 Purchase Power Agreement where the seller supplies fuel and 17 fuel transportation or a Tolling Agreement (“TA”)where the 18 Company supplies the fuel and fuel transportation.The 19 prescribed term required for bids was 15 years with at 20 least one five-year contract renewal option. 21 The RET also advised potential bidders that to 22 ensure the availability of baseload resources in 2012,the 23 Company would include a Company-developed CCCT in the 24 competitive bidding process as one of the resource 25 alternatives,referred to as the Benchmark Resource. GROW,DI 4 Idaho Power Company 1 Q.Did the Company engage an independent third- 2 party to review the Company’s competitive request for 3 proposals and bid evaluation process? 4 A.Yes.The Company retained R.W.Beck,an 5 independent consulting firm offering a complete range of 6 consulting and engineering services to the utility 7 industry,to assist with and participate in the RPP 8 process.Specifically,R.W.Beck was retained to assist 9 with preparation of the RFP,the draft power purchase and 10 tolling agreements,development of the evaluation criteria 11 and manual,evaluation of the proposals received in 12 response to the RFP,including a self—build alternative as 13 a benchmark,and to provide assurance to the Commission and 14 bidders that the Company evaluated all proposals submitted 15 in response to the Company’s RFP in a reasonable,fair,and 16 equitable manner. 17 Q.Why did the Company ultimately select the 18 Langley Gulch project as the preferred bidder? 19 A.Ultimately,based on a comparison of the price 20 and non-price attributes of each of the proposals,the 21 Company concluded that the self—build alternative used as 22 the benchmark provided the greatest value for customers. 23 The Company’s decision to select the Langley Gulch project, 24 based on the results of the REP,was primarily dictated by 25 its substantially lower price.The differential between GROW,DI 5 Idaho Power Company 1 the 20-year net present value (“NPV”)of the revenue 2 requirements of the Langley Gulch and the closest TA for a 3 combined cycle project showed the second place project was 4 approximately $108 million more expensive,and the NPV 5 analysis for the TA for the third-place combined cycle 6 project was $220 million more expensive than the Langley 7 Gulch project. 8 Q.Following the conclusion of the RFP process, 9 did the Company apply to the Commission for a Certificate 10 of Public Convenience and Necessity (“CPCN”)? 11 A.Yes,on March 6,2009,in Case No.IPC-E-09- 12 03,the Company applied for a CPCN authorizing construction 13 of the Langley Gulch power plant. 14 Q.Did the Commission issue an order in Case No. 15 IPC-E-09—03 approving the Company’s application for a CPCN 16 for the Langley Gulch power plant? 17 A.Yes.The Commission,in Order No.30892, 18 issued on September 1,2009,approved the Company’s 19 application for a CPCN.Subsequently,the Commission 20 issued Certificate No.486 for the Langley Gulch power 21 plant. 22 Q.Did the Company make any other requests in 23 Case No.IPC—E--09-03 other than the request for a CPCN? 24 A.Yes.In addition to requesting a CPCN which 25 enabled the Company to begin the construction of the GROW,DI 6 Idaho Power Company 1 Langley Gulch power plant,the Company also requested that 2 the Commission order authorization and binding commitment 3 to provide rate base treatment for the Company’s capital 4 investment in the Langley Gulch power plant and related 5 facilities.The Company made this request because it felt 6 it was necessary in order to attract capital and finance 7 the project at reasonable rates and terms. 8 Q.Did the Commission grant the Company’s request 9 for authorization and binding commitment rate base 10 treatment for the Company’s capital investment in the 11 Langley Gulch power plant and related facilities? 12 A.Yes.In Order No.30892,the Commission found 13 that Idaho Power had satisfied the statutory requirements 14 of Idaho Code §61—541 and provided Idaho Power with 15 authorization and binding commitment to provide for rate 16 base treatment of the Company’s capital investment in the 17 Langley Gulch power plant and related facilities in the 18 amount of $396,618,473 at such time as the plant was placed 19 in commercial operation. 20 Q.Did the Commission direct the Company to 21 submit quarterly progress reports in consideration of the 22 ratemaking assurance it granted pursuant to Idaho Code § 23 61—541? 24 A.Yes.In consideration of the ratemaking 25 assurance the Commission granted pursuant to Idaho Code § GROW,DI 7 Idaho Power Company 1 61—541,the Commission directed the Company to submit 2 quarterly progress reports to the Commission describing the 3 status of the Langley Gulch power plant in reasonable 4 detail.The quarterly reports were to include information 5 showing the actual progress against the project schedule, 6 estimates of cost to complete,and changes to the 7 construction schedule and any other notations of importance 8 to the Commission’s understanding of deviations or 9 adjustments to the project schedule initiated between 10 quarterly reports.The reports were to also include a 11 budget update showing the total amount expended and billed 12 to date and remaining contract dollars. 13 Q.Has the Company complied with the Commission’s 14 directive to file quarterly progress reports describing the 15 Langley Gulch power plant project? 16 A.Yes.The Company filed its first Langley 17 Gulch quarterly progress report on December 17,2009,and 18 has continued to file a progress report each quarter 19 through the present.The last Langley Gulch quarterly 20 progress report was filed February 29,2012. 21 Q.What is the current status of the Langley 22 Gulch power plant and related facilities? 23 A.To date,the overall project for the Langley 24 Gulch power plant remains on schedule and the Company 25 expects total project costs to be very close to the GROW,DI 8 Idaho Power Company 1 Commission-approved binding amount of $396,618,473,which 2 was approved in Order No.30892 (“Binding Pre—approved 3 Amount”).Construction ±5 complete on the water pipeline 4 and pump station and water is available to the plant site. 5 Construction of the gas lateral pipeline from the Williams 6 Northwest main to the site was completed in July 2011. 7 Construction of the tap and metering station was 8 substantially completed in October 2011.Williams 9 Northwest will perform final checkout of its system prior 10 to delivering gas in April 2012. 11 The construction of the 2.8 mile 230 kilovolt (“kV”) 12 line to the west of the power plant was completed in March 13 2011 and is currently in operation.The 16.3 mile 138 kV 14 line is under construction and planned to be completed by 15 May 2012. 16 All permits for air,water,conditional use,and the 17 National Environmental Policy Act are completed and in the 18 construction compliance phase.The Company continues to 19 monitor the permit requirements and is coordinating with 20 the regulatory agencies as needed. 21 Q.Has the Company made use of local labor forces 22 in the construction of the Langley Gulch power plant? 23 A.Yes.In fact,on September 12,2011,the 24 Company filed a Langley Gulch supplemental quarterly 25 progress report which responded to an inquiry about Idaho GROW,DI 9 Idaho Power Company 1 Power’s use of local construction labor.That report, 2 which has now been included in more recent quarterly 3 reports,identifies nearly 150 local businesses which have 4 been utilized from Ontario,Oregon,to Rupert,Idaho. 5 Idaho Power bias requested its contractors use local labor 6 forces as much as possible.Nearly 30 percent of Idaho 7 Power’s general contractor’s staff is local hires.Idaho 8 Power made a conscious decision to bid the other ancillary 9 projects locally (i.e.,water pipeline,substation,gas 10 pipeline,etc.).All of those projects were awarded to 11 local companies except for the gas pipeline because no 12 local bids were received. 13 Q.Has the Langley Gulch power plant project 14 created additional job opportunities? 15 A.Yes,the Langley Gulch power plant has created 16 both short—and long-term job opportunities.The 17 construction work force has averaged over 150 workers over 18 the last 18 months,including qualified local electricians, 19 pipefitters,steelworkers,excavators,carpenters,concrete 20 workers,and laborers.Additionally,in the third quarter 21 of 2011,the Company completed the hiring of 17 new full 22 time positions stationed at the Langley Gulch power plant. 23 Q.Are you sponsoring an exhibit that shows the 24 Company’s total expected investment for the Langley Gulch 25 plant? GROW,DI 10 Idaho Power Company 1 A.Yes,Exhibit No.1 details the Company’s total 2 expected investment for the Langley Gulch project when the 3 project is finally completed.The total investment will be 4 $401,416,575,which is $26 million less than the Company’s 5 originally filed commitment estimate of $427,366,739 6 (“Commitment Estimate”).Also shown on Exhibit No.1 is 7 the Company’s actual spend through January 2012,the 8 remaining dollars to be spent by the end of June,and the 9 Company’s total estimated spend through June 2012 of 10 $398,133,778.In addition,Exhibit No.1 shows,for 11 comparison purposes,the Commission—approved binding cost 12 estimate of $396,618,473. 13 Q.How does the total expected investment in 14 Langley Gulch of $401 million compare to the Binding Pre— 15 approved Amount of $396 million approved in Case No.IPC—E 16 09—03? 17 A.The Company’s total investment for the Langley 18 Gulch project will be $26 million less than the Company’s 19 originally filed Commitment Estimate,and approximately 20 $4.8 million greater than the Commission’s Binding Pre 21 approved Amount of $396 million.The Company has kept the 22 Commission notified of the various deviations and 23 adjustments to cost estimates and project schedule 24 contained in the original estimate through the Company’s 25 GROW,DI 11 Idaho Power Company 1 filing of the quarterly progress reports as directed by the 2 Commission. 3 Q.Please identify some of the reasons why the 4 total expected cost of $401 million for the Langley Gulch 5 project is $26 million below the Company’s originally filed 6 cost commitment. 7 A.There are several notable reductions from the 8 cost estimates included in both the Company’s originally 9 filed Commitment Estimate and the pre-approved $396 10 million.Most notably,the Engineering,Procurement,and 11 Construction contract will come in $5.7 million less than 12 the pre—approved amount.In addition,Capitalized Property 13 Taxes will be $1.4 million less,allowance for funds used 14 during construction will be $2.7 million less,and the gas 15 turbine will be $37,823 less than the amounts included in 16 the $396 million. 17 Q.While the Company’s expected investment in 18 Langley Gulch is $26 million less than its original 19 Commitment Estimate,you stated that ±t is $4.8 million 20 greater than the Binding Pre-approved Amount.Please 21 explain why. 22 A.One of the primary reasons for the differences 23 between the Company’s total investment of $401 million and 24 the pre-approved $396 million has to do with some of the 25 individual cost components that were included in the pre GROW,DI 12 Idaho Power Company 1 approved amount.In Order No.30892,the Commission 2 separated costs that were known with greater certainty and 3 competitively procured from amounts that were based on more 4 uncertain estimates and contingencies.This approach 5 resulted in a $30.7 million reduction to the Company’s 6 filed Commitment Estimate of $427 million and resulted in 7 the Commission establishing a pre—approved amount of $396 8 million.Any costs the Company incurs above the pre 9 approved $396 million are subject to a prudency review for 10 Commission approval. 11 Q.Please describe at a high level any 12 significant variations in the cost components included in 13 the $396 million and the Company’s total expected 14 investment of $401 million. 15 A.As is expected with any project of this 16 magnitude,the actual costs for the Langley Gulch project 17 were higher than estimated in some individual cost 18 categories and lower than estimated in other cost 19 categories.Three of the Company’s projected investments 20 that are expected to be significantly higher are 21 expenditures related to the gas line construction,REP 22 pricing components,and transmission.With regard to the 23 gas line construction,the Company’s total investments are 24 twice as much as stated in the $396 million.However,this 25 is primarily due to the fact I just described above.Due GROW,DI 13 Idaho Power Company 1 to uncertain estimates included in the Company’s original 2 cost commitment,the Commission established the gas line 3 construction cost estimate at only 50 percent of the 4 Company’s anticipated costs.The Company’s original 5 estimate for gas line construction was $3,100,000.The 6 actual total spend will be $3,170,000,just $70,000 above 7 Idaho Power’s original estimate.However,by only 8 including 50 percent of Idaho Power’s original estimate, 9 the actual costs incurred appear to be much greater than 10 the pre-approved amount. 11 Q.Please describe the increase incurred between 12 cost estimates for the RFP pricing. 13 A.The expected RFP pricing component costs of 14 $5,574,298 are $5 million higher than the costs included in 15 the $396 million.Most of this deviation comes from a 16 combination of higher than anticipated required fuel usage 17 during project commissioning and a lower than expected 18 surplus energy sales offset value.In the Company’s 19 original estimate,it was expected that commissioning would 20 occur during the spring of 2012 when market energy prices 21 were higher;i.e.,April or May,allowing the Company to 22 offset the incurred gas costs.Now the commissioning of 23 the plant is expected to occur during June when market 24 energy prices are typically lower,resulting in less of an 25 offset than was originally anticipated. GROW,DI 14 Idaho Power Company 1 Q.What variation in costs estimates has occurred 2 with transmission? 3 A.While actual transmission costs are $4 million 4 above the pre-approved amount,the Commission-approved 5 estimate did not include some of the Company’s original 6 contingency estimates and upgrades,resulting in a pre 7 approved amount that was a fraction of the original 8 Commitment Estimate.Actual total transmission costs 9 incurred are $22 million,which is $9.5 million below the 10 Company’s original Commitment Estimate. 11 Q.Does the Company’s request in this docket 12 include its total investment of $401 million in the Langley 13 Gulch project? 14 A.No,not at this time.While the $401 million 15 is $26 million less than the Company’s originally filed 16 Commitment Estimate,the Company is only requesting 17 recovery of the amount of investment that will be closed to 18 books by June 30,2012,or $398,133,778.Company witness 19 Timothy E.Tatum details the development of the incremental 20 revenue requirement associated with Langley Gulch in his 21 testimony,as it relates to the $398 million. 22 Q.When does the Company expect the Langley Gulch 23 power plant to be in commercial operation? 24 25 GROW,DI 15 Idaho Power Company 1 A.The Langley Gulch power plant is expected to 2 be in commercial operation on or before July 1,2012.The 3 first fire of the plant is expected in April 2012. 4 Q.Although it would be inappropriate to re— 5 litigate need for the plant in this proceeding,which the 6 Commission affirmed when it issued Order No.30892,does 7 Idaho Power’s current load and resource balance indicate 8 the Langley Gulch is still needed in the summer of 2012? 9 A.Yes.The peak-hour load and resource balance 10 from the 2011 IRP was updated to include the Company’s 11 latest load forecast,which accounts for reduced Hoku load 12 based on the recently proposed terms of a restated contract 13 currently before the Commission for approval,an updated 14 forecast of Public Utility Regulatory Policies Act of 1978 15 generation taking into account recent contracts and 16 expected on-line dates,and updated estimates of 17 transmission capacity available for July market purchases 18 from the Pacific Northwest.Without Langley Gulch,the 19 updated peak-hour load and resource balance shows July 20 deficits of 28 MW in 2012,169 MW in 2013,and 224 MW in 21 2014.With the Langley Gulch plant being available this 22 summer,Idaho Power will be able to reliably meet the 23 summer peak needs of customers. 24 Q.In your opinion,will the Langley Gulch power 25 plant be used and useful on July 1,2012? GROW,DI 16 Idaho Power Company 1 A.Yes.The need for a new baseload power plant 2 was first identified in Idaho Power’s 2004 and 2006 IRP5 in 3 order to meet system reliability and load growth within 4 Idaho Power’s service territory.The Langley Gulch power 5 plant will be immediately used and useful once it is in 6 commercial operation in order to help meet the Company’s 7 summer peak demand requirements and provide additional 8 system reliability needed year-round due to the increased 9 challenges of integrating variable and intermittent 10 renewable generation resources. 11 Q.Does this conclude your direct testimony in 12 this case? 13 A.Yes,it does. 14 15 16 17 18 19 20 21 22 23 24 25 GROW,DI 17 Idaho Power Company BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO.IPC-E-12-14 IDAHO POWER COMPANY GROW,DI. TESTIMONY EXHIBIT NO.I Id a h o Po w e r Co m p a n y La n g l e y Gu l c h Po w e r Pl a n t Co s t Su m m a r y Ja n u a r y Re m a i n i n g To t a l Sp e n d To t a l ex p e c t e d Bi n d i n g Pr e - A p p r o v e d Co m p a n y ’ s Or i g i n a l $s sp e n t to da t e $s to Sp e n d th r o u g h Ju n e , 20 1 2 pr o i e c t sp e n d Am o u n t Co m p o n e n t Su m m a r y Ga s Tu r b i n e 54 , 4 9 3 , 3 6 9 1,6 0 0 , 4 7 0 56 , 0 9 3 , 8 3 9 56 , 2 4 3 , 8 3 9 56 , 2 8 1 , 6 6 2 56 , 2 8 1 , 6 6 2 St e a m Tu r b i n e 34 , 9 7 2 , 7 3 6 73 9 , 6 2 3 35 , 7 1 2 , 3 5 9 35 , 8 6 2 , 3 5 9 35 , 7 1 0 , 9 0 5 35 , 7 1 0 , 9 0 5 EP C Co n t r a c t 20 3 , 2 8 7 , 5 2 6 10 , 0 5 8 , 9 2 7 21 3 , 3 4 6 , 4 5 3 21 5 , 7 2 3 , 1 6 8 22 1 , 4 2 1 , 4 3 1 22 1 , 4 2 1 , 4 3 1 Co m m i t m e n t Es t i m a t e Co n t i n g e n c y - - - - 6, 8 0 0 , 6 8 6 Si t e Pr o c u r e m e n t 1, 9 5 7 , 3 2 2 42 , 6 7 8 2, 0 0 0 , 0 0 0 2, 0 0 0 , 0 0 0 1, 9 5 0 , 0 0 0 2, 0 0 0 , 0 0 0 Wa t e r Ri g h t s 2, 0 8 3 , 4 1 9 - 2, 0 8 3 , 4 1 9 2, 0 8 3 , 4 1 9 2, 0 8 1 , 2 6 9 2, 2 0 0 , 0 0 0 NE P A Pe r m i t t i n g 21 4 , 4 3 1 - 21 4 , 4 3 1 21 4 , 4 3 1 15 0 , 0 0 0 15 0 , 0 0 0 Ai r Pe r m i t t i n g 35 0 , 5 4 7 14 , 4 5 3 36 5 , 0 0 0 39 0 , 0 0 0 32 0 , 0 0 0 32 0 , 0 0 0 Wa t e r Li n e Co n s t r u c t i o n 4, 5 6 0 , 0 4 2 19 , 9 5 8 4,5 8 0 , 0 0 0 4, 5 8 0 , 0 0 0 4,4 2 5 , 0 0 0 8, 8 5 0 , 0 0 0 Ga s Li n e Co n s t r u c t i o n 3, 1 6 6 , 0 8 7 3, 9 1 3 3,1 7 0 , 0 0 0 3,1 7 0 , 0 0 0 1,5 5 0 , 0 0 0 3, 1 0 0 , 0 0 0 Mi s c e l l a n e o u s Eq u i p m e n t (I d a h o Po w e r su p p l i e d ) 16 6 8 , 0 6 6 90 2 , 5 6 6 2, 5 7 0 , 6 3 2 2, 5 7 0 , 6 3 2 33 1 , 1 5 0 66 2 , 3 0 0 Ca p i t a l i z e d Pr o p e r t y Ta x e s 95 3 , 9 2 6 49 0 , 5 0 5 1,4 4 4 , 4 3 1 1,4 4 4 , 4 3 1 2, 8 8 1 , 2 7 7 2, 8 8 1 , 2 7 7 Id a h o Po w e r En g i n e e r i n g an d Ov e r s i g h t 2,4 0 8 , 9 1 8 33 0 , 0 0 0 2, 7 3 8 , 9 1 8 2, 8 2 0 , 0 0 0 1,9 0 0 , 0 0 0 3, 8 0 0 , 0 0 0 RF P Pr i c i n g co m p o n e n t s )i n c l u d e s st a r t up fu e l s ) 39 9 , 3 0 3 4, 6 7 4 , 9 9 6 5, 0 7 4 , 2 9 8 5, 5 7 4 , 2 9 8 50 0 , 0 0 0 2, 2 5 0 , 0 0 0 Tr a n s m i s s i o n 17 , 7 4 6 , 4 3 2 4,4 2 3 , 6 2 8 22 , 1 7 0 , 0 6 0 22 , 1 7 0 , 0 6 0 17 , 8 5 6 , 4 0 0 31 , 6 7 9 , 1 0 0 AF U O C 33 , 6 2 4 , 9 5 7 12 , 9 4 4 , 9 8 0 46 , 5 6 9 , 9 3 7 46 , 5 6 9 , 9 3 7 49 , 2 5 9 , 3 7 9 49 , 2 5 9 , 3 7 8 To t a l s 36 1 , 8 8 7 , 0 8 2 * 36 , 2 4 6 , 6 9 6 39 8 , 1 3 3 , 7 7 8 40 1 , 4 1 6 , 5 7 5 39 6 , 6 1 8 , 4 7 3 ** 42 7 , 3 6 6 , 7 3 9 ** * Re p o r t e d on Ac c r u a l ba s e d ac c o u n t i n g Bi n d i n g Pr e - a p p r o v e d Am o u n t as ap p r o v e d by Or d e r No . 3 0 8 9 2 (S t a f f ’ s Re v i s e d Co n f i d e n t i a l Ex h i b i t No . 10 9 ) Co m p a n y ’ s Or i g i n a l l y Fi l e d Co m m i t m e n t Es t i m a t e 0) 0) 1 < CD C) ci, D (D C & - z— 0- OZ C-) 1;1 -i